No Acts & Articles mentioned in this case
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR
&
THE HONOURABLE MRS. JUSTICE C.S. SUDHA
MONDAY, THE 13
TH
DAY OF DECEMBER 2021 / 22ND AGRAHAYANA, 1943
ARB.A NO. 38 OF 2020
AGAINST THE ORDER DATED 30.11.2019 IN OP(ARB) 664/2012 OF ADDITIONAL
DISTRICT COURT-V, EKM
APPELLANT/RESPONDENT:
M/S.NAVAYUGA ENGINEERING COMPANY LTD
REGISTERED OFFICE, 48-917, DWARAKA NAGAR,
VISHAKHAPATTANAM 530-016,
REPRESENTED BY ITS AUTHORISED SIGNATORY
BY ADVS.SANTHOSH MATHEW
SRI.ARUN THOMAS
SRI.JENNIS STEPHEN
SRI.VIJAY V. PAUL
SMT.KARTHIKA MARIA
SMT.VEENA RAVEENDRAN
SRI.ANIL SEBASTIAN PULICKEL
SMT.DIVYA SARA GEORGE
SMT.JAISY ELZA JOE
SHRI.ABI BENNY AREECKAL
SMT.LEAH RACHEL NINAN
SMT.SHARAN PREM
RESPONDENT/PETITIONER:
UNION OF INDIA
REPRESENTED BY THE CHIEF ENGINEER (NW),
NAVAL BASE P.O.,KOCHI-682 004.
BY ADV SRI.K.SHRI HARI RAO, CGC
THIS ARBITRATION APPEAL HAVING COME UP FOR ADMISSION ON
30.11.2021, THE COURT ON 13.12.2021 DELIVERED THE FOLLOWING:
2021/KER/52252
Arbitration Appeal No.38 of 2020
-2-
“C.R.”
P.B.SURESH KUMAR & C.S.SUDHA, JJ.
--------------------------------------------------
Arbitration Appeal No.38 of 2020
-----------------------------------------------
Dated this the 13
th
day of December, 2021
JUDGMENT
C.S.Sudha, J.
The Hon’ble Supreme Court in Project Director, National
Highways Authority of India v. M. Hakeem, (2021 SCC Online
473) held that Section 34 of the Arbitration and Conciliation Act, 1996
(the Act) does not contemplate modification of an award by a court in a
proceeding under the said Section. Now the question is what
constitutes modification of an award? If the Arbitrator has awarded
separate amounts on various independent claims, would setting aside
some of the claims, which are separable and independent of the
remaining claims, constitute a modification of the award? This is one
2021/KER/52252
Arbitration Appeal No.38 of 2020
-3-
major issue apart from the justifiability of interference made by the
court below and the arbitrability of certain disputes decided by the
Arbitrator, that calls for an adjudication in this case.
2.First, a brief reference to the facts of the case-
The appellant and the respondent herein entered into a
contract for the provision of Parade Ground, PT Complex, Athletic
Track, Swimming Pool, Covered PT and Drill Shed etc. at
Ezhimala. The work was completed on 31/10/2007. Disputes arose
between the parties and hence the matter was referred for
arbitration. Sri.N.D.Bhagatkar, Chief Engineer (QS&C), C/o.
Commander Works Engineer, Pune was appointed as the sole
Arbitrator. 31 claims were raised before the Arbitrator by the
claimant for a total amount of Rs.16,04,07,582/- with interest.
Claims 1 to 5, 7, 8, 10, 11, 14, 15,16 to 20, 27, 30 and 31 were
allowed and the remaining claims were rejected. The Arbitrator by
award dated 21.5.2012 granted an amount of Rs.3,93,24,065/- with
interest at the rate of 9% per annum w.e.f. 13/09/2009 to the date of
2021/KER/52252
Arbitration Appeal No.38 of 2020
-4-
award to be paid within 90 days from the date of award, failing
which interest was to be paid @ 11% from the date of award till
payment. The claim of the respondent for Rs.11 lakhs (Rs.5 lakhs
for cost of arbitration and Rs.8,38,032/- for repair of roof) was
rejected by the Arbitrator.
3.The respondent/Union of India (UoI) preferred O.P.
Arb. Appeal No.664/2012 before the District Court, Ernakulam
challenging the award. The Court confirmed the award under claim
no.2, 3,10,11,14,15,20 and 27 and set aside the award under claim
no.1,4,5,7,8,16, and 19. The award under claim no.31 was
modified. The award of Rs.3,93,24,065/- was thus reduced to
Rs.22,36,380/- plus cost of Rs.28,402/-. Aggrieved, the
appellant/claimant is before us.
4.Heard Sri. Anil Sebastian Pulickel, the learned counsel
for the appellant and Sri.K.Shri Hari Rao, the learned Central
Government Counsel for the respondent.
5.According to the learned counsel for the appellant, the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-5-
court below went wrong in partly setting aside the award, which in
effect, is a modification of the award. This is not permissible under
Section 34 of the Act. It was pointed out that in a proceeding
under Section 34, the court can only set aside an award on any of
the grounds mentioned in S. 34(2) or 34 (2-A) and in no case, can
the court modify an award or set aside an award partially except in
the contingency provided under the proviso to S.34 (2)(a) (iv). If
at all the court finds that a portion or part of the award is bad, the
remedy lies in S. 34 (4), goes the argument. Reference was made
to Hakeem’s (supra) case in support of the argument that the court
has no power to modify an award. The learned counsel, in all
fairness, has also brought to our notice, decisions which have held
that the doctrine of severability can be applied to awards which are
severable. Raghul Construction Engineers and Contractors v.
N.T.P.C. [(2005) SCC Online Kerala 389]; R.S. Jiwani
Mumbai v. Ircon International Ltd. Mumbai (2010 (1)
Mh.L.J 547); Anugraha Engineers & Contractors v. Union of
2021/KER/52252
Arbitration Appeal No.38 of 2020
-6-
India (2014-1-L.W.132); Saptarishi Hotels Pvt. Ltd. v.
National Institute of Tourism and Hospitality Management
(2019 SCC Online TS 1765) are the decisions referred to by the
learned counsel. Therefore, the argument advanced is that the
present appeal is liable to be allowed and the order of the court
below can be set aside on this preliminary point itself, without this
Court going into the merits of the case. On the other hand, it was
submitted on behalf of the respondent that there is no infirmity or
illegality in the impugned order as canvassed by the appellant.
6.In Raghul Construction (supra) a Division Bench of
this Court held that if some portions of the award are without
jurisdiction, such part alone can be set aside if it will not affect the
award in respect of disputes which are arbitrable. The whole award
need not be set aside. However, this decision is rendered on the
basis of the Arbitration and Conciliation Act, 1940, which
contained a specific provision for modification of the award, that
is, Section 15. In the present Act, no such provision for
2021/KER/52252
Arbitration Appeal No.38 of 2020
-7-
modification of the award has been made. Therefore, the principle
laid down in Raghul Construction (supra) cannot be applied to
the facts of the present case as it is the 1996 Act that is applicable
here.
7.In R.S. Jiwani's (supra), the questions of law that arose
for consideration before a Full Bench of the Bombay High Court
were - (i) whether the doctrine of severability could be applied to
an award in a proceeding under Section 34 of the Act; and (ii) the
scope of the proviso to Section 34(2)(iv) and whether its
application is restricted to clause (iv) alone or whether it applies to
the whole of Section 34(2) of the Act. It was held that the doctrine
of severability an established concept, has been applied to the law
of contract since time immemorial. The intention of the Legislature
in enacting the 1996 Act is to free the Arbitral Tribunal from the
rigours of strict rules of procedure and permit least interference by
the court. An arbitral award is final and binding on the parties and
even on persons claiming under them in terms of Section 35 of the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-8-
Act. Therefore, it would be unjust and unfair to deny the statutory
rights accrued to the parties by not applying the doctrine of
severability if some part of the award is unsustainable and where
other part of the award is found to be good and enforceable in law
by the court in exercise of its powers under Section 34 of the Act.
However, the case would be different where it is not possible or
permissible to sever the award. If the bad part of the award is
intermingled and interdependent upon the good part of the award,
then it is not possible to sever the award as the illegality may affect
the award as a whole. In such cases, it may not be possible to set
aside the award partially. There is no bar in law in applying the
doctrine of severability to awards which are severable. If the
principle of severability can be applied to a contract and even to a
statute, then there is no reason why it cannot be applied to a
judgment or an award containing resolution of disputes between
parties and providing them such relief as they may be entitled to in
the facts of the case. When partial challenge to an award is
2021/KER/52252
Arbitration Appeal No.38 of 2020
-9-
permissible, then certainly partial setting aside of an award is also
possible. Regarding the proviso to Section 34(2) (a) (iv), it was
held that it has to be read ejusdem generis to the main Section, as
in cases falling in that category, there is an absolute duty on the
court to invoke the doctrine of severability where the matter
submitted for arbitration is clearly separable from matters not
referred for arbitration.
8.Anugraha Engineers (supra) was a case in which the
court under Section 34 of the Act set aside the award in part in
respect of claims 1, 2 and 6 and upheld the award in respect of the
remaining claims (there were about a total of 15 claims). The
Madras High Court held that the remedy lies in sub-section (4) of
Section 34 of the Act and that the court while dealing with an
application under Section 34 can either set aside the award in its
entirety or dismiss the application, but it cannot set aside the award
in part. In other words, the court dealing with an application under
Section 34, cannot assume the power of an appellate forum and
2021/KER/52252
Arbitration Appeal No.38 of 2020
-10-
modify the award. Hence, the order of the court below was held to
be infirm and defective and therefore liable to be set aside.
9.Hakeem (supra) was a case in which land was acquired
under the National Highways Act, 1956. The Competent Authority
under the said Act awarded very low amounts as compensation,
that is, amounts ranging from Rs.46.55/- to Rs.83.15/- per sq.
meter. No infirmity was found in this, by the District Collector who
made the arbitral award. However, in the proceedings under
Section 34, the District Court enhanced the amount of
compensation to Rs.645/- per sq.meter, thereby modifying the
award of the District Collector. In appeal, a Division Bench of the
Madras High Court upheld the modification made. The respondent
therein, namely, the National Highways Authority of India took up
the matter before the Hon'ble Supreme Court. The Apex Court,
after examining various other decisions held that in a proceeding
under Section 34, the court does not have the power to modify an
award. The Apex Court disagreed with the findings of the High
2021/KER/52252
Arbitration Appeal No.38 of 2020
-11-
Court which held that merely because the words 'modify' or 'vary'
is not indicated in Section 34, it would not take away the
jurisdiction of the court exercising its jurisdiction under Section
34 to interfere with the award passed by the Arbitrator partially;
that if such a power is not vested with the court, it would lead to
multiplicity of proceedings which was never intended by the
legislature while framing Section 34; that a reasonable
interpretation to Section 34 would only lead to the irresistible
conclusion that the court can modify or vary the award of the
Arbitrator if it is contrary to the material evidence adduced by the
parties; that even otherwise, as contemplated under Section 34 (2)
(v)(b)(ii) of the Act, when the award passed by the Arbitrator is in
conflict with the public policy of our country, reversal or
modification of such award passed by the Arbitrator is well within
the provisions contained under Section 34 of the Act. The Apex
Court noticed that the question has been settled finally in
McDermott International Inc. v. Burn Standard Ltd [(2006)
2021/KER/52252
Arbitration Appeal No.38 of 2020
-12-
11 SCC 181], Kinnari Mullick vs Ghanshyam Das Damani
and Dekshin Haryana Bijli Vitran Nigam Ltd. v. Navigant
Technologies Pvt. Ltd. (2021 SCC Online SC 157). Further,
to state that the judicial trend appears to favour an interpretation
that would read into Section 34, a power to modify, revise or vary
the award would be to ignore the previous law contained in the
1940 Act; as also to ignore the fact that 1996 Act was enacted
based on the UNCITRAL Model Law on International Commercial
Arbitration, 1985, which makes it clear that even the limited
judicial interference on extremely limited grounds not dealing
with the merits of an award, the 'limited remedy' under Section 34
is co-terminus with the 'limited right', namely, either to set aside an
award or remand the matter under the circumstances mentioned in
Section 34 of the Act. It further held, if one were to include the
power to modify an award in Section 34, one would be crossing
the lakshman rekha and doing what, according to the justice of a
case, ought to be done. In interpreting a statutory provision, a
2021/KER/52252
Arbitration Appeal No.38 of 2020
-13-
Judge must put himself in the shoes of the Parliament and then ask
whether Parliament intended this result. The Parliament very
clearly intended that no power of modification of an award exists
in Section 34. It is only for the Parliament to amend the aforesaid
provision in the light of the experience of the courts in the working
of the Act and to bring it in line with other legislations the world
over. Holding so, the decision of the Madras High Court was
overruled. The Apex Court also noted that decisions of the
Supreme Court modifying awards were in exercise of its powers
under Article 142 of the Constitution of India, which power cannot
be exercised by other courts.
10.In Saptarishi Hotels case (supra), the Telangana High
Court held that by applying the doctrine of severability, an award
can be set aside in part.
11.By referring to Hakeem's case (supra), it was submitted
on behalf of the appellant that the Hon'ble supreme Court has in
quite unambiguous terms held that modification of an award under
2021/KER/52252
Arbitration Appeal No.38 of 2020
-14-
Section 34 is impermissible. That being the law of the land, the
court below went wrong in interfering with the award and setting
aside some of the claims, which is nothing but modification of the
award and hence impermissible.
12.According to us the dictum in Hakeem's case (supra)
can be distinguished on facts. As stated earlier, the District Court in
the proceedings under Section 34 found that the amount of
compensation granted to the land owners under the National
Highway Act by the authorities under the Act was abysmally low
and therefore enhanced the compensation to Rs.645/- per sq.mtr. in
the place of Rs.46.55/- to Rs.83.15/- per sq.mtr. This is the
modification that has been interdicted by the Apex Court.
However, the situation in the case on hand is different. A total of
31 claims amounting to Rs.16,04,07,582/- was made by the
appellant/claimant before the Arbitrator. An award of
Rs.3,93,24,065/- with interest was granted by the Arbitrator. The
court below in the proceeding under Section 34 initiated by the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-15-
respondent/UoI, confirmed the award on some claims and set aside
the award on certain other claims. The claims are independent and
separate. This is not a case in which the award of compensation
under any particular head was revised/changed or altered, but a
case in which the portion of the award relating to certain
independent claims were set aside.
13. In this context, we refer to the decision of the Hon'ble
Supreme Court reported in 2011 KHC (Online) 4418)
(M/s.J.G.Engineers Pvt. Ltd. vs. UoI). The claimant in the said
case was awarded the work of extension of terminal building at the
Guwahati Airport. Disputes arose between the parties and the
matter was referred for arbitration. The claimant filed a statement
of claims before the Arbitrator. Claims 1 to 11 were for
Rs.2,38,86,198.31/- which was subsequently reduced to
Rs.2,06,70,495/-. Claim 12 was for interest @18% p.a. and claim
13 was towards cost of arbitration. The Arbitrator awarded a sum
of Rs.1,04,58,298/- with interest and cost. The proceedings under
2021/KER/52252
Arbitration Appeal No.38 of 2020
-16-
Section 34 initiated by the UoI was dismissed. This order was
reversed by the Guwahati High Court in the appeal filed by the UoI
and the award was fully set aside. The Apex Court did not agree
with the judgment of the High Court setting aside the entire award.
In paragraph 18 it was held thus -
“18. The arbitrator had considered and dealt with claims (1),
(2, 4 and 5), (6), (7 and 8), (9) and (11) separately and
distinctly. The High Court found that the award in regard to
items 1, 3, 5 and 11 were liable to be set aside. The High Court
did not find any error in regard to the awards on claims 2, 4, 6,
7, 8 and 9, but nevertheless chose to set aside the award in
regard to these six items, only on the ground that in the event of
counter claims 1 to 4 were to be allowed by the arbitrator on
reconsideration, the respondents would have been entitled to
adjust the amounts awarded in regard to claims 2, 4, 6, 7, 8
and 9 towards the amounts that may be awarded in respect of
counter claims 1 to 4; and that as the award on counter claims
1 to 4 was set aside by it and remanded for fresh decision, the
award in regard to claim Nos. 2, 4, 6, 7, 8 and 9 were also
liable to be set aside. It is now well settled that if an award
deals with and decides several claims separately and distinctly,
even if the court finds that the award in regard to some items is
bad, the court will segregate the award on items which did not
suffer from any infirmity and uphold the award to that extent.
As the awards on items 2, 4, 6, 7, 8 and 9 were upheld by the
civil court and as the High Court in appeal did not find any
infirmity in regard to the award on those claims, the judgment
of the High Court setting aside the award in regard to claims
2,4,6,7,8 and 9 of the appellant, cannot be sustained. The
judgment to that extent is liable to be set aside and the award
has to be upheld in regard to claims 2, 4, 6, 7, 8 and 9.”
(Emphasis supplied)
2021/KER/52252
Arbitration Appeal No.38 of 2020
-17-
14.As in the aforesaid decision, in the case on hand also,
the award has dealt with and decided several claims separately and
distinctly. Therefore, if the court finds the award with regard to
some claims to be bad, the court can segregate the award on items
which did not suffer from any infirmity and uphold the award to
that extent. If such an interpretation is not given, it would result in
gross injustice and absurd results because the court would have to
set aside that portion of the award also which suffers from no
infirmity. This certainly cannot be what was contemplated by the
Legislature. No reference has been made to J.G. Engineers Pvt.
Ltd. (supra) in Hakeem's case nor has it been distinguished or
overruled. The decision in J.G. Engineers Pvt. Ltd. is apparently
not under Article 142 of the Constitution also. That being the
position, we find that the doctrine of severability can be applied to
proceedings under Section 34 also because as held in R.S. Jiwani
(supra), if a person can challenge an award in part, certainly the
court can also set aside an award in part. That being the position,
2021/KER/52252
Arbitration Appeal No.38 of 2020
-18-
we negative the argument advanced on behalf of the appellant that
the impugned order is liable to be set aside on the said preliminary
ground alone.
15.Having negatived the challenge on the preliminary
point, we proceed to consider whether the court below was
justified in setting aside the award in respect of some of the claims.
We will refer to the claims in the order in which arguments were
advanced challenging the findings of the court below. Reference
was first made to claim no.19. The said claim is relating to
‘additional payment for excavation of hard rock by chiseling’.
Under this head/claim, an amount of Rs.34,38,452.87/- was
claimed. The award of Rs.34,38,453/- granted by the Arbitrator has
been set aside by the court below. It was pointed out on behalf of
the appellant that the fact that excavation of hard rock was done, is
not in dispute. The dispute is only with regard to the mode of
excavation, that is, was it done by way of blasting or was it by
chiseling. The contract of agreement does not specify the method
2021/KER/52252
Arbitration Appeal No.38 of 2020
-19-
to be used for excavation. However, it has been stipulated in the
contract that if the appellant/claimant resorts to blasting, he must
get necessary permission/sanction from the authorities concerned.
Further, if excavation is done by chiseling, the claimant is entitled
to a higher rate and if it is done by blasting, he would be entitled
only to a lower rate. The Arbitrator after analyzing the evidence
adduced before him found that the excavation of hard rock had
been done by chiseling and hence awarded the aforesaid amount.
According to the appellant/claimant, the finding of the court below
that the Arbitrator never considered this aspect is wrong. On the
other hand, a detailed discussion regarding this aspect is very much
available in the award. The court went wrong in interfering with
the factual findings of the Arbitrator. Reference was made to
Madnani Construction Corporation Pvt. Ltd. vs. UoI
[(2010)1 SCC 549] to substantiate the argument on this aspect.
16.The respondent/UoI, disputed the claim of excavation
by chiseling and contended that it was the responsibility of the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-20-
claimant to have obtained the necessary permit/sanction from the
District Collector. The claimant had commenced the work on
05.05.2003, but applied for permission only on 03.09.2004, i.e.,
after a lapse of sixteen months. Excavation of hard rock was done
by blasting only. The fact that blasting alone was done, is evident
from the works' diary maintained at the work site which also
contains the signature of the appellant/claimant. Further, this
amount was never claimed by the claimant during the currency of
the work through Running Account Receipts (RARs). Further, the
appellant/claimant had during the currency of the contract,
requested for extension of time due to delay in getting permission
from the authorities concerned for blasting of rock. The Accepting
Officer by Deviation Order (DO), granted extension with no
financial effect. After that, several RARs were paid to the claimant.
The claimant then never claimed any amount for chiseling.
Therefore, this would show that the claim now made under this
head is only an after-thought. The claimant countered the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-21-
contentions of the respondent/UoI by filing a rejoinder, in which he
reiterated his claim and contended that he could not obtain
permission for blasting. The work diary, namely, Ext.GP-46 relied
on by the respondent is a fabricated document created
subsequently to suit the case of the respondent.
17.The Arbitrator in paragraph 74.9 of the award
considered the rival contentions of the parties and found that
excavation had been done by way of chiseling. The Arbitrator
noticed that the Station Commander had imposed certain
restrictions relating to the execution of the contract. The Arbitrator
also took note of the differences seen in the handwriting, ink and
pen in the entries seen in Ext.GP-46 works diary produced and
relied on by the respondent and so concluded that the argument
advanced by the claimant against the works diary is justified. It
was also found that there was no dispute regarding the calculated
quantities, but the only objection was that the amounts were never
claimed in any of the RARs. The Arbitrator found that when the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-22-
work had admittedly been done by the claimant, the same cannot
be expected to have been done gratuitously ; that the claimant
expected a DO to be issued by the respondent/UoI, but the latter
took considerable time in issuing various DOs and that some had
been issued even after the completion of the work and hence in
such circumstances, the argument of the respondent that the
claimant ought to have claimed the amounts under this head in the
RARs is not justifiable and so accepted the claim and awarded
Rs.34,38,453/-.
18.The court below deals with this claim in paragraph 29
of the impugned order which reads thus -
“29. Claim No.19 relates to additional payments for excavation by
chiseling of hard rocks. As per CA claim 26.5 in Sl. Page 223
controlled blasting contractually agreed with written permission of
GE and District Authorities. As per G.P.46 work diary it also noted
the blasting work done in field and signed by petitioner and
respondent. Without considering the admission and evidence the
arbitrator concluded that the respondent carried out the work by
chiseling and granted the amount as claimed by the respondent
which is patently illegal, unfair and unreasonable that it shocks the
conscience of the court and liable to be interfered and do so.”
19.The finding that admission made by the claimant had
2021/KER/52252
Arbitration Appeal No.38 of 2020
-23-
not been taken note of by the Arbitrator, is factually incorrect. The
claimant never admitted the entries in the works diary, on the other
hand he disputed the authenticity/genuineness of Ext.GP-46 works
diary, which contention was found to be probable from the facts,
circumstances and evidence on record by the Arbitrator. This
factual finding of the Arbitrator ought not to have been interfered
with by the court below. It is settled law that the Arbitrator is the
master of facts. Finding on facts by the Arbitrator, cannot be easily
interfered with unless and until they are found to be perverse or
patently illegal. Here, in the instant case, the Arbitrator has given
clear and cogent reasons which can in no way be termed as
perverse, unfair or one shocking the conscience of the court as held
by the court below. The court below has committed a patent
mistake by interfering with the award of the Arbitrator under claim
no.19 and hence, we set aside the finding of the court below under
claim no.19.
20.Now, to claim no.5 which is described as 'provision of
2021/KER/52252
Arbitration Appeal No.38 of 2020
-24-
links 1, 2 and 3 around cafeteria', an amount of Rs.13,06,196.51/-
claimed was allowed by the Arbitrator. The same has been set
aside. It is submitted on behalf of the appellant that the dispute
here was, whether this work is covered by the Contract Agreement
(CA) or whether it is extra works. If it is included in the CA, the
claimant is not entitled to the amount claimed, but on the other
hand, if it is extra works, he is entitled to the said amount.
According to the claimant, the work done under claim no.5 is extra
works and hence he is entitled to the amount claimed. Claim no.5
is dealt with by the Arbitrator in paragraph 16 of the award. The
contract entered into between the parties is admittedly a lump sum
contract. The claimant before the Arbitrator contended that links 1
to 3 constructed as instructed by the Garrison Engineer (GE), was
not part of lump sum contract for the construction of the cafeteria
building. These works were completed as directed by the GE as
early as in September/October, 2008. However, when the claimant
realised that no payments were made for the said links in the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-25-
RARs, he brought it to the notice of the GE by way of Ext.C5/S-2
letter. He reminded the authority concerned of the matter by
various subsequent correspondences also. However, no action was
taken by the respondent/UoI. Hence, by way of Ext.C5/S-5 letter
dated 30.1.2009, he informed the GE of his intention to claim these
works as extra works with interest through arbitration. The
respondent/UoI contended that the claim is not admissible as the
work forms part of the lump sum contract and that they are not
extra works. The Arbitrator, after hearing both sides and examining
the documentary evidence adduced by both sides, concluded that
the links were not included in the CA or in the drawings and
therefore in the absence of details in the CA, it cannot be
considered that the links had been included in the lump sum and
not payable unless it had been so specifically mentioned in the
contract. The Arbitrator found that as the drawings did not indicate
the two ends of the links and also did not indicate which link forms
part of which building, it cannot be held to be part of the CA and
2021/KER/52252
Arbitration Appeal No.38 of 2020
-26-
hence found the claim to be sustainable and awarded the aforesaid
sum. The court below in paragraph 24 of the impugned order deals
with claim no.5 which reads thus -
“24. Claim No.5 relating to construction of links 1, 2 and 3 around
that cafeteria. The respondent as well as well as arbitrator clearly
admitted that there is no stipulation in the contract to do the said
work, but according to arbitrator there is 'no end' in the drawing and
therefore the respondent is entitled to get the amount since they
conducted the work, link 1, 2 and 3 around that cafeteria. It is
evident from page 23(R) of CA that L1,2 & 3 are excluded. There is
no compulsion to the respondent to do the work if he is in a
dilemma or if the contract not specified with regard to the work. He
could have avoid the same then and there and proceed further after
getting clear a written consent from the petitioner. Here the
respondent allegedly conducted the work according to their own
interpretation, unilaterally and claiming the amount. The same is
against the contract and the Arbitrator cannot go beyond the contract
and found that the award regarding claim No.5 is contra to the
contract and liable to be interfered. Therefore as per the contract the
petitioner is not liable to pay the said amount and the findings of the
arbitrator is in conflict with the contract and set aside awarding of
claim No.5.”
21.The learned counsel for the appellant submitted that the
court below has taken up a stand which neither party had and also
that a pure finding of fact which cannot and ought not to have
been interfered with, has been interfered with, which finding of the
court below cannot be sustained. Reference was made to
M/s.Enkay Construction Company vs. Delhi Development
2021/KER/52252
Arbitration Appeal No.38 of 2020
-27-
Authority [ILR (2006)(II) Delhi 249] in which it was held that
based on Section 70 of the Contract Act, which embodies the
equitable principle of restitution and prevention of unjust
enrichment, any extra works done, which work is not expressly or
impliedly included in the original contract, the beneficiary is
obliged to pay for the benefit he receives and that a Government is
also not outside the purview of Section 70 of the Contract Act.
22.As rightly pointed out by the learned counsel for the
appellant, the finding of the court below is apparently incorrect.
The respondent/UoI had no case that the work had been done by
the claimant, unilaterally and according to his “own
interpretation”. On the other hand, their specific case is that the
works done are not “extra works” but part of the CA and hence the
claimant is not entitled to any further sum. They do not dispute the
claim that the works had been carried out as instructed by the GE.
The finding of the Arbitrator regarding this claim was also purely a
factual one, based on the materials placed before him and which
2021/KER/52252
Arbitration Appeal No.38 of 2020
-28-
finding is supported by cogent reasons. No interference was called
for and there is no justification for the interference also. Hence, the
finding of the court below on claim no.5 is liable to be set aside.
23.Claim no.8 is relating to “extension of link (1) between
substation and flotilla office, PT shed 2 to link 10”. An amount of
Rs.2,81,516.70/- claimed was allowed by the Arbitrator. This was
set aside by the court below. According to the learned counsel, the
dispute involved here also, was whether this work was part of the
CA or was it extra works. Paragraph 26 of the impugned order by
which award relating to claim no.8 was set aside, is nothing but a
verbatim reproduction of the contentions of the respondent/UoI in
the claim petition, which is not supported by any reason(s)
whatsoever and hence is also liable to be set aside.
24.Paragraph 63 of the award deals with claim no.8. The
claimant contended that this work is not part of the CA, but it was
extra work and hence he has to be reimbursed for the same. The
respondent/UoI contended that the claim was inadmissible as they
2021/KER/52252
Arbitration Appeal No.38 of 2020
-29-
form part of the CA. Paragraph 63.6 of the award deals with the
finding of the Arbitrator regarding this claim. The Arbitrator after
hearing both sides and considering the documentary evidence
produced by either side, found that the CA and drawings were not
clear on this aspect. The contract did not mention that the links are
included in the lump sum and that the respondent/UoI had failed to
establish their contention that the work had been executed by
another contractor and hence found the claim to be justifiable and
so awarded Rs.2,81,516/- to the claimant.
25.Paragraph 26 of the impugned order deals with claim
no.8 which reads thus -
“26. Claim No.8: relating to extension of link 1 between Sub
station and Flotilla office and PT shed 2 to link 10. It forming
part of lump sum as per the drawing number 3TZH-Links
-WDAP IS3 (serial No.143.3.TZH links space WADP 2 S3
(serial No.144 and 3TZH – links – WDAP. Space 3 SP(serial
No.145). As per schedule 'A' note No.6.1.2 in serial page No.18
(R)the all drawing shall be deemed to be included in respective
cost of building unless specifically excluded. Hence it is clear
and unambiguous what are included and what are excluded in
lump sum. As per the contractual conditions link No.10 is part
and parcel of quoted lump sum and the arbitrator ignored these
two vital contract conditions and arbitrarily awarded the full
amount as claimed by the respondent. According to the
arbitrator in the absence of specific stipulation, supported the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-30-
view of respondent and allowed the claim. The said conclusion
is in conflict with the contractual terms of 6.1.2 and liable to be
interfered and do so.”
26.It is apparent that no reasons have been given for setting
aside the specific findings of the Arbitrator. The court below does
not say any or for what reasons the Arbitrator was wrong in
concluding so. Hence, the factual findings supported by reasons,
set aside for no apparent reasons, is liable to be set aside.
27.Claim no.16 is relating to 'certain additional works
carried out in link 5 at the canopy'. An amount of Rs.39,783.12/-
claimed was granted by the Arbitrator. According to the claimant,
when the construction of link 5, roof and canopy was at the final
stage, the GE vide Ext.C16/S-1 letter dated 24.8.2005 demanded
extension of the link inside the canopy-roof reinforcement. The
claimant by letter dated 25.8.2005 brought it to the notice of the
GE that this was a delayed request on their part. However, he
carried out the work as directed by the GE and requested for a DO.
He also informed the GE that such changes entail some additional
2021/KER/52252
Arbitration Appeal No.38 of 2020
-31-
works beyond the terms of the contract and hence he needed to be
reimbursed and a proper DO issued. However, no action was taken
by the GE for 19 months. Hence, as per Ext.C16/S-5 letter dated
28.11.2008, he sent a draft DO for the additional works done and
requested the GE to issue a DO. Again, no action was taken by the
GE. According to the claimant, the extension of link 5 was ordered
on 24.8.2005 by the introduction of two revised drawings. These
are not missing details and as changes have been brought in as
directed by the GE, he is entitled to be reimbursed. On the other
hand, the respondent/UoI contended that the changes made in the
drawings relating to this work were changes falling under missing
details and so the claim is liable to be rejected.
28.The Arbitrator in paragraph 71.7 of the award has given
his findings on this claim. It was found that the CA has failed to
demarcate the scope of work under lump sum and that the
respondent had added supplemental details at a later stage. It was
also found that the respondent through their consultant continued
2021/KER/52252
Arbitration Appeal No.38 of 2020
-32-
to give details after the commencement of the work and then
claimed them as missing details. It was found that such details
could not be determined or foreseen at the tender stage itself and
therefore in the interest of justice and equity, the claim needs to be
upheld.
29.Claim no.16 dealt with in paragraph 28 of the impugned
order reads thus -
“28. Claim No.16 relates to additional works carried out in link 5 at the canopy
and the arbitrator allowed the claim on the conclusion that the contract failed to
demarcate scope of work under lump sum. There is clear stipulation in
condition 6 B in GCC IAWF 2249 that lump sum contract based on pre priced
schedule 'A' and the rates as inserted in MES. Therefore contract terms are
clear and the arbitrator cannot take a decision in conflict with the contract.
Hence the conclusion of arbitrator in claim No.16 is liable to be interfered and
do so.”
30.It is pointed out that here-again, the finding of the court
below is sans any reason; that there is no clause as 6B in the GCC
as mentioned in the impugned order and this finding of the court
below is also a reproduction of the allegations of the respondent
herein in the claim petition. To substantiate the argument that the
court below is bound to give reasons, the learned counsel relied on
a decision of the Delhi High Court namely, Jai Singh vs. DDA
2021/KER/52252
Arbitration Appeal No.38 of 2020
-33-
(MANU/DE/1254/2008), in which it has been held that merely
saying that claim is not in terms of the agreement or that the claim
has not been established, is not sufficient and they do not constitute
reasons for the conclusion. Therefore, in such circumstances the
court would be compelled to peruse the records to find out whether
the Arbitrator's conclusions are in accordance with law or not.
However, that is not the scope of enquiry while entertaining a
challenge to arbitration awards.
31.As pointed out by the appellant, here again the court
below does not say in what way the finding of the Arbitrator is
against the contractual provision. The court has not addressed the
rival claims of the parties as to whether the work done is extra
works/new elements or whether it is missing details of the existing
details/elements. We went through the General Conditions of
Contracts I.A.F.W.-2249 (GCC), but were not able to locate
condition 6B as referred to in the impugned order. We find only
conditions 6A, 6(A)(A) with sub clauses (a) to (f), 6(A)(B), 6(A)
2021/KER/52252
Arbitration Appeal No.38 of 2020
-34-
(C), 6(A)(D) and 6(A)(E). Probably it is condition 6(A)(B) that has
been referred to by the court below. Even if that be so, the court
below has not stated the reasons for concluding so. On the other
hand, the Arbitrator has given reasons for his conclusion and a
finding based on facts ought not to have been interfered with. As
the court below went wrong, the finding relating to claim no.16 is
also liable to be set aside.
32.Claim no.7 is relating to 'provision of local granite stone
cladding in lieu of Sadarhally stone cladding'. An amount of
Rs.49,68,150.61/- claimed was allowed by the Arbitrator. This
again has been set aside by the court below. According to the
appellant/claimant, as per CA it was 50 mm. Sadarhally stone
cladding that was to be provided on the walls of the various
building to be constructed. The respondent/UoI after the
commencement of the work wanted a change of cladding from
Sadarhally stone to 150 mm. thick local granite stone. This was a
deviation to item no.60 of part IX of schedule A. Though rates
2021/KER/52252
Arbitration Appeal No.38 of 2020
-35-
were to be calculated as per condition 62(A)(a) of the GCC, the
respondent prepared a star rate/revised rate for only Sadarhally
stone 50 mm. thick, which according to the claimant is contrary to
the contractual condition contained in 62(A)(a) of the GCC. The
respondent contended that pricing of any deviation to the CA is
governed by condition 62 of the GCC and as per 62(B)(a),
deviation is to be priced at applicable rate in the relevant part of
schedule (A) in which the deviation is involved. Therefore, the
question is whether the rate of this item which is pre-priced in
schedule (A) part IX under item 60 can be made applicable to
schedule A part I in pricing deviation. Condition 62(B)(a) of the
GCC says that the rate to be applied in such cases is the rate
mentioned in the relevant portion of the schedule in which the
deviation is involved. Here the deviation made is in schedule (A)
part I, whereas the pre-priced rate inserted by the respondent is in
schedule (A) part XI. Therefore, the respondent contended that the
rates applicable to schedule (A) part XI cannot be made applicable
2021/KER/52252
Arbitration Appeal No.38 of 2020
-36-
to the works or deviations made in the other schedules, which in
this case is schedule (A) part I. It was pointed out on behalf of the
appellant that the fact that the deviation sought by the
respondent/UOI for cladding with local granite stone with 150 mm.
thickness, has been done by the claimant is not in dispute. The only
dispute is whether the rates are to be given as provided in condition
62(A)(a) or 62(B)(a) of the GCC.
33.The finding of the Arbitrator on this claim is available at
paragraph 62.11 of the award. The Arbitrator after hearing the
parties and examining the records, accepted the case of the
claimant that, it is the rate as provided under condition 62(A)(a) of
the GCC that is to be awarded and proceeded to do so. The finding
of the court below on this claim is found at paragraph 25 which
reads thus -
“25. Claim No.7 relates to use of local granite stone cladding in lieu of
Sadarahally stone cladding. The said change was effected as per Deviation
Order No.65. It is clear that the deviation order was signed and admitted by
respondent, so the applicable rate in D.O.No.65 applicable to both and
condition 62 of GCC IAFW 2249 also covered this point. Therefore the
granting of the said claim by the arbitrator is in conflict with the terms of the
respective contract which is liable to be interfered and do so.”
2021/KER/52252
Arbitration Appeal No.38 of 2020
-37-
34.According to the appellant, the court below has taken
up a case which neither side has; that the finding is also a
reproduction of the contentions of the respondent relating to claim
no.7 in their application under Section 34; that the finding is
without actually understanding the issue involved and without
expressing any opinion on the actual issue involved and that no
reason(s) is discernible from the conclusion of the court below
which prompted it to set aside the award. This argument advanced
is also justified as it appears that the court below has not
comprehended the actual issue involved between the parties
relating to this claim. As noticed earlier, the actual dispute is
whether the rates provided under condition 62(A)(a) is applicable
or whether it is the rates provided under condition 62(B)(a) that is
applicable. This has not been addressed by the court below. On the
other hand, this point has been squarely dealt with by the
Arbitrator. In setting aside the award under this claim, not only has
the court not dealt with the actual dispute involved but has also set
2021/KER/52252
Arbitration Appeal No.38 of 2020
-38-
aside the award on the said claim on totally irrelevant grounds,
which both sides did not canvass. Hence, the finding of the court
below on claim no.7 is also not sustainable.
35.Now, coming to claim no.1 which is described as
‘additional cost of anchor fasteners towards difference in cost of
supply of M/s. CANCO make anchor fasteners in lieu of
M/s.HILTI’. An amount of Rs.4,03,550/- claimed and awarded by
the Arbitrator has been set aside by the court below. According to
the claimant, the CA provides for fixing of jalli with Rawal plugs
or fasteners. But when the works started, the GE insisted on using
HILTI heavy duty fasteners in the place of Rawal plugs. On
enquiry with M/s.HILTI the claimant was told that HILTI anchor
bolts are no longer being manufactured and that it would take
about 6 to 7 weeks for the manufacturer to make an alternate
model. Therefore, after proper enquiries and as CANCO make
stainless steel anchor bolts as fasteners are equivalent to HILTI, the
same was submitted for the approval of the GE. The GE
2021/KER/52252
Arbitration Appeal No.38 of 2020
-39-
approved the same also. CANCO anchors are in no way inferior to
HILTI and they also satisfied the GE's technical requirements. But
the rates were revised by the GE for the CANCO fasteners used
and a lower rate awarded. As per the amendment drawing, it was
provided that anchor fasteners of HILTI or its equivalent shall be
used for fixing of stone jallis and therefore the respondent could
not have revised the rates and granted a lower rate against the
terms of the agreement. The respondent/UoI contended that
initially the claimant had submitted a sample anchor bolt. The
same was not approved as it was not as per the contract provisions.
Therefore, he was asked to submit a sample as per the CA.
Thereafter, without getting the approval of the GE, the claimant
started using an anchor, to which the respondent objected. The
claimant then informed that HILTI anchor fasteners have become
obsolete and hence he suggested CANCO fasteners. As per
condition 7 of the GCC, any change from the original contract
specifications is a deviation and therefore when approval of
2021/KER/52252
Arbitration Appeal No.38 of 2020
-40-
CANCO fasteners was given by the GE, it was made clear that it
will be subject to the contract conditions. It was also contended
that though CANCO bolts are inferior to HILTI bolts, they serve
the purpose of holding the cladding in place and hence it was
approved subject to the contract conditions. The revised rate for
deviations is based on quotations obtained and hence it was
contended that the claimant is not entitled to the amount claimed
by him.
36.The Arbitrator after hearing both sides, examining the
records and after visiting the site, proceeded to give his findings
which are at paragraph 56.5 of the award. The Arbitrator also
examined the sample of fastener submitted by the claimant during
the hearing. The Arbitrator found that no technical appraisal had
been provided by the Consultant of the respondent and that there
were misrepresentations and incomplete details in the contract. The
contract, according to the Arbitrator, should have been precise and
based on availability of the product in the market. Further, the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-41-
respondent also failed to technically differentiate HILTI made
fasteners from CANCO in order to justify their revision of rates by
granting lower rates for CANCO. Therefore, the Arbitrator
concluded that CANCO cannot be said to be not equivalent to
HILTI and awarded the amount claimed by the claimant.
37.The court below set aside the award under claim no.1
by holding thus –
“20. In P.R.Shah, Shanu and Stock Brocker (P) Ltd. v. M/s.B.H.H. Securities (P)
Ltd. reported in AIR 2012 SC 1866 the apex court held that An arbitral tribunal
cannot of course make use of their personal knowledge of the facts of the
dispute, which is not a part of the record, to decide the dispute. There is no
details of his visit or notice to the petitioner or entered it into any record by the
Arbitrator herein. Therefore the findings based on subjective satisfaction of
facts or personal knowledge shall not be form part of conclusion of the award.
Of course there is price difference in HILTI and CANCO product and that
should be settled as per the rates of MES schedule stipulated under conditions
No.62 of GCC-IAWF 2249. In condition 62 it clearly provides under clause (G)
that an alteration of work or additions have been covered by the contractor the
rates shall be decided by GE, if it is not satisfied refer the matter to CWE within
7 days of receipt of decision of GE decision of CWE shall be final and binding.
It further provides if additional work done by the contractor, the Engineer-in-
charge shall appraise the value there of and if any dispute then the decision of
GE thereon shall be final and binding. Therefore the claim is limited by
condition No.62 and the award of the amount, against the condition No.62 of
GCC IAFW 2249, rate of MES schedule, is against the terms of contract and
against fundamental policy of Indian Law, in conflict with the contract between
parties and against morality of justice and the said claim is liable to be set aside
u/s 34 of the Act and do so.”
It was pointed out on behalf of the claimant that the conclusion of
the court below that the Arbitrator had used his personal
2021/KER/52252
Arbitration Appeal No.38 of 2020
-42-
knowledge in arriving at his finding on the claim is a totally
incorrect statement and a ground which neither party had raised.
The respondent never raised any grievance/objection regarding the
site visit by the Arbitrator either at the time of his visit or during
the course of arguments before the court below. The Arbitrator is a
technical expert with experience in this field and hence the reason
why the parties chose him so that he can properly assess the factual
issues by relying on his expertise and experience. It is settled that it
is permissible for technically qualified Arbitrators to use their
expertise, technical or general knowledge about a trade to decide a
matter and that the same can never be termed as personal
knowledge of the Arbitrator. According to the claimant this has
been clarified by the Apex court in P.R. Shah Shares and Stock
Brokers Pvt. Ltd. v. B.H.H. Securities Pvt.Ltd. (2012) 1
SCC 594, the very same decision relied on by the court below.
Further a reading of the award would show that the conclusions are
not based on the site visit. Moreover, the site visit was not made for
2021/KER/52252
Arbitration Appeal No.38 of 2020
-43-
gathering evidence but for appreciating the evidence led by the
parties, which is perfectly in order, goes the argument.
38.We think that the arguments advanced are justified. The
Arbitrator has not based his finding on claim no.1 on the basis of
the information collected/gathered from his visit to the site. We
have already referred to the grounds on which the Arbitrator
arrived at his conclusion and it is apparent and obvious that the
same is not based on his visit to the site. Moreover, there is
nothing wrong in the Arbitrator making site visits. It is only that
his personal knowledge cannot be used to decide the dispute.
Here, no personal knowledge is seen used by the Arbitrator to
arrive at his conclusions regarding claim no.1. The Arbitrator
admittedly an expert in this field, based on the materials placed
before him found that CANCO fasteners could in no way be
termed inferior to HILTI fasteners, a decision apparently taken
after analyzing the technical aspects, which ought not to have been
disturbed by the court below as it has obviously no technical
2021/KER/52252
Arbitration Appeal No.38 of 2020
-44-
knowhow on the matter. Hence, the finding of the court below on
this count is also liable to be set aside.
39.Claim no.4 is described as 'cost for provision of
retaining walls (RCC) in front of PT shed'. An amount of
Rs.9,84,075.23/- claimed and allowed by the Arbitrator has been
set aside by the court below. As per the original drawing forming
part of the CA, the roof of some of the buildings to be constructed
were to be pyramidal shape over space frame. But later it was
changed to hipped roofs. As per the stipulation in the CA, the pipe
grid system connected with Nodes is space frame system and the
pipe grid system connected with welding is not space frame
system. According to the claimant, this was not part of the lump
sum contract. However, the respondent in spite of his objection
termed the same as part of the lump sum contract. The claimant did
not agree to the same and hence signed the DO under protest. The
respondent/UoI contended that the lump sum cost of building does
not include the cost of space frame items listed under schedule (A)
2021/KER/52252
Arbitration Appeal No.38 of 2020
-45-
part XII. These items related to space frame are to be measured and
paid under schedule (A) part XII. The pipe systems connected with
Nodes are space frame system and those connected with welding
are not part of the space frame system and hence the works done
by the claimant shall not be measured and paid under schedule (A)
part XII.
40.The Arbitrator after considering the oral and
documentary evidence and also inspecting the work site, gave his
finding which is at paragraph 59.17 of the award. The Arbitrator
found that the respondent had not mentioned or indicated clearly
the details of the roofing and the structure in the CA or in the
drawings. He found that the structure pertaining to the roof was
joined at the Nodes. He held the claim to be sustainable as he
found that there was no clear stipulation or mention of members or
that the roofing was intended to be included in the lump sum of the
building by the respondent. The contract also did not stipulate
which part of the roof had been included in the lump sum. Hence,
2021/KER/52252
Arbitration Appeal No.38 of 2020
-46-
he allowed the claim. This was also set aside by the court below
by finding thus -
“23. Claim No.4 relates to provision of hipped roof in lieu of Pyramidal roof
in its space frame building. As per note 18 serial Page No.20(R) of CA item
No.1 to 4 schedule A Part-I the lump sum cost of building do not include the
cost of 'space frame' items listed under schedule A. part of XII. According to
the arbitrator the petitioner never indicated the details of roofing in the
contract and the contract do not stipulate which part of the roof is including in
Lump sum and the arbitrator granted claim No.4 in toto. As per Note 18 (Para
20 of CA) all items shown on drawing shall be deemed to be included in
respective cost of building unless specifically excluded. In note 18(Page
20(R)) it clearly states that those items which are related to space frame only
are to be measured and paid under schedule 'A' part XII. The pipe grid system
connected with NODES are 'space frame system.' The pipe system connected
with welding etc are not part of 'space frame system' and under no
circumstances quantities of these items shall be measured and paid under
schedule A part XII. The arbitrator also gathered information at the time of his
visit to the site without maintaining any record. Therefore the conclusion that
absence of exact mention of members and roofing intended to be included in
lump sum of building is against the terms of contract and liable to be set aside
under section 34 of the Act and do so.”
41.According to the appellant, the findings of the
Arbitrator are based on technical details which ought not to have
been disturbed by the court below, who is not an expert in this area.
Here again, we find that the court below has erred in concluding
that the Arbitrator has based his finding on personal knowledge
which is obviously not the case. Hence this finding is also liable to
be set aside.
42.Now coming to claim no.17 which is described as
2021/KER/52252
Arbitration Appeal No.38 of 2020
-47-
'additional amount due for pricing of works at quoted rates than
rates fixed in amendment no.1 and for not considering certain
items of payment'. An amount of Rs.88,17,476/- claimed was
allowed by the Arbitrator. According to the respondent/UoI, this is
an excepted matter because as per condition 65 of the GCC, the
final bills shall be submitted within three months of physical
completion of the works to the satisfaction of the Engineer-in-
charge. It also says that no further claims shall be made by the
contractor after the submission of final bills and that the said
claims shall be deemed to have been waived and extinguished.
Amendment no.1 to the CA, according to the respondent, was
signed by both parties and therefore the contract stood amended.
No claim was made before submission of the final bill and
therefore all such claims must be deemed to have been
extinguished and waived. According to the claimant, the final bill
was signed under protest; that the respondent did not act in
accordance with condition 66 of GCC by failing to make payment
2021/KER/52252
Arbitration Appeal No.38 of 2020
-48-
of the admitted amounts of the final bill within the period of six
months stipulated in the condition and that there was undue
influence and coercion due to which he was forced to sign
amendment no.1. The fact that the claimant had objection to
amendment no.1 was also conveyed at the earliest to the
respondent.
43.The Arbitrator after a detailed discussion found the case
of undue influence and coercion in execution of amendment no.1
put forward by the claimant to be probable and true. About 14
instances have been cited by the Arbitrator, which would show or
indicate or justify the allegation of undue influence, and one
among them shows the failure of the respondent to release even
admitted amounts due to the claimant. It was also found that the
claimant was all along objecting to the amendment made and that
the amendment made was not on mutual consent. The Arbitrator
found there was no justification or reasonable contractual necessity
for the respondent to have amended the contract by way of
2021/KER/52252
Arbitration Appeal No.38 of 2020
-49-
amendment no.1. After perusal of the facts and circumstances in
the case, the Arbitrator was convinced that the respondent had
erred in mentioning the correct quantities of earth work involved in
schedule (A) part IX and when they noticed the error, they made all
efforts to cover it up by various methods. When they realised their
mistake, some part of the work had already been executed and
therefore the attempt of the respondent was to cover up the same
by way of amendment in the contract. The Arbitrator found that
there was absence of any communication between the parties so as
to conclude that the amendment had been made through mutual
consent. There was no offer or acceptance for concluding the new
contract in supplement to the main contract. The intention and act
on the part of the GE and the respondent in delaying and not
paying a huge amount of about Rs.1 Crore, according to the
Arbitrator, was certainly indicative of the undue influence
exercised by the respondent, a stronger party in the contract. The
Arbitrator noticed that the respondent was finding flimsy reasons
2021/KER/52252
Arbitration Appeal No.38 of 2020
-50-
for not honoring the bills on time. In paragraph 72.11, as stated
earlier, about 14 instances have been cited by the Arbitrator which
would substantiate the claim of undue influence and coercion on
the part of the respondent. In item no.2 in the table given in the
said paragraph, the Arbitrator has noticed that one of the RARs
was held up and returned for want of signature of the claimant,
though the representatives of the claimant were readily available at
the site. It was also found that there was no rhyme or reason for the
claimant to voluntarily agree to reduce the rates drastically from
the quoted rates through any amendment when the contract
provided for variation as deviation. The error/mistake committed
by the respondent to assess the correct and sufficient quantities in
the contract cannot be foisted upon the claimant by the respondent
being a stronger party in the contract. It was found that the
claimant was able to establish that though he had protested to the
amendment as soon as it was made, the same had been foisted on
him. On examination of the disputed amendment no.1, the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-51-
Arbitrator found that it was apparent that not even variations
admissible in the contract at contract rates were given its due
importance and that the respondent had framed an amendment with
varying quantities and applying rates on quantities unilaterally
decided by them. It was also found that if the claimant had not
agreed to the terms unilaterally put forward by the respondent,
there was also the possibility of the respondent getting huge
quantity of earth work done through other agencies at lesser rates.
The rate fixed in the amendment was not based on any realistic
analysis of the rates except that it was the rate quoted by the
second lowest tender, which rates the Arbitrator found did not have
any bearing or any connection with the contract. The amendment
thus was found to be made in the absence of free consent which
was one of the essential factors for entering into a contract. The
Arbitrator concluded that the variation though allowable in the
contract was ignored in the amendment; that there was no offer and
acceptance; that huge payments were delayed thus putting the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-52-
claimant under pressure and undue influence; the basis for arriving
at the rates for the works done as per the amendment was not in
any way justifiable; that the respondent had not taken any action to
revise the amendment when it was objected to by the claimant
except contending that the same was signed voluntarily by the
claimant and that there was no record to show that the claimant
was heard before the amendment was finalized indicating the
arbitrary and unreasonable procedure adopted by the respondent.
Hence, the Arbitrator concluded that these aspects clearly showed
arbitrariness and undue influence exercised by the respondent, the
stronger party in the contract. Hence, an amount Rs.88,17,476/-
was awarded to the claimant.
44.The court below set aside this finding of the Arbitrator.
The finding is at paragraphs 9 to 13 of the impugned order. We are
not quoting the entire portion as it is a comparatively long
discussion in the order. The sum and substance of the finding of
the court below is that there was no undue influence exercised by
2021/KER/52252
Arbitration Appeal No.38 of 2020
-53-
the respondent as the relationship was purely contractual and not
fiduciary in nature; that several amendments and deviations had
been affected, all of which are admitted by the claimant except
amendment no.1 and so the same shocks the conscience of the
court; the fact that the claimant put his signature in amendment
no.1 implies offer and acceptance; that the burden of proving
undue influence has not been discharged as per the provisions of
the Evidence Act ; that the claim of undue influence has been
accepted by the Arbitrator without any evidence; that the claimant
signed the amendment with the oblique motive of filing a claim
petition and that there was no pressure on the claimant in executing
the work as it was an agreement mutually agreed to between the
parties. According to the court below, the conclusion of the
Arbitrator that the delay caused by the respondent in honoring
huge admitted payments was indicative of the undue influence, is
against morality and justice because the claimant is entitled to get
his payments if any, with interest if there was any delay illegally
2021/KER/52252
Arbitration Appeal No.38 of 2020
-54-
caused by the respondent. The court below further held that there
was no pressure on the claimant in doing the work except the
contractual obligation which had been mutually agreed to.
Therefore, according to the court below the conclusion of the
Arbitrator that one amendment alone was executed under undue
influence is not in conformity with morality and justice and hence
it shocked the conscience of the court. The court below expressed
its concern and anguish in public money going into the hands of
undeserved persons. Hence the court below proceeded to conclude
that in the absence of claim no.17 in the final bill, the dispute is not
arbitrable as condition no.65 of the GCC has not been satisfied.
45.This finding again will have to go as the Arbitrator on
facts found that the claimant had raised this issue before the final
bill had been submitted and so the dispute is arbitrable and not an
excepted matter as contended by the respondent. He also found
that the claimant had to agree to the amendment due to undue
influence and coercion and has given a detailed description
2021/KER/52252
Arbitration Appeal No.38 of 2020
-55-
supported by cogent reasons for arriving at this conclusion. Now,
even if the opinion and conclusion of the Arbitrator is wrong or a
different opinion/view is possible, that alone is not a ground for the
court to interfere in its jurisdiction under Section 34 as it is not
sitting in appeal. Merely because the claimant had affixed his
signature to the amendment, would not bar him from raising the
plea of undue influence or coercion if he had raised it at the earliest
possible opportunity and is able to bring in factors or
circumstances establishing the same. The finding of the court
below relating to undue influence seems to have been made
without understanding the ground realities. If the RARs or part
bills are not cleared in time, it would certainly be putting pressure
on the claimant. These bills have to be honored in time so as to
enable the claimant to maintain his liquidity. Otherwise, he would
inevitably find it difficult to carry out the works as the expenditure
involved ran into crores of rupees. Further, Section 19(1) of the
Act says that the Arbitral Tribunal is not bound by the
2021/KER/52252
Arbitration Appeal No.38 of 2020
-56-
Code of Civil Procedure or the Indian Evidence Act. Therefore, the
court below clearly erred in holding that the claimant had failed to
establish undue influence or coercion as per the provisions of the
Evidence Act and hence the said finding is also liable to be set
aside.
46.Now, coming to claim no.18 which is described as
‘additional cost towards space frame under schedule A part XII’.
An amount of Rs.1,52,64,424.33/- claimed was awarded by the
Arbitrator. This has also been set aside by the court below.
According to the claimant, the design of the space frame was
altered on four occasions and the last alteration brought about was
from pyramidal roof to hipped roof. However, the Quality
Assurance Plan (QAP) for the space frame work was not approved
for quite some time. It was approved only on 13.10.2006 and the
sample of materials involved in the space frame work approved on
4.12.2008. The claimant anticipating difficulties in getting a DO
prepared, star rates/revised rates made and the DO finalized, opted
2021/KER/52252
Arbitration Appeal No.38 of 2020
-57-
a path of least resistance so that the RAR payments would not be
delayed, informed the Chief Engineer (CE) that if the condition of
cost of solid Nodes and hollow Nodes are kept at par, the same
would be acceptable to him. However, the claimant was not
agreeable to the rates fixed by the GE which had been fixed
without taking into account the condition put forward by him, i.e.,
he was ready to carry out the work provided the cost of solid grade
Nodes and hollow Nodes are kept at par. Therefore, he signed the
DO on protest and also informed the GE that he is reserving his
right to go in for an adjudication of the dispute. The respondent
contended that based on the consent of the claimant, Amendment
no.3 to CA had been issued. According to the respondent the unit
of measurement mentioned in the CA is kilograms and therefore
hollow Nodes is also liable to be measured in terms of its weight
and accordingly the same was so weighed and payment made. The
respondent also took up a contention that the dispute regarding this
matter is an excepted one and hence not arbitrable. This contention
2021/KER/52252
Arbitration Appeal No.38 of 2020
-58-
of the respondent was countered by the claimant by filing a
rejoinder in which he contended that the hollow Nodes and solid
Nodes are entirely different in their specifications. The claimant
had agreed to rate per piece i.e., the same cost for one piece of
hollow Nodes as well as solid Nodes. The manufacture of hollow
Nodes involves different materials and highly sophisticated
machining process and so the cost of manufacture of hollow Nodes
is much higher than solid Nodes. Hollow Nodes weigh much lesser
than the solid Nodes but the expenses involved in its manufacture
is high. That is the reason why he had agreed for the deviation
provided the same rate was given for both Nodes. The claimant
also pointed out that the contention of the respondent that the issue
is not arbitrable is incorrect as he had raised the issue much before
the submission of the final bill as contemplated under condition 65
of the GCC.
