As per case facts, the Petitioner participated in a tender and furnished an EMD-BG. Respondent no.2 alleged a forged document and banned the Petitioner, leading Respondent no.1 to forfeit the ...
W.P.(C) 6570/2021 Page 1 of 31
$~J
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment pronounced on : 02.02.2026
+ W.P.(C) 6570/2021
PAHARPUR COOLING TOWERS LTD .....Petitioner
Through: Mr. Sanjay Ghosh, Sr. Advocate
along with Mr. Naman Jain,
Mr. Rohan Mandal and
Mr. Mohit Garg, Advocates.
versus
RAMAGUNDAM FERTILIZERS AND CHEMICALS LTD &
ANR. .....Respondents
Through: Mr. Dipak Kumar Jena, Mr.
R.K. Poshwal, Mr. Sandip
Munain, Mr. Ashutosh Singh
Deo and Mr. Raj Shekar Jena,
Advocates. and Ms. Priya
Chaudhary, MT Law.
Mr. Abhimanyu Garg, Advocate
and Mr. Himanshu Singh
Yadav, Dy. Manager, Legal
(EIL).
CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA
JUDGMENT
1. The present petition has been filed by the petitioner being
aggrieved by the encashment/forfeiture of the Bank Guarantee towards
the Earnest Money Deposit (hereinafter referred as “EMD-BG”)
amounting to Rs. 47,50,000/- by the respondent no.1/Ramagundam
Fertilizers and Chemicals Ltd. The said EMD-BG was furnished on
W.P.(C) 6570/2021 Page 2 of 31
16.12.2015 (with a validity up to 27.12.2016) by the petitioner while
participating in a tender dated 09.11.2015 floated by the respondent
no.2/Engineers India Ltd (EIL) for the work of “cooling tower and
CWTP packages for revival of Ramagundam Fertilizers and
Chemicals project”.
2. The petitioner is a company engaged in the business of
manufacturing and supplying of cooling equipments including cooling
towers. Respondent no.1 is a Joint Venture (JV) company of
EIL/respondent no.2 (an engineering consultancy and EPC company
under the ownership of the Ministry of Petroleum and Natural Gas,
Government of India), National Fertilizer Ltd (NFL) and Fertilizer
Corporation of India Ltd (FCIL) formed for setting up gas-based Urea
manufacturing plant at Ramagundam, Telangana. Respondent
no.2/EIL was awarded the detailed engineering and project
management for revival of Fertilizer Plant at Ramagundam, Telangana
and in pursuance of the same, floated a tender dated 19.11.2015 for
supply, erection and construction of FRP cooling tower.
3. Pursuant to the scrutiny/verification of the requisite documents
submitted by the petitioner for the aforementioned tender, a Show
Cause Notice (SCN) dated 14.10.2016 came to be issued against the
petitioner proposing suspension and debarment of its business on
account of alleged submission of forged document/certificate for
satisfying the bidder qualification criteria. The said SCN reads as
under:
W.P.(C) 6570/2021 Page 3 of 31
4. The aforementioned allegations were also communicated vide a
letter dated 17.10.2016 to the respondent no.1 by the respondent no.2.
The same reads as under:
W.P.(C) 6570/2021 Page 4 of 31
xxx xxx xxx
W.P.(C) 6570/2021 Page 5 of 31
5. Subsequently, respondent no.1 issued a letter dated 20.12.2016
to the bank of the petitioner for forfeiture of the EMD-BG. On
22.12.2016 the EMD-BG was released in favour of respondent no.1 by
the concerned bank.
6. In the meantime, vide an email dated 21.12.2016, the respondent
no.2, also intimated the petitioner that the competent authority of
respondent no.2 has decided to put the petitioner on “holiday list of the
EIL Construction Contractor” for a period of 3 years w.e.f.
14.12.2016.
7. Against said decision dated 21.12.2016, the petitioner preferred
a representation dated 11.01.2017 before the Appellate Authority of
respondent no.2. Vide an order dated 26.05.2017, the aforementioned
decision dated 21.12.2016 came to be revoked by the Appellate
Authority with immediate effect. The said order dated 26.05.2017
reads as under:
W.P.(C) 6570/2021 Page 6 of 31
8. In the circumstances, considering that the ban imposed upon the
petitioner has been revoked by the Appellate Authority of the
W.P.(C) 6570/2021 Page 7 of 31
respondent no.2 vide an order dated 26.05.2017, the petitioner between
2017 and 2020 made various representations to the respondents
seeking refund of EMD-BG retained by respondent no.1. However, it
is submitted that the respondents failed to respond/act upon the said
representations.
9. Consequently, the petitioner issued a legal notice dated
10.02.2021 to respondent no.1 seeking for refund of the EMD-BG
retained by them. However, again, the respondent no.1 failed to
respond.
10. In the aforesaid background, aggrieved, the petitioner preferred
the present petition seeking to direct the respondents to return/refund
the forfeited EMD-BG to the petitioner.
