No Acts & Articles mentioned in this case
C.M.S.A.No.38 of 2021
IN THE HIGH COURT OF JUDICATURE AT MADRAS
RESERVED ON : 26.09.2024
PRONOUNCED ON : 20.11.2024
CORAM:
THE HONOURABLE MRS. JUSTICE J.NISHA BANU
AND
THE HONOURABLE MRS. JUSTICE R.KALAIMATHI
C.M.S.A.No.38 of 2021
and C.M.P.Nos.7284 & 4209 of 2021 & 15035 of 2022
M/s.KSM Nirman Private Limited,
Presently known as M/s.Olympia
Tech Park (Chennai) Private Limited,
No.1, SIDCO Industrial Estate,
Guindy, Chennai 600 032 ... Appellant
Vs.
Olympia Grande Apartments
Owner's Welfare Association,
Pallavaram Registration No.569/2016,
No.328, GST Road, Pallavaram,
Chennai 600 043 ... Respondent
PRAYER: Civil Miscellaneous Second Appeal filed under Section 100 of
C.P.C. to set aside the order dated 09.11.2020 passed in Appeal No.75 of
2019 on the file of the Tamil Nadu Real Estate Appellate Tribunal
(TNREAT) and confirm the order dated 06.11.2019 passed in C.No.327 of
2019 on the file of Tamil Nadu Real Estate Regulatory Authority, Chennai.
______________
Page No.1 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
For Appellant : Mr.Isacc Mohanlal, Senior Counsel
For Mrs.M.V.V.N.Sivanthy
For Respondent : Mr.S.R.Rajagopal, Senior Counsel
For Mr.Hari Radhakrishnan
******
J U D G M E N T
(Judgment of the Court was made by J. NISHA BANU, J.)
Challenging the order passed by the Tamil Nadu Real Estate
Appellate Tribunal (TNREAT) in Appeal No.75 of 2019, dated 09.11.2020,
the aggrieved respondent therein/Developer, has preferred the present Civil
Miscellaneous Second Appeal. The Tamil Nadu Real Estate Appellate
Tribunal, set aside the order in C.No.327/2019 dated 6.11.2019 and directed
the Regulatory Authority to dispose the complaint on merits.
2. The necessary facts leading to the filing of this appeal would run
thus:
2.1.The appellant herein, M/s.KSM Nirman Private Limited,
______________
Page No.2 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
presently known as M/s.Olympia Tech Park (Chennai) Private Limited,
commenced the project in the year 2012 (16 residential towers with 744
apartments and 1 commercial tower). On 26.04.2012, the appellant has
obtained the planning permit and also obtained the building plan approval
from CMDA, which is the competent authority. The appellant completed the
construction and obtained completion certificates in a phased manner in three
phases as stated below:
(i) For the 1
st
phase of 9 Blocks, the 1
st
Partial Completion
Certificate was issued by the competent authority CMDA
dated 13.05.2015;
(ii) For the 2
nd
phase LIG (2 blocks), the 2
nd
Partial
Completion certificate was issued by the competent
authority CMDA dated 06.11.2015;
(iii) For the 3
rd
phase of 7 blocks 3
rd
Partial completion
Certificate was issued by the competent authority CMDA
dated 15.02.2016.
The term "Partial" was used in the above Completion Certificates
because the completion of the project was in a phased manner as
______________
Page No.3 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
contemplated in the Explanation to Sub Section 2 of Section 3 of RERA Act,
read with Section 2 (q) thereof.
2.2. The apartments were handed over to the respective purchasers
in a phased manner, after completion of the phases during the period from
the years 2015 to 2016. The apartment purchasers created an Owners'
Welfare Association in the year 2016 (Olympia Grande Owners Welfare
Association)/ the respondent herein and registered it with the Registrar of
Societies vide registration certificate dated 23.11.2016.
2.3. The respondent Association took control of the common area
and its maintenance in June 2017 and it is now under the control and
maintenance of the Association since then. As far as the 17th tower
(Commercial) is concerned, a revised planning permission was obtained from
CMDA and the Project Completion Certificate for the entire project was
obtained on 06.12.2017.
