APHC010549542023
IN THE HIGH COURT OF
ANDHRA PRADESH
AT AMARAVATI
WRIT APPEAL NO: 1060/2023
Bench
Sr.No:-___
[3446]
M/s.srinivasulu Reddy And Co, ...APPELLANT
Vs.
The State Of Andhra Pradesh and Others ...RESPONDENT(S)
**********
M.V.PRATAP KUMAR, Advocate representing vice AISHWARYA
NAGULA, Advocate(s) for Appellant(s)
GP FOR ROADS & BUILDINGS, Advocate(s) for Respondent(s)
CORAM : THE CHIEF JUSTICE DHIRAJ SINGH THAKUR
SRI JUSTICE R RAGHUNANDAN RAO
DATE : 04.04.2024
Per DHIRAJ SINGH THAKUR, CJ :
The present appeal under Clause 15 of the Letters Patent has
been preferred against the judgment and order dated 01.03.2023
passed in W.P.No.41906 of 2018 whereby the petition filed by the
petitioner has been dismissed.
2. It is pertinent to mention briefly the material facts in the light
of which the present controversy has arisen:
The petitioner was allotted the contract for construction of a
court complex at Kurnool on 05.05.2012 and an agreement came to
be executed between the petitioner and the Superintending
Engineer, R & B Circle, Kurnool, on 23.11.2012. According to
Clause 46 of the contract so entered between the parties, price
adjustment was envisaged for both increase and decrease in the
prices for the works completed within the original agreement
period. Clause 46.2 & 46.4 are relevant and are reproduced
hereunder:
“46.2 – Price adjustment shall be both for increase
and decrease in the prices for the works completed within
the original agreement period.
46.4 – The variation clause will be when the
variation in rates is more or less than 5% of the rate
provided in the technical sanctioned estimate based on
which bids are invited or all India wholesale price Index of
the respect item.”
3. The agreement among others also envisaged resolution of
disputes through arbitration in terms of Clause 23 of the said
contract only if the amount in dispute was less than Rs.50,000/-.
For facility of reference, Clause 23 of the said contract is
reproduced hereunder:
“23. Settlement of disputes:
……..
Settlement of Claims for Rs.50,000/- and below by
Arbitration:
All disputes or difference arising of or relating to
the Contract shall be referred to the adjudication as
follows:
a) Claims up to a value of Rs.10,000 /- -
Superintending Engineer, (R&B), Kadapa.
b) Claims above Rs.10,000/ - and up to
Rs.50,000/- - Engineer-in-Chief, (R&B), Admn
& N.H, Hyderabad
The arbitration shall be conducted in accordance
with the provisions of Indian Arbitration and
Conciliation Act, 1996, or any statutory modification
thereof.”
4. According to the stand taken by the petitioner, the
Government of Andhra Pradesh issued a G.O. Ms.No.23, dated
11.02.2014 with regard to the treatment of price adjustment in
contracts pertaining to Transport, Roads and Buildings. According
to which, the price variation over and above 5% was to be applied
whether there was an increase or decrease in the price. According
to the said G.O., recovery was to be made from the contract beyond
5%. In other words, if there was a variation in the rate to an extent
of 9%, the amount that would be payable to the contractor would be
4% i.e. 9% - 5% since the contractor would have factors into his
original bid, such an increase up to 5%. Similarly if the price is
decreased by 9%, the contractor would be permitted to retain 5%
and what would be deducted is 4%.
5. Subsequently, another G.O.Ms.No.67, dated 27.11.2015 was
issued reiterating that the price variation clause would apply to
both increase and decrease wherever the variation was more than
5%. It is stated that a supplemental agreement was executed on
27.06.2016, which in effect took away the benefit of price
adjustment in the event of decrease in the cost as was otherwise
envisaged under G.O.Ms.Nos.23 & 67. It is stated that the
supplemental agreement was executed by the petitioner on account
of “financial problems and due to the urgency in settling payments
to the workers and the suppliers”. Additionally, it is stated that the
supplemental agreement was executed by the petitioner, as it was
always under the impression that the benefit of price adjustment as
reflected in the G.O.’s would be implemented.
