S. Harcharan Singh Vs. Union of India

  Supreme Court Of India Civil Appeal /322/1976
Link copied!

Case Background

As per case facts, a contractor undertook a bridge construction project, exceeding the agreed-upon hard rock cutting quantity. The contractor sought higher remuneration for this additional work, leading to a ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 11

PETITIONER:

S. HARCHARAN SINOH

Vs.

RESPONDENT:

UNION OF INDIA

DATE OF JUDGMENT28/08/1990

BENCH:

AGRAWAL, S.C. (J)

BENCH:

AGRAWAL, S.C. (J)

MISRA RANGNATH

PUNCHHI, M.M.

CITATION:

1991 AIR 945 1990 SCR Supl. (1) 76

1990 SCC (4) 647 JT 1990 (3) 692

1990 SCALE (2)413

ACT:

Arbitration Act, 1940: Sections 14, 17, 30 and

33--Contract for specified work--Claim for entire additional

work at increased rate-Arbitrator awarding increased rate

for part of the additional work-Whether Arbitrator exceeded

his jurisdiction--Award--Whether vitiated.

HEADNOTE:

The appellant was awarded a contract for constructing

approaches to certain Bridge structure. As per the agree-

ment, he was required to do hard rock cutting to the extent

of 7,54,530 cft. and the rate fixed was Rs.129 per thousand

cft. plus 2%. Actually the appellant was required to perform

hard rock cutting to the extent of 18,18,704 cft. For the

additional work, the appellant claimed payment at the rate

of Rs.200 per thousand cft. He also claimed certain other

sums under other heads. Dispute in respect of 4 heads was

referred to arbitration. The arbitrator in his award disal-

lowed two claims and allowed the other two claims, one of

which was in respect of the additional work of hard rock

cutting, and awarded a sum of Rs.52,800 under this head. The

arbitrator filed the award in the High Court. After consid-

ering the objections filed by the respondent a Single Judge

of the High Court ordered that the award be made a rule of

the Court. The respondent filed an appeal against the said

order and the Division Bench set aside, ex-parte, the claim

for higher remuneration at the rate of Rs.200 per thousand

cft. Aggrieved, the appellant has preferred an appeal, by'

special leave.

The other appeal, also by special leave, is against the

High Court's rejection of the prayer for setting aside the

ex-parte judgment.

Allowing the former appeal and disposing of the latter one,

HELD: 1. As regards the award of an arbitrator under the

Act, the law is well settled that the arbitrator's adjudica-

tion is generally considered binding between the parties for

he is a tribunal selected by the parties and the power of

the court to set aside the award is restricted to cases set

out In section 30 of the Act. It is, however, not open to

the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 11

77

Court to speculate, where no reasons are given by the arbi-

trator, as to what impelled the arbitrator to arrive at his

conclusion. But the jurisdiction of the arbitrator is limit-

ed by the reference and if the arbitrator has assumed juris-

diction not possessed by him, the award to the extent to

which it is beyond the arbitrator's jurisdiction would be

invalid and liable to be set aside. An arbitrator or umpire

is under no obligation to give reasons in support of the

decision reached by him unless under the arbitration agree-

ment or the deed of submission he is required to give such

reasons. If the arbitrator or umpire chooses to give reasons

in support of his decision it is open to the Court to set

aside the award if it finds that an error of law has been

committed by him on the face of the record. An award can

neither be permitted nor set aside merely on the ground that

it does not contain reasons in support of the conclusion or

decisions reached in it except where the arbitration agree-

ment or the deed of submission requires him to give reasons.

[82H; 83A-E]

Jivarajbhai Ujamshi Sheth and Others v. Chintamanrao

Balaji and Others, [1964] 5 SCR 480; Raipur Development

Authority and Others v. M/s Chokhamal Contractor and Others,

[1989] 2 SCC 721, relied on.

2.1 In the instant case the arbitration agreement or the

deed of submission did not require the arbitrator to give

reasons and, therefore, the award cannot be questioned on

the ground of an error on the face of the award. The Divi-

sion Bench of the High Court set aside the award in respect

of the claim relating to payment for additional work of hard

rock cutting on the ground that in making the award the

arbitrator exceeded his jurisdiction by allowing a rate to

the contractor in excess of the agreed rate for the job of

hard rock cutting against the terms and conditions in clause

12 of the agreement. [83F-G]

2.2 Under clause 12 of the agreement, the Engineer-in-

charge was empowered to make any additions to the original

specifications that may appear to him to be necessary or

advisable during the progress of the work and the contractor

was bound to carry out the work in accordance with any

instructions given to him in writing signed by the

Engineer-in-charge. [85B-C]

2.3 It has to be inferred from the terms of the contract

whether this power to order extras, although apparently

unlimited, is in fact limited to ordering extras upto a

certain value and in such a case, extras ordered in excess

of that amount may be outside the terms of the contract.

78

Parkinson (Sir Lindsay) & Co. Ltd. v. Commissioners of

His Majesty's Works and Public Buildings, [1949] 2 K.B. 632,

referred to.

Hudson's Building and Engineering Contracts, 8th Edn.

pp. 294, 296, referred to.

3. In some awards given by the arbitrators in the Cen-

tral Public Works Department of the Government of India the

variation of the tendered quantities under the variation

clause in the contract has been restricted to 10% beyond

which the contractor was entitled to claim as extras and

awards have been accepted and implemented by the Government.

It appears that the standard form of contract of the Central

Public Works Department has been amended and now it specifi-

cally permits for a limit of variation called "deviation

limit" upto a maximum of 20% and upto such limit the con-

tractor has to carry out the work stipulated in the contract

and for the work in excess of that limit at the rates to be

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 11

determined in accordance with clause 12-A under which the

Engineer-in-Charge can revise the rates having regard to the

prevailing market rates. [88D-F]

Gajaria's Law relating to Building and Engineering

Contracts in India, 3rd Edn., pages 410-412, referred to.

4. In the instant case, the Executive Engineer, the

Superintending Engineer and the Additional Chief Engineer

have expressed the view that the additional work under the

terms of the contract may be confined to 20% and the appel-

lant may be paid at the rates prescribed in the contract for

20% of the additional work and for the extra quantity of

additional work he may be paid remuneration at the increased

rate taking into account the increased costs in execution of

the said work on account of the peculiar nature of the work

while considering the claim of the appellant the arbitrator

was required to consider the terms of the contract and to

construe the same. It was, therefore, permissible for the

arbitrator to consider whether clause 12 of the contract

enables the Engineer-in-charge to require the appellant to

execute additional work without any limit, or a reasonable

limit should be placed on the quantity of the additional

work, which the appellant may be required to execute at the

rate stipulated for the main work under the contract. For

that purpose the arbitrator could take into consideration

the practice prevalent in the Central Public Works Depart-

ment in this regard as well as the correspondence between

the appellant and the authorities recommending payment of

remuneration at the increased rate for the additional work

in excess of 20% of the quantity stipulated in the contract.

79

The appellant was claiming increased rate of Rs.200 per 1000

cft. for the entire quantity of additional work. The arbi-

trator did not accept the said claim of the appellant in

full and has partly allowed the said claim by awarding

Rs.52,800 which means that the arbitrator has awarded the

increased rate only for a part of the additional work of

hard rock cutting which the appellant was required to exe-

cute. The arbitrator was entitled to do so on the construc-

tion placed by him on clause 12 of the contract and, there-

fore, it cannot be said that in awarding the sum of

Rs.52,800 for the additional work the arbitrator has exceed-

ed his jurisdiction and the award is vitiated by an error of

jurisdiction. [88G-H; 89A-E]

5. The judgment of the Division Bench of the High Court

setting aside the award of the arbitrator with regard to the

claim relating to payment for additional work of hard rock

cutting is set aside and the order passed by the Single

Judge upholding the award of the arbitrator in this regard

is restored. [89F]

6. Since the judgment of the Division Bench of the High

Court is set aside the appeal against the order rejecting

the prayer for setting aside the ex-parte judgment, does not

survive. [90B]

JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeals Nos. 322 &

323 of 1976.