2.4. Mr.Isacc Mohanlal, Senior Counsel, appearing on behalf of
Mrs.M.V.V.N.Sivanthy, learned counsel for the appellant would contend that
______________
Page No.4 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
the Real Estate (Regulation and Development) Act, 2016 (hereinafter
referred as 'RERA') was notified with effect from 26.03.2016, and so far as
the State of Tamil Nadu is concerned, it became operational from the date of
framing and notification of the Tamil Nadu Real Estate (Regulation and
Development Rules), 2017 with effect from 22.06.2017. As such, the main
contention of the learned Senior Counsel is that the said Act and the rules
which came into operation in Tamil Nadu from 22.06.2017 cannot operate in
respect of the Real Estate Projects which were completed on or before the
said date i.e. 22.06.2017, in as much as the projects in the present case (16
residential towers) came to be completed and handed over to the allottees on
the strength of Completion Certificates dated 13.05.2015, 06.11.2015, &
15.02.2016.
2.5. According to the learned Senior Counsel, registration for the
Real Estate Projects is mandatory under the Act only in respect of ongoing
projects and for "future projects, and not, in respect of the projects which are
already completed and received Completion Certificate as provided under
Section 3 (2) and the Explanation thereto.
______________
Page No.5 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
2.6. Meanwhile, the respondent Association has filed a complaint
before the Regulatory Authority, mainly for corpus fund and for certain
rectifications in the project. The entire corpus fund of Rs.2,18,07,755/-
drawn on HDFC Bank DD No.009329 dated 11.03.2021 was handed over to
the respondent Association. While so, after three years, in the year 2019, the
respondent Association has filed a complaint "FORM M' before the Tamil
Nadu Regulatory Authority under section 31 of the RERA Act. The
complaint was numbered as C.No.327 of 2019. The said application was
objected by the appellant by way of filing preliminary objection that the
complaint itself is not maintainable since the project was completed as early
as in the year 2015 and partial completion certificates were obtained on
13.05.2015, 06.11.215 and 15.02.2016 before the RERA notification. The
Authority, after hearing the submissions, rightly dismissed the complaint
vide order dated 06.11.2019.
2.7. Aggrieved by the said order, the respondent Association filed
an appeal before the Tamil Nadu RERA Appellate Tribunal and the case was
numbered as Appeal No.75 of 2019. The Appellate Authority allowed the
______________
Page No.6 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
appeal filed by the respondent Association, thereby setting aside the order
made in C.No.327 of 2019 dated 06.11.2019 with a direction to restore
C.No.327 of 2019 to file and dispose the complaint on merits within three
months. Aggrieved against the same, the appellant has preferred the present
Civil Miscellaneous second Appeal before this Court.
3. The main grounds raised by Mr.Isacc Mohanlal, Senior Counsel,
appearing on behalf of Mrs.M.V.V.N.Sivanthy, for the appellant are as
follows:-
3.1. RERA came to be published in gazette on 26.03.2016, when
Section 1 came into force. Section 2, Sections 20 to 39, Sections 41 to 58,
Sections 71 to 28, Sections 81 to 92 came into force on 01.05.2016,
Sections 3 to 19, 40, 59 to 70, 79 and 80 came into force on 01.05.2017 and
the Real Estate Act Tamil Nadu Rules 2017 came into force on 22.06.2017.
In the present case, admittedly the apartments were completed and handed
over to the owners by 2015 and there is no dispute. The Association did not
pray for registration of the project with RERA. Further, both the Authority
and Tribunal had confirmed that the project was completed much before the
Act and its regulations came into force.
______________
Page No.7 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
3.2. According to the learned Senior Counsel, the RERA
Appellate Tribunal has held that Section 71 dealt with power to adjudicate by
the adjudicating officer Under Sections 12, 14, 18 and 19 of the RERA Act,
and in this provision, a proviso clause was included in which, it has been
specifically contemplated that, any person, whose complaint in respect of
matters for compensation etc., is pending before the Consumer forum on or
before the commencement of this Act, he may, with the permission of such
forum, withdraw the complaint and file the same before the Adjudicating
officer under this Act, Section 79 dealt with bar of Jurisdiction. Therefore,
the provision contemplates that no civil court shall have jurisdiction to
entertain any suit or proceeding in respect of any matter which the authority
or the Adjudicating officer or the Appellate Tribunal is empowered by or
under the act to determine, and emphasised that the application itself as not
maintainable.