6. After the execution of the supplemental agreement, the
petitioner addressed two communications, one, dated 20.07.2016,
to the Superintending Engineer, R&B Circle, Kurnool, and the other
dated 17.08.2016 to the Engineer -in-Chief (R&B), Buildings,
Hyderabad (A.P.), seeking the benefit of price adjustment in the
case of decrease in prices. In response of the aforementioned
communications, the Superintending Engineer vide the letter,
dated 29.08.2016, addressed to the petitioner that the benefit of
price adjustment on decrease of prices could not be given to the
petitioner inasmuch as the petitioner had executed the
supplemental agreement without any protest. It was also stated in
the said communication that report had also been submitted in that
regard to the Chief Engineer and action would be taken thereupon.
The Chief Engineer finally vide the communication, dated
22.12.2016, directed the Superintending Engineer to follow the
guidelines issued by the Government from time to time in regard to
the price adjustment for building works. Much after the aforesaid
communication, for the first time, the petitioner addressed a
communication, dated 15.11.2017, to the Superintending Engineer
explaining the circumstances in which the supplemental agreement
came to be executed. For facility of reference, the relevant portion
of the letter is reproduced herein below:
“We wish to submit that in spite of GO’s and
instructions of the Engineer-in-Chief regarding the price
adjustment calculations methods for the above work,
this office had worked out in wrong method by which we
are incurred huge loss.
As we were held up with huge amounts in the final
bill, and due to repeated pressures from the workers and
material suppliers to clear their dues, there was no
alternative for us at the time to clear the dues of the
above except to sign on the supplemental agreement for
the price adjustment which was done wrong method.
Further, we submit that however, we protested for
the final bill in the measurement book by writing “under
protest for the price adjustment is not done properly”.
Hence, we request once again that the price
adjustment calculations may please be done as per GO’s
and the instructions of the Engineer-in-Chief (R&B), as
per the memo order No.DEE.1/AE -2/CTS/17722/2009,
dt:22-12-2015 by the Engineer-in-Chief (R&B).”
7. It is not however denied by either of the parties that the
amount reflected in the final bill, dated 16.08.2016, was received
under protest by the petitioner on 17.09.2016.
8. It is in the background of the aforementioned facts that
the petitioner approached the learned Single Judge seeking writ of
mandamus for enforcem ent of the price adjustment clause as
contained in the contract, dated 29.11.2012, as also G.O. Nos. 23 of
2014 and 67 of 2015 with a further direction in the nature of
mandamus to recalculate the price adjustment amount in
connection with the said contract and to pay the differential
amount to the petitioner. The learned single Judge, by virtue of the
judgment and order impugned, observed that the differential
amount claimed by the petitioner cannot be ordered by the writ
Court and that the petitioner had accepted the final bill issued by
the Executive Engineer on 17.09.2016 and further that the
petitioner had filed the writ petition in the year 2018 when the final
bill was prepared in the year 2016 and therefore, the writ petition
was filed ‘beyond the period of limitation for claiming the
differential amount’ and dismissed the petition in the light of the
fact that there was a dispute resolution clause which envisaged that
claims above Rs.50,000/- would be settled by a Civil Court of
competent jurisdiction by way of a civil suit and not by arbitration
and in that view of the matter, directed the petitioner to approach
the competent Civil Court for redressal of his grievances. For
facility of reference, what the learned single Judge held in the
impugned judgment and order is reproduced hereunder:
“7.On a perusal of the material placed on record, the relief
sought for by the petitioner is to direct the respondent Nos. 2 and
3 to recalculate the price adjustment amount in connection with
the said contract dated 23.11.2012 and to pay the differential
amount to the petitioner, which in fact cannot be ordered by this
Court and on the other hand, the petitioner has also accepted the
final bill issued by the Executive Engineer, Roads and Buildings
Division, Kurnool on 17.09.2016, and thereafter, he approached
this Court in the year 2018 which is admittedly beyond the
period of limitation for claiming the said differential amount.
8. In view of the same, the redressal of the grievance of the
petitioner is not here, but elsewhere. Therefore, this Court feels it
appropriate to direct the petitioner to approach the competent
Civil Court for payment of said differential amount.”
