As per case facts, the petitioner sought unpaid compensation with statutory interest for land acquired for the Pirpainti Thermal Power Project. The petitioner's mother's land was acquired, but compensation was ...
No Acts & Articles mentioned in this case
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.15685 of 2022
======================================================
Shekh Kalim, Son of Shekh Bounu, Resident of Village- Kunjbanna, P.S.-
Pirpainti, District- Bhagalpur.
... ... Petitioner/s
Versus
1.The State of Bihar through the Principal Secretary, Department of Revenue
and Land Reforms, Government of Bihar, Patna.
2.The Collector-cum-District Magistrate, Bhagalpur.
3.The Distrtict Land Acquisition Officer, Bhagalpur.
4.The Managing Director, Bihar State Power Generation Company Limited,
Vidyut Bhawan, Bailey Road, Patna.
5.The Chief Engineer (P and T), Bihar State Electricity Board, Patna.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s: Ms. Pravina Kumari, Advocate
For the State : Mr. Sajid Salim, SC-25
: Mr. Atul Shankar, AC to SC-19
For the BSPGCL : Ms. Aishwarya Shankar, Advocate
======================================================
CORAM: HONOURABLE MR. JUSTICE SOURENDRA PANDEY
C.A.V. JUDGMENT
Date : 07-08-2026
Heard Ms. Pravina Kumari, learned counsel for the
petitioner, Ms. Aishwarya Shankar, learned counsel for the
BSPGCL and Mr. Sajid Salim, learned SC-25 for the State.
2. The present writ petition has been filed seeking the
following reliefs:
“That this is an application for issuance of an
appropriate writ(s), order(s), direction(s), directing the
Respondents concern to pay compensation with statutory
interest for 15 decimals of land of Khata No. 228, Plot No.
1959, Thana No. 81, Mouza-Harinkol Anchal-Pirpainti,
District-Bhagalpur in as much as 37 dec. of the said plot
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
2/20
no. 1959 has been acquired for Pirpainti Thermal Power
Project vide L.C. Case No. 26 of 2011-12 but compensation
has been paid only for 0.22 dec. land and compensation for
0.15 dec. land is still unpaid for which the petitioner is
running from pillar to post since last twelve years.
And for any other relief(s) for which the petitioner is
found to be entitled in the facts and circumstances of the
case.”
3. The case of the petitioner is that the land
appertaining to Khata No. 228, Plot No. 1959, Thana No. 81,
Mauza Harinkol, District Bhagalpur having an area 45 decimal
was recorded in the name of mother of the petitioner namely
Bibi Taslima in the revenue record of right and Jamabandi is
existing in her name and rent receipt are being issued. Out of the
total land, 0.37 decimals of land was acquired for Pirpainti
thermal Power Project but L.C. Case No. 26/11-12 was initiated
only for 22 decimals of land and notice was issued in the name
of the mother of petitioner for the same.
4. It has been submitted that Bibi Taslima is no more
and all her legal heirs have authorized the petitioner by swearing
an affidavit to make Pairvi in this matter and receive
compensation, however, notice was served only for 22 dec. land
in place of 37 decimals of land for which the petitioner raised
objections. It has next been submitted that the objection of
petitioner was not considered and they received compensation
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
3/20
for 22 decimals of land only and thus, aggrieved by the action of
Respondent No. 3, representations were filed before him on
various occasions but to no avail after which petitioner
approached the Collector cum District Magistrate, Bhagalpur
vide representation dated 03.05.2019, which was forwarded to
the District Land Acquisition Officer, Bhagalpur.
5. It has further been submitted that Chief Engineer
(Respondent No. 5) was requested to enquire vide letter dated
28.09.2019, whereafter when nothing was done the petitioner
again made representation before Respondent No. 2 which was
forwarded to Land Acquisition Officer, Bhagalpur on
07.03.2020 and on 24.02.2020 the said Land Acquisition Officer
issued letter to Managing Director (Respondent No.4) to make
an enquiry and submit report.
