As per case facts, Burdwan Development Authority (BDA) acquired land for a Satellite Township project, for which Bengal Shrachi (the petitioner's predecessor) deposited acquisition costs. Landowners challenged the compensation, leading ...
No Acts & Articles mentioned in this case
Page 1 of 47
IN THE HIGH COURT AT CALCUTTA
CIVIL REVISIONAL JURISDICTION
APPELLATE SIDE
Present:-
HON’BLE JUSTICE CHAITALI CHATTERJEE DAS.
CO 2890 OF 2025
WITH
SHRACHI BURDWAN DEVELOPERS PVT.LTD.
VS
ABDUL ALIM & ORS.
WITH
CO 2892 OF 2025
WITH
CO 3194 OF 2025
For the Petitioner : Mr. Arindam Banerjee, Sr. Adv.
Mr. Swarajit Dey, Adv.,
Mr. Amit Kr. Nag, Adv.
Mr. Partha Banerjee, Adv.
Ms. Rishita Sarkar, Adv.
For the Opposite
Party no. 1 : Mr. Gopal Chandra Ghosh, Sr. Adv.
Mr. Partha Pratim Roy, Adv.
Mr. Rajkumar Gupta, Adv.
Mr. Chandan Mondal, Adv.
Ms. Poulami Chakraborty, Adv.
For the Opposite
Party No. 5 : Mr. Sarosij Dasgupta, Adv.
Mr. Saptarshi Datta, Adv.
Ms. Srinjita Ghosh, Adv.
Mr. Pourush Kanti Pal, Adv.
Mr. Debdut Hore, Adv.
Mr. P.K. Pal, Adv.
For the Opposite
Party No. 2 and 3 : Mr. Siddhartha Banerjee, Sr. Adv.
Mr. Dyutiman Banerjee, Adv.
Mr. Debjit Dutta, Adv.
Mr. Ayanava Das, Adv.
Last heard On : 06.03.2026
Judgement On : 11.06.2025
Uploaded On : 11.06.2026
Page 2 of 47
CHAITALI CHATTERJEE DAS, J. : -
1. The three revisional applications are heard analogously since all are
interrelated with each other between the same parties. The present petitioner
filed revisional applications being C.2890 of 2025, challenging the order no.
128 dated 29.7.2025 passed by the learned Executing Court, dismissing the
application filed under Section 47 of CPC being Misc. case no. 60 of 2023, C.O
no. 2892 of 2025, challenging the order No. 129 dated 29.7.2025passed in
Money Execution case no .12 of 2012 and the order no. 132 dated 6.8.2025
passed in Money Execution case no.12 of 2012 of disposal of execution
process.
The case of the petitioner
2. 254 acres of land was requisitioned by letter dated 12.12. 2003 by the
Burdwan Development Authority (henceforth to be described as BDA) for
acquisition of such land from 4 Mouzas throug h the Land Acquisition
Collector, Burdwan and pursuant to such requisition the Government issued
12 separate Notifications under section 4 of Land Acquisition Act, 1894
notifying the purpose of acquisition of land and in the month of May 2005
issued the notifications equivocally declaring that the acquisition was for
setting up of development of a Satellite Township at Burdwan.
3. The said notice was challenged by an Association of land owners being
Paschim Burdwan Krishi Kalyan Samiti, a registered group of land losers by
filing a Writ petition which was dismissed on 23/2/2007. On December, 2005,
and January 2006 notification was issued under section 6 of Land Acquisition
Act.
Page 3 of 47
4. In between on March 8, 2006, a Memorandum of Agreement was entered into
between BDA and Bengal Shrachi and in terms of the relevant terms and
conditions of the said agreement on 25th July, 2006, Bengal Shrachi deposited
Rs.1,91,75,810/- with BDA for paying the cost of acquisition in 4 L.A cases.
BDA duly deposited the said cost as received from its Private Partner, with the
Land Acquisition Collector, Burdwan from time to time. Bengal Shrachi later
on decided to develop the said land through the Special Purpose Vehicle,
Shrachi Burdwan Developers Private limited, one of its subsidiary align with
one investor namely Xander Investment Holding VI Ltd A (Mauritius based
company) incorporated for the purpose of making investments in real estate
sector in India with the knowledge and consent of BDA .
5. Land Acquisition collector duly took over the possession of the land from 2005
to 26th February, 2007 and on 26th February, 2007 BDA handed over
possession of 284.32 acres of land to Bengal Shrachi and on 15th March, 2007
Bengal Shrachi handed over pos session of 248.32 acres of land to the
petitioner in accordance with Development Rights A ssignment Agreement
dated 20th October 2006. The balance 6.420 acres of land were handed over
by BDA on 5th September, 2008. Over this acquisition process 57 reference
cases were initiated under Section 18 of L.A Act and 37 cases travelled up to
this High Court from the order passed by the reference court and such appeals
were pending. The petitioner was informed about the reference case only on
28th July 2010 when they were intimated by BDA. In the said reference cases
under section 18 of L.A. Act filed by the owners of land, the Learned judge
enhanced the amount of compensation after assessing the market price of the
Page 4 of 47
acquired land of Rs. 35,000/- per satak and directed the proforma parties to
pay to the opposite parties compensation at the enhanced rate together with
interest at the rate of 12% per annum and other awarded amount. The
petitioner was never impleaded in the said proceeding and the award was
passed beyond their knowledge.
6. In terms of the Memorandum of agreement executed in between BDA and
Bengal Shrachi on 18.3.2006, Bengal Shrachi entered into development rights
of assignment agreement with Shrachi Burdwan Developers Private Limited on
20.10.2006, during pendency of the writ petition 16280(W) 2005. Meantime in
terms of 24 awards and decree passed in the reference cases, BDA asked
Bengal Shrachi for the payment of enhanced amount. Bengal Shrachi
challenged the same by filing a writ petition, being W.P No. 9778(w) 2012. The
decree involved in the present case was put up into execution being Money
Execution case no. 12 /2012 and on 27.8.2012 an appeal was filed against the
said decree being FAT 522/2012 by BDA on 19.10.12. On 13.6.2016, the said
appeal was dismissed for non-compliance of order. In the Writ petition, so filed
being WP. 9778(w) 2012, the learned Single Judge held that Shrachi Burdwan
is a ‘person interested’ under Section 3 (b) of the Act and the “necessary party’
as well as ‘proper party’ in the reference proceeding and set aside 4 decrees
passed by the reference court. In accordance with such order, the present
petitioner filed an application under Order 1 Rule 10(2) CPC in the reference
case being L.A. case no. 40 of 2010 which was dism issed by the learned
Additional District Judge, 1st Court at Burdwan on 23.8.2017. Challenging the
order of the learned Single Judge, an appeal was filed before the Division
Page 5 of 47
Bench of this court by the land losers of four cases being MAT no. 513 of 2017,
corresponding to FMA 887 of 2019. On 11.9.2019, the Division Bench of this
court allowed the said appeal filed by the land losers and set aside the order
dated 16.2.2017 passed by the learned Single Judge in W.P No. 9778 (W) 2012
with a cost of ₹2,00,000/- to be paid by Shrachi Burdwan. The matter
travelled up to Hon’ble Supreme Court by filing a Special Leave Petition on
31st November 2019.
The present petitioner also filed an application under Section 151 CPC before
the Executing court on 14.11.2017 in the M. Execution case no.5/2016 for
impleadment and such prayer was refused by the Learned Executing Court.
Against the order dated 23.8.2017 passed in Execution case the p resent
petitioner filed C.O no. 3809 of 2017.
7. The learned Single Bench of the High Court allowed all the revisional
applications filed by the State of West Bengal, BDA and Shrachi Burdwan by a
common order dated 26.2.2020 holding that the award passed in all the
Reference proceedings in connection with which respective orders in execution
petition challenged in the petition are null and void in the eyes of law, in view
of non-joinder of necessary party. The SLP was filed against such common
Judgement and order dated 26.2.2020 and it was dismissed and confirmed the
judgement and order of th e Learned Division of the High Court in
FMA887/2019 and set aside the order of Learned Single Bench passed in CO
1232 of 2018 and directed the Executing court to proceed with the execution
process. A contempt petition was filed by the present respondent no.1 against
the collector / DM in L.A case no. 21 of 2010 for non-compliance of the
Page 6 of 47
Executing Court’s order dated 29.8.2018 and 12.9.2018 and the Rule was
issued on 13.5.2025. Shrachi Bardhaman preferred SLP challenging the Rule
issued by the learned contempt court, which was disposed of on 16.5.2025,
directing Shrachi Burdwan to move before High Court without interference to
the order impugned.
8. On 21.5.2025, High Court discharged the Rule issued against the collector in
the contempt proceeding upon deposit of the decretal amount of Rs.₹2, 70, 80,
540/- before the executing court and after seeking unconditional apology by
the contemnor. The state of West Bengal through the Special Land Acquisition
Officer conveyed it’s no objection to the learned Contempt court and also to the
petitioner and decree holder by a letter dated 20.5.2025. In that case the
decree holders were allowed to withdraw the deposited amount. An objection
was then raised by Shrachi Burdwan under S ection 47 of C.P.C being Misc
case no. 60 of 2023 against the executability of the decree in M.Execution case
no. 12 of 2012, impleading only one Awardee namely Abdu l Aleem that is
petitioner no.2. The learned Executing court meantime permitted the decree
holders on 30.7.2025 to withdraw the deposited decretal amount and BDA did
not raise any objection. The decretal amount has been presently handed over
and deposited to bank account of the respective respondents which has been
duly acknowledged.The petitioner challenged the orders passed in the Misc.
case filed under section 47 of the code of civil procedure and also against the
order of dismisiing the application under Section 47 CPC.
Page 7 of 47
9. Under the above factual score, the argument advanced by Mr. Arindam
Banerjee the learned Senior Advocate representing the petitioner in all the
three revisional applications, are as follows;
Submission made on behalf of the petitioners
10. It is submitted that the petitioner herein being a Special Purpose Vehicle
formed under PPP ( public purpose, partnership) to be constructed to be a
representative of BDA, being a party to the proceeding under section 18 of the
land Acquisition Act, 1894, and as such the petitioner is entitled to apply
under section 47 of code of civil procedure for the decree to be declared void
and inexecutable on the ground of non impleadment of Bengal Shr achi
Developers Private Limited being a necessary party and “person interested” in
disbursing compensation under Section 3(b) of the Land Acquisition Act, 1894.
The learned Senior advocate in this regard relied upon the decisions relied on
before the learned Single Judge court in WP9778 (W) of 2012, which are as
follows. Himalayan Tiles and Marble (p) Limited versus Frangis Victor
Coutinho (Dead) by LRs.
1
, paragraph 8 and 14, Neelagangabai versus State
of Karnataka
2
, Neyvely Lignite Corporation Ltd. Versus special Tahsildar
(Land Acquisition.) Neyvely
3
, paragraph 12 to 14, Hindu Kanya Maha
vidyalaya Jind vs municipal committee, Jind
4
, Santosh Kumar versus
Central Warehousing Corporation, AIR 1986 SC 1164, and lastly
Peerappa Hanmantha Harijan (dead) by LRs vs state of Karnataka
5
.
1
(1980) 3 SCC 223
2
(1990) 3 SCC 617
3
(1995)1 SCC 221
4
AIR 1988 SC 2139
5
(2015) 10 SCC 469.
Page 8 of 47
11. The further point raised by the learned Senior advocate that section 47 of the
Code of Civil Procedure, 1908 is not maintainable being void as the petitioner
had not been made a party either before the Collector when the Award under
Section 11 of the land Acquisition Act, 1894 had been made or before the
reference court in the reference under Section 18 of the land Acquisition Act,
1894 initiated at the instance of the land losers. The order of dismissal of the
application by the learned reference Court made under Section 47 of the Code
of Civil Procedure held that the Section 47 would not be maintainable at the
instance of the petitioner who is not a party to the reference proceeding under
section 18 of the Land Acquisition Act, 1894, therefore, the learned reference
court failed to exercise the jurisdiction vested in it under law in not deciding
the merits of the petitioner’s objection to the executability of the decree and
hence liable to interfered with .
12. The alternative submission made by the learned senior advocate in his
written notes of argument that even assuming that no proc eeding under
section 47 of the Code of Civil Procedure, 1908 could have been filed by the
petitioner being not a representative of a party, the same could not result in
the Misc. case being dismissed as ‘not maintainable” on such score alone. It is
strenuously argued that an objection as to the execution of a void decree can
be made by any party at any time of the proceeding, and even by a person not
being a party to the proceeding, in the event, the said decree has some adverse
civil consequence on the third person. Therefore, when the objection raised
regarding executability of a decree on the ground of nullity of the decree it was
the duty of the Executing court to decide such question and mere wrong
Page 9 of 47
captioning of the Misc. Case as a proceeding under Section 47 of the Code of
Civil Procedure, 1908 would not denude the power of the Executing court or
the obligation to decide on such iss ue of maintainability.Therefore, the
Executing court manifestly failed to exercise the jurisdiction vested in it under
the law in refusing to decide the petitioner’s objection only on the ground that
an application under Section 47 of the code of civil procedure, 1908 would not
be maintainable at the instance of the petitioner.
13. The contention of the learned senior advocate regarding the question of the
decree being null and void for non-inclusion of necessary party, it is always
open to challenge the execution case even by that aggrieved party and relied
upon the decision of Anisminic Ltd vs Foreign Compensation Commission
6
where it was held by the majority of the House of Lords as follows;
a) Lack of jurisdiction can happen in many ways.
b) Whenever an authority is tasked with the obligation to decide a question,
the resultant final order passed by the authority may be a nullity, not only in a
case where the authority lacked in jurisdiction to decide such question, but
also in a case where, at the entry level, the authority had the jurisdiction to
decide such question, but during the course of its enquiry/adjudication, lost
jurisdiction in view of, interalia, the enquiry/administration being violative of
the principles of Natural Justice, if a relevant and vital question is not
considered by the said authority, and irrelevant or extraneous material is
considered by the authority and in other instances of like nature. In such a
case, the final outcome of the adjudicatory process, being the final order,
6
(1969) 2 AC 147
Page 10 of 47
would be a nullity, notwithstanding the fact that at the initiation of the
proceeding, the concerned adjudicating Authority had jurisdiction to consider
and deal with the question.
14. It is further contended that the above law relating to the final outcome of an
adjudicatory process being a nullity, even in spite of the fact that adjudicator
concerned had jurisdiction to enter into the process of adjudication, is now
part of the law applicable in India. In this regard relied upon the decision of
Hon’ble Supreme Court in case of Shri M.L Sethi versus RP Kapur
7
, where
the above mentioned passage from Anisminic Limited has been quoted. That
apart in Dhurandar Prasad Singh versus Jai Prakash Univ ersity and
others
8
, it was held that executing court can allow objection under Section 47
of the Code to the executability of the decree if it is found that it is void ab
initio and a nullity . Therefore, if the aforesaid principal applied to the facts of
the present case, it would bring about the consequences that without
impleading the petitioner as a party respondent, the award passed by the
reference court is a nullity and therefore when the process of adjudication
continued and ended without hearing the petitioner, it resulted in a gross
violation of the principle of natural justice in so far the petitioner is concerned
and therefore the final order/ decree is also a nullity.
15. In order to substantiate that how the present petitioner is coming within the
definition of “person interested” it is argued that the compensation payment
would ultimately to be borne by the predecessor of the petitioner, Bengal
Shrachi, the petitioner herein and it’s trite that even a person has to bear the
7
(1972) 2 SCC 427
8
(2001) 6 SCC 534
Page 11 of 47
expenses for acquisition, he would beca me a “person interested” in the
payment of compensation, simply on the age old principal that he who suffers
an adverse Civil consequence whether in an administrative or judicial action,
must be given an opportunity of hearing, leads to the inevitable conclusion
that the exclusion of the petitioner from the array of parties and the
continuous and completion of section 18 proceedings behind the back of the
petitioner without affording the petitioner an opportunity of hearing in the
matter, would amount to gross violation of principles of natural justice.
Therefore, the final order though ultimately passed by the reference court
which initially had jurisdiction to enter into the reference would be a nullity.
Once it is alleged to be a nullity the person raising such allegation has the
right to approach the executing court in a proceeding for execution of such
null and void decree. The executing court has acted with gross failure in the
exercise of jurisdiction vested in it under the law as it was the solemn
obligation of the executing court to decide the question relating to nullity as
raised by the petitioner, and the court ought to have looked into the substance
and not the form of the objection. Accordingly, it would be necessary and
interest of justice if the order passed by the executing court, refusing to decide
the question raised by the petitioner, though objection to the executability of
the decree was raised this court under Article 227 of the Constitution of India
would be pleased to set aside the order impugned and direct the executing
court to decide the said question on merit.
16. These Revisional applications arise out of interlocutory order passed in
execution proceedings to the detriment of the petitioner and in the event the
Page 12 of 47
lead matter whereby the final order dismissing the application under section
47 of the code of civil procedure has been challenged, is disposed of the
outcome of the other revisional application would be likely to follow such
outcome. Accordingly, it is submitted that the lead revisional application be
allowed and the executing court be directed to consider the objection relating
executability as raised by the petitioner on the ground of the ultimate final
order of the reference “being a nullity, upon exercising the inherent power of
the court under Section 151 of the Code of Civil Procedure.
Submission made by the Opposite P arty no 2 & 3
17. On behalf of opposite parties no.2 & 3 the learned advocate, Mr Siddharth
Banerjee raises the preliminary objection regarding the locus standi of Bengal
Shrachi and Shrachi Burdwan on the ground of their absence in the
acquisition proceedings and in determination of compensation under the Land
Acquisition Act, 1894. It is the contention of the learned advocate that it was
BDA who requisitioned for acquisition of approximately 254 acres of land from
4 Mouzas by letter dated 12.12.2003 through the land acquisition,
Collector,Burdwan , expressly undertaking to bear the entire cost of
acquisition and hence BDA stood as “requiring body”, while the state of West
Bengal was the “acquiring authority” and neither Bengal Shrachi nor Shrachi
Burdwan made any requisition whatsoever to the state; consequently, neither
entity can be regarded as requiring body in law.
18. The state issued 12 notifications under section 4 of the Land Acquisition Act,
1894 declaring that the acquisition was for a public purpose and that public/
government expenses and hence it squarely falls under part II of the Act,
Page 13 of 47
rendering part VII (acquisition for a company) wholly inapplicable as the act
does not contemplate a hybrid or PPP mode of acquisition, combining parts II
& VII. It is further contended that the declaration under Section 6 conclusively
affirm that the lands were acquired for public purpose and at the public
expense. Such declarations are final and binding upon the State, BDA and all
downstream entities. The further stand taken by the Learned Advocate, that
Bengal Shrachi was selected through a bidding process for implementation of
its project and Shrachi Bardhaman is merely an assignee and Special Purpose
Vehicle created under a Deed of Assignment dated 20.10.2006 for execution of
the project. It is further argued that Shrachi Burdwan has unequivoc ally
admitted that the land was acquired for the purpose of BDA and further in
affidavit filed by Bengal Shrachi in WP N o. 16280 (W) of 2005 it was
categorically admitted that Bengal Shrachi acted only as an agent/developer
/contractor of BDA therefore, any subsequent contradictory stand,
demonstrably, mala fide and legally impermissible. That apart the award was
declared during July–August 2006 and possession was taken on 26.2.2007
upon the land vested in the State, free from all encumbrances. The state
handed over possession to BDA on the same date. Srachi Burdwan received
the land much later under a registered lease of dated 27.8.2010, making it a
post-acquisition allottee with no statutory or equitable right in the acquisition
19. It is further submitted by Mr. Banerjee, that when the land is acquired for
public purpose, time is the essence in determination and payment of
compensation and duty is cast on the state to pay requisite compensation to
the landowner at the earliest. Any attempt made by Srachi Burdwan , in
Page 14 of 47
collusion with the state and BDA, to interfere with such process constitute a
direct infringement of the respondent’s constitutional right under article 300 A
and the idea of a welfare state which is a fraud upon the statute and
landowner. After the award dated 21 May, 2012 was dismissed on 13.6.2016
in F.A.T 184 of 2016, as filed by BDA for non-compliance was again challenged
by BDA in FAT 66 of 2016, which was also dismissed as ‘not pressed’. That
apart Shrachi Burdwan has repeatedly attempted to re-open settled issues and
its first belated Challenge in W.P number 9778 (W) 2012 was dismissed by the
Division Bench in FMA 887 of 2019, which categorically denied the locus of
Shrachi Burdwan. The said judgement was expressly affirmed by the Hon’ble
Supreme Court in C.O. 5856 of 2019 and constitutes binding precedent. The
subsequent attempt was made by filing multiple revisional application, and the
Single Bench erroneously held Shrachi Burdwan as a ‘person interested’ and a
necessary party which was set aside by the Hon’ble Supreme Court with
explicit direction to proceed with execution. Third attempt was made by filing
objection under Section 47 is nothing but as a re-litigation, which is squarely
barred by Res-judicata and principles of finality. The limited liability granted
by this court in earlier civil appeal was confirmed strictly to 8 proceedings
under Section 54 of the Act and any stretch of imagination did not extend to
reach out revisional jurisdiction and such liberty cannot override or dilute the
binding the ratio decidendi whereby Hon’ble Supreme Court a ffirmed the
judgement passed in FMA887 of 2019 and set aside the contrary view of the
single bench. No appeal has been preferred by Shrachi Burdwan against the
present award and an y such right, if assumed stands long, waived by
deliberate inaction.
Page 15 of 47
20. It is further his contention that the order of the executing court dated
9.1.2018, rejecting the claim of Shrachi Burdwan as a “person interested” was
never challenged and has attained finality and therefore the reference court’s
order under Section 18 dated 23.8.2017 stands restored by the Hon’ble
Supreme Court. It is a settled proposition of law that the requiring body may
be a proper party under Section 50 but is never a person interested under
Section 3(b) of the Act. The argument advanced that an inter se dispute
between BDA and Shrachi under MOA dated 8.3.2006, do not bind the land
losers, and the amount paid by Shrachi towards lease, premium or rent ,lost
their character upon being credited to BDA/state funds and cannot be claimed
as Shrachi’s money for purposes of compensation. In this regard relied upon
the case of Pratibha Nema and ors . vs State of M.P
9
and Naihati
Municipality vs Chinmoyee Mukherjee and O rs.
10
.
21. The learned Advocate further relied upon the decision of Shyam Behari and
Ors. Vs. State of Madhya Pradesh and O rs.
11
, State of West Bengal Vs P.N
Talukdar
12
with regard to the objections raised assailing the validity of
Section 4 and 6 notification and seek to nullify concluded acquisition
proceedings and impermissible collateral attack by precedent. Therefore, the
lands in present case having not being acquired at the behest of Shrachi and is
an allotee under the lease agreement dated 27.8.2010 from the BDA is not a
‘person interested’, not having any right to participate in assessment of
compensation proceeding under section 18 of the Act or having right to be
9
AIR 2003 SC 3140
10
AIR 1997 SC 378
11
AIR 1965 SC 427
12
AIR 1965 SC 646
Page 16 of 47
heard. Shrachi Burdwan if cannot be a pa rty in the reference proceeding
cannot have any say in execution proceeding, and hence the objection under
Section 47 CPC is not maintainable. No appeal can also be maintained for
having no locus under Section 54 of the Act. Furthermore the award dated
21.5.2012 was passed jointly in favour of three awardees, Abdul Aleem, Abdul
Aziz, and Abdul Rahim, but is several in nature. The objection under Section
47 was filed only against Abdul Alim, leaving the awards in favour of the other
two awardees untouched and fully satisfied. The revisional court cannot
enlarge the scope beyond what was originally challenged. Challenged to the
award in favour of two awardees is waived and became settled. Abdul Rahim
already died on 2.10.2017.
22. The learned Advocate further discussed the scope of section 47CPC which is
extremely narrow and the executing court and as well as the revisional court
under Section 115 CPC cannot adjudicate third-party claims, examine
disputed facts, or travel beyond the decree. The present objection validates the
binding term of Hon’ble Supreme Court in Rahul .S.Shah, Pradeep Mehra, and
Periyammal. The objection is further barred by limitation under Section 137 of
the limitation Act having been filed long after knowledge of the award and
execution process only after exhausting all attempts up to the Hon’ble
Supreme Court and relied upon the case of Rasomoy Mitra and Kerala State
Electricity Board in support of such contention. In terms of the judgement
BDA deposited the decretal amount in the executing court with no objection to
withdrawal by decree holder/landowners and they have already withdrawn the
same to the full and final satisfaction. The execution process has been closed
Page 17 of 47
and now the third-party like Shrachi Burdwan cannot really get the award
under the garb of Section 47 CPC. Accordingly prayed for dismissal of the
revisional applications with costs.
Argument made by BDA
23. The learned Advocate representing BDA argued that after having full
knowledge about the entire process of acquisition they entered into agreement
with Bengal Shrachi for the purpose of development and in terms of the
agreement BDA after acquisition of land handed over the same to Bengal
Shrachi and in accordance with the specific terms and condition the Bengal
Shrachi paid the compensation amount but after passing of the award
enhancing the compensation by the Learned L.A court they refused to pay the
same. However subsequently by virtue of the order passed by the Contempt
court the entire payment is made over to the parties and hence this proceeding
is nonest in the eye of law. It is further submitted that the petitioner is having
no locus standi to move this revisional application as he is not the requiring
body. BDA further adopts the argument advanced by the Respondent no. 2 &
3.
Analysis
24. Heard the submissions of the learned Advocates. On the above facts and
circumstances as placed before this court, this court is of the view that before
delving into the bottom of the case, it is necessary to look into the overall facts
and to revisit the provision of law under which the land was acquired and
purpose of such acquisition. By letter dated 12.12 2003, the proposal for
Page 18 of 47
acquisition of land was given by Burdwan Development Authority to the
collector, land acquisition department Burdwan for acquisition of land in 4
Mouzas for development of Satellite Township Project, and the request was
made to the collector to acquire 257.81 acres of land and to handover its
possession to the Burdwan Development Authority to enable them to develop
the proposed project. It was further mentioned that the cost of acquisition will
be borne by BDA . It is clear from the notice inviting expression of interest that
BDA is a statutory authority of the government of West Bengal formed under
the West Bengal Town and Country Planning and Develo pment Act 1979
charged with the control of land use and intends to take up the Infrastructure
Development activities through suitable Public Private Partnership project.
Therefore, undisputedly it was a public partnership project had some terms
and conditions where BDA to take all steps to acqui re the project and
handover the same free from all encumbrances and encroachment to the
private partner in accordance with the project implementation schedule to be
fixed after mutual discussion. The notification under section 4 /6 of the Act, I
of 1894 to all concerned dated 10.5.2005, 1.12.2005 were issued on behalf of
Government of West Bengal, Land a nd Land Reforms department , Land
Acquisition .On giving a cursory glance to the affidavit filed by BDA in the writ
petition 16280 (W) of 2025, it is clear that Bengal Shrachi was only interested
with the job of developing the said land and the ownership of the said land to
be remain with BDA. The record further discloses that Bengal Shrachi already
invested around ₹11, 17, 99, 824 crores, being a renowned builder and have
an experience of promoting various big projects in West Bengal. The affidavit in
opposition used by Bengal Shrachi as found from the record filed in the writ
Page 19 of 47
petition being WP no. 16280 (w) of 2008.It was specifically stated on oath that
after acquisition of the said land, it will not be transferred in favour of Bengal
Shrachi and BDA will be the actual owner of the said land. Moreover, the said
project is built for public purpose as because it will be sold to public after
development. Therefore, there is no dispute with regard to the fact that the
property was acquired for a public purpose, namely for creating infrastructure
for setting up a Satellite Township in Bardhaman City and for improvement of
the same. The Acquisition was at the expense of the BDA in the form of
requiring body, and BDA is raising fund with the help of private participation
in implementing the aforesaid public purpose.
25. By way of affidavit in opposition BDA also made statement in the above
mentioned writ petition that in terms of the land Acquisition Act, the land was
acquired and such acquisition was within the purview of public purpose as
envisaged in Section 3(f) of the land Acquisition Act 1894 and after that
declaration under section 6 has been published in newspaper and the award
was made and compensation paid in view of acquisition of the said land by
state of Bengal on behalf of BDA as requiring body. Accordingly, the entire
compensation was made over by BDA to the state of West Bengal and the State
of West Bengal has paid the compensation to the persons concerned. It was
mentioned in the affidavit in opposition by BDA that the entire compensation
has been paid by BDA. In this case, there are rounds of litigation at the
instance of the present petitioner, who has come to this entire scenario by
entering into an agreement with the BDA on 21st day of August 2010, along
with Shrachi Burdwan whereas lessee the name of Shrachi Burdwan
Page 20 of 47
Developers Pvt. Ltd it is mentioned, and as confirming party name of Bengal
Shrachi Housing Development Limited. According to such agreement, BDA
invited expression of interest from reputed company/developers for suitable
private partners for association in the township project and by the MOA, BDA
had accepted the confirming party that is Bengal Shrachi who will pay the
entire cost of construction, develop the project, prepared all design and
drawing develop its infrastructural facilities. The MOA was executed between
BDA and Bengal Shrachi on 8th March, 2006.
In clause 5 of the same it provides that company shall pay the actual cost of
acquisition of the land together with all applicable incidentals, as maybe
determined by the land Acquisition Collector, Burdwan in accordance with the
provision of land Acquisition Act, 1984. It was further agreed that the company
would also bear additional cost in connection with the acquisition like
subsequent payment to the land losers in pursuance of the court orders, etc if
any on actual basis. Therefore, the right of the present petitioner Shrachi
Burdwan Development Private Limited, emanated from the agreement entered
into with BDA on 27th day of August 2010. In the said agreement the specific
details of the parties were described and it reveals that Shrachi Burdwan is a
lessee and Bengal Shrachi Housing Limited is a confirming party. The project
land was also described which was accepted BDO Memo no . 305/BDA on
November 8,2004 and such land to be used as per development plan of BDA .
It further disclose that Memorandum of Agreement dated 8th March, 2006
between BDA and confirming party and by a letter of BDA being Memo no .
195/BDA dated 1st March 2007, whereby the confirming party has been
Page 21 of 47
accorded “No objection” certificate to special purpose vehicle to implement the
Satellite Township Project in due compliance of the terms of and condition of
MOA . The process of acquisition commenced in the year 2005 /2006 when
there was no existence of Shrachi Burdwan Pvt ltd /petitioner herein. It was
Bengal Shrachi who deposited ₹1,91,75,810 with BDA for paying the cost of
Acquisition in 4 LA cases. Therefore, it is evident that at the time of process of
Acquisition, the present petitioner was not into the forey and his right derived
from an agreement entered into between BDA,Shrach i Burdwan and Bengal
Shrachi as confirming party with certain terms and conditions entered into
between them. In terms of the relevant provision of section 18, as discussed
above of the Land Acquisition Act and specially when the instant project was
only for public purpose which is governed under part II of the Act and not
under part VII which is acquisition for a company and hence the stand taken
by the petitioner that it was a public purpose, partnership and the petitioner
to be constituted as a representative of BDA is not tenable in the eye of Law.
26. The challenge before this court as assailed by the petitioners in three
revisional applications are the refusal by the executing court to implead the
petitioner as a party to the execution proceeding, secondly the petitioners are
aggrieved with the order dated 29th July 2925 dismissing the application filed
under Section 47 Cr.P.C and against the order dated 30.7.25 refusing to stay
the further proceeding of the execution case.
27. Upon giving an anxious consideration of the facts and circumstances of the
case it is evident although the petitioner tried to be a party in the proceeding
with the contention that they are the representative of BDA and hence party
Page 22 of 47
interested and necessary party ,such contention though was accepted by the
Learned Co-ordinate Bench but set aside by the Division Bench of this court
and duly affirmed by the Hon’ble Supreme Court. The observations made by
the Division Bench as well as the Hon’ble Apex Court questions the locus of
the petitioner which was found not established. The learned senior advocate
relied upon all the judgement relied before the learned single Bench regarding
the locus standi of the present petitioner and those were duly dealt with by the
learned Single Bench, where the definition of a ‘person interested’ given in
section 18 was discussed. In Himalaya Tiles and Marble (p) Limited (Supra)
it was held that the definition of person interested must be liberally construed,
so as to include a body, local authority, or a company for whose benefit the
land is acquired and who is bound under an agreement to pay the
compensation. The question was raised that how can it be said that a person
for whose benefit the land is acquired and who is to pay the compensation is a
person interested even though it’s take maybe extremely vital.
