No Acts & Articles mentioned in this case
THE HIGH COURT OF SIKKIM : GANGTOK
(Civil Appellate Jurisdiction)
----------------------------------------------------------------------------
DIVISION BENCH: THE HON’BLE MR. JUSTICE BISWANATH SOMADDER, CHIEF JUSTICE
THE HON’BLE MR. JUSTICE BHASKAR RAJ PRADHAN, JUDGE
---------------------------------------------------------------------------
Arbitration Appeal No. 1 of 2020
1. Sikkim Power Development Corporation Ltd.,
Through its Managing Director,
31 A, National Highway,
Gangtok, Sikkim – 737101.
2. The State of Sikkim,
Through its Secretary,
Power Department,
Government of Sikkim,
Kazi Road,
Gangtok, Sikkim – 737101. ….. Appellants
versus
M/s Amalgamated Transpower (India) Ltd.,
Through its Managing Director,
Having its office at E-10/8,
Vasant Vihar,
New Delhi. ….. Respondent
Appeal under section 37 of the Arbitration & Conciliation Act, 1996
[Against the judgment dated 26.12.2019 passed by the Commercial Court, East
Sikkim, Gangtok, in Arbitration Case No. 05 of 2017]
------------------------------------------------------------------
Appearance:
Mr. Jishnu Saha, Senior Advocate with Mr. Tarun Johri, Mr. Aarohi Bhalla,
Ms. Tamanna Chhetri, Mr. Tenzing Thinlay Lepcha, Mr. Vidhan Vyas,
Mr. Tanish Ganeriwala and Mr. Vishwajeet Tyagi, Advocates for the
appellants.
Mr. Prasanna Kumar Das, appearing in -person, as representative of the
respondent.
-------------------------------------------------------------------------------
and
Arb. A. No.1 of 2020 2
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
Arbitration Appeal No. 1 of 2021
Amalgamated Transpower (India) Ltd.,
Through its Chief Executive Officer
and Authorised Representative,
E-10/8, Vasant Vihar,
New Delhi 110057. ….. Appellant
versus
1. M/s Sikkim Power Development Corpo ration Ltd.,
Through its Managing Director,
31 A, National Highway,
Gangtok, Sikkim – 737101.
2. The State of Sikkim,
Through its Principal Chief Engineer-cum- Secretary,
Power Department,
Government of Sikkim,
Kazi Road,
Gangtok, Sikkim – 737101. ….. Respondents
Appeal under section 37 of the Arbitration & Conciliation Act, 1996
read with section 96 of the Code of Civil Procedure, 1908.
------------------------------------------------------------------
Appearance:
Mr. Prasanna Kumar Das, appearing in -person, as representative of the
appellant.
Mr. Jishnu Saha, Senior Advocate with Mr. Tarun Johri, Mr. Aarohi Bhalla,
Ms. Tamanna Chhetri, Mr. Tenzing Thinlay Lepcha, Mr. Vidhan Vyas,
Mr. Tanish Ganeriwala and Mr. Vishwajeet Tyagi, Advocates for the
respondents.
-------------------------------------------------------------------------------
Date of hearing: 10.03.2023, 13.03.2023, 14.03.2023, 15.03.2023,
16.03.2023, 20.03.2023, 21.03.2023, 22.03.2023,
23.03.2023, 29.03.2023 & 19.04.2023
Date of judgment : 10.05.2023
-------------------------------------------------------------------------------
J U D G M E N T
Scope of the two appeals:
(1) Arbitration Appeal No. 1 of 2020 filed by Sikkim Power
Development Corporation L imited (SPDC) and the State of
Sikkim (SoS)
(2) Arbitration Appeal No. 1 of 2021 filed by Amalgamated
Transpower (India) L imited (ATPL)
1.(i) This judgment shall dispose of the two appeals as stated
above, both preferred under section 37 of the Arbitration and
Arb. A. No.1 of 2020 3
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
Conciliation Act, 1996 (Arbitration Act), against the judgment dated
26.12.2019 (impugned judgment) passed by the learned
Commercial Court, East Sikkim, at Gangtok (the Commercial Court)
in Arbitration Case No. 05 of 2017, preferred under section 34 of the
Arbitration Act by Sikkim Power Development Corporation Ltd.
(SPDC) and the State of Sikkim (SoS) – the appellants in Arbitration
Appeal No. 1 of 2020.
1.(ii) On 30.09.2017, the Sole Arbitrator had passed the
Award (the Award) on all the 35 issues framed by it. The Sole
Arbitrator granted all the prayers, except prayer [H] in favour of
Amalgamated Transpower (India) Limited (ATPL) . The total amount
awarded against prayers [F], [G] & [I] is ₹4,40,55,44,212/- (Rupees
four hundred and forty crores, fifty-five lakhs, forty-four thousand,
two hundred and twelve only) along with prayers [A], [B] and [C]
and alternatively, if prayers [A], [B] and [C] are not discharged by
the respondents, an award of ₹10,95,22,00,945/- (Rupees one
thousand ninety-five crores, twenty-two lakhs, nine hundred and
forty-five only) as against prayers [D] & [G]. The Sole Arbitrator has
awarded the aforesaid sums along with interest thereon @15% till
the pronouncement of Award, i.e., 30.09.2017. The Sole Arbitrator
further awarded simple interest @18% per annum from the date of
award till the date of payment. The Sole Arbitrator further awarded
a sum of ₹41.07 lakhs towards costs along with interest @15% per
annum from the date of award till date of payment.
1.(iii) In Arbitration Appeal No.1 of 2020, SPDC and the SoS
have challenged the impugned judgment of the Commercial Court to
the extent it upheld the Award and prayed for setting it aside.
Arb. A. No.1 of 2020 4
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
1.(iv) Amalgamated Transpower (India) Limited (ATPL) — the
appellant in Arbitration Appeal No. 1 of 2021 — is also aggrieved by
the impugned judgment. ATPL has challenged the impugned
judgment to the extent it has set aside the findings of the Sole
Arbitrator with respect to issues no. 9, 20 and 11.
1.(v) Issue no.9 was whether ATPL, in the alternative to
prayers [A], [B] and [C] was entitled to an award of damages in its
favour for a sum of ₹418.50 crores.
1.(vi) Issue no.20 was whether prayer [D] could be
maintained without sufficient pleading.
1.(vii) Issue no.11 was whether ATPL was entitled to damages
for a sum of ₹49.66 crores, as claimed in prayer [F].
1.(viii) The Sole Arbitrator held that prayer [D] was a claim for
compensation for damages to be paid by SPDC and the SoS for non-
adherence to prayers [A], [B] and [C] and allowed the same to have
effect upon their failure to adhere to the said prayers. The Sole
Arbitrator also held issues nos.20 and 11 in favour of ATPL.
1.(ix) On 28.12.2017, SPDC and the SoS filed an application
under section 34 of the Arbitration Act against ATPL aggrieved by
the Award. ATPL didn‘t challenge the Award although it did not grant
prayer [H].
Genesis of the dispute
2.(i) On 22.12.1998, a tender was floated by SPDC inviting
bids for construction of Hydro Electric Power Projects (HEPs) on 100
percent debt financing basis. ATPL submitted its bid on 05.01.1999,
which was accepted. SPDC issued letter of intent on 11.03.1999 for
Arb. A. No.1 of 2020 5
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
setting up the HEPS of different capacities for a total cost of ₹275
crores on 100 percent debt financing basis.
2.(ii) An Agreement dated 18.04.1999 (the First Agreement)
was entered between SPDC, the SoS and ATPL, to initially develop
four HEPs (Rolep-I - proposed to be 9 MW capacity , Rolep-II -
proposed to be 12 MW capac ity, Ralong - proposed to be 16 MW
capacity and Chakungchu - proposed to be 24 MW capacity ) of
varying capacities through debt financing and implementation
schemes in the State of Sikkim as run of the river schemes. A
significant clause in the First Agreement, being clause 10, reads as
follows:-
―10. Any variation in this Agreement or to any of the Appendices
can be done subject to the parties duly signing any supplementary
Agreement to be referred as addendum to this Agreement .‖
2.(iii) On 03.07.1999, the SoS gave an unconditional and
irrevocable guarantee for repayment of the principal amount and
interest thereon and raised an amount of ₹50.01 crores as bond
amount against the guarantee.
2.(iv) On 22.01.2002, SPDC and the SoS moved a proposal
for allotment of the projects to ATPL on Build Own Operate and
Transfer (BOOT) basis for an initial period of 35 years to be renewed
on mutually agreed terms and conditions. ATPL was required to give
Bank Guarantee to take over the borrowings made by SPDC.
2.(v) On 21.12.2002, another agreement (the Second
Agreement) was executed which superseded the First Agreement.
This Agreement also contained a similar and significant clause, as
Arb. A. No.1 of 2020 6
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
stated in paragraph 2(ii) hereinabove. This clause, being clause 25,
reads as follows:-
―25. Any variation or amendment to this Agreement can be done
subject to the parties duly signing any Supplementary Agreement to
be referred as addendum to this Agreement.‖
2.(vi) Admittedly, simultaneously with the execution of the
Second Agreement, ownership of all the three (now revised) HEPs
(Rolep – 36 MW, Ralong – 40 MW and Chakungchu -50 MW) were
transferred to ATPL. On 19.02.2003, reconciliation of accounts in
terms of the Second Agreement took place. It reflects that the SoS
had paid interest of ₹21,37,77,543/- (Rupees twenty-one crores,
thirty-seven lakhs, seventy-seven thousand, five hundred and forty-
three only), on the bonds.
2.(vii) The reconciliation of accounts signed by the parties also
accepts the fact that expenditure incurred by SPDC as per the
Second Agreement was verified by the parties. It endorsed and
accepted that the reconciliation of accounts in terms of the Second
Agreement would be an addendum to it.
2.(viii) SPDC gave their confirmation of the expenditure
incurred by SPDC and the SoS towards the three HEPs on
02.09.2003 amounting to ₹85.35 crores as per details attached
therewith.
2.(ix) Admittedly and significantly, however, no Detailed
Project Reports (DPRs) were submitted by ATPL for any of the three
HEPs, namely, Rolep, Ralong and Chakungchu within a period of 6
(six) months, as per agreement entered into by and between the
parties. Subsequently, it transpires that ATPL submitted a single
DPR for Rolep HEP for 36 MW after which techno -economic
Arb. A. No.1 of 2020 7
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
clearance was granted by the SoS on 06.05.2003 with a clear
understanding that the proposed capacity could be modified based
on bankable final optimization study. Admittedly, the estimated
installed capacity was later enhanced to 60 MW. However, no fresh
DPR for the enhanced capacity of Rolep was ever submitted by ATPL
at any subsequent point of time. Nor was any DPR ever submitted
subsequently in respect of the two other HEPs, namely, Ralong HEP
and Chakungchu HEP. On the basis of the preliminary DPR of Rolep
HEP, as submitted by ATPL, the SoS granted lease of 10.796
hectares of land at the Rolep site vide lease deed dated 29.05.2004.
However, admittedly again, the lease rent of ₹10,000/- per annum
has not been paid by ATPL, till date.
2.(x) There were several review meetings held by the then
Chief Secretary from time to time. During the course of hearing of
this matter, our attention was drawn to the minutes of the meetings
held on 21.08.2003, 14.11.2003, 09.03.2004, 26.04.2004,
23.07.2004, and 15.10.2004. These meetings discus sed the
progress of the project and sought to clear the bottlenecks. None of
the minutes of the meetings records the intention of the parties to
amend the Second Agreement nor was the Second Agreement ever
amended in terms of clause 25. The minutes of the meeting held on
09.03.2004 and 15.10.2004 also records the presence of a third
party, namely, Larsen and Toubro Limited (L&T), who was never
made a party before the Sole Arbitrator at any point of time.
2.(xi) The record reveals that an attempt was made to work
out an addendum to amend and restate the Second Agreement .
Although correspondences were exchanged between the parties, no
Arb. A. No.1 of 2020 8
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
such addendum was ever signed by and between the parties in
terms of clause 25 of the Second Agreement.
2.(xii) On 22.06.2006, SoS issued a final notice to ATPL. The
notice stated that the delay and the mounting pressure from bond
holders had compelled the SoS to take certain decisions. ATPL was
thus required to redeem the bond liability of Rs.50.01 crores,
including interest, by 31.07.2006. The notice also sought response
from ATPL confirming the redemption to be communicated to the
Managing Director, SPDC, by 10.07.2006. The notice informed ATPL
that failure to redeem the bond liability would lead to termination of
the Second Agreement and all three HEPs awarded to ATPL would
stand withdrawn without any further notice, leaving the SoS free to
award the projects to interested dev elopers. The notice further
sought for refund of the excess payment drawn by ATPL against
raising of bonds and the advance drawn by ATPL towards
construction of roads for Rolep HEP. The notice also sought a written
confirmation from ATPL agreeing to the redemption of the bonds to
reach SPDC by 10.07.2006, to be followed by total redemption of
Rs.50.01 crores by 31.07.2006 to the bond holders. It would be an
assumed indicator of ATPL‘s seriousness in developing the projects.
2.(xiii) On 02.05.2008, the SoS wrote to ATPL terminating the
Second Agreement considering the failure of ATPL to abide by its
terms and conditions and the delay in the implementation of the
project. Finally, the dispute was referred to arbitration. The Hon‘ble
Supreme Court appointed the Sole Arbitrator on 05.12.2011.
Arb. A. No.1 of 2020 9
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
The proceedings before the Sole Arbitrator and the
Commercial Court
3. ATPL filed its statement of claims on 08.06.2012. On
09.09.2012, SPDC and SoS filed their statement of defence and
counter claim. ATPL filed its rejoinder on 24.11.2012. SPDC and the
SoS filed their replication on 08.06.2013 and ATPL its sur-rejoinder
on 24.08.2013. The Award was passed on 13. 09.2017. SPDC and
SoS, thereafter, filed an application under section 34 of the
Arbitration Act challenging the Award before the Commercial Court.
The Commercial Court passed the impugned judgment on
26.12.2019.
The Award
4.(i) The Sole Arbitrator granted all the prayers in favour of
ATPL, except prayer [H]. While granting prayer [A], the Sole
Arbitrator directed SPDC and the SoS to perform all its obligations
under the Second Agreement in a time bound manner. It further
directed SPDC and the SoS, as agreed in the meeting dated
15.10.2004, to provide land, required access roads and bridges for
the three HEPs within a specific time-frame. The Sole Arbitrator
awarded perpetual injunction against SPDC and the SoS and
directed them not to deal with the three HEPs contrary to the
Second Agreement in terms of prayer [B]. The Sole Arbitrator
awarded mandatory injunction in favour of ATPL directing SPDC and
the SoS to allow the three HEPs to be implemented by ATPL in terms
of prayer [C]. Having granted all the three prayers [A], [B] and [C]
in favour of ATPL, the Sole Arbitrator went on to award the
alternative prayer [D] on the condition that it shall have effect upon
Arb. A. No.1 of 2020 10
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
failure of the respondent to adhere to prayers [A], [B] and [C].
ATPL, however, had specifically prayed for grant of damages under
prayer [D] only if the Sole Arbitrator did not grant prayers [A], [B]
and [C].
4.(ii) The Sole Arbitrator while deciding issue no.2 found that
there was no provision under the Second Agreement permitting its
termination unilaterally by the SoS; that SPDC, which was a
separate legal entity, had not taken a decision to terminate the
Second Agreement; that SoS had not issued any show cause notice
before issuance of letter dated 02.05.2008, in violation of the rules
of natural justice; that the ground of delay by ATPL was not justified
as it was SPDC and SoS who had continuously de ferred the
performance of its obligation to provide land and access road
without which the construction work of the projects could not start;
that the letter dated 02.05.2008 was issued with mala fide intention
and ulterior motive.
4.(iii) While deciding issues nos. 3, 22 and 23, the Sole
Arbitrator held that the Second Agreement regarding submission of
bank guarantee by ATPL was modified by the minutes of the
meeting dated 09.03.2004 and 26.04.2004. Sole Arbitrator also held
that in the minutes of the meeting dated 15.10.2004, further major
changes took place in terms of the Second Agreement. It was held
that the parties to the joint meeting dated 09.03.2004, 26.04.2004
and 15.10.2004 decided to modify their respective obligations and
SPDC and the SoS had signed these minutes on their own free will.
The Sole Arbitrator found that SPDC and the SoS had the right to
modify the terms of the agreement under section 63 of the Indian
Arb. A. No.1 of 2020 11
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
Contract Act, 1872. The Sole Arbitrator held that ATPL was no
longer required to provide bank guarantee till SPDC and the SoS
provided entire land record for Rolep and Chakungchu project in
view of the agreement between the parties in the meeting held o n
09.03.2004 and 26.04.2004. It was further held that since the land
was not provided by SPDC and the SoS, the feasibility of submitting
any bank guarantee by ATPL did not arise and subsequently after
the decision of the parties in the meeting held on 15.10.2004, the
responsibility to repay the bond holder was taken over by the SoS
and consequently, the question of ATPL providing bank guarantee
did not arise.
4.(iv) While deciding issues nos. 4 and 28, the Sole Arbitrator
concluded that it was not necessary to decide whether the Second
Agreement was in the nature of BOO or BOOT arrangemen t. It also
held that the SoS had transferred the ownership of the three HEPs
to ATPL.
The impugned judgment rendered by the Commercial Court
5.(i) The opinion of the Sole Arbitrator that M/s Rolep Hydro
Electric Power Co. Ltd. and Velankani Renewable Energy Pvt. Ltd.
were not necessary parties was upheld by the Commercial Court.
5.(ii) The opinion of the Sole Arbitrator that neither the letter
dated 22.06.2006 nor the letter dated 02.05.2008 had the effect of
terminating the Second Agreement was also upheld.
5.(iii) The Commercial Court upheld the view of the Sole
Arbitrator that the minutes of meeting dated 09.03.2004,
26.04.2004 and 15.10.2004 modified the Second Agreement and
Arb. A. No.1 of 2020 12
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
they were in the nature of addendum and supplement al to the
Second Agreemen t. It was held that clause 25 of the Seco nd
Agreement did not disentitle the parties to amend it.
5.(iv) Contrary to the findings of the Sole Arbitrator, it was
held that the recital in the Second Agreement makes it clear tha t
the parties had in fact agreed to do the project on BOOT basis and
the terms of the Second Agreement was clear and unambiguous.
5.(v) The Commercial Court also upheld the view of the Sole
Arbitrator that SPDC and SoS had failed to perform their part of the
promise as per the minutes of the meeting dated 09.03.2004,
26.04.2004 and 15.10.2004 and relinquished their claim for bank
guarantee from ATPL; as such there was no question of breach on
the part of ATPL.
5.(vi) The Commercial Court upheld the grant of specific
performance in favour of ATPL by the Sole Arbitrator. However, it
was held that since ATPL had itself sought damages in the
alternative to specific performance, the Sole Arbitrator exceeded the
scope of its jurisdiction in awarding both damages as well as specific
performance of the Second Agreement. It was also held that the
Sole Arbitrator had committed patent illegality while doing so. It was
held that when a party claims specific performance or damages in
the alternative, it is always entitled to elect between the two
remedies.
5.(vii) The Commercial Court set aside the Sole Arbitrator‘s
finding on issues no. 9 and 20 while maintaining the findings on
issue no.6. The Award, to the extent it granted damages, was set
aside, being patently illegal and unjust.
Arb. A. No.1 of 2020 13
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
5.(viii) The Commercial Court also set aside the reasoning and
findings of the Sole Arbitrator on issue no.11, which awarded further
damages even for the expenses incurred in executing various works
by ATPL in performance of its obligation to develop the project prior
to the issuance of letter dated 02.05.2008 by the SoS as being
patently illegal and unjust. It was held that those expenses incurred
by ATPL were incurred in performance of its part of the Second
Agreement. Since SPDC and SoS are required to now perform their
part of the Second Agreement they could not be obliged to incur the
expenses which ATPL was required to incur under the Second
Agreement.
5.(ix) Accordingly, the Commercial Court partly allowed the
petition under section 34 of the Arbitration Act preferred by SPDC
and SoS.
The Second Agreement
6.(i) The Second Agreement signed between SPDC, the SoS
and ATPL on 21.12.2002, acknowledged that subsequent to the First
Agreement, parties performed various obligations and
responsibilities and that it was understood that the ownership of the
projects was to be transferred to ATPL, who would develop, own and
operate the projects on BOOT basis and not on debt financing and
implementation scheme as agreed earlier.
6.(ii) SPDC, the SoS and ATPL agreed that the Second
Agreement would supersede the First Agreement.
6.(iii) They also agreed that the project would consist of Rolep,
Ralong and Chakungchu with 36 MW, 40 MW and 50 MW ,
Arb. A. No.1 of 2020 14
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
respectively, as estimated installed capacity. They agreed that ATPL
shall operate these projects on BOOT basis for a period of 35 years
to be renewed for another 35 years on mutually agreed terms.
6.(iv) They agreed under clause 25 that any variation or
amendment to the Second Agreement could be done subject to the
parties duly signing any supplementary agreement, which was to be
referred as addendum to the Second Agreement . For convenience,
clause 25 is again reproduced hereinbelow:-
―25. Any variation or amendment to this Agreement can be done
subject to the parties duly signing any Supplementary Agreement to
be referred as addendum to this Agreement.‖
6.(v) They made it clear that the Second Agreement sets forth
the entire understanding between the parties relating to the subject
matter and superseded all other prior agreements an d
understanding.
6.(vi) ATPL clearly agreed to take over the responsibilities of
payment of bond amount to the extent of ₹50.01 crores; interest
already paid @ 13.75%; and interest @12.4 5% to be paid half
yearly after reconciliation of accounts. ATPL also agreed to furnish
bank guarantee for the said amounts within a period of 12 month s
of signing of the Second Agreement.
6.(vii) The Second Agreement recorded that ATPL had taken
over the responsibility of repayment of the bond and interest
thereon on the understanding that the ownership of the projects
was transferred to ATPL.
6.(viii) It was agreed that the balance amount of the money
raised (₹50.01 crores) lying with SPDC and the SoS was to be
Arb. A. No.1 of 2020 15
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
released to ATPL against equal amount of bank guarantee to be
submitted by ATPL.
6.(ix) SoS was required to provide land on lease of 99 years to
ATPL immediately upon identification of such land jointly by ATPL
and SoS. The annual lease rent was quantified at ₹10,000/- per
annum, till the projects were with ATPL.
6.(x) SPDC and the SoS, at their cost, were to provide access
roads to the major structures of the project as required by ATPL.
6.(xi) SPDC and the SoS were required to complete land
acquisition, transfer it to ATPL and also construct access roads to
major structures of the projects after confirmation by ATPL
regarding required roads and bridges.
6.(xii) ATPL was required to give their confirmation (details of
roads and bridges) within six months of signing of the agreement.
6.(xiii) In case SPDC and the SoS gave consent to ATPL to bear
the cost of roads and bridges and commit ted to complete them
within reasonable specified time to enable ATPL to complete the
projects on time, only then ATPL was required to submit the DPRs
for these projects within six months thereafter.
6.(xiv) ATPL was to obtain clearances and approvals from
various agencies and organisations of the Government of Sikkim
including clearances from the State Forest, Environment and
Pollution Control Boards, etc., which were to be facilitated by SPDC
and the SoS. Similarly, ATPL was also required to obtain clearances
and approvals from Government of India and other agencies o utside
Sikkim, and SPDC and SoS were to provide the necessary
assistance.
Arb. A. No.1 of 2020 16
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
6.(xv) ATPL was to provide the SoS 12% of total electricity
generated, after deduction of auxiliary consumption and
transformation losses free of cost for the first 15(fifteen) years from
the date of commencement of commercial production and thereafter
from the 16
th
year, 15% of the total electricity generated after
deduction of auxiliary consumption and transformation losses from
each of the projects or money equivalent thereof.
6.(xvi) ATPL was also required to give SoS from the year
following one year of commencement of commercial production , 2%
from their annual net profit of each of these projects, which could be
enhanced commensurate with higher power generation and
increased profit.
6.(xvii) Clause 24 of the Second Agreement is reproduced
hereinbelow:-
―24. The First Party and the Second Party shall have the right to
carry out the survey and investigation/explore/execute any river valley
schemes in the upstream as well as d ownstream of the projects,
except those permitted under this agreement, without detriment to the
Projects mentioned in this Agreement including their operation,
generation, etc. The Third Party shall not have any claim over
generation from any other projects existing and being envisaged in the
upstream/downstream of the three projects, except those permitted
under this Agreement. In case, construction of approach roads
including bridges to major structures of Ralong and/or Chakungchu
HEPs involve very long time and high cost; or get resistance from
Forest and Environment Department of the State/Central
Governments; and if their clearances take considerable time; or these
two projects, after detail geo-technical investigation, are found to be
techno-economically unviable to make the arrangements under this
Agreement viable the First Party and the Second party shall
immediately allot one or more projects of similar sizes downstream of
Ralong and Rolep Projects to be selected by t he Third Party, where
such road works will involve less time and cost, in favour of the Third
Party on the similar terms and conditions as mentioned in this
Agreement.‖
Submission of the parties
7. Mr. Jishnu Saha, learned Senior Advocate, representing
SPDC and the SoS, relying upon the provisions of sections 34 and
Arb. A. No.1 of 2020 17
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
37 of the Arbitration Act and the opinions expressed by the Hon‘ble
Supreme Court on those provisions from time to time submitted that
the learned Commercial Court had failed to appreciate that the
Award was vitiated on various other grounds besides those which
were upheld by the Commercial Court holding that it amounted to
the Sole Arbitrator committing patent illegality. He submitted that
the Sole Arbitrator went beyond the terms of the Second Agreement
and granted reliefs which were not even sought for by ATPL; that
the Award was in conflict with the public policy of India as it was in
contravention to the fundamental policy of Indian law and also in
conflict with the most basic notions of morality or justice; that the
Award was vitiated by patent illegality appearing in the face of the
Award. Mr. Saha pointed out that the Award reflects non-application
of judicial mind inasmuch as the Sole Arbitrator passed the Award
beyond what was even claimed by ATPL. It was argued that the Sole
Arbitrator had passed the Award in violation of sections 16, 21(1)
and (2) of the Specific Relief Act, 1963. He also submitted that in
respect of the three (3) HEPs, not a brick or a stone was laid by
ATPL and as such, the Award carrying a fantastic sum, will shock the
conscience of the Court.
8. Mr. P. K. Das, as representative of ATPL, sought to
defend the Award and challenge that part of the impugned judgment
rendered by the Commercial Court , which held that some parts of
the Award were patently illegal. He argued that in view of the
admission of SPDC and the SoS, in reply to the claim petition
regarding the relevant time for submission of DPRs , no issue was
framed by the Sole Arbitrator. It is the case of ATPL that there is no
Arb. A. No.1 of 2020 18
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
statutory provision to support the submission of SPDC and the SoS
that until DPRs were submitted by ATPL, their obligation to provide
land, access roads and bridges would not commence. The finding of
the Sole Arbitrator regarding issues no. 21, 30 and 31 remained
unassailed. He argued that the reason for not laying a single brick or
stone for any of the HEPs is attributable to the failures of SPDC and
the SoS and not ATPL. He argued that SPDC and the SoS had clearly
admitted in their appeal that the Second Agreement was not
determinable in response to the finding in the Award that their
counter claim was barred by limitation. He submitted that the
finding of the Sole Arbitrator on issues nos. 26 and 27 has been
upheld in the impugned judgment which has not been challenge d in
their appeal by SPDC and SoS. Various grounds taken in the appeal
preferred by SPDC and the SoS were neither taken before the Sole
Arbitrator nor before the Commercial Court. The terms of the
Second Agreement w ere modified by the minutes of the meeting
dated 09.03.2004, 26.04.2004 and 15.10.2004. The Award is not
patently illegal as the Sole Arbitrator had examined each of the
issues and rendered his findings on each of them, most of which
remains unassailed. The appeal of SPDC and the SoS is an
assortment of contradictory pleas which are liable to be rejected.
With regard to the grant of ₹265.10 crores by the Sole Arbitrator in
the claim of ATPL for damages of ₹120 crores only, Mr. Das
submitted that the Sole Arbitrator had considered the cost
escalation from the date of termination, i.e., 02.05.2008, till the
filing of the claim petition, i.e., 02.05.2012, on civil costs as per
CEA/CWC norms. It was further argued that the calculation of price
Arb. A. No.1 of 2020 19
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
escalation as provided by ATPL as annexure ‗A‘ to their replication
remain unassailed by SPDC and the SoS. Thus, SPDC and the SoS
were precluded from challenging it before this Court. With regard to
the Sole Arbitrator awarding more than what was claimed for, Mr.
Das submitted that even if the Award is considered as perverse on
that ground, the same did not go to the root of the matter and
therefore the entire Award could not be set aside.
The relevant provisions of the Arbitration & Conciliation Act,
1996
9. Sections 34 and 37 of the Arbitration Act, to the extent
relevant, are set out hereunder:-
―34. Application for setting aside arbitral award . — (1)
Recourse to a Court against an arbitral award may be made only
by an application for setting aside such award in accordance with
sub-section (2) and sub-section (3).
(2) An arbitral award may be set aside by the Court only if —
(a) the party making the application furnishes proof that—
…………………………… ……………………………………………………………………..
(iv) the arbitral award deals with a dispute not contemplated by
or not falling within the terms of the submission to arbitration, or
it contains decisions on matter beyond th e scope of the
submission to arbitration:
Provided that, if the decisions on matters submitted to
arbitration can be separated from those not so submitted, only
that part of the arbitral award which contains decisions on
matters not submitted to arbitration may be set aside; or
………………………… …………………………………………………………………………
(b) the Court finds that —
…………………………… ……………………………………………………………………..
(ii) the arbitral award is in conflict with the public policy of India.
[Explanation 1.- For the avoidance of any doubt, it is clarified
that an award is in conflict with the public policy of India, only if,
—
(i)The making of the award was induced or affected by fraud or
corruption or was in violation of section 75 or section 81; or
(ii)it is in contravention with the fundamental policy of Indian
law; or
(iii)it is in conflict with the most basic notions of morality or
justice.]
[Explanation 2. – For the avoidance of doubt, the test as to
whether there is a contravention with the fundamental policy of
Indian law shall not entail a review on the merits of the dispute.]
(2A) An arbitral award arising out of arbitrations other than
international commercial arbitrations, may also be set aside by
the Court, if the Court finds that the award is vitiated by patent
illegality appearing on the fact of the award:
Arb. A. No.1 of 2020 20
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
Provided that an award shall not be set aside merely on the
ground of an erroneous application of the law or buy
reappreciation of evidence.]
…………………………………………………………………………………… …………………
x x x
37. Appealable orders. - (1) An appeal shall lie from the
following orders (and from no others) to the Court authorized by
law to hear appeals from original decrees of the Court passing
the order, namely:-
………………………………………… ………………………………………… …………….
(c) setting aside or refusing to set aside an arbitral award under
section 34.
…………………………………………………………………………………… …………...‖
Law laid down by the Hon’ble Supreme Court
Renusagar Judgment
10.(i) The Hon‘ble Supreme Court in Renusagar Power Co. Ltd.
vs. General Electric Co.
1
, construed the term ―public policy‖ under
section 7(1)(b)(ii) of the Foreign Awards (Recognition and
Enforcement) Act, 1961, and held that an award contrary to (i) the
fundamental policy of Indian law; or (ii) the interests of India; or
(iii) justice or morality; would be set aside on the ground that it
would be contrary to the public policy of India.
Scope of Section 34 of the Arbitration & Conciliation Act, 1996
10.(ii) In Oil & Natural Gas Corporation Ltd. vs. Saw Pipes Ltd.
2
,
the Hon‘ble Supreme Court construed the expre ssion, ―the public
policy of India‖ contained in section 34(2)(b)(ii) of the Arbitration
Act, 1996 and held that award could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or (b) the interest of India; or
(c) justice or morality; or (d) in addition, if it is patently illegal. It
1
(1994) Supp (1) SCC 644
2
(2003) 5 SCC 705
Arb. A. No.1 of 2020 21
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
was also held that the illegality must go to the root of the matter
and if the illegality is of trivial nature it cannot be held that award is
against the public policy. Award could be set aside if it is so unfair
and unreasonable that it shocks the conscience of the Court. Such
award is opposed to public policy and is required to be adjudged
void.
10.(iii) The Hon‘ble Supreme Court in McDermott International
Inc. vs. Burn Standard Co. Ltd. & Others
3
held that the Arbitration Act
makes provision for the supervisory role of Courts for the review of
the arbitral award only to ensure fairness. Intervention of the Court
is envisaged in few circumstances only; like, in case of fraud or bias
by the arbitrators, violation of natural justice, etc. The Court cannot
correct errors of arbitrators. It can only quash the award leaving the
parties free to begin arbitration if it is desired. So, the scheme of the
provision aims at keeping the superv isory role of the Court at
minimum level and this can be justified as parties to the agreement
make a conscious decision to exclude the Court‘s jurisdiction by
opting for arbitration as they prefer the expediency and finality
offered by it. The Hon‘ble Supreme Court also examined judgments
of various High Courts and thereafter concluded that there can be
no doubt that given the law laid down by it, section 34 of the
Arbitration Act cannot be held to include within it a power to modify
an award. The jurisdiction of the Court and the scope of Section 34
of the Arbitration Act is thus sufficiently clear.
3
(2006) 11 SCC 181
Arb. A. No.1 of 2020 22
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
10.(iv) In Associate Builders vs. Delhi Development Authority
4
, the
Hon‘ble Supreme Court examined section 34 of the Arbitration Act
and the various judgments rendered and went on to explain the
various grounds available in interfering with arbitral awards.
Disregarding orders of Superior Courts in India as well as the
binding effect of the judgment of the Superior Court was considered
as being contrary to the fundamental policy of Indian law. It was
also held that equally important and fundamental to the policy of
Indian law is the principle that a Court and so also a quasi-judicial
authority must, while determining the rights and obligations of
parties before it, do so in accordance with the principles of natural
justice. Non-application of mind is a defect that is fatal to any
adjudication. A decision which is perverse or so irrational that no
reasonable person would have arrived at the same will not be
sustained in a Court of law. Judicial approach ensures that authority
acts bona fide and deals with the subject in a fair, reasonable and
objective manner and that its decision is not actuated by any
extraneous consideration. Judicial approach in that sense acts as a
check against flaws and faults and can render the decision of a
Court, tribunal or authority vulnerable to challenge. It was held that
the juristic principle of a judicial approach demands that a decision
be fair, reasonable and objective. On the obverse side, anything
arbitrary and whimsical would obviously not be a determination
which would either be fair, reasonable or objective. It was also held
that it was neither necessary nor proper to attempt an exhaustive
4
(2015) 3 SCC 49
Arb. A. No.1 of 2020 23
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
enumeration of what constitutes the fundamental policy of Indi an
law nor is it possible to place the expression in the straightjacket of
a definition. The Hon‘ble Supreme Court also explained the next
ground on which an award may be set aside, i.e., that it is contrary
to the interest of India and held that this ground is to evolve on a
case to case basis. The Hon‘ble Supreme Court held that the third
ground of public policy is, if an award is against justice or morality.
The fourth ground available according to the Hon‘ble Supreme Court
was patent illegality. It was held that contravention of substantive
law of India would result in the death knell of an arbitral award. It
was explained that such illegality must go to the root of the matter
and cannot be of trivial nature. A contravention of the Arbitration
Act itself would be regarded as patent illegality. Contravention of
section 28(3) of the Arbitration Act was also held to be the third
subhead of patent illegality. The Arbitral Tribunal is required to
decide in accordance with the terms of the contract and shall take
into account the usages of the trade applicable to the transaction. A
caveat, however, cautioned that if an arbitrator construes a term of
the contract in a reasonable manner, it will not mean that the award
can be set aside on this ground. Construction of the terms of the
contract is primarily for an arbitrator to decide unless the arbitrator
construes the contract in such a way that it could be said to be
something that no fair minded or reasonable person would do. It is
settled law that where a finding is based on no evidence, or an
Arbitral Tribunal takes into account something irrelevant to the
decision which it arrives at; or ignores vital evidence in arriving at
his decision, such decision would necessarily be perverse. The next
Arb. A. No.1 of 2020 24
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
ground on which an award may be set aside is that it is contrary to
the interest of India which concerns itself with India as a member of
the world community in its relation with foreign power. The third
ground of public policy is, if an award is against justice or morality.
An award can be said to be against justice only when it shocks the
conscience of the Court. It was also held patent illegality as a
principle contains three sub-heads, i.e., contravention of substantive
law of India, contravention of the Arbitration Act and contravention
of the terms of the contract.
10.(v) In Maharashtra State Electricity Distribution Co. Ltd. vs.
Datar Switch Gear Ltd. & Others
5
, the Hon‘ble Supreme Court had held
that a Court hearing a section 34 petition does not sit in appeal.
10.(vi) In Ssangyong Eng ineering & Construction Co. Ltd. vs.
National Highways Authority of India ( NHAI)
6
, the Hon‘ble Supreme
Court explained that under the guise of interfering with an award on
the ground that the arbitrator has not adopted a judicial approach,
the Courts cannot intervene on the merits of the award . It also
clarified that violation of principles of natural justice would continue
to be a ground for challenge of an award. The Hon‘ble Supreme
Court explained that the ground for interference on the basis that
the award is in conflict with justice and morality is to be understood
as a conflict with the ―most basic notions of morality or justice
and it is only such arbitral award that shock s the conscience
of the Court that can be set aside on this ground.‖ It was also
opined that patent illegality appearing on the face of the award
5
(2018) 3 SCC 133
6
(2019) 15 SCC 131
Arb. A. No.1 of 2020 25
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
which refers to such illegality as goes to the root of the matter but
which does not amount to mere erroneous application of the law
may also be a ground of challenge. Re-appreciation of evidence was
held not permissible under the ground of patent illegality appearing
on the face of the award. A mere contravention of the substantive
law of India, by itself, is no longer a ground available to set aside an
arbitral award. However, if the arbitrator gives no reason for an
award and contravenes section 31(3) of the Arbitration Act, that
would certainly amount to patent illegality on the face of the award.
It was held that the construction of the terms of a contract is
primarily for an arbitrator to decide, unless the arbitrator construes
the contract in a manner that no fair minded or reasonable person
would; in short, that the arbitrator‘s view is not even a possible view
to take. Also if the arbitrator wanders outside the contract and deals
with matters not allotted to him, he commits an error of jurisdiction.
This ground of challenge will now fall within the new ground added
under section 34(2-A). A finding based on no evidence at all or an
award which ignores vital evidence in arriving at his decision would
be perverse and liable to be set aside on the ground of patent
illegality. Additionally, a finding based on documents taken behind
the back of the parties by the arbitrator would also qualify as a
decision based on no evidence in as much as such decision is not
based on evidence led by the parties, and therefore, would also
have to be characterised as perverse.
Arb. A. No.1 of 2020 26
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
10.(vii) The Hon‘ble Supreme Court in MMTC Ltd. vs. Vedanta Ltd.
7
held that a section 34 proceedings does not contain any challenge
on the merits of the award.
10.(viii) In PSA Sical Terminals Pvt. Ltd. Vs. Board of Trustees of V.O.
Chidambranar Port Trust Tuticorin and Others
8
, the Hon‘ble Supreme
Court held that it is more than settled legal position that in an
application under section 34, the Court is not expected to act as an
Appellate Court and re-appreciate the evidence. The scope of
interference will be limited to grounds provided under section 34 of
the Arbitration Act. The interference would be so warranted when
the award is in violation of ―public policy of India‖, which has been
held to mean, ―the fundamental policy of Indian law‖. A judicial
intervention on account of interfering on the merits of the award
would not be permissible. However, the principles of natural justice
as contained in section 18 and 34(2)(a)(iii) of the Arbitration Act
would continue to be the ground s of challenge of an award. The
ground for interference on the basis that the award is in conflict with
justice or morality is now to be understood as a conflict with the
―most basic notions of morality or justice ‖. It is only such
arbitral award that shocks the conscience of the Court that can be
set aside on the said ground. An award would be set aside on the
ground of patent illegality appearing on the face of the award and as
such, which goes to the roots of the matter. However, an illegality
with regard to a mere erroneous application of law would not be a
ground for interference. Equally, re-appreciation of evidence would
7
(2019) 4 SCC 163
8
2021 SCC Online SC 508
Arb. A. No.1 of 2020 27
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
not be permissible on the ground of patent illegality appearing on
the face of the award. A decision which is perverse, though, would
not be a ground for challenge under ―public policy of India‖, would
certainly amount to a patent illegality appearing on the face of the
award. However, a finding based on no evidence at all or an award
which ignores vital evidence in arriving at its decision would be
perverse and liable to be set aside on the ground of patent illegality.
It was also held that to understand the test of perversity it would be
relevant to refer to paragraphs 31 and 32 from the judgment in
Associate Builders (supra).
10.(ix) In State of Chhattisgarh & Another vs. Sal Udyog Private
Limited
9
, the Hon‘ble Supreme Court explained what constitutes
patent illegality and held that when the arbitrator fails to decide
matters in accordance with the terms of contract g overning the
parties, it would attract patent illegality thereon.
10.(x) In Indian Oil Corporation Ltd. vs. Shree Ganesh Petroleum
Rajgurunagar
10
and Delhi Airport Metro Express Private Limited vs. Delhi
Metro Rail Corporation Limited
11
, the Hon‘ble Supreme Court
reiterated the restricted grounds on which only an award may be
interfered with and set aside.
Scope of section 37 of the Arbitration & Conciliatio n Act, 1996
11.(i) We shall now examine the jurisdiction and scope of
section 37 of the Arbitration Act. In Punjab State Civil Supplies
Corporation Ltd. and Another vs. Ramesh Kumar and Company and
9
(2022) 2 SCC 275
10
(2022) 4 SCC 463
11
(2022) 1 SCC 131
Arb. A. No.1 of 2020 28
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
Others
12
, the Hon‘ble Supreme Court held that the jurisdiction in a
first appeal arising out of a decree in a civil suit is distinct from the
jurisdiction of the High Court under section 37 of the Arbitration Act
arising from the disposal of a petition challenging an arbitral award
under section 34. It was held that the High Court was required to
determine as to whether the District Judge had acted contrary to the
provisions of section 34 of the Arbitration Act in rejecting the
challenge to the arbitral award.
11.(ii) In Haryana Tourism Ltd. vs. Kandhari Beverages Ltd.
13
, the
Hon‘ble Supreme Court held that the award can be set aside under
section 34/37 of the Arbitration Act, if the award is found to be
contrary to (a) fundamental policy of Indian law; or (b) the interest
of India; or (c) justice or morality; or (d) if it is patently illegal. It
also held that the High Court while deciding an appeal under section
37 cannot enter into the merits of the claim.
11.(iii) In Dr. A. Parthasarathy and Others vs. E. Springs Avenues
Pvt. Ltd. and others
14
, the Hon‘ble Supreme Court reiterated that
under section 37 of the Arbitration Act, the Court cannot remand the
matter to arbitrator for fresh decision unless it is consented by both
the parties following the law laid down in Kinnari Mullick vs.
Ghanshyam Das Dam ani
15
and I-Pay Clearing Services Pvt. Ltd. vs. ICICI
Bank Ltd.
16
. It held that only two options are available to the Court
considering the appeal under section 37 of the Arbitration Act. The
High Court may either relegate the parties for fresh arbitration or to
12
2021 SCC OnLine SC 1056
13
(2022) 3 SCC 237
14
(2022) SCC OnLine SC 719
15
(2018) 11 SCC 328
16
(2022) SCC OnLine SC 4
Arb. A. No.1 of 2020 29
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
consider the appeal on merits on the basis of the material available
on record within the scope and ambit of the jurisdiction under
section 37 of the Arbitration Act.
Consideration
12. ATPL had, in their claim petition, sought for the following
reliefs:-
“A] Pass an Award of Specific Performance in favour of the
Claimant Company and against the Opposite Parties thereby
enforcing the Terms of the Agreement dated 21.12.2002 and
thereby directing the Opposite parties to perform all their
obligations under the said Agreement in a time bound manner;
and
B] Pass an Award of Perpetual Injunction in favour of the
Claimant Company and against the Opposite Parties thereby
restraining the Opposite parties from dealing with the 3 Hydro
Electric Projects contrary to Agreement dated 21.12.2002; and
C] Pass an Award of Mandatory Injunction in favour of the
Claimant Company and against the Opposite parties thereby
directing the Opposite parties to implement the 3 Hydro Electric
Projects in terms of the Agreement dated 21.12.2002; or
D] In the alternative to prayer [A], [B] and [C], pass an Award of
Damages in favour of the Claimant Company and against the
Opposite Parties for a sum of ₹418.50 Crores; and
E] Pass an Award of Declaration in favour of the Claimant
Company and against the Opposite Parties declaring that the
letter of termination dated 02.05.2008 is illegal, malafide and
void and has no legal effect; and
F] Pass an Award of Damages in favour of the Claimant Company
and against the Opposite Parties for a sum of ₹496,689,279/-
(Rupees Forty Nine Crores Sixty Six Lakhs Eighty Nine Thousand
Two Hundred and Seventy Nine only) in terms of Paragraph 76 of
the Claim Petition; and
G] Pass an Award of Damages in favour of the Claimant
Company and against the Opposite Parties for a sum of
₹471,353,405/- (Rupees Forty Seven Crores Thirteen Lakhs Fifty
Three Thousand Four Hundred and Five only) in terms of
Paragraph 77 of the Claim Petition; and
H] Pass an Award of Damages in favour of the Claimant
Company and against the Opposite Parties for a sum of
₹1,080,000,000/- (Rupees One Hundred and Eight Crores) in
terms of Paragraph 78 of the Claim Petition; and
I] Award of Damages in favou r of the Claimant Company and
against the Opposite Parties for a sum of ₹1,200,000,000/-
(Rupees One Hundred and Twenty Crores) in terms of paragraph
79 of the Claim Petition; and
Arb. A. No.1 of 2020 30
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
J] Pass an Award of interest in favour of the Claimant Company
and against the Opposite Parties from the date of breach at the
rate of 18 per cent per annum; and
K] Pass an Award of cost of the instant arbitral proceedings in
favour of the claimant company and against the opposite parties;
and
L] Pass such other and further Award(s)/order(s) in favour of the
claimant company and against the opposite parties as this
Hon’ble Tribunal may deem fit and proper in the facts and
circumstances of the case.‖
13. The award of a fantastic sum as damages by the Sole
Arbitrator has caught our attention. That apart and in any event, the
conscience of this Court has been rudely shaken upon going through
the entire facts and circumstances of the instant case. Admittedly,
although the Second Agreement was signed in the year 2002 , till
date, not a single brick or stone has been laid by ATPL for any of the
three HEPs. It is ATPL‘s case that because of the defaults of SPDC
and the SoS, they had not been able to do so. A cursory glance of
the prayers quoted above reflects, however, that only prayer [F] for
damages for a sum of ₹496,689,279/- (Rupees forty-nine crores,
sixty-six lakhs, eighty-nine thousand, two hundred and seventy-nine
only), was the claim for actual expenditure. The claim of ATPL,
however, was that they had incurred total expenditu re of
₹220,278,098/- (Rupees twenty-two crores, two lakhs, seventy-
eight thousand and ninety-eight only), for field investigation and
survey, preparation of DPR, environmental studies, geo-technical
and geo-physical investigation, construction of temporary
structures, drilling on the river, gauge and discharge system and
cost of establishment, cost of site establishment and cost of
consultancy. This will appear from ATPL‘s claim petition itself.
Evidently, ATPL‘s claim as actual expenditure was only for
Arb. A. No.1 of 2020 31
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
preliminary works. As against the actual expenditure, admittedly
incurred by ATPL, t he Sole Arbitrator has awarded
₹4,40,55,44,212/- (Rupees four hundred and forty crores, fifty-five
lakhs, forty-four thousand, two hundred and twelve only), as award
of claim in prayer [F], [G] and [I] along with interest thereon and
₹10,95,22,00,945/- (Rupees one thousand ninety -five crores,
twenty-two lakhs, nine hundred and forty -five only), in the
alternative, if award [A], [B] and [C] are not discharged by SPDCL
and the SoS in favour of ATPL. Admittedly and significantly, all this
in the absence of any DPRs, save and except one DPR for the Rolep
HEP and that too, at the initial stage and limited to 36 MW.
Prayer [D]
14. The Commercial Court has held that the Sole Arbitrator
has committed patent illegality by awarding damages in terms of
prayer [D] of Rs.418.50 crores when ATPL itse lf has sought for it
only in the event the Sole Arbitrator did not award prayers [A],
[B] and [C] in his favour. Prayer [A] was for specific performance of
the Second Agreement. P rayer [B] was for award for perpetual
injunction restraining SPDC and the SoS from dealing with the three
HEPs contrary to the Second Agreement. Prayer [C] was for award
of mandatory injunction directing SPDC and the SoS to implement
the three HEPs in terms of the Second Agreement. The Sole
Arbitrator granted all the three prayers [A], [B] and [C] and
thereafter also decided to examine prayer [D] and granted it against
SPDC and the SoS, in case they failed to adhere to prayers [A], [B]
and [C]. In Associate Builders (supra), the Hon‘ble Supreme Court
Arb. A. No.1 of 2020 32
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
has held that an award can be said to be against justice only when it
shocks the conscience of the Court. The Hon‘ble Supreme Court
illustrated it by giving an example of a claimant being content with
restricting his claim to a particular amount in a statement of claim
before the arbitrator and at no point seeking anything more. The
arbitral award, however, awarded him much more than his claim
without any acceptable reason or justification. In the present case
as well, although the claim was precisely for grant of prayers [A],
[B] and [C] and if the Sole Arbitrator did not grant those prayers,
ATPL had sought for damages as claimed in prayer [D] as an
alternative, the Sole Arbitrator nevertheless went beyond the scope
of the prayers made by ATPL and granted prayer [D] without any
acceptable reason or justification even after granting prayers [A],
[B] and [C].
15. This part of the Award is also against section 21 of the
Specific Relief Act, 1963. When the Sole Arbitrator awarded specific
performance in terms of prayer [A], compensation could be granted
only on a finding that it was not sufficient to satisfy the justice of
the case. There was no such finding recorded by the Sole Arbitrator.
Further, the Sole Arbitrator could not have awarded compensation
unless ATPL had claimed such compens ation in its claim petition.
When, therefore, ATPL had sought for damages in terms of prayer
[D] as an alternative to non-grant of prayers [A], [B] and [C], the
Sole Arbitrator was not authorised or competent to even determine
the compensation sought for in prayer [D], leave alone grant the
same in the manner he did.
Arb. A. No.1 of 2020 33
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
16. Further, section 36 of the Arbitration Act provides for
enforcement of arbitral award in accordance with the provisions of
the Code of Civil Procedure, 1908, as if it were a decree of a Court.
When, thus, the Sole Arbitrator granted prayer [A] for specific
performance of Second Agreement — obviously, on the conclusion
that it could have been specifically performed — there was no need
for the Sole Arbitrator to ignore section 36 of the Arbitration Act.
The presumption that at some future stage, SPDC and S oS would
not be able to specifically perform and based on such presumption,
proceeding not only to determine the compensation payable on such
failure — but even going ahead to grant it — was grossly and
patently erroneous on part of the Sole Arbitrator.
17. The sole ground of determining prayer [D] that SPDC
and the SoS may not, in the future, specifically perform the
contract, therefore, is not an acceptable reason or justification. It is
held that the award of damages in terms of prayer [D] by the Sole
Arbitrator would squarely fall as one which is contrary to justice and
which shocks the conscience of this Court. The conclusion of the
Commercial Court setting the Award in terms of prayer [D] aside is
upheld.
Prayer [I]
18. Prayer [I] was a claim for damages for a sum of ₹120
crores for loss suffered towards cost escalation in the cost of three
HEPs with effect from 02.05.2008. The basis of this claim was that if
ATPL had to complete the project in accordance with the Second
Agreement, it would have been completed by 02.05.2008. According
Arb. A. No.1 of 2020 34
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
to ATPL, the cost of civil construction of the project was ₹4 crores
per MW which had escalated by 6% per annum from 02.05.2008 till
the date of construction. ATPL claimed that as on the date of the
claim, the total cost escalation caused due to failure of SPDC and
the SoS was ₹120 crores for 126 MW of the three HEPs. The Sole
Arbitrator granted ₹265.10 crores to ATPL for cost escalation
instead. The Sole Arbitrator completely ignored or lost complete
sight of the crucial fact that ATPL had not even laid a single brick or
stone for any of the projects or submitted the fundamental
requirement of DPRs for Chakungchu and Ralong HEPs till date for
the project to see even the light of day. By the same reasoning, as
held above, the grant of an award of damages of the sum of
₹265.10 crores, when ATPIL had sought for a specific sum of ₹120
crores only — in prayer [I] — as their claim for cost escalation,
necessarily requires to be set aside, being against the most basic
notions of justice and which shocks the conscience of the Court.
Prayer [A] – on the issue of specific performance
19. Prayer [A] sought specific performance of the Second
Agreement directing SPDC and the SoS to perform their obligations
under it. This prayer was not amended by ATPL. The Sole Arbitrator
framed issue no.6 to the effect whether ATPL is entitled to an award
of specific performance in its favour for enforcement of the Second
Agreement. Thus, it is certain that ATPL had not sought for specific
performance of those minutes of the meetings. The Sole Arbitrator
had held that ATPL sought direction upon SPDC and the SoS to
perform their obligations under the Second Agreement and what
Arb. A. No.1 of 2020 35
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
was decided on 15.10.2004. The Sole Arbitrator infers this from
paragraph 82 of the claim petition. Contrarily, in paragraph 82 of
the claim petition, ATPL has not sought so. The Sole Arbitrator,
therefore, clearly went beyond the pleadings and the prayer of ATPL
in order to hold as above.
On minutes of the meeting held on 15.10.2004
20. While answering issue no.6, the Sole Arbitrator has also
referred to issue no.3. Issue no.3 framed by the Sole Arbitrator was
whether the terms of the Second Agreement stood modified , as
pleaded by ATPL. The Sole Arbitrator refers to the contention of
ATPL with regard to issues no. 3, 22 and 23 in paragraphs 276 to
278 of the Award. In paragraph 278, the Sole Arbitrator records that
―.....thereafter another joint meeting was held on 15.10.2004 which
resulted in clear modification of the agreement dated 21.12.2002.‖
Besides that sentence, the Sole Arbitrator has not set out any
contention of ATPL that the Second Agreement stood modified by
subsequent minutes of the meetings between the parties.
21. Issues are framed based on the pleadings of the parties.
The claim petition does not assert that the Second Agreement stood
modified by minutes of any meetings held between the parties. Even
if the Sole Arbitrator was of the opinion that ATPL had, in fact,
pleaded that the minutes of the meeting dated 15.10.2004 had
modified the Second Agreement, it was clearly contrary to the
record of the said minutes. The minutes of the meeting dated
15.10.2004 was entered between the SoS, ATPL and Larsen &
Toubro (L&T) and not between the parties to the Second
Arb. A. No.1 of 2020 36
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
Agreement. On a cursory glance of the minutes of the meeting, it is
clear that L&T had reconfirmed their interest in developing the three
HEPs and that their consortium would be the single largest
shareholder in the Special Purpose Vehicle (SPV) in which ATPL
would also be a shareholder. L&T also wanted the confirmation by
the SoS that the projects had been allotted to ATPL on competitive
bidding and they had no objection in joining the SPV as the single
largest shareholder for implementation of the projects. L&T also
informed that the SPV would develop Rolep followed by Chakungchu
and Ralong HEPs. The said minutes also record that if the SoS fulfil
their commitments on the five points therein, SPV agreed to release
₹50.01 crores by February 2007 which would be utilised by SoS
towards repayment of the principle bond amount and the balance
principle amount lying in the bank along with ₹5 crores advanced to
ATPL (who, in turn, have advanced ₹1.85 crores to L&T) shall be
utilised for servicing the interest. In order to implement the project
on time, the SoS committed to provide all infrastructure and State
level clearances as detailed therein. Further, the minutes of the
meeting dated 15.10.2004 clearly records that it wo uld be
formalised by a detailed agreement between the SoS, SPDC, ATPL
and L&T, which was never done. The claim petition asserts an
agreement entered between ATPL and L&T. It is thus clear that the
minutes recorded the broad understanding if L&T came forwar d and
took over the projects from ATPL by forming an SPV with them as
the single largest party and ATPL as a shareholder only. Admittedly,
this did not happen. Unfortunately, the Sole Arbitrator not only
completely ignored this crucial fact and sought to i mpose the
Arb. A. No.1 of 2020 37
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
obligation under the minutes of 15.10.2004 on SPDC and the SoS in
favour of ATPL — in a manner which is in gross ignorance of the
record before him — he also lost sight of the fact that L&T was
never made a party before the Arbitral Tribunal by ATPL at any point
of time. The subsequent minutes also do not dwell on this crucial
aspect.
On minutes of the meeting held on 09.03.2004
22. The minutes of the meeting dated 09.03.2004 also
records clearly that it was chaired by the then Chief Secretary for
review of progress of the three HEPs. It also records that the
presence of L&T and ATPL was required to forward copy of
specification issued by them to L&T to SPDC . Again, certain steps
contemplated to be taken by the parties in the review meeting held
by the then Chief Secretary in the presence of L&T which ultimately
did not take over the project could not have firstly modified the
Second Agreement , as held by the Sole Arbitrator and the
Commercial Court and secondly, could not have bound SPDCL and
the SoS, especially in the absence of L&T as a party to the Arbitral
proceeding.
On minutes of the meeting held on 26.4.2004
23. The minutes of the meetings held on 26.04.2004 also
reveal that it was held by the then Chief Secretary to take stock of
the progress of the three HEPs , clear bottlenecks and never
intended to modify the Second Agreement.
24. Under section 63 of the Indian Contract Act, 1872, there
must be a clear intention to relinquish a right that is fully known to a
Arb. A. No.1 of 2020 38
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
party, as waiver is an intentional relinquishment of a known right.
The minutes of the meetings referred to, does not reflect such clear
intention. In view of the specific clause 25 of the Second
Agreement, we are also of the considered view that the minutes of
the above meetings could not have modified the Second Agreement
as held by the Sole Arbitrator and the Commercial Court, ignoring
what was clearly written in the said minutes of the meetings, and
reading only those paragraphs which would give an impression that
SPDC and the SoS had agreed to modify the Second Agreement.
25. The Award of the Sole Arbitrator granting specific
performance of the Second Agreement , which was held modified by
the minutes of the meeting dated 15.10.2004, is beyond prayer [A]
of ATPL‘s claim petition and thus, wholly contrary to justice and
which shocks the conscience of this Court. The finding of the Sole
Arbitrator on this aspect is also against the terms of the Second
Agreement, which the Sole Arbitrator directed specific performance
of. The Sole Arbitrator has clearly committed an error of jurisdiction
wandering outside the scope and purview of the Second Agreement.
26. Further, the Second Agreement was in terms of Article
166 and 299 of the Constitution of India and expressed to be made
by the Governor of the State of Sikkim. Article 299 specifically
provides that contracts made in exercise of executive power of the
State shall be expressed to be made by the Governor or other
specified authority and shall be executed on behalf of the Governor
by such persons and in such manner as he may direct or authorise.
Arb. A. No.1 of 2020 39
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
In Chatturbhuj Vithaldas Jasani vs. Moreshwar Parashram and others
17
,
the Hon‘ble Supreme Court held that Article 299 was not inserted for
the sake of mere form and the provision was there t o safeguard
against unauthorised contracts. It was also held that if, in fact, a
contract is unauthorised or in excess of authority, the Government
should be safeguarded. The language of Article 299 therefore
suggests that any variation in terms of the contract made under it
should also be made in accordance with the same procedure as the
original contract. The minutes of the meetings referred to above
does not comply with the provisions of Article 299 of the
Constitution of India as well apart from the crucial fact that it is not
even in accordance with the specific clause, being clause 25 of the
Second Agreement.
27. While granting specific performance, the Sole Arbitrator
directed SPDC and the SoS to make over the required land, access
roads and bridges for Rolep, Chakungchu and Ralong HEPs within a
specified time-frame in terms of the Second Agreement , as stood
modified by the minutes of meeting dated 15.10.2004. It does not,
however, spell out what were the required lands, access roads and
bridges to be provided by SPDC and the SoS. More importantly, the
Second Agreement contains various reciprocal obligations between
the parties. The Sole Arbitrator has not directed fulfilling of any of
the reciprocal obligations of ATPL except for directing it to make
payments of certain amounts for getting land and access roads for
17
A.I.R. 1954 S.C. 263
Arb. A. No.1 of 2020 40
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
bridges for Rolep HEP, land and access roads for bridges for
Chakungchu HEP and land and access roads for Ralong HEP.
28. The Second Agreement required each of the party to
perform certain obligations. As admitted by ATPL in the claim
petition itself, the ownership of the three HEPs was transferred to
ATPL, which was stipulated under clause one (1). The first clause
also stipulated that ATPL was to develop, own, operate these
projects on BOOT basis. However, admittedly, none of the projects
have been developed with the laying of even one brick or a stone,
leave alone being operated by ATPL. By clause two (2), as seen
above, ATPL agreed to take over the responsibility of payment of
bond amount to the extent of ₹50.01 crores; interest at the rate of
12.45%, payable half yearly; and interest already paid at a higher
rate (13.75%) after reconciliation of account which was to be
completed within 60 days of signing of the Second Agreement.
Admittedly, reconciliation of account was completed on 19.02.2002,
within the period of 60 days of signing of the Second Agreement.
Thus, ATPL was bound to take over the responsibility of payment of
bond amount and interest thereon as aforesaid after reconciliation of
account on 19.02.2002. ATPL was to also furnish necessary bank
guarantee from a Nationalised Bank for ₹50.01 crores as well as
guarantees for payment of interest within a period of 12 months
from signing of the Second Agreement. However, admittedly, ATPL
has not done so, till date.
29. The Second Agreement clearly records that SPDC and
the SoS had under the First Agreement borrowed funds of the said
amount of ₹50.01 crores through bonds to finance the
Arb. A. No.1 of 2020 41
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
implementation of the three HEPs, which was required to be repaid.
The Sole Arbitrator, however, held issues nos.3, 22 and 23 in favour
of ATPL and thereby further held that the Second Agreement had
been modified in the meeting of the parties dated 09.03.2004,
26.04.2004 and 15.10.2004; that after the meeting of the parties
dated 15.10.2004, ATPL was no longer responsible to repay the
bond holder; and that SPDC and the SoS had relinquished their
claim for bank guarantee.
30. We have already concluded that the minutes of the
meetings could not have either modified or amended the Second
Agreement for four clear reasons. Firstly, clause 25 of the Second
Agreement clearly envisaged a ―supplementary agreement ‖ to be
termed as an ―addendum‖ signed by the parties for any variation
or amendment thereof, which was never done. Thus, there was a
clear bar of doing it in any other manner other than what had been
specifically agreed upon by and between the parties under clause 25
of the Second Agreement. It would have been a different scenario
had clause 25 specifically allowed the parties to modify and/or vary
and/or amend the Second Agreement by means of holding meetings
and recording in its minutes of any decision to modify and/or vary
and/or amend the Second Agreement. Secondly, the minutes of the
meeting held on 15.04.2004 were on the proposal of L&T coming
into the picture and taking over the projects, which did not happen.
Consequently, SPDC and the SoS cannot be held bound by the
minutes of the meeting of 15.04.2004 without L&T taking over the
projects. Similarly, as stated earlier, L&T was never made a party.
Thirdly, the minutes of the other meetings were only for the purpose
Arb. A. No.1 of 2020 42
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
of the then Chief Secretary taking stock of the projects and
attempting to clear the bottlenecks and not for the purpose of
amending the Second Agreement. Fourthly, Article 299 of the
Constitution of India prohibits the amendment of a Governmen t
contract like the Second Agreement , without its compliance.
Additionally, a holistic reading of the Second Agreement makes it
apparent that SPDC and the SoS had clearly transferred their
liability under the First Agreement, having borrowed ₹50.01 crores,
to ATPL and that ATPL had agreed to take it over. This was the most
essential condition of the Second Agreement. However, the Sole
Arbitrator, as well as the Commercial Court, completely ignored the
record of the case which was most material and held that the
minutes of the meeting dated 15.10.2004 with L&T had modified the
Second Agreement and that SPDC and the SoS had abandoned their
right under the Second Agreement. Although, we would like to
exercise caution and restraint, we cannot ignore the fact that the
findings of the Sole Arbitrator borders towards perversity.
31. For the above reasons, it is also held that the finding of
the Sole Arbitrator that ATPL was no longer required to pay the
bond amount or give the bank guarantee in terms of the Second
Agreement is patently illegal on the face of the Award and liable to
be set aside. Additionally, it is also held that the Sole Arbitrator has
construed the contract in a manner that no fair minded or
reasonable person would and that his view is not even a possible
view to take, even remotely.
32. At this juncture, it would be important to examine the
finding of the Sole Arbitrator that SPDC and the SoS had failed to
Arb. A. No.1 of 2020 43
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
perform their part of the Second Agreement by providing ATPL with
lands and access roads and bridges.
33. The Second Agreement, envisaged ATPL doing the
preliminary survey, making the DPRs and identifying specific
locations for establishing the major structures of the projects,
requiring and confirming the access roads to the m ajor structures
from SPDC and the SoS. SPDC and the SoS were then to provide
access roads as required and confirmed by ATPL at their cost.
Admittedly, land in Rolep was provided on lease to ATPL when ATPL
submitted their preliminary and the only DPR. Admittedly, ATPL
never submitted any DPR either for Chakungchu or Ralong HEPs.
Without the DPRs — being an essential part for the purpose of
giving shape to the HEPs under the agreement — there has been no
progress at all.
34. Admittedly, ATPL has submitted only one DPR, i.e., for
36 MW Rolep HEP. Quite evidently for development of the three
HEPs, as envisaged in the Second Agreement , to be built, owned,
operated and subsequently transferred to SPDC and the SoS by
ATPL, it was important for ATPL to have prepared and submitted
DPRs to provide for a proper road map for all the projects‘
successful execution. As ATPL was to build, own and operate it,
quite obviously, as envisaged in the Second Agreement, ATPL was to
provide for details of roads and bridges and require it from SPDC
and the SoS. ATPL was also required to submit the DPRs and in case
SPDC and the SoS gave their consent to bear the cost of roads and
bridges and commit to complete these within reasonable specified
time to enable ATPL to complete the proje cts on time, ATPL was
Arb. A. No.1 of 2020 44
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
then required to submit the DPRs of these projects within six
months thereafter. SPDC gave the confirmation of the expenditure
incurred by SPDC and the SoS in terms of clause 13 of the Second
Agreement, towards the three HEPs on 02.09.2003. Thus, ATPL was
contractually bound to submit the DPRs for the three HEPs within six
months from 02.09.2003. The record, however, clearly reveals that
this was not done.
35. The Sole Arbitrator as well as the Commercial Court
have completely misread the terms of the Second Agreement to
mean that there was no requirement for ATPL to submit DPRs. This
finding is not only against the terms of the Second Agreement but
also against sheer common sense and logic. The terms of the
Second Agreement did not a nd could not have implied that ATPL,
the proposed builder, owner and operator may not submit DPR s for
such huge projects. It would be unfathomable that such hydro -
electric power projects could be executed without any DPR s that
would outline its feasibility, viability and potential. It would be
equally absurd to think that without any detailed information about
the projects, including its scope, objective, budget, timelines, etc.,
prepared by experts, such hydro-electric power projects would see
the light of day.
36. The fact that ATPL had submitted DPR for 36 MW Rolep
HEP in three volumes covering various aspects of the project asserts
the indispensible nature of DPRs for the proposed HEPs. We are,
therefore, constrained to notice that the Sole Arbitrator has awarded
specific performance of the Second Agreement, as held modified by
the minutes of the meeting dated 15.10.2004, without the DPRs.
Arb. A. No.1 of 2020 45
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
37. It was argued on behalf of ATPL that the Sole Arbitrator
did not even frame an issue with regard to the relev ant time for
submission for DPRs as SPDC and the SoS in their reply to the claim
petition filed by ATPL had admitted certain facts. However, to the
contrary, SPDC and the SoS took a clear stand that ATPL had failed
to submit DPRs, as required, in their reply to the claim petition.
38. We are of the considered view that this approach of the
Sole Arbitrator as well as of the Commercial Court is contrary to not
only the terms of the Second Agreement but also to common sense
and logic. We hold that the Award of specific performance by the
Sole Arbitrator, in the manner as aforesaid, amounts to patent
illegality on the face of the award and shocks the conscience of this
Court as it veers towards perversity.
39. The Commercial Court while examining the appeal of
SPDC and the SoS against the Award under section 34 of the
Arbitration Act, went on to uphold the grant of specific performance
in favour of ATPL. However, it is seen that the Commercial Court did
not examine the grant of specific performance of the Sec ond
Agreement, as held modified by minutes of the meeting dated
15.10.2004. Thus, for the same reason for setting aside the Award
of specific performance by the Sole Arbitrator, we set aside the
finding of the Commercial Court as well.
40. As we have held that the minutes of the meetings
between the parties do not amount to modification of the Second
Agreement, it necessarily follows that the parties were bound to
carry out their respective obligations. It was ATPL who approached
the Sole Arbitrator for arbitration by filing the claim petition seeking
Arb. A. No.1 of 2020 46
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
specific performance of the Second Agreement. As held by the
Hon‘ble Supreme Court in C. Haridasan vs. Anappath Parakkattu
Vasudeva Kurup & Others
18
, the provisions of section 16 of the
Specific Relief Act, 1963, have to be mandatorily complied with by
the parties seeking relief of specific performance. The relief of
specific performance cannot be granted in favour of a party who has
not performed his obligations under the contract. Section 16
provides that specific performance of a contract cannot be enforced
in favour of a person, inter alia, who has become incapable of
performing, or violates any essential term of the contract that on his
part remains to be performed, or acts in fraud of a contract, or
wilfully acts at variance with, or in subversion of, the relation
intended to be established by the contract; or who fails to prove
that he has performed or has always been ready and willing to
perform the essential terms of the contract which are to be
performed by him, other than terms the performance of which has
been prevented or waived by the defendant.
41. If it is the contention of ATPL that by the subsequent
minutes of the meetings they were not required to perform an
essential term of the contract of taking over the bond amount and
interest thereon which had been borrowed by SPDC and the SoS in
terms of the First Agreement , quite clearly, ATPL has become
incapable of performing and violated the essential term of the
Second Agreement and thus, could not h ave sought its specific
performance. Thus, the question of award of compensation under
18
(2023) SCC Online 36
Arb. A. No.1 of 2020 47
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
section 21 of the Specific Relief Act, 1963, as argued by ATPL, does
not arise. In Kanshi Ram vs. Om Prakash Jawal & Others
19
, the Hon‘ble
Supreme Court held that it is well settled law that granting decree
for specific performance of a contract of immovable property is not
automatic. It is one of discretion to be exercised on sound
principles.
42. The Sole Arbitrator found that SPDC and the SoS had
the right to modify the terms of the agreement under section 63 of
the Indian Contract Act, 1872 and therefore, they were bound by
the decision taken in those meetings. Section 63 only recognises the
right of every promisee to dispense with or remit, wholly or in part,
the performance of the promise made to him, or may extend the
time for such performance, or may accept instead of it any
satisfaction which he thinks fit. However, it does not deal with the
manner in which a party could dispense with it. This manner was
clearly envisaged in clause 25 of the Second Agreement and,
therefore it could have been done only in terms of clause 25 and in
no other way. The reliance of the Sole Arbitrator to section 63 of the
Indian Contract Act, 1872 to validate the theory of modification of
the Second Agreement by the subsequent minutes of the meeting
was clearly misdirected.
43. It is seen that the Sole Arbitrator has taken in oral
deposition of witnesses contrary to the clear language of the terms
of the Second Agreement, the minutes of the meetings as well as
various exchanges between the parties and by doing so held that
19
(1996) 4 SCC 593
Arb. A. No.1 of 2020 48
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
the terms of the Second Agreement had been completely varied so
as to even do away with one of the essential obligations of ATPL to
take over the responsibility of the payment of bond amount, interest
thereon and also provide bank guarantee for the same . It is settled
law that a document speaks for itself and no oral evidence can be
admitted to contradict, vary, add or subtract from its express terms.
The finding of the Sole Arbitrator to that extent is contrary to the
fundamental policy of Indian law. It reflects patent illegality
appearing on the face of the award, which goes to the root of the
matter and not just mere misapplication of the law.
Prayer [E] - on termination of the Second Agreement
44. The learned Commercial Court upheld the opinion of the
Sole Arbitrator that neither the letter dated 26.02.2006 nor the
letter dated 02.05.2008 had the effect of terminating the Second
Agreement. It opined that the unilateral decision of the SoS to issue
letter dated 02.05.2008 cannot be considered to be the decision of
SPDC automatically as it was a separate legal entity. A perusal of
the Second Agreement makes it apparent that there were three
parties to it. The parties were separate legal entities who had
entered the Second Agree ment with specific obligations and
liabilities. It also reflects that there was a specific provision for
serving of notices to each of the parties. Clause 28, which was
invoked by ATPL, is the arbitration clause which provided that all
matters, questions, disputes or differences whatsoever arising
between the parties in respect of construction, meaning, operation
or effect of the contract or relating to the contract or relating to
Arb. A. No.1 of 2020 49
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
breach thereof shall be settled by way of arbitration. It is contended
that the Second Agreement does not contain a termination clause
and therefore it could not have been terminated. In Rajasthan
Breweries Limited vs. The Stroh Brewery Company
20
, a Division Bench
of Delhi High Court held that even in the absence of a specific clause
authorising and enabling either party to terminate the agreement in
the event of happening of the events specified therein, from the
very nature of the agreement, which is private commercial
transaction, the same could be terminated even without assigning
any reason by serving a reasonable notice. The Second Agreement
was an agreement for developing HEPs. The Second Agreement
envisaged ATPL developing, ow ning and operating these HEPs on
BOOT basis for a period of 35 years to be renewed for another 35
years on mutually agreed terms and conditions. 70 years was the
outer limit of the total period contemplated by the Second
Agreement for ATPL to operate the HEPs. ATPL was to transfer the
ownership of the three HEPs after the expiry of the period envisaged
therein. The Second Agreement also contains certain essential
conditions to be fulfilled within certain timelines. The first of which,
as envisaged by the Second Agreement , was for SPDC and the SoS
to transfer the ownership of the three HEPs to ATPL as required by
clause 1, which was admittedly done. The second essential condition
was for ATPL to take over the responsibility of payment of bond
amount, interest thereon and also provide bank guarantee for the
same within a timeline. Admittedly, ATPL has, till date, not taken
20
2000 SCC Online Del 481
Arb. A. No.1 of 2020 50
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
over the responsibility of payment of bond amount, interest thereon
or provided bank guarantee as envisaged by clause 2 of the Second
Agreement. It would be equally absurd to suggest that one of the
parties who had substantial stakes in the three HEPs and was
therefore a signatory to the Second Agreement as an independent
party, could not have terminated it on the failure of the defaulting
party to fulfil its essential obligations merely because another party
did not sign the termination letter issued by the other. There was no
binding clause in the Second Agreement which provided that SPDC
and SoS should only act jointly. Failure of any of the parties to the
Second Agreement to fulf il their respective essential obligations
without which the purpose of the agreement may itself be
unachievable should entitle the suffering party to determine the
contract although there was no termination clause. The fact that the
SoS issued notice dated 22.06.2006 and thereafter, the letter of
termination dated 02.05.2008, is not in dispute. The language of the
notice as well as the letter of termination makes the intention of the
SoS to terminate the Second Agreement, certain. The failure of any
of the parties to comply with the terms of the Second Agreement
would lead to the dispute being referred to arbitration. SPDC has not
protested the termination by the SoS. We are, thus, of the view that
the SoS had the right to terminate the Second Agreement on t he
failure of ATPL to comply with any of its essential terms, even if
there was no specific termination clause. The only question is
whether the termination by the SoS was justifiable. As we have held
that ATPL had failed to take over the responsibility of payment of
the bond amount, interest thereon and also provide bank guarantee
Arb. A. No.1 of 2020 51
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
for the same, which was an essential term of the Second
Agreement, we are of the considered view that ATPL was clearly in
default. ATPL was also in default for not submitting the DPRs for
Chakungchu and Ralong HEPs and the revised DPR for the revised
Rolep HEP. The fact that ATPL had clearly sought to run away from
their most essential obligation under the Second Agreement by
misleading the Sole Arbitrator into believing that the minutes of the
meeting held with L&T on 15.10.2004 had modified the Second
Agreement and thereby SPDC and the SoS had abandoned their
right has also established beyond reasonable doubt that they were
not interested in the three projects as agreed upon. Thus, we are of
the considered view that the termination of the Second Agreement
by the SoS was justified and we set aside the findings of the Sole
Arbitrator as well as the Commercial Court granting prayer [E] in
favour of ATPL.
Prayers [B] & [C]
45. In view of what we have held above, the grant of prayer
[B] and [C] in favour of ATPL by the Sole Arbitrator as well as the
Commercial Court cannot also stand. It is accordingly set aside.
Prayer [F]
46. Prayer [F] was a claim for award of damages for a sum
of ₹496,689,279/- (Rupees forty-nine crores, sixty-six lakhs, eighty-
nine thousand, two hundred and seventy -nine only), in terms of
paragraph 76 of the claim petition. In paragraph 76, ATPL had
pleaded that it had spent huge amounts for field investigation and
survey, preparation of detailed project report, environmental
Arb. A. No.1 of 2020 52
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
studies, geo-technical and geo-physical investigation, construction
of temporary structures, drilling on the river, gauze and discharge
system and cost of establishment, cost of site estab lishment and
cost of consultancy for which it had spent ₹220,278,098/- (Rupees
twenty-two crores, two lakhs, seventy-eight thousand and ninety-
eight only), from 21.12.2002 till 02.05.2008. ATPL therefore claimed
the said amount along with interest @ 9% compounded annual ly on
year to year basis amounting to ₹496,689,279/- (Rupees forty-nine
crores, sixty-six lakhs, eighty-nine thousand, two hundred and
seventy-nine only).
47. The Second Agreement was an agreement for
implementation of the three HEPs on BOOT basis. The Sole
Arbitrator directed the specific perf ormance of the Second
Agreement by SPDC and the SoS for implementation of three HEPs.
SPDC and the SoS submitted that having sought for Specific
Performance, ATPL could not have asked for prayer [F] as well, as
those were expenses which ought to have been incurred by ATPL.
They further submitted that ATPL having quantified damages in lieu
of specific performance in prayer [D], they could not have claimed
damages on account of expenses incurred as claimed in prayer [F]
as well. The Sole Arbitrator, however, granted prayer [A] for specific
performance, the alternative prayer for quantified damages as
claimed in prayer [D] and thereafter, also awarded the claim for
expenses incurred in terms of prayer [F] without assigning any
reason whatsoever for granting them. The direction upon SPDC and
SoS to specifically perform the Second Agreement would necessarily
presuppose that ATPL would have to fulfil their obligations under it.
Arb. A. No.1 of 2020 53
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
This would mean that ATPL would have to incur all the expenses it
reflected as their expenses in prayer [F] and sought to claim it from
SPDC and the SoS. Thus, having granted specific performance of the
Second Agreement, as prayed for in prayer [A] by ATPL, there was
no reason for the Sole Arbitrator to grant prayer [F]. Further, ATPL
had also claimed damages in prayer [D] at the rate of Rs.1.5 crores
per MW for 279 MW for the three projects. This prayer [D] having
been granted in favour of ATPL, it would also cover the expenses
incurred by ATPL for the implementation of the HEPs as per the
Second Agreement as claimed in prayer [F]. There is, however, no
cogent or justifiable reason or rationale to grant prayer [F] by the
Sole Arbitrator. We, therefore, set aside the Award of prayer [F] in
favour of ATPL. The Award, thus, also suffers from non-application
of mind. However, as we have not granted specific performance of
the Second Agreement in terms of prayer [A] and damages in terms
of prayer [D], we leave it to the parties to determine the actual
expenses only that may have been incurred by ATPL and whether in
the facts and circumstances of the case, it is at all payable to ATPL,
by way of arbitration. Needless to say, the issue of any counter-
claim by SPDC and SoS to be considered in this regard, is also kept
open.
Prayer [G]
48. In prayer [G], ATPL had claimed award of damages for a
sum of ₹471,353,405/- (Rupees forty-seven crores, thirteen lakhs,
fifty-three thousand, four hundred and five only), in terms of
paragraph 77 of the claim petition in which it had stated that as per
Arb. A. No.1 of 2020 54
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
the reconciliation of the accounts done on 19.02.2003 the SPDC was
to pay ATPL a sum of ₹21,22,48,608/- (Rupees twenty-one crores,
twenty-two lakhs, forty-eight thousand, six hundred and eight only),
which was lying with them. ATPL also sought interest @9% per
annum from 19.02.2003, till date of payment and it claimed that the
total amount due as on the date of making the claim as
₹471,353,405/- (Rupees forty-seven crores, thirteen lakhs, fifty-
three thousand, four hundred and five only). ATPL also stated that
the calculation of interest from 19.02.2003 on the said amount was
shown in schedule B of the Claim Petition. Clause 2 and clause 3 of
the Second Agreement would be relevant to appreciate this claim
which is extracted below:-
―2. In terms of the superseded Agreem ent dated 18th
April, 1999, the First Party assisted by the Third Party
have borrowed funds amounting to Rupees 50.01 crores
through bonds to finance the implementation of the said
projects which is to be repaid along with the interest by
the First Party and the Second Party. The First and the
Second Party have given a State Government guarantee
to secure the payment of principal and the interest
thereof. It has now been agreed that the Third Party
shall take over the responsibilities of the payment of
Bond Amount upto an amount of Rs.50.01 crores, and
interest at the rate of 12.45% payable half-yearly and
also interest already paid at a higher rate (13.75%) after
reconciliation of account. Reconciliation of accounts shall
be completed within a period of sixty days from the date
of signing of the Agreement. The Third Party shall furnish
necessary Bank Guarantee from a Nationalized Bank
totalling upto Rs.50.01 crores, as well as guarantees for
payment of interest payable on outstanding principle
amount within a period of 12 months of signing of this
Agreement. Further, the Third Party and the First Party,
with the consent of the lenders, shall release State Govt.
Guarantee within 12 months from the date of signing of
this Agreement. The Third Party shall also take over the
responsibilities of payment of Bond amount upto
Rs.50.01 crore together with the interest accrued and
also the expenditures incurred on account of Bond
registration fees, stamp duty, fees paid to the Trustee
Bank and Advocates for Registration of Bond if any.
3. The balance amount of the money raised (Rs.50.01
crores) lying with the First Party and the Second party
shall be released to the Third Party against the equal
amount of Bank Guarantee from any Nationalized Bank
Arb. A. No.1 of 2020 55
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
to be submitted by the Third Party through the Trustee
Bank (Central Bank of India).‖
49. A bare perusal of the above two clauses reflects that
SPDC assisted by ATPL had borrowed funds amounting to ₹50.01
crores through bonds to finance the implementation of the three
projects which was liable to be repaid along with interest by the
SPDC and the SoS in terms of the First Agreement. It is also clear
that SPDC and the SoS had given State Government Guarantee to
secure the payments of principle and interest thereof. Vide clause 2
of the Second Agreement, ATPL agreed to take over the
responsibilities of the payment of bond amount up to an amount of
₹50.01 crores; an interest at the rate of 12.45% , payable half
yearly and also interest already paid at a higher rate (13.75 %)
after reconciliation of accounts. Reconciliation of accounts was to be
completed within a period of sixty days from the date of signing of
the Second Agreement. ATPL was also required to furnish necessary
Bank guarantee from a Nationalised Bank totalling up to ₹50.01
crores, as well as guarantee for payment of interest payable on
outstanding principal amount within a period of 12(twelve) months
of signing of the Second Agreement. ATPL and SPDC, with the
consent of the lenders, was to release State Government Guarantee
within 12(twelve) months from the date of signing of the Second
Agreement. ATPL was also to take over the responsib ility of
payment of bond amount up to ₹50.01 crores together with interest
accrued and also the expenditures incurred on account of bond
registration fee, stamp duty, fees paid to the Trustee Bank and
Advocates for registration of bond if any. Importantly, as agreed
under clause 3 of the Second Agreement, the balance amount of the
Arb. A. No.1 of 2020 56
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
money raised (₹50.01 crores) lying with SPDC and the Government
of Sikkim was to be released to ATPL against equal amount of Bank
Guarantee from any Nationalised Bank to be submitted by the ATPL
through the Trustee Bank (Central Bank of India).
50. Reading clauses 2 and 3 of the Second Agreement
together, it is amply clear that by entering upon the Second
Agreement, SPDC and the SoS had sought to get out of the financial
burden it had incurred under the superseded First Agreement dated
18.04.1999. The balance money in terms of clause 3 of the Second
Agreement was clearly payable only upon ATPL taking over the
sovereign debt of the SoS and guarantee payment of the same
along with the payment of interest and other expen ses already
borne. The Sole Arbitrator, however, directed the payment of
damages in terms of prayer [G] without ATPL taking over the
sovereign debt of the SoS and guaranteeing payment of the same
along with the payment of interest and other expenses. This was not
in terms of the Second Agreement and the Sole Arbitrator by
awarding damages as claimed in prayer [G] made out a new
contract between the parties, which is impermissible. Further, the
Sole Arbitrator proceeded on the basis that the Second Agreement
was modified by the minutes of the meeting dated 15.10.2004 with
L&T. However, even while doing so, the Sole Arbitrator went beyond
even the minutes of the meeting dated 15.10.2004 , which
contemplated ATPL paying the SoS a sum of ₹50.01 crores in three
tranches, which the SoS would use to discharge its sovereign debt.
It was also contemplated therein that SPDC need not pay ATPL the
balance of the sum of ₹50.01 crores lying with it as it would be used
Arb. A. No.1 of 2020 57
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
to service the interest on the debt till the repayment of the same
from out of the monies received from ATPL in three tranches.
Therefore, the Sole Arbitrator, while awarding prayer [G], seems to
have gone not only beyond the terms of the Second Agreement but
also beyond the terms of the minutes of the meeting dated
15.10.2004. It reflects complete non-application of mind as well and
the decision on this aspect is irrational.
Prayer [H]
51. As ATPL has not challenged the Sole Arbitrator‘s Award
declining to grant damages in terms of prayer [H], we do not
interfere with it.
Prayers [J] & [K]
52. Consequently, the Award of interest in terms of prayer
[J] and costs in terms of prayer [K] are also set aside. ATPL may
claim the actual cost incurred by them, as prayed for in prayer [F]
and interest thereon by way of fresh arbitration, if they so desire.
SPDC and SoS are at liberty to file their counter-claim in this regard.
Conclusion
53. In conclusion, the impugned judgment — to the extent it
declines grant of prayers [D] and [F] in favour of ATPL — is upheld.
The finding that Rolep Hydro Electric Power Co. Ltd. and Velankani
Renewable Energy Private Limited were not necessary parties is
upheld. The finding of the Commercial Court that the recital in
Second Agreement makes it clear that the parties had in fact agreed
to do the project on BOOT basis is upheld. The setting aside of the
Arb. A. No.1 of 2020 58
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
finding of the Sole Arbitrator on Issues No.9, 11 and 20 are also
upheld. The finding of the Commercial Court , upholding the
reasoning of the Sole Arbitrator that the letter dated 02.05.2008 did
not terminate the contract (prayer [E]) and that the ground for
termination was unjustified, is set aside. It is found that on the
failure of ATPL to fulfil the essential term of the Second Agreement
of taking over the responsibility of bond amount, interest thereon as
well as provide bank guarantee for the same, SoS had rightly issued
the letter dated 02.05.2008 terminating the contract. The finding of
the Commercial Court that the petitioners therein (SPDC and SoS)
had relinquished their claim for submission of Bank Guarantee in
terms of the minutes of the meetings dated 09.03.2004, 26.04.2004
and 15.10.2004, is also set aside. It is held that the Commercial
Court‘s finding that clause 25 of the Second Agreement did not
disentitle the parties to amend it is grossly erroneous and against
the plain and simple intention of clause 25. The language of clause
25 is clear and unambiguous. It is also held that the finding of the
Commercial Court that the minutes of the meeting s dated
09.03.2004, 26.04.2004 and 15.10.2004, were in the nature of
addendum and supplemental is also grossly erroneous and against
the clear and unambiguous language and intention of clause 25 of
the Second Agreement. The finding of the Commercial Court ,
upholding the reasoning of the Sole Arbitrator that since SPDC and
SoS had failed to perform their promise as per the minutes of the
meetings dated 09.03.2004, 26.04.2004 and 15.10.2004 , they had
relinquished their claim for Bank Guarantee and therefore there was
no question of breach by ATPL, is also set aside. Grant of specific
Arb. A. No.1 of 2020 59
Sikkim Power Development Corporation Ltd. & An r. vs. Amalgamated Transpower (India) Ltd.
&
Arb. A. No.1 of 2021
Amalgamated Transpower (India) Ltd. vs. M/s Sikkim Power Development Corporation Ltd. & Anr.
performance (prayer [A]), perpetual injunction (prayer [B]) and
mandatory injunction (prayer [C]) against SPDC and SoS by the
Sole Arbitrator in favour of ATPL , which was upheld by the
Commercial Court, is set aside. The award of damages in favour of
ATPL, in terms of prayers [F], [G], [I] by the Sole Arbitrator are set
aside. Grant of interest and cost in terms of prayers [J] and [K],
consequently, is also set aside. Non-grant of prayer [H] by the Sole
Arbitrator to ATPL is not interfered with. ATPL may, if they so desire,
claim the actual cost incurred by them in terms of prayer [F] and
interest thereon against SPDC and the SoS by way of fresh
arbitration. SPDC and SoS are at liberty to file their counter-claim in
this regard. Consequently, Arbitration Appeal No. 1 of 2020 is
allowed to the extent above, while Arbitration Appeal No. 1 of 2021
preferred by ATPL stands dismissed.
54. Consequently, the amount deposited b y SPDC and SoS
in terms of the order of the Hon‘ble Supreme Court dated
14.10.2022 in Special Leave Petition (Civil) No. 18211-18212 of
2022, shall be released along with interest accrued thereon.
55. The two Appeals stand disposed of accordingly.
56. Parties to bear their respective cost.
( Biswanath Somadder ) ( Bhaskar Raj Pradhan )
Chief Justice Judge
Approved for reporting : Yes/No
Internet : Yes/No
Jk/bp/ak
Legal Notes
Add a Note....