6. It has further been submitted that even at this stage
when compensation was not received as prayed for, the
petitioner filed writ bearing CWJC No. 1542 of 2021 before this
Hon’ble court and vide order dated 23.03.2021, this court
granted liberty to petitioner to approach the Land Acquisition
Officer, however even then nothing was done. It is next
submitted that upon submission of application before the said
Land Acquisition Officer for payment of compensation for
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
4/20
remaining 0.15 decimals of land, which was found to be correct,
still no payment was made. It is furthermore submitted that the
Land Acquisition Officer was asked by Bihar State Power
Generation Company vide letter dated 18.08.2021 for payment
of compensation with respect to 0.15 decimals of land, however,
Land Acquisition Officer has not made any payment while due
amount is admitted after which again several representations
were made by petitioner. It has also been submitted that
petitioner is entitled to get interest on the total amount of
compensation of 0.15 decimals of land from the date of
notification dated 23.06.2011. It is evident from the records that
due to fault of Respondent Authorities, compensation has only
been paid for 0.22 decimals of land against the acquisition of
0.37 acres.
7. It has lastly been submitted that through letter
dated 28.09.2019 and 24.01.2020 the District Land Acquisition
Officer has enquired into the claim of petitioner and concluded
that 0.37 decimals of land has been acquired and there is
physical possession with concerned department over which they
have constructed boundary wall and thus, compensation for
remaining 0.15 decimals has to be paid to the petitioner.
Submissions on behalf of Respondents 4 and 5
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
5/20
8. It is submitted on behalf of Respondent Nos. 4 and
5 through Counter Affidavit that total land of 1179.08 acres
under Mauza Raipura, Sundarpur and Harinkol-I and Harinkol-
II were to be acquired for Pairpanti Thermal Power Project,
Bhagalpur which is carried out by Industrial Development
Authority (IDA), Government of Bihar under which 988.40
acres was acquired by then. It is next submitted that amount for
compensation has been transferred by the said IDA but
distribution of compensation to concerned landowners had to be
dealt by Officer of District Land Acquisition, Bhagalpur, who
vide letter No. 53 dated 24.01.2020 has accepted requisition for
0.43 acres of land for the said project as claimed by petitioner
had been received by their office from Bihar State Power
Generation Company Ltd. and also accepted that due to
measurement mistake, only 0.22 acres of land has been assessed
in place of 0.43 acre of land.
9. It is submitted that, after enquiry, it was found that
only 0.37 acres of land owned by the petitioner falls under the
project. It is also submitted that land acquisition was not done
by Bihar State Power Generation Company Limited but is made
a party respondent. It is lastly submitted that an officer of this
company vide letter No. 02/LAO dated 18.08.2021 also
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
6/20
requested District Land Acquisition Officer, Bhagalpur (DLAO)
to verify claim of petitioner from register II of their office and to
compensate petitioner as per new Acquisition Act, if it is found
that acquired land is more than which is on record.
10. Through supplementary Counter Affidavit of
answering respondents, it has been brought to notice that vide
letter No. 06/LAO cell dated 27.06.2023 the DLAO, Bhagalpur
was reminded to address the grievance of petitioner and pay the
due compensation claimed for remaining 0.15 decimals of land
and vide letter no. 04/LAO addressed to DLAO, Bhagalpur, it
was requested for payment of remaining amount. It is submitted
that answering respondents in another letter dated 25.04.2025
categorically stated that IDA transferred Rs.1021 crores to
DLAO, Bhagalpur for paying compensation to beneficiaries
after which the remaining Rs.150 crores were returned to State
Consolidated Fund due to which 100 percent compensation was
not paid to some of the raiyats including the petitioner. It is also
submitted that District Magistrate, Bhagalpur, requested IDA to
provide Rs. 150 crores for compensation and the present
respondents requested DLAO, Bhagalpur, to compensate the
petitioner for his claim. It is further stated that Bihar
Government Energy Department vide letter dated 28.04.2025
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
7/20
requested the Additional Chief Secretary, Industries Department
for providing Rs.150 crores, which was returned to State.
Submissions on behalf of Respondent Nos. 2 and 3
11. It is submitted that after receiving petitioner’s
application and vide letters issued to DLAO, Bhagalpur, it took
note of the same and got the missing plot measuring 0.15 acre
measured by the Amin and that report has been sent to LAO,
BSPGCL, Patna for further necessary action vide letter No. 885
dated 19.06.2024. Another Counter Affidavit was filed by these
respondents wherein it has been submitted that through oral
order of Hon’ble High Court dated 04.07.2025, Rs.20,54,709/-
has been directed to be paid to the petitioner. It is stated that the
total available amount in the report submitted by IDA is
Rs.13,88,74,132 which is automatically deducted as a result of
completion of five consecutive financial years under CFMS
maintenance system. It is next submitted that for payment of
amount that stands due to concerned raiyats to be paid out of Rs.
150 crores, letters have been issued to IDA and in fact, the GM
(human resources/administration) BSPGC has also addressed
DLAO, Bhagalpur to compensate the petitioner as per rules.
Pursuant to order dated 07.04.2025 passed by this court asking
the reason, as to why petitioner has not been paid his due
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
8/20
amount and who is responsible for that, the answering
Respondents through Supplementary Affidavit submit that a
request has been made from LAO, Bhagalpur to BSPGC Ltd.
regarding payment of compensation.
12. It has been submitted that Letter No. 1458 dated
27.08.2025 was given to Branch Manager, Tikamanjhi,
Bhagalpur, for making payment of Rs. 20,14,200/-. It is
submitted that the award under section 23 and 30 of
RFCTLARR Act 2013 amounts to Rs. 20,54,709/- which was
calculated from Sl. No.20 as Earned Investment whereas Cess,
Establishment Expenditure and Contingency Expenditure is Rs.
40,509/-. Thus, excluding this amount (i.e., 20,54,709- 40,509)
the payable amount stands at Rs. 20,14,200/-, which has been
paid to the petitioner.
13. At this juncture, 4
th
Supplementary Counter
Affidavit was filed on behalf of Respondent Nos. 2 and 3
pursuant to order dated 16.04.2026 of this court. It is submitted
that total compensation amount after calculations (Format-VII)
stood at Rs. 16,03,800/- and calculation of interest as per
stipulations of section 80 of the Act, 2013 stands at Rs.
4,10,400/- (Annexure-R/B to this Supplementary C.A.). It is,
thus, submitted that compensation amount of Rs. 20,14,200/- as
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
9/20
assessed also includes interest amount and the same has been
paid to petitioner.
14. Through the 5th supplementary counter affidavit
filed on behalf of Respondent No. 3 a consolidated reply has
been filed. It is submitted that the petitioner received Rs.
20,14,200/- on 27.08.2025 however, the calculated amount is
Rs. 14,62,284/- according to rules. It is next submitted that
taking into account the Market value as per section 26 of
RFCTLARR Act, compensation amount is Rs.14,62,284/- and
interest amount as per Section 80 of the Act is Rs. 4,26,914/-. It
is next submitted that the total payable amount to the petitioner
is Rs. 18,89,198/- (Annexure-R/B to this Supplementary C.A.).
It is further submitted that calculation of all acquired lands of
Pirpainti Thermal Power project including other state projects
have been done accordingly. It is further submitted that the total
interest under Section 80 of the Act has been wrongly calculated
by the petitioner on total amount, however, according to Section
26 of the Act, the interest is to be calculated based on market
value of land which is Rs. 2,85,000/-. Hence, it is submitted that
compensation of Rs. 20,14,200/- is already paid to the petitioner
as against the calculated amount of Rs.18,89,198/-.
Submissions in Rejoinder filed on behalf of the
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
10/20
petitioner
15. The petitioner through rejoinder has filed a reply
to counter affidavit by Respondent Nos. 3 and 4 stating that
petitioner received Rs. 20,14,200/- on 27.08.2025 against
calculated amount of Rs. 20,54,709/- whereas Rs. 40,509/- has
wrongly been deduced. It is submitted that after proper
calculation of interest as under Section 80 of the Act, it would
entail the total interest amount to be Rs. 2878343/-.
16. Furthermore, the petitioner contended that after
calculations, total principal amount stood at Rs. 19,09,482/- and
interest calculated as per Section 80 of the Act, 2013 will come
to Rs. 2878343/-, making the total payable amount to Rs.
47,87,825/-. It is next submitted that petitioner is further entitled
to Rs. 27,33,116/- [Total amount Rs. 47,87,825/- - Paid amount
Rs. 20,54,709/-]. It is also submitted that compensation amount
is not considered as interest and this is additional compensation
considered as a fine or damages penalty or loss under the law
for delay which compensates for delay in payment of principal
amount. It is lastly submitted that extra 12% p.a. on market
value of land for the period of publication of notification to the
date of announcement of award must be given.
17. The learned counsel for the petitioner submits
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
11/20
that now the only dispute which remains to be adjudicated is the
quantum of the total compensation which is to be paid to the
petitioner i.e. Principal plus statutory interest.
18. The learned S.C.-25 submits that the calculation
filed by the petitioner through supplementary affidavit is not
correct, especially the Principal amount of Rs. 19,09,482/-. It
has been submitted that Principal amount of compensation over
which interest both under Section 30(3) of the Act, 2013 as well
as Section 80 of the Act, 2013 has to be paid are different as
interest @ 12% as contemplated under Section 30(3) of the Act,
2013 is to be paid on market value plus assets without adding
any solatium.
19. At this juncture, it would be apt to record the
calculations of the petitioner as well as the State to verify and
assess their respective claims.
20. The Principal amount, as per the petitioner has
been calculated as under:-
(a) Cost of 1 Acre land-Rs. 19,00,000.00
(b) Cost of 1 Decimal land- Rs. 19,000.00
(c) Cost of 15 Decimals land- Rs. 19,000 X 15=
Rs. 2,85,000.00
(d) Factor-2 rate of 15 Decimals land – Rs.
2,85,000 X 2= Rs. 5,70,000.00
(e) Assets – Rs. 1,00,800.00
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
12/20
(f) Total cost of land & Assets – Rs. 5,70,000 +
Rs. 1,00,800 = Rs. 6,70,800.00
2. 100% Solatium = Rs. 670800.00
Factor - 2 applied -
Rs.
13,41,600.00 (i)
3. Amount of compensation from the publication of
notification from 27.09.2011 to date of
announcement of Award 07.04.2015 (3 years 6
months 10 days).
For 1 year- Rs. 1341600 X = Rs. 1,60,992.00.
So 3½ years 1,60,992 X 3.5 = 5,63,472.00
10 days X 10=4410/-
Total amount of compensation 563472 + 4410=
Rs. 5,67,882.00 (ii)
Total principal amount (i)+(ii)
13,41,600+5,67,882 = Rs. 19,09,482
21. The Principal amount, as per the District Land
Acquisition Officer has been calculated as under:-
(a) Cost of 1 Acre land-Rs. 19,00,000.00
(b) Cost of 1 Decimal land- Rs. 19,000.00
(c) Cost of 15 Decimals land- Rs. 19,000 X 15=
Rs. 2,85,000.00
(d) Factor-2 rate of 15 Decimals land – Rs.
2,85,000 X 2= 5,70,000.00
(e) Assets – Rs. 1,00,800.00
(f) Total cost of land & Assets – Rs. 5,70,000 +
1,00,800 = Rs. 6,70,800.00
3. Amount of compensation from the
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
13/20
publication of notification from 27.09.2011 to date
of announcement of Award 07.04.2015 (3 years 6
months 10 days i.e. 1288 days – 2,85,000 X 1288 X
12/36500 = Rs.1,20,684.00
Hence Total amount Rs. 6,70,800 +
Rs.6,70,800 + Rs.1,20,684.00 = Rs.14,62,284.00
22. Having heard the learned counsels for the parties
and also their respective claims and counter claims, this Court
finds that in the calculation furnished by the petitioner, 12%
interest as per Section 30(3) of the Act, 2013 has been added on
Rs. 13,41,600/- i.e. along with solatium amount. This to the
understanding of the Court is against the statutory provision as
contained in Sections 26 to 30 of the Act, 2013.
23. Section 27 and 29 of the Act, 2013 are being
reproduced hereunder for better understanding -
“27. Determination of amount of
compensation -
The Collector having determined the
market value of the land to be acquired shall
calculate the total amount of compensation
to be paid to the land owner (whose land has
been acquired) by including all assets
attached to the land.
28…...
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
14/20
29. Determination of value of things
attached to land or building -
(1). The Collector in determining the
market value of the building and other
immovable property or assets attached to the
land or building which are to be acquire, use
the services of a competent engineer or any
other specialist in the relevant field, as may
be considered necessary by him.
(2). The Collector for the purpose of
determining the value of trees and plants
attached to the land acquired, use the
services of experienced persons in the field
of agriculture, forestry, horticulture,
sericulture, or any other field, as may be
considered necessary by him.
(3). The Collector for the purpose of
assessing the value of the standing crops
damaged during the process of land
acquisition, may use the services of
experienced persons in the field of
agriculture as may be considered necessary
by him.”
24. From the bare perusal of the aforesaid provisions,
it is crystal clear that the determination of market value of the
land to be acquired shall be done including all assets attached to
the land. Section 29 of the Act, 2013 contemplates
determination of value of things attached to the land or building.
