As per case facts, a promoter issued a Holding Receipt and later an Allotment Letter for a flat, receiving a significant payment from the allottees. The project was registered under ...
SA-258-26.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
SECOND APPEAL NO. 258 OF 2026
Rare Townships Pvt. Ltd.
CTS 194-B, Ghatkopar – Mankhurd Road,
Opp. Chedda Nagar, Chembur (East),
Mumbai – 400089, Maharashtra ...Appellant
Versus
1. Archana Y A Upadhyay & anr.
Age : - Adult,
2. Dr. A K Upadhyay,
Age:- Adult,
Both having residential address
at Flat No. A-802, Sabari
Aashiana, Near Anushaktinagar,
Deonar Farm Road, Deonar,
Mumbai – 400088, Maharashtra.
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
…Respondents
_ _ _ _ _ _ _ _ _
WITH
INTERIM APPLICATION NO. 3953 OF 2026
IN
SECOND APPEAL NO. 258 OF 2026
Mr. Mayur Khandeparkar, a/w Mr. Rubin Vakil, Ms. Ayushi
Anandpara, Mr. Shubham Hundia, i/b Satyaki Law
Associates, for the Appellant.
Ms. Archana Upadhyay & Mr. A K Upadhyay – Respondents.
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
CORAM :N. J. JAMADAR, J.
RESERVED ON : 28
th
SEPTEMBER 2026
PRONOUNCED ON : 13
th
OCTOBER 2026
SAINATH, PA 1/23 2026:BHC-AS:41705
SA-258-26.DOC
JUDGMENT:
1.This Appeal is directed against an order dated 26
th
November, 2025 passed by the Maharashtra Real Estate
Appellate Tribunal, Mumbai (“Appellate Tribunal”) in
Miscellaneous Application No. 860/2025 in Appeal No.
AT06/00747/2025 preferred by the Respondents/allottees,
and an order dated 16
th
April, 2026 in Review Application
No. 05/2026 whereby the first order was modified to
correct the amount paid by the allottees and the date of
the allotment letter.
2.The background facts leading to this Appeal can be
summarized as under :-
2.1The appellant is the promoter of the project “Rising
City”, Ghatkopar, Mumbai. On 15
th
January, 2011, the
appellant issued a Holding Receipt in respect of a Flat
bearing No. B-706 admeasuring 1200 sq.ft. plus one
parking space, for a total consideration of Rs.
1,35,72,000/- (Rupees One Crore Thirty Five Lakhs
Seventy Two Thousand only).
2.2Subsequently, on 30
th
September 2014, an allotment
letter was issued in favour of the allottees in respect of Flat
SAINATH, PA 2/23
SA-258-26.DOC
No. 805 in building ‘A-1’ admeasuring 1103.01 sq. ft, (“the
subject flat”) for a consideration of Rs. 1,24,80,000/-
(Rupees One Crore Twenty Four Lakhs Eighty Thousand
only). The allottees claimed to have paid a sum of Rs.
58,47,609/- (Rupees Fifty Eight Lakhs Forty Seven
Thousand Six Hundred and Nine only) up to 07
th
November, 2016. Upon coming into force of the Real Estate
(Regulation and Development) Act, 2016 (“the RERA,
2016”), the project in question came to be registered with
the Maharashtra Real Estate Regulatory Authority (“the
Authority”) as “North Sea Heights (A-1)”.
2.3On 05
th
May, 2024, asserting that, the promoter
failed to execute a registered agreement for sale despite
having received a substantial consideration; complete the
project and deliver the possession of the subject flat, the
allottees filed a complaint before the Authority seeking
diverse reliefs including of interest for delayed possession
and compensation.
2.4By a judgment and order dated 02
nd
July, 2025, the
Authority was persuaded to partly allow the complaint. The
promoter was directed to execute a registered agreement for
SAINATH, PA 3/23
SA-258-26.DOC
sale with respect to the subject flat in conformity with the
statutory obligation under Section 13 of the Act, 2016 as
per the terms and conditions incorporated in the allotment
letter dated 30
th
September, 2014, within a period of 30
days thereof.
