As per case facts, the Punjab State Load Despatch Centre (PSLDC) and Punjab State Power Corporation Limited (PSPCL) imposed penalties on Talwandi Sabo Power Limited (TSPL) for misdeclaration of Declared ...
2026 INSC 515 Page 1 of 34
Civil Appeal No.7432 of 2025 etc.
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No. 7432 of 2025
Punjab State Power
Corporation Limited
...Appellant
Versus
Talwandi Sabo Power
Limited & Ors.
...Respondents
with
Civil Appeal No. 7436 of 2025
J U D G M E N T
K. VINOD CHANDRAN , J.
The appeals are filed by the Punjab State Load Despatch Centre
(PSLDC) and the Punjab State Power Corporation Limited (PSPCL)
against the judgment of the Appellate Tribunal for Electricity (APTEL)
reversing the order of the Punjab State Electricity Regulatory
Commission (SERC). The impugned order sets aside the finding of
‘misdeclaration of Declared Capacity’ as found by the PSLDC on four
days in January 2017. Initially, misdeclaration was found for five days
i.e. on 10.08.2015, 15.01.2017, 17.01.2017, 24.01.2017 and 31.01.2017
Page 2 of 34
Civil Appeal No.7432 of 2025 etc.
leading to a levy of penalty coming to Rs.162,74,72,865/- by Memo
No. 278 dated 15.03.2017, out of which a penalty of Rs.74,27,27,159/-
stood deducted from the pending bills. At the instance of the State
Generating Station, Talwandi Sabo Power Limited (SGS or TSPL,
alternatively) directions were issued by the High Court referring the
matter, first to the Commercial and Metering Committee and then to
the State Grid Code Review Committee. Dissatisfied with the
proceedings thereat, again on the directions of the High Court, the
matter was referred to the SERC which affirmed the findings of the
PSLDC that the SGS had failed to demonstrate its capacity on four
occasions in the month of January 2017 but rejected the finding of
misdeclaration in the month of August 2015. The APTEL reversed the
said order and deleted the findings of misdeclaration, and the
resultant penalty.
Appellants; in support of the SERC: -
2. Shri M.G. Ramachandran, appearing for the PSLDC at the outset
pointed out that the energy requirement in the State varies with the
demand, being high during May to September; the paddy season,
and comparatively lower for the remaining months of the year.
Reference was made to Schedule-7 of the Power Purchase
Page 3 of 34
Civil Appeal No.7432 of 2025 etc.
Agreement (PPA) which provides for a two-part tariff, one; on the
capacity based on the Declared Capacity/Capability (DC), a fixed
charge, and a variable charge on the energy scheduled for supply.
The SGS, the generator, is required to declare the electricity
generation capacity in megawatts (MW) for every given day, the
scheduling of which is decided by the PSLDC based on the
anticipated requirements of PSPCL, equal to or below the declared
capability. Even if the scheduling required by the PSPCL is lower it
has an obligation to pay the fixed charges, the difference being
termed as deemed generation, subject to incentives and
disincentives based on the percentage of declared availability as
determined annually. The PSLDC exercises statutory functions under
Section 32 of the Electricity Act, 2003 (the Act of 2003) to oversee,
monitor and control the availability schedule and despatch of
electricity as generated by the SGS and supplied to PSPCL.
3. The Punjab State Grid Code, 2013 (SG Code) provides for
detailed steps for declaration of capability, scheduling and despatch
as also enables revision of injection and drawal schedule on a real
time basis relatable to the requirements, subject to forced outages,
bottlenecks etc. The PSLDC has overriding powers insofar as calling
Page 4 of 34
Civil Appeal No.7432 of 2025 etc.
upon the SGS at any point of time to revise the schedule which has to
be effective from the 4
th
time block, the first being counted as that in
which the revised schedule is issued, each of such time blocks being
of 15 minutes duration. The SGS is also required to declare the
possible ramping up/ramping down of generation in every time
block which in the present case has been declared as 1% per minute.
The very purpose behind the regulatory measure as provided in the
SG Code ensures that the SGS faithfully declares its capability and
maintains it throughout, subject to revisions, despite the schedule
being lower and its readiness to ramp up or down being occasioned
at every revision sought for, by the PSPCL through the PSLDC.
4. The PSPCL being unable to draw the full capacity of the
declared availability enables the generator to have the benefit of
deemed generation of the declared availability with significant
consequences on the capacity/fixed charges. This unwittingly gives
an opportunity to the generator to declare far more than its capacity,
on an estimation of the drawal requirements of the procurer and also
in certain instances, make undue gain at the cost of the procurer and
the consumers at large. To curb such unfair practices the SG Code
provides for steps to curb misdeclarations by way of issuing warning
Page 5 of 34
Civil Appeal No.7432 of 2025 etc.
notices and then show-cause notices against any indulgence in
gaming as per Regulation 11.3.12 or for imposition of penalty for
misdeclaration in the event of failure to demonstrate the declared
capacity as required by the PSLDC. Regulation 11.3.13 brings in a
strict liability which is the penalty imposed in the present case.