3.3. According to the learned Senior Counsel, Chapter -III,
Sections 11, 12, 14, 18 and 19 of the Act, start with, the Promoter shall, upon
receiving his login ID and Password under clause (a) of Sub Section (1) or
______________
Page No.8 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
under Sub Section (2) of Section 5, as the case may be, create his web page
on the website. That being so, according to the learned senior Counsel, the
Tribunal failed to consider its own finding that the project was already
completed and handed over. Therefore, it is very clear that the above sections
will come into play only when the project is registered and if the promoter
violates any of those sections, then penal provisions will follow.
3.4. The learned senior counsel further submits that in the present
case, the project was completed before the RERA Act came into force.
Therefore, the apartment owners have all the rights to approach the civil
court/consumer court for any grievances.
3.5. Moreover, Section 3 of the RERA Act has categorically
described when the registration of the projects is required and when not
required. Section 3 of the RERA Act, reads as under:
Section 3: Prior registration of real estate project with
the Real Estate Regulatory Authority:
1) No promoter shall advertise, market, book, sell, offer
for sale, or invite persons to purchase in any manner any
______________
Page No.9 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
plot, apartment or building, as the case may be, in any real
estate project or part of it, in any planning area, without
registering the real estate project with the Real Estate
Regulatory Authority Established under this act. Provided
that projects that are ongoing on the date of
commencement of this act and for which the completion
certificate has not been issued, the promoter shall make an
application to the authority for registration of the said
project within a period of three months from the date of
commencement of this Act.
Notwithstanding anything contained in Sub-Section 1, no
registration is required of the real estate project shall be
required.
(b) where the promoter has received a completion certificate
for a real estate project prior to the commencement of this
Act.
As per Section 3 (2) proviso it is very clear that the projects
already completed are not required to register with RERA. The present
project was completed in all aspects and a partial completion certificate was
obtained before the Act came into force. Therefore the impugned order is
liable to be set aside.
______________
Page No.10 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
3.6. Further, the learned Senior Counsel brought to the notice of
this Court that at the time of admission it was fairly committed to this Court
that the corpus fund collected from the individual apartment owners are kept
in a Fixed Deposit and the appellant would return the corpus fund amount
Rs.2,75,37,100/- to the respondent Association, and this Court recorded the
same and passed an interim order dated 04.03.2021 directing the appellant to
return the corpus fund. However, the appellant at a later stage found that they
had spent a sum of Rs.73,80,917/- towards various purposes of the
residential project from out of pocket, due to oversight, the same was not
brought before the notice of this Court at the time of admission.
Subsequently, the appellant has returned the undisputed Corpus fund a sum
of Rs.2,18,07,755/- drawn on HDFC Bank DD No.009329 dated 11.03.2021
to the Association after retaining a sum of Rs.66,51,083/- and the same has
been kept in a Fixed Deposit. Since there is a difference in the returning
amount, the appellant herein filed C.M.P.No.7284 of 2021 to modify the
order dated 04.03.2021. This Court has directed the Authority to hear the
parties and pass final orders in C.No.327 of 2019 but to keep the final orders
in a sealed cover till the disposal of this C.M.S.A.No.38 of 2021.
______________
Page No.11 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
Subsequently, the Authority heard the parties and passed final orders and
kept the same in a sealed cover.
3.7. The appellant herein is continuously maintaining the Sewage
Treatment Plant (STP) and incurring further expenditures and therefore, filed
C.M.P.No.247 of 2023 to direct the Association to reimburse a sum of
Rs.50,00,852/- to the appellant and further direct the respondent Association
to take over the STP maintenance henceforth. Since the monthly maintenance
charges were collected by the respondent Association from the individual
apartment owners, the respondent Association have to maintain the STP and
reimburse the amount spent by the appellant. The appellant had filed an
additional typed set of papers to bring to the notice of this Court that they
had totally spent a sum of Rs.1,38,35,774/- on account of STP maintenance.
3.8. The learned Senior counsel further relied upon the following
judgments:-
(a) Newtech Promoters and Developers Pvt Ltd., Vs State of
UP and others reported in 2021 SCC Online SC 1044;
______________
Page No.12 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
(b) ECGC Ltd vs Mokul Shriram EPC JV, reported in 2021
SCC Online SC 1044;
(c) Neelkamal Relators suburban Pvt Ltd.vs.Union of India
reported in 2017 SCC online BOM 9302;
(d) Macrotech Developers Ltd., vs. The State of
Maharashtra, registered as W.P.No (ST) No.1118 of 2021;
(e) Kusum Ignots and alloys Ltd., vs. Union of India-
reported in (2004) 6 SCC 254;
(f) State of Maharashtra vs. Kalir Koil Subramaniam
Ramasamy reported in (1997) 3 SCC 525;
(g) Commissioner of Income Tax, Vidarbha vs Smt.
Godaveri Devi Saraf-reported in 1997 SCC Online BOM
215;
(h) Shiv Kumar vs Union of India, reported in ILR 2014
KAR 2474;
(i) T.Rajakumari & Ors vs. Government of Tamil Nadu &
others, reported in AIR 2016 Mad 177;
(j) Farouk Irani vs The Deputy Collector, reported in
______________
Page No.13 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
MANU/TN/2655/2017; and
(k) Shri Ajay Kumar Gupta vs Adjudication Authority,
registered as Crl.OP.Nos.10497 and 10500 of 2017.
4. Per contra, Mr.S.R.Rajagopal, learned Senior Counsel for
Mr.Hari Radhakrishnan, appearing on behalf of the respondent Association
made the following submissions:-
4.1. The appellant had completed the construction of the residential
units, comprising 16 towers, by the year 2015 and partial completion
certificates were obtained on 13.5.2015, 6.11.2015 and 15.2.2016, which
were much before the coming into force of the provisions of RERA, 2016,
whereas, the term partial completion certificate has not been
provided/recognised under RERA Act. Sec.2(q) defines completion
certificate.
4.2. The term partial completion certificate cannot be equated to
completion certificate as defined under Sec.2(q) of the Act. Even though
there is no provision either under the Development Regulations or under any
______________
Page No.14 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
other law for issuance of a partial completion certificate, the authorities
issued partial completion certificate in respect of project where construction
is in phases. When the promoter registers each phase as a project separately,
then only a completion certificate would be issued and not a partial
completion certificate. A partial completion certificate is issued only in
respect of integrated projects, where construction is in phases, for enabling
availing civic facilities and electricity.
4.3. In order to term the project as an integrated project, the project
includes 17 towers consisting of A (9 Towers), B (3 Towers), C (1 Tower), D
(1 Tower), E (1 Tower) and F (2 Towers) and the appellant had applied for a
common planning permit for construction of all the 17 towers and
accordingly, CMDA granted permission vide Permit No.7105C/PP/MSB-
IT/28 A to T/2012 dated 26.04.2012 for construction of 17 residential
towers. It is submitted that all the 789 owners have paid for the UDS for the
total common area and has right and privilege to use the common area for the
common purposes. Further, the Appellant had also obtained Environmental
Clearance No.SEIAA/TN/ F-453/EC/8(a)/145/2011 dated 16.04.2013 and
______________
Page No.15 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
amendment No. SEIAA/TN/ E453/KPM/8(a)/EC-145-Amdt/2011 dated
24.02.2015 for construction of 17 towers as an integrated project.
Environmental Clearance (EC) to construct 744 dwelling units in 6 blocks
having 17 towers and a club house. On 16.04.2013, the Environmental
Clearance was also obtained for 17 towers. This is evident from the fact that
the project name, for the integrated development is "Olympia Grande". There
is one entry and one exit for all the 17 towers/apartments. All the 789
allottees have UDS in the total project area of 6.36 acres. Therefore, the
project is an integrated project, though construction was in phases.
4.4. It is only as the construction was in phases in an integral
project with one approval, for the sake of convenience, the appellant had
obtained partial completion certificates on 13.05.2015, 06.11.2015 and
15.02.2016 as and when certain towers were built, so that the units in these
buildings could become habitable and so that the appellant could make sales
of the said dwelling units. However, these partial completion certificates do
not indicate that the entire project, as approved, has been developed
according to the sanction plan, layout plan and specifications as approved by
______________
Page No.16 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
the competent authority and further it is stated that the structural stability of
the building has not been tested.
