As per case facts, the appellant challenged a judgment dismissing their petitions against the rejection of their technical bid for a rail-cum-road bridge project. The tender required no history of ...
Page No.# 1/15
GAHC010057962026
2026:GAU-AS:4655-DB
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WA/79/2026
SPS CONSTRUCTION INDIA PRIVATE LIMITED,
THROUGH ITS AUTHORIZED REPRESENTATIVE MR. MADHAV SINGLA,
HAVING REGISTERED OFFICE AT 1006-1007, 10TH FLOOR,
PEARLS BEST HEIGHT-1, NETAJI SUBHASH PLACE,
PITAMPURA, NEW DELHI – 110034.
….……Appellant
-VERSUS -
1.UNION OF INDIA,
THROUGH MINISTRY OF RAILWAYS,
HAVING ITS OFFICE AT 256-A, RAISINA ROAD,
RAJPATH AREA, CENTRAL SECRETARIAT,
NEW DELHI- 110001.
2:NORTHEAST FRONTIER RAILWAY,
THROUGH CHIEF ENGINEER,
HAVING ITS OFFICE AT CONSTRUCTION OFFICE,
MALIGAON, GUWAHATI -781011.
3:LARSEN AND TOUBRO LIMITED,
HAVING ITS OFFICE AT 8TH FLOOR,
VATIKA MINDSCAPE BUILDING,
DELHI MATHURA ROAD, FARIDABAD – 121003.
…… Respondents
Page No.# 2/15
– BEFORE –
HON’BLE THE CHIEF JUSTICE MR. ASHUTOSH KUMAR
HON’BLE MR. JUSTICE ARUN DEV CHOUDHURY
Advocate for the Appellant(s): Mr. Vivek Chib, Senior Advocate assisted by Mr.
Siddhartha Sunil, Mr. Aditya Mittal, Mr. Vibhu Pahuja
and Mr. A Chakraborty, Advocates.
Advocate for the respondent(s0: Mr. K. Gogoi, Central Government Counsel, for
respondent Nos.1 & 2.
: Mr. D. Das, Senior Advocate assisted by Mr. R.
Sarmah, Ms. M. Kakoty and Ms. A. Gupta,
Advocates for respondent No.3.
Date of Hearing : 27.03.2026 & 31.03.2026.
Date of Judgment : 01.04.2026.
J UDGMENT & O RDER
(Ashutosh Kumar, CJ)
We have heard the learned counsel for the parties.
2. The appellant/SPS Construction India Private Limited has
challenged the judgment dated 18.02.2026 passed by a learned Single
Judge of this Court in WP(C) No.5051/2025 and WP(C) No.6625/2025,
whereby the afore-noted two writ petitions have been dismissed,
upholding the validity of the eligibility condition for the revised Request
For Proposal (in short “RFP”) dated 23.07.2025 and the rejection of the
appellant’s technical bid as non-responsive.
3. The respondent Nos.1 and 2 had issued an RFP dated
Page No.# 3/15
19.05.2025 for execution of major infrastructure project on Engineering,
Procurement and Construction (EPC) Mode, namely, construction of
second rail-cum-road bridge over river Brahmaputra along with
associated works.
4. The original RFP contained an eligibility condition in Clause
2.2.2.4.iii.ii.2 of Section 2 thereof that there should not be a history of
collapse of superstructure/substructure of any span of a
bridge/flyover/via-duct/metro-line work during construction/service in
last 5(five) years, ending last day of month previous to the one in which
tender is invited and that an undertaking in that regard shall be
submitted along with the bid.
5. Upon representation by the prospective bidders including the
appellant, the respondents issued a revised RFP dated 23.07.2025,
clarifying that only collapses attributable to design failure or quality
failure would be relevant; and the look-back period would be reduced
from 5(five) years to 3(three) years.
6. The appellant submitted its bid pursuant to the revised RFP but
with the “without prejudice” clause and contemporaneously filed WP(C)
No.5051/2025, [WP(C) No.5051/2025 was filed on 26.08.2025 as claimed
by the appellant i.e. a day before the submission of the bid but
according to the respondents the afore-noted was filed after the
submission of the bid] challenging the validity of the clause or in the
alternative, a declaration from the Court that such clause would not
operate against the bidders having suffered a collapse in respect of any
Page No.# 4/15
of their projects in the last 3(three) years on account of force majeure
and/or in absence of any determined or adjudicated fault of the bidder.
7. While the afore-noted writ petition was pending, the technical
bid of the appellant was rejected on 28.10.2025 as non-responsive in
terms of the afore-noted clause. Another writ petition vide WP(C)
No.6274/2025 thus was filed, challenging the said rejection. However, on
submission that the Letter of Acceptance (LOA) had already been issued
to respondent No.3/Larsen and Toubro Limited (L&T), the afore-noted writ
petition [WP(C) No.6274/2025] was withdrawn by the appellant with the
liberty to challenge the same. Thereafter, the appellant had preferred
WP(C) No.6625/2025 challenging the grant of LOA to respondent No.3.
8. Before the learned Single Judge, it was argued on behalf of
the appellant that the clause in question was void as it was vague,
uncertain and ambiguous and, therefore, it did not provide a “level
playing field” on account of inherent uncertainties in the application of
such clause. In a project undertaken by the appellant in the State of
Bihar within 3(three) years of the present RFP, there had been a collapse
of few spans of the bridge under construction but without any fatalities
and the cause of such collapse has till date not been ascertained.
It was thus contended by the appellant that the history of the
collapse, referred to above, could not have been read against it.
9. A reference was made by the appellant to the judgment of
the Supreme Court in Reliance Energy Limited & Anr. –Vs- Maharashtra
State Road Development Corporation Limited & Ors. :: (2007) 8 SCC 1 ,
Page No.# 5/15
wherein it was held that where tenders are invited, the terms and
conditions must indicate with legal certainty the norms and benchmarks.
Any vagueness or subjectivity in the said norms would result in
unequal/discriminatory treatment, thus, violating the doctrine of “level
playing field”. Reference was also made to the judgment of the Supreme
Court in Atlanta Limited -Vs- Union of India & Anr. :: 2018 SCC OnLine
Del 8269 and Blue Dreamz Advertising Private Limited -Vs- Kolkata
Municipal Corporation Limited & Ors.:: (2024) 15 SCC 26 4 to argue that
the clause in question actually led to automatic debarment of the
appellant in the absence of any determined guilt, which is impermissible.
10. The learned Single Judge framed a number of issues but
primarily as to whether the appellant, having participated in the tender
process had the locus to challenge the eligibility condition? (b) Whether
the impugned clause is vague, arbitrary or violative of the doctrine of
“level playing field”? (c) Whether the impugned clause amounts to
automatic blacklisting and (d) Whether the rejection of the appellant’s
technical bid is legally sustainable?
11. The learned Single Judge, on perusal of the facts of the case,
found that the appellant had submitted its bid after the issuance of the
revised RFP with full knowledge of the impugned eligibility condition.
12. Applying the law laid down in National High Speed Rail
Corporation Limited -Vs- Montecarlo Limited & Anr. :: (2022) 6 SCC 401 ,
it was held by the learned Single Judge that a bidder who participates in
a tender process with the knowledge of its terms cannot subsequently
Page No.# 6/15
challenge those terms upon being unsuccessful. The appellant perhaps,
according to the learned Single Judge, attempted to circumvent this
principle by contending that the writ petition was filed with “without
prejudice” clause and contemporaneously with or perhaps after the bid
submission.
It was found that the appellant had already participated in
the process, which was a conscious commercial decision. The tendering
authority, more often than not, would structure its process on the
assumptions that bidders have accepted the terms. Allowing such a
challenge would enable bidders to adopt the practice of participating in
the process and then, upon failure, assailing the conditions, which is
impermissible.
13. Challenging the afore-noted finding of the learned Single
Judge, it was argued on behalf of the appellant that the first writ petition
[WP(C) No.5051/2025) was filed on 26.08.2025, questioning the inclusion
of the disqualification criterion at Clause 2.2.2.4.iii.ii.2 of the said RFP,
being vague, over-broad, arbitrary and specifically targeted, as it
required the bidders to undertake that they do not have any history of
collapse of superstructure/substructure of any span of a bridge/flyover
during construction or service in the last 3(three) years, but without
clarifying whether the incidents for which no adjudicated liability has
been fixed on the bidder would be included in this clause. The appellant
had submitted its bid on 27.08.2025 looking at the time-line provided in
the RFP.
Page No.# 7/15
14. In support of the afore-noted fact, it was contended on behalf
of the appellant that it is a matter of record that the first writ petition was
notarized and filed on 26.08.2025.
It has also been pointed out that the appellant had given an
undertaking dated 26.08.2025 along with its bid in compliance of the said
clause of RFP on a “without prejudice” basis.
Even though the same was brought on record before the
learned Single Judge by way of an additional affidavit, it was held by the
learned Single Judge that the challenge to the eligibility condition was
made after participation by the appellant.
15. It would not be necessary for us to go into the afore-noted
aspect as it appears that despite deciding the locus of the appellant to
challenge the eligibility condition in the negative, the learned Single
Judge proceeded to determine other questions framed, namely,
whether the clause in question was vague or arbitrary or it resulted in
automatic blacklisting and whether the rejection of the appellant’s bid
was sustainable.
16. The learned Single Judge, on perusal of the undertaking given
by the appellant, found that there was no explanation that the collapse
of a few spans of the bridge during construction by the appellant in
Bihar, was not because of any design failure or quality failure. The
appellant had understood the ambit of reach of the clause in question.
There was no vagueness and uncertainty regarding the application of
that clause. The State has a right to fix its own terms of the tender which is
Page No.# 8/15
not open to judicial scrutiny. A reference was made in the impugned
judgment to Tata Cellular -Vs- Union of India :: (1994) 6 SCC 651.
17. The learned Single Judge concluded on a detailed reading of
the clause in question that there was no arbitrariness or mala fides.
Relying on a judgment of Supreme Court in Uflex Limited -Vs-
Government of Tamil Nadu & Ors. :: (2022) 1 SCC 165 , wherein it was
held by the Supreme Court that in every tender, there are certain
qualifying parameters whether it be technology or turnover and the
Courts cannot in exercise of judicial review sit over such conditions,
rejected the contention of the appellant.
18. Let us now examine the clause in question to understand
whether the same is vague or arbitrary.
19. The records reveal that the original concern of vagueness
stood substantially addressed by the clarification in the revised RFP. The
clause, as it stands now, limits the disqualification to collapse attributable
to (i) design failure or (ii) quality failure. These are well understood
technical parameters in engineering practice, which, in our estimation,
are neither indeterminate nor subjective.
20. Post the clarification, the eligibility clause became applicable
uniformly to all bidders and it also reflected a rational nexus with the
objective of ensuring structural safety in a complex bridge project. This
condition is, in fact, a risk mitigation measure. Infrastructure project of this
magnitude demands high degree of reliability. Excluding the bidders for
recent history of collapse attributable to design failure or quality failure is
Page No.# 9/15
a legitimate policy choice.
21. That apart, the reduction of the look-back period from five
years to three years further demonstrates that the respondents acted
fairly and responsibly.
22. The argument that the impugned clause amounts to
automatic blacklisting is also misconceived. Blacklisting entails stigmatic
exclusion from all future contracts and carries civil consequences. The
impugned clause in its present form, merely prescribes an eligibility
criterion for a specific tender. It neither imposes a penalty nor prohibits
future participation in other tenders. The distinction between the eligibility
condition and blacklisting is well recognized in tender jurisprudence. The
clause in question, therefore, falls squarely within the category of a valid
risk mitigation clause.
23. The contention that the clause cannot be activated in the
absence of prior determination or adjudication of the cause of collapse
and is, therefore, faulty, does not merit acceptance.
24. At the first glance, the argument appears to be attractive but
it proceeds on a fundamentally incorrect understanding of the nature
and purpose of eligibility condition in a tender.
25. As noted above, the clause is not penal in character. It is
preventive and is a risk-cover, intended to enable the employer to assess
the technical reliability and risk profile of bidders in high-stakes
infrastructure projects.
Page No.# 10/15
26. Requiring a prior judicial or quasi-judicial adjudication of cause
of collapse would defeat the very purpose of such a clause.
Infrastructure failures often involve prolonged technical investigations;
expert committee reports and delayed or inconclusive findings. If the
applicability of the clause were made contingent upon the final
adjudication, the employer would be compelled to either indefinitely
delay the procurement or ignore recent and potentially serious structural
failures. Neither of the consequences would be acceptable in public
procurements.
27. The appellant’s argument prima-facie appears to rest on the
assumption that the clause operates mechanically upon mere
occurrence of a collapse. This is incorrect. The Revised RFP specifically
limits its application to collapses attributable to the design failure or
quality failure.
Thus, in the impugned clause, there is an in-built causal filter. It
does not disqualify every bidder with a collapse history but only those
where collapse is linked to the deficiencies attributable to the bidder.
28. In a tender process, the burden of demonstrating eligibility lies
on the bidder. Where a bidder has a known history of collapse within the
relevant period, it is incumbent upon such a bidder to disclose the
incident fully and explain with supporting materials, if necessary, that the
collapse was not due to design or quality failure, but for other factors like
force majeure, third party interference or any other extraneous causes. If
the bidder fails to provide such clarification, the employer would be
Page No.# 11/15
entitled to proceed on the basis of the available record.
29. In the present case, the learned Single Judge has rightly found
that the appellant’s undertaking does not contain any such categorical
clarification.
30. There is no principle in tender jurisprudence that eligibility
conditions must depend upon prior adjudication of disputed facts. On
the contrary, the Supreme Court has consistently held in Tata Cellular
(supra) and Jagdish Mandal -Vs- State of Orissa & Ors. :: (2007) 14 SCC
517 that the tender authorities have wide latitude in prescribing eligibility
criteria. The Courts do not substitute their own standards and the
commercial decisions can be based on reasonable assumptions of risk,
not proved beyond doubt.
31. Tender evaluation is not a judicial trial. It is only a commercial
and a technical screening process.
32. Accepting the appellant’s argument would lead to
impractical consequences. Every bidder with a collapse history could
claim pending inquiry and remain eligible or the employer would be
forced to independently investigate technical causes mid-tender and, in
that case, the procurement process would become unworkable and
uncertain. Public authorities are entitled to adopt administrable criteria,
particularly in any technically sensitive projects involving public safety.
33. We, therefore, are of the view that the clause, as it stands after
clarification, narrows the scope to specific causes, namely,
Page No.# 12/15
design/quality failure; it limits the timeframe of three years and requires
an undertaking from the bidder, striking a reasonable fairness between
bidder and protection of public interest.
34. The absence of formal adjudication does not render the
clause vague or unworkable; rather it places a duty of disclosure and
explanation on the bidder.
35. The appellant has had a recent collapse incident and no
conclusive explanation was made available to the extent that it was
unrelated to design failure or quality failure. The undertaking given by the
appellant does not dispel the risk contemplated by the clause. In such
circumstances, the tender authority acted within its rights in treating the
bid of the appellant as non-responsive.
36. Another issue raised on behalf of the appellant is the rationale
of a three years’ look-back period.
This is a matter of policy grounded in commercial and
technical considerations in infrastructure contracts, particularly those
involving bridges over major rivers. The employer is entitled to assess the
current technical and operational reliability of a bidder. A recent failure
within 3(three) years is far more relevant indicator of a present capability
than an older incident. The original FRP prescribed a five years’ period.
Upon representations, this was consciously reduced to three years,
demonstrating that the authority applied its mind and responded to the
industry concerns and in fact, adopted a less restrictive standard. A
defined temporal cut-off ensures certainty and uniformity. Any longer
Page No.# 13/15
period may become unduly harsh; while a shorter period might dilute
safety concerns. The choice of three years, according to us, lies within a
reasonable band of discretion.
37. As held in Uflex Limited (supra), the authorities are best
placed to determine the technical and commercial threshold required
for a project. The Courts do not calibrate such parameters unless they
are manifestly arbitrary.
38. No materials have been placed on record to show that the
three years’ period is capricious, irrational or without nexus to object of
ensuring structural safety. The challenge, therefore, fails.
39. Another argument raised on behalf of the appellant is that
such a clause would operate as a hindrance to his participation in other
tenders across India. This argument is misconceived for the reason that it
is a tender specific condition. Each tender is an independent invitation,
governed by its own terms. The clause in the present RFP applies only to
this procurement process and in no case creates a binding precedent for
other authorities. It does not amount to blacklisting. It does not debar the
appellant from future tenders and also does not create any adverse
record enforceable by other authorities. Different Government bodies
may adopt different eligibility criteria, depending upon project
complexities, risk profile and technical requirements.
40. The apprehension of exclusion from pan India tenders thus is
purely speculative. The Courts ought not to invalidate a clause on the
basis of hypothetical downstream effects.
Page No.# 14/15
41. Another argument raised on behalf of the appellant is that the
requirement of giving an undertaking has been made implicit but without
providing any contours within which such undertaking is to be given.
This contention is equally untenable. The purpose of
undertaking is clear. It is required to affirm that there is no disqualifying
collapse attributable to design failure or quality failure within the
stipulated period. What should be the substance of declaration is,
therefore, absolutely unambiguous. The tender conditions primarily
require declarations without prescribing exhaustive formats.
42. What is required is substantive compliance and not ritualistic
adherence to any template. Where a bidder is aware of potential
disqualification event, it is incumbent upon it to disclose the history of
collapse fully; explain its causes and clarify why it does not fall within the
disqualification criteria.
43. The appellant has not provided a clear statement that the
Bihar collapse was unrelated to design failure or quality failure. He has
not placed any material or explanation to that effect.
44. The impugned eligibility framework represents a legitimate
exercise of contractual discretion, aimed at safeguarding public interest
in a technically sensitive project. The appellant has failed to demonstrate
that the conditions are vague or unworkable ; or that the process is
arbitrary or unfair.
45. For the afore-noted reasons, this writ appeal is dismissed and
Page No.# 15/15
the impugned judgment passed by the learned Single Judge is sustained
and upheld.
JUDGE CHIEF JUSTICE
Comparing Assistant
Legal Notes
Add a Note....