Learned Senior Counsel also took us through the findings of the SERC
which have been reversed by the APTEL on misconstruing the
provisions of the Act and the Grid Code. Reliance was placed on
Union of India vs. Dharamendra Textile Processors
1 to distinguish
a penalty arising on a civil liability from one arising in a criminal
liability, the requirement of mens rea being absent in the former.
5. Shri Shubham Arya appearing for the PSPCL adopts the
arguments addressed by the PSLDC and points out that though the
penalty is payable to the PSPCL, the ultimate beneficiary is the
consumer since the PSLDC has an obligation to account for the entire
penalty which would be reflected in the tariff, based on the profit or
income generated by the PSPCL, passed on to the consumer by
reduction in tariff. A portion of the penalty imposed having been
deducted, the same was paid with applicable interest/payment
1
(2008) 13 SCC 369
Page 6 of 34
Civil Appeal No.7432 of 2025 etc.
surcharge as per the PPA so as to ensure that PSPCL does not suffer
any further liability of surcharge/interest, but under protest and
subject to the final decision in the above civil appeals. It is pointed
out that the demonstration of capability has to be either in the four-
time blocks or as per the 1% ramp up per minute, also declared by
the SGS of which the former gives the SGS a better elbow room by
way of more time being available for the demonstration by achieving
the declared capability. The 1% ramp up per minute is also a
declaration made by the SGS which too has to be strictly adhered to.
Regulation 5.3.8 is pointed out to contend that the ramp up/ramp
down percentage is prescribed by the SG Code itself.
Respondents; in support of the APTEL: -
6. Shri Sajan Poovayya commenced with the declaration of fidelity
of the SGS he represents, vouched by the fact that it had not once run
into rough weather in the last nine years of the relationship. On the
discord now alleged, even according to SLDC and PSPCL, the
demonstration of its declared capacity had to be done within four-
time blocks from the receipt of the notice and the CERC also
adjudicated the issue as to whether such demonstration was achieved
in the 4
th
time block. Hence, the ramp up rate of 1% is
Page 7 of 34
Civil Appeal No.7432 of 2025 etc.
inconsequential insofar as Regulation 11.3.13 of the SG Code is
concerned. In fact that regulation does not specify a time in which the
demonstration had to be carried out and, in such circumstances,
neither 4
th
time block nor the 1% ramp up can be determinative of
the factum of demonstration. Further, since no time was specified,
even in the notice issued, demonstration could be at any time of the
day on which it is required. It is argued that what is alleged is gaming
as a consequence of the misdeclaration, which required a finding of
deliberate intention with the motive of making money; ie: to earn
undue capacity charges, without which finding, there can be no
misdeclaration alleged or penalty imposed.
7. Reliance is placed on TPDDL v. PPCL
2 dated 29.11.2023 of the
CERC wherein an identical issue was considered. Misdeclaration of
the declared capability is established only when the generating
station lacks the necessary fuel or coal to generate power upto its
declared capability or its power plant is shutdown or under repair
due to faulty machinery, thus causing restriction in the generating
capacity of the station. On all the four days of the alleged
2
“Tata Power Delhi Distribution Limited v.
Pragati Power Corporation Limited and Others” in Petition No.199/MP/2019
Page 8 of 34
Civil Appeal No.7432 of 2025 etc.
misdeclaration, the TSPL’s plant had generated power on multiple
time blocks as per the declared capacity and this demonstrates that
the SGS had the necessary coal stock and was technically capable of
generating power up to its declared capacity: putting to peril any
allegation of misdeclaration.
8. Reliance was also placed on the judgment dated 11.12.2007 of
the APTEL in PSEB v. CERC
3 wherein less than 1% deviation was
found to be within practical limits; not necessarily justifying an
allegation of gaming by the generating unit. The 1% ramp up rate is
merely a normative value and has no relation to the actual operation
of the generation capability of the SGS and even regulation 5.3.8
provides only for a possible generation as per the ramping up/down
rate as declared by the SGS. The decision of this Court in Excel Crop
Care Ltd. v. CCI
4
is relied on to argue that if two possible
interpretations are possible, both being reasonable, especially while
considering a penal provision, the Court should lean towards the
interpretation which exempts the penalty rather than one which
imposes it.
3
“Punjab State Electricity Board v. CERC” in Appeal No. 79 of 2007
4
(2017) 8 SCC 47
Page 9 of 34
Civil Appeal No.7432 of 2025 etc.
9. Allegation of discrimination is raised citing the case of Nabha
Power Limited, another generating station of the State of Punjab,
which too injected power less than its declared capacity on multiple
occasions, but was absolved from any imposition of penalty. It is
asserted, on the strength of the words employed in the provisions of
the SG Code that there should be an enquiry with appropriate
hearing afforded, to the generating station to find gaming and that
conclusion of misdeclaration leading to gaming can be arrived at
only when there is a mala fide intention found on the generating
station, to earn undue profits, by the measure employed of
misdeclaration. It was specifically pointed out that the CERC despite
finding in its order that the act of the generating station has to be
‘deliberate or intentional’ and there should be ‘motive found to make
money’ either as undue capacity charges or to benefit from deviation;
the principle was lost sight off while the penalty was affirmed. There
is also an alternate contention taken that the finding in the present
case is only of a deviation which is regulated by the CERC (Deviation
Settlement Mechanism and Related Matters) Regulations, 2014
5
.
5
The DSM Regulations
Page 10 of 34
Civil Appeal No.7432 of 2025 etc.
10. Mr. Vishrov Mukerjee, learned Counsel for the respondent,
follows up with the assertion that misdeclaration and deviation are
distinct, the former being a misdemeanour while, to find deviation,
there need not be any inquiry into the intent or obtainment of illegal
gain. Misdeclaration can be found only by an inquiry into the intent
and the monetary gain achieved by such misdemeanour. Insofar as
the demonstration of the declared capability in a time block is
concerned, the notice issued by the SLDC did not specify the time
frame in which it had to be achieved and hence the SERC ought not
to have found misdeclaration without an inquiry into the intent behind
such alleged misdemeanour. The table relating to scheduling,
despatch and net drawal, as extracted by the SERC is specifically
pointed out to show that demonstration was achieved within the
required time blocks or at least in the same day; which we will deal
with a little later.
The Order of the SERC: -
11. The SERC by Annexure A50 order found that as and when notice
is issued by the SLDC to demonstrate the DC, the SGS has to comply
with it as per the ramp up/ramp down rate under Regulation 11.3.10
of the SG Code and on failure it would be liable for penalty on the
Page 11 of 34
Civil Appeal No.7432 of 2025 etc.
ground of misdeclaration. However, it was also found that in the
instant case, the PSLDC had allowed the petitioner to implement the
directions from the 4
th
time block and hence no literal interpretation
could be adopted. The SERC found that gaming in Regulation 11.3.4
and deliberate over/under declaration of plant availability in
Regulation 11.3.12 has the same connotation and that the act of the
generator has to be deliberate or intentional and there should be a
motive to make illegal enrichment. As far as the monitoring
procedure delineated under Regulation 13.5 of the SGCRC, it was
found to be distinct from Regulation 11.3.12 and 11.3.13, dealing with
only monitoring and evaluation of the performance of the generating
plants. A 12% margin as provided by the DSM Regulations is to
ensure maintenance of grid discipline and grid security as envisaged
under the Grid Code. The intention of providing deviation volume
limit is to curb tendency of users to deviate drastically from the
schedule, under threat of deviation charges. The DSM Regulations
were found to be not applicable in the case of demonstration of DC
governed by the provisions of the SG Code.
12. On the basis of the above interpretation, the factual matrix was
examined, and it was found that in December 2016, the SLDC noticed
Page 12 of 34
Civil Appeal No.7432 of 2025 etc.
a regular pattern of generation, below the scheduled declaration, for
which notices were issued pointing out that this would tantamount to
misdeclaration of declared capability resulting in SG Code violation.
On 19.12.2016, on receipt of such communication through email, the
SGS was found to have lowered its declared capability. Again on
30.12.2026, a pattern was detected with a maximum under injection
of 27% recorded under one time log, when again warning notices
were issued. Yet again, rather than increasing the generation, the
SGS lowered its declared capability. The SERC specifically
emphasised the analysis of injection in December 2016 as projected
by the PSLDC, wherein the SGS failed to deliver requisite generation
in 387 time blocks out of the total 459-time blocks, taking the under
generation to 84.13% of the time blocks corresponding to the
declared capability. This led to notices being issued on the times
specified on the four dates in January 2017. The declared capability,
the scheduled generation, actual injection and the deviation in
various time blocks after the notice period were tabulated. The SERC
analysed it to find a misdeclaration for reason of failure of SGS to
demonstrate the declared capability on it being sought by the SLDC;
the details of which will be dealt with by us in our own analysis. The
Page 13 of 34
Civil Appeal No.7432 of 2025 etc.
SERC found misdeclaration on the four specified dates in the month
of January 2017 for which the penalty was imposed, as per the
corresponding monthly capacity charge payment; the computation
of which we need not go into.
The Impugned Order: -
13. The APTEL noticed Regulation 11.3.10; which mandates
declaration of generation capability, Regulation 11.3.12 ;
empowering SLDC to issue a notice alleging gaming and Regulation
11.3.13; enabling SLDC to require demonstration of declared
capability, to find that there is no time limit specified for
demonstrating the declared capability. It was found that the SERC
had erroneously relied on the ramp rate as the measure for
demonstration of capability and declined the contention of the
appellants herein that the SGS is required to demonstrate generation
on the 4
th
time block on receipt of notice. It was held that Regulation
11.5 (xi) is in a totally different context of revision of schedule and
does not govern demonstration of DC. As far as the misdeclaration
of declared capability, reliance was placed on the order of the CERC
in TPDDL
2, which according to the APTEL held that misdeclaration
can be found only when there is absence of adequate coal stock or
Page 14 of 34
Civil Appeal No.7432 of 2025 etc.
when the plant is under shutdown or repair due to faulty machinery.
The SGS on 17.01.2017 raised technical issues of the coal handling
plant which necessitated downward revision and shutdown, duly
communicated to the PSLDC. Finding that ramp rate or the 4
th
time
block, does not apply insofar as demonstration of DC is concerned it
was observed that the notices issued also did not specify any time
block within which the declared capability had to be demonstrated,
which in any event, was demonstrated on the very same day.
14. On facts, it was found that on each of the days complained of,
the DC was demonstrated on 15.01.2017, within 4
th
and 6
th
time
blocks with a slight deviation and on 24.01.2017, on the 7
th
and 8
th
time blocks with deviation of 1.02% and 0.34% respectively. The
order dated 11.12.2007 in PSEB v. CERC
3 was relied on to hold that
the deviation of less than 1% of DC is within the practical limits and
shall not be considered as gaming by the generating company. The
APTEL set aside the findings on misdeclaration on the four dates in
January 2017 and directed refund of the penalty amounts adjusted in
the bills payable. The APTEL however concurred with the findings of
the SERC that the DSM Regulations do not govern the demonstration
of declared capability.
Page 15 of 34
Civil Appeal No.7432 of 2025 etc.
Adjudication: -
15. At the outset we have to notice that the argument put forth, by
the SGS of force majure conditions having impeded demonstration of
DC was hastily resiled from, on our querying on the specifics. We are
also not impressed by the assertion of fidelity in the last 9 years of
relationship with the Distribution Company, which the SGS swears
by, which also has to be continued for another 16 years. Morality in
past conduct, though attractive by itself, can seldom be a justification
for deviation from express terms of a contract especially when there
is a strict liability enforced without reference to a guilty mind; the
mens rea. The PPA admittedly provides for fixed capacity charges
and variable energy charges as is seen from Annexure A1 produced
along with Civil Appeal No.7436 of 2025 (the documents from which
appeal is referred to, by us in this judgment).
16. The fixed capacity charges are to be paid based on the
contracted capacity at normative availability, specified as equal to
80%, subject to incentives and disincentives, dependent on the
percentage of availability achieved, annually. For an availability
beyond 85%, as per Clause 1.2.4 of Schedule 7 of the PPA, an
incentive at the rate of 40% of the Quoted Non Escalable Capacity
Page 16 of 34
Civil Appeal No.7432 of 2025 etc.
Charges (QNECC) for the contract year, subject to a maximum of that
corresponding to the availability in excess of 85% is payable. This is
applicable on an annual basis and included in the monthly tariff
demand in the first month of the next contract year. A disincentive in
the nature of a penalty is determined as per Clause 1.2.5 of the
Schedule when the availability for a contract year is less than 75%,
inviting a penalty at the rate of 20% of the simple average capacity
charge for all months in the contract year applied on the energy
corresponding to the difference between 75% and the availability
during such calendar year, also a civil liability. The fixed charges
being applicable to the contracted capacity, the incentives and
disincentives will depend upon the availability which would be
determined on the basis of the Regional Energy Accounts (REA)
maintained for the year.
17. The ‘Scheduling and Despatch’ are regulated by Part IV of the
SG Code which has that nominal heading. As is clear from the
objectives Regulation - 11.2, the SG Code delineates the procedure
for scheduling of the net injection/drawals of the State Entities on a
day-ahead basis, streamlining the flow of information between the
SLDC and the State Entities, herein being the SGS; the generator-
Page 17 of 34
Civil Appeal No.7432 of 2025 etc.
TSPL, and the PSPCL; the procurer. The SGS in the instant case as per
the PPA, is obliged to maintain three units, each having the capability
of generation of 660 MW. The SG Code provides for a procedure of
submission of capability/capacity declaration by the SGS and the
drawal requisition by the procurer of power, who carries out
distribution to the consumers. Regulation 6.3.8 of the ‘Operational
Planning’ mandates that all distribution licensees/users shall provide
to SLDC their estimated demand for each 15-minute block for the
ensuing day with estimates of load in discrete blocks, a day ahead at
11.00 hours of each day. ‘Steps in Scheduling’ in Part IV, Section 11
by sub-clause (i) under Regulation 11.4 requires the SGS to intimate
the station-wise ex-power plant MW and MWh capabilities, foreseen
for the next day between 00.00 to 24.00 hrs in time blocks of 15
minutes interval to the SLDC. Similarly, sub-clause (ii) requires the
distribution licensees to intimate the overall requirement in MW and
MWh for the next day on 15 minutes interval to the SLDC by 11.00
hours of the previous day after receipt of information as provided
under sub-clause (i). The SLDC also is required to finalise by 15.00
hours of the previous day the generation schedule of the SGS and the
drawal schedule of each distribution licensee for the next day, for
Page 18 of 34
Civil Appeal No.7432 of 2025 etc.
each 15 minute time blocks. The variable energy charges are
payable on the scheduled generation, this being capable of revision
on a real time basis, within the declared capacity. The deviations
from that scheduled and actually injected is dealt with by the
Unscheduled Interchange (UI) charges.
18. The general conditions under Part IV, Section 11 deals with the
measure of gaming and the demonstration of declared capability (or
‘capacity’; alternatively used herein). Regulation 11.3.2 requires the
SLDC to issue despatch instructions as delineated hereinabove to
regulate all generation and imports from SGS, in accordance with the
15-minute day ahead generation schedule as finalised by the SLDC.
As per Regulation 11.3.4, the SLDC is responsible for; (i) coordinating
the scheduling of all generating stations within the State (ii) real time
monitoring of the station’s operations (iii) checking that there is no
gaming in its availability declaration, or (iv) in any other way revision
of availability declaration and injection schedule, switching
instruction, meter data processing, collections/disbursement of UI
payments, outage planning etc.; each of these being separate and
distinct aspects/obligations.
Page 19 of 34
Civil Appeal No.7432 of 2025 etc.
19. ‘Gaming’ is defined as an intentional misdeclaration of a
parameter related to commercial mechanism in order to make an
undue commercial gain; clearly requiring a finding of a guilty intent
and illegal enrichment. Regulation 11.3.4 while emphasising that the
SLDC shall ensure that there is no gaming in scheduling, in the event
of a suspicion enables the SLDC to disallow the energy
corresponding to suspected gaming from UI account till a final
decision is taken. Regulation 11.3.12 obliges the SGS to declare the
plant capability faithfully, in accordance with their best assessment.
Over/under declaration of plant capability resulting in deviation
from schedules, given on the basis of their capability declarations,
requires the SLDC to serve notice of gaming and affording an
opportunity to the SGS to explain the situation with necessary backup
data. The deviation in injection from the scheduled or capability
declared also should have resulted in monetary gain either as undue
capacity charge or as the charge for deviations from schedule. We
fully concur with the respondent’s contention that gaming requires
mens rea coupled with illegal enrichment which requires an inquiry
fully complying with the principles of natural justice.
Page 20 of 34
Civil Appeal No.7432 of 2025 etc.
20. However, the SERC, according to us, in its order mistook the
present allegation as one of gaming and erroneously found
imperative - ‘intention and a motive to make money’, to impose
penalty for the misdeclaration alleged. True, despite the above
finding, though in this case, there was no enquiry into a deliberate
attempt to profiteer, the penalty was upheld; rightly so as we would
presently demonstrate. We are in favour of the contention of the
appellant that demonstration of declared capability and deviation
from the despatch schedule are quite distinct and different in
themselves and more so from gaming.
21. Demonstration of the declared capability of a generating
station is provided for in Regulation 11.3.13, which, for its relevance,
is extracted hereunder: -
“11.3.13 The SGS shall be required to demonstrate the
declared capability of its generating station as and when
asked by the SLDC. In the event of the SGS failing to
demonstrate the declared capability, the capacity charges
due to the generator shall be reduced as a measure of
penalty. The quantum of penalty for the first mis-
declaration for any duration/block in a day shall be the
charges corresponding to two days fixed charges. For the
second misdeclaration the penalty shall be equivalent to
fixed charges for four days and for subsequent mis-
Page 21 of 34
Civil Appeal No.7432 of 2025 etc.
declarations, the penalty shall be multiplied in the
geometrical progression over a period of a month.”
22. The demonstration as required by Regulation 11.3.13 is a stand-
alone provision, the penalty for which is ingrained therein. There is
no reason to intermingle the concepts of gaming and demonstration
of declared capability, even though both can be found literally to be
misdeclarations leading to two different consequences, the former,
requiring mens rea and the latter inviting strict liability. We are also
of the opinion that the responsibilities of the SLDC as listed under
Regulation 11.3.4 are also distinct in nature. While checking on
gaming; having the ingredients of intention and illegal enrichment, is
one of the responsibilities, coordination of scheduling and real time
monitoring of the generating station’s operations are matters which
fall under ‘better system operation’ the responsibility to ensure which
is also cast on the SLDC by Regulation 11.5 (xi); extracted here under,
for emphasis : -
“(xi) If, at any point of time, SLDC observes that there is
need for revision of the schedules in the interest of better
system operation, it may do so on its own and in such cases,
the revised schedules shall become effective from the 4th
time block, counting the time block in which the revised
schedule is issued by SLDC to be the first one.”
Page 22 of 34
Civil Appeal No.7432 of 2025 etc.
23. We cannot accept the finding of the APTEL that the above
Regulation applies only to revision of schedules, which is governed
by Regulation 11.5.(vii) enabling revision of schedules/declared
capability to become effective from the 6
th
time block. The notice to
demonstrate declared capacity is to ensure due adherence to time
blocks in the event of revision which could be sought as high as the
declared capacity itself and to meet specified contingencies.
Regulation 11.5 of Part IV, Section 11 has the nominal heading of
‘Revision in injection/drawal schedule on real time basis’, providing
for revision of injection or drawal schedule by the SLDC on the
various conditions delineated thereunder. Demonstration of DC is a
measure of ensuring that the SGS has the ability to generate the
capacity declared on a real time basis and that the declaration is
made faithfully, especially when fixed charges are paid on the
declared capability and incentives earned for annual generation in
excess of 80% of the declared capability. Sub clauses (i) to (v) of
Regulation 11.5 though do not regulate the demonstration of
declared capability, it definitely has a bearing on that aspect.
Ensuring better system operation is to ensure its efficacy and
functionality as juxtaposed with the integrity of the declaration made,
Page 23 of 34
Civil Appeal No.7432 of 2025 etc.
which is not akin to a normal revision as contemplated under
Regulation 11.5(vii). The demonstration of capability checks the
efficiency of the system to respond to every contingency, including
that provided under Regulation 11.5 (i) to (v), on a real time basis,
which response has to be materialized within four-time blocks. Thus,
the fourth time block is relevant for demonstration, which mandate is
as per sub-clause (xi) of Regulation 11.5, extracted herein above.
The alacrity and expedition with which the SGS responds, is the hall
mark of the integrity of its declaration.
24. Demonstration of declared capability we reiterate, stands on a
different footing from gaming. On notice being issued by the SLDC,
the same has to be demonstrated within the 4
th
time gap, the first
being the one in which the notice is received. In so far as deviation
is concerned, it is governed by the DSM Regulations, which term has
been defined as the total actual injection minus total scheduled
generation in a time block, for a seller, and for a buyer, total actual
drawal minus its total scheduled drawal, again in a time block. In
fact, Regulation 6.1 of the DSM Regulations specifies that the
provisions of the Grid Code and that of the Central Electricity
Regulatory Commission (Open Access in Inter-State Transmission)
Page 24 of 34
Civil Appeal No.7432 of 2025 etc.
Regulations, 2008 as amended from time to time shall be applicable
for declaration of capacity, scheduling and elimination of gaming.
The DSM Regulations as found by the SERC and the APTEL hence, do
not govern a measure adopted to curb either demonstration of the
declared capacity or gaming.
25. A conspectus of the above, according to us, would indicate that
a deviation simplicitor would neither amount to gaming nor
misdeclaration for failure to demonstrate declared capability. But a
failure to demonstrate DC and a measure employed of gaming would
definitely constitute a deviation. Likewise, a failure to demonstrate
declared capability, on notice issued, would not necessarily lead to
an allegation of gaming, which if raised, as we have already found,
should be commenced with a notice, proceeded with an inquiry,
affording a reasonable opportunity to the SGS.
26. Insofar as the ramp up or ramp down is concerned, we cannot
but notice from the SGS that it is provided under the nominal heading
of ‘Governor Action’. Thermal generating units having
electrohydraulic governor system as per the SG Code is to be
operated under restricted governor mode of operation, the features
of which are delineated under the SG Code itself. Ramp up/ramp
Page 25 of 34
Civil Appeal No.7432 of 2025 etc.
back is a recommended rate for changing the governor setting as per
Regulation 5.3.8 of the SG Code, which is not applicable herein.
27. From the above discussion what comes to fore is that the SG
Code in its operation and scheduling and despatch contemplates
breach by the SGS on four facets : (i) over-injection and under-
injection, covered in UI Regulations (ii) deviation, reckoned by the
DSM Regulations (iii) gaming, contemplated under Regulation 11.3.4
read with 11.3.12 and 11.3.20 (iv) demonstration of declared
capability, specified under Regulation 11.3.4 read with Regulation
11.3.13 and 11.5 (xi). Gaming in relation to the SG Code contemplates
an intentional misdeclaration of capacity by a generating station in
order to make an undue gain through UI charges or otherwise. We
reiterate that the notice issued in the instant case is not one for
gaming; for which the finding of mens rea and illegal enrichment is
mandatory, that too in pursuance of an inquiry in compliance of
principles of natural justice.
28. The decision in TPDDL
2, according to us, has been misread
both by the respondent and the APTEL. Therein, the TPDDL, the
procurer of electricity sought for holding respondent No.1, the SGS,
liable for misdeclaration of declared capacity on the ground that at
Page 26 of 34
Civil Appeal No.7432 of 2025 etc.
various instances it had failed to supply power, despite claiming a
higher capability. It was argued by the SGS that this was caused due
to frequent tripping during the winter months, for reason of the filters
of the generating units getting chocked due to combination of fog and
dust. In paragraph 22, APTEL only emphasized that the availability/
capability of a generating station is primarily declared based on the
availability of fuel and the plant’s machinery. This was only in the
nature of an observation that the stock of fuel and the functionality of
the plant are the perceivable grounds on which declaration of
capacity is made and not that these should be the subject of enquiry
when an allegation of misdeclaration is raised. It was also observed
that in the said case there was no reported instances of unavailability
of fuel or the machinery being under shutdown or repair, causing
restriction to the generating station’s capacity. There were only a few
technical issues reported like choking of filters which, as noticed in
paragraph 27 was verified and confirmed by the SLDC as not
amounting to misdeclaration. The deviation between the scheduled
and the actual generation was to be addressed under the DSM
Regulations, was the finding.
Page 27 of 34
Civil Appeal No.7432 of 2025 etc.
29. The observations made in paragraph 22 definitely cannot be
taken as the National Electricity Regulatory Commission (NERC)
having found that a misdeclaration can be raised only if there is
absence of sufficient stock of coal or when the machineries in the
plant were under repair or shutdown, warranting a verification on
that count. A misdeclaration could also occur when, despite the
availability of coal or the plant being ship-shape, higher capability is
declared, with an intention to profiteer which practice is termed as
gaming. Again, a higher capability could be declared despite non-
availability of coal or repair or shutdown of plant, the veracity of
which declaration could be verified by demanding a demonstration
of capability; the measure incorporated to take in such situations. The
availability of coal and the due functionality of the plant, as per the
PPA, is the obligation of the SGS. Any problems surfacing on running
of the generation unit, in the course of the day, could be brought to
the notice of the SLDC and the procurer, enabling also a revision of
declared capacity as per the SG Code. The respondent as we
observed had attempted to raise a contention of force majure which
was hastily abandoned on our query to substantiate it, which
contention was also not raised before the SERC or the APTEL.
Page 28 of 34
Civil Appeal No.7432 of 2025 etc.
30. In the present case on 15.01.2017 one of the plants of the SGS
was shut down and the same was communicated to the SLDC.
However notice was issued to demonstrate the declared capability as
emanating from the two operational units, which the SGS was unable
to demonstrate. No consequence arose to both parties even when
there was shut down of one among the three plants, since the
procurer scheduled their necessity below that possible of generation
from the two functional plants. The consequence arose when the SGS
was not able to demonstrate even that capability declared on the
strength of the functional plants.
31. The demonstration of declared capability invites strict liability
if the declared capability is not achieved within four time-blocks,
treating the time block in which the notice of demonstration is
received as the first block. This is also a measure of ensuring that the
SGS has declared its capability faithfully and in accordance with the
SG Code, since the procurer has the liability to pay in accordance
with the generation schedule as formulated by the SLDC as per the
‘Steps in Scheduling’ in the SG Code, even if the drawal of the
procurer is lesser than the scheduled generation and the declared
capability. The procurer is liable to pay fixed charges in accordance
Page 29 of 34
Civil Appeal No.7432 of 2025 etc.
with the declared capability and variable charges as per the
generation schedule. The SLDC who has finalized the generation
schedule of the SGS and the drawal schedule of the procurer hence
is empowered to seek demonstration, to verify the veracity of the
capability declared. The failure of the SGS would be because of
absence of sufficient stock of coal, repair of machinery or any other
reason which the SGS should have reckoned before intimating the
station-wise power plant capabilities, as per the SG Code, or seek
revision if a reduction of capability is occasioned on a real time basis.
32. Dharamendra Textile Processors
1 considered the issue as to
whether Section 11-AC of the Central Excise Act, 1944 imposes a
mandatory penalty on evasion of duty and whether mens rea is an
essential ingredient in levying penalty; thus, clothing the authority
with a discretion in the matter of the quantum of penalty imposed.
The dictum in Chairman, SEBI v. Sri Ram Mutual Fund and Anr.
6
was approved wherein it was held that mens rea though sine qua non
for criminal or quasi criminal proceedings, it cannot result in a
straitjacket formula without looking at the language and scheme of
the Act. If the imposition of penalty arises from a breach of civil
6
(2006) 5 SCC 361
Page 30 of 34
Civil Appeal No.7432 of 2025 etc.
obligation, then the mere use of the word ‘penalty’ would not be
determinative of whether the nature of proceedings is criminal or
quasi criminal. The contravention, whether it be with a guilty intent
or not if it leads to breach of a civil obligation, the absence of mens
rea will not be of any consequence. The penalty as coming out from
Regulation 11.3.13 of the SG Code is a civil liability since the
obligation of the SGS to generate power in accordance with its
declared capability flows from the contract, a civil obligation. A
default therein as coming out from a failure to demonstrate declared
capability attracts penalty, without anything more, making its
imposition imperative, as per the statutory scheme. The said measure
of imposition of penalty does not call for any finding of mens rea or a
finding of illegal profiteering as would be required when there is an
allegation of gaming.
33. In considering the failure to demonstrate the declared capacity
on each day, we have looked at the spread sheets of ‘Summary of
Declared Capacity, Schedule Generation, Actual Generation and
Deviation’ for each of these days, as produced before us across the
Bar by the respondent. On 15.01.2017, one of the three units were on
reserve shutdown, and the day started with a declared capacity of
Page 31 of 34
Civil Appeal No.7432 of 2025 etc.
1563.80 MW, and scheduled generation of 616 MW. The deviation, as
per the SLDC was minimal, though existing. On the time block
between 5:45 to 06:00, the SGS sent a revision of declared capability,
hiking it up to 1841.40 MW. The SLDC at 07:50 and 08:23 revised the
schedule generation and a demonstration notice was sent in the time
block of 09:30 to 09:45. The declared capability revised by the SGS,
in the course of the day to 1841.40 MW was not at all achieved on the
said day, much less on the 4
th
time block from the time block in which
the notice was received.
34. On 17.01.2017 only one unit was running, the second being
under reserve shutdown and the third on scheduled shutdown due to
fault in the plant. The declared capacity as on the start of the time
blocks of the day was 1229.80 MW, which was revised by the SGS in
the time block 02:30 to 02:45. The SLDC sought the first revision of
scheduled generation and a second revision. respectively at 03.43 &
05:23. A demonstration notice is admitted to be received at 8:15
hours and based on it the declared capacity of 922.80 MW, as
reduced in the course of the day, was to be achieved in the 4
th
time
block from then. However, on the second time block from the
issuance of demonstration notice, the SGS sought a downward
Page 32 of 34
Civil Appeal No.7432 of 2025 etc.
revision of the declared capacity at 08:58 hours and revised it to 250
MW. The SGS not only failed to demonstrate the declared capacity
but sought the declared capacity to be reduced after the
demonstration notice was issued. Yet again, the declared capacity
was revised to 150 MW on the same day.
35. On 24.01.2017, the declared capacity commenced with 1600
MW and the schedule generation was 924 MW which was revised on
a total of nine occasions in the course of the day, by the SLDC.
Obviously, finding no positive response, a demonstration notice was
issued by the SLDC received by the SGS at 14:48 hours. The declared
capacity and the scheduled generation, both at 1650 MW was neither
achieved at the 4
th
time block nor at any time after that.
36. The situation was slightly better on 31.01.2017 when the
declared capacity commenced with 1473.12 MW and the scheduled
generation was 924 MW. Two demonstration notices were issued;
one received by the SGS at 08:20 hours and the other at 09:23 hours.
The declared capacity was not achieved at the 4
th
time block from the
first notice. However, at the 3
rd
time block from the first notice, that
is the 7
th
time block from the first notice it was achieved. The finding
of misdeclaration insofar as the failure to demonstrate the declared
Page 33 of 34
Civil Appeal No.7432 of 2025 etc.
capacity, on each of these days thus stands established
unequivocally.
37. PSEB
3 was in the context of the generating stations using both
gas and liquid, to fire their plants; the use of gas being more
economical. The allegation was of substitution of fuel, thus receiving
more than the due share of variable charges by under-declaring the
generation capacity on gas, while declaring more on liquid fuel. The
excess generation alleged by use of gas came to 1% of the declared
capacity on gas, which was found to be within practical limits,
relatable to gross calorific value of gas received on a day-to-day
basis, totally inapplicable to the instant case.
38. On the above reasoning, we set aside the order of the APTEL
and restore the order of the SERC. We also modify the restored order
to the extent of interfering with the finding that Regulation 11.3.13
provides the procedure to deal with the measure of gaming under
Regulation 11.3.4 & 11.3.12; which we have found to be distinct
misdemeanors and the finding that on imposing penalty based on a
failure to demonstrate the declared capability, ‘deliberate intention
and motive to make money’ are necessary ingredients; which we have
found otherwise. The consequences of such reversal insofar as the
Page 34 of 34
Civil Appeal No.7432 of 2025 etc.
affirmation of the penalty imposed and the resultant interest liability
if any, shall necessarily follow. Any surcharge paid on the bills only
for reason of deductions made of the penalty imposed, based only on
the reversal of the order of the SERC shall also be refunded to the
PSPCL, with interest/surcharge at the same rate since the SGS had the
benefit of such amounts in the ensuing period after the order of
APTEL.
39. The appeals are allowed with the above directions.
40. Pending applications, if any, shall also stand disposed of.
.………………………… …... J.
(SANJAY KUMAR)
..………… .…………………. J.
(K. VINOD CHANDRAN )
NEW DELHI;
MAY 20, 2026.
Legal Notes
Add a Note....