28. In the instant case, this point was agitated before the learned executing court
when the petitioners filed the application under Order 1 Rule 10 (2) of Code of
Civil Procedure and the learned court held that the terms of agreement entered
in between Burdwan, Shrachi and BDA or Burdwan Shrachi and Bengal
Shrachi are not binding upon the present petitioners/land losers or the State
as none of them are parties in the said agreement/contracts. In terms of the
agreement, Shrachi is required to pay additional compensation, if any to the
land looser, and if that be so the court was of the view that BDA is at liberty to
recover the same from Shachi and pay the same to the actual looser. The
Page 23 of 47
Division Bench while deciding appeal filed against the order passed by the
single bench dealt with the legal questions which are as follows.
“I) whether the first respondent herein, in its capacity
as the person implementing as the public project for
which the land was acquired under an agreement
with the requiring body would be a “person
interested” within the meaning of Section 3(b) of the
Act of 1894.
II) Whether the first respondent herein, in such status,
was entitled to be a party to the reference
proceedings under Section 18 of the Act of 1894.
III) Whether either the reference court or the land-
losers who had sought the references for
enhancement of compensation was obliged to issue
any notice to the first respondent herein , enjoying the
status as indicated above, or implead such person in
the reference cases before any enhancement of
compensation could be allowed in the reference.
IV) Were the writ petitioners entitled to the order that
they have obtained?
29. The Division Bench discussed the Act of 1894, which en visages the
acquisition of land by the state for any public purpose or at the behest of a
company and the Act provides for publication of a preliminary notification
under section 4 thereof, the hearing of objections from persons interested in
any land which has been notified under section 4(1) of the Act in accordance
with Section 5A thereof and issuance of declaration that the land is required
for public purpose or for a company issued under section 6 of the Act. For all
Page 24 of 47
practical purposes, the physical possession of the acquired land may be taken
over upon publication being made under Section 6 of the Act and the
collector’s award being declared, though matters pertaining to the final
compensation and the like, may take years thereafter. It was also discussed
that the Act of 1894 provides for an extraordinary situation since the land is to
be acquired for a direct public purpose, or for a private body, for the larger
interest of the economy, the physical access to the land and the right to use
the same is given paramount importance and the rights of the land losers, qua
the receipt of due compensation need not be conclusively assessed by the time
the nature and character of the acquired land is irreversibly changed and such
land is forever lost to the land losers. It was also discussed that the proviso to
Section 6(1) of the Act of 1894 mandates that no declaration under section 6 of
the act shall be made unless the compensation to be awarded for such
property is to be paid by a company, or wholly or partly out of public revenues
or some fund controlled or managed by a local authority.
30. The Division Bench further discussed definition of company which includes
companies as defined in Section 3 of Companies A ct, 1956, other than
government companies and also includes private registered societies and
private cooperative societies, government companies and registered societies
and cooperative societies controlled by the government are included within the
definition of corporation owned or controlled by the State in Section 3(cc) of the
act of 1894. Therefore, from the interpretation of the provisions envisaged in
the Act of 1894, regarding acquisition of the land for the public purpose or for
the company clearly defined and in the instant case from the content of the
Page 25 of 47
notification, there remains no ambiguity that the acquisition was made for the
purpose of development of Burdwan Satellite Township that is for public
purpose and lands were acquired after complying with all required formalities
and also in accordance with the law the compensation as decided by the state
Authority was paid. In terms of section 18 of Land Acquisition Act, if any
person interested who has not accepted the award may apply before the
collector for measurement of the land and determination of the quantum of
compensation. Section 18 reads as follows.
“18: Reference to court.
1) any person interested, who has not accepted the
award may by written application to the collector,
require that the matter be referred by the collector for
the determination of the court, whether his objection
be to the measurement of the land, the amount of the
compensation, the person to whom it is payable or the
apportionment of the compensation among the
persons interested.
2) the application shall state the grounds on which
objection to the is taken:
Provided that every such application shall be made-
a) if the person making it was present or
represented before the collector at the time
when he made his award, within six weeks
from the date of the collector’s award;
b) In other cases, within six weeks of the
receipt of the notice from the collector under
Section 12, Sub-Section (2), or within six
Page 26 of 47
months from the date of the collector’s award,
which your period shall first expire.”
31. Before the Division Bench, the learned Advocate appeared on behalf of the
land losers referred the second proviso to Section (1) of the Act of 1894 to
emphasise that it matters a little whether, Shrachi Burdwan would be merely
discharging the obligation of the requiring body in terms of an agreement with
the requiring body and according to them, in s uch a scenario, Shrachi
Burdwan would not aquire any status, independent of the body to be entitled
to have a voice in courts in the reference proceedings or any say in the matter
of assessment of the compensation to be paid to the land losers. It was further
contended that the moment the court recognise that the acquisition was made
for public purpose, it endorsed the declaration that was made under section 6
of the Act of 1894, and as a consequence, the compensation to be awarded for
the acquisition was to be paid wholly or partly out of public revenues or some
fund controlled or managed by a local authority or else the declaration would
never have been made.
Section 50 of the Act of 1894 reads as follows:-
“50. Acquisition of land at cost of a local authority or company.
1) Where the provisions of this act put in force for the
purpose of acquiring land at the cost of any fund
controlled or managed by a local authority or of any
company, the charges of and incidental to such
acquisition shall be defrayed from or of such fund or
company
Page 27 of 47
2) In any proceeding held before a collector or court in
such cases the local authority or company concerned
may appear and adduce evidence for the purpose of
determining the amount of compensation;
Provided that no such local authority or company
shall be entitled to demand reference under section
18.”
32. It is apparent from the record as well as from the submissions advanced that
the writ petitioners claimed and filed objection under Section 5A of the Act of
1894, which was deemed to be rejected upon declaration is being issued under
section 6 of the Act that the land proposed to be acquired was required for the
public purpose, and the Division Bench held that therefore, the principal
ground urged by the petitioners about the purpose for which such acquisition
was made or that it was made for private profit making exercise because of
involvement of private promoters was dismissed upon the court, expressing
satisfaction that the acquisition was for public purpose and noticing that the
recurring body was a development of authority constituted by state
government under the Act of 1979 for the Burdwan planning area, an area
declared as such under the State Act of 1979.
33. The Division Bench of this court meticulously discussed all the judgements
relied upon before the learned Single Bench as well as before the Division
Bench by the learned Senior advocate, Mr. Arindam Banerjee representing the
petitioner .The Learned Senior advocate referred to the concept of Public
Private partnership in the Act of 2013, that has now replaced the Act of 1894
and Section3 (zb) of the Act of 2013 which defines “Requiring body” which is
Page 28 of 47
placed along with Section 95 thereof and it correspondence to section 50 of the
Act of 1894, but specifically a right to the requiring body to appear and adduce
evidence for the purpose of determining compensation before the collector. The
submission made on behalf of the present petitioner that the present
Acquisition Act of 1894 to be guided by the subsequent legislation, was not
accepted by the learned Division Bench. It was clearly observed that,;
“First, the Act of 2013 makes a deliberate departure
from its predecessor statute in such regard. Secondly,
Shrachi Burdwan cannot be seen to be the requiring
body in the milieu of the subject acquisition.”
34. The distinction was drawn between a person covered by the expression
“person interested” in Section 3(b) of the Act of 1894 and the expression “Any
person interested’ in Section 18 thereof. This argument was also discussed and
held that “the expression “any person interested” in section 18 of the Act gives
such person a right to refer the collector’s award for determination of the court and
any expansive meaning attributed to such expression has to be tempered by the
prohibition in the proviso to section 50 of the Act of 1894.”