47.The Arbitrator after considering all the materials before
him, found that the dispute has come up because of lack of clear
2021/KER/52252
Arbitration Appeal No.38 of 2020
-59-
and sufficient clarity regarding Amendment no.3. The claimant had
clearly informed the GE of his condition relating to the rates of the
Nodes. However, this was not incorporated in the amendment. The
amendment ought to have contained a clear clause regarding the
basis on which the rates would be awarded, i.e., whether it would
be rate per piece / per Node or based on their weight in kilograms.
Without specifying the same, it is unjust for the respondent to
contend that rates would be given based on kilograms because
hollow Nodes would be much lighter than solid Nodes. The cost of
manufacture of hollow Nods is higher and so if rates are given on
the basis of their weight in kilograms and not per piece as agreed to
by the claimant, the same would result in great loss to the claimant.
It was also found that the dispute had been raised by the claimant
before the finalization of the final bill and hence the dispute is not
an excepted matter as contended by the respondent and so found
the dispute to be arbitrable and proceeded to award a sum of
Rs.1,52,64,424/-.
2021/KER/52252
Arbitration Appeal No.38 of 2020
-60-
48.The court below set aside the award under claim no.18,
the finding of which reads thus -
“14. Claim No.18 also challenged by the petitioner at the preliminary
stage since it covered as per amendment No.3, dated 30.12.2006. The
said amendment was admitted by the respondent and arbitrator but
according to the arbitrator it was incomplete since the rate not specified
therein. The said work is related to part – XII – space frame and claim of
additional towards space frame an amount of Rs.1,52,64,424.33/-. The
respondent has agreed to change materials of nodes and props at par with
the costs existing in CA. In the amendment it clearly stated as third
clause that, the above changes had taken place to suit they decide
parameters of the designee provided by specialists agencies as per C.A.,
as projected by the contractor and approved by the competent authority.
It concluded to facilitate the execution space from work by the specialist
firm engaged by the contractor (respondent). The amendments was based
on mutual agreement and the arbitrator overlook that aspect and granted
an amount for the entire roofs including Pipe grid based on that the
amendment was incomplete. The said act of the arbitrator is not in
accordance with the agreement of parties since the said matter concluded
in amendment No.3 and the same is not arbitrable and it ought to have
been included in the final bill as per condition 65of IAFW 2249.”
“15. The respondent has not even denied the execution of this
amendment No.3, through which change of design effected. But the
arbitrator has noted that after the amendment the respondent has signed it
under protest. There is no need of executing amendment or contract with
protest. If the respondent not agreeing with the amendment he could
have avoid it. As per the original contract the solid nodes included and as
per amendment it changed into hollow nodes and fixed rates based
Kilogram. The arbitrator granted the claim of respondent based on same
price or solid nodes since the difference of rate is not mentioned in
Amendment No.3. As per amendment No.3 third clause it clearly stated
that the amount should be as per with the approval of the Competent
Authority though the design supplied by the specialized agency through
the contractor. According to the arbitrator since the rate of hollow nodes
not mentioned in amendment No.3, the amendment is to be considered as
incomplete. As per condition No.62 Valuation of Deviation mentioned in
detail based on rate applicable in the MES schedule and it should be
adopted if there any difference in price. Without considering the
contractual rate, as mentioned in condition 62 of GCCIAFW 2249 the
arbitrator allowed the entire claim put forward by the respondent.
Ofcourse hollow nodes value is less than solid nodes always. Therefore
2021/KER/52252
Arbitration Appeal No.38 of 2020
-61-
granting of price equal to solid nodes is unreasonable that shocks the
conscience of court and patently illegal. In the amendment No.3 itself in
first and second clause it clearly mentioned that amended accordingly
without any extra cost to the department (petitioner). That itself shows
that it shall not cause any extra cost than the real cost and not higher than
fixed earlier. The granting of said claim No.18 is also against the terms
of the respective contract and patently illegal. The said claim ought to
have been incorporated in the final bill but not included and it waived or
terminated under condition No.65 of GCC IAFW 2249 and not
arbitrable. Therefore the said claim, claim No.18 is not arbitrable and
will not come under the purview of arbitration.”
49.It was argued on behalf of the appellant that the finding
of the court below is an unreasoned departure from the view of the
Arbitrator. Here again, the court has interfered in a matter in which
it has no expertise or knowhow, whereas the Arbitrator an expert in
this field is in a much better position to adjudicate the same. This
argument advanced on behalf of the appellant is also justified. The
court below is seen to have observed in its discussion - “…. Of
course, hollow nodes value is less than solid nodes always. …”
The basis on which this finding has been made is not known and is
unclear. Probably as pointed out on behalf of the appellant, a
commonsensical approach has been taken by the court below to
conclude so. Here is a case where the claimant has specifically
2021/KER/52252
Arbitration Appeal No.38 of 2020
-62-
contended that the cost of manufacture of hollow Nodes is more
compared to solid nodes. This has not been disputed by the
respondent and the said claim has not been rejected by the
Arbitrator also. This point is not seen addressed and the court
below without properly comprehending the situation seems to have
arrived at its conclusion based on a common man’s understanding
of the same, which appears to be apparently incorrect. The findings
of the Arbitrator supported by cogent reasons ought not to have
been interfered with by the court below. Further, it was after
examining the communications between the parties and other
materials, the Arbitrator had concluded that the dispute had been
raised by the claimant before the finalization of the final bill as
contemplated under condition 65 of the GCC. These materials have
also not been referred to and without referring to the same, the
court below concluded that the claim is not arbitrable. The findings
of the Arbitrator based on facts and supported by reasons is not
liable to be interfered with hence this finding of the court below is
2021/KER/52252
Arbitration Appeal No.38 of 2020
-63-
also liable to be set aside.
50.Finally, coming to claim no.31 which deals with
'arbitration cost'. An amount of Rs.3 Crores was claimed. The
Arbitrator awarded Rs.5 lakhs. The court below reduced it to
Rs.28,402/-. Paragraph 32 of the impugned order reads thus -
“32. Claim No.31 relating to cost of arbitration, awarded an amount of `5
lakhs out of claim of `30,00,000/-. The contention is that without any basis
it granted. Since the respondent preferred arbitration he has to bear the
expense and the amount of cost is tenable. As per award the arbitrator
awarded total amount of `3,93,24,065/- to the respondent and cost of
`5,00,000/- awarded by rejecting the claim of `30,00,000/- which comes
1.27% of total award amount. Arbitrator exercised his discretion and there
is no ground to interfere in it. Therefore the respondent is entitled to get
1.27% of the amount fixed by this court, `22,36,380/- (Total of claim
Nos.2,3,10, 11, 14, 15, 20 and 27) which comes `28,402/- and this claim
found accordingly.”
51.The finding of the Arbitrator regarding costs and the
rate has not been disturbed. The reduction came about only
because the aforesaid claims have been set aside. This finding will
also have to necessarily go in the light of our above made
conclusions.
52.Before concluding, we place on record our appreciation
for the assistance given by Adv.Anil Sebastian Pulickel, the learned
counsel for the appellant who was meticulous in his arguments and
2021/KER/52252
Arbitration Appeal No.38 of 2020
-64-
had painstakingly taken us through all the relevant portions of the
award as well as the corresponding portions in the impugned
order.
For the aforesaid reasons, the appellant succeeds. The
appeal is allowed and the award of the Arbitrator is restored.
All pending interlocutory applications, if any, shall
stand disposed of.
Sd/-
P.B.SURESH KUMAR , JUDGE
Sd/-
C.S.SUDHA, JUDGE
STK/ami
2021/KER/52252
Legal Notes
Add a Note....