As per the case facts, appeals were filed challenging a Delhi High Court order that appointed an arbitrator under Section 11(6) of the Arbitration & Conciliation Act 1996, stemming from ...
2024 INSC 218 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.___________OF 2024
[Arising out of Special Leave Petition (Civil) Nos.7573-7574 of
2021]
NBCC (INDIA) LIMITED ...APPELLANT (S)
VERSUS
ZILLION INFRAPROJECTS PVT.LTD. ...RESPONDENT (S)
J U D G M E N T
B.R. GAVAI, J.
1. Leave granted.
2. The present appeals challenge the interim order dated 12
th
March 2021 and final judgment & order dated 9
th April 2021,
passed by the learned Single Judge of the High Court of Delhi
(hereinafter, “High Court”), in Arbitration Petition (Arb. P.) No. 44
2
of 2021, whereby the High Court allowed the application under
Section 11(6) of the Arbitration & Conciliation Act 1996
(hereinafter referred to as, “the Arbitration Act”) and appointed
the Sole Arbitrator to adjudicate the dispute between the parties
to the present lis, arising from the Letter of Intent dated 4
th
December 2006.
3. Facts, in brief, giving rise to the present appeals are as
follows:
3.1 The appellant, NBCC (India) Limited (Formerly known as
National Buildings Construction Corporation Ltd.), is a Public
Limited Company and Government of India undertaking,
engaged in construction of power plants and other infrastructure
projects on EPC and/or PMC basis.
3.2 The respondent, M/s Zillion Infraprojects Pvt. Ltd.
(Formerly known as Durha Constructions Pvt. Ltd.), is a Private
Limited Company, engaged in the construction and
infrastructure sector.
3
3.3 The appellant issued an invitation for tender, being NIT No.
01-WEIR/06 dated 3
rd November 2006, for “Construction of Weir
with Allied Structures across river Damodar at DVC, CTPS,
Chandrapura, Dist – Bokaro, Jharkhand – Package “A”
(hereinafter referred to as, “Construction of the Weir”), containing
inter-alia, the General Conditions of Contract, Special Conditions
of Contract, Bill of Quantity, etc. (collectively referred to as,
“Tender Documents”).
3.4 In response to the aforementioned tender, the Respondent
submitted its Techno Commercial Bid on 16
th November 2006.
3.5 On fulfilment of the tender criteria, vide Letter of Intent No.
AGM/RAN/CTPS -AWARD/06/1660 dated 4
th December 2006,
the appellant awarded the contract for Construction of the Weir
to the respondent for a total value of Rs. 19,08,46,612/-.
3.6 With the passage of time, certain disputes arose between
the parties to the present lis & as a result, the respondent issued
a notice dated 6
th March 2020, in terms of Clause 3.34 of Section
III Volume II of the Tender Documents (GCC), thereby invoking
4
arbitration and further seeking consent of the appellant for the
appointment of a former Judge of a High Court, as Sole
Arbitrator.
3.7 The appellant did not respond to the aforementioned notice
invoking arbitration, so the respondent filed an application at the
High Court under Section 11(6) of the Arbitration Act.
3.8 Vide interim order dated 12
th March 2021, the High Court
allowed the Arbitration Petition and proposed the appointment
of a former Judge of the High Court, as the Sole Arbitrator, to
adjudicate the dispute between the parties.
3.9 Vide final judgment & order dated 9
th April 2021, the High
Court confirmed the proposed appointment of the former Judge
of the Delhi High Court, as the Sole Arbitrator.
3.10 Aggrieved by the orders of the learned single judge of the
High Court, the appellant filed the present appeals thereby
challenging both the interim order and the final judgement &
order.
5
3.11 This Court vide order dated 23
rd July, 2021, issued notice
and stay of further proceedings of the arbitration was granted.
4. We have heard Shri Gopal Sankaranarayanan, learned
Senior Counsel appearing on behalf of the appellant & Shri Sumit
Kumar, learned counsel appearing on behalf of the respondent.