4.5. It is further submitted that the appellant had applied for a final
completion certificate for the entire project only on 31.05.2017. It is
submitted that in pursuance of the said application, the CMDA issued a
deficiency notice dated 20.06.2017 pointing out various deficiencies.
Thereafter, a final completion certificate was issued on 06.12.2017 for the
entire project. Therefore, it is apparent that as on coming into force of RERA
Act, 2016, final completion certificate was not even applied for.
4.6. The learned Senior Counsel further submitted that the
appellant applied for a revised planning permission on 09.08.2017 to convert
the usage of 17th tower from residential to restaurant cum service apartment.
Therefore, it is submitted that the project developed by the appellant,
construction put up in phases, would be covered under the definition of
'ongoing project' as defined in Rule 2(h) of the Tamilnadu Real Estate
(Regulation and Development) Rules, 2017.
______________
Page No.17 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
4.7. Form A' appended to the TNRERA Rules, 2017, is the format
for making an application for registration of a project under RERA Act,
2016. Paragraph (A) of the said form stipulates that, where the project is
supposed to be developed in phases, an authenticated copy of the planning
permission, building permit/building sanction plan and partial completion
certificate for each of such phases has to be submitted for registration.
Therefore, the TNRERA Rules, 2017 clearly contemplates that even where a
project in developed in phases, a builder is required to register the project
under RERA by enclosing copies of partial completion certificate obtained
for each of such phases.
4.8. The term "ongoing project has not been so defined under the
Act while the expression "Real Estate Project is defined under Section 2 (zn)
of the Act, which reads as under:-
2(zn)-real estate project means the
development of a building or a building consisting of
apartments, or converting an existing building or a part
thereof into apartments, or the development of land into
plots or apartments, as the case may be, for the purpose
of selling all or some of the said apartments or plots or
______________
Page No.18 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
building, as the case may be, and includes the common
areas, the development works, all improvements and
structures thereon, and all easement, rights and
appurtenances belonging thereto".
4.9. As per the legislative mandate, the Act is intended to apply
even to the ongoing real estate projects. The expression "On Going Project
has been defined under Rule 2(h) of the Tamil Nadu Real Estate (Regulation
and Development) Rules, 2017 and projects, where application for
completion certificate has been made after the date of coming into force of
sub-section (1) of section 3 of the Act, then it would be termed to be an
'ongoing project'. Therefore, as per the scheme of Act 2016 in particular,
Section 3 says all ongoing projects that commence prior to the Act and in
respect to which completion certificate has not been issued are covered under
the Act. The legislative intent is to make the Act applicable, not only to the
projects which were yet to commence after the Act became operational, but
also to bring under its fold the ongoing projects and to protect from its
inception the inter se rights of the stake holders, including allottees/home
buyers, promoters and real estate agents, while imposing certain duties and
______________
Page No.19 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
responsibilities on each of them and to regulate, administer and supervise the
unregulated real estate sector, within the fold of the real estate authority.
4.10. The learned Senior Counsel further submitted that on a
harmonious reading of TNRERA Rules, 2017 and the definition of
'completion certificate' mentioned in Section 2(q) of the Real Estate
(Regulation and Development) Act, 2016, it can be safely concluded that the
completion certificate that is required to be obtained by a builder can only
mean a final completion certificate, which is issued after ascertaining
whether the entire real estate project has been completed with the required
roads, amenities etc. The builder is relived from all his obligations and
liabilities only after the issuance of the final completion certificate. In the
present case on hand, the final completion certificate was applied only on
31.05.2017.
4.11. The learned senior counsel for the respondent Association
further submitted that the appellant had applied for a final completion
certificate on 31.05.2017 for the above project and in pursuance of the said
______________
Page No.20 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
application, CMDA had issued the Final Completion Certificate on
06.12.2017. It is submitted that RERA Act, 2016 and the TNRERA Rules,
2017 make a distinction between partial completion certificate and final
completion certificate. This is evident from the fact that the application
prescribed in Form 'A' for registration of the project prescribed "partial
completion certificate" as one of the documents to be submitted along with
the application filed for registration under Rule 3(2) of TNRERA Rules,
2017. It is submitted that Completion certificate can only be one and it has to
be issued finally after CMDA is satisfied that the builder has complied with
the conditions of the planning permission and has constructed the building in
accordance with the permission given.