From the Judgment and Order dated 27.3.1973 and 23.5.75

of the Delhi High Court in F.A.O. (O.S.) No. 35 of 1969 and

C.M. No. 1300 of 1974 in F.A.O. (O.S.) 35 of 1969.

P.P. Juneja for the Appellant.

B.B. Barua, Ms. A. Subhashini (N.P.) and Ms. Indira

Sawhney ( N.P. ) for the Respondent.

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 11

The Judgment of the Court was delivered by

S.C. AGRAWAL, J. Civil Appeal No. 322 of 1976

This appeal by special leave has been filed against the

judgment dated March 27, 1973 of the High Court of Delhi in

F.A.O. (O.S.) No. 35 of 1968.

The appellant, S. Harcharan Singh, was awarded a contract

for

80

constructing approaches to the Bridge Structure B-2 on the

North Sikkim Road in 1959-60. Under the agreement the appel-

lant was required to do hard rock cutting to the extent of

7.54,530 cft. The rate fixed for the said work in the con-

tract was Rs.129 per thousand cft. plus 2%. The appellant

was required to perform hard rock cutting to the extent of

18, 18,704 cft. The appellant claimed payment at the rate of

Rs.200 per thousand cft. for the additional work of hard

rock cutting. He also claimed certain other sums under other

heads. The dispute in respect of four heads was referred to

arbitration in accordance with the clause 25 of the agree-

ment. The arbitrator gave his award dated February 5, 1965

wherein he disallowed the claim of the appellant in respect

of two items but made an award in favour of the appellant in

respect of two items of claim. In this appeal we are only

concerned with the claim of the appellant in respect of the

additional work of hard rock cutting which the appellant was

required to execute. The arbitrator awarded a sum of

Rs.52,800 against the said item. The award was filed in the

High Court by the arbitrator alongwith his letter dated June

6, 1968. Objections were filed by the respondent under

Sections 30 and 33 of the Arbitration Act, 1940 (hereinafter

referred to as 'the Act'). The said objections were consid-

ered by the learned single Judge of the Delhi High Court and

by order dated April 23, 1969. the said objections of the

respondent were rejected and it was ordered that the award

be made a rule of the Court. The respondent filed an appeal

against the said order and decree passed by the learned

single Judge. The appeal was partly allowed by the Division

Bench of the High Court by judgment dated March 27, 1973,

whereby the award as regards the claim for higher remunera-

tion at the rate of Rs.200 per thousand cft. for the addi-

tional work of hard rock cutting was set aside. The award in

respect of other item of the claim relating to expenditure

incurred by the appellant in reconstructing the retaining

walls after damage, was maintained. Aggrieved by the said

decision of the Division Bench of the High Court the appel-

lant has filed this appeal after obtaining special leave.

As indicated earlier, this appeal is confined to the

claim of the appellant for payment for the additional work

of hard rock cutting which the appellant was required to

execute. The appellant has claimed a higher rate of Rs.200

per thousand cft. for this additional work. Under the agree-

ment the appellant was required to execute hard rock cutting

to the extent of 7,54,530 cft. but actually he was required

to execute such cutting to the extent of 18.15 lacs cft. The

extent of the additional work was about 10.60 lacs cft.,

i.e. about 140%. While undertaking the execution of the

additional work of hard rock

81

cutting the appellant in his letter dates August 24, 1960

addressed to the Executive Engineer, Central Division No.

