As per case facts, a property owner and a builder entered a joint development agreement for flats, which faced significant delays in construction and handover of the owner's share. Disputes ...
1/27 APPEAL(CAD) No. 22 of 2023
IN THE HIGH COURT OF JUDICATURE AT MADRAS
RESERVED ON : 20.01.2026
PRONOUNCED ON : 19.02.2026
CORAM
THE HONOURABLE MR JUSTICE C.V. KARTHIKEYAN
AND
THE HONOURABLE MR.JUSTICE K.KUMARESH BABU
APPEAL(CAD) No. 22 of 2023
and
CMP No.24440 of 2024
1. M/s.Malar Homes,
Rep. by its Managing Partner,
T.Gokulakrishnan, 1/7,
Sengeni Amman Koil 2nd Street,
Maduvankarai, Guindy,
Chennai-600 032.
2. T.Gokulakrishnan
Appellant(s)
Vs
1. R.Saroja
2.A.Seenivasan
Respondent(s)
PRAYER: Appeal filed under Section 13 of Commercial Court Act to set aside
the judgment and decree dated 17.08.2022 passed by the Commercial Court at
Chennai in COS No.216 of 2022.
For Appellant(s):Mr.S.Ramesh
For Respondent(s):Mr.S.Rajasekar for R1 https://www.mhc.tn.gov.in/judis
2/27 APPEAL(CAD) No. 22 of 2023
JUDGMENT
(Judgment of the Court was delivered by C.V.Karthikeyan, J.)
The first and second defendants in COS No.216 of 2022 have filed the
present appeal questioning the judgment and decree dated 17.08.2022, passed
by the Commercial Court at Chennai.
2.COS No.216 of 2022 had been initially instituted in the Original Side of
this Court as CS No.794 of 2012 and later transferred to the Vth Additional City
Civil Court, Chennai and renumbered as O.S.No.3970 of 2022 and on
constitution of the Commercial Court at Chennai, had been again transferred
and renumbered as COS No.216 of 2022.
3.The suit had been filed by the plaintiff seeking a direction against the
first and second defendants to pay a sum of Rs.50,50,000/- together with
interest at 15% per annum on 40,00,000/- from 01.03.2011 till the date of the
plaint and future interest and a further direction against the first and second
defendants to pay damages to a sum of Rs.20,20,000/- towards loss of rental
income, cost of unfinished civil work along with future rents and for mandatory
injunction directing the first and second defendants to deliver the schedule
mentioned flats to the plaintiff and for a declaration that the agreement of sale
entered into with the third defendant as null and void and for the costs of the https://www.mhc.tn.gov.in/judis
3/27 APPEAL(CAD) No. 22 of 2023
suit. However, owing to the subsequent events during trial, the relief sought
was confined only to the relief seeking damages for a sum of Rs.20,20,000/-
towards the loss of rental income, cost of unfinished civil work along with
future rents.
4.The schedule of properties in the plaint for which damages was sought
were two flats, flats A and B both in the first floor, admeasuring 1280 sq.ft each
inclusive of common area at D.No.27 A, 3
rd
street, Abhiramapuram, Chennai
600 018.
5.The Commercial Court by judgment dated 17.08.2022 had decreed the
suit with respect to the relief of payment of damages. The damages had been
crystallised to Rs.42,40,000/-, at Rs.80,000/- per month for both flats A and B
for the period from April 2011 till September 2015. It had also directed that this
amount shall be paid together with interest at 15% per annum from the date of
plaint till the date of decree and thereafter at 6% per annum till the date of
realisation of the entire amount. Challenging that judgment and decree, the
present appeal has been filed by the first and the second defendants.
6.In the plaint, the plaintiff Mrs.R.Saroja contended that she had entered
into a joint development agreement with the first defendant, M/s.Malar Homes,
represented by its Managing Partner, Mr.T.Gokulakrishnan, who was also
impleaded in his individual capacity as the second defendant, to develop the https://www.mhc.tn.gov.in/judis
4/27 APPEAL(CAD) No. 22 of 2023
sub-divided portion of the property measuring an extent of 2835 sq.ft. at
D.No.27 A, 3
rd
street, Abhiramapuram, Chennai 6000108. She had executed a
registered Power of Attorney in favour of the second defendant on 13.06.2007
to complete the joint venture apartment project.