4.12. Further, it is submitted that if these so called partial
completion certificates were sufficient, there would be no necessity for the
appellant to apply for the completion certificate once again in December,
2017. Therefore, the Appellant, understanding and accepting the position,
had thus applied for completion certificate on 31.05.2017 and thereafter
applied to CMDA for revision of planning permit in August, 2017. The
______________
Page No.21 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
above facts clearly establish that as on the date of coming into force of
Section 3 of RERA, 2016, the appellant did not have a valid completion
certificate. It is to be noted that the application for final completion
certificate was submitted before obtaining plan permit and completion of
project and that too, was rejected by CMDA vide their order dated
21.06.2017. This further substantiates that the project was an ongoing
project' on the date of coming into force of RERA Act, 2016.
4.13. Further, it is argued that the CMDA website clearly states
that the appellant had applied for a revised planning permission and the same
was granted by the CMDA, vide revised planning permission
No.C/PP/MSB/34(A to D)/2017 and planning permit No.11162 in letter
No.C3(S)/1261/2016 dated 9.8.2017. So, it is clear that a revised planning
permission was only given to the appellant on 9.8.2017. Therefore, the
construction was 'ongoing' on the date of coming into force of Section 3 of
RERA, 2016.
4.14. It is further submitted that after obtaining the revised
planning permission in August, 2017, the appellant continued with their
______________
Page No.22 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
construction. However, on 07.08.2023, CMDA issued a notice to the
appellant stating that there are several defects/deviations/violations with
regard to the construction put up by the appellant and disapproved the
revised planning permit application submitted by the appellant on
12.09.2022. Therefore, it is apparent that obtaining of the completion
certificate or even the partial completion certificate has no significance if the
construction is not put up as per the approval given.
4.15. It is submitted that once it is established that the construction
was completed only in December 2017, it can be safely concluded that the
appellant has failed to register themselves under Section 3 of the RERA,
2016. The first proviso to Section 3(1) of RERA, 2016 states that, 'projects
which are ongoing on the date of commencement of this Act and for which
completion certificate has not been issued are liable to be registered within
a period of three months from the date of the commence of the Act'. In the
present case, the completion certificate was issued by the appellant only on
5.12.2017. Therefore, the appellant ought to have registered themselves
under Section 3(1) of RERA, 2016 within a period of three months from the
date of commencement of the Act ie. within three months from 01.05.2017.
______________
Page No.23 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
4.16. The learned Senior Counsel also invited the attention of this
Court to Environmental Clearance Report dated 30.10.2017 issued by the
Ministry of Environment, Forest and Climate Change vide F.No
EP/12.1/SLAA/2017-18/13/TN/1731, which points out large number of
violations committed by the appellant, which till date stands non-complied.
Besides, the Tamil Nadu Pollution Control Board has called upon the
appellant to pay an Environmental Compensation of Rs.7,11,60,000/- for
failure to obtain consent as per the provisions of Section 25 of the Water Act,
1974 and Section 21 of the Air Act, 1981 Tamil Nadu Pollution Control
Board (TNPCB), vide their proceedings dated 21.12.2020 and 12.01.2021,
the Sewage Treatment Plant (STP) is not operational and is also not being
maintained. This finding has been reiterated in the Inspection Report dated
14.02.2023 of the TNPCB. The Tamil Nadu Fire and Rescue Services
Department has inspected the building for issuance of Fire License and
issued notice dated 20.05.2020 vide K.Dis. No. 15551/C1/2019 informing
several defects. Further, the Highways Department has issued a notice dated
02.03.2021 stating that the ramp contracted for entry into the apartment
complex is encroaching the service road which leads to the Pallavaram
______________
Page No.24 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
Railway flyover and also causing hindrance to the storm water drainage.
Therefore, there are several defects/deviations/discrepancies in the
construction put up by the appellant and mere possession of a "partial
completion certificate" will not absolve the appellant from mandatorily
registering under the provisions of RERA.
