HI

Power Grid Corporation of India Limited Vs. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors.

  Supreme Court Of India C.A. No.14780-14781 of 2025; C.A. No.13153 of 2026
Link copied!

Case Background

As per case facts, Power Grid Corporation of India Limited (PGCIL) raised a tariff claim for two Line-In Line-Out (LILO) assets at Tuticorin Pooling Station, commissioned in early 2015. The ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

2026 INSC 1237 Page 1 of 51

C.A. No.14780-14781 of 2025 etc.

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

Civil Appeal Nos.14780-14781 of 2025

Power Grid Corporation of India Limited

...Appellant

Versus

Tamil Nadu Generation and Distribution Corporation

Limited (TANGEDCO) & Ors.

...Respondents

With

Civil Appeal No.13153 of 2026

J U D G M E N T

K. VINOD CHANDRAN, J.

The controversy in the above appeals is pinned on the

tariff claim raised by the appellant, separately for two LILOs

(Line-In Line-Out/Loop-In Loop-Out) at the two circuits of

Tuticorin JV-Madurai 400kV D/C (Quad) transmission line

(hereinafter ‘Tuticorin JV-Madurai line’) at the Tuticorin Pooling

Station. The first LILO was commissioned on 04.01.2015 and the

second, identically located, commissioned on 08.01.2015. That

the generating company (Moxie Power Generation Limited,

Page 2 of 51

C.A. No.14780-14781 of 2025 etc.

formerly known as Coastal Energen Private Limited) produced

electricity, which was transmitted through the lines of Power

Grid Corporation of India Ltd . (PGCIL), the Central

Transmission Utility (CTU); the Inter-State Transmission

License, it’s receipt and consequential supply to consumers by

the distribution licensee for the State of Tamil Nadu (Tamil Nadu

Generation and Distribution Corporation Limited , the

TANGEDCO) are admitted. The generation, transmission,

supply and end use being admitted, the issue revolves around

whether the LILOs were operational, functional and used in the

transmission. The generating company and TANGEDCO

asserts that it was never used; the Commercial Operation Date

(COD) having not been approved under the Central Electricity

Regulatory Commission (Terms and Conditions of Tariff)

Regulations, 2014 (Tariff Regulations). There could, hence, be

no factoring of the LILOs in the tariff especially since the

upstream transmission lines from the Tuticorin Pooling Station

to the Salem Pooling Station leading up to Madhugiri having not

been installed or commissioned till 01.12.2016. The period for

which the claim is raised is between 04.01.2015 up to

27.10.2016; with respect to the LILOs of the first circuit and

Page 3 of 51

C.A. No.14780-14781 of 2025 etc.

08.01.2015 to 27.10.2016 insofar as the LILOs in the second

circuit. The date 27.10.2016 is relatable to the date on which the

generating company built its dedicated transmission line (DTL)

directly to the Tuticorin Pooling Station.

Arguments of the Appellant : -

2. Mr.Ramji Srinivasan, learned Senior Counsel appearing

for the PGCIL pointed out that the two LILOs were approved by

the Central Electricity Regulatory Commission (CERC) by

order dated 29.07.2016, accepting the COD as proffered by the

PGCIL, which was overturned by the Appellate Tribunal for

Electricity (APTEL) thus denying transmission charges on that

element, for the period during which the LILOs were functional

and put to use for transmission of the power generated by the

generating company to TANGEDCO. There being no DTL

constructed by the generating company, the tariff has to be

determined on a non-PoC (Point Of Connection) basis. The

learned Senior Counsel specifically referred to the minutes of

the 29

th

, 30

th

and 38

th

Meetings of the Standing Committee which

comprehensively dealt with the Southern Region Transmission

Scheme, finalizing the Tuticorin Pooling Station and associated

evacuation lines. Reliance was also placed on the 5

th

Joint Co-

Page 4 of 51

C.A. No.14780-14781 of 2025 etc.

ordination Committee Meeting on 22.07.2011. The generating

companies, two at that point, entered into Bulk Power

Transmission Agreements (BPTA), undertaking to construct and

commission their DTLs directly to the Tuticorin Pooling Station,

simultaneous to the COD of their generating units on 24.02.2010

which stood amended on 08.09.2011. The minutes of the

meetings of the Standing Committee along with the Annexures

to the BPTA clearly indicate that the LILOs were a permanent

infrastructure, the use of which commenced even before the

upstream transmission lines, leading to Salem and Madhugiri

were constructed and made operational.

3. The two LILOs were respectively commissioned in full

compliance with the statutory framework but with a delay of

less than nine months; the scheduled date of commission of the

transmission system being 11.04.2014. The COD was approved

by the CERC after verification of the Regional Load Despatch

Centre (RLDC) certificate, issued on successful trial operation

and the Central Electricity Authority (CEA) certificate issued

under Regulation 43 of Central Electricity Authority (Measures

Related to Safety & Electricity Supply) Regulations, 2010 (CEA

Regulations) as also approvals obtained in the 30

th

Standing

Page 5 of 51

C.A. No.14780-14781 of 2025 etc.

Committee pursuant to Regulation 4(3) of the Tariff Regulations.

The Standing Committee’s decisions have a statutory binding

force under Section 29(4) of the Electricity Act. Neither

TANGEDCO nor the generating companies placed any material

to challenge the factual commissioning of the LILOs as

approved by the CERC. The CERC by its order clearly held that

since the generating company delayed the construction of the

mandatory DTL and utilised PGCIL’s LILO lines they were liable

to bear the transmission charges under Section 10 of the

Electricity Act until regular commissioning of their DTLs.

4. The finding of the Appellate Tribunal for Electricity

(APTEL), that the LILOs had no beneficial use runs contrary to

the admitted fact of utilisation for transmission of electricity,

from the generating company to the distribution licensee. The

delay in the upstream transmission lines from the Tuticorin

Pooling Station to Salem and Madhugiri did not at all affect the

transmission of electricity from the initial date of its generation

i.e. 23.12.2014. It was facilitated initially through the Tuticorin

JV-Madurai line directly and from the commissioning of LILOs

through the Tuticorin Pooling Station, despite the upstream

transmission lines to Salem and Madhugiri having not been

Page 6 of 51

C.A. No.14780-14781 of 2025 etc.

commissioned. The Tuticorin JV-Madurai line was also a part of

the evacuation plan, which too served as an upstream

transmission line. The seamless transmission of electricity

requires the LILOs to be factored in the tariff, which was rightly

carried out by the CERC, erroneously reversed by the APTEL.

5. The defence taken that the Short-Term Open Access

(STOA) and Medium-Term Open Access (MTOA) charges

absolve the generator from paying capital cost transmission

tariff, proceeds on a fundamental misconception of the tariff

regulatory framework. The transmission tariff as distinguished

from Open Access charges is determined by CERC under

Sections 61 and 62 of the Electricity Act to service capital

expenditure, return on equity, interest on loans, and

depreciation broadly termed as Yearly Transmission Charges

(YTC), while the open access charges are operational charges

computed by the National Load Despatch Centre (NLDC). The

STOA/MTOA would contain a certain portion of YTC for fixed

assets for which tariff had been determined by the CERC; at

which point of time the tariff for LILO assets were yet to be

determined and therefore did not form part of the STOA/MTOA.