7.It was contended that the joint venture was initiated in the year 2005
and an agreement was written down in the year 2007. There was however
considerable delay in commencing the project. The entire project was thereafter
re-worked and a Memorandum of Understanding was entered on 20.02.2010.
The first defendant agreed to put up a stilt in the ground floor and construct the
first and second floors with a total of four flats. Two flats were allotted to the
plaintiff and two flats were allotted to the share of the first defendant. The
plaintiff was also entitled to monetary consideration of Rs.1.25/- crores. It had
been contended that there was considerable delay in completing the project
though the time limit was determined at six to eight months from February
2010. On the date of the plaint, it was contended that out of the monetary
consideration of Rs.1.25/- crores, the first and second defendants had paid only
Rs.85,00,000/- and therefore, a relief was sought for the payment of balance
Rs.40,00,000/-, but subsequently, the said amount was paid. The first defendant
had also agreed to renovate the existing bungalow of the plaintiff in the
adjoining land. https://www.mhc.tn.gov.in/judis
5/27 APPEAL(CAD) No. 22 of 2023
8.It had been further contended that the first defendant also signed a letter
of undertaking on 16.09.2010 after identifying a buyer for flat D in the second
floor and assured to make the balance payment and hand over possession of the
flats A and B allotted to the plaintiff by March 2011.
9.The plaintiff contended that there was a clause in the agreement that
while identifying the buyer, the plaintiff would be consulted and the flats could
be sold only after obtaining the consent of the plaintiff. The sale in favour of
the purchaser of flat D was agreed by the plaintiff and the sale deed was also
executed on 13.09.2010. It had been stated that the first and second defendants
did not complete the construction of the flats in the first floor within the time
period fixed.
10.With respect to the other flat in the second floor, the first and second
defendants issued a letter on 11.08.2011 indicating the prospective purchaser. A
reply was given on 28.08.2011 by the husband of the plaintiff. The first and the
second defendants however entered into an agreement with the prospective
purchaser who was impleaded as third defendant and it was under those
circumstances that a relief was sought, seeking a restraint on execution of any
document conveying the flat to the third defendant. But however, subsequently
during the pendency of the trial, the flat had actually been sold to the third
defendant and therefore, that relief did not survive for adjudication. https://www.mhc.tn.gov.in/judis
6/27 APPEAL(CAD) No. 22 of 2023
11.The plaintiff cancelled the General Power of Attorney after issuing a
notice and registered the revocation document also. The plaintiff then raised a
demand for damages to a sum of Rs.20,00,000/- including loss of rental income
for the two flats from April 2011 and also costs of civil work left unfinished by
the first defendant and also damages for the mental agony suffered by the
plaintiff. It was under those circumstances that the suit had been filed for the
reliefs aforementioned.
12.It must also be stated that during the pendency of the suit, the flats A
and B mentioned in the schedule to the plaint had been handed over to the
plaintiff on September 2015. The only relief which therefore stood for
consideration is the claim for loss of rental income and damages for the delay in
handing over the possession of the two flats.
13.The first defendant filed written statement. It was contended that
initially an agreement was entered into in September 2005 for development of
the properties by constructing flats and to complete repairing works in the
adjoining building. It was stated that a contractor had already been engaged to
carry out the repair work, but owing to disputes, they had left halfway through.
Under the original agreement, the plaintiff was to receive one flat of 1250 sq.ft
and proportionate UDS of 708 sq.ft and also a sum of Rs.65,00,000/-. The
remaining three flats were allotted to the first defendant. Thereafter, a https://www.mhc.tn.gov.in/judis
7/27 APPEAL(CAD) No. 22 of 2023
Memorandum of Understanding was entered into on 05.04.2006. Subsequently,
another agreement was entered into on 14.06.2007, called Amendment of
Agreement. A final agreement was entered into on 20.02.2010.
14.The plaintiff was entitled to two flats and the first defendant was
entitled to the other two flats. The first defendant sold one flat to a purchaser.