4.17. The learned Senior Counsel relied on the judgment made by
the Division Bench of this High Court in the case of Subashini Tulasiram
Vs. SPR & RG Constructions Pvt. Ltd. (order dated 15.09.2020 passed in
CMSA No.22/2019), wherein it has been held that non-obtaining of prior
environment clearance will vitiate the completion certificate obtained by the
builder in the eye of law, since the said certificate cannot be considered to be
compete and final. This Court further held that an environment clearance
certificate is mandatory, and obtaining of post-facto clearance would not
legalize the construction put up by the Builder. In the present case, the
construction was put up without obtaining prior Consent to Operate and the
appellant first issued with two show cause notices dated 17.12.2019 under
the Water Act, 1974 and under the Air Act, 1991. Consequently, the
______________
Page No.25 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
appellant was imposed with a liability of Rs.7,11,60,000/- as environment
compensation and the consent was finally given only on 07.12.2020, which
is much after the putting up of the construction. Therefore, a post-facto
approval given to the appellant would not legitimize or validate the partial
completion certificates issued to the appellant in the year 2015.
4.18. Learned Senior Counsel further relied on the case of SARE
Shelters 16 Projects Pvt. Ltd Vs. SARE Squires & Anr. (Order dated
16.02.2021 passed in CMSA No 27/2020) -, wherein it has been held that a
completion certificate, which does not disclose whether the building was
constructed as per the norms and whether the amenities were provided as per
the specification cannot be considered to be valid completion certificate. In
paragraph 24 of the said order, this Court held that a completion certificate
issued in the year 2014, without fulfilling the requirements and conditions
stipulated in the Town and Country Planning Act cannot be considered as a
valid completion certificate for the purpose of grant of exclusion from
registration under Setion3(ii) of RERA Act, 2016. The said decision squarely
applies to the present case. The large scale deficiencies and defects noted by
CMDA would establish that the project has not been completed till date.
______________
Page No.26 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
4.19. The objects and reasons for enactment of The Real Estate
(Regulation and Development) Ac, 2016 states as follows:
"An Act to establish the Real Estate
Regulatory Authority for regulation and promotion of
the real estate sector and to ensure sale of plot,
apartment or building, as the case may be, or sale of
real estate project, in an efficient and transparent
manner and to protect the interest of consumers in the
real estate sector and to establish an adjudicating
mechanism for speedy dispute redressal and also to
establish the Appellate Tribunal to hear appeals from
the decisions, directions or orders of the Real Estate
Regulatory Authority and the adjudicating officer and
for matters connected therewith or incidental thereto."
Therefore, RERA Act, 2016 provision was intended to a single
umbrella to address all the grievances of home buyers, irrespective of the fact
whether the real estate project was or was not required to be registered in
terms of Section 3 of the Act.
4.20. Therefore, it is submitted by the learned Senior Counsel for
the respondent Association that the adjudicatory mechanism provided under
______________
Page No.27 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
RERA will also apply to projects, where completion certificate has been
obtained prior to coming into force of the Act. In support of the above view,
reliance is placed on the decision rendered by the Real Estate Appellate
Tribunal, Punjab in the case of Silver city Construction Ltd Vs. State of
Punjab (Order dated 24.07.2019 passed in Appeal No.49/2018] - and the
decision of the Haryana Real Estate Appellate Tribunal in the case of Emaar
MGF Land Ltd Vs. Simmi Sikka, [Order dated 03.11.2020 passed in Appeal
Nos.52 & 64 of 2018.