The open access charges collected are adjusted against the

Page 7 of 51

C.A. No.14780-14781 of 2025 etc.

Point of Connection (PoC) base pool, only after commissioning

of the DTL directly from the generating station to the Tuticorin

Pooling Station, after which the asset charges were socialised

into the PoC pool and bilateral billing was stopped on the

generating company. Essentially, the subject recovery from the

generating unit is for the period between the COD of the LILOs

and the commissioning of the DTL. The tariff order in the

disputed period was issued on 29.07.2016, when the YTC of the

subject LILOs were not included in the regional PoC base pool,

and was applicable only till the DTL was commissioned, which

occurred on 27.10.2016.

6. In conclusion, it is submitted that paragraph 72 of the

CERC order actually recorded the contention of TANGEDCO

but erroneously put it forth as the CERC’s opinion clearly

contrary to the spirit of the order of the CERC. In fact, the CERC

had in paragraph 73 specifically raised the question of the

liability with respect to the transmission charges in the context

of upstream/ downstream transmission system not being ready

which was dealt with on a perusal of the minutes of the meetings

of the Standing Committee, eventually ruling in favour of the

PGCIL. The two LILOs having been put to actual commercial use

Page 8 of 51

C.A. No.14780-14781 of 2025 etc.

by the generating company for supply to TANGEDCO, in

evacuating power, the transmission licensee cannot be denied

recovery of tariff on an erroneous standard of ‘beneficial use’,

unheard of in transmission parlance and an artificial reopening

of COD.

Arguments of the Respondents: -

7. Mr. Sajan Poovayya, learned Senior Counsel appeared for

Moxie Power Generation Limited (formerly Coastal Energen

Private Limited), the generating company. It was asserted on

the basis of Annexure A1, pictorial depiction of the evacuation

arrangement for Long Term Open Access (LTOA) projects in

the Tuticorin area, that the subject LILOs, the use of which is

sought to be included in the tariff, was never put to

use. According to him, the LILO referred to under the Standing

Committee Meetings (SCMs) is the one which connected the

generating station with the Tuticorin JV-Madurai transmission

line through which the energy evacuation was carried out and

drawn by TANGEDCO for the purpose of supply and end use of

consumers. Electricity, it is contented was transmitted

seamlessly; as is wont to happen in the event of zero resistance,

though the Tuticorin JV-Madurai line for onward transmission to

Page 9 of 51

C.A. No.14780-14781 of 2025 etc.

Trichy, where TANGEDCO received it. The DTL which was to

be constructed by the generating station and the delay in such

construction is immaterial insofar as the upstream infrastructure

for transmission of electricity from the Tuticorin Pooling Station

to the Salem Pooling Station and then to Madhugiri had not

materialised till much later. The generating unit though was

granted LTOA since the upstream connection had not

materialised, a LILO was created in the Tuticorin JV-Madurai

line through which evacuation of power was commenced on

24.10.2014 under STOA and then continued as a MTOA, paying

the applicable charges for transmission of electricity. The DTL

to the Tuticorin Polling Station was commissioned on

27.10.2016, well in advance of PGCIL's upstream Tuticorin-

Salem Pooling Station line, which came into operation only on

13.11.2016. It was still later on 01.12.2016, the LTOA to the

generating unit was operationalised. The PGCIL's LILO had

started operation only after the commissioning of the PGCIL's

upstream transmission system on 13.11.2016.

8. The contention also is that there can be no liability on the

generating company and the subject claim is unsustainable

since the statutory mandate for declaration of COD; where

Page 10 of 51

C.A. No.14780-14781 of 2025 etc.

there is failure of either of the contracting parties, was not

followed. The LTOA having not been operationalised during the

subject period, when transmission charges were levied on a

STOA/MTOA basis, there could be no further claim set up by

the CTU. The statutory scheme under Regulation 4(3)(ii) and

Regulation 12 (2) of the Tariff Regulation mulcts liability on a

generator only when the COD is declared as per the

Regulations. The directions by the APTEL to get declared the

COD is apt in the facts and circumstances of the case. The

generating unit having commenced evacuation of power before

the PGCIL’s LILOs were operationalised as per the BPTA it

could have continued seamlessly even without the intervention

of the PGCIL LILOs; based solely on the LILO of one circuit in

the Tuticorin JV-Madurai line, at the generating station. The

interim arrangements continued till the upstream transmission

lines were operationalised which was later to the

commissioning of the DTL, thus making irrelevant the delay in

commissioning of the DTL. If the CERC declares, on the remand

made, that the COD of the LILOs is as claimed by PGCIL,

definitely the liability would fall on the generating company.

But otherwise, the end consumers would be unnecessarily

Page 11 of 51

C.A. No.14780-14781 of 2025 etc.

mulcted with a liability, without actual use of the subject assets,

in the transmission; is the contention.

9. Ms.Vrinda Bhandari, learned Advocate on Record,

appearing on behalf of the TANGEDCO adopted the arguments

of the generating company and stressed upon paragraph 72 of

the CERC’s order which findings were in affirmation of the

contention raised by TANGEDCO. It is also argued that the

subject assets; being the PGCIL’s LILOs were not independent

transmission assets and were an integral part of the composite

transmission arrangement for evacuation of power from the

generating stations at Tuticorin through the Tuticorin Pooling

Station and the associated 765 kV upstream transmission

system. It was urged that APTEL was correct in holding that the

COD does not depend upon the facility being made viable, and

the liability on the generating unit could only arise if it is

capable of serving its purpose; which was not possible till the

upstream transmission system was established and made

operational. Hence, the beneficial use as contemplated by the

APTEL was perfectly in order.

Page 12 of 51

C.A. No.14780-14781 of 2025 etc.

The Order of the CERC : -

10. The CERC looked at the investment approval dated

12.12.2011 and the modified Revised Cost Estimates (RCE)

dated 23.02.2015. The scope of work was indicated to be the

LILO in both circuits of Tuticorin JV–Madurai line and

establishment of 400kV Pooling Station at Tuticorin, initially

charged at 400kV including 1x80 MVAR bus reactor. The

elements covered in the scope of the project, was first claimed

as a single asset for the purpose of tariff, while the LILOs in the

first circuit and the second circuit of the Tuticorin JV–Madurai

line, was claimed separately under various heads. TANGEDCO

required the cost to be checked prudently and had challenged

the claims under various heads as also assailed the specific

claim with respect to the LILOs on the ground that without

commissioning the other elements of the common transmission

system, the LILOs cannot be practically put to use. The specific

contention of TANGEDCO was that the LILOs upon which the

claim was raised was redundant until the Salem and Madhugiri

Pooling Stations providing upstream connectivity from the

Tuticorin Pooling Station is put under Commercial Operation.

Page 13 of 51

C.A. No.14780-14781 of 2025 etc.

