As per case facts, OPG Power Generation Pvt. Ltd. (Appellant) had a power supply agreement with Shree Karthik Papers Ltd. (Respondent). The Appellant unilaterally increased the power tariff, which the ...
2026:MHC:9381
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Reserved on : 17.02.2026
Pronounced on : 06.03.2026
CORAM:
THE HONOURABLE MR. JUSTICE C.V.KARTHIKEYAN
AND
THE HONOURABLE MR. JUSTICE K.KUMARESH BABU
OSA.No. 301 of 2020
OPG Power Generation Pvt. Ltd.,
No.6, Sardar Patel Road
Guindy, Chennai – 600 032. ... Appellant
Vs.
Shree Karthik Papers Ltd.,
25, 50 Feet Road
Krishnaswamy Nagar,
Ramanathapuram,
Coimbatore – 641 045. ... Respondent
PRAYER: Appeal filed under Order 36 Rule 1 of O.S. Rules read with
Clause 15 of Letters Patent Appeal and Section 37 of the Arbitration and
Conciliation Act, 1996, against the order dated 19.08.2020 in O.P.No. 353 of
2020 passed by his Lordship Hon'ble Mr.Justice M.Sundar.
***
For Appellant: Mr. P.Vinod Kumar
for M/s. J.Sagar Associates
https://www.mhc.tn.gov.in/judis
2
For Respondent : Mr. M.Krishnappan
Senior Counsel
for Ms. R.Swarnalatha
JUDGMENT
(Order of the Court was made by C.V.KARTHIKEYAN, J.)
The petitioner in O.P.No. 353 of 2020 which had been filed under
Section 34 of the Arbitration and Conciliation Act, 1996, aggrieved by the
order dated 19.08.2020 of the learned Single Judge of this Court, is the
appellant herein.
2. O.P.No. 353 of 2020 had been filed to set aside an arbitral award
dated 31.01.2020 passed by the sole arbitrator. The respondent herein, Shree
Karthik Papers Ltd., at Coimbatore, had filed a claim petition under Section
8(1) of the Arbitration and Conciliation Act, 1996 seeking to refer to
arbitration the disputes which had arisen with regard to an agreement dated
18.04.2018 entered into by them with the appellant herein, OPG Power
Generation Pvt. Ltd. The agreement dated 18.04.2018 was a power supply
agreement for a period of three years. The appellant, OPG Power Generation
Pvt. Ltd., was the supplier of the electricity and the respondent herein Shree
Karthik Papers Ltd., was the consumer.
3. In the agreement, the tariff had been set out for one year. Monthly https://www.mhc.tn.gov.in/judis
3
bills had been raised computing the month from 28
th
to 27
th
of the
succeeding month. The respondent had to effect payment within a period of
7 days from the date of the bill raised.
4. It had been contended that the bill for the month 28.08.2018 till
27.09.2018 was raised on 01.10.2018. It was further contended that the
appellant had stopped supply of power on and from 28.09.2018. The
respondent had to procure power from TANGEDCO at a higher rate
resulting in loss. Contending that this abrupt stoppage of power was a
breach of the contract and in view of the fact that there was a clause in the
agreement to refer the disputes to arbitration, the respondent had filed a
claim petition before the arbitrator under Section 8(1) of the Act. The
respondent had laid a claim for a sum of Rs.51,55,488/- towards excess
power charges from 28.09.2018 till 23.03.2019 and also for interest on the
increased amount deposited before TANGEDCO as on 08.10.2018 as
damages and also sought interest at 12% p.a., on the said amounts from
09.10.2018 till date of realisation. The sole arbitrator passed an award on
31.01.2020 granting a sum of Rs.40,82,400/- as the amount incurred by the
respondent towards excess power charges for the period from 28.09.2018 to https://www.mhc.tn.gov.in/judis
4
23.03.2019 and also for interest on the increased amount of deposit to
TANGEDCO as damages. It was also held that the appellant was liable to
pay interest at 12% p.a., from the respective dates for payment and not from
09.10.2018 and from 29.03.2019 which was the last date for payment. It
was also held that the respondent was entitled for interest at 12% p.a., on the
sum of Rs.9,68,490/- from 23.05.2019 which was the additional security
deposit paid by the respondent to TANGEDCO.