Hence, the present writ appeal.
9. Learned counsel for the appellant would submit that only
because there was a dispute resolution clause as per the agreement
envisaged settlement of disputes by way of a civil action before the
Civil Court would not take away the right of the petitioner to
approach the High Court seeking exercise of jurisdiction under
Article 226 of the Constitution of India inasmuch as the action of
the respondent - State was totally arbitrary and contrary to the
terms and conditions as envisaged in the agreement, dated
23.11.2012, as also was contrary to the G.O.Nos.23 and 67 of 2014.
10. Reliance was placed upon the Apex Court judgments in the
cases of ABL International Limited and another Vs. Export Credit
Guarantee Corporation of India Limited and others
1; R L Kalathia
and Company Vs. State of Gujarat
2; and M.P. Power Management
1
(2004) 3 SCC 553
2
(2011) 2 SCC 400
Company Limited Vs. M/s. Sky Power South Ea st Solar India
Private Limited and Others
3.
11. Learned counsel for the respondents on the other hand
questioned the very maintainability of the writ petition under
Article 226 of the Constitution of India in a contractual matter
which is non-statutory in character and did not possess any public
law character. Even otherwise, it was stated that assuming that the
contract in question was held to be one having such a statutory
character and public law character, yet there was no arbitrariness
in the action of the official respondents in not giving the benefit of
price adjustment on the decrease of the prices in view of the fact
that the petitioner had executed the supplemental agreement,
dated 27.06.2016. It was urged that the petitioner had executed
the supplemental agreement and accepted the price adjustment
calculation on 29.06.2016 on the following basis:
* When variation is more than +5%, say +6%, price
adjustment computed for 1% (6% - 5%)
* When variation is -6%, recovery computed for 6%,
which is advantageous to the Government.
* When variation is within +/-5%, no recovery was
made.
3
(2023) 2 SCC 703
12. It was also stated that the G.O.No.23, dated 11.02.2014, was
issued by the Panchayat Raj & Rural Development of the
Government of Andhra Pradesh, which related to the road works
related to the Panchayat Raj only and not for all the Engineering
Departments especially the current contract which related to the
Roads and Building Department and hence it is stated that the said
G.O. was not followed. It is however stated that the supplemental
agreement having been executed by the petitioner without any
murmur, the petitioner cannot be permitted to go back on the same
and claim that the price adjustment as envisaged under G.O.No.67
r/w Clause 46 of the agreement ought to have been granted to the
petitioner.
13. Heard learned counsel for the parties.
Maintainability of the writ petition under Article 226 of the
Constitution of India:
14. The issue of maintainability of a petition under Article 226 of
the Constitution of India in contractual matters where the State is a
party, has been a subject under consideration by Courts from time
to time. One of the earlier cases in this regard where the issue was
considered was in the case of Radhakrishna Agarwal v. State of
Bihar
4 wherein the Apex Court held as under:
“10. It is thus clear that the Erusian Equipment &
Chemicals Ltd.'s case (supra) involved discrimination at the very
threshold or at the time of entry into the field of consideration of
persons. with whom the Government could contract at all. At this
stage, no doubt, the State acts purely in its executive capacity
and is bound by the obligations which dealings of the State with
the individual citizens import into every transaction entered into
in exercise of its constitutional powers. But, after the State or its
agents have entered into the field of ordinary contract, the
relations are no longer governed by the constitutional provisions
but by the legally valid contract which determines rights and
obligations of the parties inter se. No question arises of violation
of Article 14 or of any other constitutional provision when the
State of its agents, purporting to act within this field, perform any
act. In this sphere, they can only claim rights conferred upon
them by contract and are bound by the terms of the contract only
unless some statute steps in and confers some special statutory
power or obligation on the State in the contractual field which is
apart from contract.”
15. However, in Kumari Shrilekha Vidyarthi v. State of UP
5, the
Apex Court expanded the scope of applicability of Article 14 beyond
the threshold stage of making a contract and held that even after
entering into the contract, Article 14 required the State to adhere
to the requirements of Article 14. It was held as under:
“20 ……………… Applicability of Article 14 to all executive
actions of the State being settled and for the same reason its
4
(1977) 3 SCC 457
5
(1991) 1 SCC 212
applicability at the threshold to the making of a contract in
exercise of the executive power being beyond dispute, can it be
said that the State can thereafter cast off its personality and
exercise unbridled power unfettered by the requirements of
Article 14 in the sphere of contractual matters and claim to be
governed therein only by private law principles applicable to
private individuals whose rights flow only from the terms of the
contract without anything more? We have no hesitation in saying
that the personality of the State, requiring regulation of its
conduct in all spheres by requirements of Article 14, does not
undergo such a radical change after the making of a contract
merely because some contractual rights accrue to the other party
in addition. It is not as if the requirements of Article 14 and
contractual obligations are alien concepts. which cannot co-exist.
21. The Preamble of the Constitution of India resolves to
secure to all its citizens Justice, social, economic and political;
and equality of status and opportunity. Every State action must
be aimed at achieving this goal. Part IV of the Constitution
contains ‘Directives Principles of State Policy which are
fundamental in the governance of the country and are aimed at
securing social and economic freedoms by appropriate State
action which is complementary to individual fundamental rights
guaranteed in Part III for protection against excesses of State
action to realise the vision in the Preamble. This being the
philosophy of the Constitution, can it be said that it contemplates
exclusion of Article 14-non-arbitrariness which is basic to rule of
law from State actions in contractual field when all actions of the
State are meant for public good and expected to be fair and just?
We have no doubt that the Constitution does not envisage or
permit unfairness or unreasonableness in State actions in any
sphere of its activity contrary to the professed ideals in the
Preamble. In our opinion, it would be alien to the Constitutional
Scheme to accept the argument of exclusion of Article 14 in
contractual matters. The scope and permissible grounds of
judicial review in such matters and the relief which may be
available are different matters but that does not justify the view
of its total exclusion. This is more so when the modern trend is
also to examine the unreasonableness of a term in such contracts
where the bargaining power is unequal so that these are not
negotiated contracts but standard form contracts between
unequals.
22. There is an obvious difference in the contracts between
private parties and contracts to which the State is a party,
Private parties are concerned only with their personal interest
whereas the State while exercising its powers and discharging its
functions, acts indubitably, as is expected of it, for public good
and in public interest. The impact of every State action is also on
public interest. This factor alone is sufficient to import at least
the minimal requirements of public law obligations and impress
with this character the contracts made by the State or it s
instrumentality. It is a different matter that the scope of judicial
review in respect of disputes failing within the domain of
contractual obligations may be more limited and in doubtful cases
the parties may be relegated to adjudication of their rights by
resort to remedies provided for adjudication of purely contractual
disputes. However, to the extent, challenge is made on the ground
of violation of Article 14 by alleging that the impugned act is
arbitrary, unfair or unreasonable, the fact that the dispute also
fails within the domain of contractual obligations would not
relieve the State of its obligation to comply with the basic
requirements of Article 14. To this extent, the obligation is of a
public character invariably in every case irrespective of there
being any other right or obligation in addition thereto. An
additional contractual obligation cannot divest the claimant of
the guarantee under Article 14 of non-arbitrariness at the hands
of the State in any of its actions.”
16. Subsequently, in Verigamto Naveen v. Govt. of A.P.
6, it was
held as under:
“21……. In cases where the decision making authority
exceeded its statutory power or committed breach of rules or
principles of natural justice in exercise of such power or its decision
is perverse or passed an irrational order, this Court has interceded
even after the contract was entered into between the parties and
the Government and its agencies. We may advert to three decisions
of this Court in Dwarkadas Marfatia & Sons v. Board of Trustees of
the Port of Bombay; Mahabir Auto Stores v. Indian Oil Corporation;
and Srilekha Vidyarthi v. State of U.P. Where the breach of contract
involves breach of statutory obligation when the order complained
of was made in exercise of statutory power by a statutory authority,
though cause of action arises out of or pertains to contract, brings
within the sphere of public law because the power exercised is apart
from contract.”