SUBMISSIONS ON BEHALF OF THE PETITIONER
11. Learned senior counsel on behalf of the petitioner submitted that
even before a reply was submitted by the petitioner to the Show Cause
Notice dated 14.10.2016, a communication dated 17.10.2016 came to
be issued by the respondent no.2 to respondent no.1 alleging
submission of forged document by the petitioner. Further, the
respondent no.1 issued a letter dated 20.12.2016 to the bank of the
petitioner for forfeiture of the EMD-BG without issuing any Show
Cause Notice or an independent enquiry into the said matter.
12. It is further contended that the petitioner is entitled to a refund
of the EMD-BG encashed by respondent no.1 inasmuch as the letter
dated 20.12.2016 issued by respondent no.1 to the petitioner’s bank
for forfeiture of the furnished security, was premised upon a
W.P.(C) 6570/2021 Page 8 of 31
communication dated 17.10.2016 from respondent no.2, alleging
submission of a forged document/certificate by the petitioner.
However, the unconditional revocation of the banning order dated
21.12.2016 by the Appellate Authority of respondent no.2 vide order
dated 26.05.2017, effectively nullified the allegations of forgery which
constituted the very foundation of the aforesaid communication dated
17.10.2016, consequent ban by respondent no.2 and encashment of the
EMD-BG by respondent no.1.
13. It is further submitted that the allegation pertaining to the
forgery of documents emanated from an inadvertent error made by the
petitioner. It is stated that during the bidding process, the petitioner
furnished an experience certificate dated 14.12.2015 bearing ref:
GGEL/HR/Mech./2015-16 (hereinafter referred as “Exhibit 1”) issued
by one of its previous employers i.e., Godavari Green Energy Pvt. Ltd,
(hereinafter referred as “GGEL”). Due to certain procedural
requirement, the said certificate dated 14.12.2015 was revised and
again submitted in the desired format. However, inadvertently, the
petitioner submitted draft version dated 18.04.2016 bearing ref:
GGEL/HR/ Mech/2015-16 (hereinafter referred as “Exhibit 2”) of the
revised certificate instead of the certificate dated 18.04.2016 bearing
ref: GGEL/HR/Mech/2016/02 (hereinafter referred as “Exhibit 3”)
approved by GGEL. The said inadvertent error was subsequently
clarified and rectified and is evident from an email dated 20.10.2016
received from GGEL.
14. It is further brought out that the tender dated 09.11.2015, for
which the EMD-BG deposited by the petitioner was forfeited by the
W.P.(C) 6570/2021 Page 9 of 31
respondent no.1 was cancelled/withdrawn/not acted upon by the
respondents. Subsequently, a fresh tender for the same work was re-
issued on 12.06.2017 by the respondent no.2, which ultimately came
to be awarded vide a Letter of Award dated 08.08.2017 in favour of
the petitioner and duly executed. It is contended that had the
petitioner’ action been void of bonafide intentions, the aforesaid award
would have not been awarded in its favour.
15. It is submitted that till date, there is no material/order/finding on
record that would justify forfeiture of EMD-BG by the respondent
no.1. Further, mere existence of an alternative remedy does not oust
the jurisdiction of this Court under Article 226 of the Constitution of
India inasmuch as the conduct of respondent no.1 is clearly in
contravention of the principles of natural justice, arbitrary in nature
and void of any cogent rationale. In this regard, reliance has been
placed upon catena of judgments rendered by the Supreme Court
1
.
16. It is further submitted that it is a settled law that the period of
limitation does not apply to writ jurisdiction and instead the concept of
laches is applicable. An entity under Article 12 of the Constitution of
India cannot justify unjust enrichment by resorting to a mere technical
plea of limitation, especially considering that the petitioner was
continuously pursuing the said matter with the officials of respondents
1
Union of India & Ors. vs. Tantia Constructions (P) Ltd., (2011) 5 SCC 697; Harbanslal Sahnia
v. Indian Oil Corporation Ltd., (2003) 2 SCC 107; Whirlpool Corporation v. Registrar of Trade
Marks, (1998) 8 SCC 1; National Sample Survey Organization and Anr. v. Champa Properties
Limited and Anr., (2009) 14 SCC 451; Hindustan Petroleum Corporation Limited and Ors. v.
Super Highway Services and Anr., (2010) 3 SCC 321; ABL International Ltd. and Ors. vs.
Export Credit Guarantee Corporation of India Ltd. and Ors., (2004) 3 SCC 553 and UP Power
Transmission Corporation Ltd. and Ors. vs. CG Power and Industrial Solutions Limited and
Ors., (2021) 6 SCC 15.
W.P.(C) 6570/2021 Page 10 of 31
for resolution since 2017 and never abandoned the same. Thus, the
cause of action finally arose when the respondent no.1 failed to
respond to the legal notice dated 10.02.2021. Even otherwise, without
prejudice to the aforesaid, assuming that the cause of action arose on
26.05.2017, the period of limitation which would have expired on
25.05.2020 ought to have been relaxed in line with the directions
rendered by the Supreme Court in Suo Moto Writ Petition No. 3/2020.
SUBMISSIONS ON BEHALF OF THE RESPONDENT
17. Learned counsel on behalf of the respondent no.1 submitted that
in view of the violation of contractual obligation by the petitioner,
under clause 36.8.1 of General Conditions of Contract (GCC) EMD-
BG was forfeited. Further, the petitioner never approached the
Appellate Authority of respondent no.2 against the forfeiture of EMD-
BG by the respondent no.1 and instead directly invoked the
jurisdiction of this Court.
18. It is further contended that the present petition is not
maintainable inasmuch as (i) the dispute between the parties to the
present petition are private in nature and there is no violation of
statutory duty (ii) the petitioner has approached this Court without
exhausting an alternative remedy (arbitration) available to the
petitioner in terms of clause 35.2.2 of the GCC. Reliance in this regard
is placed upon judgment rendered by the Supreme Court in Joshi
Technologies International Inc vs Union of India and Ors, (2015) 7
SCC 728 and K.K Saxena vs International Commission on Irrigation
and Drainage, (2015) 4 SCC 670 (iii) the EMD-BG was forfeited by
W.P.(C) 6570/2021 Page 11 of 31
the respondent no.1 in 2016 and the present petition has been filed
after a delay of 5 years without any cogent rationale thereof.
19. It is submitted that the during the scrutiny and verification of
documents, it came to the knowledge of respondent no.2, that the
experience certificate dated 18.04.2016 purportedly issued by GGEL
was false and fabricated. The said allegation has been supported by an
email dated 10.10.2016, wherein, GGEL categorically denied issuance
of the aforesaid certificate.
20. Further, attention is drawn to a letter dated 21.01.2019 along
with inter-office Memorandum dated 09.01.2019, issued by the
respondent no.2, justifying the forfeiture of EMD-BG by the
respondent no.1 and categorically observing that the
document/certificate purportedly issued by GGEL, submitted by the
petitioner along with the bid was not genuine and tantamount to fraud
on part of the petitioner. The letter dated 21.01.2019 and inter-office
Memorandum dated 09.01.2019 reads as under:-
W.P.(C) 6570/2021 Page 12 of 31
W.P.(C) 6570/2021 Page 13 of 31
W.P.(C) 6570/2021 Page 14 of 31
ANALYSIS AND FINDINGS
21. At the outset, this Court is not persuaded by the objections of
the respondents as regards (non) maintainability of the present writ
petition. The law is well settled that this Court has jurisdiction, even in
contractual or tender matters to redress the arbitrariness and/or denial
of principles of natural justice.
22. The legal position in this regard has been reiterated by the
Supreme Court time and again in various judgments including that of
Subodh Kumar Singh Rathour v. Chief Executive Officer and
Others, 2024 SCC OnLine SC 1682, by observing as under:-
57. Thereafter, this Court in its decision in M.P. Power Management
Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd. [M.P. Power
Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd.,
(2023) 2 SCC 703] exhaustively delineated the scope of judicial
review of the courts in contractual disputes concerning public
authorities. The aforesaid decision is in the following parts:-
Scope of judicial review in matters pertaining to contractual disputes
57.1. This Court in M.P. Power Management case [M.P. Power
Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd.,
(2023) 2 SCC 703] held that the earlier position of law that all rights
against any action of the State in a non-statutory contract would be
governed by the contract alone and thus not amenable to the writ
jurisdiction of the Courts is no longer a good law in view of the
subsequent rulings. Although writ jurisdiction is a public law remedy,
yet a relief would still lie under it if it is sought against an arbitrary
action or inaction of the State, even if they arise from a non-statutory
contract. The relevant observations read as under: (M.P. Power
Management case [M.P. Power Management Co. Ltd. v. Sky Power
Southeast Solar India (P) Ltd., (2023) 2 SCC 703] , SCC p. 763, paras
81-82)
“81. … when the offending party is the State. In other words, the
contention is that the law in this field has witnessed an evolution
and, what is more, a revolution of sorts and a transformatory
change with a growing realisation of the true ambit of Article 14 of
the Constitution of India. The State, he points out, cannot play the
W.P.(C) 6570/2021 Page 15 of 31
Dr Jekyll and Hyde game anymore. Its nature is cast in stone. Its
character is inflexible. This is irrespective of the activity it indulges
in. It will continue to be haunted by the mandate of Article 14 to act
fairly. There has been a stunning expansion of the frontiers of the
Court's jurisdiction to strike at State action in matters arising out
of contract, based, undoubtedly, on the facts of each case. It
remains open to the Court to refuse to reject a case, involving State
action, on the basis that the action is, per se, arbitrary.
***
82.1. It is, undoubtedly, true that the writ jurisdiction is a public
law remedy. A matter, which lies entirely within a private realm of
affairs of public body, may not lend itself for being dealt with under
the writ jurisdiction of the Court.
82.2. The principle laid down in Bareilly Development
Authority [Bareilly Development Authority v. Ajai Pal Singh,
(1989) 2 SCC 116] that in the case of a non-statutory contract the
rights are governed only by the terms of the contract and the
decisions, which are purported to be followed, including
Radhakrishna Agarwal [Radhakrishna Agarwal v. State of Bihar,
(1977) 3 SCC 457] , may not continue to hold good, in the light of
what has been laid down in ABL [ABL International Ltd. v. Export
Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553 : (2004)
118 Comp Cas 213] and as followed in the recent judgment in
Sudhir Kumar Singh [State of U.P. v. Sudhir Kumar Singh, (2021)
19 SCC 706] .
82.3. The mere fact that relief is sought under a contract which is
not statutory, will not entitle the respondent State in a case by itself
to ward-off scrutiny of its action or inaction under the contract, if
the complaining party is able to establish that the action/inaction
is, per se, arbitrary.”
Exercise of writ jurisdiction in disputes at the stage prior to the award
of contract
57.2. An action under a writ will lie even at the stage prior to the award
of a contract by the State wherever such award of contract is imbued with
procedural impropriety, arbitrariness, favouritism or without any
application of mind. In doing so, the courts may set aside the decision
which is found to be vitiated for the reasons stated above but cannot
substitute the same with its own decision. The relevant observations read
as under: (M.P. Power Management case [M.P. Power Management Co.
Ltd. v. Sky Power Southeast Solar India (P) Ltd., (2023) 2 SCC 703] ,
SCC p. 764, para 82.4)
“82.4. An action will lie, undoubtedly, when the State purports to award
any largesse and, undoubtedly, this relates to the stage prior to the
contract being entered into (see Ramana Dayaram Shetty [Ramana
W.P.(C) 6570/2021 Page 16 of 31
Dayaram Shetty v. International Airport Authority of India, (1979) 3 SCC
489 : AIR 1979 SC 1628] ). This scrutiny, no doubt, would be undertaken
within the nature of the judicial review, which has been declared in the
decision in Tata Cellular v. Union of India [Tata Cellular v. Union of
India, (1994) 6 SCC 651] .”
xxx xxx xxx
Other relevant considerations for exercise of writ jurisdiction
57.5. Lastly, this Court in M.P. Power Management case [M.P. Power
Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd., (2023)
2 SCC 703] held that the courts may entertain a contractual dispute
under its writ jurisdiction where: (I) there is any violation of natural
justice, or (II) where doing so would serve the public interest, or (III)
where though the facts are convoluted or disputed, but the courts have
already undertaken an in-depth scrutiny of the same provided that it was
pursuant to a sound exercise of its writ jurisdiction. The relevant
observations read as under: (M.P. Power Management case [M.P. Power
Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd., (2023)
2 SCC 703] , SCC p. 766, para 82)
“82. … 82.13. A lodestar, which may illumine the path of the Court,
would be the dimension of public interest subserved by the Court
interfering in the matter, rather than relegating the matter to the
alternate Forum.
82.14. Another relevant criteria is, if the Court has entertained the
matter, then, while it is not tabooed that the Court should not relegate
the party at a later stage, ordinarily, it would be a germane
consideration, which may persuade the Court to complete what it had
started, provided it is otherwise a sound exercise of jurisdiction to
decide the matter on merits in the writ petition itself.
82.15. Violation of natural justice has been recognised as a ground
signifying the presence of a public law element and can found a cause
of action premised on breach of Article 14. (See Sudhir Kumar
Singh [State of U.P. v. Sudhir Kumar Singh, (2021) 19 SCC 706] ).”
58. What can be discerned from the above is that there has been a
considerable shift in the scope of judicial review of the court when it
comes to contractual disputes where one of the parties is the State or its
instrumentalities. In view of the law laid down by this Court in ABL [ABL
International Ltd. v. Export Credit Guarantee Corpn. of India Ltd.,
(2004) 3 SCC 553 : (2004) 118 Comp Cas 213] , Joshi
Technologies [Joshi Technologies International Inc. v. Union of India,
(2015) 7 SCC 728 : (2015) 374 ITR 322] and in M.P. Power [M.P.
Power Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd.,
(2023) 2 SCC 703] , it is difficult to accept the contention of the
respondent that the writ petition filed by the appellant before the High
W.P.(C) 6570/2021 Page 17 of 31
Court was not maintainable and the relief prayed for was rightly declined
by the High Court in exercise of its writ jurisdiction. Where State action
is challenged on the ground of being arbitrary, unfair or unreasonable,
the State would be under an obligation to comply with the basic
requirements of Article 14 of the Constitution and not act in an arbitrary,
unfair and unreasonable manner. This is the constitutional limit of their
authority. There is a jural postulate of good faith in business relations
and undertakings which is given effect to by preventing arbitrary exercise
of powers by the public functionaries in contractual matters with private
individuals. With the rise of the social service State more and more
public-private partnerships continue to emerge, which makes it all the
more imperative for the courts to protect the sanctity of such relations.
23. Likewise, in Unitech Limited and Others vs Telangana State
Industrial Infrastructure Corporation (TSIIC) and Ors., (2021) 16
SCC 35, it was held by the Supreme Court as under:-
“39. A two-Judge Bench of this Court in ABL International Ltd. v. Export
Credit Guarantee Corpn. of India Ltd. [ABL International Ltd. v. Export
Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] [ABL
International] analysed a long line of precedent of this Court [K.N.
Guruswamy v. State of Mysore, (1954) 2 SCC 125 : AIR 1954 SC
592; Gujarat State Financial Corpn. v. Lotus Hotels (P) Ltd., (1983) 3
SCC 379; Gunwant Kaur v. Municipal Committee, Bhatinda, (1969) 3
SCC 769] to conclude that writs under Article 226 are maintainable for
asserting contractual rights against the State, or its instrumentalities, as
defined under Article 12 of the Indian Constitution.
39.1. Speaking through N. Santosh Hegde, J. the Court held : (ABL
International case [ABL International Ltd. v. Export Credit Guarantee
Corpn. of India Ltd., (2004) 3 SCC 553] , SCC p. 572, para 27)
“27. … the following legal principles emerge as to the maintainability
of a writ petition:
(a) In an appropriate case, a writ petition as against a State or an
instrumentality of a State arising out of a contractual obligation is
maintainable.
(b) Merely because some disputed questions of fact arise for
consideration, same cannot be a ground to refuse to entertain a writ
petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is
also maintainable.”
This exposition has been followed by this Court, and has been adopted by
the three-Judge Bench decisions of this Court in State of U.P. v. Sudhir
Kumar Singh [State of U.P. v. Sudhir Kumar Singh, (2021) 19 SCC 706 :
W.P.(C) 6570/2021 Page 18 of 31
2020 SCC OnLine SC 847] and Popatrao Vyankatrao Patil v. State of
Maharashtra [Popatrao Vyankatrao Patil v. State of Maharashtra,
(2020) 19 SCC 241] .
39.2. The decision in ABL International, cautions that the plenary power
under Article 226 must be used with circumspection when other remedies
have been provided by the contract. But as a statement of principle, the
jurisdiction under Article 226 is not excluded in contractual matters.
39.3. Article 23.1 of the development agreement in the present case
mandates the parties to resolve their disputes through an arbitration.
However, the presence of an arbitration clause within a contract between
a State instrumentality and a private party has not acted as an absolute
bar to availing remedies under Article 226 [Harbanslal Sahnia v. Indian
Oil Corpn. Ltd., (2003) 2 SCC 107; Ram Barai Singh & Co. v. State of
Bihar, (2015) 13 SCC 592 : (2016) 1 SCC (Civ) 770] .
39.4. If the State instrumentality violates its constitutional mandate under
Article 14 to act fairly and reasonably, relief under the plenary powers of
Article 226 of the Constitution would lie. This principle was recognised
in ABL International [ABL International Ltd. v. Export Credit Guarantee
Corpn. of India Ltd., (2004) 3 SCC 553] : (ABL International case [ABL
International Ltd. v. Export Credit Guarantee Corpn. of India Ltd.,
(2004) 3 SCC 553] , SCC p. 572, para 28)
“28. However, while entertaining an objection as to the
maintainability of a writ petition under Article 226 of the Constitution
of India, the court should bear in mind the fact that the power to issue
prerogative writs under Article 226 of the Constitution is plenary in
nature and is not limited by any other provisions of the Constitution.
The High Court having regard to the facts of the case, has a discretion
to entertain or not to entertain a writ petition. The Court has imposed
upon itself certain restrictions in the exercise of this power.
(See Whirlpool Corpn. v. Registrar of Trade Marks [Whirlpool
Corpn. v. Registrar of Trade Marks, (1998) 8 SCC 1] .) And this
plenary right of the High Court to issue a prerogative writ will not
normally be exercised by the Court to the exclusion of other available
remedies unless such action of the State or its instrumentality is
arbitrary and unreasonable so as to violate the constitutional mandate
of Article 14 or for other valid and legitimate reasons, for which the
Court thinks it necessary to exercise the said jurisdiction.”
39.5. Therefore, while exercising its jurisdiction under Article 226, the
Court is entitled to enquire into whether the action of the State or its
instrumentalities is arbitrary or unfair and in consequence, in violation
of Article 14. The jurisdiction under Article 226 is a valuable
constitutional safeguard against an arbitrary exercise of State power or
a misuse of authority.
39.6. In determining as to whether the jurisdiction should be exercised in
a contractual dispute, the Court must, undoubtedly eschew, disputed
W.P.(C) 6570/2021 Page 19 of 31
questions of fact which would depend upon an evidentiary determination
requiring a trial. But equally, it is well settled that the jurisdiction under
Article 226 cannot be ousted only on the basis that the dispute pertains to
the contractual arena. This is for the simple reason that the State and its
instrumentalities are not exempt from the duty to act fairly merely
because in their business dealings they have entered into the realm of
contract. Similarly, the presence of an arbitration clause does (sic not)
oust the jurisdiction under Article 226 in all cases though, it still needs to
be decided from case to case as to whether recourse to a public law
remedy can justifiably be invoked.
39.7. The jurisdiction under Article 226 was rightly invoked by the Single
Judge and the Division Bench of the Andhra Pradesh High Court in this
case, when the foundational representation of the contract has
failed. Tsiic, a State instrumentality, has not just reneged on its
contractual obligation, but hoarded the refund of the principal and
interest on the consideration that was paid by Unitech over a decade
ago. It does not dispute the entitlement of Unitech to the refund of its
principal.
24. Similarly, in GAIL v. Indian Petrochemicals Corpn. Ltd.,
(2023) 3 SCC 629, the Supreme Court held as under:-
“21. Although the dispute arises from a commercial contract, we
find that the writ petition challenging the clauses was
maintainable. It is not disputed that GAIL is a public sector
undertaking and thus qualifies under the definition of “State” as
per Article 12 of the Constitution. At the time of entering into
contract, GAIL was enjoying a monopolistic position with respect
to the supply of natural gas in the country. IPCL, having incurred
a significant expense in setting up the appropriate infrastructure,
had no choice but to enter into agreement with GAIL. Thus, there
was a clear public element involved in the dealings between the
parties. Further, writ jurisdiction can be exercised when the State,
even in its contractual dealings, fails to exercise a degree of
fairness or practises any discrimination. We are fortified in our
view by this Court's decision in ABL International [ABL
International Ltd. v. Export Credit Guarantee Corpn. of India
Ltd., (2004) 3 SCC 553] and Joshi Technologies [Joshi
Technologies International Inc. v. Union of India, (2015) 7 SCC
728]”
25. This Court is also not inclined to accept the contention of the
respondents that the present petition is “barred by limitation”.
W.P.(C) 6570/2021 Page 20 of 31
26. In Sudama Devi (Smt.) vs. Commissioner and others., (1983) 2
SCC 1, the Supreme Court observed that period of limitation is not
stipulated for filing a writ petition and maintainability of a petition on
account of delay requires to be adjudged case-to-case basis after
considering as to whether the concerned party is guilty of laches. The
relevant portion of the said judgment reads as under: -
“We are of the view that so far as writ petition under Article 226
of the Constitution is concerned, there can be no hard and fast
rule of 90 days by way of period of limitation but the general rule
of laches alone can be applied and this must necessarily depend
on the facts and circumstances of each case. The High Court has
said in its order that “the writ petition was beyond time by 136
days. Neither the explanation of 136 days nor the explanation for
filing it today, was given.” This view does not appear to be correct
because the High Court has proceeded on the assumption that
there is a period of limitation of 90 days and unless sufficient
cause is shown as contemplated under Section 5 of the Limitation
Act a writ petition filed after the expiration of 90 days is liable to
be rejected. This assumption is wholly unjustified. There is no
period of limitation prescribed by any law for filing a writ petition
under Article 226 of the Constitution. It is in fact doubtful whether
any such period of limitation can be prescribed by law. In any
event one thing is clear and beyond doubt that no such period of
limitation can be laid down either under rules made by the High
Court or by practice. In every case it would have to be decided on
the facts and circumstances whether the petitioner is guilty of
laches and that would have to be done without taking into account
any specific period as a period of limitation. There may be cases
where even short delay may be fatal while there may be cases
where even a long delay may not be evidence of laches on the part
of the petitioner. We would, therefore, set aside the order of the
High Court and remand the writ petition to the High Court so that
the High Court may dispose it of on merits in accordance with
law. We accordingly allow the appeal, set aside the judgment and
order of the High Court and direct that the writ petition may be
disposed of by the High Court on merits in accordance with law.
There will be no order as to costs.”
27. Further, a three Judge Bench of the Supreme Court in VetIndia
W.P.(C) 6570/2021 Page 21 of 31
Pharmaceuticals Ltd vs. State of Uttar Pradesh and Anr., (2021) 1
SCC 804 categorically opined that “writ petition was not barred by
unexplained delay as the appellant had been pursuing the matter with
the authorities and it is they who sat over it”. The relevant portion of
the said judgment reads as under: -
“15. That brings us to the question of delay. There is no doubt that
the High Court in its discretionary jurisdiction may decline to
exercise the discretionary writ jurisdiction on the ground of delay
in approaching the court. But it is only a rule of discretion by
exercise of self-restraint evolved by the court in exercise of the
discretionary equitable jurisdiction and not a mandatory
requirement that every delayed petition must be dismissed on the
ground of delay. The Limitation Act stricto sensu does not apply to
the writ jurisdiction. The discretion vested in the court under
Article 226 of the Constitution therefore has to be a judicious
exercise of the discretion after considering all pros and cons of
the matter, including the nature of the dispute, the explanation for
the delay, whether any third-party rights have intervened, etc. The
jurisdiction under Article 226 being equitable in nature, questions
of proportionality in considering whether the impugned order
merits interference or not in exercise of the discretionary
jurisdiction will also arise. This Court in Basanti Prasadv. Bihar
School Examination Board [Basanti Prasad v. Bihar School
Examination Board, (2009) 6 SCC 791 : (2009) 2 SCC (L&S)
252] , after referring to Moon Mills Ltd. v. M.R. Meher [Moon
Mills Ltd. v. M.R. Meher, AIR 1967 SC 1450] , Maharashtra
SRTC v. Balwant Regular Motor Service [Maharashtra SRTC v.
Balwant Regular Motor Service, (1969) 1 SCR 808 : AIR 1969 SC
329] and State of M.P. v. Nandlal Jaiswal [State of M.P. v.
Nandlal Jaiswal, (1986) 4 SCC 566] , held that if the delay is
properly explained and no third-party rights are being affected,
the writ court under Article 226 of the Constitution may condone
the delay, holding as follows : (Basanti Prasad case [Basanti
Prasad v. Bihar School Examination Board, (2009) 6 SCC 791 :
(2009) 2 SCC (L&S) 252] , SCC p. 796, para 18)
“18. In the normal course, we would not have taken exception
to the order passed by the High Court. They are justified in
saying that a delinquent employee should not be permitted to
revive the stale claim and the High Court in exercise of its
discretion would not ordinarily assist the tardy and indolent
W.P.(C) 6570/2021 Page 22 of 31
person. This is the traditional view and is well supported by a
plethora of decisions of this Court. This Court also has taken
the view that there is no inviolable rule, that, whenever there is
delay the Court must refuse to entertain a petition. This Court
has stated that the writ court in exercise of its extraordinary
jurisdiction under Article 226 of the Constitution may condone
the delay in filing the petition, if the delay is satisfactorily
explained.”
16. The contention of the respondents that they have acted in
accordance with the provisions of the Drugs Act pursuant to the
report of the analyst for misbranded product under Section 9 is
devoid of substance and merits no consideration. It is not the case
of the respondents that the procedure prescribed under Sections
23, 25 and 26 of the Drugs Act has been followed. The feeble
attempt to show compliance with provisions of the Drugs Act by
alleged purchase of the samples under Form 14-A at Annexure R-
5 to the counter-affidavit dated 21-7-2008 from an unknown
source and date must be rejected outright as an attempt to create
evidence where none exists.
17. The aforesaid discussion, therefore, leads us to the conclusion
that the writ petition was not barred by unexplained delay as the
appellant had been pursuing the matter with the authorities and it
is they who sat over it, triggering rejection of the appellant's
tender by the Rajasthan Government on 5-7-2019 leading to the
institution of the writ petition on 24-7-2019. The High Court
therefore erred in dismissing the writ petition on grounds of delay.
The illegality and the disproportionate nature of the order dated
8-9-2009, with no third-party rights affected, never engaged the
attention of the High Court in judicious exercise of the
discretionary equitable jurisdiction. Consequently, the impugned
order [Vetindia Pharmaceuticals Ltd. v. State of U.P., 2019 SCC
OnLine All 6734] of the High Court as well as the order dated 8-
9-2009 of the respondents are set aside, and the appeal is
allowed.”
28. It is noticed that in the present petition as well the petitioner has
been pursuing the matter with the respondents ever since it preferred a
representation dated 11.01.2017 before the Appellate Authority of
respondent no.2 against the decision of putting the petitioner on
W.P.(C) 6570/2021 Page 23 of 31
“Holiday List” (vide communication dated 21.12.2016). Even pursuant
to the passing of order dated 26.05.2017 by the Appellate Authority,
between 2017 and 2020, the petitioner made various representations
before the respondents for redressal of the said matter. Importantly,
vide a letter dated 11.06.2019, the respondent no.2 intimated the
petitioner that the said issue has been referred to respondent no.1 and
petitioner shall contact the latter thereof. The said communication
dated 11.06.2019 reads as under: -
W.P.(C) 6570/2021 Page 24 of 31
29. Subsequently, since no action/response was received despite
multiple representations, the petitioner ultimately issued a legal notice
dated 10.02.2021 to the respondent no.1. However, to no avail.
30. Evidently, therefore, the petitioner had been proactively
pursuing the matter with the respondents, however, the respondents
were remiss in taking a suitable decision. In the peculiar factual
backdrop, it cannot be said that the petition is not maintainable on
account of delay or laches.
31. On merits, the primary grievance canvassed by the learned
senior counsel on behalf of the petitioner is that in light of the decision
dated 26.05.2017 passed by the Appellate Authority of respondent
no.2, the allegations of forgery and fraudulent practice forming the
very basis for forfeiture of the EMD-BG under the clause 36.8.1 of
GCC by respondent no.1 ceased to exist. In such circumstances,
respondent no.1 ought to have not continued to retain the said EMD-
BG, particularly in the absence of any independent enquiry or cogent
finding casting aspersions on the bonafides of the petitioner.
32. Evidently, the controversy between the parties arose as regard
the veracity of certificate dated 18.04.2016 bearing ref:
GGEL/HR/Mech./2015-16 (stated to be issued by GGEL) submitted
by the petitioner during the bidding process. The respondent no.1,
upon receipt of letter dated 17.10.2016 from the respondent no.2 in
this regard, on account of the alleged violation, invoked clause 36.8.1
of the GCC and forfeited the EMD-BG furnished by the petitioner.
Clause 36.8.1 of the GCC reads as under:-
W.P.(C) 6570/2021 Page 25 of 31
33. Despite the Appellate Authority of respondent no.2 discharging
the petitioner from the alleged violation (as communicated vide letter
dated 17.10.2016) vide order dated 26.05.2017, the rationale for
continuing to retain the forfeited EMD-BG in terms of clause 36.8.1 of
the GCC by respondent no.1, as canvassed on behalf of the respondent
no.1, is that (i) the forfeiture of EMD-BG by respondent no.1 is
independent of any action/inaction on part of respondent no.2 (which
acted as the project consultant for respondent no.1) (ii) during the
bidding process the petitioner with a malafide intention deliberately
furnished a forged and fabricated certificate dated 18.04.2016 bearing
ref: GGEL/HR/Mech/2015-16 to secure the bid. In this regard, reliance
has been placed upon an email dated 10.10.2016, whereby, the GGEL
in response to a query raised by the respondents as to the veracity of
the aforementioned certificate furnished by the petitioner, refuted
issuance of the same.
34. However, this Court is unable to uphold the aforesaid rationale
advanced by the learned counsel on behalf of the respondent no.1 for
retention of the forfeited EMD-BG inasmuch as:
i. the petitioner by virtue of order dated 26.05.2017 passed by the
W.P.(C) 6570/2021 Page 26 of 31
Appellate Authority of respondent no.2 has been exonerated of
the allegation of forgery/fraud that at the very first instance led
to issuance of letter dated 17.10.2016 by respondent no.2 to
respondent no.1 and consequent invocation of clause 36.8.1 of
the GCC by the respondent no.1 for forfeiture of the EMD-BG
furnished by the petitioner.
ii. In view of the aforesaid, no action/ enquiry was undertaken/
made by the respondent no.1 to go into the allegation of forgery/
fraud levied against the petitioner.
iii. The petitioner specifically apprised the respondents that the very
rationale of the order dated 26.05.2017 passed by the Appellate
Authority was that the allegations of forgery/fraud against the
petitioner were unfounded. As a consequence, thereof, pursuant
to the decision of the Appellate Authority, rationale for
forfeiture of EMD-BG also stood dissipated/ extinguished.
iv. The reliance by respondent no.1 upon an email dated
10.10.2016 issued by the GGEL to justify the allegation of
fraud/forgery is misplaced inasmuch as it disregards subsequent
emails dated 20.10.2016 and 23.11.2016 sent by GGEL itself,
clarifying the matter. All the certificates that found their way to
the respondent no.2, were dealt with and explained in the
aforementioned emails by the GGEL. It is pointed out that the
certificate enclosed as Exhibit no.2 in email dated 20.10.2016
(dated 18.04.2016 bearing ref: GGEL/HR/Mech/2015-16),
issuance of which was earlier refuted by the GGEL, was a draft
certificate. The actual certificate that came to be issued by the
W.P.(C) 6570/2021 Page 27 of 31
GGEL i.e., certificate dated 18.04.2016 bearing ref:
GGEL/HR/Mech/2016/02, was enclosed as Exhibit no.3 to the
email dated 20.10.2016 and the contents of the same are not at
variance with the said draft certificate.
It clearly transpires that it was only on account of an
erroneously sent “draft certificate”, that a confusion arose as to
whether the same was fabricated. The correct position, having
been explained by the author of the concerned certificates, the
matter clearly stood explained in terms of the said emails dated
20.10.2016 and 23.11.2016.
Evidently, it was for this reason that the order dated 21.12.2016
whereby the petitioner had been sought to be “holiday listed”
was revoked by the Appellate Authority. After the controversy
stood resolved in this manner, there was no occasion for
respondent no.1 to retain the amount released by way of
encashment of EMD-BG of Rs.47,50,000/-
v. The aforesaid clarification/s were also brought to the attention
of the Chairman and Managing Director of respondent no.2 by
the petitioner vide a letter dated 09.12.2016. The same was not
refuted/ replied.
vi. Undisputedly, a tender dated 12.06.2017 re-floated by
respondent no.2 for the same work (as tender dated 09.11.2015)
was awarded in favour of the petitioner by the respondent no.2
vide an award dated 08.08.2017. Not only was the said work
completed by the petitioner but for the same Pre-
Commissioning Certificate came to be issued by the respondent
W.P.(C) 6570/2021 Page 28 of 31
no.1 as under: -
W.P.(C) 6570/2021 Page 29 of 31
W.P.(C) 6570/2021 Page 30 of 31
vii. Moreover, attention has also been brought to a letter dated
10.02.2022 issued by the General Manager of respondent no.2
to respondent no.1 (handed over during the course of
proceedings), whereby, respondent no.2 opined that “in view of
the fact that PCTL (petitioner herein) is already exonerated fully
of charges of forgery of documents, retaining EMD is not
recommended” and advised respondent no.1 to return the
forfeited EMD-BG to the petitioner by way of amicable
settlement. The said letter reads as under:-
W.P.(C) 6570/2021 Page 31 of 31
35. In the circumstances, since the very premise for forfeiture of the
EMD-BG stood dissipated, therefore, there is no justification for
respondent no.1 in retaining the said amount. The action taken by the
respondent no.1 in retaining the said amount is inconsistent with the
decision of the Appellate Authority whereby the petitioner was
exonerated of the very same allegation which was the very basis for
forfeiture of EMD-BG.
36. In the circumstances, the respondent no. 1 is directed to refund
the EMD-BG amount of Rs. 47,50,000/- to the petitioner within a
period of 4 weeks from today.
37. The petition is disposed of in the above terms.
SACHIN DATTA, J
FEBRUARY 2, 2026/sl
Legal Notes
Add a Note....