2.5It was declared that, upon execution of the
agreement for sale, the allottees shall be liable to pay the
outstanding amount towards the consideration and also
interest for the delay in making the payments as per the
stage of construction as mandated under Section 19(7) of
the Act, 2016. Simultaneously, the promoter was directed
to pay interest for the delayed delivery of possession to the
allottees from 04
th
October, 2024 at the stipulated rate till
the date of offer of possession with an Occupation
Certificate (OC) on the actual amount paid by the allottees
towards consideration. Making a provision for adjustment
and set off, the Authority directed that the balance
amount, if any, payable by either party shall be paid at the
time of delivery of possession.
2.6The allottees preferred an appeal before the Appellate
Tribunal seeking inter alia directions to the promoter to
SAINATH, PA 4/23
SA-258-26.DOC
execute a RERA compliant agreement in favour of both the
allottees, and incorporating therein the promised amenities
including specific parking slot, and clauses compliant with
the model agreement for sale, and to refrain from
demanding payments and issuing termination notices until
a RERA compliant agreement for sale was executed and
registered.
2.7In the said appeal, the allottees filed an application,
inter alia, seeking stay to the execution of the agreement
for sale until compliance with the orders was verified by
the Authority and to restrain the promoter from
demanding payments or issuing termination notices till the
decision of the appeal.
2.8By an order dated 26
th
November, 2025, the Appellate
Tribunal was persuaded to allow the said interim
application, with the following directions :-
“i) The promoter shall, in the light of
observations made here-in-above, share the draft
Agreement for Sale which is RERA compliant and in
terms of the allotment letter dated 30.11.2014 and
shall execute RERA complaint Agreement for Sale
within 60 days of this order.
SAINATH, PA 5/23
SA-258-26.DOC
ii) The applicants have paid Rs. 58,47,609/-
towards the consideration of the said flat to the
promoter which shall be recorded in the draft
Agreement for Sale.
iii)The consideration amount of Rs.
1,24,80,000/- will be in accordance with the said
allotment letter dated 30.11.2014.
iv) The draft Agreement for Sale shall also
specify the due date of possession as per the said
allotment letter and if not specified in the said
allotment letter, shall not be more than three years
from the date of the said allotment letter. Further,
Agreement for Sale shall specify the payment
schedules to be paid by the applicants in the
Agreement for Sale to be executed and registered and
also specify the car parking space as per the said
allotment letter.
v) The promoter shall not further make demand
of any amounts from the applicants till the RERA
compliant Agreement for Sale is executed and
registered.
vi) There would be no question of any interest
on account of delayed payments would arise for any
prior period of Agreement for Sale to be executed and
registered and the payments would be strictly made
by the applicants as per the payment schedule as
incorporated in Agreement for Sale to be executed
and registered by the parties.
SAINATH, PA 6/23
SA-258-26.DOC
vii)Further, the promoter shall provide to the
applicants the deviation report with respect to the
model Agreement for Sale as made available by the
MahaRERA before execution of the said Agreement
for Sale.
viii)The promoter shall not issue any termination
notice on the grounds of non-payment of
outstanding amounts, unless the Agreement for Sale
is executed and registered.
ix) The applicants have granted liberty to file
appropirate Misc. Application for bring on record
additional documents without prejudice to the rights
of the non-applicant to respond to such an
application to be filed by the applicants within 2
weeks of this order.”
2.9In the Review Application filed by the promoter, after
noticing that, upon reconciliation of the accounts, the
parties were ad idem that, the allottees had paid a sum of
Rs. 38,47,247/- (Rupees Thirty Eight Lakhs Forty Seven
Thousand Two Hundred and Forty Seven only) and the
correct date of allotment letter was 30
th
November, 2014,
the Appellate Tribunal corrected the figure in clause (ii)
(extracted above) to Rs. 38,47,247/- from Rs. 58,47,690/-,
and the date of the allotment letter from 30
th
November,
SAINATH, PA 7/23
SA-258-26.DOC
2024 to 30
th
November, 2014. The rest of the prayers of the
promoter in the Review Application were not acceded to.