5. Challenging this award, the appellant had filed O.P.No. 353 of
2020 under Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996
to set aside the arbitral award. By order dated 19.08.2020, the learned
Single Judge of this Court had dismissed the said Original Petition,
necessitating filing of the present Appeal.
6. It is the contention of the learned counsel for the appellant that the
appellant had the right to revise the price under certain circumstances.
Accordingly, after due information, it was communicated that there would https://www.mhc.tn.gov.in/judis
5
be increase in the price from the next billing cycle which was from the 28
th
of that particular month till the 27
th
of the succeeding month. It had been
further contended that the appellant was to supply and the respondent was to
purchase 0.216 lakhs unit of electricity per day. The agreement also provided
that if the respondent failed to pay the bill within 7 days from the issuance of
the bill, the appellant was entitled to terminate the agreement or reduce or
even stop the allotment and supply of electricity. If payments were made
with delay, then interest at the rate of 3% per month should be paid. It was
contended that the cost of imported coal which was the fuel used for
generation of electricity increased owing to various factors. After intimating
the respondent, the appellant increased the price in accordance with Clause
11.8 of the agreement. However, the respondent had raised a protest. With
respect to the billing period 28.08.2018 to 27.09.2018, the appellant had
raised the invoice dated 01.10.2018 at the existing tariff for a sum of
Rs.35,26,360/-. It was contended that the respondent did not effect payment
within the stipulated period. By a communication dated 25.10.2018, the
appellant had called upon the respondent to remit the payment. Since the
payment was not received, the appellant did not supply any power to the
respondent for the subsequent billing period, 28.09.2018 to 27.10.2018. The https://www.mhc.tn.gov.in/judis
6
appellant also raised a debit note on 31.10.2018 for a sum of Rs.73,039/- for
the delayed payment for the months of July to September 2018. There were
exchange of correspondences between the parties. The appellant then issued
a notice under the Insolvency and Bankruptcy Code 2016, on 07.12.2018. It
was contended that the arbitration proceedings were initiated in response to
the issuance of such notice.
7. The allegation that the appellant had increased the price of the
supply of power was denied. It had been further contended that the appellant
had put the respondent on notice that if the amount raised in the bill were
paid, then there would not be stoppage of supply of power. The appellant
claimed that they acted in accordance with the rights granted under the
agreement.
8. The learned arbitrator after examining the rival contentions had
held that it was a fact that the respondent had purchased power at higher rate
from TANGEDCO. It was also held that the appellant had stopped supply of
power even before the expiry of the 7 days time granted to effect payment of https://www.mhc.tn.gov.in/judis
7
the bill amount raised. The learned arbitrator therefore, on consideration of
all the facts and circumstances granted an award as stated above.
9. The learned Single Judge held that the cessation of supply of
power by the appellant on 28.09.2018 was not justified and that this itself
was a breach of the agreement. It was also found that there was no
explanation for the subsequent period wherein there had been enhancement
of the tariff. It was held that the appellant did not have a vested right to
increase the tariff. It was finally held that no ground had been made to
interfere with the award and the petition was therefore dismissed.
10. Heard Mr.P.Vinod Kumar, learned counsel for M/s. J.Sagar
Associates for the appellant and Mr.M.Krishnappan, learned Senior Counsel
for Ms. R.Swarnalatha, learned counsel for the respondent.
11. The point which arises for consideration are:
(i) whether grant of damages on account of
non supply of electricity was justified when it was
held by the arbitrator that the appellant was
entitled to stop supply of electricity on the ground
of non payment of the invoices by the respondent. https://www.mhc.tn.gov.in/judis
8
12. The Appellant, OPG Power Generation Pvt. Ltd., and the
respondent Shree Karthik Papers Ltd., had entered into a power sharing
agreement by which the appellant agreed to supply power to the respondent
on the terms as provided in the said agreement. In the agreement, it had been
provided that the appellant, who was termed as the 'generator' had offered to
the respondent,who was termed as 'member consumer' a portion of power
generated from the power plant of the appellant from the delivery point and
from the date of enhancement of supply. In the said agreement, the Billing
Period had been defined as follows:-
“”Billing period” means the period for
which commercial invoice will be raised by the
GENERATOR for allotment of the contracted
capacity and is the period between any two
successive Meter Reading Dates. The first Billing
Period shall commence with the date of
commencement of supply of power and end with
the immediately following Meter Reading Date.”
13. Due date had been defined as follows:- https://www.mhc.tn.gov.in/judis
9
“”due date” means within Seven days from the Billing
Date including the Billing Date, in the case of a
commercial invoice, and seven days from the date
specified in a Supplementary invoice, as the case may
be.”
14. It had been covenanted that after the date of commencement of
supply, the contracted capacity would be 0.216 lakh units per day. It was
further provided that during any billing period, the appellant shall allot
power to the respondent which may be equal to or less than the contracted
supply. It had been further provided as follows:-
“Further, any failure by the Generator to not
supply / allot power to the Member Consumer due
to any fault or negligence of the Member
Consumer or this representatives and Officials
(including the provision of incorrect or late
documentation) will not constitute as a default of
any provisions of this Agreement by the Generator
and will not entitle the member Consumer for any
compensation/damages nor entitle the Member
Consumer to terminate this Agreement.” https://www.mhc.tn.gov.in/judis
10
15. It had been further provided as follows:-
“3.8. If the member consumer defaults in making
payments by the Due Date of any of the invoice(s) raised
by the Generator and/or falls to consume the Contracted
Capacity in any Billing Period, whether in part or in full,
then the GENERATOR may at its sole option and
discretion, without any intimation to the Member
Consumer, with immediate effect:
(a) Transfer or cause the Escrow Agent to transfer
the Equiry Shares (in part of in full, as determined by the
Generator in accordance with the Electricity Rules,
2005) held by the Member Consumer to any person,
and /or
(b) Terminate this Agreement, and/or
(c) Reduce the allotment and supply of the
Contracted capacity, or cease the allotment and supply of
the contracted capacity to the Member Consumer, and /
or
(d) Invoke the Letter of Credit and the Additional
Letter of credit.”
16. There were separate covenants referring to billing and payment.
It was agreed as follows:- https://www.mhc.tn.gov.in/judis
11
“a. In the last day of every Billing Period,
the Commercial Invoice for that Billing Period for
the entire Contracted Capacity.”
17. With respect to the delay in effecting payment, the parties had
agreed as follows:-
“The Member Consumer shall make payments on
or before the Due Date of any invoice(s) issued by
the GENERATOR either by Demand Draft payable
at Chennai or by RTGS. All charges associated
with any payment are to be borne by the Member
Consumer. The account details for the payment
shall be specified to the Member Consumer by the
GENERATOR (“Designated Account”). The
Member Consumer shall notify the Generator of
its payment of any invoice(s) into the Designated
Account on the same day of payment. In the event
of delay in payment of any invoice by the Member
Consumer beyond its Due Date, the Member
Consumer shall be liable to pay to the
GENERATOR interest at the rate of 3% p er month
on the amount of outstanding payment on a day to
day basis from the Due Date to the day of https://www.mhc.tn.gov.in/judis
12
payment.”
18. If there were any disputes, the following conditions had been
agreed upon:-
“4.6.1 If the Member Consumer does not
dispute in writing a invoice raised by the
GENERATOR within (seven) days of receiving it,
such invoice, issue a notice (“Bill Dispute
Notice”) to the GENERATOR setting out:
(i) the details of the disputed amount with
calculation and basis for the dispute
(ii) its estimate of what the correct amount
should be; and
(iii) all written material in support of its
claim.”
19. The respondent had also undertaken as follows:-
“To make payments against all invoices, to
the GENERATOR on or before the Due date.”
20. It was further agreed that the agreement shall be in force till https://www.mhc.tn.gov.in/judis
13
31.03.2021. It had been finally covenanted by the parties as follows:-
“No variation, waiver or modification of any of the
terms of this Agreement shall be valid unless reduced to
writing and signed by both the parties.”
21. On 19.09.2018, just about 5 months from the date of entering into
the aforementioned agreement, the appellant had forwarded an E-mail to the
respondent giving the revised tariff dated 28.09.2018. This was replied to by
the respondent by E-mail dated 24.09.2019. They had a raised protest that
this increase in the price was not acceptable to them. It was further pointed
out that in the agreement, it had been stated that for any statutory charge, the
fuel surcharge must be borne by TANGEDCO, and would be shared in equal
proportion by both of them. A request was made not to increase the power
charges and maintain the power tariff at Rs.5.75/ per unit.
22. A further mail was forwarded by the appellant to the respondent
on 24.09.2018 which is extracted in entirety.
“Dear Sir, https://www.mhc.tn.gov.in/judis
14
In line with our discussion, we once again repeat
that the schedule provided by you for the period
beginning 28
th
September, will be allotted only at the
price mentioned in our email dated 19
th
September 2018.
We request that you provide a confirmation mail
on or before 4.30 p.m on 25
th
September 2018. Please
note that if no response is received by this time, it will be
treated as irrevocable acceptance of our email dated 19
th
September, 2018.
The supply and allotment of power from your
captive power plant from 28
th
September 2018 will only
be done on the above basis.
We look forward to your long term support and
cooperation.
GPG Sales Team.”
23. An electronic communication was then sent by the respondent to
the appellant wherein they had again protested the increase in the power
tariff. https://www.mhc.tn.gov.in/judis
15
24. A careful perusal of the correspondences above would show that
the appellant sought to increase the price. It had been provided in the
agreement that such increase could be resorted to only with prior notice
issued to the respondent. It is the case of the respondent that the appellant
had however escalated the tariff without any reason and without granting
opportunity to the respondent to raise a protest. The agreement also
necessitated reasons to be given for stoppage of supply of power. It had also
been agreed between the parties that the billing cycle would be from the 28
th
of a month to the 27
th
of the succeeding month. The respondent was also
given 7 days to effect payment.
25. The appellant then issued a communication on 19.09.2018
increasing the tariff with effect from 28.09.2018 from Rs.5.75 per unit to
Rs.6.15 per unit. The respondent replied that in the agreement, it had been
provided that if there was any increase in tariff by TANGEDCO or by any
statutory authority the same could be shared equally by both the respondent
and the appellant. They also pointed out that there was no increase in the
tariff by TANGEDCO and therefore, requested the appellant to maintain the https://www.mhc.tn.gov.in/judis
16
tariff at Rs.5.75 per unit. The appellant in their reply to this communication
practically threatened the respondent by stating that they would supply
power only at the increased price. The respondent were also directed to
issue a reply confirmation. It was also stated that the supply and allotment
from 28.09.2018 would only be done on the escalated price. A further
communication was issued by the respondent specifically stating that there
was no provision in the contract for the increase in the price. The respondent
then issued a further letter on 08.10.2018 stating that they would be forced to
pay additional interest to the bank and would financially suffer owing to the
refusal to supply power during the contract period. Further the deposit
maintained with TANGEDCO would be increased which would cause
substantial loss to them. The respondent enclosed a debit note quantifying
the loss and requested settlement of the same.
26. It is thus seen that on and from that date, a dispute had arisen
between the parties. The appellant had escalated the tariff rate and the
respondent had protested and had raised a demand for the damages incurred
owing to procuring power from TANGEDCO and in suffering increase in the
security deposit demanded by the TANGEDCO. https://www.mhc.tn.gov.in/judis
17
27. It was under those circumstances that the respondent had filed a
claim before the arbitrator complaining that the appellant had abruptly
stopped supplying electricity with effect from 28.09.2018, consequent to
which the respondent herein had to procure power from TANGEDCO at a
higher rate. The respondent claimed a sum of Rs.51,55,488/-. In the
statement of defence, the appellant had claimed that they had intimated their
proposal to increase the price per unit in exercise of their right under Clause
11.8 of the power supply agreement.
28. Clause 11.8 provided as follows:-
“11.8 In the event of change in Law and/or
change in price of fuel for the power plant or
change in transmission or wheeling losses and
charges, the GENERATOR shall have right to
revise terms of this Agreement especially relating
to Price, mode, method, billing and Contribution
towards energy.”
29. It is seen from the above that when there was a change in law or
change in price of fuel or change in transmission, the appellant shall have
the right to revise the terms of the agreement relating to price and on other https://www.mhc.tn.gov.in/judis
18
aspects.
30. The learned Arbitrator in his award had specifically noted that
there was no communication about increase in the landed cost of coal
warranting upward reversion of tariff. The Arbitrator had also noted that the
contract permits stoppage of supply due to non payment. But however, he
observed that the dispute had arisen only because the appellant had
unilaterally raised the tariff on 19.09.2018. It had been further observed that
the claim for increase in the landed cost of coal was only an after thought. It
was further observed that the appellant had not produced any document to
show that there was an increase in the cost of generation of coal. The
arbitrator finally held that the appellant had committed breach of the Power
Supply Agreement and that the respondent would therefore be entitled to
claim damages / compensation. It was also held that the appellant had not
produced any material justifying increase in tariff. It was further held that
the appellant cannot unilaterally increase the tariff from Rs.5.75 to Rs.6.15
per unit. The Arbitrator then examined the quantity of the power purchased
from TANGEDCO which was to a sum of Rs.6,53,529/- and further included
the power purchased in the months from September 2018 till March 2019. https://www.mhc.tn.gov.in/judis
19
31. The learned counsel for the appellant argued that the Tribunal had
stated that there was justification in increase in the tariff. However, this
observation must be viewed from a wider context. It was only an
observation as the Arbitrator had examined Clause 11.8 and stated that there
could be increase in the power tariff only when there was consequential
increase in the fuel price. It was also observed that there were no material
produced to justify increase in the tariff. It was observed that the appellant
gave, alternate reasons for the increase in the power tariff.
32. The learned Single Judge in the order now under appeal had held
that cessation of supply of power was a breach committed by the appellant.
It was also found that even if there could be a right to enhance the tariff, the
same could be done only after due communication to the respondent.
33. The learned counsel for the appellant had placed reliance on the
following Judgments:-
(1) Timbola Irmaos Ltd., Vs. Jorge Anibal Matos, (1977) 3 SCC
474, wherein paragraph Nos. 19 and 20 are as follows:- https://www.mhc.tn.gov.in/judis
20
“19. Coming now to the second question,
we find that the findings of fact recorded by the
Judicial Commissioner are unexceptionable.
Firstly, it was found that, although, under the
contract, the defendants-respondents could load
iron ore, at any time during 24 hours, which
included the night, yet, the defendants were
prevented from doing so owing to the failure of the
plaintiff to provide either sufficient lighting or
enough winches to enable due performance of the
contract. Secondly, it was admitted that the
appellant never opened a Letter of Credit with the
named bank by 27th January, 1954, as promised by
it. Thirdly, the delay in loading was held to be due
to the fault of the company. The Judicial
Commissioner rightly concluded that the company
had not discharged its own part of the contract so
that it could not claim demurrage or damages.
Indeed, it was found that the company did not have
to pay any demurrage at all to the shippers for
delayed departure.
20. learned Counsel for the appellant relied
strongly on the following terms in the contract of
23rd January, 1954: https://www.mhc.tn.gov.in/judis
21
Demurrage (if any) in loading payable by Seller at
the rate of US $ 800.00 per running day fraction of
day pro rata. Buyers to pay despatch money at half
the demurrage rate for all time saved in loading.
Payment either way in Portuguese Indian rupee
currency at the rate of exchange of Rs. 476/- for
US $100.00" The contention was that this created
an absolute liability to pay for delay in loading
irrespective of whether the company had to pay the
shippers any demurrage. It was urged that the
liability was upon the seller irrespective of whether
such payment had to be made to the shipping
company or not. We think that the demurrage could
not be claimed when the delay in loading was due
to the default of the respondents themselves. It is
apparent that the basis upon which the agreement
to pay demurrage rested was that the appellant will
afford proper facilities for loading. When the
appellant itself had committed breaches of its
obligations, it is difficult to see how the
respondents could be made responsible for the
delay in loading. We think that the Judicial
Commissioner had rightly disallowed this part of
the claim.”
34. The facts in the instant case are distinguishable on the ground that https://www.mhc.tn.gov.in/judis
22
the defendants therein were prevented from loading iron ore owing to the
failure of the plaintiff to provide sufficient lighting or enough winches to
enable due performance of the contract.
35. In the instant case, the breach first commenced with the cessation
of supply of power, placing reliance on clause 11.8 of the agreement which
clause was not directly attracted as an alternate reason was given that the
respondent had not paid the bills within the time.
36. The observation in the Judgment that “when the appellant itself
had committed breaches of its obligations, it is difficult to see how the
respondents could be made responsible” would be applicable to the
appellants in this case owing to their initial breach of cessation of supply of
power.
(2) Pulavarti Sitaramamurthy Vs. Bangaru Sobhanadri, (1950) 63
LW 947 (Mad) with reference to the following passage:
“Unfortunately, the learned Sub-Judge
considered the surrounding circumstances and https://www.mhc.tn.gov.in/judis
23
decided the case against the defendants largely
because the price of gunnies had risen and the
defendants would have profited by not delivering
the bales. On this conclusion, he held the
defendants liable for breach, as they had a motive
to commit a breach, and awarded damages of Rs.
631-4-0 against them on the difference in price
between the market rate on the delivery dates and
the agreed contract rates. It is obvious that he
erred in doing so. Motive, by itself, will not do in
law, Civil or Criminal. Many a man who has a
strong motive to commit a murder may not commit
it, and cannot be convicted of murder merely
because he had a motive to commit it. So too, a
man having merely a motive to commit a breach of
contract cannot be mulcted in damages if he is not
proved to have committed a breach. The Court has
first to concentrate on the law, and then only on
the results of its findings on law .”
37. In the instant case, as consistently stated, the initial breach was on
the part of the appellant, who could have deferred the increase in the tariff
and could have increased the same after discussions with the respondent.
38. In the instant case, as repeatedly pointed out, the initial breach https://www.mhc.tn.gov.in/judis
24
was only by the appellant and not by the respondent.
(3) Sikkim Subba Associates Vs. State of Sikkim, (2001) 5 SCC 629
wherein paragraph No. 14, it had been held as follows:
“14. It is also, by now, well settled that an
Arbitrator is not a conciliator and his duty is to
decide the disputes submitted to him according to
the legal rights of the parties and not according to
what he may consider it to be fair and reasonable.
Arbitrator was held not entitled to ignore the law
or misapply it and cannot also act arbitrarily,
irrationally, capriciously or independently of the
contract (See 1999(9) SCC 283 : Rajasthan State
Mines and Minerals Ltd. v. Eastern Engineering
Enterpresies & Anr.). If there are two equally
possible or plausible views or interpretations, it
was considred to be legitimate for the Arbitrator to
accept one or the other of the available
interpretations. It would be difficult for the Courts
to either exhaustively define the ward `misconduct'
or likewise enumerate the line of caes in which
alone interference either could or could not be https://www.mhc.tn.gov.in/judis
25
made. Courts of Law have a duty and obligation in
order to maintain purity of standards and preserve
full faith and credit as well as to inspire confidence
in alternate dispute redressal method of
Arbitration, when on the face of the Award it is
shown to be based upon a proposition of law
which is unsound or findings recorded which are
absurd or so unreasonable and irrational that no
reasonable or right thinking person or authority
could have reasonably come to such a conclusion
on the basis of the materials on record or the
governing position of law to interfere. So far as the
case before us is concerned, the reference to the
Arbitrator is found to be a general reference to
adjudicate upon the dispute relating to the alleged
termination of the agreement by the State and not a
specific reference on any particular question and
consequently, if it is shown or substantiated to be
erroneous on the face of it, the award must be set
aside.”
39. In the instant case, the arbitrator and also the learned Judge
examining the petition under Section 34 of the Act had only proceeded on
the interpretation of Clause 11(8) and 11(4) of the agreement between the
parties and both had held that there was no justification for the increase in https://www.mhc.tn.gov.in/judis
26
the price and that there was no justification for the cessation of supply of
power. It is also to be noted that in the claim petition, the appellant had very
specifically stated the reasons for the amounts claimed by them. The award
of the Tribunal does not suffer for non consideration of relevant points.
(4) Kanchan Udyog Ltd., Vs. United Spirits Ltd., (2017) 8 SCC 237
wherein paragraph No. 17 is as follows:
“17. Considering the principle of causation
to award loss of anticipated profits by breach of
agreement, it was held in the facts of the case, that
it was not the result of the breach, but was a
composition of various factors like lack of brand
acceptance, financial crunch of the appellant and
lack of adequate infrastructure by it. The claim for
damages was therefore, remote as there was not
even a speculated chance for making profit by the
appellant. ”
40. In the instant case, the claim for damages was based on the
increased tariff paid to TANGEDCO and the increased interest paid owing to
the increase in the security deposit to TANGEDCO. The respondent had
given the details of the loss incurred every month and therefore, it cannot be https://www.mhc.tn.gov.in/judis
27
stated that the claim for damages was remote. It was proximate and directly
related to the cessation of supply of power by the appellant.
(5) PSA Sical Terminals Pvt. Ltd., Vs. Board of Trustees, V.O.C.
Port Trust, (2023) 15 SCC 781 wherein paragraph Nos. 41 and 42 are as
follows:
“41. A decision which is perverse, though would
not be a ground for challenge under “public policy of
India”, would certainly amount to a patent illegality
appearing on the face of the award. However, a finding
based on no evidence at all or an award which ignores
vital evidence in arriving at its decision would be
perverse and liable to be set aside on the ground of
patent illegality.
42. To understand the test of perversity, it will
also be appropriate to refer to paragraph 31 and 32
from the judgment of this Court in Associate Builders
Vs. DDA (2015) 2 SCC (Civ) 204, which read thus:
“31. The third juristic principle is that a decision
which is perverse or so irrational that no reasonable
person would have arrived at the same is important and
requires some degree of explanation. It is settled law
that where: https://www.mhc.tn.gov.in/judis
28
(i) a finding is based on no evidence, or
(ii) an Arbitral Tribunal takes into account
something irrelevant to the decision which it arrives at;
or
(iii) ignores vital evidence in arriving at its
decision, such decision would necessarily be perverse.
32. A good working test of perversity is
contained in two judgments. In Excise and Taxation
Officer-cum-Assessing Authority v. Gopi Nath & Sons
[1992 Supp (2) SCC 312], it was held: (SCC p. 317,
para 7)
“7. … It is, no doubt, true that if a finding of fact
is arrived at by ignoring or excluding relevant material
or by taking into consideration irrelevant material or if
the finding so outrageously defies logic as to suffer
from the vice of irrationality incurring the blame of
being perverse, then, the finding is rendered infirm in
law.”