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
15/20
Thus, it is clear that the total compensation to be paid includes
both the market value of land as well as the value of assets. It is
only on this amount that the solatium is determined as contained
in Section 30(1) of the Act, 2013. In such a view of the matter,
the calculations done by both the petitioner and the State are not
correct. The petitioner has included the solatium amount for
interest as contemplated in Section 30(3) of the Act, 2013.
While the State has taken only the market value of the land in
doing so.
25. The statute is very clear on this point and as per
the provisions, the interest under Section 30(3) of the Act, 2013
has to be calculated as under :-
(a) Cost of 1 Acre land-Rs. 19,00,000.00
(b) Cost of 1 Decimal land- Rs. 19,000.00
(c) Cost of 15 Decimals land- Rs. 19,000 X 15=
Rs. 2,85,000.00
(d) Factor -2 rate of 15 Decimals land – Rs.
2,85,000 X 2= Rs. 5,70,000.00
(e) Assets – Rs. 1,00,800.00
(f) Total cost of land & Assets – Rs. 5,70,000 +
1,00,800 = 6,70,800.00
Amount of interest from the publication of
notification from 27.09.2011 to date of
announcement of Award 07.04.2015 (3 years 6
months 10 days).
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
16/20
For 1 year- Rs. 6,70,800 X =
Rs.80,496/-
So for 3½ years - Rs. 80,496 X 3 years and 6
months= Rs.2,81,736/-
10 days- Rs. X 10= Rs.2205/-
Total amount of interest under Section 30 (3)
of the Act, 2013 = Rs.2,83,941/-
26. Once the interest on the Principal amount of
compensation is decided, then only the solatium is added to the
Principal amount (Market value of land+value of assets) only.
Thus, the total compensation payable to the petitioner stands as:
Rs.6,70,800/- + Rs.6,70,800/- + Rs.2,83,941/- = Rs.16,25,541/-
27. The calculation of interest as per Section 80 of
the Act, 2013 as done by the petitioner was also being disputed
by the state on the ground that the interest shall be payable only
on the initial amount of the Market value of the land i.e. Rs.
2,85,000/-. The State, through its 5
th
supplementary counter
affidavit has given details of the calculation of interest under
Section 80 of the Act, 2013 in paragraph-10 and has stated the
total interest to be Rs. 4,26,914/-.
28. The aforesaid calculation too is completely
against the statutory provision, as Section 80 provides that the
interest is to be paid on the amount of compensation which was
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
17/20
not paid or deposited on or before taking possession of the land.
29. Section 80 of the Act, 2013 is reproduced for
reference:-
“80. Payment of Interest
When the amount of such
compensation is not paid or deposited on or
before taking possession of the land, the
Collector shall pay the amount awarded with
interest thereon at the rate of nine per cent,
per annum from the time of so taking
possession until it shall have been so paid or
deposited:
Provided that if such
compensation or any part thereof is not paid
or deposited within a period of one year
from the date on which possession is taken,
interest at the rate of fifteen per cent per
annum shall be payable from the date or
expiry of the said period of one year on the
amount of compensation or part thereof
which has not been paid or deposited before
the date of such expiry.”
30. Thus, from the above it is evident that the amount
which was to be paid to the petitioner at the time of possession
was the total amount upon which the interest had to be paid
under Section 80 of the Act, 2013, then the calculation has to be
done on the total compensation and not as per market value of
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
18/20
the land only.
31. In view of such finding, the petitioner is liable to
be paid the following amount –
(i) Compensation + Solatium = Rs.13,41,600/-
(Rs.6,70,800/- + Rs.6,70,800/-)
(ii) Interest under Section 30(3) of the Act
= Rs.2,83,941/-
(iii) Interest under Section 80 of the Act on total
amount payable to the petitioner, i.e., Rs.16,25,541/-
(Rs.6,70,800/- + Rs.6,70,800/- + Rs.2,83,941/- =
Rs.16,25,541/-)
(a) For 1
st
year @ 9 % from 07.04.2015 to
06.04.2016 = Rs.16,25,541 X = Rs.1,46,299/-
(b) For the period starting from 07.04.2016 to
07.04.2025 @ 15 % = Rs.16,25,541 X X 9 =
Rs.21,94,480/-
(c) For the period starting from 07.04.2025 to
25.08.2025 (141 days) =
Rs.16,25,541x = Rs. = Rs.668/- per day
Thus, for 141 days (Rs. 668 x 141) = Rs.94,188/-
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
19/20
Total, i.e.,(a+b+c) = Rs.1,46,299/- + Rs.21,94,480/-
+ Rs.94,188/- = Rs.24,34,967/-
Grand total payable to the petitioner thus stands as
sum of the above i.e. (i+ii+iii) = Rs.13,41,600/- +
Rs.2,83,941/- + Rs.24,34,967/- = Rs.40,60,508/-
32. The admitted amount already paid to the
petitioner is to the tune of Rs. 20,54,709/- therefore the amount
which the State has to pay the petitioner now is Rs. 20,05,799/-
(Rs. 40,60,508 - Rs. 20,54,709)
33. The District Land Acquisition Officer, Bhagalpur,
is directed to pay the aforesaid amount to the tune of
Rs.20,05,799/- (Twenty Lakhs Five Thousand Seven Hundred
Ninety Nine) within a period of two months from the date of
this order.
34. The learned S.C. 25 shall communicate the order
forthwith for compliance by the District Land Acquisition
Officer, Bhagalpur.
35. It is made clear that if the aforesaid amount,
which has been directed to be paid to the petitioner, if not paid
within two months from the date of this judgment, then the State
shall be liable to pay 12% penal interest on the payable amount
from 07.04.2015 till the date of payment.
Patna High Court CWJC No.15685 of 2022 dt.07-08-2026
20/20
36. The learned S.C. 25 shall communicate the order
forthwith for compliance by the District Land Acquisition
Officer, Bhagalpur.
37. The writ application stands allowed with the
directions aforesaid.
tannu/manoj-
(Sourendra Pandey, J)
AFR/NAFR NAFR
CAV DATE 09.07.2026
Uploading Date 07.08.2026
Transmission Date NA
In a significant ruling, the Patna High Court has meticulously clarified the calculation of Land Acquisition Compensation and statutory interest under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act, 2013). This case, Shekh Kalim v. The State of Bihar (CWJC No. 15685 of 2022), now stands as a pivotal reference point on CaseOn, offering detailed insights into the complexities of land acquisition disputes.
The petitioner, Shekh Kalim, sought proper compensation and statutory interest for 0.15 decimals of land acquired for the Pirpainti Thermal Power Project in Bhagalpur. While 0.37 decimals of land belonging to his deceased mother, Bibi Taslima, were acquired, compensation was only paid for 0.22 decimals. Despite repeated representations and a previous writ petition, the remaining compensation remained unpaid, leading to the present legal challenge.
The central issue before the Patna High Court was to determine the correct principal amount and statutory interest payable to the petitioner for the remaining 0.15 decimals of acquired land, ensuring compliance with the provisions of the RFCTLARR Act, 2013.
The Court's decision primarily hinged on the interpretation and application of several key sections of the RFCTLARR Act, 2013:
The Court carefully examined the petitioner's claim and the counter-affidavits filed by the respondents (Bihar State Power Generation Company Limited - BSPGCL, and District Land Acquisition Officer - DLAO, Bhagalpur).
Both the petitioner and the State submitted their own calculations, which the Court found to be incorrect:
The Patna High Court meticulously re-calculated the compensation based on the correct application of the RFCTLARR Act, 2013:
Interest under Section 80: Calculated on Rs. 16,25,541/- from 07.04.2015:
The grand total compensation payable was thus determined to be Rs. 40,60,508/-. Given that the petitioner had already received Rs. 20,54,709/-, the outstanding amount payable by the State was Rs. 20,05,799/-.
At this juncture, CaseOn.in's 2-minute audio briefs prove invaluable for legal professionals, offering a concise yet comprehensive analysis of these specific rulings, allowing for quick comprehension of complex calculations and legal reasoning without sifting through lengthy documents.
The Patna High Court allowed the writ application, directing the District Land Acquisition Officer, Bhagalpur, to pay the remaining amount of Rs. 20,05,799/- to the petitioner within two months from the date of the judgment. The Court further stipulated that if the payment is not made within this period, the State shall be liable to pay 12% penal interest on the payable amount, calculated from 07.04.2015 until the actual date of payment.
This judgment is crucial for legal professionals and students specializing in property law and land acquisition due to several key reasons:
Disclaimer: All information provided in this article is for informational purposes only and does not constitute legal advice. Readers are encouraged to consult with a qualified legal professional for advice pertaining to their specific circumstances.
Legal Notes
Add a Note....