35. It was clearly held by the learned Division Bench that it is doubtful Shrachi
Burdwan can even be regarded as a “person interested” within the meaning of
relevant expression in Section 3 (b) of the Act of 1894, and the petitioner did
not take any steps to be completed in the reference proceeding or even
bothered to prefer any appeal against such orders. There remains no doubt
that Shrachi Burdwan was aware of the references and the order passed there
in. At any rate with exercise of minimum diligence, Shrachi Burdwan should
have been aware of the pendency of the references and contemporaneously
Page 29 of 47
aware of the orders of enhancement. Even o therwise, in view of the status
under the agreement with the requiring body, Shrachi Burdwan ought to have
kept self-informed of the references, the progress made there in and the fate
their off; and no argument to the contrary made by Shrachi Burdwan can be
countenanced in the equitable jurisdiction exercised under Article 226 of the
Constitution. The learned Division Bench also negated the stand taken by the
present petitioner that it was the duty of the land losers or the reference court
to implead the petitioner or issue notice of the reference proceeding to it. It was
lastly held that Shrachi Burdwan could never have been recognised to be ‘Any
person interested’ within the meaning of Section 18(1) of the Act of 1894 and
had no right to challenge the order granted or the annulment of the orders of
enhanced compensation passed by the reference court in the light of its
conduct and dates, unable and abject failure to protect its perceived rights
with the degree of diligence that was expected of it. It was further held that;
“it cannot be said by any stretch of imagination, that
it was the duty of either the land, losers or the
reference court to implead Shrachi Burdwan or issue
notice of the reference proceeding to it. Even upon
applying the dictum of Constitution Bench judgement
in UP Awas , Shrachi Burdwan could not have been
regarded by the reference court suo motu as the
requiring body or the person for whose benefit the
acquisition was made.”
36. The view of the learned Division Bench as appears “the Shrachi Burdwan is
not left without a remedy. Once he discharge its unequivocal obligation under
the agreement with BDA to put the requiring body in funds to satisfy the decree,
Page 30 of 47
obtained by the appellants herein , Shrachi Burdwan may, subject to the laws of
limitation, bring an action against partner BDA if it perceives BDA to have
colluded with the appellants herein or to have otherwise unlawfully facilitated,
the Appellants herein to obtain undeserving orders of enhancement of
compensation. But before the forum to which such action is carried, Shrachi
Burdwan would have to contain exactly the opposite of what it has conversed in
these proceedings before the writ court and in this appeal, Shrachi Burdwan
would then have to assert that since it was neither a requiring body in the
acquision of the land, nor a person for whose benefit the exercise was
undertaken, it’s right to proceed against BDA for damages, remain unaffected by
the reverse that it suffers in this appeal and, on the contrary, is strengthened
thereby. If the relevant forum holds otherwise, and the claim is repelled, BDA
would only be a victim of its conduct or of its erroneous perception of having
suffered any prejudice by the end, enhanced awards.”
37. The legal question that was raised was answered to this extent that ‘it is
doubtful that Shrachi Bardawan in its capacity as the person implementing the
public project for which the land was acquired under the agreement with the
requiring body, maybe regarded as a “person interested” as per the definition in
Section 3(b) of the Act of 1894”. It was also decided that Shrachi Burdwan in
such status was not entitled to be a party to the reference proceeding under
Section 18 of the Act of 1894. Neither the reference court nor the land losers
were obliged to issue any notice of the reference proceeding to Shrachi
Burdwan. The Division Bench with such observation clearly held as per the
status of the petitioner Shrachi Burdwan is not entitled to be a party in the
Page 31 of 47
reference proceeding under Section 18 of the Act of 1894 and the writ
petitioners were not entitled to any relief in the light of the Shrachi Burdwan’s
dismal conduct and accordingly set aside the appeal being FMA 887 of 2019.
Assailing such order Shrachi Burdwan went up to Hon’ble Supreme Court by
filing Civil Appeal No. 5856 of 2021. Arifa Khatoon and ors. also moved SLP
before Hon’ble Supreme Court against the judgement and order dated
26.2.2020 passed in C.O No. 1232 of 2018 whereby also the learned single
Bench held the award passed enhancing the compensation awarded in respect
of a reference proceeding is null and void and the award passed by the
reference court enhancing the compensation was set aside. Hon’ble Supreme
Court by a common judgement affirmed the order passed by the Learned
Division Bench and set aside the order passed by the learned single Bench.
38. The point was raised that in view of the definition of Section 3 (b) of the Act
Shrachi Burdwan can it said to be a person interested as the ultimate liability
to pay the enhanced compensation would be upon the appellant and he was
not included as a party in the reference court under Section 18 of the Act and
was not heard by the reference court. It was observed by the Hon’ble Supreme
Court that-
“Therefore, in the facts and circumstances of
the case and particularly when the locus of the
appellant Shrachi Burdwan to challenge the
judgment and award passed by the Reference
Court is seriously disputed and whether the
appellant, Shrachi Burdwan can be said to be a
“person interested” within the definition of
Section 3(b) of the Land Acquisition Act and
Page 32 of 47
thereby the appellant can challenge the
judgment and award passed by the Reference
Court enhancing the compensation are all
disputed question of facts are all contentious
issues, we are of the opinion that learned single
judge of the High Court ought not to have
entertained the writ petition under Article 226 of
the Constitution of India and not to have set
aside the judgement and award passed by the
reference court, enhancing the amount of
compensation under the provisions of the land
Acquisition Act.”
The order passed by the learned single judge in civil appeal number 5857–
5880 of 2021 was also set aside being not sustainable at law.
39. The learned Senior Advocate Mr. Arindam Banerjee, draws the attention of
this court to the paragraph 15 of the judgement delivered by the Hon’ble
Supreme Court, where by civil appeal was dismissed but it was observed that:-
“it will be open for the appellant/Shrachi
Burdwan Developers Private Limited to pursue
whatever other remedies may be availabl e to
them in accordance with law ,which may be
including filing of appeal under section 54 of the
Land Acquisition Act ,however subject to the
leave to appeal granted by the High Court for
which the appellant has to file a proper
application n for leave to appeal and satisfy the
High court that the appellant company can be
said to be the person interested under Section 3
(b) of the Land Acquision Act and that the
Page 33 of 47
appellant company has a locus to prefer appeal
under Section 54 of the Land Acquision Act”.
It was further observed that:-
“It will be open for the land owners to challenge
the locus of the appellant -Shrachi Burdwan as a
person inducted within the definition of section
3(b) of the land Acquisition Act and to contend
that the applicant has no locus to challenge the
judgement and award passed by the reference
court. All the aforesaid questions are kept open
to be considered by the High Court as and when
such application is preferred along with the
appeals.”
40. Therefore from the observation it is evident that, the Hon’ble Supreme Court
kept open the issue of the locus of the present petitioner to be decided by the
High Court which may be including filing of appeal under Section 54 of Land
Acquision Act and to take all other remedies may be available to them in
accordance with law . It is specific stand of the learned Senior Advocate that in
view of such leverage given to the petitioner the petitioner filed the application
for addition of party in the Execution case since by the time the execution
proceeding was initiated which was turned down by the Learned executing
Court giving rise to filing of the revisional application as it was not the
mandate of the Hon’ble Apex court that the petitioner can only filed the appeal.
In the observation of the Hon’ble Supreme Court a specific condition was even
expressed that such appeal under Section 54 Of L.A Act can be filed subject to
leave granted by the High Court satisfying about the locus of the petitioner
company that they are person interested Unser Section 3(b) of the Land
Page 34 of 47
Acquisition Act. As it appears that the petitioner company never prayed for any
leave to file appeal before any Court nor filed any appeal as directed by the
Hon’ble court but interpreting the order “which may include’ which according
to Mr. Arindam Banerjee the learned Senior Advocate has opened a wider
scope to approach the executing court by filing a petition under Section 47 of
CPC coupled with two application under Section 151 CPC .The learned
executing court by the order dated 29th July 2025 dismissed all the
applications. The learned Executing court observed that Section 47 CPC deals
with the question arising between the parties to th e suit or their
representatives apropos the execution, discharge or satisfaction of a decree
and it is no longer integra that the executing court cannot go beyond the
decree between the parties to the suit or their representatives. It was clearly
observed that the petitioner is neither a party nor the representative of any
party of the original land Acquisition case. More so the executing court cannot
act as an appellate court or revisional court.
41. It is unambiguously clear and held by the Division Bench affirmed by the
Hon’ble Apex court that despite having knowledge about the reference
proceeding the petitioner never tried to be impleaded as party in the reference
proceeding and waited till the award was passed and subsequently enhanced
and the decree was put into execution . The petitioner has miserable failed to
satisfy the Division Bench of Calcutta High Court as well as the Apex court
about their locus to be impleaded in the reference proceeding and therefore the
appropriate remedy would have been before the appellate authority against
the award passed in the reference proceeding . He cannot be otherwise said to
Page 35 of 47
be interested person in the subsequent proceeding, when the reference was
filed for enhancement of the compensation. The leverage given by the Hon’ble
Supreme Court to the petitioner to take appropriate measures can never be
interpreted to raise the same issue and to challenge the decree/award passed
by the reference court considering the same as null and void since passed
without giving him an opportunity of hearing. The learned Division Bench of
this Court meticulously discussed the status of the petitioner in view of the
law laid down and the said observation has been duly affirmed by the Hon’ble
Supreme Court however allowed the petitioner to prove his locus in the original
proceeding. BDA filed the appeal challenging the decree being F.A184 of 2016,
got dismissed on 13.6.2016 for non- compliance and again BDA challenged it
in FAT 66 of 2016 which was dismissed as “not pressed”.
42. The present petitioner has filed an application to recall such order which is
yet to be decided and therefore at present, there is no appeal pending
challenging the award passed by the reference court in enhancing the
compensations despite the opportunity given by the Hon’ble Supreme Court .
The petitioner left no stone unturned and filed the application under section
47 CPC in the execution case filed in connection with such award despite
being aware about the scope of Section 47 CPC being extremely narrow. A
third party claim to examine disputed facts cannot be adjudicated and the
executing court also cannot travel beyond the decree. Section 47 CPC reads as
under;
“47. Questions to be determined by the court
executing degree;
Page 36 of 47
1) all questions arising between the parties to the suit
in which the decree was passed, or their
representatives, and relating to the execution,
discharge or satisfaction of the decree, shall be
determined by the court, executing the degree and not
by a separate suit.
****
3) where a question rises as to whether any person is
or is not the representative of a party, search question
shall, for the purposes of this section be determined
by the court.
Explanation I- for the purpose of this section, plaintive
whose suit has been dismissed and a defendant
against whom a suit has been dismissed, our parties
to the suit.
Explanation II;-
a) for the purposes of this section, a purchaser of
property at a sale in execution of a decree shall be
deemed to be a party to the suit in which the decree is
passed; and
b) all questions relating to the delivery of possession
of such property to such purchase purchaser or his
representative shall be deemed to be questions
relating to the execution, discharge or satisfaction of
the decree within the meaning of this section.”
Page 37 of 47
43. In the decision as relied upon by the learned advocate, representing the
respondents 2 & 3 in Anand Chandra Panda Dead Through Lrs. versus
Collector, Keonjhar and another
13
held that-
“on a reading of Section 47 of the CPC, it becomes
evident that all questions arising between the parties
to the suit in which the decree was passed or their
representatives relating to the execution discharge or
satisfaction of the decree must be determined by the
court, executing the degree and not by a separate
suit. This manifest the questions must be determined
during the process of the execution of the degree. It is
during the pendency of the execution and proceeding,
and not subsequently when the execution proceeding
is closed and the decree has been executed to the
satisfaction of the executing court.”
In the instant case, in view of the subsequent orders passed by the learned
single bench in the contempt proceeding, filed by the land losers after the
application under section 47 CPC was dismissed, and the decree was executed
after being satisfied, directed the amount as deposited with BDA to be paid to
the land losers and accordingly the same has been paid. Therefore, practically
their remains nothing to be adjudicated further in this proceeding, unless the
present petitioner could prove their locus before the appropriate forum to
challenge the proceeding.
44. In the decision of R.P.A. Valliammal vs R. Palanichami
14
held that:-
13
2026 SCC OnLine SC 121
14
(1997) 10 SCC 209
Page 38 of 47
“Section 47 postulates that all questions
arising between the parties to the suit in which
the degree was passed or their representative
and relating to the execution, discharge or
satisfaction of the decree, shall be determined by
the court, executing the decree and not by a
separate suit”.
The petitioner has not been able to prove as of now that he is the
representative of the judgement debtor or any of the parties to the original
proceeding. The judgement delivered by the Supreme Court in Dhurandhar
Prasad Singh (supra) the power of the court under Section 47 of the Civil
Procedure Code, 1908 was discussed and held that objections under Section
47 to executability of decree held can be allowed if it is found that decree is
void ab initio and a nullity . This judgement has been relied upon by both the
learned advocates and much emphasis has been given by t he learned Senior
advocate, Mr. Arindam Banerjee that since no opportunity was given to the
petitioner in the original reference proceeding hence any decree passed without
offering opportunity to the necessary party to be treated as a nullity and hence
petitioner is entitled to raise the objection, even at the stage of execution of
such decree, where he was not a party.
45. In order to buttress such argument, the learned Advocate Mr Siddharth
Banerjee relied upon the paragraph 24 of the said judgement where it was held
that the exercise of power under Section 47 of the code is microscopic and lies
in a very narrow inspection hole. More so when the present petitioner was very
much aware about the proceeding initiated for granting compensation and
subsequently, the reference filed for enhancement of the compensation when
Page 39 of 47
they did not participate in the proceeding or made any attempt to be
impleaded and belatedly filed their first objection by filing a writ petition and
became successful, but such order of the learned single judge was set aside by
the Hon’ble Division Bench and affirmed by the Hon’ble Supreme Court can in
no manner be assailed such decree as a void ab intio which would enable the
petitioner to reopen the case by allowing the application under section 47 of
code of civil procedure. Careful perusal of the judgement further reveals that in
that case situations were discussed where the decree can be said to be void or
only without jurisdiction, for example maybe transaction against a minor
without being represented by his next friend. Such a transaction is a good
transaction against the whole world. So far as the minor is concerned, if he
decides to avoid the same and succeeds in avoiding it by taking records to
appropriate proceeding, the transaction becomes void from the very beginning.
In the same decision also, a situation was taken note of as discussed in
Marshalsea case
15
that:-
“…when a court has jurisdiction of the cause, and
proceeds inverso ordine or erroneously, there the
party who sues, or the officer or minister of the court
who execute the precept for process of the court, no
action lies against them. But when the court has not
jurisdiction of the cause, there are the whole
proceeding is coram non judice, and actions will lie
against them without any regard of the precept or
process…..”
15
(1612) 10 Co Rep 68b: 77 ER 1027
Page 40 of 47
46. In the instant case no such situation arose and the learned reference court
passed the award enhancing the compensation in accordance with law and the
award was put into execution. The petitioner approached the executing court
to be impleaded as a party which was refused and the order of the learned
single judge permitting the petitioner to be included as a party was set aside
by the Division Bench and duly affirmed by the Hon’ble Supreme Court.
Despite liberty is granted to the petitioner, no appeal has been preferred as of
now against such award and the appeal preferred by BDA was dismissed being
noted, and an application is now pending for recalling the order of dismissal of
the initial appeal filed by BDA and filed the application under Section 47 of
Code of Civil Procedure.
47. The present petition clearly mentioned that the District Magistrate issued
12 separate notifications under section 4 of the land Acquisition Act, notifying
that the land needed for the purpose of a project in the month of April 2005, in
May 2005, and in the month of December 2005, and January 2006, the notice
under Section 6 was issued by th e land and land reforms department
Declaring that the land needed for setting up of the project. The Bengal
Shrachi entered into the agreement of assignment in the year 2006 with the
present petitioner Shrachi Burdwan where under Bengal Shrachi investor,
Xander Investment holding VI limited a Mauritius based company incorporated
for the purpose of making investments in a real estate sector in India as
permitted under regulatory regime, agreed to develop the same project through
the petitioner Shrachi Burdwan as a special purpose vehicle, the SPV and by
the side agreement Bengal Shrachi assigned and transferred all its rights, a
Page 41 of 47
title and interest in the development of the state project to the petitioner
Shrachi Burdwan but at no point of time any of the land loser was a party to
the said agreement. No intimation was ever given regarding such deed of
assignment to the land losers or the purpose for which the acquisition of land
as declared was changed. Even if any such assignment is permitted by BDA
and if not followed subsequently the entire dispute lies between BDA and the
developers and the subsequent assignees which has been categorically
observed by the Hon’ble Division Bench affirmed by the Hon’ble Supreme
Court.
48. Before this court the challenge is made against the said order of the
Executing court dismissing refusing to entertain the application filed under
Section 47 of CPC and in view of the facts and circumstances the observations
made by the Hon’ble Apex court affirming the observation of the Hon’ble
Division Bench ,there is no room left to hold that the executing court acted
with gross failure in exercise of jurisdiction vested in it under the law as the
decree was void being passed by not impleading the petitioner as in the
execution proceeding since under public purpose, partnership the petitioner is
to be construed as a representative of BDA . This stand was negated at every
stage since this proceeding emanated in terms of land Acquisition Act Of 1894.
In the decision of Anisminic Ltd. (supra) decided the issue of lack of
jurisdiction which may arise in various ways which include absence of
formalities or things which are conditions precedent before the tribunal may at
the end make an order that it has no jurisdiction to make. The aforesaid
Page 42 of 47
proposition finds reflection in the observation of one of their Lordship, which
reads as under-
“Lack of jurisdiction may arise in various ways.
There may be an absence of those formalitie s or
things which are conditions precedent to the tribunal
may at the end, make an order that it has no
jurisdiction to make. Or, in the intervening stage,
while engaged in a proper enquiry, the tribunal may
depart from the rules of natural justice.; or it may ask
itself the wrong questions; or it may take into account
matters which it was not directed to take into
account. Thereby it would step outside its jurisdiction.
It would turn its enquiry into something not directed
by the Parliament and failed to make the enquiry
which the parliament did direct. Any of these things
would cause it purported decision to be a nullity.’”
49. In the present case as on date the petitioner has not taken any steps
against BDA for violation of any terms of the agreement which was also
observed by the Hon’ble Division bench .In view of the law lay down in this
regard, lack of jurisdiction and the explanations found in various judicial
announcement, this court do not find any substance regarding maintainability
of the revisional applications by the petitioners. Challenging the orders passed
by the executing court refusing to entertain the application under Section 47
of the Code of Civil Procedure, refusing to implead the petitioner as a party to
the execution proceeding and also disposing of the execution case in terms of
the award passed by the reference Court finally after being satisfied with the
Decree as the entire amount of compensation was deposited and withdrawn by
the land losers. It is clearly evident that a contempt application was filed by
Page 43 of 47
the Land losers in connection with Money Execution case being 12 of 2012
where the specific direction was given to the District Magistrate, Purba
Burdwan to comply the order dated. 29.8.2018 and 12.9.2018 and accordingly
the District Magistrate undertook the compliance. And as a consequence a
certificate proceeding was also initiated. The Hon’ble Supreme Court in the
case of Rahul S. Shah versus Jinendrakumar Gandhi
16
has held that-
“…..the benefit of section 47 CPC cannot be availed
to conduct a retrial causing failure of realisation of
the fruits of the decree. Section 47 is intended to
prevent multiplicity of suits .It simply lays down the
procedure and the form whereby the court reaches a
decision. For the applicability of the section, two
essential requisites have to be kept in mind. Firstly,
the question must be the one arising between the
parties and secondly, the dispute relate to the
execution, discharge or satisfaction of the decree.
Thus, the objective of section 47 is to prevent
unwanted litigation and dispose of all objections as
expeditiously as possible.”
50. This court is of the view that the petitioner in order to delay and drag the
proceeding without settling their initial onus to prove their locus to interfere
into the reference proceeding under Section 18 of land Acquisition Act, 1894
continue with their filing of application applications before the executing court
as well as before this revisional court, knowing fully well that these are not the
appropriate forum to decide the locus. That apart, the proceeding has reached
to fate accompli as the degree has not only been discharge, but the payment is
16
(2021) 6 SCC 418
Page 44 of 47
already made to the land losers and the prayer made by the petitioners to pass
any direction to behold such amount by the land losers until the status of the
present petitioners are established, does not find any leg to stand on. It is
decided as of now that the Appellant is not a person interested since the land
was not acquired for the purpose of appellant, and he has no right to question
the award. The Lessee company of the award land is neither a beneficiary not
an interested person under Section 3(b) all Section 9 of the act and is not
entitled to participate in the award proceeding. It is decided that Lessee
Company being post acquisition allottee of land is neither necessary, not
proper, but not interested person and nor has any locus to be heard in the
matter of determination of compensation. There is a distinction between the
acquisition under II public purpose at public expense and under part VII
acquisition for company of the L.A act 1894, and in this case, it is clearly
under part II for public purpose at public expense.
51. In the case of M/S ultra Tech cement Limited versus M ast Ram and
others
17
the dispute relates to ownership of subject land and health cannot be
an impediment to legitimate rights of original land owners to receive
compensation. Payment of full and final compensation to land owner is a
precursor to taking position of land sought to be acquired from such persons.
In the said case in notice under Section 4 of A.A act 1894 was issued by state
of Himachal Pradesh, declaring its intention toward the subject land
measuring 56 to 14 Vega for the purpose of acquiring the land was to create a
safety zone surrounding the mining area. During the acquisition proceedings
of the land owners did not allow the authorities to undertake the evaluation of
17
2024 INSC 709
Page 45 of 47
their houses, trees structures for the purpose of determination of
compensation, and the proceeding was challenged before High Court and an
ad interim order was granted the acquisition proceeding by the High Court.
The petition was ultimately dismissed on the ground that acquisition of the
lands was for a public purpose and then the award was passed b y the LA
collector in terms of Section 24(1)(a) of the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
and determine the compensation. Being dissatisfied with the award petition
was filed with a prayer to pass a supplementary award after 2020, finding the
compensation for the damage caused to the structures and standing crops and
accordingly direction was passed to the supplementary award which was also
passed during pendency of this acquisition proceeding JAL entered into an
agreement with Apple, M/s. Ultra Tech cement for transfer of the cement
project in question, the dispute arose as to who should pay the compensation
amount determined under the supplementary award to the land losers and the
High Court relying on the terms of the scheme, passed the order, directing the
Appellant to pay the compensation amount at the first instance and left it open
for them to recover the same from JAL letter, if permissible in law. The matter
went up to Hon’ble Supreme Court where role of the state under Article 300 A
of the Constitution was discussed and it was found that the amount
determined as compensation under the supplementary award was not paid to
the land owners for a period of more than two years and no effort was made by
the state to get the same paid at an hour. It was held that time is of the
essence in determination and payment of compensation, as is evident from the
judgement in Kukreja construction Company and others versus State of
Page 46 of 47
Maharashtra and others.
18
, where also it was decided that “once the
compensation has been determined, the same is payable immediately without
any requirement of a representation or request by the landowners and the duty
is cast on the state to pay such compensation to the land losers otherwise, there
would be a breach of Article 300A of the Constitution.” Further, it is found that
the state of Himachal Pradesh did not ensure payment of compensation to the
respondent number 1 to 6 before taking possession of their land when Section
38(1) indicates that the payment of full and final compensation to the
landowners is a pre-to taking possession of the land sought to be acquired
from such persons.
Conclusion
52. Therefore in summation of supra and after considering entire facts and
circumstances this court do not find any merit in the case.
53. This Court further is of the view that the petitioner has persistently raised
the same contention before different forums ,notwithstanding that the issue
stands conclusively settled by the Supreme Court .In absence of any
appropriate challenge to the said decision ,such proceedings are hit by res
judicata and constitute an unwarranted consumption of precious judicial
time.
54. Accordingly the Revisional applications being C.O. 2890 of 2025, 2892 of
2025 and 3194 of 2025 are hereby dismissed with cost of Rs.1,00,000/-/- to
be paid to the Calcutta High Court Legal Aid Services Committee.
18
2024 SCC OnLine SC 2547
Page 47 of 47
55. All other connected applications are hereby disposed of.
56. Urgent certified copy if applied by any of the parties to be supplied subject to
observance of all formalities.
(CHAITALI CHATTERJEE DAS, J.)
Legal Notes
Add a Note....