The first defendant also identified a purchaser for the other flat. It was
contended that at all material point of time, the plaintiff and her husband
hindered the work and the civil works had to be redone again. It was contended
that the plaintiff and her husband wanted the market rate to increase to gain
maximum profit. The first defendant stated that the plaintiff and her husband
delayed the fixing of tiles and wood work so that the works are completed at a
later point of time so as to give an impression that the flats are new flats. It was
specifically stated that the construction of the entire flats were completed in
November 2010. There were only minor works to be done.
15.It was further contended that the plaintiff has to pay Rs.10,00,000/-
towards the work done in the adjacent bungalow and another sum of
Rs.10,00,000/- for the additional work done and materials used in the two flats.
16.It was further contended that the third defendant had been identified as
a purchaser. He had obtained Bank loan for payment of the sale consideration, https://www.mhc.tn.gov.in/judis
8/27 APPEAL(CAD) No. 22 of 2023
but however the sale deed could not be executed owing to the protests raised by
the plaintiff and her husband. It was contended that after having received and
enjoyed the money paid by the first defendant, the plaintiff had unilaterally
cancelled the Power of Attorney. It was contended that the first defendant was
not liable for any of the reliefs sought and that the suit should be dismissed.
17.On the basis of the above pleadings and owing to the fact that the
defendants had paid a sum of Rs.40,00,000/- claimed by the plaintiff towards
the balance monetary consideration, and had also handed over the possession of
the flats A and B to the plaintiff and the sale deed in favour of the third
defendant had also been executed, the relief relating to the claim of damages
was alone put to trial.
18.During trial, the husband of the plaintiff was examined as PW1 and a
Civil Engineer was examined as PW2. The plaintiff marked Exs.P1 to P21.
Ex.P2 dated 13.06.2007 was the copy of the General Power of Attorney and
Ex.P10 dated 13.06.2007 was the copy of the revocation of the said Power of
Attorney. Ex.P3 was the Memorandum of Understanding dated 20.02.2010 and
Ex.P4 was the Letter of Understanding dated 16.09.2010. The letters exchanged
between the parties were marked as Exs.P6, P7, P9, P11, P12 and P15. The
report of the Advocate Commissioner dated 12.04.2014 was marked as Ex.P13.
The reports of the Civil Engineer were marked as Exs.P19 and 20. https://www.mhc.tn.gov.in/judis
9/27 APPEAL(CAD) No. 22 of 2023
19.The second defendant examined himself as DW1 and marked Exs.D1
to D7. Exs.D1 and D2 were the earlier agreements in September 2005 and April
2006. Ex.D4, D6 & D7 were copies of the building plan.
20.The Trial Judge examined Ex.P3, by which, the first and second
defendants had agreed to complete the construction work and handover two
apartments to the plaintiff within a period of six to eight months. It was
observed that the first and second defendants had not completed the
construction or handed over the flats to the plaintiff. Even when the plaint was
presented before the Court, the construction work was not completed and an
Advocate Commissioner had been appointed, whose report has been marked as
Ex.P13. A Civil Engineer had measured the construction and noted the physical
features in the report. The report was also annexed with the report of the
Advocate Commissioner. The works which had not been completed had also
been mentioned and the total estimate of the unfinished work was also given. It
was also observed that when the suit was pending in the Original Side of the
High Court, a direction had been passed against the first and second defendants
to complete painting, wood work, electrical work and other works and hand
over the possession of A and B flats to the plaintiff. It was therefore held by the
Trial Judge that the delay was only owing to the defendants. https://www.mhc.tn.gov.in/judis
10/27 APPEAL(CAD) No. 22 of 2023
21.With respect to the issue of damages and the rental value, the Trial
Court relied on the evidence of PW2, who had determined the monthly rent at
Rs.47,965/- for flat A and Rs.48,303/- for flat B. The Trial Court had fixed a
uniform rent of Rs.40,000/- for each of the two flats and had observed that the
loss of rental income was Rs.80,000/- per month. It was also observed that the
plaintiff had suffered rental income for a period of 53 months from April 2011
till September 2015. The damages was therefore crystallised at Rs.42,40,000/-.
Though the plaintiff had claimed Rs.20,20,000/-, the suit was partly decreed and
dismissed with regard to the other reliefs which had become infructuous.
Questioning this judgment and the reasonings thereunder, the first and second
defendants have filed the present appeal.
22.Mr.S.Ramesh, learned counsel for the appellants/first and second
defendants took the Court through the facts of the case. He stated that even
according to the plaintiff, an agreement between the first and second defendants
and the plaintiff was initiated in the year 2005 and an agreement was entered
into in the year 2007 and subsequently, Memorandum of Understanding was
again entered into on February 2010. The learned counsel stated that the terms
had been varied in accordance with the wishes of the plaintiff. The learned
counsel pointed out that the appellants had performed their part of the
agreement, but unfortunately, there was obstruction at every stage from either
the plaintiff or her husband. He pointed out that there was an obstruction in https://www.mhc.tn.gov.in/judis
11/27 APPEAL(CAD) No. 22 of 2023
laying of the tiles and completing the wood work. He stated that the first
respondent wanted to delay the completion of construction of the flats,
particularly, the interior works only to take advantage of the increase in the
market value. The learned counsel pointed out Ex.P13, which was the report of
an Engineer annexed along with the report of the Advocate Commissioner,
wherein, the total value of the unfinished work was estimated to Rs.5,00,000/-
He contended that the bonafide of the appellants could be seen from the fact that
they paid the balance consideration to be paid to the respondent. Further, the
sale deed had also been executed in favour of the third defendant in the suit.
With reference to the issue of damages, the learned counsel pointed out that
PW2 had inspected the building after the cross examination of PW1 was
completed and after PW1 had admitted that he had not produced any document
to determine the rental value and the loss suffered by him. The learned counsel
for the appellants therefore contended that the Court should reject the report of
PW2. The learned counsel asserted that the delay in handing over the flats is
only owing to the conduct of the plaintiff and her husband and stated that the
suit should be dismissed and even if decreed should only be confined to the
penalty as agreed by the parties in their agreement.
23.Mr.S.Rajasekar, the learned counsel for the first respondent however
denied and disputed the said contentions. The learned counsel pointed out that
it was reasonably insisted by the first respondent who had to live in the https://www.mhc.tn.gov.in/judis
12/27 APPEAL(CAD) No. 22 of 2023
adjoining flats to be informed about the intending purchaser and about his
details since there was no necessity for the first respondent to live with a
neighbour with whom peace would not reign. The learned counsel stated that
the appellants had completed the flats allotted to them in the second floor at a
very fast rate and one of the flats had actually been conveyed and the purchaser
for the other flat had also been identified. However, the appellants had not
proceeded with the same speed in completing the flats in the first floor, which
fell to the share of the first respondent.
24.The learned counsel stated that the delay was deliberate and damages
therefore should be imposed on the appellants for the delay in handing over of
the flats. The learned counsel stated that in this connection to determine the
rental value, the first respondent had examined PW2, the Engineer who had
forwarded his reports. He contended that the reports, Exs.P19 and 20 had been
finalised taking into consideration all factors and as a matter of fact stated that it
was on the lower scale. The learned counsel argued that the appellants did not
have the monetary capacity to complete the constructions of flats within the
time stipulated. He therefore insisted that the appeal should be dismissed and
the decree of the Trial Court should be affirmed.
25.We have carefully considered the arguments advanced. The following
points arise for consideration: https://www.mhc.tn.gov.in/judis
13/27 APPEAL(CAD) No. 22 of 2023
(i) Whether the contention of the
appellants that the delay in completion of
construction of the flats in entirety was
only owing to the obstructive nature of the
respondents had been established during
trial?
(ii)If the delay was attributable also
on the appellants, the quantum of damages
payable by the appellants?
(iii)Whether this Court can take into
consideration Exs.P19 and 20, the reports
of PW2, the Civil Engineer when
admittedly the Civil Engineer visited the
suit properties after cross examination of
PW1?
26.Since the evidence relating to the three issues are interlinked, all the
three issues are taken up for consideration together.
27.The first respondent herein and the appellants had entered into a
Memorandum of Understanding on 20.02.2010 with respect to construction of
four flats in the land belonging to the first respondent. The understanding
envisaged that the appellants herein would construct four flats leaving a stilt in
the ground floor and putting up two flats each in the first and second floors in
the land belonging to the first respondent. The appellants also undertook the https://www.mhc.tn.gov.in/judis
14/27 APPEAL(CAD) No. 22 of 2023
repair works in the bungalow of the first respondent which was just adjoining.
As a matter of fact, the parties had commenced discussions in the year 2005 and
an agreement had been entered into in September 2005, which had been
produced by the appellants and marked as Ex.D1. In the plaint, the first
respondent had also contended that the joint venture had been initiated in the
year 2005 and later culminated in an agreement in the year 2007. However, the
fact that there was an agreement in the year 2005 had not been stated explicitly
in the plaint by the first respondent. This fact would only go to show that both
parties had been protracting coming to terms on the issue of construction of flats
right from the year 2005 onwards. Therefore, there cannot be a definite finding
rendered that the appellants alone were the cause for the delay. But the fact
remains that the parties continued to have a business relationship in spite of the
project not starting from the year 2005 till the year 2010. In the year 2007, the
respondents had executed a General Power of Attorney, which was marked as
Ex.P2 and dated 13.06.2007. The Memorandum of Understanding on which
construction was commenced by the appellants, had been entered into only on
20.02.2010, nearly 4 ½ years after Ex.D1, the first agreement in September
2005. There was also an earlier Memorandum of Understanding on 05.04.2006,
which was marked as Ex.D2. These three documents Ex.D1, Ex.D2 and Ex.D3
itself would show that negotiations went on for a protractive period of time. It
is contended by the appellants that it was the first respondent who protracted
negotiations and in finalising the terms of the agreement. A building plan had https://www.mhc.tn.gov.in/judis
15/27 APPEAL(CAD) No. 22 of 2023
been obtained on 12.09.2009, which had been marked as Ex.D7. The revised
plans were obtained on 05.03.2010 and marked as Ex.D6 and Ex.D7.
28.But however the prevailing agreement was the Memorandum of
Understanding under Ex.P3. In Ex.P3, it had been provided as follows:
The builder will complete and
handover the apartments in 6 to 8 months
from the time of signing this MOU.
29.This clause had been emphasised by the learned counsel for the first
respondent who argued that since the construction had not been completed and
the two flats had not been handed over to the first respondent, the appellants
must pay damages for the delayed handing over of the flats. But however, a
further perusal of the agreement would show that there was no possibility of the
appellants commencing construction on the date when the Memorandum of
Understanding, dated 20.02.2010, was executed since even in the said
Memorandum of Understanding, it had been stated as follows:
The Builder will have a revised plan
sanctioned by the appropriate authority and build
4 apartments in the subdivided plot as in Schedule
‘B’.
It is thus evident that on the date of Memorandum of Understanding,
there was no sanctioned plan to enable construction to commence. The revised https://www.mhc.tn.gov.in/judis
16/27 APPEAL(CAD) No. 22 of 2023
sanctioned plan was issued later on 05.03.2010 as seen from Exs.D6 and D7.
Therefore, there could not have been a possibility of strict adherence to the time
limit mentioned in Memorandum of Understanding. It is further seen from
Ex.P4 dated 16.09.2010 that two flats were allotted to the owners and that the
flats will be handed over to the owners by 15
th
January 2011 and wood work
and interior final painting would take two months after that date. It had been
further undertaken as follows:
In case of any delay, Rs.6,000/- PM will
be paid as penalty till handover/completion.
30.It is thus seen that both parties had consciously agreed that the penalty
payable for delayed handing over of possession of the flats was Rs.6,000/- per
month. When sanctity is insisted on performance of the agreement with respect
to the time limit stipulated, sanctity must also be attached to this clause also. It
was further contended that all works including in the common areas will be
completed by March 2011. Thus, the time period for completion of work had
been extended and there is no evidence that this extension of the time had been
protested by the first respondent. This document had been marked by the first
respondent. Further, it had been also stated as follows:
Construction Agreement will be signed for owners within 2 weeks.
31.No document relating to such construction agreement had been
produced before this Court. https://www.mhc.tn.gov.in/judis
17/27 APPEAL(CAD) No. 22 of 2023
32.It has to be therefore held that the parties were still negotiating and did
not reach finality in their agreement. But however very pertinently, penalty had
been determined at Rs.6,000/- per month, specifically for the delay in handing
over the flats. In the plaint, the first respondent had also referred to this
document Ex.P4 and had also stated that the appellants had undertaken to
handover possession of the flats by March 2011. But however the quantum of
penalty determined had been stated suppressed in the plaint.
33.Letters were then exchanged between the parties with each raising
allegations against each other. The first from the appellants on 11.08.2011
under Ex.P6 for which a reply was given by the first respondent under Ex.P7 on
28.08.2011. In Ex.P6, the appellants had given their own reasons as to why the
flats could not be completed within March 2011. A reply had been issued under
Ex.P7 on 28.08.2011. In that reply, the husband of the first respondent had
stated as follows:
1.Must complete the flat belonging to me in a
month’s time including wood works as specified in
MOU.
Therefore, the time limit had again been shifted from August 2011 to
October 2011. A perusal of the tenor of the letters exchanged between the
parties would show that there has been complete breakdown of mutual trust. https://www.mhc.tn.gov.in/judis
18/27 APPEAL(CAD) No. 22 of 2023
34.It had then come to the knowledge of the first respondent that the
appellants had entered into an agreement of sale with the third defendant in the
suit. This prompted the first respondent to proceed to revoke the Power of
Attorney given in favour of the appellants. This revocation deed was marked as
Ex.P10 dated 09.04.2012. In the revocation deed, the first respondent had
stated as follows:
I hereby CANCEL the said Power of
Attorney absolutely and completely and revoke
all the Powers and Authorities thereby and
thereunder given to him either expressly or
impliedly, to all interests and purpose. I now
hereby revoke and declare as null and void all
and singular the Power and Authority conferred
on the said Mr.T.Gokula Krishnan through the
above mentioned General Power of Attorney.
35.It is therefore evident that on and from this date, the appellants could
not act on behalf of the first respondent with respect to the suit properties.
36.They had an obligation to construct the flats, but the first respondent
had revoked all powers and authorities given either expressly or impliedly.
Under the Power of Attorney which had been marked as Ex.P2 dated
13.06.2007, the authority given was as follows:
3.To enter into an agreement/MOU for https://www.mhc.tn.gov.in/judis
19/27 APPEAL(CAD) No. 22 of 2023
sale with any third parties, sign the sale
agreement(s) on my behalf and also to receive
the advances/sale consideration in respect of
the schedule B property measuring about 2835
Sq.ft. The Sale of Undivided Share of land by
the Power Agent is limited to maximum 2135
Sq.ft. as the Principal is intend to retain about
700 Sq.ft for the purpose of owning one flat in
the proposed construction of residential
building in the Schedule B.
37.Thus, effectively, the first respondent had revoked the authority given
to the appellants to sell the flat in favour of the third defendant. The flat had
actually been conveyed subsequently to the same intended party/the third
defendant. This also indicated that both parties have been oscillating in their
relationship, taking extreme stands and levelling allegations against each other.
However, the fact remains that the penalty for delayed handing over of the flats
was fixed at Rs.6,000/- per month and that has not been altered and even sought
to be altered by any of the letters exchanged between the parties on subsequent
dates.
38.Further letters were then exchanged. The first one on 10.04.2012
under Ex.P11 by the appellants to the first respondent, wherein, it had been
specifically stated as follows:
Moreover the two flats falling to
your share are fit and ready for occupation
for the past 6 months. We can handover https://www.mhc.tn.gov.in/judis
20/27 APPEAL(CAD) No. 22 of 2023
possession, once the accounts are
reconciled and all pending payments are
made.
39.This letter was replied by the first respondent under Ex.P12 dated
10.05.2012, wherein, she had stated as follows,
4) I still disagree with your contention that
the two flats falling to my share are fit and ready
for occupation. To set right the controversy I would
like to make an inspection of the aforesaid flats with
the help of a Chartered Civil Engineer on a day
convenient to both of us. You may indicate few days
falling in this month and the convenient time for
such inspection. Once an independent assessment
is done by the Chartered Civil Engineer I will be in
a position to take appropriate decision. Hope you
would co-operate in this regard and hand over the
flats completely finished with everything agreed
upon in the Memorandum of Understand fulfilled,
including wood works.
40. It is thus seen that the correspondences exchanged between both sides
only contain allegations against each other.
41.The plaint was then presented on 30.11.2012. During the pendency of
the suit, an Advocate Commissioner had been appointed. He filed a report
enclosing a report of an Engineer. This document had been marked as Ex.P13. https://www.mhc.tn.gov.in/judis
21/27 APPEAL(CAD) No. 22 of 2023
The Engineer was appointed to determine the unfinished work, their estimates,
measurements as well the status on painting, electrification, flooring works etc.
42.The Engineer had also given a report dated 12.04.2013 listing out the
works which had not been done and estimated their total cost at Rs.5,83,994.30.
Even though it is claimed that the respondents had raised objections to the same,
the said objections are not on record. Be that as it may, while examining the
issue as to who was responsible for the delay, it is evident that both sides are
equally responsible. But again, it is to be pointed out that the penalty for
delayed handing over of the flats was determined at Rs.6,000/- per month and in
the plaint that had not been questioned or challenged or objected to or claimed
to have been altered.
43.PW1 had been examined and cross examined. He reiterated the same
facts. The reason for the delay was placed solely on the appellants. DW1 had
been cross examined and he placed the reasons for the delay solely on the first
respondent.
44.However, since the issue had narrowed down only to the payment of
damages for the delayed handing over of the flats, which damages were
quantified at Rs.20,20,000/- in the plaint, PW1 was questioned as to how he
had determined that amount. The plaint also did not contain a work sheet as to https://www.mhc.tn.gov.in/judis
22/27 APPEAL(CAD) No. 22 of 2023
how that particular amount was crystallised. It had only been mentioned as
follows:
A demand was also made for the balance sum of
Rs.40,00,000/- with a reasonable interest @ 18% per
annum from March 2011 apart from the damages to
tune of Rs.20 lacs inclusive of loss of rental income for
the two flats from April 2011, cost of painting the
exterior of the bungalow and other civil work left
unfinished by the first defendant and damages for
mental agony suffered by the plaintiff.
45.It had been stated that this Rs.20,00,000/- was inclusive of loss of
rental income for the two flats from April 2011 and for the cost of unfinished
work. But however, the rental income was then mentioned in the plaint at
Rs.45,000/- per flat per month. The first respondent had calculated the loss of
rental income at Rs.90,000/- per month for the two flats from April 2011 till
November 2012, which was when the plaint was presented. But again, no
working sheet was produced determining the rent at Rs.45,000/-. During his
cross examination, PW1 admitted to this fact and stated as follows:
Since I did not get any revenue from the flats and
was also denied access to the flats, I have made a claim
of Rs.20,20,000/-. I have not filed any documentary
proof in support of such claim. I deny the suggestion
that my claim is speculative. https://www.mhc.tn.gov.in/judis
23/27 APPEAL(CAD) No. 22 of 2023
46.This admission was on 11.12.2017 and is very significant. Even
during the pendency of the suit, for five years from the date of presentation, the
first respondent had not taken any steps to determine the probable rental value.
Thereafter, the first respondent had engaged a Civil Engineer who was
examined as PW2. He had inspected the suit schedule flats on 18.12.2018 to
determine the rental value. In his cross examination, he admitted that he did not
issue any notice to the appellants before his inspection. He further stated that he
was requested by the first respondent to inspect and give a report just one week
prior to 18.02.2018. It is thus seen that the entire exercise had been undertaken
after the cross examination of PW1 had been completed.
47.Any plaintiff who comes to Court with specific allegations must have
marshalled his documentary and oral evidence before the commencement of
trial and not indulge in gathering evidence during the course of trial and
moreover particularly, after admitting that he had not filed any documentary
proof for the claim made, in this instant case of Rs.20,20,000/-. Having
mentioned the rental income at Rs.45,000/- per month in the plaint, the plaintiff
was duty bound to produce documents to that effect along with the plaint. That
amount should have been stated in the plaint on the basis of documents
available. Failure to do so would only render the documents subsequently
produced as having been produced to be inconsonance with the pleadings
already pleaded. Any document subsequently produced would only be in https://www.mhc.tn.gov.in/judis
24/27 APPEAL(CAD) No. 22 of 2023
alignment with the pleadings and they can never be stated to be an independent
unbiased assessment of the rental value.
48.The learned Trial Judge had granted damages payabel from April 2011
till September 2015. But however, the documents themselves show that the first
respondent had extended the period for further time in the reply under Ex.P7
and shifted the time period to September 2011. In view of these facts which
have been deduced from the documents and the evidence adduced by the
parties, it is clear that time was never the essence of the agreement and even if
time period had been determined in the Memorandum of Understanding under
Ex.P3, it was impossible to keep up with that time period since the revised plan
was not even sanctioned on that date. Further, the claim for damages on the
basis of loss of rental income does not admit to logic. If the first respondent
seeks damages for loss of rental income, then it is obvious that the flats were not
to be a place of personal residence. If that be the case, the first respondent had
no right to question the sale in favour of the third defendant. This objection to
convey the property to the third defendant was wholly unjustified. We would
therefore answer the points framed for consideration that the delay was owing to
the conduct of both parties at irregular intervals. It is evident that there was
complete breakdown of trust and moreover with the revocation of Power of
Attorney in April 2012 under Ex.P10, the authority and the responsibility of the
appellants to commit to their obligations under the Memorandum of https://www.mhc.tn.gov.in/judis
25/27 APPEAL(CAD) No. 22 of 2023
Understanding stood diluted. It is to be however stated that they still proceeded
with the completion of the flats.
49.The reports of PW2, the Engineer will necessarily have to be rejected
as they have been prepared during the course of trial, after commencement of
recording of evidence and most specifically, after the cross examination of PW1
and more importantly, after the admission of PW1 that he had not produced any
document to substantiate the quantum of damages and further since PW2 had
been appointed by PW1 and was therefore obliged to PW1. Admittedly, PW2 is
not an independent Engineer appointed by the Court. The Engineer appointed
by the Advocate Commissioner, had given a report under Ex.P13 that the
estimate of the unfinished work amounted to Rs.5,83,994.30.
50.In view of these reasons, we would interfere with the amount
determined by the learned Trial Judge as damages and retain the amount as
determined by the parties in the letter of undertaking Ex.P4, dated 16.09.2010
and quantify the same from September 2011 till September 2015, which should
be for 48 months. The amount agreed by the parties was Rs.6,000/- per month,
which comes to Rs.2,88,000/-.
51.Accordingly, we hold that the damages for 48 months should be
Rs.2,88,000/-. We would partly allow the appeal and determine the quantum of https://www.mhc.tn.gov.in/judis
26/27 APPEAL(CAD) No. 22 of 2023
damages payable by the appellants to the first respondent at Rs.2,88,000/-
together with interest at 15% per annum from the date of the plaint till this date
and thereafter, interest at 6% per annum till the date of realisation of the entire
amount. In view of the fact that we have rendered a finding that the delay was
also due to the conduct of the first respondent and also of the appellants, we are
not inclined to grant costs to either side.
52.The appeal is partly allowed. No costs. Consequently, connected
miscellaneous petition is also closed.
(C.V.K.J., ) (K.B.J., )
19.02.2026
Index:Yes/No
Speaking/Non-speaking order
Internet:Yes
Neutral Citation:Yes/No
sli
To
The Commercial Court,
Chennai. https://www.mhc.tn.gov.in/judis
27/27 APPEAL(CAD) No. 22 of 2023
C.V.KARTHIKEYAN, J.
AND
K.KUMARESH BABU, J.
sli
Pre-delivery Judgment in
APPEAL(CAD) No. 22 of 2023
19.02.2026 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....