3.Being aggrieved, the promoter has preferred this
Appeal.
4.I have heard Mr. Mayur Khandeparkar and Mr. Rubin
Vakil, the learned Counsel for the appellant/promoter, and
the Respondents – allottees in person. With the assistance
of the learned Counsel and the parties-in-person, I have
perused the material on record.
5.Mr. Khandeparkar would urge that, the order dated
26
th
November, 2025 passed by the Appellate Tribunal at
an interim stage almost forecloses the determination of the
appeal. At an interim stage, the Appellate Tribunal could
not have issued mandatory directions, that too without
recording reasons, was the thrust of the submission of Mr.
Khandeparkar. Criticizing the directions under clause (iv)
of the impugned order, (extracted above), Mr.
Khandeparkar would urge that, the date on which the
possession of the subject flat was agreed to be delivered
was a matter of contest and yet to be adjudicated by the
Appellate Tribunal. Thus, the direction therein that the
SAINATH, PA 8/23
SA-258-26.DOC
agreement for sale should also specify the due date of
possession as per the allotment letter dated 30
th
November,
2014 and, if not specified therein, the date of possession
should not be more than 3 years from the date of the said
allotment letter, renders the adjudication in the appeal
redundant.
6.Likewise, the direction in clause (vi) of the impugned
order restraining the promoter from claiming interest on
account of delayed payment in accordance with the terms
of the contract between the parties for the period prior to
the execution of the agreement for sale has the trappings
of finally deciding the appeal. Therefore, Mr. Khandeparkar
would urge, at the least, two substantial questions of law
arise. First, whether the Appellate Tribunal committed a
manifest error in passing the interlocutory operative
directions as contained in clause (iv) of the order dated 26
th
November, 2025 sans reasons ? And second, whether the
Appellate Tribunal committed manifest error in specifying
the date of delivery of possession to be incorporated in the
agreement for sale without recording reasons in support
thereof, especially in the context of the operative directions
at Paragraph No. 14(f) of the order passed by the Authority.
SAINATH, PA 9/23
SA-258-26.DOC
7.The allottees in person have stoutly countered the
submissions on behalf of the appellant. Highlighting the
nature of the dispute and the defaults on the part of the
promoter to deliver the possession of the subject flat
though a period of more than 15 years has elapsed, the
allottees have asserted that no substantial question of law
arises for consideration. The allottees laid emphasis on the
purported blameworthy conduct of the promoter. It was
urged that, since the promoter did not prefer an appeal
against the order passed by the Authority, the said order
has attained finality qua the promoter and the impugned
order passed by the Appellate Tribunal has merely
operationalised and given meaning and content to the
order passed by the Authority.
8.To start with the uncontroverted facts. First, the jural
relationship between the appellant and the respondents as
promoter – allottees is not in dispute. There is also not
much controversy over the fact that initially a Holding
Receipt dated 15
th
January, 2011 in respect of Flat No. B-
706/East Block for a consideration of Rs. 1,35,72,000/-
(Rupees One Crore Thirty Five Lakhs Seventy Two
Thousand only) was issued and, subsequently, the parties
SAINATH, PA 10/23
SA-258-26.DOC
agreed to a change in flat and consideration therefor. The
consequent issuance of a provisional letter of allotment
dated 30
th
November, 2014 in favour of allottees in respect
of the subject flat for a consideration of Rs. 1,24,80,000/-
(Rupees One Crore Twenty Four Lakhs Eighty Thousand
only), is incontestable. The parties are also not at issue
over the registration of the project under the name and
style “North Sea Heights (A-1)” after the coming into force
of the RERA, 2016.
9.By and large, there is not much controversy over the
fact that the allottees have paid a sum of Rs. 38,47,247/-
towards consideration, by the year 2016. As a matter of
fact, the agreement for sale has not been executed by the
promoter in favour of the allottees. The controversy
between the parties revolves around the defaults in the
execution of the agreement for sale, the payment of
balance consideration, the terms of the agreement for sale
and the delay in the completion of the project and the
resultant liability of the parties.
10.The imperativeness of the execution of a registered
agreement for sale cannot be overemphasized. It is the
SAINATH, PA 11/23
SA-258-26.DOC
mischief of accepting substantial amounts from the flat
purchasers without executing the Agreements for Sale that
was sought to be addressed by legislative measures. The
provisions contained in Section 4 of the Maharashtra
Ownership Flats (Regulation of the Promotion of
Construction, Sale, Management and Transfer) Act, 1963,
(“MOFA, 1963”), proscribed acceptance of any sum of
money as advance payment or deposit exceeding 20% of
the sale price without entering into a written agreement for
sale and mandated that such agreements shall be
registered under the Registration Act, 1908. To address
the further mischief of exploiting the vulnerabilities and
lack of bargaining power of flat purchasers, the law
mandated that the Agreements for Sale should be executed
in the prescribed form, incorporating essential terms of the
bargain, so as to protect the interest of the flat purchasers.
MOFA 1963, thus directed that such agreement shall be in
the prescribed form.
11.RERA, 2016, has made it obligatory on the promoter
to execute a registered agreement for sale, before the
promoter accepts a sum of more than 10% of the cost of
the apartment. Sub-section (1) of Section 13 mandates
SAINATH, PA 12/23
SA-258-26.DOC
that the promoter shall not accept a sum of more than 10%
of the cost of the apartment, plot or building, as an
advance payment or an application fee from a person
without first entering into a registered written agreement
for sale. Sub-section (2) of Section 13 provides that the
agreement for sale shall be in such form as may be
prescribed, and enumerates the particulars that are
required to be mandatorily specified therein, apart from
such other particulars, as may be prescribed.
12.The mandatory specifications include, inter alia, the
particulars of the development of the project including the
construction of the building and apartments, alongwith
specifications and internal development works and
external development works, the dates and manner by
which the payment towards the cost of the apartment, plot
or building, as the case may be, is to be made by the
allottee, and the date on which possession of the
apartment is to be handed over, and the rates of interest
payable by the promoter to the allottee and the allottee to
the promoter in case of default.
SAINATH, PA 13/23
SA-258-26.DOC
13.In the light of the aforementioned statutory mandate,
which has been incorporated to ensure that the sale of the
apartment takes place in a transparent manner and to
protect the interest of consumers in the real estate sector,
the legality and justifiability of the impugned order
deserves to be appreciated.
14.As noted above, the promoter has accepted a sum of
Rs. 38,47,247/- without executing an agreement for sale.
The said amount constitutes more than 30% of the agreed
consideration. Under the legal regime governing the field,
even before the enforcement of RERA 2016, also, the
promoter could not have accepted the said amount without
executing a registered agreement for sale. Thus, the
direction issued by the Authority to execute the registered
agreement for sale in favour of the allottees, in conformity
with the provisions contained in Section 13 of RERA 2016
is legally impeccable.
15.The fulcrum of the challenge was the specification of
the date of delivery of possession in the agreement for sale
to be executed by the promoter in favour of the allottees.
The Authority did not, in terms, indicate the date of
SAINATH, PA 14/23
SA-258-26.DOC
delivery of possession to be incorporated in the agreement
for sale in Clause 14(c), which directed the execution of a
registered agreement for sale. The substance of the
submission on behalf of the promoter was that the
direction in Clause (iv) of the impugned order to specify the
due date of possession as per the allotment letter and, in
the absence of such specification in the allotment letter,
the date of possession shall not be more than three years
from the date of the allotment letter was sans
consideration and reasons, and that could not have been
done at an interlocutory stage.
16.To appreciate the aforesaid submission in the
backdrop of the facts that prima facie emerge from the
record, (being fully conscious of the fact that the appeal
preferred by the allottees awaits final adjudication by the
Appellate Tribunal), recourse to the stipulations in the
allotment letter becomes necessary. Clause (10) of the
allotment letter dated 30
th
September, 2014 reads as under:
“10.We have informed you that the said building will
be completed within a period of 42-months from the date
of start of construction and or of obtaining of the
commencement certificate in respect whereof, subject
however, to force majeure and circumstances beyond our
control.”
SAINATH, PA 15/23
SA-258-26.DOC
17.The aforesaid stipulation makes it crystal clear that
the promoter had agreed to complete the construction of
the building within a period of 42 months from the grant of
the commencement certificate. The allotment letter thus
indicated the time frame within which the building was to
be constructed and possession of the subject flat was to be
delivered to the allottees.
18.This Court finds that in paragraph 13(i), (j), (k) and
(l), the Authority construed the terms of the allotment
letter to arrive at a finding regarding the date of delivery of
possession of the subject flat by the promoter to the
allottees. Taking note of the grant of the commencement
certificate on 1
st
October, 2016 and the revision thereof, the
Authority recorded that the expected date of delivery of
possession would have been 4
th
April, 2023. The Authority
further professed to grant the benefit of the provisions
contained in Section 8(b) of MOFA 1963, and the extension
granted by the Authority in the wake of the COVID-19
pandemic and held that the date of delivery of possession
of the subject flat stood extended upto 4
th
October, 2024.
The allottees were thus held entitled to seek interest on
account of delay in the delivery of possession, as
SAINATH, PA 16/23
SA-258-26.DOC
prescribed under Section 18 of the RERA 2016, from 4
th
October, 2024 till the date of offer of possession of the
subject flat with Occupation Certificate (OC).
19.Undoubtedly the aforesaid determination by the
Authority is under challenge before the Appellate Tribunal.
Yet, it is imperative to note that, the aforesaid order passed
by the Authority was not challenged by the promoter. Nor
does it appear that the promoter preferred any cross-
objection in the appeal preferred by the allottees.
20.In the light of the above, the broad features of the
case deserve to be noted. First, the termination of the
allotment by the promoter has been explicitly declared by
the Authority to be neither proper nor legal as it was in
contravention of Section 13 of RERA 2016. Second, the
statutory liability to execute the registered agreement for
sale can hardly be disputed. Third, in the order passed by
the Authority, which is impugned before the Appellate
Tribunal, the date of delivery of possession has been
arrived at by the Authority, though in the operative order,
the Authority has not specified the said date. Fourth, the
promoter has not challenged the order passed by the
SAINATH, PA 17/23
SA-258-26.DOC
Authority, including the direction in paragraph 14(f) of the
order passed by the Authority to pay interest for the
delayed possession from 4
th
October, 2024.
21.If considered, in the backdrop of the aforesaid
features, the directions in the impugned order appear to be
in consonance with the object of RERA 2016, and the
provisions thereunder, save and except the stipulation as
to the date to be specified in the agreement for sale for the
delivery of possession of the subject flat. In the considered
view of this Court, the date of delivery of possession is a
matter which warrants adjudication at the final hearing of
the Appeal, especially in view of the categorical finding of
the Authority that the date of possession stood extended
upto 4
th
October 2024.
22.It would be contextually relevant to note that, the
respondents-allottees have filed an affidavit regarding the
date of delivery of possession of the subject flat to be
determined by the Appellate Tribunal at the time of final
adjudication of the appeal. In the affidavit filed on behalf of
the allottees on 19
th
August, 2026 the allottees have
affirmed that, without prejudice to the rights and
SAINATH, PA 18/23
SA-258-26.DOC
contentions of the allottees, the Appellate Tribunal may fix
the date of delivery of possession of the subject flat.
Paragraphs 10 and 11 of the said affidavit read as under:
“10.As suggested during the deliberations
before this Hon’ble Court, we have no objection if
the Hon’ble Maharashtra Real Estate Appellate
Tribunal (MahaREAT) considers fixing a definite
date of possession in place of the present
direction contained in Clause (iv) of the operative
portion at page 14 of the order dated 26
th
November 2025, which reads as under :
“iv) The draft agreement for sale shall also specify
the due date of possession as per the said
allotment letter and if not specified in the said
allotment letter, shall not be more than three
years from the date of the said allotment letter.”
11.It is humbly submitted that our no
objection recorded above is, however, subject to
the following so as to fully safeguard our interests
and to ensure that all facets of the pending appeal
before the Hon’ble MahaREAT continue without
any prejudice :
(a)Any definite date of possession that may be
fixed by the Hon’ble MahaREAT shall be without
prejudice to all our rights, contentions, claims
and remedies in the pending Appeal
No.AT06/00747 of 2025 and connected
proceedings before the Hon’ble MahaREAT.
(b)The pending appeal before the Hon’ble
MahaREAT shall continue on all issues,
including but not limited to the correct date of
booking (January 2011), quantum of payments
made, deviations from the model Agreement for
Sale, interest and compensation under Section 18
of the Real Estate (Regulation and Development)
Act, 2016, parking, amenities, and all other
grounds raised by us;
(c)Fixation of any definite possession date
shall not amount to waiver, abandonment,
curtailment or prejudice of any our rights or
contentions, nor shall it limit or affect the scope of
the Appeal pending before the Hon’ble MahaREAT
in any manner;
SAINATH, PA 19/23
SA-258-26.DOC
(d)All other directions contained in the order
dated 26
th
November 2025 (as modified /
corrected by the Review Order dated 16
th
April
2026) shall continue to operate with full force and
effect; and
(e)The present statement of no
objection is made purely in furtherance
speedy delivery of justice and is without
prejudice to all our rights and contentions
in the present Second Appeal as well as in
the proceedings pending before the
Hon’ble MahaREAT.”
23.In view of the aforesaid statement made on behalf of
the allottees that, the question of date of delivery of
possession be kept open to be adjudicated by the Appellate
Tribunal, it would be appropriate to modify the direction in
regard to the date of delivery of possession, to be
incorporated in the agreement and specify that the date
stipulated by the Authority in the order impugned before
the Tribunal, i.e., 4
th
October, 2024, shall be incorporated
in the agreement for sale as a tentative date, subject to the
final adjudication by the Appellate Tribunal. In the event
the Appellate Tribunal alters the date of delivery of
possession determined by the Authority, the parties rights
and liabilities will be governed by the determination so
made by the Appellate Tribunal, and the parties will have
to execute an appropriate deed of rectification.
SAINATH, PA 20/23
SA-258-26.DOC
24.At this juncture, this Court need not delve into the
other disputes between the parties, including the terms of
the agreement for sale. Suffice to clarify that the agreement
for sale to be executed by the promoter in favour of the
allottees, shall be in conformity with the provisions
contained in Section 13 of RERA, 2016, and the model
form of the agreement for sale prescribed by the Authority.
And all questions shall remain open for adjudication by the
Appellate Tribunal.
25.Hence, the following order:
: O R D E R :
(I)The second appeal stands disposed with the following
directions:
(a)The date of delivery of possession to be incorporated
in the agreement for sale to be executed by the
appellant in favour of the respondents shall be 4
th
October, 2024.
(b) The aforesaid date shall be tentative and without
prejudice to the rights and contentions of the parties,
and subject to the final adjudication by the Appellate
Tribunal in the appeal preferred by the allottees.
SAINATH, PA 21/23
SA-258-26.DOC
(c)In the event the Appellate Tribunal alters the
aforesaid date, the rights and liabilities of the parties
shall be governed by such date of delivery of
possession to be determined by the Appellate
Tribunal and, in that event, the parties shall execute
the requisite deed of rectification.
(d) The agreement for sale to be executed by the
Appellant in favour of the respondents shall be in
conformity with the provisions of Section 13 of RERA
2016, and the model form of agreement (Annexure ‘A’)
prescribed under Rule 10(1) of the Maharashtra Real
Estate (Regulation and Development) (Registration of
Real Estate Projects, Registration of Real Estate
Agents, Rates of Interest and Disclosure on website)
Rules, 2017.
(e) Such agreement for sale shall be executed and
registered within a period of four weeks from today.
(f)All contentions of the parties on all the points are
expressly kept open and shall be adjudicated by the
Appellate Tribunal at the time of final adjudication of
the appeal.
SAINATH, PA 22/23
SA-258-26.DOC
(II)In view of disposal of the appeal, IA/3953/2026 also
stands disposed.
[N. J. JAMADAR, J.]
SAINATH, PA 23/23