5. Shri Gopal Sankaranarayanan , learned Senior Counsel
appearing for the appellant submits that the High Court has
grossly erred in invoking its power under Section 11(6) of the
Arbitration Act. It is submitted that Clause 2.0 of the Letter of
Intent dated 4
th December 2006 (“L.O.I.” for short) though states
that all terms and conditions as contained in the tender issued
by the Damodar Valley Corporation (“DVC” for short) to the NBCC
shall apply mutatis mutandis, it also makes it clear that where
the terms and conditions have been expressly modified by the
NBCC, the same would not be applicable. It is submitted that
Clause 1.0 of the L.O.I. specifically states that various conditions,
i.e., contractual, financial and technical mentioned in the
documents contained therein shall be binding on the respondent
6
for execution of works and they shall form part of the agreement.
Clause 10.0 also states that the L.O.I. shall also form a part of
the agreement. It is submitted that the intention is amply clear
from Clause 7.0 of the L.O.I., which states that the redressal of
dispute between the NBCC and the respondent shall only be
through civil courts having jurisdiction of Delhi alone. It further
states that the laws applicable to the contract between the parties
shall be the laws enforceable in India. It is submitted that merely
on account of reference in the L.O.I. to the terms and conditions
as contained in the tender issued by the DVC to the NBCC,
Clause 3.34 of the Additional Terms & Conditions of Contract
would not apply in view of specific modification as stated in
Clause 2.0 of the L.O.I.
6. Learned Senior Counsel submits that a mere reference to
the terms and conditions without there being an incorporation in
the L.O.I. would not make the lis between the parties amenable
to the arbitration proceedings. Relying on the judgment of this
Court in the case of M.R. Engineers and Contractors Private
7
Limited vs. Som Datt Builders Limited
1, he submits that
unless the L.O.I. specifically provides for incorporation of the
arbitration clause, a reference to the arbitration proceedings
would not be permitted in view of the provisions of sub-section
(5) of Section 7 of the Arbitration Act.
7. Shri Sumit Kumar, learned counsel appearing for the
respondent, on the contrary, submits that there is a specific
reference in Clause 2.0 of the L.O.I. to the terms and conditions
in the tender issued by the DVC to the NBCC. He submits that
the only modification is that under Clause 3.34 of the Additional
Terms & Conditions of Contract, the jurisdiction is vested with
the Court in the City of Kolkata only, whereas in the L.O.I. the
jurisdiction would be vested in the civil courts having jurisdiction
of Delhi alone. It is submitted that the learned single judge of
the Delhi High Court has rightly considered this aspect and as
such, no interference would be warranted in the impugned order.
1
(2009) 7 SCC 696
8
8. Sub-section (5) of Section 7 of the Arbitration Act reads
thus:
“7. Arbitration Agreement.-1)……………….
xxx xxx xxx
(5) The reference in a contract to a
document containing an arbitration clause
constitutes an arbitration agreement if the
contract is in writing and the reference is
such as to make that arbitration clause part
of the contract.”
9. The issue is no more res integra. The provisions of sub-
section (5) of Section 7 of the Arbitration Act have been
considered by this Court in the case of M.R. Engineers and
Contractors Private Limited (supra). After considering the
relevant passages from Russell on Arbitration and various English
judgments, this Court held thus:
“24. The scope and intent of Section 7(5) of
the Act may therefore be summarised thus:
(i) An arbitration clause in another
document, would get incorporated into a
contract by reference, if the following
conditions are fulfilled:
9
(1) the contract should contain a
clear reference to the documents
containing arbitration clause,
(2) the reference to the other
document should clearly indicate an
intention to incorporate the
arbitration clause into the contract,
(3) the arbitration clause should be
appropriate, that is capable of
application in respect of disputes
under the contract and should not be
repugnant to any term of the contract.
(ii) When the parties enter into a
contract, making a general reference to
another contract, such general reference
would not have the effect of incorporating
the arbitration clause from the referred
document into the contract between the
parties. The arbitration clause from
another contract can be incorporated
into the contract (where such reference is
made), only by a specific reference to
arbitration clause.
(iii) Where a contract between the
parties provides that the execution or
performance of that contract shall be in
terms of another contract (which
contains the terms and conditions
relating to performance and a provision
for settlement of disputes by arbitration),
then, the terms of the referred contract
in regard to execution/performance
10
alone will apply, and not the arbitration
agreement in the referred contract,
unless there is special reference to the
arbitration clause also.
(iv) Where the contract provides that
the standard form of terms and
conditions of an independent trade or
professional institution (as for example
the standard terms and conditions of a
trade association or architects
association) will bind them or apply to
the contract, such standard form of
terms and conditions including any
provision for arbitration in such
standard terms and conditions, shall be
deemed to be incorporated by reference.
Sometimes the contract may also say
that the parties are familiar with those
terms and conditions or that the parties
have read and understood the said terms
and conditions.
(v) Where the contract between the
parties stipulates that the conditions of
contract of one of the parties to the
contract shall form a part of their
contract (as for example the general
conditions of contract of the Government
where the Government is a party), the
arbitration clause forming part of such
general conditions of contract will apply
to the contract between the parties.”
11
10. It could thus be seen that this Court has held that when the
parties enter into a contract, making a general reference to
another contract, such general reference would not have the
effect of incorporating the arbitration clause from the referred
document into the contract between the parties. It has been held
that the arbitration clause from another contract can be
incorporated into the contract (where such reference is made),
only by a specific reference to arbitration clause. It has further
been held that where a contract between the parties provides that
the execution or performance of that contract shall be in terms
of another contract (which contains the terms and conditions
relating to performance and a provision for settlement of disputes
by arbitration), then, the terms of the referred contract in regard
to execution/performance alone will apply, and not the
arbitration agreement in the referred contract, unless there is
special reference to the arbitration clause also.
11. This Court further held that where the contract provides
that the standard form of terms and conditions of an independent
12
trade or professional institution will bind them or apply to the
contract, such standard form of terms and conditions including
any provision for arbitration in such standard terms and
conditions, shall be deemed to be incorporated by reference. It
has been held that sometimes the contract may also say that the
parties are familiar with those terms and conditions or that the
parties have read and understood the said terms and conditions.
It has also been held that where the contract between the parties
stipulates that the conditions of contract of one of the parties to
the contract shall form a part of their contract, the arbitration
clause forming part of such general conditions of contract will
apply to the contract between the parties.
12. A perusal of sub-section (5) of Section 7 of the Arbitration
Act itself would reveal that it provides for a conscious acceptance
of the arbitration clause from another document, by the parties,
as a part of their contract, before such arbitration clause could
be read as a part of the contract between the parties.
13
13. It is thus clear that a reference to the document in the
contract should be such that shows the intention to incorporate
the arbitration clause contained in the document into the
contract.
14. The law laid down in the case of M.R. Engineers and
Contractors Private Limited (supra) has been followed by this
Court in the cases of Duro Felguera, S.A. vs Gangavaram Port
Limited
2 and Elite Engineering and Construction
(Hyderabad) Private Limited represented by its Managing
Director vs Techtrans Construction India Private Limited
represented by its Managing Director
3.
15. No doubt that this Court in the case of Inox Wind Limited
vs Thermocables Limited
4 has distinguished the law laid down
in the case of M.R. Engineers and Contractors Private Limited
(supra). In the said case (i.e. Inox Wind Limited), this Court has
held that though general reference to an earlier contract is not
2
(2017) 9 SCC 729
3
(2018) 4 SCC 281
4
(2018) 2 SCC 519
14
sufficient for incorporation of an arbitration clause in the later
contract, a general reference to a standard form would be enough
for incorporation of the arbitration clause. Though this Court in
the case of Inox Wind Limited (supra) agrees with the judgment
in the case of M.R. Engineers and Contractors Private Limited
(supra), it holds that general reference to a standard form of
contract of one party along with those of trade associations and
professional bodies will be sufficient to incorporate the
arbitration clause. In the said case (i.e. Inox Wind Limited), this
Court found that the purchase order was issued by the appellant
therein in which it was categorically mentioned that the supply
would be as per the terms mentioned therein and in the attached
standard terms and conditions. The respondent therein by his
letter had confirmed its acceptance. This Court found that the
case before it was a case of a single-contract and not two-contract
case and, therefore, held that the arbitration clause as mentioned
in the terms and conditions would be applicable.
15
16. The present case is a ‘two-contract’ case and not a ‘single-
contract’ case.
17. It will be relevant to refer to Clause 3.34 of the Additional
Terms & Conditions of Contract as contained in the tender issued
by the DVC to the NBCC. Clause 3.34 reads thus:
“3.34 SETTLEMENT OF DISPUTES &
ARBITRATION
Any dispute(s) or difference(s) arising out of or
in connection with the contract shall to the
extent possible be settled amicably between
the owner and supplier/contractor.
In the event of any dispute or difference
whatsoever arising under the contract or in
connection therewith including any question
relating to existence meaning and
interpretation of the contract or any alleged
breach thereof the same shall be referred to
the sole arbitration of the Secretary, CEO of
Damodar Valley Corporation, Kolkata-54 or to
a person appointed by him for that purpose.
The arbitration shall be conducted in
accordance with the provisions of arbitration
and conciliation law 1996 and the
decision/judgment of Arbitrator shall be final
and binding on both the parties.
16
All suits arising out of this enquiry and
subsequent purchase order, if any, are
subject jurisdiction of court in the City of
Kolkata only and no other door when
resolution/settlement through mutual
discussion and arbitration fails.”
18. No doubt that Clause 3.34 provides for a reference of the
dispute to the sole arbitration of the Secretary, CEO of Damodar
Valley Corporation, Kolkata-54 or to a person appointed by him
for that purpose.
19. It will also be apposite to refer to Clauses 1.0, 2.0, 7.0 and
10.0 of the L.O.I., which read thus:
“1.0 The work shall be executed you on
contractual, financial and technical
conditions of contract as contained in
the following documents which shall
be applicable and binding on you for
execution of works and shall form part
of agreement with you as also
mentioned in the above mentioned
NIT-01/WEIR/06 dated November 3,
2006.
(a) Notice Inviting Tender
(b) General Conditions of Contract
(c) Special Conditions of Contract
(d) Bill of Quantity
17
2.0 All terms and conditions as contained
in the tender issued by DVC to NBCC
shall apply mutatis mutandis except
where these have been expressly
modified by NBCC.
7.0 The redressal of dispute between
NBCC and you shall only be through
civil courts having jurisdiction of Delhi
alone. The laws applicable to this
contract shall be the laws enforceable
in India.
10.0 This letter of intent shall also form a
part of the agreement.
20. In view of Clause 1.0, the documents stated therein shall
also form part of the agreement. In view of Clause 2.0, all terms
and conditions as contained in the tender issued by the DVC to
the NBCC shall apply mutatis mutandis except where these have
been expressly modified by the NBCC. Clause 7.0 specifically
provides that the redressal of dispute between the NBCC and the
respondent shall only be through civil courts having jurisdiction
of Delhi alone. Clause 10.0 further provides that the L.O.I. shall
also form a part of the agreement.
18
21. It is thus clear that the intention between the parties is very
clear. Clause 7.0 of the L.O.I. which also forms part of the
agreement specifically provides that the redressal of the dispute
between the NBCC and the respondent shall only be through civil
courts having jurisdiction of Delhi alone. It is pertinent to note
that Clause 7.0 of the L.O.I. specifically uses the word “only”
before the words “be through civil courts having jurisdiction of
Delhi alone”.
22. As already discussed herein above, when there is a
reference in the second contract to the terms and conditions of
the first contract, the arbitration clause would not ipso facto be
applicable to the second contract unless there is a specific
mention/reference thereto.
23. We are of the considered view that the present case is not a
case of ‘incorporation’ but a case of ‘reference’. As such, a general
reference would not have the effect of incorporating the
arbitration clause. In any case, Clause 7.0 of the L.O.I., which is
also a part of the agreement, makes it amply clear that the
19
redressal of the dispute between the NBCC and the respondent
has to be only through civil courts having jurisdiction of
Delhi alone.
24. In that view of the matter, we find that the learned single
judge of the Delhi High Court has erred in allowing the
application of the respondent. The appeals are accordingly
allowed. The impugned orders are quashed and set aside. There
shall be no order as to costs.
25. Pending applications, if any, shall stand disposed of.
…….........................J.
[B.R. GAVAI]
…….........................J.
[SANDEEP MEHTA ]
NEW DELHI;
MARCH 19, 2024
Legal Notes
Add a Note....