In Kuldeep Singh v. Commr. of Police [(1999)
2 SCC 10: 1999 SCC (L&S) 429], it was held: (SCC p.
14, para 10) https://www.mhc.tn.gov.in/judis
29
“10. A broad distinction has, therefore, to be
maintained between the decisions which are perverse
and those which are not. If a decision is arrived at on
no evidence or evidence which is thoroughly unreliable
and no reasonable person would act upon it, the order
would be perverse. But if there is some evidence on
record which is acceptable and which could be relied
upon, howsoever compendious it may be, the
conclusions would not be treated as perverse and the
findings would not be interfered with.”
'
41. We are of the opinion that neither the award of the arbitrator nor
the order of the learned Single Judge can be termed as perverse. The
respondent had laid a claim for the additional loss incurred by them for
having procured power from TANGEDCO since the appellant had cased to
supply power.
42. Both the arbitrator and the learned Single Judge had examined
who was first in breach of the agreement and had come to an uniform
conclusion that it was the appellant, who had initially raised the tariff and
later exercising right under Clause 11.8 had stopped supply. The appellant
claimed later that they had stopped supply only because the respondent
failed to pay the bill within the time period stipulated. But again, even if the https://www.mhc.tn.gov.in/judis
30
bill had not been paid within the time, the appellant could not and should not
have stopped supply of power without following the guidelines under clause
11.4 of the agreement. These issues have been discussed by both the
Arbitrator and by the learned Single Judge and we hold that both the award
and the order can never be termed as perverse.
43. The learned Senior Counsel for the respondent had placed
reliance on the Judgment of the Hon'ble Supreme Court reported in Civil
Appeal No. 2153 of 2010 [M/s. Dyna Technologies Pvt. Ltd., Vs. M/s.
Crompton Greaves Ltd.,] with specific reference to paragraph No. 26 which
is as follows:-
“26. There is no dispute that Section 34 of
the Arbitration Act limits a challenge to an award
only on the grounds provided therein or as
interpreted by various Courts. We need to be
cognizant of the fact that arbitral awards should
not be interfered with in a casual and cavalier
manner, unless the Court comes to a conclusion
that the perversity of the award goes to the root of
the matter without there being a possibility of
alternative interpretation which may sustain the https://www.mhc.tn.gov.in/judis
31
arbitral award. Section 34 is different in its
approach and cannot be equated with a normal
appellate jurisdiction. The mandate under Section
34 is to respect the finality of the arbitral award
and the party autonomy to get their dispute
adjudicated by an alternative forum as provided
under the law. If the Courts were to interfere with
the arbitral award in the usual course on factual
aspects, then the commercial wisdom behind
opting for alternate dispute resolution would
stand frustrated. ”
44. The scope of interference with an award is extremely narrow. If
any error has been committed by the arbitrator unless they are found to be
perverse, the award cannot be set aside. The award must be held to be
contrary to the basic principles under which the agreement had been entered
into and should suffer from patent illegality or perversity.
45. A careful perusal of the award and also the order of the learned
Single Judge in the instant case does not give rise to any such ground to lead https://www.mhc.tn.gov.in/judis
32
us to such a conclusion.
46. We hold that the order of the learned Single Judge and the award
of the arbitrator require no interference. We therefore dismiss the Appeal
with costs.
47. Accordingly, this Appeal stands dismissed with costs.
[C.V.K., J.] [K.B., J.]
06.03.2026
Index: Yes/No
Internet:Yes/No
Neutral Citation: Yes/No
vsg
Note: The respondent is at liberty to seek permission to withdraw the amount deposited
by the appellant consequent to interim directions given by this Court at the time when the
appeal came up for admission by filing a memo. On filing of such memo, the Registrar
General may recall the deposit and pay the amount together with accrued interest directly
to the respondent. In the memo, the Bank details of the respondent may also be given by
the respondent.
C.V.KARTHIKEYAN, J.
AND
K.KUMARESH BABU, J.
vsg
Pre-Delivery Judgment made in https://www.mhc.tn.gov.in/judis
33
OSA.No. 301 of 2020
06.03.2026 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....