As per case facts... A Public Interest Litigation (PIL) was filed challenging a government notification that set lower and upper limits for tender bids and introduced standard bidding documents which ...
Page No.# 1/18
GAHC030001952026
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : PIL/1/2026
1.Shri Vanlalruata Sailo
S/o Thangthuama
R/o LK/C 36, Leitan K Section,
Tlangnuam (Part), Aizawl, Durtlang,
Mizoram-796025
………Petitioner
-Versus-
1. THE STATE OF MIZORAM, through
The Chief Secretary, Government of
Mizoram, New Secretariat Complex,
Khatla, Aizawl, Mizoram-796001
2. THE PRINCIPAL SECRETARY,
Finance Department, Government of
Mizoram, New Secretariat Complex,
Khatla, Aizawl, Mizoram-796001.
Page No.# 2/18
3. THE SECRETARY, Law & Judicial
Department, Government of
Mizoram, New Secretariat Complex,
Khatla, Aizawl, Mizoram-796001
……..Respondents
BEFORE
HON’BLE MR. JUSTICE NELSON SAILO
HON’BLE MR. JUSTICE KAUSHIK GOSWAMI
Advocates for the petitioner: Mr. Kartik Jain, Adv
Advocate for the respondents: Mr. Biswajit Deb, A.G,
Mrs. Linda L. Fambawl, Addl. A.G.
Date on which judgment is reserved : 02.09.2026
Date of pronouncement of judgment : 09.09.2026
Whether the pronouncement is of the
Operative part of the judgment? : No
Whether the full judgment has been
Pronounced? : Yes
JUDGEMENT AND ORDER (CAV)
(Nelson Sailo, J)
Heard Mr. Kartik Jain, learned counsel for the petitioner and
Mr. Biswajit Deb, learned Advocate General assisted by Mrs. Linda
Page No.# 3/18
L. Fambawl, learned Addl. Advocate General appearing for the
State.
[2.] Brief facts of the case has already been highlighted in our
Order dated 20.05.2026 and the same is being abstracted
hereunder for brevity:
“Heard Mr. Kartik Jain, learned counsel for the petitioner as well as Mr.
Biswajit Deb, learned Advocate General, Mizoram, assisted by Mrs. Linda L.
Fambawl, learned Addl. A.G., Mizoram.
[2.] The learned counsel for the petitioner submits that a public
spirited person has filed the instant PIL to espouse the arbitrariness and
illegality committed by the State respondents in coming up with the
Notification dated 15.07.2024 fixing the permissible lower limit of tender at
5% below the estimated cost and the higher ceiling at 10% above the
estimated cost. Further vide Office Memorandum dated 26.09.2025 the State
Government in the Finance Department has also prescribed two (2) Standard
Biding Documents (SBD) for procurement of building & other related works;
and for road works. He submits that as per both the SBDs certain provision
and provisos of Clause-4 of the General Rules and Directions of the
Government of India, Central Public Works Department amongst others has
been omitted/excluded. The competent authority is therefore given an
unbridled power to choose the bidder of his choice. The learned counsel
Page No.# 4/18
submits that the State respondents have themselves flouted the provisions of
the Mizoram Public Procurement Rules, 2020 published in the Mizoram
Gazette dated 12.02.2020, the Mizoram Transparency and Public Procurement
Act, 2008 published in the Mizoram Gazette dated 28.04.2008 and the
Government of Mizoram Notification No. PWE-7/72/71 dated 01.05.1976.
[3.] The learned counsel submits that in view of the impugned
Notification as well as the Standard Bidding Document issued by the State
respondents, there is no scope of having a fair play, there is no transparency
and also no reasonable procedure for selecting a successful bidder, since it is
already known to everyone that the lowest tenderer would be the one who
has quoted 5% below the estimated cost. Under the impugned Notification
and the Standard Bidding Document, the Competent Authority will be able to
pick and choose the tenderer of his choice. Therefore, the Court’s
interference to the impugned notification and the SBDs is necessary to ensure
fairness in the selection of tenderers.
[4.] Per contra, Mr. Biswajit Deb, learned Advocate General, Mizoram,
submits that the instant petition is not a Public Interest Litigation but a
private interest litigation. He submits that the impugned Notification has been
issued in the year 2024, whereas, the instant PIL is initiated only two (2)
years thereafter and purportedly in furtherance of the representation
submitted by an interested person. He submits that the Notification dated
15.07.2024 is the outcome of a policy decision of the State Government and a
Page No.# 5/18
result of due consideration of pros and cons of such fixation. He submits that
unless a limit is fixed, public interest will suffer in view of the fact that
quotations will be made at a fairly low rate and thereby resulting in sub-
standard works, revision of estimates and also escalation of costs. Therefore,
taking into account all such issues, the Notification was issued.
[5.] The learned Advocate General, Mizoram, submits that in matters
relating to tender and contract, the role of the Court is to see whether the
State has acted validly and for a discernable reason and not whimsically for
ulterior purpose. Insofar as the fixation of value of tenders is concerned, it is
entirely within the purview of the executive and Courts have little or no role.
In support of his submission, he has relied upon the case of Michigan Rubber
(India) Limited Vs. State of Karnataka and Ors., (2012) 8 SCC 216 and
Judgment dated 17.09.2021 of the Apex Court in Civil Appeal No. 4862-4863
of 2021(UFLEX Limited Vs. Government of Tamil Nadu & Ors.).
[6.] We have considered the rival submissions. From a perusal of the
Notification dated 15.07.2024 impugned by the petitioner, we have noticed
that the permissible lower limit while considering tenders is fixed at 5%
below the estimated cost put to tender and the permissible upper ceiling is
fixed at 10% of the estimated cost put to tender. While such is the fixation,
the Clause-4 of the Government of India, Central Public Works Department is
being applied by the State through the SBD for procurement of building and
other related works as well as for road works. However, the original
Page No.# 6/18
prescription of the Government of India, CPWD under Clause-4 providing the
procedure in case of more than two or more contractors having quoted the
lowest rate has been omitted. All that is provided is that in the case of two or
more lowest bidders, the successful bidder amongst such bidders will be
decided by the competent authority. This in our prima-facie view appears to
restrict competition in as much as the authority concerned has empowered
itself to pick and choose the successful bidder from amongst two or more
lowest bidder. The lowest bidder is already defined in terms of the impugned
Notification dated 15.07.2024, whereby, the permissible lower limit is fixed at
5% below the estimated cost put to tender. There can be no argument with
the principles enunciated by the Apex Court in the authorities relied upon by
the learned Advocate General. The State and its instrumentalities indeed has
a free hand to pick the best tenderer from amongst the valid tenders, but by
the impugned Notification and the SBDs it prima-facie appears that there is
no scope for having a competition amongst the tenderers and there is lack of
transparency and lack of reasonable procedure for selecting successful bidder.
Accordingly, in the interim, we are of the view that the impugned Notification
dated 15.07.2024 as well as the SBDs for procurement of building and other
related works as well as the road works should be stayed. It is ordered
accordingly.
[7.] List the matter again after three (3) weeks.
[8.] In the meantime, the respondents to file their counter-affidavit.”
Page No.# 7/18
[3.] In response to the PIL, the State respondents have filed an
affidavit-in-opposition on 16.06.2026 contending inter-alia with the
impugned Notification dated 15.07.2024 in fact was issued in the
larger interest of the public with the primary objective of
safeguarding the quality of public works and ensuring prudent
utilization of public funds. They have also highlighted instances,
where similar variations below and above the estimated cost put
to tender have been issued which therefore would show that
fixation of the lower limit of bidding is necessary. Further,
reference has been made to the CPWD Manual which provides for
the power to accept the lowest tender after call of tender with or
without negotiation for both original and maintenance work.
According to the respondents, the Competent Authority with
financial powers for Rs.1 crore, 10 crore, 30 crore and 50 crore are
the Executive Engineer, Superintending Engineer, Chief Engineer
and the Addl. Director General/Engineer-in-Chief respectively.
Further, in case of tied bids as per the CPWD Manual, the
Competent Authority makes the final selection in the interest of
the Government based on factors such as past performance,
ongoing works, work done, quality and quantity of works executed
Page No.# 8/18
and compliance integrity pact. The respondents thus contend that
fixation of 5% lower price ceiling is intended to prevent
abnormally low bids which often result in poor quality execution,
substandard materials and premature deterioration of public
assets. Such practices therefore could cause greater financial loss
to the exchequer. The cap ensures that contractors quote realistic
prices that reflect genuine costs of quality construction and
maintenance.
[4.] The respondents further contend that in pursuance to the
interim order dated 20.05.2026, it has been notified vide Office
Memorandum dated 26.05.2026 that the Notification dated
15.07.2024 shall remain inoperative w.e.f 20.05.2026 until further
orders. That in the meantime, all procurement/works shall be
governed by the provisions of Mizoram Transparency in Public
Procurement Act, 2008, The Mizoram Public Procurement Rules,
2020 and the applicable provisions of Clause-IV of the CPWD
Manual until further instructions are issued by the Government.
[5.] The State respondents thereafter filed an additional affidavit
on 03.07.2026, justifying the impugned Notification dated
Page No.# 9/18
15.07.2024 with regard to capping of the lower ceiling by referring
to a number of decisions rendered by the Apex Court on the
subject matter.
[6.] When the matter was listed on 13.08.2026, the Court
recorded that from the submissions of the learned counsel for the
petitioner only one point has been stressed i.e., in the event there
is more than one lowest bidder, there is no fixed criteria on the
basis of which the successful bidder would be selected. The
submission of the learned Advocate General was also recorded
that in view of the interim order dated 20.05.2026 passed by this
Court, an Office Memorandum dated 26.05.2026 was issued by the
Government providing that in view of the said order the provisions
of Clause-IV of the CPWD Manual would be followed until further
instructions are issued. The Court therefore was of the considered
view that keeping the issue of maintainability of the PIL open, if
the State Government come up with a selection criteria as was
indicated in the said order, the grievance of the petitioner would
be fully addressed and nothing more would remain in the PIL.
[7.] Thereafter, the State respondents have filed an additional
Page No.# 10/18
affidavit on 24.08.2026, incorporating a Notification dated
19.08.2026, issued by the Finance Department (Expenditure
Control Branch) on the subject “Procedure for section amongst
multiple responsive lowest bidders (L-1) and determination of
competent authority in procurement/works-regarding.” The said
Notification provides that this Court vide order dated 13.08.2026
by modifying interim order dated 20.05.2026 had granted liberty
to the State to formulate an appropriate criteria for selection
amongst multiple L-1 bidders and to specify the Competent
Authority in relation to the contract value. Accordingly, guidelines
for selection of bidder/contractor in case of tied bids was framed
which includes record of past performance in contract works,
record of experience in similar works, litigation, current or during
the last 5 years in which a bidder is involved, record of poor
performance, record of financial failure, availability of essential
construction equipments and man power and bid capacity.
[8.] Further, there is also a clause preventing the near relatives of
the Divisional Accountant or Engineering Officers between the
grades of Superintending Engineer and Junior Engineer from
Page No.# 11/18
participating in the tender process. Also the Competent Authority
for the purpose of the guidelines would be a committee under the
chairmanship of the next higher authority to the authority
competent to accept the bid/tender as per delegation of financial
powers in Standard Operating Procedures for CPWD Works Manual
in force. A chart/table in this regard was also prepared.
[9.] In response to the above affidavit-in-opposition and two
additional affidavits filed by the State, the petitioner has not filed
any response. Mr. Kartik Jain, learned counsel for the petitioner
submits that fixation of lower ceiling at 5% is a restriction which is
unreasonable since there may be prospective tenderers who would
like to submit their bid more than 5% below the estimated cost
put to tender. He submits that there are instances where variations
have gone up to 30% below the estimated cost put to tender.
Therefore, by putting a restriction only up to 5% below the
estimated cost, the same amounts to wastage of funds from the
public exchequer. As the same is not in public interest, the
Notification dated 15.07.2024 should be set aside.
[10.] The learned counsel submits that insofar as the
Page No.# 12/18
Notification dated 19.08.2026, issued by the Finance Department
is concerned, the same appears to be only a procedure to be
adopted during the technical bid. He submits that in a tender
process there are ordinarily two bidding process i.e., technical bid
and financial bid. He submits that the Notification dated
19.08.2026 covers only the technical bid and therefore, the claim
of the respondents that the said procedure provided in the
Notification dated 19.08.2026 is for a situation in case of more
than one lowest bid is only misleading and cannot be accepted.
[11.] The learned counsel as regards the maintainability of the
PIL submits that the guidelines itself provide that petitions
concerning matters of public importance can be entertained as a
PIL. Therefore, the issue raised in the instant PIL being a matter
of public importance, the PIL is only maintainable.
[12.] Per-contra, Mr. Biswajit Deb, learned Advocate General
submits that as per the guidelines issued by the Supreme Court of
India based on a full Court decision dated 01.12.1988 and the
subsequent modifications, cases falling under the assigned
category of the compilation alone can be entertained as the PIL
Page No.# 13/18
and that complaint against the Central/State Government
Department and local bodies except those mentioned in Sl. No.1 to
10 of the compilation will not be entertained as PIL. Considering
the same, the learned Advocate General submits that the instant
PIL is not maintainable. In order to support his submission, the
learned Advocate General amongst others has relied upon the
Apex Court decision in Michigan Rubber (India) Limited v.
State of Karnataka and Ors, (2012) 8 SCC 216 and
Judgment dated 17.09.2021 of the Apex Court passed in Civil
Appeal Nos.4862 - 4863 of 2021 (Uflex Limited v. Government
of Tamil Nadu and Ors.).
[13.] The learned Advocate General further submits that by
order of this Court dated 13.08.2026, the issue in the instant PIL
has also been scaled down to only one point i.e., what would be
the criteria for selecting a successful bidder in the event there is
more than one lowest bidder. Apart from this, the issue of
maintainability has been left open to be considered. He submits
that the learned counsel for the petitioner on the other hand has
withheld this fact from this Court by enlarging the scope of
Page No.# 14/18
consideration beyond what was recorded on 13.08.2026 by this
Court. The learned Advocate General submits that this fact has
also been taken into account subsequently by this Court on
25.08.2026. This Court by taking into account the Notification
dated 19.08.2026 brought on record by way of the additional
affidavit dated 24.08.2026 was of the view that the grievance of
the petitioner only appeared to have been redressed. That it was
only on the insistence of the learned counsel appearing on behalf
of the conducting counsel that the matter was adjourned. He thus
submits that the PIL should be dismissed on the ground of non-
maintainability and in view of the Notification dated 19.08.2026,
issued by the State Government in the Finance Department.
[14.] We have considered the submissions made by the
learned counsel appearing for the rival parties. This Court on
20.05.2026 after having a prima-facie view that there appears to
be lack of transparency and lack of reasonable procedure for
selecting successful bid, stayed the impugned Notification dated
15.07.2024 as well as the standard bidding documents for
procurement of building and other related works. Following the
Page No.# 15/18
same, the Office Memorandum dated 26.05.2026 was issued.
[15.] Thereafter, when the matter was listed on 13.08.2026, as
already stated in the preceding paragraph, the Court recorded that
from the submission made by the counsel for the petitioner, only
one point is now stressed which is regarding unavailability of a
fixed criteria for selection of a successful bidder in the event there
is more than one lowest bidder. Accordingly, it was observed that if
the State Government comes up with a selection criterion to be
adopted in such a situation, the grievance of the petitioner would
be met and nothing would remain in the PIL. Apart from this
observation, the issue of maintainability of the PIL was kept open.
It was also importantly observed that the earlier interim order
dated 20.05.2026 was accordingly modified to enable the State to
proceed with the tender process but however, for the time being,
the State Engineering Departments should follow the Office
Memorandum dated 26.05.2026, till the policy of selection of a
successful bidder in the event there is more than one lowest
bidder as was suggested by the Advocate General is notified.
Therefore, the order dated 13.08.2026 and the subsequent order
Page No.# 16/18
dated 25.08.2026 has only scaled down the issue for consideration
to (i) the maintainability of the PIL and (ii) the criteria to be
followed in case of more than one lowest bidder in order to select
a successful tender.
[16.] Pursuant to the order dated 13.08.2026, the State
Government in the Finance Department (Expenditure Control
Branch) have come up with the Notification dated 19.08.2026
providing for the procedure for selection in the event of multiple
responsive lowest bidders (L-1). The guidelines for making the
selection of the Competent Authority to select bidder in case of
tied bids has also been provided by the said Notification. The same
is already been mentioned in the preceding paragraphs, and
therefore not being repeated for brevity. The said criteria was not
provided in the standard bidding documents for procurement of
building and other related works issued through the Office
Memorandum dated 26.09.2025. All that was provided was that in
case of two or more bidders who have quoted the lowest amount,
the successful bidder amongst such bidders shall be decided by
the Competent Authority. Therefore, lack of transparency in the
Page No.# 17/18
selection of successful bidder was the glaring point to be
considered. However, as per the Notification dated 19.08.2026, the
procedure and guidelines for selecting bidder/contractor in case of
tied bids have now been provided and therefore, it is seen that the
issue raised by the petitioner has already been addressed.
[17.] Be that as it may, it is neither within the domain of this
Court nor within the scope of judicial review to embark upon an
enquiry in the present PIL as to whether a particular criterion for
selection amongst successful bidders in the event of a tie is wise,
appropriate or preferable, or whether any other criterion could
have been evolved. In matters pertaining to policy and formulation
of criteria for selection, the Government has considerable latitude
to determine the manner in which such matters are to be
regulated, so long as the decision is bona fide, is within the limits
of the authority vested in it and does not suffer from any manifest
illegality or arbitrariness. In the present case, the
guidelines/criteria now prescribed do not appear to be in violation
of any law, nor is there any material to suggest that the same
have been framed or applied mala-fide. This Court, therefore,
Page No.# 18/18
finds no ground to interfere with the same in exercise of its power
of judicial review.
[18.] Insofar as, fixation of the lower and upper ceiling of the
estimated cost put to tender, the same is now not open for
consideration since the scope of the PIL has been confined only to
the criteria for selecting a successful bidder in case of more than
one lowest bidder apart from maintainability of the PIL.
[19.] Insofar as the maintainability of the PIL is concerned, in
view of the developments that has taken place after filing of the
instant PIL, more particularly, the Notification dated 19.08.2026,
we are not inclined to dwell upon the same and instead leave it
open for consideration in appropriate proceedings.
[20.] In the result, the PIL stands closed. Interim order/orders
passed earlier stands vacated.
JUDGE JUDGE
Comparing Assistant
In a significant ruling concerning government procurement, the Gauhati High Court recently pronounced its judgment in PIL/1/2026, a Public Interest Litigation challenging aspects of Mizoram's Government Tender Policy. This case, now prominently featured on CaseOn, delves into critical issues of transparency and fairness in public contracts.
The petitioner, Shri Vanlalruata Sailo, initiated this Public Interest Litigation (PIL) to challenge specific actions by the State of Mizoram. The primary concerns revolved around:
The court’s decision was guided by several key legal instruments and precedents:
Initially, the High Court, finding a prima facie lack of transparency and a reasonable selection procedure, issued an interim order on 20.05.2026. This order stayed the impugned Notification dated 15.07.2024 and the Standard Bidding Documents (SBDs).
In response, the State of Mizoram issued an Office Memorandum (OM) on 26.05.2026, declaring the 15.07.2024 Notification inoperative and mandating adherence to the Mizoram Transparency in Public Procurement Act, 2008, Mizoram Public Procurement Rules, 2020, and the applicable provisions of Clause-IV of the CPWD Manual until further instructions.
As the case progressed, the primary focus narrowed to the absence of clear criteria for selecting a successful bidder when multiple bidders quoted the lowest amount (L-1). The State, acknowledging this concern, filed an additional affidavit on 24.08.2026, incorporating a new Notification dated 19.08.2026 from the Finance Department.
This new Notification provided a detailed procedure and guidelines for selecting among multiple responsive L-1 bidders. The criteria included:
The Notification also established a committee, chaired by the next higher authority to the one competent to accept the bid, for making these selections. Additionally, it included a clause to prevent near relatives of Divisional Accountants or Engineering Officers from participating in the tender process.
The Court reiterated that its role in tender and contract matters is limited. It primarily assesses whether the State acted validly and for discernible reasons, not whimsically or for ulterior purposes. While the petitioner argued that the 5% lower ceiling was an unreasonable restriction, the Court noted that this issue was no longer a primary point of contention, as the PIL's scope had been narrowed to the criteria for tied bids.
The Court emphasized that it does not substitute its judgment for that of the executive in formulating policy or selection criteria, provided the government's decision is bona fide, within its authority, and free from manifest illegality or arbitrariness. The newly prescribed guidelines for tied bids were found to satisfy these conditions, showing no violation of law or evidence of mala fide intent.
For legal professionals grappling with similar intricate judgments, CaseOn.in's 2-minute audio briefs prove invaluable. They distill complex rulings like this one into digestible summaries, helping legal practitioners quickly grasp key details, judicial reasoning, and implications for their cases.
In light of the State Government's proactive measures, particularly the Notification dated 19.08.2026 addressing the selection criteria for tied bids, the Gauhati High Court concluded:
This judgment serves as a critical illustration of several principles vital for legal professionals and students:
All information provided in this article is for informational purposes only and does not constitute legal advice. While efforts have been made to ensure accuracy, readers should consult with a qualified legal professional for advice on specific legal issues.
Legal Notes
Add a Note....