11. The date of Commercial Operation (COD) was accepted

as 04.01.2015 and 08.01.2015 for the two LILOs termed Asset 1

and Asset 2 respectively. This was also based on the RLDC’s

successful trial operation certificate and the CEA Certificate, as

also the implementation of 1x80 MVAR bus reactor at the

Tuticorin Pooling Station. While the delay occurred was

explained by PGCIL, it was found to be not substantiated with

valid reasons for which liberty was left to the PGCIL to provide

documentary proof at the time of truing-up. The aspect of the

time over-run having not been condoned, it had a bearing in

determination of the amounts to be quantified under the various

heads, wherein the scheduled COD was reckoned rather than

the actual COD.

12. The CERC eventually considered the question as to who

would bear the transmission charges and found the minutes of

the 30

th

SCM held on 05.05.2010 would be relevant from which

the following was quoted:

“5.0 Transmission System Associated with the

Coastal Energen Pvt Ltd (2x660 MW) and IND Barath

Power Ltd (2x660 MW) projects in Tuticorin area of

Tamil Nadu:

Page 14 of 51

C.A. No.14780-14781 of 2025 etc.

5.1 Chief Engineer, CEA explained that the Tuticorin

Pooling Station-Tutlcorin JV Station (of NLC) 400kV D/C

Quad Line was inter-alla agreed as part of the

transmission system associated with the Coastal

Energen Pvt Ltd (2x600 MW) and IND Barath Power Ltd

(2x660 MW) projects in Tuticorin area of Tamil Nadu.

Later, NLC informed that they could spare only one bay

at their Tuticorin JV station. As such, considering space

constraint and better capacity utilization of the 400kV

quad D/C line, it is now proposed that instead of the

Tuticorin Pooling Station of Tuticorin DV Station 400kV

D/C line, both the circuits of Tuticorin JV-Madurai

400kV Quad D/C line may be LILOed at Tuticorin

Pooling Station.

-----------------------

5.2 After discussions, the above proposed

modifications in the transmission system for the Coastal

Energen Pvt. Ltd (2x600 MW) and IND Barath Power Ltd

(2x660 MW) projects in Tuticorin area of Tamil Nadu

were agreed.”

13. Based on the above as per the RLDC Certificate, the LILO

in one circuit was intended for the use of Coastal Energen, as a

measure of extraction at the Tuticorin JV–Madurai Line, a

temporary line for evacuation of power from the generating

station and again LILO-ed at the Tuticorin Pooling Station on the

Page 15 of 51

C.A. No.14780-14781 of 2025 etc.

Tuticorin JV-Madurai Line. The LILO by Coastal Energen was

found to be a temporary measure which was liable to be

dismantled, according to the CERC, within six months from the

date of the issue of the order; obviously on commissioning of

the DTL. Reliance was placed on a connected matter and it was

held that the transmission charges for the instant assets, i.e. the

two LILOs termed Asset 1 and Asset 2 were to be borne by

Coastal Energen and Ind-Barath Power till the commercial

operation of the DTL up to the Tuticorin Pooling Station, which

was the obligation of Coastal Energen and Ind-Barath were

occasioned. Ind-Barath never commenced operation.

Pertinently, despite being made a party, the generating

company did not appear before the CERC to raise its

contentions.

The Order of the APTEL: -

14. The APTEL considered the issue of Non-PoC charges of

Rs.15,43,26,909/- for the period between 04.01.2015 to

27.10.2016. APTEL framed five issues and answered them in the

following manner :

(i) The LILO of both circuits of the Tuticorin JV- Madurai

line at Tuticorin Pooling Station was a permanent part

Page 16 of 51

C.A. No.14780-14781 of 2025 etc.

of the transmission plan, as approved in the 30

th

SCM

and sanctioned by the CERC in Petition No.233 of 2009.

(ii) The decision of the CERC to grant COD of the assets

under consideration is not correct since the correct

procedure was not adopted; namely the procedure

under Regulation 4 (3)(ii) of the Tariff Regulations,

2014.

(iii) The subject assets being not a temporary

arrangement, PGCIL was not liable to bear its cost on

a Non-PoC basis.

(iv) The construct of PoC transmission charges is based on

usage and hence no transmission charges could be

claimed by PGCIL for the assets since no power was

flowing through these LILOs.

(v) The availability of Dedicated Transmission Line (DTL)

of the generating company is irrelevant since

upstream transmission from Tuticorin to Salem and

Madhugiri Pooling Stations was not operationalized,

thus disabling the full power of the generating station

from being evacuated. The COD of the LILO as granted

by the CERC needs to be reviewed.

Page 17 of 51

C.A. No.14780-14781 of 2025 etc.

Hence while finding the LILO to be a permanent structure of the

evacuation arrangement, it was held that the same were not put

in use. In the review filed by PGCIL the matter was remanded

to the CERC for determination of the COD of the LILOs; which

order is impugned in the other appeal.

Preliminary Analysis: -

15. For better understanding of the controversy, we have to

necessarily look at the pictorial depiction as seen at Annexure

A-1 (extracted hereinbelow, a little later) which clearly

indicates that the LILOs at Tuticorin Pooling Station on the

Tuticorin JV–Madurai Line intercepted the two circuits of the

said line. Hence, on evacuation of power, from Coastal Energen

and Tuticorin JV; the two generating stations, to the Tuticorin

JV–Madurai Line, it had to be necessarily intercepted at the

LILO for the purpose of routing it through the Tuticorin Pooling

Station and send back to the Tuticorin JV–Madurai Line for

onward transmission to Madurai and its eventual receipt by the

distribution licensee, TANGEDCO, at the downstream

transmission lines. We would elaborate on this when we look

at the statutory scheme of transmission of electricity and the

Page 18 of 51

C.A. No.14780-14781 of 2025 etc.

necessity of a Pooling Station. Suffice it to notice, for the present

that Tuticorin JV is a generating station set up by the Neyveli

Lignite Corporation (NLC) and TANGEDCO as a joint venture

(JV). By the introduction of two other generating stations, as

originally contemplated there were multiple sources; stations,

of electricity generation.

16. The argument of the generating company that electricity

moves through the path of least resistance though indubitable

is fundamentally flawed on the facts herein and does not

support the contention of no beneficial use of the LILOs having

been made. The pictorial depiction clearly indicates that after

evacuation of power through the temporary LILO put up by the

Coastal Energen in the Tuticorin JV–Madurai Line, there is a

diversion through the permanent LILO of the PGCIL, at the

Tuticorin Pooling Station. The free flow of electricity through the

path of least resistance hence supports the plea of PGCIL that

on its interception at the Loop-In/Line-In, the path of least

resistance is the one leading to the Tuticorin Pooling Station and

from there, after stabilization, through the Loop-Out/Line-Out,

back to the Tuticorin JV–Madurai Line. There cannot be two

opinions on this, and the contention raised is rejected. We also

Page 19 of 51

C.A. No.14780-14781 of 2025 etc.

notice the specific contention taken up by the generating

company, in its appeal before the APTEL, which is as under: -

“…..It is submitted here that the Appellant has

commissioned its first unit on December 23, 2014, and

has been using Tuticorin Pooling Station to evacuate

power under STOA/MTOA since then. Further MTOA of

558 MW has been provided by the Respondent No.2 to

Appellant on the instant transmission assets (LILG) for

supplying power to TANGEDCO for the period from

1.7.2015 to 30.6.2018. The MTOA stands duly

operationalized and it is evident that the subject

transmission system was being used. In view of this, it

could be stated that the instant assets are and will be

used to evacuate power for Southern Region

Beneficiaries, it is therefore submitted before the

Hon'ble Commission that the transmission charges for

the same must be shared by all beneficiaries through

the PoC mechanism.”

Hence, the use of LILOs was admitted and the contention was

only of sharing, which cannot be raised without commissioning

the DTL.

17. At the risk of repetition, it cannot but be observed that

admittedly the generation commenced on 23.12.2014 upon

which the power was evacuated through the Tuticorin JV-

Page 20 of 51

C.A. No.14780-14781 of 2025 etc.

Madurai 400/220 kV lines by creating a LILO on one of the

circuits of the said lines which continued seamlessly during the

disputed subject period also. Hence, generation, transmission,

supply and consumption are clearly admitted and there arose

no situation where the generating station held its horses, after

it become operational and ready for generation of power; thus,

creating a liability on the CTU which had the responsibility and

obligation to transmit electricity on its generation. The issue is

only as to whether the two LILOs created as intervention to the

two circuits on the Tuticorin JV-Madurai line was used or not;

which on its commissioning is a foregone conclusion.

18. The PGCIL categorically asserted that the two LILOs were

made operational on 04.01.2015 and 08.01.2015 respectively.

We will deal with the issue of COD a little later; which we have

to merely notice now, as having been found by the CERC to be

on the dates projected. While according to the generating unit,

the Tuticorin Pooling Station could be operated only on the

upstream connection established, the contention of the

appellant is that the power generated and evacuated from the

generating unit had to be first brought to the Pooling Station

through the Line-In (Loop-In) from the Tuticorin JV-Madurai line

Page 21 of 51

C.A. No.14780-14781 of 2025 etc.

and then pooled out from the Line-Out (Loop-Out) back to the

Tuticorin JV-Madurai line which was a part of the plan

contemplated for evacuation of power from the generating units

in the Tuticorin area, strengthening the Southern Region

Transmission. Hence, the upstream transmission lines from the

Tuticorin Pooling Station to Salem Pooling Station, though

delayed did not cause any hindrance to the power generated

by the generating unit and the same was transmitted to the

purchaser, the distribution licensee, who had supplied it to the

end consumers, de hors the upstream line to Salem not being

established.

19. In fact, the plan comprehensively contemplated the

LILOs as an integral part of the composite transmission

agreement as admitted by TANGEDCO. The situation of the

creation and operation of the LILO of the PGCIL, puts in place

the evacuation arrangement of power in the Tuticorin area. This

makes relevant the delay in establishment of the DTL directly to

the Tuticorin Pooling Station, which was the obligation of the

generating company. The claim raised by the appellant is not

from the date of generation which is 23.12.2014 and does not

extend after the DTL was established by the generating

Page 22 of 51

C.A. No.14780-14781 of 2025 etc.

company, which was on 27.10.2016. The claim is within the

period of the operation of the LILOs on 04.01.2015 and

08.01.2015 up to 27.10.2016 when the DTL was established and

made operational.

Questions of Law -

20. The questions of law, hence arising from the orders

challenged; one in original and the other in review are the

following: -

I. Whether the transmission licensee, the appellant PGCIL,

is entitled to transmission tariff, including the element of

the two LILOs spanning over 10 kms, bringing in the

power generated to the Tuticorin Polling Station and then

transmitting it further through the Tuticorin JV–Madurai

line especially since the LILOs were a part of the statutory

planning under Section 29(4) of the Electricity Act, 2003

and the BPTA ?

II. Whether the Appellate Tribunal was right in law in its

interpretation of Regulation 4(3)(ii) of the Tariff

Regulations in directing the CERC to consider the COD of

the LILOs when already it has been approved by the

CERC ?

Page 23 of 51

C.A. No.14780-14781 of 2025 etc.

III. Whether the delay in construction of the DTL would

enable the liability for the period between

04.01.2015/08.01.2015 and 27.10.2016 to be mulcted on

the generating company ?

The Statutory Scheme -

21. While the appellant, PGCIL banks on the delay in

establishing and operationalisation of the DTL by the

generating company, the generating company and the

distribution licensee; TANGEDCO, projects the delay in

establishing and operationalisation of the upstream

transmission lines between Tuticorin and Salem Pooling

Stations to be determinative of the absence of any liability on

the generating company or the distribution licensee. The

upstream transmission lines and the downstream transmission

system referred to in Regulation 4(3)(ii) having not been

defined in the statute, we have to look at the statutory scheme

to better understand the rival contentions of the parties.

22. Generation of Electricity is dealt with in Part III of the

Electricity Act, 2003. A generating company is entitled to

establish, operate and maintain a generating station without

Page 24 of 51

C.A. No.14780-14781 of 2025 etc.

obtaining a licence under the Act, if it complies with the

technical standards relating to connectivity with the grid

referred to in clause (b) of Section 73. A generating station also

includes a hydro-electric generation and captive generating

station, which has additional requirements to be satisfied under

Sections 8 and 9; which we are not concerned with. Section 10

stipulates the duties of the generating companies, which are; to

establish, operate and maintain generating stations, tie-lines,

sub-stations and dedicated transmission lines (DTL) connected

therewith in accordance with the provisions of the Act, the Rules

and the Regulations. A DTL is defined under clause (16) of

Section 2 as any electric supply-line for point-to-point

transmission required for the purpose of connecting electric

lines or electric plants, also under Section 9 and Section 10, to

any transmission lines or sub-stations or generating stations or

the load centre. The DTL, hence, is the obligation of the

generating station.

23. Part V of the Act deals with the Transmission of Electricity,

which includes both inter-State and intra-State transmission. For

the purpose of inter-State transmission, the Central

Government is empowered to make a region-wise demarcation

Page 25 of 51

C.A. No.14780-14781 of 2025 etc.

of the Country for the efficient, economical and integrated

transmission and supply of electricity as per Section 25. Section

26 speaks of a National Load Despatch Centre (NLDC) for

optimum scheduling and despatch of electricity between the

Regional Load Despatch Centres (RLDCs); which RLDC’s are

established under Section 27. Insofar as the intra-State

transmission is concerned, the State Commission is empowered

to facilitate and promote transmission, wheeling and inter-State

transmission connection within its territorial jurisdiction under

Section 30 for effective functioning for which a State Load

Despatch Centre (SLDC) is constituted under Section 31. The

functions of the NLDC are as prescribed by the Central

Government under sub-section (2) of Section 26 and that of the

RLDC and SLDC are delineated respectively under Section 28

and Section 32. While the Central Transmission Utility (CTU) as

notified by the Central Government under Section 38

undertakes establishment and facilitation of inter-State

transmission under Section 38, the distribution licensees under

Section 42 are obliged to develop and maintain an efficient, co-

ordinated and economic distribution system in their area of

supply. The State Transmission Utility as notified under Section

Page 26 of 51

C.A. No.14780-14781 of 2025 etc.

39 has an obligation to undertake transmission of electricity

through the intra-State transmission system.

24. It is the CEA constituted under Section 70 which specifies

the technical standards for construction of electrical plants,

electric lines and connectivity to the grid, the compliance of

which, as provided under clause (b) of Section 73, is stipulated

in Section 7, with reference to a generating company setting up

a generating station. The ‘Grid’ is defined under clause (32) of

Section 2, which means “the high voltage backbone system of

inter-connected transmission lines, sub-stations and generating

plants” (sic). The transmission lines are defined under clause

(72) of Section 2, which means all high-pressure cables and

overhead lines, not being an essential part of the distribution

system of a licensee, transmitting electricity from a generating

station to another generating station or a substation with an

intervening step-up and step-down transformer, switch-gear

and other works necessary and used for the control of such

cables or overhead lines.

25. Here, we should also have a better understanding of what

a Pooling Station is and the purpose it serves. A Pooling Station

is defined under the Central Electricity Regulatory Commission

Page 27 of 51

C.A. No.14780-14781 of 2025 etc.

(Indian Electricity Grid Code) Regulations, 2023. The Preamble

of the said Regulation refers to the definition of ‘Grid’ in sub-

section (32) of Section 2 of the Electricity Act, which is extracted

hereinabove, as a backbone system. Keeping in view the

mandate and statutory framework as envisaged in the Act for

stable, reliable and secure grid operation in order to achieve

maximum economy and efficiency of power system, the grid

code is brought in; which apart from the provisions relating to

the role of various statutory bodies and organizations and

functional linkages contains extensive provisions pertaining to

various aspects as delineated thereunder. A Pooling Station is

defined as ‘the ISTS grid sub-station where pooling of generation

of connected individual generating stations is done for interfacing

with the next higher voltage level’. It has to be specifically

observed that in the subject evacuation arrangement, the

Tuticorin Pooling Station was to aggregate power from three

sources; Tuticorin JV, Coastal Energen and Ind-Barath. The

Pooling Station acts as an intermediary electrical hub collecting

power generated from multiple energy sources and

aggregates it into a single high voltage output for efficient

evacuation to the main transmission grid. This is in tune with

Page 28 of 51

C.A. No.14780-14781 of 2025 etc.

Section 61 of the Electricity Act 2003, which requires the

generation, transmission, distribution and supply of electricity

to be conducted inter alia on commercial principles,

encouraging competition, efficiency and economical use of the

resources, good performance and optimum investments as also

safeguarding of consumers’ interest, enabling recovery of the

cost of electricity in a reasonable manner (sic. clauses (b) (c)

and (d) of Section 61).

26. From a conspectus of the above statutory scheme, the

Grid encompasses the entire transmission system starting from

the generating company at the point of evacuation of electricity

generated, which moves through the dedicated transmission

lines (DTL), as established by the generating company and gets

transmitted through the transmission lines established by the

CTU, including the LILOs, Pooling Stations etc; which come

within the ambit of “other works” as found in the definition

clause (72) of Section 2, received by the distribution licensee

and supplied to its end consumers through its distribution lines.

The distribution licensee receives the power from the

transmission lines of the CTU and extracts it and through the

distribution system, for supply to the end consumers. The

Page 29 of 51

C.A. No.14780-14781 of 2025 etc.

transmission, hence can be divided into three stages, (i) the

DTL which extracts power from the generating station and

brings it to the transmission lines of the CTU (ii) the

transmission lines of the CTU, which transmits the power

through the transmission lines to the distribution licensee and

(iii) the distribution system established by the distribution

licensee which extracts power from the transmission lines of the

CTU and supplies it to the end consumers. From this statutory

scheme, the upstream transmission system is the inter-State

transmission system established by the CTU and the

downstream transmission system is that established by the

distribution licensee within the respective States. It is with this

understanding of the statutory scheme that we have to look at

the facts of the case.

Adjudication on the Facts: -

27. On facts, we commence with Annexure A2, the Minutes of

the 29

th

Meeting of the Standing Committee on Power System

Planning in Southern Region (SCPSPSR) held on 27.08.2009.

Under Clause (12) discussions on the Inter State Transmission

Systems (ISTS) with respect to the Long Term Open Assess

(LTOA) Applications made to the CTU for Projects in Southern

Page 30 of 51

C.A. No.14780-14781 of 2025 etc.

Region, Coastal Energen Pvt. Ltd. and Ind Barath Power Madras

Ltd., in Tuticorin area, Tamil Nadu were considered. Insofar as

the Coastal Energen Pvt. Ltd. and Ind Barath Power Madras Ltd.,

the Transmission Systems contemplated are seen from Clause

12.3.2, which are as under: -

12.3.2 Transmission System for Coastal Energen Pvt Ltd

(2x660 MW) and IND Barath Power Madras Ltd. (4x350 MW)

projects in Tuticorin of Tamil Nadu:

(i) Establishment of 765 kV pooling station in Tuticorin,

Salem and Madhugiri (north of Bangalore) (initially charged

at 400 kV)

(ii) Coastal Energen generation switchyard - Tuticorin

pooling station 400kV D/C Quad / High-capacity line

(iii) Ind-Barath generation switchyard Tuticorin pooling

station 400kV D/c Quad/High-capacity line

(iv) Tuticorin Pooling station - Salem Pooling station 765kV

D/C line initially charged at 400kV

(v) Salem pooling station-Madhugiri pooling station 765kV

S/C initially charged at 400kV.

(vi) Madhugiri - Yelahanka 400 kV Quad D/C line

(vii) Tuticorin pooling station - Tuticorin JV 400 kV D/C

quad line.

28. Pertinently it has to be observed that the LILOs at the

Tuticorin Pooling Station were not contemplated, and the

Common Transmission for Coastal Energen and Ind Barath

Page 31 of 51

C.A. No.14780-14781 of 2025 etc.

Projects as decided are found under Clause (c) which is again

as below: -

i. Common transmission for Coastal Energen and Ind-

Barath projects

• Establishment of 765 kV pooling station in Tuticorin,

Salem and Madhugiri (near Bangalore) (initially

charged at 400 kV)

• Tuticorin Pooling station - Salem Pooling station 765

kV D/c line initially charged at 400 kV.

• Salem pooling station - Madhugiri pooling station 765

kV S/c initially charged at 400 kV.

• Tuticorin pooling station - Tuticorin JV 400 kV D/c

quad.

The estimated Cost of the evacuation system shall be about

Rs. 2500 Crores.

29. The dedicated transmission system with respect to

Coastal Energen was to commence from the generation station

of Coastal Energen evacuated to the Tuticorin Pooling Station

400 kV D/C quad/high-capacity line. A temporary measure for

drawing startup power as well as to evacuate power till the

commission of dedicated transmission system was

contemplated as hereinbelow:

iv) Further a temporary measure for Coastal Energen

to draw startup power as well as to evacuate power till

Page 32 of 51

C.A. No.14780-14781 of 2025 etc.

the commissioning of above transmission system, LILO

of one circuit of Tuticorin JV – Madurai 400 kV Quad D/c

line (under construction by POWERGRID) was agreed

which shall be restored matching with the

commissioning of pooling station in the Tuticorin area.

30. This led to the Bulk Power Transmission Agreement

entered into on 24.02.2010 between the appellant on the one

side and Coastal Energen and Ind-Barath Power, on the other

side. The transfer of power from the respective station of

generation to the place of delivery was specified in Annexure

1. The Transmission System required for direct evacuation of

power from the respective generating stations to the pooling

points of the PGCIL was finalized in consultation with the

Central Electricity Authority and indicated at Annexure 2. The

Transmission System to evacuate and dispatch power to

respective beneficiaries from the generation projects was

indicated at Annexure 3 and the applicable transmission

charges were agreed to be shared and borne as decided by the

CERC, which mechanism was indicated at Annexure 4. The

extracts from these annexures of the BPTA are relevant for

consideration.

Page 33 of 51

C.A. No.14780-14781 of 2025 etc.

31. Annexure 2 of the BPTA refers to the dedicated

transmission line, which was the obligation of Coastal Energen,

which as noticed hereinabove commences from the generation

switch yard to the Tuticorin Pooling Station. The common

transmission system to be developed by PGCIL as per

Annexure 3 of the BPTA, for strengthening the system in

Southern and Eastern Region, has been specified at Serial No.1,

of which that intended for Southern Region alone are extracted

herein below:

a) Establishment of 765 kV Pooling station at Tuticorin and

Salem (initially charged at 400 kV)

b) Tuticorin Pooling station - Salem Pooling Station 765 kV

D/c line (initially charged at 400 kV)

c) Salem Pooling station - Madhugiri Pooling Station 765 kV

S/c line (initially charged at 400 kV)

d) LILO of both circuits of Tuticorin JV - Madurai 400 kV D/c

quad line at Tuticorin Pooling station

e) Establishment of 400/220 kV, 2x500 MVA substation at

Madhugiri (near Bangalore) with 765/400 kV provision in

the same switchyard

f) Madhugiri - Yelahanka 400 kV D/c quad line

g) Associated 400kV bays at Tuticorin Pooling station,

Salem Pooling station, Madhugiri Pooling station and

Tuticorin JV substations.

Page 34 of 51

C.A. No.14780-14781 of 2025 etc.

32. The BPTA specifically provided for the LILO of both

circuits of Tuticorin JV-Madurai Line at Tuticorin Pooling Station,

which is not the LILO of the generating company created as a

temporary measure for the purpose of evacuation of electricity

from the generating station, before the commissioning of the

dedicated transmission line (DTL). Annexure 3 was replaced on

08.09.2011 and the common transmission system was

contemplated in two parts as Part A and Part B as specified

hereinafter:

1. Transmission System Strengthening in Southern Region

for evacuation of power from Coastal Energen Private

Limited and Ind-Barath Power (Madras) Limited in the

Tuticorin area

Part-A

a) Establishment of 765 kV Pooling station at Tuticorin

(initially charged at 400 KV)

b) LILO of both circuits of Tuticorin JV - Madurai 400 kV D/c

quad line at Tuticorin Pooling station

Part - B

a) Establishment of 765 kV Pooling station at Salem (initially

charged at 400 kV)

b) Tuticorin Pooling station - Salem Pooling Station 765 kV

D/c line (initially charged at 400 kV)

Page 35 of 51

C.A. No.14780-14781 of 2025 etc.

c) Salem Pooling station - Madhugiri Pooling Station 765 kV

S/c line (initially charged at 400 kV)

d) Salem Pooling Station - Salem 400 kV Quad line

e) Associated 400kV bays at Tuticorin Pooling station,

Salem Pooling station, Madhugiri substation.

This was in consonance with the decision of the 30

th

SCM held

on 05.05.2010, extracted in paragraph 12 of this judgment. Due

to the incapacity of Tuticorin JV to spare more than one bay, the

LILO’s were necessitated.

33. The commissioning schedule of Part A as per Annexure 4,

replaced on 08.09.2011, was July 2014 and that of Part B was

December 2014. The establishment of the 765 kV Pooling

Station at Tuticorin initially charged at 400kV was in time and

the LILO of both circuits of Tuticorin JV-Madurai line at Tuticorin

Pooling Station occurred respectively on 04.01.2015 and

08.01.2015 with a marginal delay. As is evident from the order

of the CERC, the investment approval was on 12.12.2011 and

the scheduled date of Commercial Operation was 11.04.2014.

There was a time over-run of 8 months 23 days with respect to

the first LILO and 8 months and 27 days with respect to the

second LILO, which was considered by the CERC in its order,

Page 36 of 51

C.A. No.14780-14781 of 2025 etc.

which time over-run in the case of the subject assets was not

condoned, but the PGCIL given liberty to substantiate the

reasons for the delay along with documentary proof at the time

of truing up.

34. The various claims raised were considered and some

declined, which eventually led to the order directing the

generating companies to pay transmission charges for the

instant assets till the dedicated transmission line (DTL) up to the

Tuticorin Pooling Station is constructed and declared as

commercially operational and put to regular use by the

concerned generating station. Fifty percent of the charges of

the LILO was to be included under PoC and the balance 50% of

the transmission charges to be borne by the generating

company, which had not commissioned the dedicated

transmission line. It was categorically found by the CERC that

the LILOs were agreed upon in the SCMs, and an extract was

made from the meeting of 38

th

SR-SCM dated 07.03.2015 in

paragraph 74 of the CERC order. It was also found that the LILO

of Coastal Energen on one circuit of Tuticorin Madurai

transmission line was agreed as an interim arrangement which

was directed to be removed within six months from the date of

Page 37 of 51

C.A. No.14780-14781 of 2025 etc.

issue of the order of CERC; simultaneous to which the dedicated

transmission line (DTL) was to be made operational.

35. From the above, it is very evident that the LILOs on the two

circuits of the Tuticorin JV-Madurai Line, though not initially

contemplated, was later made part of the transmission system,

which even according to the respondents is an integral part of

the system. The liability now cast on the power generating

company is only by reason of the DTL having not been

constructed, which would have extracted power from the

generating station and transmitted it directly to the Tuticorin

Pooling Station. In the absence of the DTL, power was

evacuated from the generating station through the temporary

LILO on the Tuticorin JV-Madurai Line at the location of the

generating station, which, from 04.01.2015 was taken to the

Tuticorin Pooling Station and further transmitted to the

distribution licensee. The intervening LILOs were, hence,

essential for the purpose of implementation of the system and

was an integral part of the system, which was made

commercially operative on 04.01.2015 and 08.01.2015. After the

establishment of the LILO, there could not have been a direct

transmission of electricity from the LILO of the generating

Page 38 of 51

C.A. No.14780-14781 of 2025 etc.

company directly to Madurai as is clear from the pictorial

depiction, which we extract hereunder: -

Page 39 of 51

C.A. No.14780-14781 of 2025 etc.

36. Upstream connection, which was not established as per

the timelines stipulated is the one shown in red commencing

from the Tuticorin Pooling Station to the Salem Pooling Station

and then further to Madhugiri. The delay in such establishment

did not in any manner affect the evacuation arrangement, since

the Tuticorin JV-Madurai line was utilized from the initial

generation of power from Coastal Energen as on 23.12.2014.

Though as argued by the generating company, electricity

moves seamlessly through the transmission lines, upon the

intervention made by the LILOs respectively on 04.01.2015 and

08.01.2015, the power generated from the NTPL , i.e. the

Tuticorin JV, and Coastal Energen evacuated through Tuticorin

JV-Madurai Transmission lines necessarily gets diverted to the

Tuticorin Pooling Station from which it is again evacuated and

transmitted through the Tuticorin JV-Madurai Line to the

distribution licensee. The LILOs being an integral part of the

system, the delay in implementation of the upstream

transmission to Salem does not affect the evacuation

arrangement at all. Hence, when the evacuation arrangement

as contemplated with the two LILOs were put in place on

04.01.2015 and 08.01.2015; which operated as the upstream

Page 40 of 51

C.A. No.14780-14781 of 2025 etc.

transmission path, the delay in operationalizing the DTL

assumes significance.

37. The DTL in the above depiction is again indicated by the

broken red lines starting from Coastal Energen and ending at

the Tuticorin Pooling Station. The temporary arrangement by

way of a LILO for extraction of power from the generating

station is depicted by the broken blue lines commencing from

the generating station and the LILO at one circuit of the Tuticorin

JV-Madurai Line. The LILOs intersecting the power and

diverting it to the Tuticorin Pooling Station is shown again in two

sets of broken green lines commencing from the Tuticorin JV-

Madurai line and ending in the Tuticorin Pooling Station and

then retransmitted to the Tuticorin JV-Madurai Transmission

Lines. The beneficial use is hence clearly established.

Commercial Operation Date: -

38. Insofar as the COD is concerned, we extract the definition

clause Regulation 3(53) and Section 4 hereunder:

3 (53) ‘Regular Service’ means putting into use a

transmission system or element thereof after successful trial

operation and a certificate to that effect has been issued by

the concerned Regional Load Dispatch Centre.

xxx xxx xxx

Page 41 of 51

C.A. No.14780-14781 of 2025 etc.

4. Date of Commercial Operation: The date of commercial

operation of a generating station or unit or block thereof or

a transmission system or element thereof shall be

determined as under:

(1) Date of commercial operation in case of a generating

unit or block of the thermal generating station shall mean

the date declared by the generating company after

demonstrating the maximum continuous rating (MCR) or

the installed capacity (IC) through a successful trial run after

notice to the beneficiaries, if any, and in case of the

generating station as a whole, the date of commercial

operation of the last generating unit or block of the

generating station:

Provided that

(i) where the beneficiaries have been tied up for

purchasing power from the generating station, the

trial run shall commence after seven days notice by

the generating company to the beneficiaries and

scheduling shall commence from 0000 hrs after

completion of the trial run:

(ii) the generating company shall certify to the effect

that the generating station meets the key

provisions of the technical standards of Central

Electricity Authority (Technical Standards for

Construction of Electrical plants and electric lines)

Regulations, 2010 and Grid Code:

(iii) the certificate shall be signed by CMD/CEO/MD of

the company subsequent to its approval by the

Page 42 of 51

C.A. No.14780-14781 of 2025 etc.

Board of Directors in the format enclosed at

Appendix VI and a copy of the certificate shall be

submitted to the Member Secretary, (concerned

Regional Power Committee) and concerned RLDC

before declaration of COD:

39. Sub-clause (ii) of clause (3) of Regulation 4 applies only

when a transmission system or an element thereof is prevented

from regular service for reasons not attributable to the

transmission licensee or its supplier or its contractors but is on

account of the delay in commissioning of the concerned

generating stations or in commissioning of the upstream and

downstream transmission system. Hence, when a generating

station has operationalized its power generation and there is a

delay in the operationalization of the transmission lines or vice-

versa when the transmission lines are operationalized and there

is a delay in the generating station being operationalized, then

the defaulting party would be made liable for which an

appropriate application for approval of the date of commercial

operation (COD) is required to be filed before the CERC.

40. In the present case, as has been admitted by both the

generating company and the distribution licensee, there was no

Page 43 of 51

C.A. No.14780-14781 of 2025 etc.

impediment caused to the transmission of electricity from the

date of commencement of generation at the generating station.

The upstream transmission system insofar as the subject

evacuation arrangement had two alternatives, one the Tuticorin

to Salem Pooling Station and further to Madhugiri and the LILOs

on the Tuticorin JV-Madurai Line at the Tuticorin Pooling Station,

the latter of which stood established, though with some delay.

Despite the delay not being condoned, the liability falls on the

generating company from the date of the COD of the LILOs;

especially for reason of the DTL having not been established.

The definition clause, as extracted hereinabove, clearly

indicates that ‘Regular Service’ means putting into use of the

transmission system or element thereof, after successful trial

operation and a certificate to that effect issued by the

concerned RLDC. This is in consonance with clause (3) of

Regulation 4 which declares the COD to be the date declared

by the transmission licensee from 0000 hours of which an

element of the transmission system is in regular service after

successful trial operation.

41. The CERC in its order has specifically referred to the

claim of the petitioner, the CTU, of commercial operation of

Page 44 of 51

C.A. No.14780-14781 of 2025 etc.

Asset 1 and Asset 2, both being LILOs at the Tuticorin Pooling

Station, implemented as on 04.01.2015 and 08.01.2015. The

RLDC certificate for charging of the instant assets after the

successful trial run and the CEA certificate under Regulation 43

of the Central Electricity Authority (Measures Related to Safety

and Electricity Supply) Regulations 2010 had been submitted

by the CTU through an affidavit dated 12.05.2016. The CTU also

submitted the implementation of 1x80 MVAR bus reactor in its

Tuticorin Pooling Station for the purpose of voltage control.

Referring to the 29

th

and 30

th

Standing Committee Meetings, as

per scheme approved by the Southern Region beneficiaries,

the commercial operation date of Asset 1 and Asset 2 as on

04.01.2015 and 08.01.2015 was accepted. This calls for no-

redetermination under Regulation 4(3)(ii) of the Tariff

Regulations.

The Precedents: -

42. All the parties placed heavy reliance on the decision of

this Court in Power Grid Corporation of India Limited vs.

Madhya Pradesh Power Transmission Company Limited and

Page 45 of 51

C.A. No.14780-14781 of 2025 etc.

Ors.

1 (authored by one of us: Justice J.B. Pardiwala) wherein the

first respondent who was the distribution licensee was required

to construct and commission the Inter-State Transmission Line

coinciding with the timeline of completion of works, which were

within the scope of the appellant, the CTU. Therein the time

over-run was attributable to the distribution licensee, who

delayed the commissioning of the downstream intra-State asset

while the CTU obtained approval of the COD under Regulation

of 4(3)(ii) of the transmission lines set up by the CTU. The CERC

not only allowed the CTU to claim compensation for the period

prior to the COD as liquidated damages, interest during

construction and incidental expenses incurred during

construction, but also the transmission charges in case of all the

assets, to be borne by the first respondent, from the COD

determined under Regulation 4(3)(ii) up to one day before

actual charging of the downstream system. The first respondent

argued that there was no regulation to support the said liability.

43. Looking at Section 79 and 178 of the Act of 2003, it was

held that the CERC, the statutory authority under the Electricity

Act is enjoined with the tasks of both; regulation as well as

1

(2025) 8 SCC 705

Page 46 of 51

C.A. No.14780-14781 of 2025 etc.

adjudication on the aspects of generation transmission and

distribution of electricity. However, such functions by

themselves were distinct and separate, since those under

Section 79 were administrative or adjudicatory in nature, while

those under Section 178 were delegated legislative powers. It

was held so under paragraph 42, relying on PTC India Limited

v. Central Electricity Regulatory Commission, Thr.

Secretary

2 :

“42. What is discernible from the aforesaid exposition of

law is that there is a dichotomy between the power to make

a regulation under Section 178 and the power to regulate or

adjudicate on the various areas enumerated under Section

79(1). A regulation under Section 178 is of general

application to the entirety of a particular subject-matter as

opposed to regulation on a case-to-case basis which may

be done by CERC under Section 79. Therefore, making of a

regulation under Section 178 has the effect of interfering

with and overriding existing contractual relationships

between the regulated entities. On the other hand, the

orders under Section 79 have to be confined to the existing

statutory regulations and do not have the effect of altering

the terms of contract between the specific parties before

CERC.”

44. PTC India Limited

2 declared that ‘making of a regulation

under Section 178 is not a precondition to the Central Commission

2

(2010) 4 SCC 603

Page 47 of 51

C.A. No.14780-14781 of 2025 etc.

taking any steps/measures under Section 179 (1)’ (sic). While

unequivocally declaring that if there is a regulation under

Section 178 then the measure under Section 79(1) has to be in

conformity with such regulation, it was also held that an order

imposing regulatory fees could be passed even in the absence

of a regulation under Section 178. While the validity of the

delegated legislation under Section 178 has to be tested by way

of judicial review, an unreasonable levy under Section 111,

whether it be; in the absence of a regulation, or on an

interpretation of the regulation enacted under Section 178,

could be challenged before the APTEL by way of an appeal.

45. Reliance was also placed on Energy Watchdog v. Central

Electricity Regulatory Commission and Ors. Etc.

3, which

found Section 79(1) to be the repository of the regulatory

powers of the CERC, which powers should be exercised in

conformity with the guidelines or regulations; if in existence

under Section 178, and even otherwise despite a regulatory

lacuna. The order of the CERC which was impugned in PGCIL

imposing liability of payment of compensation for delay on the

part of the first respondent was upheld despite absence of a

3

(2017) 14 SCC 80

Page 48 of 51

C.A. No.14780-14781 of 2025 etc.

regulation under Section 178; finding the liability to be

reasonably imposed on the defaulting party. The dictum

squarely applies in the present case, where the generating

company failed to establish and operationalise its DTL within

the time stipulated. In the period between COD of the LILOs

established by the CTU and the establishment of the DTL by the

generating company, the liability cast by the CERC on the

generating company is perfectly in order.

In Denouement of the APTEL Order: -

46. We are definitely of the opinion that the APTEL erred in

finding the usage of LILOs to be absent in the transmission of

power. We have seen that the strengthening of the Southern

Region Transmission System as available from the minutes of

the SCM, which were duly agreed to, in the BPTA, required the

LILO of both circuits of the Tuticorin JV-Madurai Line to be made

at the Tuticorin Pooling Station. The PGCIL thus was obliged to

construct the said LILO, which was also a permanent part of the

transmission plan. However, while accepting the LILO to be a

permanent part of the transmission plan, surprisingly the APTEL

found its use to be not established and the COD having not been

granted in the manner it should have been done; despite clear

Page 49 of 51

C.A. No.14780-14781 of 2025 etc.

admission of its use by the generating company. We have

already held that the consideration of the COD by the CERC, in

the context of no prevention of regular service, to be perfectly

in order. In fact the COD as projected by the PGCIL was

accepted on the basis of the admitted ‘Regular Service’ as

defined in the Tariff Regulations, on the strength of the

successful trial operation certified by the RLDC.

47. It is pertinent that APTEL noticed the contention of PGCIL

that TANGEDCO has taken mutually destructive pleas of; no

liability to transmission charges despite utilization of the LILOs,

and the plea of the LILOs have been not been put to use at all.

The APTEL also noticed that under Section 29(4) of the

Electricity Act, the decision taken by the Regional Power

Committee of the SCM, in furtherance of grid stability and

coordinated transmission planning has legal sanctity and hence

the approval of the LILO in the 30th SCM participated by all

stakeholders, including TANGEDCO binds all parties. It is

pertinent here, to observe that the generating company never

raised any objection in the SCMs and also did not participate in

the tariff determination before the CERC.

Page 50 of 51

C.A. No.14780-14781 of 2025 etc.

48. The error committed by the APTEL also in placing heavy

reliance on paragraph 72 of the CERC order, based on which

the concept of ‘beneficial use’ was coined, in the context of

absence of the upstream transmission lines. As we observed,

paragraph 72 of the CERC order cannot be isolated and

considered out of context. Looking at the spirit and tenor of the

CERC order, paragraph 72 cannot be termed as a finding of the

CERC and can only be looked at as the recording of the

contentions of the TANGEDCO, while paragraph 73 to 77 posed

the question of liability of the transmission charges and mulcted

it squarely on the generating company, based also on the

minutes of the 30

th

SCM the extract from which, we also

extracted in paragraph 12 of this judgment. The conclusion of

the APTEL that the pictorial depiction clearly indicates the

temporary arrangement of a LILO made by the generating

company on the Tuticorin JV-Madurai line, which proceeds

directly to Madurai and does not reach the Tuticorin Pooling

Station, factually is incorrect. The LILO’s on the line restricted

such transmission directly to Madurai without being routed

through the Tuticorin Pooling Station.

Page 51 of 51

C.A. No.14780-14781 of 2025 etc.

49. The first question of law is answered in the affirmative,

finding the element of the two LILOs, in the Tuticorin JV-

Madurai line at Tuticorin Pooling Station, as includable in the

transmission tariff, as found by the CERC, from 04.01.2015 upto

the establishment of the Dedicated Transmission Line (DTL) on

27.10.2016 as non-PoC. The second question of law is answered

in the negative, finding the interpretation of the APTEL, on the

COD, to be erroneous. The third question of law is again

answered in the affirmative, based also on the decisions of this

Court cited as precedents hereinabove.

50. We, hence, on the above reasoning, set aside the

impugned orders of the APTEL in both the appeals and restore

the order of the CERC.

51. The appeals are allowed.

52. Pending application (s), if any, shall stand disposed of.

……...…….……………………. J.

(J. B. PARDIWALA)

...………….……………………. J.

(K. VINOD CHANDRAN )

NEW DELHI

NOVEMBER 18, 2026.

Reference cases

Description

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter