municipal governance, administrative law, local authority, public law
0  15 Nov, 2019
Listen in 01:59 mins | Read in 54:00 mins
EN
HI

Municipal Corporation of Greater Mumbai (Mcgm) Vs. Abhilash Lal & Ors.

  Supreme Court Of India Civil Appeal /6350/2019
Link copied!

Case Background

The Municipal Corporation of Greater Mumbai invokes Section 62 of the Insolvency and Bankruptcy Code, 2016, contesting the National Company Law Appellate Tribunal’s rejection of its appeal related to a ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

REPORTABLE

   IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 6350 OF 2019

MUNICIPAL CORPORATION OF GREATER

MUMBAI (MCGM)      ...APPELLANT(S)

VERSUS

ABHILASH LAL  & ORS.             ...RESPONDENT(S)

J U D G M E N T

S. RAVINDRA BHAT, J.

1.The   Municipal   Corporation   of   Greater   Mumbai   (hereafter

“MCGM”)   appeals   under   Section   62   of   the   Insolvency   and

Bankruptcy Code, 2016 (hereafter “IBC” or “the Code”) against the

order of  the National Company Law Appellate Tribunal (hereafter

variously “NCLAT” and “the Appellate Tribunal”), rejecting its plea

with respect to a resolution plan approved by the National Company

Law Tribunal (“NCLT”) under the provisions of that Code. 

2

2.MCGM owns  inter alia,  Plot Nos. 155­156, 162 and 168 (all

plots hereafter called “the lands”) in village Marol, Andheri (East)

Mumbai. By a contract (dated 20

th

  December, 2005) SevenHills

Healthcare (P.) Ltd. (the company facing insolvency proceedings,

hereafter “SevenHills”) agreed to develop these lands (which were to

be leased to it for 30 years) and construct a 1500 bed hospital.

MCGM stipulated several conditions, including that 20% of the beds

had to be reserved for use by the economically deprived, and that

SevenHills   had   to   complete   the   construction   in   60   months

(excluding monsoons). The sixty­month period ended on 24

th

 April,

2013; the project however, was not completed. In terms of Clause

15(g), the lease deed had to be executed within a month after

completion. However, the deed was not executed as the project was

not completed. Further, SevenHills had to pay lease rent at the

annual   rate   of   10,41,04,000.   MGCM   alleges   that   there   were

defaults in these payments. In these circumstances, MCGM issued

a show cause notice on 23

rd

 January, 2018, proposing termination

of the contract/agreement. It is submitted that SevenHills owed

MCGM an amount of   76,05,07,780.  

3

3.On the strength of the contract, SevenHills had borrowed from

banks and financial institutions. It had created security by way of

mortgage of the said lands, citing Clause 5, which enabled the

creation of such encumbrances. SevenHills’ inability to repay its

debts led to the initiation of insolvency proceedings by Axis Bank.

On 13

th

  March, 2018, before the period given by MCGM’s show­

cause notice ended, the Petition (CP (IB) No. 282/7/HBD/2017) was

admitted   by   the   Hyderabad   Bench   of   the   NCLT.     The   first

respondent was appointed as the Resolution Professional (hereafter

“RP”); this was approved by the Committee of Creditors (“CoC”) as

required   by   the   Code,   on   12   April,   2018.   A   publication   for

expression of interest (“EOP”) was issued on 14 May, 2018; later, on

25

th

 June, 2018 and 16

th

 July, 2018, the terms of the Request for

Proposal (RFP) and criteria for evaluation (of RFPs received) were

approved. As a result of the RFP published, a resolution plan was

submitted   by   Dr.   Shetty’s   New   Medical   Centre   (“SNMC”).   After

discussion with the CoC, a revised RFP was submitted by the RP.

The   revised   resolution   plan   was   approved   by   the   CoC   on   4th

September, 2018. 

4

4.The resolution plan projected infusion of over  1000 crores by

SNMC.   That   amount   was   to   be   borrowed;   for   this   purpose,

SevenHills’ properties ­ movable and immovable, were proposed to

be secured by hypothecation and mortgage respectively. Operational

creditors were to be paid off to the extent of 75%. Further, the plan

proposed payout to the tune of  102.3 crores to MCGM as against

its total claim of  140.88 crores, and also committed to honouring

the terms of the agreement entered into by SevenHills and providing

20% of the beds (of the hospital to be constructed) to the poor and

weaker sections of society. The net­worth certificate furnished by

SNMC indicated that it possessed sufficient funds. 

5.MCGM filed an application (I.A. No. 207/ 2018) claiming that

it ought to be declared as a Financial Creditor and a Member of the

Committee   of   Creditors.   It   made   several   submissions,   which

indicated that subject to stipulations with respect to completion of

the hospital project in a timebound manner, and subject to SNMC

providing   20%   beds   in   the   completed   hospital,   for   use   by   the

economically weaker sections (and at the disposal of MCGM) and,

5

lastly subject to clearing its (MCGM’s) claims to the tune of  140.88

crores,   it   was   agreeable   to   the   resolution   plan.   However,   later

during the proceedings, it opposed the resolution plan, arguing that

being a public body as well as a planning authority, it had to

comply with the provisions of the Mumbai Municipal Corporation

Act, 1888 (“MMC Act”), which meant that all action and approval

had to be taken by the Improvement Committee of the Corporation.

It was also stated that the show cause notice (“SCN”) dated 23

rd

January, 2018 had been already issued by MCGM proposing to

terminate the contract (with SevenHills) to which there was no

response and that in the absence of a lease, the provisions of

Section 14(1)(d) of the Code could not prevent the MCGM from

terminating the agreement. Another argument made was that the

period of CIRP in the case began on 13

th

  March, 2018 when the

petition was admitted and the period of 270 days expired on 8

th

September, 2018; an extension of 90 days provided in Section 12(3)

was granted by the Adjudicating Authority on 4

th

 September, 2018

and the extended period came  to an end on 7

th

 December, 2018;

thus the CIRP has lapsed by efflux of time.

6

6.The NCLT, after considering the views of the RP, MCGM, the

creditors and SNMC, held that:

“29.It  may  be  relevant  to  note  here  that  the

Application   for   approval   of   the   resolution   plan

was filed on 07.09.2018. The MCGM at a belated

stage   has   come   up   with   its   objections   to   the

Resolution   Plan   with   the   contention   that   it   is

undisputed owner of the plot on which one of the

hospitals of the Corporate Debtor in Mumbai is

built. The various objections raised by MCGM as

enumerated hereinabove at a belated stage are

neither tenable nor acceptable. It is clear from the

record that MCGM is taking a stand which is

totally contrary to its own decisions and factual

submissions.   The   final   prayer   of   MCGM   is   to

reject   the   'resolution   plan'   and   order   for

liquidation of the Corporate Debtor. The RP in his

submissions has clearly pointed out as to why

the   averments   of   MCGM   are   erroneous   and

incorrect.   For   the   sake   of   briefness,   the

submissions made by RP as stated supra are not

discussed in detail once again. This Adjudicating

Authority   is   of   the   view   that   the   contentions

raised by MCGM cannot be accepted due to the

conflicting and contradictory stands taken by it in

the course of hearings. Further, the contention of

MCGM relating to expiry of the period of 270 days

is untenable and unacceptable for the reason that

the Application by the Resolution Professional for

7

the   approval   of   the   Resolution   Plan   has   been

made well before the expiry of the period of CIRP

and the same is in accordance with the provisions

of the Code. Therefore, the objections raised by

the MCGM are hereby rejected.”

7.The   NCLT   also   held   that   the   plan   filed   along   with   the

application met the requirements of Section 30(2) of the Code, and

Regulations 37, 38, 38(IA) and 39(4) of IBBI (CIRP) Regulations,

2016. It also held that the resolution plan did not contravene any of

the provisions of Section 29A and was unanimously approved by

that CoC; it provided for 78.07% of payment to financial creditors

and 75% of payment to operational creditors including doctors,

irrespective of claims in incorrect forms. Further, the resolution

applicant is also addressing the dues payable to MCGM as stated in

the   resolution   plan.   Further,   that   NCLT   observed   that   on

comparison of the amount offered in the resolution plan with Form­

H submitted by the RP, it was seen that the amount proposed in the

plan was more than that of the value of liquidation of the Corporate

Debtor. It accordingly approved the plan.

8

8.Aggrieved by NCLT's order, MCGM approached the Appellate

Tribunal, before which several grounds were urged, including that

since the conditions stipulated in the contract (with SevenHills

Healthcare) had not been complied with, there was no lease deed

and consequently no interest inured in the land, in favour of the

Corporate Debtor. It was also urged that the resolution applicant

was aware that the property belonged to MCGM, and had not vested

in the Corporate Debtor. Despite these circumstances, the proposal

and revised proposal incorporating encumbrances of the lands were

made contrary to law. It was also specifically urged that mandatory

provisions of the MMC Act requiring express authorization by the

corporation for transfer or creation of any interest in land had not

been   complied   with   and   resultantly,   the   proposal   and   revised

proposal approved by the NCLT, so far as they dealt  with the

property and lands, were not enforceable against MCGM.

9.The NCLAT in its impugned order, took note of a memo filed

on behalf of the MCGM on 20th April, 2019 (before the NCLT), that

the   revised   resolution   plan   had   been   accepted   and   all   terms

9

specified in its written submissions, were to be incorporated. As a

result, the NCLAT was of the opinion that there was no scope for

interference with the order of the Adjudicating Authority/NCLT.

10.It is argued on behalf of MCGM by its learned senior counsel,

Mr. Neeraj Kaul, that no lease deed was executed in favour of

SevenHills, the Corporate Debtor. MCGM was the undeniable owner

of the land; as there were no assets of the Corporate Debtor, it

stated that a duly registered lease deed would be executed. The

proposal and revised proposal seeking direction with regard to the

lease deed, had to be necessarily dealt with in accordance with law.

This meant that unless MCGM, expressly approved the revised

plan, whereby a lease deed could be executed in favour of the

SevenHills   Healthcare   Pvt.   Ltd.   (or   in   favour   of   the   resolution

applicant SNFC), neither the adjudicating authority nor the NCLAT

could issue any direction seeking to bind MCGM with respect to the

manner it had to deal with properties that belonged to it.

11.It was emphasised that the effect of the impugned order is to

prevent MCGM from violating the law. The direction which was

10

highlighted was in violation of Section 92 of the MMC Act. Learned

senior counsel underlined that the written submissions filed on

behalf of MCGM could not be construed as an admission, or that

MCGM   was   bound   to   agree   to   the   revised   proposal.   It   was

alternatively   argued   that   at   best,   these   submissions   could   be

considered as concessions of law which were never binding on

MCGM.

12.It was argued that there was no question of incorporating any

direction   or   approving   the   revised   plan,   which   in   any   manner

affected   MCGM’s   properties.   In   this   context,   Mr.   Neeraj   Kaul,

learned   Senior   Counsel,   urged   that   the   terms   of   the   original

contract (dated 20

th

 December, 2005) had been violated; the 1500

bed   hospital   had   not   been   completed   by   the   stipulated   date.

Furthermore, arrears of lease rentals had mounted together every

attendant   liability.   In   these   circumstances,   even   before   the

insolvency proceedings were initiated, MCGM issued a show cause

notice   proposing   to   terminate   the   contract.   It   was   further

emphasised that since the terms of the contract were infringed, in

fact, there was no subsisting lease which could have been dealt

11

with   by   the   revised   proposal   and   later   by   the   Adjudicating

Authority. It was submitted that the impugned order has completely

noted these salient aspects.

13.On   behalf   of   the   RP   (who   has   been   arrayed   as   the   first

respondent) it is argued by Mr. C.A. Sundaram, learned senior

counsel that MCGM had categorically consented to the resolution

plan in writing before the NCLT and the Appellate Tribunal. He

points out that in the written submissions dated 28

th

  November,

2018, 29

th

  April, 2019 and 14

th

  May, 2019 MCGM categorically

stated that the resolution plan be approved and its application

before   the   NCLT   ought   to   be   disposed   of   in   terms   of   the

commitment given by the resolution applicant/SNMC. It is pointed

out that the Appellate Tribunal, after hearing the submissions of

MCGM that it had no objections to the resolution plan, affirmed it.

MCGM, counsel submitted, has not refuted that such a statement

was made before the NCLAT. It is therefore the undisputed position

that MCGM had no objections to the resolution plan. That being the

case, counsel argues that the appeal is not maintainable.

12

14.Mr.   Sundaram   argued   that   MCGM’s   contentions   that   no

interest or leasehold rights in the land were created in favour of the

Corporate   Debtor,   flies   in   the   face   of   its   letters   and   also   its

application to the NCLT, which in para 4, admitted that the lands

were   leased   to   the   Corporate   Debtor.   In   fact,   MCGM   filed   the

application claiming that the lease was a capital or finance lease

and   the   unpaid   lease   rentals   were   a   financial   debt   within   the

meaning of the Code. Unlike the written submissions, MCGM did

not even explain on what basis it had filed the application to the

NCLT regarding its position that no leasehold rights subsisted.

15.Learned senior counsel submitted that MCGM was invited to

attend and participate in CoC meetings due to its position as owner

of the land on which the Mumbai hospital of the Corporate Debtor

is located. The issue of whether or not the corporate debtor has any

leasehold rights under the contract (of 2005) is a disputed question

of fact which can only be adjudicated upon in civil proceedings after

conducting a civil trial.

13

16.It is also argued alternatively, that assuming for the purpose

of argument that no leasehold rights were created in favour of the

Corporate Debtor, the resolution plan does not create any leasehold

rights in favour of the respondent applicant/SNMC. Learned senior

counsel argued that the resolution plan merely envisages a change

in the shareholding of the Corporate Debtor but does not transfer

any of MCGM’s assets to SNMC. Therefore, it is false to suggest that

the   resolution   plan   transfers   MCGM’s   assets   to   SNMC.   It   was

argued furthermore that though MCGM was not entitled to, nor

treated   as   a   financial   creditor,   it   was   nevertheless   invited   to

participate in CoC meetings, interact as well as negotiate favourable

terms with potential resolution applicants. To further safeguard

MCGM’s interests, the RFP also required all prospective resolution

applicants to submit their plans to resolve the dispute with MCGM. 

17.Mr. Sundaram also submitted that SNMC’s revised proposal to

MCGM assured repayment of its entire dues. In light of a proposal

of this nature, MCGM’s stand seeking liquidation of the Corporate

Debtor appears not only arbitrary but also prima facie vindictive.

14

18.It is also submitted that the resolution plan is absolutely

unconditional   in   nature   and   in   no   manner   contingent   on   the

resolution of the dispute with MCGM. It is submitted that such

unconditionality is the most fundamental aspect of the resolution

plan.   This   unconditional   nature   is   recorded   in   the   minutes   of

meetings of the 8th meeting of the CoC held on 20

th

 August 2018.

MCGM participated in the meetings of the CoC, including the 8th

CoC   meeting,   and   was   provided   a   copy   of   the   minutes

contemporaneously.   These   minutes   record   SNMC’s   categorical

statement that the negotiations with MCGM are in progress and

that   the   resolution   plan   is   unconditional   and   in   no   manner

dependent on the outcome of such negotiations. Further, there is

no provision in the resolution plan (and none has been cited by

MCGM) which suggests that the plan is conditional on settlement

with it (i.e. MCGM).

19.It is also submitted that any dispute with MCGM in relation to

the lease of the underlying land has no bearing on the validity of the

resolution   plan,   under   Section   31   of   the   Code.   Having   been

15

approved by the CoC and the NCLT on merits, the plan attained

finality and binds MCGM as a stakeholder in the Corporate Debtor.

MCGM therefore, cannot hold the entire CIRP of the Corporate

Debtor to ransom despite not even having raised a single objection

on the validity of any specific term in the resolution plan under

Section 30(2) of the Code.

20.Mr. Ramji Srinivasan, appearing on behalf of the CoC, argued

that the financial creditors were interested in ensuring that their

dues were paid, preferably in full. SNFC’s resolution plan held out

the   best   assurance   toward   that   end.   He   also   argued   that   the

question of obtaining any approval under Section 92A either for

creation of charge, or for any other purpose did not arise, because

the terms of the contract, which in fact amounted to a lease (as it

was a registered instrument and MCGM had received over   10

crores as initial lease consideration). Therefore, the resolution plan

approved by the NCLT, and later, NCLAT, were sound and did not

call for interference. 

16

21.It was argued, furthermore, that the reliance on Section 92 of

the MMC Act is misguided as it seeks to superimpose provisions of

the   MMC   Act   on   the   provisions   of   the   Code.   This   is   clearly

impermissible in terms of the non­obstante provision contained in

Section 238 of the Code.

22.Mr.   K.V.   Vishwanathan,   learned   senior   counsel   for   SNFC,

argued that the plan approved provided the best solution for the

financial woes of the Corporate Debtor. It was argued that SNFC

never represented that it would mortgage or obtain any loan on the

strength of the lease. Nor did it ever urge that MCGM’s permission

was not necessary. He pointed to the terms of the resolution plan

and submitted that they were subject to MCGM’s obligations to

follow the law. 

23.It   was   submitted   that   the   proposed   plan   contemplates

compliance with the various conditions of the contract agreement

including without limitation, 20% reservation of beds for MCGM's

employees and settlement of MCGM's claimed dues. The resolution

plan proposed payment to MCGM (which was enhanced to 100% by

17

a later proposal) at clause 2.2.2(b). Further, clause 2.2.3(f) of the

resolution plan again records the proposed payment to MCGM by

stating that while the resolution professional has not admitted the

claims submitted by MCGM, SNMC recognizes such dues payable to

it and shall pay  102 crores in terms of the offer made to MCGM as

recorded.

24.In the present case, Section 92 of the MMC Act has no bearing

on the validity of the resolution plan, the approval order or the

impugned   order.   Section   92   of   the   MMC   Act   mandates   and

prescribes the manner in which disposal of land belonging to the

appellant would take place. However, the resolution plan does not

contemplate   any   disposal   of   the   said   land   or   creation   of   any

additional rights and obligations of MCGM or the Corporate Debtor

in   relation   to   the   lands.   It   is   merely   the   shareholding   of   the

Corporate   Debtor   which   undergoes   a   change   pursuant   to   the

resolution   plan.   MCGM   cannot   place   any   embargo   on   such

shareholding changes by resorting to proceeding under the Code.

18

25.It was urged that SNMC does not acquire any interest in the

said land and only acquires managerial control over the Corporate

Debtor by way of holding equity shares in the Corporate Debtor.

Therefore, there arises no question of Section 92 of the MMC Act

being violated through the resolution plan.

Discussion   regarding   the   insolvency   process   and   relevant

provisions of the MMC Act

26.On   admission   of   an   insolvency   application   preferred   by   a

financial creditor/operational creditor, a moratorium is declared on

the continuation and initiation of all legal proceedings against the

debtor.   The   NCLT   appoints   an   interim   resolution   professional

(“IRP”).   The   moratorium   operates   till   the   completion   of   the

insolvency resolution process which, by law should be completed

within a mandated time frame. During the moratorium period, the

debtor   cannot   transfer,   encumber   or   sell   any   asset.   Upon

appointment of an IRP, the board of directors stands suspended

and management vests with the IRP. These professionals (IRPs)

19

have to conduct the insolvency resolution process, take over the

assets   and   management   of   the   company,   assist   creditors   in

collecting   information   and   manage   the   insolvency   resolution

process. The term of the IRP continues until an RP is appointed

under   Section   22.   The   IRP   has   to   first   determine   the   debtor’s

financial position through information collection regarding assets,

finances and operations. Information may include data relating to

operations, payments, list of assets and liabilities. The IRP further

has to receive and collate claims submitted by creditors.

27.The RP selected by the NCLT has to constitute a committee of

creditors   (CoC)   comprising   all   the   financial   creditors   of   the

corporate debtor. This provision is aimed at creditors adopting a

collective   approach   towards   insolvency   resolution   instead   of

proceeding individually. Key decisions of the process, and the plan

to be eventually finalized are to be approved by the CoC upon its

satisfaction that the provisions of the most acceptable plan would

ensure that their dues are cleared.

20

28.The Code is principally aimed at aiding a corporate debtor in

the   resolution   of   its   insolvency   condition   without   approaching

liquidation.   The   key   to   this   process   is   the   finalization   of   an

insolvency   resolution   plan.   A   suitably   structured   plan   would

provide for repayment of the debtor’s outstanding liabilities after

evaluating its financial worth, at the same time ensuring its survival

as a going concern. The resolution plan must necessarily provision

for repayment of the debt of operational creditors in a manner such

that it shall not be lesser than the amounts that would be due,

should the debtor be liquidated per Section 30(2) of the Code. Also,

the plan should identify the manner of repayment of insolvency

resolution   costs,   the   implementation   and   supervision   of   the

strategy, and should be in compliance with the law. If the terms

(including the terms of repayment) under the resolution plan are

approved   by   the   committee   of   creditors,   it   has   to   be   further

approved by the NCLT, which is the adjudicating authority.

29.In this case, it is not the provisions of the IBC which this court

has to primarily deal with; it is rather whether the process and

21

procedure adopted by the NCLT and later the NCLAT, in overruling

MCGM’s concerns and objections with regard to the treatment of its

property (i.e. the lands) is in accordance with law. The relevant

provisions of the Municipal Corporation of Greater Mumbai Act,

1888 are extracted below:

Provisions   governing   the   disposal   of   municipal

property:

Section   92.   With   respect   to   the   disposal   of

property belonging to the corporation other than

property   vesting   in   the   corporation   for   the

purposes of the Brihan Mumbai Electric Supply

and   Transport   Undertaking,   the   following

provisions shall have effect, namely: — 

(a)   the   Commissioner   may,   subject   to   the

regulations made in this behalf, dispose of, by

sale or otherwise, any movable property belonging

to the corporation not exceeding in value, in each

instance, five lakh rupees, of grant a lease of any

immovable property belonging to the corporation,

including any right of fishing or of gathering and

taking   fruit   and   the   like,   for   any   period   not

exceeding twelve months at a time : 

Provided that every lease of immoveable property

granted   by   the   Commissioner   (other   than   a

contract for a monthly tenancy) the annual rent

where of at a rack rent exceeds 6 [fifty thousand

22

rupees] shall be reported by him, within fifteen

days after the same has been granted, to the

Improvements Committee; 

(b) the Commissioner may, — 

(i) with the sanction of the concerned Committee,

dispose off, by sale of otherwise any movable

property held  by the  Corporation, the  value of

which exceeds rupees five lakhs ; 

(ii) with the sanction of the 9[Standing Committee],

dispose off any moveable property held by the

Corporation, the value of which exceeds rupees

two crores ; 

(iii) with the sanction of the concerned Committee,

grant a lease (other than a lease in perpetuity) of

any   immovable   property   belonging   to   the

Corporation,   including   any   such   right   as

aforesaid; or sell, or grant a lease in perpetuity of

any immovable property, the value of which does

not exceed 50,000 rupees or the annual rent of

which does not exceed 3,000 rupees ; 

(c)   with   the   sanction   of   the   corporation,   the

Commissioner may lease, sell or otherwise convey

any   immovable   property   belonging   to   the

corporation 

(cc) the consideration for which any immovable

property or any right belonging to the corporation

may be sold, leased or otherwise transferred shall

not be less than market value of such premium,

rent or other consideration; 

23

(d) sanction of the corporation under clauses (b)

and (c) may be given either generally for any class

of cases or specially in any particular case ; 

(dd) notwithstanding anything contained in this

section, the Commissioner may, with the sanction

of the Corporation, and with the approval of the

State Government, grant a lease of immovable

property belonging to the Corporation to a Co­

operative Housing Society formed exclusively by

the officers and servants of the Corporation, or to

a   public   trust   exclusively   for   medical   and

educational   purposes   registered   under   the

Bombay Public Trust Act, 1950 or to a society

registered under the Societies Registration Act,

1860 or the Maharashtra Co­operative Societies

Act,   1960,  a   public   trust   registered  under   the

Bombay Public Trust Act, 1950, or a company

registered under the Companies Act, 1956 3[or

any person for the purposes of provision of public

latrines,   urinals   and   similar   conveniences   or

construction   of   a   plant   for   processing

excrementitious   and   other   filthy   matters   of

garbages] or to a person who is dishoused as a

result of the implementation of any Development

Scheme of the Corporation or to a Co­operative

Housing   Society   formed   exclusively   by   the

persons who are dishoused as a result of the

implementation of any Development Scheme of

the Corporation, at such rent, which may be less

than the market value of the premium, rent, or

other consideration, for the grant of such lease,

24

and   subject   to   such   conditions,   as   may   be

provided  by  the  bye­laws  made  under  section

461; 

(ddd) notwithstanding anything contained in this

section, the Commissioner may, with the sanction

of the Corporation, and with the approval of the

State Government, grant a lease for a period not

exceeding 60 years, of municipal land which is

declared as a slum area under the provisions of

the   Maharashtra   Slum   Areas   (Improvement,

Clearance and Re­development) Act, 1971 to a co­

operative society of slum dwellers occupying such

land, at such rent, which may be less than the

market   value   of   the   premium,   rent,   or   other

consideration, for grant of such lease, and subject

to   such   conditions,   as   the   Corporation   may

impose. The approval of the State Government

under this clause may be given either generally

for any class of cases of such lands or specifically

in any particular case of such land : Provided

that,   the   Commissioner   may   in   like   manner

renew, from time to time ; the lease for such

period   and   subject   to   such   conditions   as   the

Corporation may determine and impose ; 

(dddd) All leases granted by the corporation of the

immovable properties belonging to the corporation

for whatever term shall be subject to the following

conditions in addition to the conditions stipulated

in the Lease­deed or Lease­agreement executed

by the corporation, namely: — 

25

(i) Leasehold rights in respect of the properties

belonging to the corporation and given on lease

may be further assigned or transferred only with

the   prior   permission   of   the   Commissioner,   on

payment of such premium on account of unearned

income and transfer fees or charges at such rates

as may be specified by the corporation, from time

to time. 

(ii)   In   the   case   of   any   contravention   of   the

provisions   of   sub­clause   (i),   the   lessee   or

transferor of such leasehold rights, shall be liable

to pay penalty in addition to such premium and

transfer fees or charges, at such rates as may be

specified by the corporation, from time to time. 

(e) the aforesaid provisions of this section shall

apply, respectively, to every disposal of property

belonging to the Corporation made under or for

any purpose of this Act; 

Provided that nothing in this section shall apply

Dr. Bhau Daji Lad Museum or to the site thereof

referred to in section 89C except with the previous

sanction of 5[the 6[State] Government]. 

Section 92A. Where— 

(1) the Commissioner has transferred by way of

sale   or   exchange   any   immovable   property

belonging to the Corporation and the terms of

such transfer direct that the property shall be

applied or enjoyed in a particular manner or the

use or enjoyment thereof shall be restricted in a

particular manner, or 

26

(2)   the   owner   of   any   immovable   property   has

entered into an agreement with the Corporation

concerning the application, enjoyment or use of

the property in a particular manner, such term,

condition   or   obligation   shall   be   held   to   be

annexed   to  the   property  which   is   the  subject­

matter of the transfer or agreement and shall be

enforced against the transferee or owner and all

persons deriving title or interest under or through

him, notwithstanding— 

(a) any law for the time being in force, and 

(b) that the Corporation are not in possession of or

interested   in   any   immovable   property   for   the

benefit of which, the term, condition or obligation

was agreed to, entered into or imposed.”

30.At this stage, it would be relevant to notice certain conditions

in the contract.  Clause 2(i) stipulates the minimum lease rent as

10.40 crores for which SHCL agreed to pay 0.1% over and above

the minimum lease rent.   Clause 5 of the agreement permitted

SevenHills   to   mortgage   and/or   create   charge   of   the   schedule

property. The conditions read as follows:

"5.  The Owner hereby agrees to permit and allow

the SHCL on the   terms   and conditions to be

approved   by   the   Owner   which

permission/approval   shall   not   be   unreasonably

withheld, to mortgage and/or create charge on the

Schedule Property and/or SHCL's leasehold right

27

thereon   with   or   without   the   Buildings   on   the

Schedule property during the lease period or prior

thereto   i.e.   during   the   project   period)   in   any

manner whatsoever either in whole or in part as

SHCL   may   require   from   time   to   time   to   the

satisfaction   of   the   lenders,   for   the   purpose   of

raising   financial   assistance   from   the   Financial

Institutions/Banks/NBFOs/Co­operative

Societies/   Trust/   UF/   Partnership/Proprietary

Firm   and   any   other   lending

individuals/institutions, whether incorporated or

not, for any purpose for and in connection with the

said   Project   including   for   the   purpose   of

commencing,   carrying   out   and   completing   the

construction   of   the   Buildings,   setting   up   of

hospital,   Medical   Educational   institutions

commercial and other establishments within the

Frame work of Development Control Regulations

in   force,   in   such   Buildings,   their   running,

maintenance, renovation, reconstruction etc.   For

this purpose, the SHCL shall have to apply for

permission not mortgage and/or create charge to

Municipal Commissioner two months in advance

and if the approval is not received within two

months from the date of receipt of such a request

by   the   Commissioner,   it   will   be   deemed   as

approved and SHCL shall be at liberty to create

the mortgage of the Schedule Property in favour of

the Lenders without any recourse to the Owner."

28

31.Clause   15(a)   which   stated   that   the   lease   deed   had   to   be

entered into upon on completion of the project and contained other

conditions, pertinently,  reads as follows:

"15. LEASE OF PLOT:

a)Lease period:

i) The SHCL shall enter into a Lease Deed on

completion of project period for leasing the plot to

SHCL for the period of 60 years. After 60 years,

the lease period will be extended with the mutual

consent of Owner and SHCL on the terms that

may be mutually agreed upon by both the parties

for further period.

ii) The lease period of 60 years shall commence

from the date of completion of the Project period.

iii) On completion of the said Project the Owner

shall   issue   to   SHCL   'Project   Completion

Certificate'. Till the completion and commissioning

of the project and running of the Project facilities,

till   the   end   of   lease   period,   this   Contract

Agreement is to be read, in conjunction with the

said Lease Deed which both Parties will enter into

on completion of the project period.

iv) The SHCL shall complete the construction of

the hospital building within the project period of

60 months excluding monsoon.  the MCGM shall

be   liable   to   issue   the   Project   Completion

29

Certificate on written application by SHCL to that

effect after completion of the project.

xxxxxx xxxxxx xxxxxx

e)Penalty for delay:

i)SHCL shall complete the entire Project and

open the facility to public use within the approved

time   limit.     SHCL   shall   submit   the   work

programme with defined milestones.   the

progress of the work shall be strictly as per the

programme   of   construction   submitted   by   SHCL

and approved by the Commissioner.

In   case   SHCL   fails   to   complete   the   Project   as

aforesaid   within   the   said   Project   Period   of   60

(sixty) months excluding monsoon from issuance of

Commencement   Certificate,   and   unless   such

failure is due to force Majeure conditions, penalty

for delay shall be charged for the period of delay

which will be equivalent to 25% of Lease Rent

which SHCL would have paid to the Owner for

that period, had the Project been completed within

the Project Period and this shall be in addition to

lease rent.

ii)SHCL   shall   have   to   separately   pay   the

compensation for delay to the Owner at the end of

notice period.

iii)However, in case any delay occurs because

of circumstances beyond the control of SHCL only

30

suitable   extension   in   the   period   of   the   Project

without   imposing   penalty   or   demand   for

compensation   for   delay   shall   be   granted   for

completing   the   Project.     No   other   claim   or

compensation   of   whatsoever   nature   shall   be

entertained.

xxxxxx xxxxxx xxxxxx

g)Lease Deed:

A   Lease   Deed   shall   be   executed   as   per   draft

annexed   to   this   Contract   Agreement   as

Annexure­'II'  within one month from the expiry of

the Project period or on intimation from the owner

whichever is earlier.

17.  MORTGAGE OF PLOT AND BUILDINGS

a) The   SHCL   is   hereby   allowed   to   sublease;

mortgage and create a charge on the said plot and

buildings either in part or in total to the satisfaction

of   lenders   for   the   purpose   of   raising   financial

assistance   to   commence,   progress,   complete,

commission and run the hospital complex and other

commercial activities during the Pendency of the

lease   period,   from   the   financial   institutions/

FIIS/Banks/Mutual   Funds/Co­operative   Societies,

Trusts/individuals/HUFs/Partnership Firms, other

lending institutions and lenders of any constitution

for the said Project with the prior permission of the

Commissioner,   which   permission   shall   not   be

unreasonably withheld, during the Project period

31

and/or during the subsistence of the lease and the

Owner shall be kept informed of such deals after

permission by the Commissioner and SHCL shall

file relevant documentary evidence to that effect for

record of the owner.

The permission which shall be granted by the

Owner to SHCL to mortgage the Schedule Property

in favour of the lender (s) for raising finance will

remain   irrevocable   and   irreversible   during   the

tenure   of   the   Project   period   and   lease   period

except when the contact is terminated.   In case

the contract is terminated for valid reason, the

Owner shall not bear any cost and consequences

of resultant termination of mortgage by SHCL to

any   Financial   Institution.   While   the   right   of

ownership   will   remain   with   the   Owner,   the

leasehold rights to the property will remain free

from encumbrances and dedicated to the lenders

during the currency of loan or the lease period

whichever is earlier and the lenders shall continue

to enjoy the same rights and privileges as that of

SHCL.

SHCL is also hereby allowed, with prior written

permission   from   Commissioner   to   sublet   the

whole or part thereof and/or the buildings on the

Schedule Property.  The SHCL shall be entitled to

sublet the Schedule Property and the Building/s

thereon from time to time in whole or in part for

any duration (not beyond the lease period) to any

other Party/ies (sub­lessee/s) on such terms and

32

conditions, as may be agreeable to SHCL within

the frame work of the tender and this Agreement

and for the same or similar purposes for which

agreement   is   intended,   by   means   of   duly

registered Deed/s. SHCL shall have to apply for

permission   to   Municipal   Commissioner   two

months in advance and if the approval is not

received   within   two   months   from   the   date   of

receipt of such a request by the Commissioner, it

shall be deemed as approved."

32.A   cumulative   reading   of   the   stipulations   reveals   that   the

contract/agreement contemplates that the lease deed was to be

executed after the completion of the project.  The contract reveals

that (a) the project period was for 60 months starting from the date

excluding the monsoon period; (b) by Clauses 5 and 17, SevenHills

could mortgage the property for securing advances from financial

institutions   for   the   construction   of   the   project   and   thereafter

towards its working. Such mortgage/charge or interest was subject

to   approval   by   MCGM.   In   the   event   the   contract   was   to   be

terminated, it was agreed that MCGM would not in any manner be

liable   towards   the   mortgaged   amount   and   all   its   rights   and

33

ownership would continue to vest in it free from encumbrances

(Clause 17).

33.The show cause notice in this case preceded admission of the

insolvency   resolution   process.     In   view   of   the   clear   conditions

stipulated in the contract, MCGM reserved all its rights and its

properties could not have therefore, in any manner, been affected

by the resolution plan.   Equally in the opinion of this Court, the

adjudicating authority could not have approved the plan which

implicates the assets of MCGM especially when SevenHills had not

fulfilled its obligations under the contract.

34.The argument of the RP, the financial institutions (CoC), and

the SNMC with regard to MCGM's interest not being affected, in this

court's opinion is insubstantial.  SNMC's proposed insolvency plan

on the one hand no doubt provided for the liquidation of MCGM’s

liabilities initially to the tune of  102 crores (later revised to over

140 crores).  However, the provisions of the resolution plan clearly

contemplated infusion of capital to achieve its objectives. One of the

modes spelt out in the plan for securing capital was mortgaging the

34

land.     Initially,   no   doubt,   SNMC   stepped   into   the   shoes   of

SevenHills and assumed its control.  What is important to notice is

that the corporate restructuring was a way of taking over of the

company’s liquidation by SNMC as it was not only Seven Hills’

project   with   shares   and   liquidation   of   debts,   but   also   the

restructuring of the company’s liabilities if necessary, by creating

fresh debts and mortgage of the land which directly affected MCGM.

35.Section   92   unequivocally   prescribes   the   method   whereby

MCGM’s properties can be dealt with through lease or by way of

creation of any other interest.  The only mode permitted is through

prior permission of the corporation.  It is a matter of record that in

the present case, the resolution plan was never approved by the

corporation and that it was put to vote.    The contesting parties,

including the RP and CoC were unable to point out to anything on

the record to establish that a valid permission contemplated by

Section 92 was ever obtained with regard to the proposal in the

resolution   plan.   The   proposal   was   approved   by   the   NCLT   and

MCGM’s appeal was rejected by NCLAT. The proposal could be

35

approved only to the extent it did not result in encumbering the

land belonging to MCGM.

36.It is evident from a plain reading of Section 92(c), that the

Commissioner (of MCGM) is empowered to, with the sanction of the

corporation, “lease, sell or otherwise convey any immovable property

belonging to the corporation.”   It is not in dispute that the original

contract entered into on 20­12­2005 contemplated the fulfilment of

some important conditions, including firstly, the completion of the

hospital project within a time frame; and secondly, timely payment

of annual lease rentals. It is a matter of record that the hospital

project was scheduled to be completed by 24

th

 April, 2013. MCGM

cites Clause 15(g) of the contract to urge that within a month of this

event,   i.e.   completion   of   the   hospital,   a   lease   deed   had   to   be

executed. This event never took place. Therefore, the terms of the

contract remained, in the opinion of the court, an agreement to

enter into a lease; it did not  per se  confer any right or interest,

except that in the event of MCGM’s failure or omission to register

the lease (in the event SevenHills had complied with its obligations

36

under the contract), it could be sued for specific performance of the

agreement, and compelled to execute a lease deed. That event did

not occur; SevenHills did not complete construction of the 1600 bed

hospital. Apparently, it did not even fulfill its commitment, or pay

annual   lease   rentals.   In   these   circumstances,   MCGM   was

constrained to issue a show cause notice  before the insolvency

resolution process began, and before the moratorium was declared

by NCLT on 13   

th

    March, 2018. According to MCGM, in terms of

Clause 26 (of the contract), even the agreement stood terminated

due   to   default   by   SevenHills.   This   court   does   not   propose   to

comment on that issue, as that is contentious and no finding has

been recorded by either the adjudicating authority or the NCLAT.

37.In  Ram Singh Vijay Pal Singh & Ors. v. State of U.P. & Ors

(2007) 6 SCC 44, this court dealt with a similar provision, requiring

prior approval of the statutory authority without which the property

could not be disposed of. The court held that:

"The proviso to Sub­section (1) of Section 12 of the

Act would show that the Mandi Samiti (Committee)

is   not   empowered   to   transfer   any   immovable

37

property without the previous approval in writing

of the State Agricultural Produce Markets Board

(Mandi Parishad). Section 26­L of the Act deals

with the powers and functions of the Board. The

Director of Mandi Parishad (Board) has not been

conferred any power whereunder he may issue a

general   direction   that   the   shops,   godowns   and

sheds of the Mandi Parishad shall be transferred

or   sold   to   the   traders   on   hire­purchase   basis.

Therefore,   the   appellants   can   derive   no   benefit

from the letter of the Director dated 4.11.1995,

wherein it  was  mentioned that  a  decision had

been taken to give the shops on hire­purchase

basis.   In   the   counter   affidavit   the   respondents

have specifically asserted that the Board never

took any such decision to sell the property of the

Mandi   Samiti   to   the   traders   either   on   hire­

purchase basis or otherwise. No document has

been filed to show that the Board ever took any

such decision. It is the case of the respondents

that the letter sent by the Director was his own

action which had never been authorized by the

Board.   At   any   rate   the   proposal   made   by   the

Director never fructified as no such decision was

taken   by   the   Board   and   the   Board   never

authorized   the   Mandi   Samities   (Committees)   of

various   districts   in   the   State   to   transfer   the

property of the Samiti in favour of the traders of

agricultural produce who had been allotted the

shops,   godowns   and   sheds   by   the   Mandi

Parishad. In this view of the matter, the appellants

38

have no legal right to claim that the property be

given to them on hire­purchase basis."

38.In Essar Bulk Terminal Limited & Anr. v. State of Gujarat &

Ors. (2018) 3 SCC 750, again, this court held as follows:

"16. Despite this, what is clear from the record is

that   the   Appellants   appear   to   have   actually

dredged the channel to a depth of 14 meters and

appear to have reclaimed an area of 164 hectares

plus 170 hectares to the south of the mangroves,

without   any   permission   at   all.   When   this   was

pointed out to Shri Mihir Joshi, the answer given

was   that   when   permission   is   granted   Under

Section 35(1) of the Gujarat Maritime Board Act, a

letter granting such permission specifically says

that it is permission that is granted Under Section

35(1)  and  for  this purpose, a  letter  dated 2nd

August, 2008 was referred to. According to him,

therefore, the letter dated 14th June, 2007, which

referred only to an NOC for reclamation, could not

be given the status of permission Under Section

35(1). According to the learned Counsel, therefore,

if Section 35(1) were to be read with Section 35(2),

it would be clear that permission for reclamation

would only be necessary if a private asset were to

be   created   in   the   hands   of   a   private   person.

However, it is clear that the asset to be created

belonged only to the Government of Gujarat and it

was   for   the   GMB   to   grant   permission   to   the

39

Appellants to use the same. We are afraid that it is

difficult for  us  to accept this  line of  argument.

Section 35(1) is couched in negative language and

does   not   refer   to   private   rights   being   created.

Section 35(2) cannot be read so as to throw light

on Section 35(1), as Under Section 35(2), the GMB

is only given a discretionary power to require a

person, who has acted in contravention of Section

35(1),   to   remove   the   illegal   erection.   The   wide

language of Section 35(1) cannot be whittled down

by Section 35(2) in the manner argued by Shri

Joshi, as the GMB may or may not utilise the

discretionary power granted to it Under Section

35(2). The plain language of Section 35(1) cannot

be curtailed by reading by inference, into Sub­

section (2), the fact that the GMB may, by notice,

require a person to remove an erection, only when

it has been made without previous permission, so

as to create a private asset in the hands of a

private person. The wide language of Section 35(1)

makes it clear that any reclamation within the

limits of the GMB cannot be carried out except with

the previous permission in writing of the GMB. It is

clear, therefore, that dredging to a depth of below

8 meters and reclamation of any area to the south

of the mangroves was done by the Appellants in

the teeth of Section 35(1) of the Gujarat Maritime

Board Act.

17. Mr. Sibal laid great stress on the letter dated

15th November, 2012 to show that, in point of fact,

what the Appellants were really angling for was to

40

conduct commercial operations beyond the captive

requirements of the Essar Steel plant at Hazira.

This letter, while asking for an addition of 3700

meters in addition to the existing 1100 meters

waterfront, also went on to speak of developing a

700   meters   berth,   along   with   the   GMB,   for

handling commercial cargo. Apart from this, Essar

planned to build a world class container terminal

and a dry dock, which would serve the shipping

industry generally. It also proposed to reclaim a

further 334 hectares land on the southern side

with the additional dredged material. A perusal of

this letter would leave no doubt about the fact that

despite Essar Steel's production being at much

less   than   what   was   projected,   the   Appellants'

continued   demands   would   show   that   the   real

motive was to go beyond a captive jetty and to

develop   a   commercial   port   which,   as   we   have

seen,   cannot   be   done   without   a   global   tender

under the Gujarat Infrastructure Development Act.

18.   As   stated   hereinabove,   as   many   as   three

MOUs were executed between the Appellants, the

GMB   and   the   State   Government,   which   MOUs

were valid only for a period of 12 months and

were stated not to have granted any right to the

Appellants, who would incur all the expenditure

for the same. This being the case, it is a little

difficult to appreciate Shri Joshi's contention that

any legitimate expectation could be based on any

of the aforesaid expired MOUs. The High Court is

correct in its conclusion that no such expectation

41

could possibly have arisen out of the aforesaid

MOUs   or   the   correspondence   between   the

Appellants   and   the   GMB   referred   to.

19.   It   is   also   important   to   note   from   the

correspondence between the Appellants and the

GMB, that the Appellants were clearly told that the

land to be reclaimed by the Appellants would not

only belong to the Government of Gujarat, but also

that the GMB could utilize the aforesaid land for

any purpose. What seems to emerge on a reading

of   the   letters   between   the   parties   is   that   the

Appellants wished to dredge the canal, at their

own cost, which was next to their captive jetty, for

their own purposes, for which they obtained the

necessary permission. However, since dumping of

earth, which would emerge as a consequence of

dredging, into the open sea would be extremely

expensive, it was stated that instead this earth

could be dumped to create reclaimed land next to

the captive jetty, which would then benefit both

the Appellants and the GMB. In point of fact, 140

hectares out of 195 hectares that is reclaimed by

the Appellants is allocated to the Appellants for

their own purposes, the balance to be given as

and when a jetty of 1100 meters plus 3700 meters

of waterfront is constructed. The argument that

huge amounts had been spent to reclaim land is

wholly   fallacious­huge   amounts   were   spent   to

dredge   a   canal   which   was   permitted   as   the

Appellants alone were to bear the cost, and as an

42

increased draft would benefit all, as the canal

was open to all to use. Therefore, any plea as to a

legitimate   expectation   of   reclaimed   land   being

allocated for the Appellants' own use, thanks to

large   amounts   being   spent,   is   contrary   to   the

correspondence by the Appellants themselves."

An identical approach was adopted in Saroj Screens Pvt. Ltd. v

Ghanshyam & Ors., (2012) 11 SCC 434.

39.The principle that if a statute requires a thing to be done in a

particular manner, it should be done in that manner or not at all,

articulated in Nazir Ahmad v. Emperor, AIR 1936 PC 253, has found

widespread acceptance. In the context of this case, it means that if

alienation   or   creation   of   any   interest   in   respect   of   MCGM’s

properties   is   contemplated   in   the   statute   through   a   particular

manner, that end can be achieved only through the prescribed

mode, or not at all.

40.This Court also notices that an initial No Objection Certificate

was issued by MCGM voluntarily, for creation of interest in respect

of its properties. Upon its refusal to grant approval, SevenHills filed

proceedings under Article 226 before the Bombay High court (W.P.

43

No 1728 of 2011), in which the Court directed to grant issuance of

certificate. At the same time, the High Court observed as follows: 

"11. ...... It is, however, required to be noted here

that the Corporation is nor borrowing any amount

for its purpose....If the petitioners want financial

assistance   from   the   Bank,   naturally,   it   cannot

mortgage only the superstructure but the entire

property is required to be mortgaged. Aprart from

that even if there is a defect in the title in the

matter of creating mortgage, the Corporation is not

going to suffer in any manner and it is for the

concerned Bank to consider the same while giving

financial assistance. The Corporation is not going

to get any financial assistance from the Bank and,

therefore,   whatever   documents   which   the

petitioners may execute in favour of the Bank, the

Corporation is not bound by the same....The said

NOC can be granted by the Corporation without

prejudice to its rights and contentions that the

land in question belongs to them and, therefore, no

mortgage could have been created for the same. It

is always open to the Corporation to ascertains

right to the extent that they are not bound by

execution   of   such   documents   with   the

Bank....However, such grant of NOC, would be

without prejudice to the rights and contentions of

the   Corporation.   The   Corporation   may   also

mention   such   aspect   while   giving   NOC   to   the

petitioners   that   such   NOC   is   given   without

prejudice to the rights and contentions that their

44

land   could   not   have   been   mortgaged   by   the

petitioners with the Bank. (emphasis supplied)

12. ......Apart from the same, by granting NOC it

cannot be construed that the Corporation has also

mortgaged its property in favour of Axis Bank in

any manner....

15.   ....It   is   clarified   that   this   order   is   passed

without prejudice to the rights and contentions of

both the sides and it will have no effect so far as

deciding the matter on merit is concerned.....”

***************                         *************

41.The material placed on record by MCGM before this Court also

reveals that the meeting held by the Corporation on 14

th

 December,

2018, referred back to the resolution proposal given by SNMC. The

minutes   of   the   meeting   records   that   three   members   were

unanimous in their view that since SevenHills had not complied

with the terms and had even sought to encumber the property by

mortgage, SNMC, a UAE based company, ought not be granted

approval to take over the plot and proceed with its project.

42.Now, this court proposes to deal with the contention that the

provisions of the Code override all other laws and hence, that the

45

resolution plan approved by the NCLT acquires primacy over all

other  legal  provisions.  Facially,  this  argument  appears merited.

Section 238 enacts that: 

“238.   Provisions   of   this   Code   to   override   other

laws. — The provisions of this Code shall have

effect,   notwithstanding   anything   inconsistent

therewith contained in any other law for the time

being in force or any instrument having effect by

virtue of any such law.”

43.The scope of this provision has been the subject matter of

debate   in   several   judgments   of   this   court.   In  Jaipur   Metals   &

Electricals Employees Organization v. Jaipur Metals & Electricals Ltd.

(2019) 4 SCC 227, the correctness of a High Court’s view which

refused to transfer winding up proceedings pending before it and set

aside  the   NCLT’s   order   admitting   an   insolvency   resolution

application at the behest of a financial creditor, was in issue. This

court held as follows, setting aside the judgment impugned in that

case:

“It   is   clear   that   Respondent   No.   3   has   filed   a

Section   7   application   under   the   Code   on

11.01.2018, on which an order has been passed

46

admitting   such   application   by   the   NCLT   on

13.04.2018.   This  proceeding  is   an   independent

proceeding   which   has   nothing   to   do   with   the

transfer of pending winding up proceedings before

the High Court. It was open for Respondent No. 3

at any time before a winding up order is passed to

apply under Section 7 of the Code. This is clear

from a reading of Section 7 together with Section

238 of the Code which reads as follows:

“238. Provisions of this Code to override

other laws. — The provisions of this Code

shall   have   effect,   notwithstanding

anything inconsistent therewith contained

in any other law for the time being in force

or any instrument having effect by virtue

of any such law.”

18.   Shri   Dave’s   ingenious   argument   that   since

Section   434   of   the   Companies   Act,   2013   is

amended by the Eleventh Schedule of the Code,

the amended Section 434 must be read as being

part of the Code and not the Companies Act 2013,

must be rejected for the reason that though Section

434 of the Companies Act, 2013 is substituted by

the  Eleventh  Schedule  of  the  Code,  yet  Section

434,   as   substituted,   appears   only   in   the

Companies Act, 2013 and is part and parcel of that

Act. This being so, if there is any inconsistency

between   Section   434   as   substituted   and   the

provisions of the Code, the latter must prevail. We

are   of   the   view   that   the   NCLT   was   absolutely

47

correct in applying Section 238 of the Code to an

independent   proceeding   instituted   by   a   secured

financial   creditor,   namely,   the   Alchemist   Asset

Reconstruction Company Ltd. This being the case,

it is difficult to comprehend how the High Court

could have held that the proceedings before the

NCLT   were   without   jurisdiction.   On   this   score,

therefore, the High Court judgment has to be set

aside.”

44. In the recent judgment in Duncans Industries v. A.J. Agrochem

2019   SCC   Online   (SC)   1319,   the   issue   was   that  action   under

Section 16D(4) of the Tea Act, which provides that the Central

Government could take such steps as may be necessary for the

purpose of efficiently managing the business of the undertaking,

had been taken. It was urged that any notification under Section

16D has effect for five years, which could only be extended if the

Central Government was of the opinion that it is expedient to do so

in public interest, for such period not exceeding one year at a time,

and for total period not exceeding six years. It was submitted that

Section  16E  refers to the  power of  the  Central  Government  to

restart the tea undertaking if it is found necessary in the interest of

48

the general public. The argument was that an insolvency process is

also meant to culminate in liquidation, if there is no revival, and

that since the Tea Act permits  the Central Government to take over

the management of a tea estate which is not run properly, prior

permission under Section 16G is applicable to such an estate, the

management of which has been taken over by the Government. This

contention was negatived, by this court, which relied on Section

238 of the Code.

45.In Macquaire Bank Ltd. v. Shilipi Cable Techologies Ltd. (2018)

2 SCC 674, one of the issues was the interplay between Section 9 of

the Code and provisions of the Advocates Act. It was argued that a

demand notice issued through an advocate was not permissible and

that the provisions of the Code overrode all other laws. This court

negative   the   contention,   holding   that   it   is   only   in   the   case   of

inconsistency, that by reason of Section 238 of the Code would its

provisions prevail. On a harmonious construction of the seemingly

inconsistent provisions, if the court could give effect to both, it

would do so.

49

46.Dharani Sugars & Chemicals Ltd. v. Union of India & Ors.

(2019) 5 SCC 480 is a relevant recent decision of this court. The

question   which   arose   in   that   case   was   the   legality   and

constitutionality of directions issued by the Reserve Bank of India,

through a circular of 12

th

 February, 2018 regulating resolution of

stressed   assets   of   debtors.   This   court   elaborately   dealt   with

provisions of the Banking Regulation Act, 1949 and the Reserve

Bank of India Act, 1934 and held that the power to issue directions

regarding initiation of insolvency proceedings vested in the RBI,

subject   to   the   approval   of   the   Central   Government.   The   court

significantly held that the power was contained “within the four

corners” of Section 35AA and observed as follows:

“A conspectus of all these provisions shows that

the   Banking   Regulation   Act   specifies   that   the

Central Government is either to exercise powers

along with the RBI or by itself. The role assigned,

therefore,   by   Section   35AA,   when   it   comes   to

initiating the insolvency resolution process under

the Insolvency Code, is thus, important. Without

authorisation   of   the   Central   Government,

obviously, no such directions can be issued.

50

30.   The   corollary   of   this   is   that   prior   to   the

enactment   of   Section   35AA,   it   may   have   been

possible to say that when it comes to the RBI

issuing directions to a banking company to initiate

insolvency resolution process under the Insolvency

Code, it could have issued such directions Under

Sections 21 and 35A. But after Section 35AA, it

may do so only within the four corners of Section

35AA.

31. The matter can be looked at from a slightly

different angle. If a statute confers power to do a

particular act and has laid down the method in

which   that   power   has   to   be   exercised,   it

necessarily prohibits the doing of the act in any

manner   other   than   that   which   has   been

prescribed. This is the well­known Rule in Taylor

v. Taylor, [1875] 1 Ch. D. 426, which has been

repeatedly followed by this Court. Thus, in State of

U.P. v. Singhara Singh, (1964) 4 SCR 485, this

Court held:

‘The   Rule   adopted   in   Taylor   v.   Taylor

[(1875) 1 Ch D 426, 431] is well recognised

and is founded on sound principle. Its result

is that if a statute has conferred a power to

do an act and has laid down the method in

which that power has to be exercised, it

necessarily prohibits the doing of the act in

any other manner than that which has been

prescribed. The principle behind the Rule is

that   if   this   were   not   so,   the   statutory

provision   might   as   well   not   have   been

51

enacted. A Magistrate, therefore, cannot in

the   course   of   investigation   record   a

confession except in the manner laid down

in  Section  164.  The  power  to  record  the

confession had obviously been given so that

the   confession   might   be   proved   by   the

record of it made in the manner laid down.

If proof of the confession by other means

was   permissible,   the   whole   provision   of

Section   164   including   the   safeguards

contained in it for the protection of Accused

persons would be rendered nugatory. The

section,   therefore,   by   conferring   on

Magistrates the power to record statements

or   confessions,   by   necessary   implication,

prohibited   a   Magistrate   from   giving   oral

evidence of the statements or confessions

made to him. (at pp. 490­491)

Following this principle, therefore, it is clear that

the   RBI   can   only   direct   banking   institutions   to

move under the Insolvency Code if two conditions

precedent are specified, namely, (i) that there is a

Central Government authorisation to do so; and (ii)

that it should be in respect of specific defaults. The

Section,   therefore,   by   necessary   implication,

prohibits this power from being exercised in any

manner other than the manner set out in Section

35AA.”

52

47.In the opinion of this court, Section 238 cannot be read as

overriding the MCGM’s right – indeed its public duty ­ to control

and regulate how its properties are to be dealt with. That exists in

Sections 92 and 92A of the MMC Act. This court is of opinion that

Section 238 could be of importance when the properties and assets

are of a debtor  and not when a third party like the MCGM is

involved. Therefore, in the absence of approval in terms of Section

92 and 92A of the MMC Act, the adjudicating authority could not

have overridden MCGM’s objections and enabled the creation of a

fresh interest in respect of its properties and lands. No doubt, the

resolution   plans   talk   of   seeking   MCGM’s   approval;   they   also

acknowledge the liabilities of the corporate debtor; equally, however,

there   are   proposals   which   envision   the   creation   of   charge   or

securities   in   respect   of   MCGM’s   properties.   Nevertheless,   the

authorities under the Code could not have precluded the control

that MCGM undoubtedly has, under law, to deal with its properties

and the land in question­ which undeniably are public properties.

The resolution plan therefore, would be a serious impediment to

53

MCGM’s independent plans to ensure that public health amenities

are   developed   in   the   manner   it   chooses,   and   for   which   fresh

approval under the MMC Act may be forthcoming for a separate

scheme formulated by that corporation (MCGM).

48.The last contention of the respondents, that MCGM was bound

by the statement made by its counsel, in the opinion of this court,

cannot prevail. As held earlier, there is no approval for the plan, in

accordance   with   law;   in   such   circumstances,   the   written   plea

accepting the plan, by a counsel or other representative who is not

demonstrated to possess the power to bind MCGM, is inconclusive.

In this regard, the court notices the well­known principle that there

can be no estoppel against the express provisions of law. (Ref.

Kasinka Trading v. Union of India (1995) 1 SCC 274, Darshan Oils

(P) Ltd. v. Union of India (1995) 1 SCC 345, Shrijee Sales Corporation

v. Union of India  (1997) 3 SCC 398,  Shree Sidhbali Steels Ltd. v.

State of U.P.  (2011) 3 SCC 193,  Pappu Sweets and Biscuits v.

54

Commr.   of   Trade   Tax,   U.P.  (1998)   7   SCC   228   and  Commr.   of

Customs v. Dilip Kumar & Co. (2018) 9 SCC 1.)

49.In view of the foregoing reasons, this court holds that the

impugned order and the order of the NCLT cannot stand; they are

hereby set aside. The appeal is accordingly allowed, without orders

on costs.

........................................J.

                                           [ARUN MISHRA] 

........................................J.

                                           [VINEET SARAN] 

........................................J.

                                          [S. RAVINDRA BHAT] 

New Delhi,

November 15 , 2019.

Reference cases

Description

Legal Notes

Add a Note....