II, Gangtok, had requested for revision of the rate for hard

rock cutting and stated that the minimum working rates for

this item are 52% above the tendered rates. The ExecUtive

Engineer by his letter dated September 2, 1960, requested

the appellant to submit an analysis of rate for hard rock

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 11

cutting. The appellant submitted his analysis of rates on

September 14, 1960 wherein after analysing the rates of

materials and labour the workable rate worked out to Rs.200

per thousand cft. The Executive Engineer also got an analy-

sis of rates done on the basis of the data collected on

actual observation and he arrived at a figure of Rs.237 per

thousand cft. By his letter dated November 9, 1961 addressed

to the Superintending Engineer, Calcutta Central Circle No.

III, CPWD, Calcutta, the Executive Engineer recommended the

extra rate of Rs.200 per thousand cft. for work in excess of

20% of the stipulated quantity. The Superintending Engineer,

in his letter dated February 23, 1962 addressed to the

Additional Chief Engineer III, Central P.W.D., New Delhi,

made a similar recommendation and the Additional Chief

Engineer made a similar recommendation in his letter dated

July 16, 1962 addressed to the Secretary to the Government

of India, Ministry of Works and Housing. It appears that the

Government did not agree to pay at a rate in excess of the

rate of Rs.129 per thousand cft. plus 2% stipulated under

the agreement. The dispute was, therefore, referred to

arbitration.

The arbitrator in his award has considered this item of

claim as under:

Claim Dispute Award

"The contractor claims The arbitrator The claim of the

that for Item No 3 of is to deter- contractor is

the agreement he should mine whether partly justified.

be paid at the rate of under the He should be paid

Rs.200 per 1000 cft. terms and con- an amount of

for the quantities ditions of the Rs.52,800 (Rupees

beyond what is stipu- contract, the fifty two thousand

lated in the agreement. claim is jus- and Eight hundred

tified and if only) in addition

so, to what ex to the payment to

tent. be made to him at

relevant agreement

rate for the total

quantity of work

executed by him

under this item."

82

Before the learned single Judge it was submitted on

behalf of the respondent that the award is a speaking award

and from the award it is apparent that the arbitrator has

fixed rates for additional work done by the contractor which

the arbitrator has no jurisdiction to do by reason of clause

12 of the agreement between the parties which provides that

additions to the contract work shall be carried out by the

contractor on the same conditions in all respects on which

he agreed to do the main work and at the same rates as

specified in the tender for the mainwork. The learned single

Judge rejected the said contention and held that the arbi-

trator was determining only the value of the additional work

at the rate of Rs.200 which had been agreed by the

Engineer-in-charge and the Superintending Engineer of the

Circle as contemplated by clause 12 and the scope of the

inquiry before the arbitrator was only the quantity of work

which was additional to the quantities specified in the

agreement. The learned Judges of the Division Bench of the

High Court have disagreed with the said view and have ob-

served that it is clear from the statement of claim as

incorporated in the award, and the affidavit of the contrac-

tor that there was no dispute with regard to the quantity of

work and the only dispute was with regard to the rate and

that the arbitrator had allowed a sum of Rs.52,800 to the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 11

contractor in respect of the total quantity of work executed

by him under item No. 3 in addition to the agreed rate and

that there was no escape from the conclusion that the arbi-

trator had awarded the above 'amount by applying a rate

higher than the agreed rate. The learned Judges of the

Division Bench were of the view that under clause 12 of the

agreement the provision with regard to the fixing of the

rate by the Engineer-incharge and the Superintending Engi-

neer of the Circle comes into play only when the additional

item of work does not form part of the main work and the

rates for such work are not specified in the schedule of

rates. The learned Judges of the Division Bench have held

that since the additional hard rock cutting job done by the

appellant was part of the main work and the agreement pro-

vided the rate for the said item, there was no occasion for

the Engineer-in-charge or the Suprer intending Engineer to

fix the rate for the extra quantity of hard rock cutting and

that the action of the arbitrator in allowing the rate to

the contractor in excess of the agreed rate for the job of

hard rock cutting was against clause 12 of the agreement and

thereby the arbitrator had exceeded his jurisdiction.

