As per case facts, the Respondent, a small enterprise, entered into a contract with the Petitioner for the design, engineering, manufacture, supply, erection, and commissioning of an Electro Static Precipitator ...
2026:MHC:669Arb O.P(COM.DIV.) No. 682 of 2022
IN THE HIGH COURT OF JUDICATURE AT MADRAS
ORDER RESERVED ON : 17 - 02 -2026
ORDER PRONOUNCED ON : 19 - 02 -2026
CORAM
THE HON'BLE MR JUSTICE N. ANAND VENKATESH
Arb O.P.(COM.DIV.) No. 682 of 2022
M/s.TGV SRAAC LTD.,
(Formerly M/s Sree Rayalaseema Alkalies and
Allied Chemicals Limited), 40-304, 2nd Floor,
Krishna Jyothsna Complex, Bhagyanagar,
Kurnool-518 004. Andhra Pradesh.
..Petitioner(s)
Vs
M/s.Unicon Engineers
513-A/6, Bharthi Street, Chinnavedampatti,
Coimbatore-641 049.
..Respondent(s)
PRAYER: This Original Petition is filed under Section 34 (2) of the Arbitration
and Conciliation Act, 1996, to set aside the impugned Arbitration Award dated
02.11.2021 passed by the Arbitrator.
__________
Page 1 of 17
https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
For Petitioner(s):Ms. Punnagai M.
for M/s Hari Radhakrishnan
For Respondent(s):Mr. B.Manoharan
ORDER
The petitioner has assailed the Award passed by the sole Arbitrator dated
02.11.2021 in the present petition filed under Section 34 (2) of the Arbitration
and Conciliation Act, 1996, (for brevity, hereinafter referred to “the Act”).
2. The case of the respondent/claimant is that they are a small enterprise
registered in the year 1991 under the Micro, Small and Medium Enterprises
Development Act, 2006, (hereinafter referred to as “the MSMED Act”) and that
they are engaged in the manufacture of air pollution control equipments. The
petitioner proposed to install a captive thermal power Plant of 25 MW capacity
for the purpose of supplying energy to its manufacturing units. This power plant
required pollution control equipment and, for that purpose, the petitioner
negotiated with the respondent and issued a Letter of Intent (LOI) dated
12.03.2009 containing various terms and conditions for the design, engineering,
manufacture, supply, storage, erection and commissioning of Elector Static
__________
Page 2 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
Precipitator (hereinafter referred to as “ESP”). The contract price was fixed at
Rs.3,95,00,000/-.
3. The further case of the respondent is that they supplied the ESP
machinery at a price of Rs.3,75,00,000/- upon various payment terms. In the
purchase order, it was stated that a separate work order will be issued later for
erection and commissioning at a cost of Rs.20,00,0000/-. Subsequently, the
purchase order was amended vide letter dated 22.05.2009, whereby the cost of
supply was revised to Rs.3,55,00,000/- and the cost of erection and
commissioning was revised to Rs.40,00,000/-.
4. It is the further case of the respondent that an advance amount of 10%
of the contract value, amounting to Rs.37,50,000/-, was paid by the petitioner
by means of cheques. When the respondent sent the scanned copy of the
drawings, the petitioner released a further payment of Rs.33,50,000/- vide
cheques in line with the terms contained in the purchase order.
5. There was a delay in making further payments and the parties arranged
for a meeting and entered into a fresh agreement, which was recorded in the
minutes of the meeting held from 12.03.2011 to 14.03.2011. Pursuant to the
__________
Page 3 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
agreement, an amended letter dated 01.04.2011 was issued by the petitioner to
the respondent, increasing the purchase price from Rs.3,55,00,000/- to
Rs.3,97,60,000/-. This amended letter also provided for a hike in the price of
erection and commissioning to the tune of Rs.47,40,000/-.
6. Once again, the parties were not able to comply with the terms of
agreement, which resulted in a subsequent agreement, which was recorded in
the minutes of the meeting held on 01.06.2011. Pursuant to the revised
agreement, the petitioner opened an LC for Rs.1,50,00,000/- on 07.07.2011 and
another LC for the remaining amount on 23.05.2012 and 19.01.2013,
respectively. Accordingly, the respondent completed the supply of the ESP
machinery on 04.04.2013 and conducted the necessary tests.
7. Both parties alleged breach of contract against each other. Since the
parties were not able to reach an amicable settlement, the dispute ultimately
reached the sole Arbitrator. The respondent made a claim for a sum of
Rs.1,66,27,986/- on various heads. The petitioner also made certain
counterclaims.
__________
Page 4 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
8. The respondent relied upon documents marked as Ex.C1 to Ex.C125
and the petitioner relied upon documents marked as Ex.R1 to Ex.R102.
9. The sole Arbitrator, on considering the facts and circumstances of the
case and on appreciation of evidence, allowed Claim Nos.1(a), 1(b), 1(c), 1(d),
2(ii), 2(iv), and 2(v) and rejected the remaining claims. Insofar as the
counterclaims made by the petitioner are concerned, the entire counterclaim was
rejected.
10. Aggrieved by the same, the present petition has been filed before this
Court.
11. When this petition came up for final hearing on 04.02.2026, the
learned counsel raised certain preliminary issues which touched upon the very
jurisdiction of the arbitral tribunal and hence, this Court recorded the
submissions and passed the following order:-
“This Court heard the learned counsel for the petitioner.
2. The learned counsel for the petitioner raised two preliminary
objections questioning the very jurisdiction of the Arbitral Tribunal
in entertaining the claim made by the respondent. The first
preliminary issue that was raised on the side of the petitioner is that
the purchase order for supply and commissioning of Electro Static
__________
Page 5 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
Precipitator [ESP] was executed between the parties on 17.03.2009
and the same was amended on 13.05.2009 and 22:05:2009
respectively. According to the petitioner, the respondent had
obtained registration under the MSMED Act, 2006 only on
27.04.2016, which was subsequently modified on 25.08.2020.
Therefore, the respondent is not entitled to seek any benefit under
the provisions of MSMED Act. To substantiate this submission, the
learned counsel relied upon the judgments of the Apex Court in
Tata Power Company Ltd., vs. Genesis Engineering Company
reported in [MANU/DE/2550/2023], Sterling and Wilson Pvt.,
Ltd., vs. Union of India reported in [MANU/MH/1631/2017].
P.L.Adke Vs. Wardha Municipal Corporation reported in
MANU/MH/2179/2021] and the judgment in Gujarat State Civil
Supplies Corpn. Ltd. v. Mahakali Foods (P) Ltd., reported in
(2023) 6 SCC 401.
3. The second preliminary issue that has been raised by the
learned counsel for the petitioner is that the nature of contract
between the parties involved Design, Engineering, Manufacture,
Supply, Storage, Erection and Commissioning of ESP and that this
work awarded to the respondent was essentially a works contract
and it is not for procurement of goods or services. Hence, the
learned counsel by relying upon the judgment of the Apex Court in
Kone Elevator India (P) Ltd. v. State of T.N., reported in (2014) 7
SCC 1, submitted that the contract executed is essentially for
erection and commissioning of ESP and the supply of goods and
services was incidental and therefore the said judgment of the Apex
Court will squarely apply to the facts of will the case. Consequently,
it was contended that the proceedings under Section 18(1) of the
MSMED Act, is without any legal sanctity. To substantiate his
submission, the learned counsel relied upon the judgments of the
Apex Court in Silpi Industries vs. Kerala State Road Transport
Corporation reported in [MANU/SC/0390/2021] and in Anupam
Industries Ltd., Vs. The State Level Industry Facilitation
Council reported in [MANU/GJ/3013/20221]
4.In the light of the above preliminary objections raised on the
side of the petitioner, there shall be a direction to the learned
counsel for the petitioner to file a convenience set containing the
documents, order passed by the Arbitral Tribunal on the preliminary
__________
Page 6 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
objections and also the judgments relied upon by the petitioner. An
advance copy shall be served on the learned counsel for the
respondent. This Court will hear both sides on the preliminary
objections raised and if the preliminary objection is upheld, there
will be no need to go into the merits of the case. If it is rejected, this
Court will consider the case on merits and pass final orders.
5. Post this case under the caption part heard cases on
10.02.2026.”
12. The learned counsel for the respondent submitted that the petitioner
had given up the preliminary objection regarding the status of the respondent as
a ‘Supplier’ as defined under Section 2(n) of the MSMED Act and, therefore,
the petitioner cannot be permitted to raise those preliminary objections and that
the present case has to be necessarily dealt with on merits.
13. As recorded in the previous proceedings dated 04.02.2026, one of the
issues that has been raised by the learned counsel for the petitioner goes to the
root of the matter, touching upon the very jurisdiction of the sole Arbitrator,
which is circumscribed under Section 18 of the MSMED Act. Hence, even if
the parties give up the issue of jurisdiction, if ultimately the exercise of
jurisdiction by the Arbitral Tribunal becomes questionable, the Court has to
necessary deal with that issue considering the fact that an Award passed by an
Arbitral Tribunal without jurisdiction will be construed as non est in the eye of
__________
Page 7 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
law. In any event, a jurisdiction that is not vested in the Arbitral Tribunal cannot
be conferred by the parties, more particularly in a case, where such jurisdiction
is defined under the MSMED Act.
14. The main preliminary issue that was raised on the side of the
petitioner is that the nature of the contract between the parties does not confine
itself to mere supply of goods and rendering of services and it also includes
within itself erection and commissioning of the ESP, which makes it a works
contract. If the contract between the parties is ultimately held to be a works
contract, it would fall outside the jurisdiction of the Arbitral Tribunal
constituted under the MSMED Act.
15. The law on this issue was dealt with by the Apex Court in the case of
Kone Elevator India Private Limited Vs. State of Tamil Nadu reported in
(2014) SCC OnLine SC 430, wherein the majority judgment held as follows:-
70. Coming back to Kone Elevators, it is perceivable that the three-
Judge Bench has referred to the statutory provisions of the 1957 Act and
thereafter referred to the decision in Hindustan Shipyard Ltd. , and has
further taken note of the customers’ obligation to do the civil construction
and the time schedule for delivery and thereafter proceeded to state about the
major component facet and how the skill and labour employed for
converting the main components into the end product was only incidental
__________
Page 8 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
and arrived at the conclusion that it was a contract for sale. The principal
logic applied, i.e., the incidental facet of labour and service, according to us,
is not correct. It may be noted here that in all the cases that have been
brought before us, there is a composite contract for the purchase and
installation of the lift. The price quoted is a composite one for both. As has
been held by the High Court of Bombay in Otis Elevator, various technical
aspects go into the installation of the lift. There has to be a safety device. In
certain States, it is controlled by the legislative enactment and the rules. In
certain States, it is not, but the fact remains that a lift is installed on certain
norms and parameters keeping in view numerous factors. The installation
requires considerable skill and experience. The labour and service element is
obvious. What has been taken note of in Kone Elevators is that the company
had brochures for various types of lifts and one is required to place order,
regard being had to the building, and also make certain preparatory work.
But it is not in dispute that the preparatory work has to be done taking into
consideration as to how the lift is going to be attached to the building. The
nature of the contracts clearly exposit that they are contracts for supply and
installation of the lift where labour and service element is involved.
Individually manufactured goods such as lift car, motors, ropes, rails, etc. are
the components of the lift which are eventually installed at the site for the lift
to operate in the building. In constitutional terms, it is transfer either in
goods or some other form. In fact, after the goods are assembled and
installed with skill and labour at the site, it becomes a permanent fixture of
the building. Involvement of the skill has been elaborately dealt with by the
High Court of Bombay in Otis Elevator and the factual position is
undisputable and irrespective of whether installation is regulated by statutory
law or not, the result would be the same. We may hasten to add that this
position is stated in respect of a composite contract which requires the
contractor to install a lift in a building. It is necessary to state here that if
there are two contracts, namely, purchase of the components of the lift from
a dealer, it would be a contract for sale and similarly, if separate contract is
__________
Page 9 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
entered into for installation, that would be a contract for labour and service.
But, a pregnant one, once there is a composite contract for supply and
installation, it has to be treated as a works contract, for it is not a sale of
goods/chattel simpliciter. It is not chattel sold as chattel or, for that matter, a
chattel being attached to another chattel. Therefore, it would not be
appropriate to term it as a contract for sale on the bedrock that the
components are brought to the site, i.e., building, and prepared for
delivery. The conclusion, as has been reached in Kone Elevators , is based
on the bedrock of incidental service for delivery. It would not be legally
correct to make such a distinction in respect of lift, for the contract itself
profoundly speaks of obligation to supply goods and materials as well as
installation of the lift which obviously conveys performance of labour and
service. Hence, the fundamental characteristics of works contract are
satisfied. Thus analysed, we conclude and hold that the decision rendered
in Kone Elevators does not correctly lay down the law and it is, accordingly,
overruled.
16. The above judgment was followed by the Delhi High Court in the
case of Tata Power Company Limited Vs. Genesis Engineering Company
reported in 2023 SCC OnLine Del 2366 and the relevant portions are extracted
hereunder:-
17. The primary question to be adjudicated before coming to the
arbitrability of the disputes in question is the applicability of the
MSME Act to the case at hand. In order to determine, the applicability
of the sald Act, it is pertinent to peruse the contract and determine the
nature of the contract.
18. Pursuant to the issuance of the LoC, the parties entered into
the following Work Orders along with the General Conditions of
__________
Page 10 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
Contract:
(a) Work Order No. 6000040502 for Replacement of Street Lights
along with LEDs; and
(b) Work Order bearing No. 6000042695 for Supply & Installation
of Tubular poles, Supply & Installation of Earth Wire, Supply &
Installation of PVC Cable and other relevant accessories and services
as per BOQ.
19. In order to ascertain whether the scope of work as awarded to
Petitioner would qualify as a 'work contract' or 'composite supply', the
judgment of the Hon'ble Supreme Court of India in Kone Elevator
India Private Limited v. State of Tamil Nadu, (2014) 7 SCC 1 is
relevant to appreciate the categories of contract, i.e. (a) Contract for
work to be done for remuneration and for supply of materials to be
used in the execution of work for a price (b) Contract for work in
which the use of the materials is necessary or incidental to the
execution of the work (c) Contract for supply of goods where some
work is required to done as Incidental to the sale. The Hon'ble
Supreme Court has opined that category (a) as composite contract
consisting of two contracts, one of which is for the sale of goods and
the other which is for work and labour. It was held that the
involvement of supply of goods and material as well as installation of
the lift had concluded that the contracts awarded to Kone Elevators
satisfy the characteristics of Works Contract and held that it cannot be
considered as contract of sale.
20. Applying the judgment to the instant case, the Works Orders
as executed by the parties in the instant case falls within category (a)
as it comprises of two contracts which include supply of goods such as
Cables, wire, connectors, street lights and poles and subsequent
involvement of work and labour for its installation. Further, the
element of both supply of goods and element of labour and service is
involved in the Work Orders. It is also a settled principled of law that
that dispute/claims arising from Works Contract are not amenable to
the jurisdiction of Facilitation Council constituted under the MSME
Act.
__________
Page 11 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
17. The next judgment that was relied upon is again the judgment of the
Delhi High Court in the case of M/s.Shree Gee Enterprises Vs. Union of India
and Anr. reported in 2015 SCC OnLine Del 13169. In this judgment, the Delhi
High Court took into consideration the clarification given by the Ministry of
Micro, Small and Medium Enterprises and the relevant portions are extracted
hereunder:-
“10. Reference may also be had to the office memorandum dated
20.02.2014 issued by the Director of the Office of the Development
Commissioner, Ministry of MSME, Union of India, wherein frequently
asked questions and their answers had been circulated to the various
Ministries and in particular to question No. 18 and their answers thereto
which reads as under:-
Ques. 18. Whether this policy is applicable for works/trading
activities also?
Ans. Policy is meant for procurement of only goods produced and
services rendered by MSEs.
11. A reading of the policy along with the frequently asked
questions meant for giving preference in respect of procurement of goods
produced and services rendered by Micro, Small and Medium Enterprises
(MSME). It would not be applicable to a "works contract” simpliciter.