In Praga Tools Corporation v. Shri C.A. Imanual
7, it had been
held that if the challenged action did not have any public element,
writ of mandamus could not be issued as the action would
essentially be of a private character.
17. The issue was also considered at length in ABL International
Limited v. Export Credit Guarantee Corporation of India
Limited
8, and after noticing the various judgments on the point,
the following legal principles were crystallized regarding
maintainability of the writ petition:—
6
(2001) 8 SCC 344
7
1969 1 SCC 585 = 1969 AIR SC 1306
8
(2004) 3 SCC 553
a. In an appropriate case, a writ petition as against the
State or an instrumentality of the State arising out of the
contractual obligations is maintainable.
b. Merely because some disputed questions of fact
arise for consideration, same cannot be a ground to refuse to
entertain a writ petition in all cases, as a matter of rule.
c. A writ petition involving the consequential benefit
of monetary claims is also maintainable.
The Court further proceeded to hold that in entertaining the
writs under Article 226, the Court has the discretion to entertain
or not to entertain the petition and with reference to Whirlpool
Corporation v. Registrar of Trade Marks, Mumbai
9, it was held
that the Court has imposed upon itself certain restrictions in the
exercise of this power. It was further held that the prerogative
writ will not normally be exercised by the Court to the exclusion
of other available remedies unless such action of the State or its
instrumentality is arbitrary and unreasonable so as to violate the
constitutional mandate of Article 14 or for other valid and
legitimate reasons, for which the Court thinks it necessary to
exercise the writ jurisdiction.
9
(1998) 8 SCC 1
18. In “Joshi Technologies International Inc. v. Union of
India”
10 , the Apex Court on a detailed conspectus of the ratio of
the judgments rendered from the said Court from time to time
crystallized the legal position in regard to exercise of writ
jurisdiction in paragraph Nos. 68 & 69. It was held thus:—
“68. The position thus summarized in the aforesaid
principles has to be understood in the context of discussion
that preceded which we have pointed out above. As per this,
no doubt, there is no absolute bar to the maintainability of
the writ petition even in contractual matters or where there
are disputed questions of fact or even when monetary claim
is raised. At the same time, discretion lies with the High
Court which under certain circumstances, can refuse to
exercise. It also follows that under the foll owing
circumstances, ‘normally’, the Court would not exercise
such a discretion:
(a) the Court may not examine the issue unless the action has
some public law character attached to it.
(b) Whenever a particular mode of settlement of dispute is
provided in the contract, the High Court would refuse to
exercise its discretion under Article 226 of the Constitution
and relegate the party to the said made of settlement,
particularly when settlement of disputes is to be resorted to
through the means of arbitration.
(c) If there are very serious disputed questions of fact which are
of complex nature and require oral evidence for their
determination.
10
(2015) 7 SCC 728
(d) Money claims per se particularly arising out of contractual
obligations are normally not to be entertained except in
exceptional circumstances.
69. Further legal position which emerges from various
judgments of this Court dealing with different
situations/aspects relating to the contracts entered into by
the State/public Authority with private parties, can be
summarized as under:
(i) At the stage of entering into a contract, the State acts purely
in its executive capacity and is bound by the obligations of
fairness.
(ii) State in its executive capacity, even in the contractual field,
is under obligation to act fairly and cannot practice some
discriminations.
(iii) Even in cases where question is of choice or consideration of
competing claims before entering into the field of contract,
facts have to be investigated and found before the question
of a violation of Article 14 could arise. If those facts are
disputed and require assessment of evidence the
correctness of which can only be tested satisfactorily by
taking detailed evidence, Involving examination and cross-
examination of witnesses, the case could not be
conveniently or satisfactorily decided in proceedings under
Article 226 of the Constitution. In such cases court can
direct the aggrieved party to resort to alternate remedy of
civil suit etc.
(iv) Writ jurisdiction of High Court under Article 226 was not
intended to facilitate avoidance of obligation voluntarily
incurred.