As regards the award of an arbitrator under the Act. the

law is well settled that the arbitrator's adjudication is

generally considered binding between the parties for he is a

tribunal selected by the parties and the power of the court

to set aside the award is restricted to cases

83

set out in section 30 of the Act, viz. (a) if the arbitrator

has misconducted himself or the proceedings; or (b) when the

award has been made after the issue of an order by the Court

superseding the arbitration or after arbitration proceedings

have become invalid under Section 35; or (c) when the award

has been improperly procured or is otherwise invalid. Under

clause (c) of Section 30 the Court can set aside an award

which suffers from an error on the face of the award. It is.

however. not open to the Court to speculate, where no rea-

sons are given by the arbitrator. as to what impelled the

arbitrator to arrive at his conclusion. But the jurisdiction

of the arbitrator is limited by the reference and if the

arbitrator has assumed jurisdiction not possessed by him,

the award to the extent to which it is beyond the arbitra-

tor's jurisdiction would be invalid and liable to be set

aside (See: Jivarajbhai Ujarnshi Sheth and Others v. Chin-

tatnanrao Balaji and Others, [1964] 5 SCR 480). This posi-

tion at law has been reiterated by the Constitution Bench of

this Court in its recent decision in Raipur Development

Authority and Others v. M/s Chokharnal Contractors and

Others, [1989] 2 S.C.C. 721. It has been held that an arbi-

trator or umpire is under no obligation to give reasons in

support of the decision reached by him unless under the

arbitration agreement or the deed of submission he is re-

quired to give such reasons and if the arbitrator or umpire

chooses to give reasons in support of his decision it is

open to the Court to set aside the award if it finds that an

error of law has been committed by the arbitrator or umpire

on the face of the record on going through such reasons and

that an award can neither be remitted nor set aside merely

on the ground that it does not contain reasons in support of

the conclusion or decisions reached in it except where the

arbitration agreement or the deed of submission requires him

to give reasons.

In the instant case the arbitration agreement or the

deed of submissions did not require the arbitrator to give

reasons and, therefore, the award cannot be questioned on

the ground of an error on the face of the award. The learned

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 11

Judges of the Division Bench of the High Court have set

aside the award in relation to claim No. 1 relating payment

for additional work of hard rock cutting on the ground that

in making the award the arbitrator exceeded his jurisdiction

by allowing a rate to the contractor in excess of the agreed

rate for the job of hard rock cutting against the terms and

conditions contained in clause 12 of the agreement.

The question which needs to be considered here is as to

whether in awarding the sum of Rs.52,800 to the appellant

for the additional

84

work of hard rock cutting executed by him the arbitrator has

disregarded clause 12 of the agreement. The said clause

reads as under:

"The Engineer-in-charge shall have power to make any altera-

tions in, commissions from, additions to or substituting

for, the original specifications, drawings, designs and

instructions, that may appear to him to be necessary or

advisable during the progress of the work, and the contrac-

tor shall be bound to carry out the work in accordance with

any instructions which may be given to him in writing signed

by the Engineer-in-charge, and such alterations, omissions,

additions or substitutions shall not invalidate the con-

tract: and any altered, additional or substituted work which

the contractor may be directed to do in the manner above

specified as part of the work shall be carried out by the

contractor on the same conditions in all respects on which

he agreed to do the main work and at the same rates as are

specified in the tender for the main work. The time for the

completion of the work shall be extended in the proportion

that the additional or substituted work bears to the Origi-

nal work, and the certificate of the Engineer-in-charge

shall be conclusive as to such proportion. And if the al-

tered, additional or substituted work included any class of

work for which no rate is specified in this contract, then

such class of work shall be carried out at the rates entered

in the schedule of rates of the C.P.W.D. Schedule of Rates

53-54 on which the estimated cost shown on page 1 of tender

is based provided that when the tender for the original work

is a percentage above the schedule rates the altered, addi-

tional or substituted work required as aforesaid shall be

chargeable at the said schedule rate plus the same percent-

age deduction addition and if such class of work is not

entered in the said schedule of rates, then the contractor

shall within seven days of the date of the receipt of the

order to carry out the work inform the Engineer-incharge of

the rat. e which it is his intention to charge for such

class of work, and if the Engineer-in-charge does not agree

to this rate he shall by notice in writing be' at liberty to

cancel his order to carry out such class of work and arrange

to carry it out in such manner as he may consider advisable

provided always that if the contractor "shall commence work

or incur any expenditure in regard thereto before the rates

shall have been determined as lastly hereinbefore

85

mentioned, then and in such case he shall only be entitled

to be paid in respect of the work carried out or expenditure

incurred by him prior to the date of the determination of

the rate as aforesaid according to such rate or rates as

shall be fixed by the Engineer-in-charge. In the event of a

dispute the decision of the Superintending Engineer of the

Circle shall be final."

Under this clause the Engineer-in-charge was empowered

to make any additions to the original specifications that

may appear to him to be necessary or advisable during the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 11

progress of the work and the contractor was bound to carry

out the work in accordance with any instructions given to

him in writing signed by the Engineer-in-charge. As regards

payment for the additional work which the contractor was

directed to do it was provided that:

(i) The contractor shall be paid at the same rates as are

specified in the tender for the main work;

(ii) If the additional work included any class of work for

which no rate was specified in the contract then the con-

tractor shall be paid at the rates entered into the schedule

of rates of the C.P.W.D. Schedule of Rates 53-54 on which

the estimated cost shown on page 1 of tender is based and if

the tender for the original work is a percentage above the

schedule rates the additional work shall be chargeable at

the said schedule rates plus the same percentage

deductions/addition; and

(iii) If such class of work is not entered in the said

Schedule of Rates then the contractor should inform the

Engineer-in-charge within seven days of the receipt of the

order the rate he wants to charge for such class of work and

the Engineer-in-charge, if he does not agree to the said

rate, may cancel the order for such additional work and if

the contractor has commenced the work or incurred expendi-

ture in regard thereto before the determination of the rates

the contractor shall be paid in respect of work carried out

or expenditure incurred by him prior to the determination of

the rates according to such rates or rates as shall be fixed

by the Engineer-in-charge and in the event of a dispute the

decision of the Superintending Engineer of the Circle would

be final.

The case of the appellant is that clause 12 envisages alter-

ations or

86

additions within reasonable limits and an addition to the

extent of 140% in respect of one particular item alone is

not covered by this clause and that in awarding Rs.52,800 as

extra payment for the additional work the arbitrator has not

acted in disregard of clause 12 and he cannot be said to

have exceeded his jurisdiction.

A clause making provision for additions and variations

is generally found in building and construction contracts.

In Hudson's Building and Engineering Contracts 8th Edn. it

has been observed:

"It may be that it can be inferred from the terms of the

contract that the power to order extras, although apparently

unlimited, is in fact limited to ordering extras up to a

certain value and, in such a case, extras ordered in excess

of that amount, although work of a kind contemplated by the

contract, may yet be quite outside the terms of the con-

tract." (p. 294)

"If the extra work ordered is outside the contract the terms

of the contract have no application." (p. 296)