18. It is quite clear from the above judgments that where the contract
between the parties is a composite contract, which includes supply of goods,
rendering services and other components like, installation, commissioning, etc.,
it has to be treated as a works contract since it is not a sale of goods or rendering
of services simpliciter. This clarification was in fact, given by the Ministry
__________
Page 12 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
concerned under the FAQs to the effect that the policy under MSMED Act is
meant only for goods produced and services rendered and is not applicable to
works contract.
19. In the case in hand, even though separate purchases orders were
issued for supply and services, the ultimate bill that was raised included within
its fold manufacture, supply, storage, erection and commission of the ESP. This
clearly constitutes a works contract and it is not a contract of manufacturing of
goods and rendering of services simpliciter.
20. The learned counsel for the respondent relied upon an order passed in
W.P.No.17814 of 2022, dated 13.06.2023, where a similar objection was
refused to be gone into by this Court. This order will not apply to the facts of
the present case, since this Court was dealing with a writ petition and the nature
of contract involved was held to be a question of fact, which cannot be gone
into while exercising a writ jurisdiction. The learned counsel for the respondent
also relied upon a judgment of the Calcutta High Court in WPO No.2896 of
2022, dated 27.06.2023, where the Calcutta High Court held otherwise, even
insofar as a works contract is concerned. It was brought to the notice of this
Court that the said order passed by the learned single Judge was subsequently
__________
Page 13 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
stayed by a Division Bench. In view of the same, this judgment cannot be taken
as a precedent.
21. In the case in hand, an application came to be filed under Section 16
of the Act before the sole Arbitrator raising preliminary objection on the
jurisdiction of the Tribunal to deal with the matter. Section 15 of the MSMED
Act was brought to the notice of the sole Arbitrator and a ground was raised to
the effect that only goods and services will come within the purview of the
MSMED Act. This ground virtually touches upon the core issue that was
discussed by this Court supra and the sole Arbitrator had rejected the
application on 20.02.2020. Therefore, it is not as if this issue was not raised
before the sole Arbitrator, but however, it was not addressed in a proper form,
but in substance what was questioned was the jurisdiction of the Arbitral
Tribunal. Hence, the petitioner is not raising this issue for the first time before
this Court.
22. In the light of the above discussion, this Court holds that the term
“buyer” defined under Section 2(d) of the MSMED Act only deals with goods
or services. Similar is the definition of “enterprise” under Section 2(e) of the
MSMED Act. These definitions, along with the law enunciated by the Apex
__________
Page 14 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
Court and the other High Courts, make it clear that MSMED Act would apply
only to supply of goods or services and does not cover the works contract,
which is a composite supply of goods and services and which also includes
erection and commissioning of equipment. Accordingly, the sole Arbitrator
lacked jurisdiction to deal with the claim made by the respondent since the
jurisdiction is specifically defined under the MSMED Act, 2006. Accordingly,
the Award rendered by an Arbitral Tribunal without jurisdiction will render the
Award non est in the eye of law.
23. In the light of the above finding, it is not necessary for this Court to
go into the other preliminary issue raised by the learned counsel for the
petitioner to the effect that the respondent was not registered as an enterprise on
the date of entering into the contract with the petitioner until the completion of
the entire project and therefore, could not claim for the benefits under the
MSMED Act. Getting into this issue will only be an academic exercise since
this Court has rendered the Award as non est while dealing with the first
preliminary issue raised by the learned counsel for the petitioner.
__________
Page 15 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
24. The upshot of the above discussion leads to the only conclusion that
the Award passed by the sole Arbitrator dated 02.11.2021 is liable to be
interfered with and is accordingly set aside. It is left open to the parties to take
steps to appoint a fresh Arbitrator to refer the dispute in accordance with law.
25. In the result, this Original Petition is allowed in the above terms.
Considering the nature of the issue, there shall be no order as to costs.
19-02-2026
Index : Yes
Speaking Order: Yes
Neutral Citation: Yes
Asi
To
M/s.Unicon Engineers
513-A/6, Bharthi Street, Chinnavedampatti,
Coimbatore-641 049.
__________
Page 16 of 17 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 682 of 2022
N. ANAND VENKATESH, J.
Asi
Arb O.P.(COM.DIV.) No. 682 of 2022
19-02-2026
__________
Page 17 of 17 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....