(v) Writ petition was not maintainable to avoid contractual
obligation. Occurrence of commercial difficulty,
inconvenience or hardship in performance of the conditions
agreed to in the contract can provide no justification in not
complying with the terms of contract which the parties had
accepted with open eyes. It cannot ever be that a licensee
can work out the license if he finds it profitable to do so : and
he can challenge the conditions under which he agreed to
take the license, if he finds it commercially inexpedient to
conduct his business.
(vi) Ordinarily, where a breach of contract is complained of, the
party complaining of such breach may sue for specific
performance of the contract, if contract is capable of being
specifically performed. Otherwise, the party may sue for
damages.
(vii) Writ can be issued where there is executive action
unsupported by law or even in respect of a corporation there
is denial of equality before law or equal protection of law or
if can be shown that action of the public authorities was
without giving any hearing and violation of principles of
natural justice after holding that action could not have been
taken without observing principles of natural justice.
(viii) If the contract between private party and the
State/instrumentality and/or agency of State is under the
realm of a private law and there is no element of public law,
the normal course for the aggrieved party, is to invoke the
remedies provided under ordinary civil law rather than
approaching the High Court under Article 226 of the
Constitutional of India and invoking its extraordinary
jurisdiction.
(ix) The distinction between public law and private law element
in the contract with State is getting blurred. However, it has
not been totally obliterated and where the matter falls
purely in private field of contract. This Court has
maintained the position that writ petition is not
maintainable. Dichotomy between public law and private
law, rights and remedies would depend on the factual
matrix of each case and the distinction between public law
remedies and private law, field cannot be demarcated with
precision. In fact, each case has to be examined, on its facts
whether the contractual relations between the parties bear
insignia of public element. Once on the facts of a particular
case it is found that nature of the activity or controversy
involves public law element, then the matter can be
examined by the High Court in writ petitions under Article
226 of the Constitution of India to see whether action of the
State and/or instrumentality or agency of the State is fair,
just and equitable or that relevant factors are taken into
consideration and irrelevant factors have not gone into the
decision making process or that the decision is not
arbitrary.
(x) Mere reasonable or legitimate expectation of a citizen, in
such a situation, may not by itself be a distinct enforceable
right, but failure to consider and give due weight to it may
render the decision arbitrary, and this is how the
requirements of due consideration of a legitimate
expectation forms part of the principle of non-arbitrariness.
(xi) The scope of judicial review in respect of disputes falling
within the domain of contractual obligations may be more
limited and in doubtful cases the parties may be relegated to
adjudication of their rights by resort to remedies provided
for adjudication of purely contractual disputes.”
19. In K.K. Saksena v. International Commission on
Irrigation & Drainage
11, the Court held that even when a body
was performing a public duty and was amenable to writ
jurisdiction, its decisions would not be subject to judicial
review except those which had a public law element therein.
11
(2015) 4 SCC 670
While elucidating as to what constituted a public function
amenable to judicial review, reliance was placed upon R.
(Hopley) v. Liverpool Health Authority
12 and held:
“50. ...In R. (Hopley) v. Liverpool Health
Authority [2002 EWHC 1723 (Admin) : 2002 Lloyd's Med
Rep 494] (unreported)(30 -7-2002), Justice Pitchford
helpfully set out three things that had to be identified when
considering whether a public body with statutory powers
was exercising a public function amenable to judicial review
or a private function. They are : (i) whether the defendant
was a public body exercising statutory powers; (ii) whether
the function being performed in the exercise of those powers
was a public or a private one; and (iii) whether the
defendant was performing a public duty owed to the
claimant in the particular circu mstances under
consideration.”
20. In a recent judgment, the Apex Court in M.P. Power
Management Company Limited, Jabalpur v. Sky Power Southeast
Solar India Private Limited and Others
13 on a conspectus of the law
as it developed starting from the case of Radhakrishna
Agarwal (supra) held that the principle of law laid down in
Radhakrishna Agarwal (supra) would not hold good in view of the
law laid down in ABL International Limited v. Export Credit
Guarantee Corporation of India Limited
14 and further held that
even if a contract was non-statutory in character, it would not
12
[2002 EWHC 1723 (Admin) : 2002 Lloyd's Med Rep 494] (unreported)(30-7-2002)
13
(2023) 2 SCC 703
14
(2004) 3 SCC 553
entitle the State to ward off scrutiny of its action or inaction under
the contract if it was established that such action or inaction, per
se, was arbitrary and further held that Article 14 enabled the writ
Court to deal with arbitrary action even after contract was entered
into by the State.
The Supreme Court in the aforementioned judgment while
holding that existence of an arbitration provision would be viewed
as a near bar to the entertainment of a writ petition and existence
of an alternate remedy was to be borne in mind in declining relief
in a writ petition in a contractual matter, yet there was no
prohibition in the writ Court in deciding even disputed questions of
fact particularly when the dispute pertained only to demystifying
of documents. It was further held as under:
“82.12. In a case the State is a party to the contract and a
breach of a contract is alleged against the State, a civil action
in the appropriate forum is, undoubtedly, maintainable. But
this is not the end of the matter. Having regard to the
position of the State and its duty to act fairly and to eschew
arbitrariness in all its actions, resort to the constitutional
remedy on the cause of action, that the action is arbitrary, is
permissible (see in this regard Shrilekha Vidyarthi v. State
of U.P. [Shrilekha Vidyarthi v. State of U.P., (1991) 1 SCC
212 : 1991 SCC (L&S) 742] ). However, it must be made
clear that every case involving breach of contract by the
State, cannot be dressed up and disguised as a case of
arbitrary State action. While the concept of an arbitrary
action or inaction cannot be cribbed or confined to any
immutable mantra, and must be laid bare, with reference to
the facts of each case, it cannot be a mere allegation of breach
of contract that would suffice. What must be involved in the
case must be action/inaction, which must be palpably
unreasonable or absolutely irrational and bereft of any
principle. An action, which is completely mala fide, can
hardly be described as a fair action and may, depending on
the facts, amount to arbitrary action. The question must be
posed and answered by the Court and all we intend to lay
down is that there is a discretion available to the Court to
grant relief in appropriate cases.”
21. Reference to the aforementioned judgments would thus make
it clear that even in non-statutory contracts wherever there is
arbitrariness by the State, being one of the contracting parties,
judicial review is permissible under Article 226 of the Constitution
of India. In that view of the matter, the objection in regard to
maintainability of the petition in regard to a non -statutory
concluded contract is unsustainable. However, a connected
question that requires to be dealt with is whether this is a fit case
where the petitioner ought to have been relegated to the remedy of
a civil suit as has been ordered by the learned single Judge in the
judgment and order impugned. In our opinion, the issue raised by
the petitioner in the writ petition was not such as would consume
much time in demystifying the issues and the documents relied
upon by the petitioner with a view to support and buttress its claim
regarding the price adjustment in reference to the agreement
executed between the Government and the petitioner and
therefore, we now proceed to deal with the issue with regard to the
respective stands of the parties.
22. Admittedly, as per the agreement executed between the
petitioner and the respondents, it was agreed that price adjustment
would be both for increase and decrease in the prices for the works
completed. G.O.23, dated 11.02.2014, although issued by the
Panchayat Raj Department of the Government of Andhra Pradesh
did envisage such a similar price adjustment which was applicable
both for increase and decrease in the prices for the works
completed. In any case, G.O.No.67 was issued by the Transport,
Roads and Buildings Department of the Government of Andhra
Pradesh, which envisaged a similar provision as was contained in
the agreement with regard to price adjustment. Notwithstanding
the agreed terms and conditions with regard to price adjustment in
the agreement, dated 23.11.2012, so executed between the parties
and notwithstanding the G.O.67, dated 27.11.2015, it is not denied
that the petitioner did execute a supplemental agreement with the
Government and agreed to accept the amounts, which were based
upon calculations giving effect to the price adjustment clause to the
extent of 5% only in the case of increase of rates and not in a case
where the rates stood decreased from the agreed rates. Therefore,
the petitioner even when had a right to claim in terms of the
agreement executed between the parties had a right to enforce the
price adjustment clause, the condition as regards price adjustment
as it appears in Clause 46 of the agreement and reiterated in
G.O.Nos.23 of 2014 and 67 of 2015, yet must be deemed to have
waived his right to the limited extent of the supplemental
agreement.
23. It is not the case of the petitioner that the supplemental
agreement was executed under any undue coercion or duress as the
communications on record do not suggest so. It needs to be noted
that the petitioner in the writ petition has not made any murmur
about the supplemental agreement having been executed under any
fraud, coercion or undue influence.
24. On the other hand, the averment made in the writ petition by
the petitioner is that supplemental agreement was executed by the
petitioner due to financial problems and due to urgency in settling
payments to the workers and suppliers.
25. It is not out of place to mention that two communications,
both dated 20.07.2016 and 17.08.2016, addressed by the
petitioner to the Superintending Engineer and the Engineer -in-
Chief of R & B Circle only prayed for the price adjustment beyond
5% of the decrease in the rates and did not in the least mention that
the supplemental agreement was executed under any fraud,
coercion or undue influence by the respondents. In the absence of
such an averment and in the absence of such material on record,
the official respondents based upon the supplemental agreement
were justified in refusing any differential payment as claimed by
the petitioner and to that extent, in our opinion, it cannot be said
that there has been any arbitrariness on the part of the official
respondents in that regard, which would justify the exercise of
extraordinary jurisdiction of this Court under Article 226 to issue a
mandamus to make such a payment.
26. In R.N.Gosain Vs. YashpalDhir
15, the Court held:
“Law does not permit a person to both approbate and
reprobate. This principle is based on the doctrine of election which
postulates that no party can accept and reject the same instrument
and that “a person cannot say at one time that a transaction is valid
and thereby obtain some advantage, to which he could only be
entitled on the footing that it is valid, and then turn around and say
it is void for purposes of securing some other advantage.”
27. The petitioner having entered into supplemental agreement
and having agreed to receive a particular amount based upon the
calculation reflected in the supplemental agreement cannot be
15
(1992) 4 SCC 683
permitted to take a somersault and claim an amount which was
otherwise not reflected in the supplemental agreement as payable
to the petitioner. Unless and until the petitioner succeeded in
establishing that the supplemental agreement was executed under
fraud, coercion or undue influence, which in the present case the
petitioner has failed to establish, it will not help the petitioner to
succeed in the present case on the ground that the supplemental
agreement was executed on account of financial compulsion,
commercial pressure or economic duress. Reference in this regard
can also be made to the Apex Court judgment in the case of National
Insurance Company Limited Vs. M/s. Boghara Polyfab Pvt. Ltd.
16,
which held as follows:
“52 (v). A claimant makes a claim for a huge sum,
by way of damages. The respondent disputes the claim.
The claimant who is keen to have a settlement and avoid
litigation, voluntarily reduces the claim and requests for
settlement. The respondent agrees and settles the claim
and obtains a full and final discharge voucher. Here even
if the claimant might have agreed for settlement due to
financial compulsions and commercial pressure or
economic duress, the decision was his free choice. There
was no threat, coercion or compulsion by the
respondent. Therefore, the accord and satisfaction is
16
(2009) 1 SCC 267
binding and valid and there cannot be any subsequent
claim or reference to arbitration.”
28. It is settled law in the case of Bishundeo Narain and Another
Vs. Seogeni Rai and Jagernath
17 that general allegations of fraud,
coercion or undue influence, in howsoever strong language they
may couch in are insufficient without a party putting forth full
particulars in that regard before the Court. Not only should there be
a specific averment in the pleadings but there must also be
sufficient material to buttress the allegations in that regard.
29. Be that as it may, we find no merit in the present appeal which
is accordingly dismissed. No costs.
Consequently, connected miscellaneous petitions, if any, shall
stand closed.
DHIRAJ SINGH THAKUR, CJ
R RAGHUNANDAN RAO, J
kbs/akn
17
AIR 1951 SC 280
_____
HON’BLE MR. JUSTICE DHIRAJ SINGH THAKUR, CHIEF JUSTICE
&
HON’BLE MR. JUSTICE R.RAGHUNANDAN RAO
W.A. No.1060 of 2023
(per Dhiraj Singh Thakur, CJ)
Dt: 04.04.2024
kbs/akn
Legal Notes
Add a Note....