In this context it would be relevant to take note of the

decision of the Court of Appeal in England in Parkinson (Sir

Lindsay) & Co. Ltd. v. Commissioners of His Majesty's Works

and Public Buildings, [1949] 2 K.B. 632. In that case the

contractors had agreed with His Majesty's Commissioners of

Works and Public Buildings to erect an ordnance factory

according to the general conditions and specifications and

bills of quantities and drawings annexed for the contract

sum of Pound 3,500,000 and under the general conditions of

contract the Commissioners had power, at their absolute

discretion, to modify the extent and character of the work

or to order alterations of or additions to the works and it

was the duty of the contractor to comply with the archi-

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 11

tect's instructions in this respect. In the contract it was

also provided that it is probable that further work to the

value of approximately, Pound 500,000 would be ordered on a

measured basis under the terms of the contract. The contract

was amended by a deed of variation and it was provided that

exceptional methods should be used to hasten the work and

that a system of uneconomic working should be introduced to

bring about the completion of the factory by the date fixed

by the contract. The Commissioners ordered work to be exe-

cuted greatly in excess of the amount contemplated although

not different in character from that covered by the varied

contract, so that the works could not be completed until a

year beyond the time anticipated and the actual cost of the

87

contracts was L6,683,056 which amount had been paid to them

-

alongwith L300,000 the maximum profit under the deed of

-

variation. During the progress of the work the contractors

had. complained to the Commissioners that they were being

called on to execute more work than was contemplated by the

varied contract and claimed that they were entitled to extra

remuneration for the work in excess of that contemplated but

they proceeded with the work at the request of the Commis-

sioners leaving the issue to be subsequently decided by

arbitration. The arbitrator found that the estimated cost of

the work under the varied contract was L500,000 and awarded

-

L90,298 as proportionate or reasonable profit or remunera-

-

tion to the contractors for the additional work. The said

award was upheld by the Court of Appeal on the view that a

term must be implied in the varied contract that the Commis-

sioners should not be entitled to require work materially in

excess of the sum of L5,000,000 and that such excess work

-

having been done by the contractors, the Commissioners were

liable to pay the contractors reasonable remuneration there-

fore. On behalf of the Commissioners reliance was placed on

Condition 33 of the original contract which gave the Commis-

sioners an unlimited power of ordering extras even to the

extent of altering the character of the work. The contrac-

tors, on the other hand, placed reliance on the following

observations of Mc Cardie, J. in Naylor, Benzon & Co. v.

Krainische Industrie Gesellschart, [1918] 1 K.B.331:

"It is essential to remember, however, that words, even

though general, must be limited to circumstances within the

contemplation of the parties."

Accepting the contention urged on behalf of the contrac-

tors Asquith L. J. observed:

"If the original contract plus the deed are read without any

implied limitation on their literal meaning, the result, as

indicated above, is that after L300,000 profit has been

-

earned by the contractor, he can be compelled to labour like

the Danaids without reward or limit, or any further "extras"

which the commissioners may elect to exact from him, 'till

the last syllable of recorded time.' Only the most compel-

ling language would induce a court to construe the combined

instruments as placing one party so completely at the mercy

of the other. Where the language of the contract is capable

of a literal and a more restricted meaning, all relevant

circumstances can be taken into account in decid-

88

ing whether the literal or a more limited meaning should be

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 11

ascribed to it". (p. 662)

Similarly Singleton L.J. has observed:

"1 find myself unable to agree with the submission of Mr.

Rewcastle that under the contract as varied by the deed of

variation, the contractors would have been bound to continue

making alterations and additions, if ordered, for years and

years, without any extra payment by way of profit. That

would have led to manifest absurdity and injustice, as

Mathew, J. said in Bush v. Whitehaven Trustees, (1). There

must be a limit." (p. 673)

Here also the question has often arisen whether the

contractor under the variation clause is liable to execute

the extra or additional quantities of the tendered items at

the tendered rates to an unlimited extent. In some awards

given by the arbitrators in the Central Public Works Depart-

ment of the Government of India the variation of the ten-

dered quantities under the variation clause in the contract

has been restricted to 10% beyond which the contractor was

entitled to claim as extras and these awards have been

accepted and implemented by the Government. It appears that

the standard form of contract of the Central Public Works

Department has been amended and now it specifically permits

for a limit of variation called "deviation limit" upto a

maximum of 20% and upto such limit the contractor has to

carry out the work at the rates stipulated in the contract

and for the work in excess of that limit at the rates to be

determined in accordance with clause 12-A under which the

Engineer-in-charge can revise the rates having regard to the

prevailing market rates (See: Gajaria's Law relating to

Building and Engineering Contracts in India, 3rd Edn., pages

410-412).