4.21. The learned Senior counsel appearing for the respondent
Association further relied upon the following judgments:-
(a) Subashini Thulasiram vs. SPR & RG Constructions
Pvt. Ltd order dated 15.09.2020 passed by this Court in
CMSA No. 22 of 2019;
(b) Silver City Construction Ltd vs. State of Punjab order
dated 24.07.2019 passed by the Real Estate Appellate
Tribunal, Punjab SAS Nagar (Mohali);
(c) Emaar MGF Land Ltd vs. Simmi Sikka dated
______________
Page No.28 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
03.11.2020 passed by the Haryana Real Estate Appellate
Tribunal;
(d) Lucknow Development Authority vs. Uma Shankar
Dubey reported in 2020 (SCC) Online RERA (UP) 10;
(e) Securities and Exchange Board of India vs. Ajay
Agarwal reported in MANU/SC/0137/2010;
(f) Bombay Anand Bhavan Restaurant vs. Deputy
Director, ESI Corporation reported in
MANU/SC/1596/2009;
(g) Bharat Singh vs. Management of New Delhi
Tuberculosis Center, New Delhi reported in
MANU/SC/0322/1986;
(h) M3M India vs. Dr. Dinesh Sharma dated 04.09.2019
passed by the High Court of Delhi in CM(M) No. 1244 of
2019 & CM Appl. 38052-38053 of 2019;
(i) Imperia Structures Ltd vs. Anil Patni and ors. Reported
in MANU/SC/0811/2020; and
______________
Page No.29 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
(j) Ireo Grace Realtech Pvt. Ltd vs. Abhishek Khanna and
ors. reported in MANU/SC/0013/2021;
5. Heard the learned Senior Counsel appearing for the appellant
and the respondent and perused the materials placed before this Court.
6. The legislative intent behind the Act is to bring the disputes and
grievances regarding the Real Estate sector under the single roof namely
RERA Act. Therefore, it is not specifically provided where the RERA Act is
applicable to the projects which were completed before the Act came into
force or applicable only to the projects which are ongoing on the date of
commencement of the Act.
7. As per Section 14(3) of RERA Act, the grievance of the
buyers/allottee relating to such development, if any, is brought to the notice
of the promoter, within a period of five years from the date of handing over
possession, it shall be the duty of the promoter to rectify the same. In this
provision, the legislature specifically mentioned the period of limitation as
______________
Page No.30 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
five years. In Section 11 (4) (a) proviso clause, the responsibility of the
promoter extended beyond the period of five years as contemplated in
section 14(3) and shall continue even after the conveyance deed of all the
apartments, plots or buildings, as the case may be, to the allottees are
executed. So even after all the apartments were handed over and the sale
deeds executed, for the structural defect or any other defect the promoter is
liable and the responsibility is fixed without any limitation. The above said
provisions are contemplated in this Act since it is a welfare legislation not
only for the allottees but also for the promoters. Therefore, the question of
maintainability does not arise and the same has been clearly addressed by the
Appellate Authority by holding that the complaint raised by the respondent
Association is maintainable before the Regulatory Authority since there is no
other ways and means for the respondent Association to redress their
grievance.
8. Section 71 proviso clause and Section 79 of the RERA Act is
intended to redress the grievances of the home buyer or promoter under the
provisions of the RERA Act. The respondent Association has sought relief
______________
Page No.31 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
on the basis of the duties and responsibilities of the promoter, which is
contemplated under Section 11 of the RERA Act and for the said relief, the
respondent Association cannot approach the Civil Court since there is a
specific bar under Section 79 of the RERA Act. Without considering the
above, the Regulatory Authority has rejected the claim made by the
respondent Association by dismissing the complaint as not maintainable,
which has been rightly answered by the Tribunal and ordered as
'maintainable', thereby allowing the appeal and setting aside the order of the
Regulatory Authority in C.No.327 of 2019 dated 06.11.2019, which does not
warrant the interference of this Court. Accordingly, the order passed by the
Tribunal stands confirmed and the Regulatory Authority is directed to restore
C.No.327 of 2019 to file and dispose of the complaint within a period of two
months from the date of receipt of a copy of this judgment.
9. Accordingly, the Civil Miscellaneous Second Appeal stands
dismissed. No costs. Consequently, connected miscellaneous petitions stand
closed.
(J.N.B., J.) (R.K.M.J.,)
20.11.2024
______________
Page No.32 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
Internet : Yes/No
Index: Yes/No
Speaking Order: Yes/No
sts
To:
1) The Tamil Nadu Real Estate Appellate Tribunal (TNREAT), Chennai
2) Tamil Nadu Real Estate Regulatory Authority, Chennai
______________
Page No.33 of 34 https://www.mhc.tn.gov.in/judis
C.M.S.A.No.38 of 2021
J.NISHA BANU.,J.
and
R.KALAIMATHI , J.
sts
Judgment made in
C.M.S.A.No.38 of 2021
Dated:
20.11.2024
______________
Page No.34 of 34 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....