In the instant case, it appears that the Executive

Engineer, the Superintending Engineer and the Additional

Chief Engineer in their letters dated November 9, 1961,

February 23, 1962 and July 16, 1962 respectively have ex-

pressed the view that the additional work under the terms of

the contract may be confined to 20% and the appellant may be

paid at the rates prescribed in the contract for 20% of the

additional work and for the extra quantity of additional

work he may be paid remuneration at the increased rate

taking into account the increased costs in execution of the

said work on account of the peculiar nature of the work.

While considering the claim of the appellant the

89

arbitrator was required to consider the terms of the con-

tract and to construe the same. It was, therefore, permissi-

ble for the arbitrator to consider whether clause 12 of the

contract enables the Engineer-incharge to require the appel-

lant to execute additional work without any limit or a

reasonable limit should be placed on the quantity of the

additional work, which the appellant may be required to

execute at the rate stipulated for the main work under the

contract. For that purpose the arbitrator could take into

consideration the practice prevalent in the Central Public

Works Department in this regard as well as the correspond-

ence between the appellant and the authorities including the

letters dated November 9, 1961, February 23, 1962 and July

16, 1962 of the Executive Engineer, the Superintending

Engineer and the Additional Chief Engineer recommending

payment of remuneration at the increased rate for the addi-

tional work in excess of 20% of the quantity stipulated in

the contract. The appellant was claiming increased rate of

Rs.200 per 1000 cft. for the entire quantity of additional

work. The arbitrator did not accept the said claim of the

appellant in full and has partly allowed the said claim by

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 11

awarding Rs.52,800 which means that the arbitrator has

awarded the increased rate only for a part of the additional

work of hard rock cutting which the appellant was required

to execute. The arbitrator was entitled to do so on the

construction placed by him on clause 12 of the contract and,

therefore, it cannot be said that in awarding the sum of

Rs.52,800 for the additional work the arbitrator has exceed-

ed his jurisdiction and the award is vitiated by an error of

jurisdiction. In the circumstances, we are unable to agree

with the judgment of the learned Judges of the Division

Bench of the High Court on this part of the claim.

The appeal is, therefore, allowed and the judgment of

the Division Bench of the High Court setting aside the award

of the arbitrator with regard to item No. 1 of the claim

relating to payment for additional work of hard rock cutting

is set aside and the order passed by the learned Single

Judge upholding the award of the arbitrator in this regard

is restored. The appellant will be entitled to his costs.

Civil Appeal No. 323 of 1976

This appeal is directed against the order dated May 23,

1975 of the High Court of Delhi whereby the High Court

rejected C.M. No. 1300 of 1974 filed by the appellant under

Order 41, rule 21 read with Section 151 C.P.C., praying that

the ex-parte judgment dated March 27, 1973 in F.A.O. (O.S.)

No. 35 of 1969 may be set aside and the appeal be re-admit-

ted to its original number and the appeal be heard

90

and decided on merits. The appellant has filed C.A. No. 322

of 1976 against the said judgment of the High Court dated

March 27, 1973 in F.A.O. (O.S.) No. 35 of 1968. The said

appeal has been allowed by the judgment given today. Since

the judgment of the High Court dated March 27, 1973 has been

set aside by this Court in C.A. No. 322 of 1976 this appeal

does not survive and it is disposed of accordingly. No

costs.

G.N. Appeal disposed of.

91

Description

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter