As per case facts, an EPC contract was awarded to the respondent who later suspended work due to the appellant's non-payment for initial milestones. Despite several legal notices, the appellant ...
2026 INSC 835 REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 876 OF 2021
SRINIVASA REDDY VELAGALA ... APPELLANT
VERSUS
SRAVANTHI INFRATECH PVT. LTD . ... RESPONDENT
J U D G M E N T
C.A. No. 876 of 2021 Page 2 of 62
J. B. PARDIWALA, J. :
For the convenience of exposition, this judgment is divided into the following
parts: -
INDEX
A. FACTUAL MATRIX .................................................................................... 4
B. SUBMISSIONS OF THE PARTIES ......................................................... 15
i. Submissions on behalf of the appellant ................................................ 15
ii. Submissions on behalf of the respondent ............................................. 20
C. ISSUES TO BE DETERMINED ........................................................... 26
D. ANALYSIS .................................................................................................. 26
(i) Subsistence of the EPC contract ........................................................... 26
(ii) Amount claimed by the respondent is operational debt .................... 33
(iii) Pre-existing dispute between the parties ............................................. 36
(iv) Respondent’s claim is barred by limitation ......................................... 43
E. DETERMINATION OF THE ISSUES IDENTIFIED ........................... 56
I. Whether the EPC contract entered into by and between the appellant
and respondent was frustrated by the efflux of time? ............................... 56
I. Whether the monies claimed by the respondent in the application
under Section 9 of the IBC constitute ‘operational debt’ as defined under
Section 5(21) of the IBC? ............................................................................. 57
C.A. No. 876 of 2021 Page 3 of 62
II. Whether there existed a prior dispute in respect of the claims of
respondent? ................................................................................................... 58
III. Whether the application filed by the respondent under Section 9 of the
IBC was time-barred in respect of the dues amounting to ‘operational
debt’? .............................................................................................................. 60
F. CONCLUSION ........................................................................................... 61
C.A. No. 876 of 2021 Page 4 of 62
1. This appeal arises from the judgment and order dated 01.02.2021 passed by
the National Company Law Appellate Tribunal at New Delhi (“NCLAT”)
in the Company Appeal (AT) (Insolvency) No. 188 of 2020, preferred by the
appellant herein against the admission of the insolvency application filed by
the respondent herein under Section 9 of the Insolvency and Bankruptcy
Code, 2016 (“IBC”), by which the NCLAT affirmed the order of the
National Company Law Tribunal, Amravati Bench (“NCLT”) admitting the
Section 9 application and initiating insolvency proceedings against the
appellant herein.
A. FACTUAL MATRIX
2. The appellant herein (the corporate debtor) had invited an International
Competitive Bid by advertisement dated 13.12.2010, for setting up a 225
MW gas based combined cycle Power Station at Bikkavolu, East Godavari
District, Andhra Pradesh.
3. The respondent herein (the original petitioner before the NCLT), i.e., the
operational creditor, was awarded the contract for execution of the aforesaid
project as it submitted the lowest bid. The appellant issued the Letter of
Award dated 24.12.2010 (the “LOA”) to the respondent for an amount of
C.A. No. 876 of 2021 Page 5 of 62
Rs. 827 crore. The parties subsequently entered into a contract for
Engineering Procurement and Construction (“EPC agreement” / “EPC
contract”) dated 09.02.2011. It was decided amongst the parties that the
EPC contract was supposed to be completed in 14 months. It was mutually
agreed between the parties that any disputes arising out of the EPC
Agreement shall be referred to arbitration.
4. The EPC agreement enumerated several obligations and conditions for
payment. The terms of payment in the EPC agreement signed between the
parties is reproduced hereinbelow:
“Appendix – B
TERMS OF PAYMENT
SUPPLY OF EQUIPMENT
Sl.
No.
Milestone Payment
1 Initial Advance Payment 10% of Contract Price
against Corporate
Guarantee
2 Payment against ordering major
equipment;
5% of Contract Price
C.A. No. 876 of 2021 Page 6 of 62
a) Against ordering of GTGs
b) Against ordering of STG
c) Against ordering of HRSGs
d) Against ordering of CT / ACC
3 Payment against release of advances
a) Against release of advance of
GTGs
b) Against release of advance of STG
c) Against release of advance of
HRSGs
d) Against release of advance of CT /
ACC
5% of Contract Price
4 Payment against Billing Break-up (BBU) 70% of the contract
price shall be paid as
per agreed billing
break up.
5 Payment on Commissioning 5% payment shall be
made on
Commissioning in
Open Cycle or 45 days
of readiness of
facilities and against
submission of
performance corporate
guarantee for 5% of the
contract value.
6 Payment on Commissioning 5% payment shall be
made on
Commissioning in
C.A. No. 876 of 2021 Page 7 of 62
Combined Cycle or 45
days of readiness of
facilities and against
submission of
performance corporate
guarantee for 5% of the
contract value.
(…)”
5. The monetary break-up of the contract price in terms of the aforesaid
payment schedule is provided below:
Sl.
No.
Milestone Payment Amount to be
paid in
milestones
(In Rs.)
1 Initial Advance Payment 10% of Contract
Price against
Corporate
Guarantee
82.7 crore
2 Payment against ordering
major equipment;
e) Against ordering of
GTGs
f) Against ordering of
STG
g) Against ordering of
HRSGs
5% of Contract
Price
41.35 crore
C.A. No. 876 of 2021 Page 8 of 62
h) Against ordering of
CT / ACC
3 Payment against release of
advances
e) Against release of
advance of GTGs
f) Against release of
advance of STG
g) Against release of
advance of HRSGs
h) Against release of
advance of CT / ACC
5% of Contract
Price
41.35 crore
4 Payment against Billing
Break-up (BBU)
70% of the
contract price
shall be paid as
per agreed
billing break up.
578.9 crore
5 Payment on Commissioning 5% payment
shall be made on
Commissioning
in Open Cycle or
45 days of
readiness of
facilities and
against
submission of
performance
corporate
guarantee for 5%
41.35 crore
C.A. No. 876 of 2021 Page 9 of 62
of the contract
value.
6 Payment on Commissioning 5% payment
shall be made on
Commissioning
in Combined
Cycle or 45 days
of readiness of
facilities and
against
submission of
performance
corporate
guarantee for 5%
of the contract
value.
41.35 crore
TOTAL 827 CRORE
6. On the basis of the aforesaid payment schedule, the respondent was supposed
to receive the payment of 10% of the contract price, i.e., Rs. 82.7 crore upon
completion of the first milestone. The first milestone was achieved when the
LOA was issued to the respondent on 24.12.2010 and the Corporate
Performance Guarantee and Advance Corporate Guarantee respectively was
provided by the respondent to the appellant on 26.04.2011 and 29.04.2011
C.A. No. 876 of 2021 Page 10 of 62
respectively. However, the appellant made payment of Rs. 50.15 crore as
advance out of Rs. 82.7 crore that was supposed to be paid.
7. Further, the second instalment of 10% of the contract price, i.e., Rs. 82.7
crore was supposed to be paid once the respondent achieved the second and
third milestones. The respondent, having finalized the purchase order copy
for GTG, STG and HRSG respectively, submitted the same on 15.02.2011.
The status reports in regard to the work done by the respondent on the site
were also being forwarded to the appellant regularly. The appellant vide its
letter dated 05.01.2012 to the Chief Engineer IRP Division Central
Electricity Authority, New Delhi, duly acknowledged in detail the work done
by the respondent.
8. Though the respondent achieved the first, second and third milestones
respectively yet, the appellant made payment of only Rs. 50.15 crore out of
the cumulative Rs. 165.4 crore that remained due to the respondent.
9. The respondent, in order to finish the contract works in a timely manner and
to achieve the fourth milestone, placed various on shore and offshore orders
and hired sub-contractors for completion of the works. The respondent
accordingly sent the Billing Break-up (“BBU”) to the appellant on
C.A. No. 876 of 2021 Page 11 of 62
13.07.2011. The BBU was submitted once again on 03.01.2012 on demand
by the appellant and the same was acknowledged without any dispute by the
appellant. However, no payment was made by the appellant to the respondent
in pursuance of the BBU.
10. Aggrieved by the non-payment of its dues by the appellant, the respondent
sent a notice of suspension dated 30.07.2011 to the appellant on the ground
that the amount of Rs. 32.55 crore was pending from the advance payment
which became due after the first milestone. Pursuant to the suspension
notice, the respondent stopped all EPC activities and stated that the same
would be resumed only after the receipt of the initial advance. The
respondent also terminated its contracts with the vendors and sub-contractors
hired for completing the contract works.
11. The respondent sent legal notices dated 25.07.2014, 16.09.2014 and
15.07.2015 respectively wherein it demanded payment in terms of the
payment provisions enumerated in the EPC contract. It was stated in the said
notices that the appellant’s failure to complete the payment caused the
respondent to suspend the works, as it was unable to continue with full
mobilization at the site and subsequently, it had to completely demobilize by
November 2011. It was clarified that the works remained suspended as the
C.A. No. 876 of 2021 Page 12 of 62
appellant had failed to cure its default in payments. It was further clarified
that the appellant had not terminated the EPC agreement and therefore, the
duties and obligations thereunder continued to operate as regards the parties.
No response to the aforesaid legal notices is present in the record.
12. The respondent after the lapse of almost three years sent a demand notice
dated 02.07.2018 in due compliance of the statutory stipulation under
Section 8 of the IBC. The total amount of debt demanded thereunder was
stated to be Rs. 1292,13,35,000/- (Rupees One thousand Two hundred and
Ninety Two Crores Thirteen Lakhs and Thirty Five Thousand Only) which
fell due on 25.02.2011. It was also stated therein that the BBUs sent on
03.01.2012 were acknowledged by the appellant but remained unpaid.
13. As there was no response to the aforesaid demand letter, the respondent filed
the application under Section 9 of the IBC on 12.10.2018, which came to be
admitted on 13.12.2019 by the NCLT. The NCLT admitted the Section 9
application on the following grounds:
a) The application under Section 9 of the IBC was maintainable as the
amount demanded by the respondent herein was an operational debt in
terms of the definition under Section 5(21) of the IBC.
C.A. No. 876 of 2021 Page 13 of 62
b) Despite non-payment of the operational debt to the respondent, neither
the appellant nor the respondent terminated the EPC contract. The EPC
contract was a continuous contract which could only be completed upon
fulfilment of the obligations stipulated thereunder or be terminated by
invocation of the termination clause by either of the parties. Since
neither course of action was taken by the parties, it was held that the
EPC contract between the parties continued to subsist. Hence, the
appellant owed an operational debt to the respondent in terms of the
contractual provisions.
c) As regards the prior existence of a dispute between the parties, it was
held that since the appellant did not respond to the respondent’s demand
notice dated 02.07.2018 issued under Section 8 of the IBC, therefore,
there was no question of a pre-existing dispute barring the Section 9
application of the respondent.
d) As regards the issue of Section 9 application being barred by limitation,
it was held that since the EPC contract had neither been terminated by
the parties, nor did it get frustrated due to efflux of time, the contract
continued to subsist. Hence, the plea of the appellant herein that the
Section 9 application was time-barred was rejected.
C.A. No. 876 of 2021 Page 14 of 62
14. Aggrieved by the aforesaid order, the appellant preferred an appeal with the
NCLAT. The NCLAT dismissed the appeal by way of the impugned
judgment on the following grounds:
a) The question whether the claim of the respondent under Section 9 of the
IBC was barred by limitation was answered in the negative. The NCLAT
observed that none of the parties terminated the EPC contract. As a result,
the same continued to subsist till date. As such, the appellant’s plea of
limitation could not be accepted as there was no termination of the EPC
contract.
b) As regards the issue whether the claim of the respondent was an
operational debt in terms of Section 5(21) of the IBC, it was held that the
respondent’s claim in the Section 9 application was an operational debt.
c) It was further held that since the EPC contract was silent on the frustration
of contract due to efflux of time, it could not be said that the contract had
automatically been frustrated.
d) As regards the question whether there existed any prior dispute in respect
of the claims of the respondent under Section 9 application, it was held
that the appellant raised no dispute once the respondent issued the
C.A. No. 876 of 2021 Page 15 of 62
demand notice under Section 8 of the IBC. Therefore, it could not be said
that the application under Section 9 of the IBC was liable to be rejected
on this ground.
e) In the last, it was observed that the EPC agreement was a continuing
contract. Therefore, the debt sought to be claimed by the respondent
continued to fall even on the date of the judgment as the EPC contract
was never terminated by either of the parties, be it the appellant or the
respondent. Thus, there was no error in the NCLT’s order admitting the
Section 9 application filed by the respondent.
B. SUBMISSIONS OF THE PARTIES
i. Submissions on behalf of the appellant
15. Mr. Shyam Divan, the learned senior counsel appearing on behalf of the
appellant, addressed himself on the following points:
• First, the operational debt being claimed is a time-barred debt and the
insolvency procedure under the IBC cannot be used to revive such time-
barred claims.
C.A. No. 876 of 2021 Page 16 of 62
• Secondly, the application under Section 9 of the IBC could not have
been filed in light of the pre-existing dispute between the parties in
respect of the operational debt.
16. As regards the question whether the claim of the respondent under Section 9
application is barred by limitation, the learned senior counsel submitted that
in the facts of the present matter, the due amount claimed by the respondent
was first quantified to the tune of Rs. 1210.78 crore for the first time in its
legal notice dated 25.07.2014. On the strength of this notice, the recovery
proceedings against the appellant ought to have been initiated within 3 years
of such breach, in terms of Article 137 of the Schedule to the Limitation Act,
1963.
17. It was submitted that even if the legal notice dated 25.07.2014 was
considered to be the date on which the default crystallized, yet the claim of
the respondent would remain hopelessly time-barred as the proceedings
under the IBC were initiated on 02.07.2018 when the statutory demand
notice was sent by the respondent to the appellant. It was the submission of
the appellant that the starting point for limitation began even earlier.
C.A. No. 876 of 2021 Page 17 of 62
18. The learned senior counsel submitted that the application of the respondent
under Section 9 of the IBC was liable to be rejected as the respondent placed
no explanation/averment on record as regards the exclusion or extension of
the limitation period in any manner whatsoever. It was submitted that the
respondent was unable to show any acknowledgment of the debt on behalf
of the appellant in writing or in the balance sheet, or through payment.
19. The learned senior counsel placed reliance on this Court’s dictum in Babulal
Vardharji Gurjar v. Veer Gurjar Aluminium Industries (P) Ltd., reported
in (2020) 15 SCC 1, to submit that it cannot be the intention of the IBC to
give a new lease of life to debts that are time-barred. The period of limitation
starts running from the date of the default of non-payment and the right to
apply under the IBC accrues from such date. If such default occurred over
three years prior to the date of filing of the application, the application would
be time-barred unless and until there has been an acknowledgment of the
debt.
20. It was further submitted that the judgment in Babulal Vardharji Gurjar
(supra) makes it clear that limitation is a mixed question of fact and law, and
therefore, any plea for extension or enlargement of the period of limitation
C.A. No. 876 of 2021 Page 18 of 62
must necessarily be accompanied by the relevant facts and evidence. Since
no such pleadings were made in the present matter, there could be no
extension or enlargement of the period of limitation.
21. As regards the acknowledgment of debt by a debtor, it was submitted by the
learned senior counsel that acknowledgment does not create a new right of
action, it merely renews the debt. He relied on this Court’s judgment in Asset
Reconstruction Co. (India) Ltd. v. Bishal Jaiswal, reported in (2021) 6 SCC
366 to submit that it is imperative that the statement on which a plea of
acknowledgment is based, must relate to a present subsisting liability.
22. Mr. Divan also brought to our attention this Court’s observations in
Sabarmati Gas Ltd. v. Shah Alloys Ltd., reported in (2023) 3 SCC 229
wherein it was held that the period of limitation for an application under
Section 9 of the IBC would be three years from the date when the right to
apply accrues as provided by Article 137 of the Limitation Act, 1963 (the
“Limitation Act”). It was further explained that the right to apply under the
IBC accrues on the date when default occurs and it is extendable only by
application of Section 5 of the Limitation Act.
C.A. No. 876 of 2021 Page 19 of 62
23. It was further submitted by the learned senior counsel that though the EPC
contract provided for arbitration as a method for dispute resolution, yet the
respondent elected not to exercise the same and instead, chose to file a time-
barred claim under the IBC. Mr. Divan argued that such conduct indicated
lack of bona fide on the part of the respondent in approaching the NCLT.
24. As regards the question whether there was a pre-existing dispute between the
parties, the learned senior counsel submitted that the legal notices dated
25.07.2014, 16.09.2014 and15.07.2015 respectively, sent by the respondent,
indicated that there were disputes arising out of the EPC contract. Mr. Divan
placed reliance on the judgment of this Court in Mobilox Innovations Pvt.
Ltd. v. Kirusa Software (P) Limited, reported in (2018) 1 SCC 353 to submit
that the application filed by an operational creditor under Section 9 of the
IBC was liable to be rejected if there was a pre-existing dispute between the
parties in respect of the debt which forms the subject matter of the
application. It was argued that the resolution process under the IBC cannot
be used for the purpose of recovery of debt.
25. In the last, the learned senior counsel prayed for the relief to set aside the
judgment and order delivered by the NCLAT dated 01.02.2021 and to reject
C.A. No. 876 of 2021 Page 20 of 62
the admission of the Section 9 application of the respondent on the grounds
that the debt is time-barred and there exists a pre-existing dispute between
the parties.
ii. Submissions on behalf of the respondent
26. Mr. Nitin Bhardwaj, the learned counsel appearing on behalf of the
respondent, addressed himself on the following questions:
• Whether the EPC contract came to be terminated or frustrated due to
efflux of time?
• Whether the debt claimed by the respondent under the Section 9 IBC
application was barred by limitation?
• Whether the amount claimed by the respondent under the Section 9 IBC
application was in the nature of operational debt under Section 5(21) of
the IBC or damages?
• Whether there was a pre-existing dispute between the parties that would
bar the respondent from filing the application under Section 9 of the
IBC?
27. The learned counsel placed the material facts before us to submit that non-
payment of the entire advance amount and the amounts due upon completion
C.A. No. 876 of 2021 Page 21 of 62
of the subsequent milestones was a failure on the part of the appellant to fulfil
its obligations under the EPC contract. This compelled the respondent to
issue notice of suspension of works dated 30.07.2011.
28. It was submitted by the learned counsel that the suspension in no manner
amounted to termination, and the EPC contract could have been revived by
either of the parties by fulfilling the terms of the contract. He submitted that
treating suspension as termination of the EPC contract would be contrary to
the terms of the contract.
29. It was submitted that the contract could have been terminated only by way
of invocation of Clause 14 of the EPC contract which reads thus:
“14. l Termination for Owner's Convenience. Owner may
for its convenience terminate any part of the Supplies or
any or all remaining Supplies hereunder at any time upon
at least 30 (Thirty) days' prior written notice to Supplier
specifying the part of the Supplies to be terminated and the
effective date of termination. Upon receipt of such notice,
Supplier shall promptly initiate steps to stop provision of
such terminated Supplies. In the event of a partial
termination, Supplier shall continue to produce the part of
the Supplies not terminated. In case of a termination of
part of the Supplier's Work, Owner shall authorize a Scope
Change Order making reasonable adjustments to one or
more of the Schedule Unit(s). Completion date, Scheduled
Facility Completion Date, the Contract Price, the Contract
C.A. No. 876 of 2021 Page 22 of 62
Schedule, the Performance Guarantees and any other
affected provisions of this Agreement, as applicable. In the
event of termination by Owner under this Article 14.1,
Owner shall pay to Supplier (or Supplier may retain) such
amounts as are required pursuant to Article 4.4 hereof In
case of a termination of all or remaining part of the
Supplier's Work, the Owner shall provide at least 30 days'
prior written notice to Supplier providing details of the
reasons for such termination and the effective date of
termination. Owner will authorize a Scope Change Order
making reasonable adjustments to the Contract Price as
applicable.
14.2 Termination Upon Non-Payment by Owner. If Owner
fails to pay to Supplier any payment as required hereunder
and such failure continues for 25 days after written notice
thereof has been given to Owner by Supplier, then Supplier
shall give ten days' prior written notice thereof to Owner
and the Financing Parties, and thereafter may stop all
performance of Supplier's obligations hereunder until
Supplier receives payment of all amounts then due plus
reasonable suspension and resumption expenses. Owner
shall be responsible for reimbursement of all costs
incurred by Supplier as a result of the stoppage of
Supplier's work. If Supplier's performance hereunder is
suspended by Supplier pursuant to this Article 14.2, Owner
will authorise a Scope Change Order making an equitable
adjustment to the Scheduled Unit(s) Completion Date,
Scheduled Facility Completion Date and the Contract
Schedule and required reasonable adjustments to one or
more of the Contract Price, the Terms of Payment and any
relevant terms and conditions of this Agreement, as
appropriate. If such suspension continues uninterrupted
C.A. No. 876 of 2021 Page 23 of 62
for at least four months, or if two or more suspensions exist
for an aggregate of at least four months, Supplier may
terminate this Agreement; provided that Supplier shall
give the Financing Parties a further 60 days prior written
notice, and opportunity to cure, before terminating this
Agreement. In the event of such a termination by Supplier,
Own.er shall pay to Supplier (or Suppler may retain) such
amounts as are required pursuant to Article 4.4. hereof.”
30. It was vehemently argued by the learned counsel that the EPC contract had
never been terminated by either of the parties. Further in a suspended EPC
contract which had not been terminated or revived, there was no question of
frustration due to efflux of time.
31. Mr. Bhardwaj submitted that the appellant was always in a position to
terminate the EPC contract after paying the dues of the respondent that had
accrued as on the date, as per the terms of the contract. However, no such
action was taken by the appellant. Therefore, the EPC contract continued to
exist, and the appellant was duty bound to clear the dues payable to the
respondent. In such a scenario, there could be no frustration of contract by
efflux of time.
32. As regards the issue whether the claim of the respondent was barred by
limitation, it was submitted that the law of limitation would not jeopardize
C.A. No. 876 of 2021 Page 24 of 62
its claim because there exists a continuous cause of action between the
parties. The learned counsel placed the aforesaid submission on the ground
that the EPC contract had been suspended vide notice dated 30.07.2011
because of non-payment of dues by the appellant. However, the works could
start again at any time once the appellant cleared dues or alternatively, the
EPC agreement could have been terminated as per Clause 14 by clearing all
the dues payable to the respondent till date. It was submitted by the
respondent that since the appellant had chosen neither of the said courses of
action, the EPC contract subsists. Therefore, there was a continuing cause of
action thereby putting the claim of the respondent well within the limitation
period.
33. As regards the question whether the claims of the respondent amounted to
operational debt under Section 5(21) of the IBC or were in the nature of
damages, Mr. Bhardwaj submitted that the Resolution Professional (“RP”)
had already undertaken the scrutiny of the books of accounts of the appellant
as well as the claim of the respondent. It was submitted that the quantification
of claim was the sole responsibility of the RP and he had accordingly rejected
the parts of the claim that were concluded to be in the nature of damages and
C.A. No. 876 of 2021 Page 25 of 62
proceeded with the part of the claim that was found to be due and payable as
operational debts under the law.
34. Mr. Bhardwaj also canvassed submissions on whether there was pre-existing
dispute between the parties. He submitted that at no stage of the contractual
relationship between the parties had any dispute as regards the claim amount
in question was raised by the appellant. It is an admitted fact that the
existence of the debt due and payable to the respondent had never been
denied by the appellant in any manner before the application under Section
9 of the IBC was filed.
35. It was submitted that the notices dated 25.07.2014, 16.09.2014 and
15.07.2015 respectively, were sent by the respondent to seek the payment of
their dues through the years and none of the aforesaid notices were ever
denied or disputed by the appellant. Therefore, the Section 9 application filed
by the respondent was not barred in law on account of the existence of a prior
dispute between the parties in respect of the same claim.
C.A. No. 876 of 2021 Page 26 of 62
C. ISSUES TO BE DETERMINED
36. Having heard the learned counsel appearing for the parties and having gone
through the materials on record, the following questions fall for our
consideration:
(i) Whether the EPC contract entered into by and between the appellant
and respondent was frustrated by the efflux of time?
(ii) Whether the monies claimed by the respondent in the application under
Section 9 of the IBC constitute ‘operational debt’ as defined under
Section 5(21) of the IBC?
(iii) Whether there existed a prior dispute in respect of the claims of
respondent?
(iv) Whether the application filed by the respondent under Section 9 of the
IBC was time-barred in respect of the dues amounting to ‘operational
debt’?
D. ANALYSIS
(i) Subsistence of the EPC contract
37. The parties have extensively canvassed submissions on whether the EPC
contract continued to subsist or got frustrated due to the efflux of time. It is
C.A. No. 876 of 2021 Page 27 of 62
necessary for us to look into the clauses that stipulate the terms of termination
of the EPC contract, i.e., Clauses 14.1 and 14.2 respectively. The aforesaid
clauses read thus:
“14.1 Termination for Owner's Convenience. Owner may
for its convenience terminate any part of the Supplies or
any or all remaining Supplies hereunder at any time upon
at least 30 (Thirty) days' prior written notice to Supplier
specifying the part of the Supplies to be terminated and the
effective date of termination. Upon receipt of such notice,
Supplier shall promptly initiate steps to stop provision of
such terminated Supplies. In the event of a partial
termination, Supplier shall continue to produce the part of
the Supplies not terminated. In case of a termination of
part of the Supplier's Work, Owner shall authorize a Scope
Change Order making reasonable adjustments to one or
more of the Scheduled Unit(s) Completion Date, Scheduled
Facility Completion Date, the Contract Price, the Contract
Schedule, the Performance Guarantees and any other
affected provisions of this Agreement, as applicable. In the
event of termination hy Owner under this Article 14.1.
Owner shall pay to Supplier (or Supplier may retain) such
amounts as are required pursuant to Article 4.4 hereof. In
case of a termination of all or remaining part of the
Supplier's Work, the Owner shall provide at least 30 days'
prior written notice to Supplier providing details of the
reasons for such termination and the effective date of
termination. Owner will authorize a Scope Change Order
making reasonable adjustments to the Contract Price as
applicable.
C.A. No. 876 of 2021 Page 28 of 62
14.1.1 Owner's Right to Suspend Completion of the
Supplier's Work. Owner may elect to suspend completion
of all or any part of the Supplies hereunder upon at least
15 (fifteen) days' prior written notice to Supplier (or, in
emergency situations, upon such prior notice as
circumstances permit) indicating (a) the portion of the
Supplies the completion of which Owner has elected to
defer; (b) Owner's estimate of the duration of such
suspension; and (c) the effective date of such suspension of
such Supplies. Upon receipt of and consistent with the
effective date of such notice, Supplier shall stop production
of the Supplies that Owner has elected to defer and shall
continue to complete production of the balance of the
Supplies. In the event of a suspension of the Supplier's
performance hereunder pursuant to this Article 14.1.1,
Owner will authorize a Scope Change Order making
required adjustments to one or more of the Scheduled
Unit(s) Completion Date, Scheduled Facility Completion
Date, the Contract Price, the Terms of Payment, the
Contract Schedule, and the Performance Guarantees, as
applicable.
14.2 Termination Upon Non-Payment by Owner. If Owner
fails to pay to Supplier any payment as required hereunder
and such failure continues for 25 days after written notice
thereof has been given to Owner by Supplier, then Supplier
shall give ten days' prior written notice thereof to Owner
and the Financing Parties, and thereafter may stop all
performance of Supplier's obligations hereunder until
Supplier receives payment of all amounts then due plus
reasonable suspension and resumption expenses. Owner
shall be responsible for reimbursement of all costs
incurred by Supplier as a result of the stoppage of
C.A. No. 876 of 2021 Page 29 of 62
Supplier's work. If Supplier's performance hereunder is
suspended by Supplier pursuant to this Article 14.2, Owner
will authorize a Scope Change Order making an equitable
adjustment to the Scheduled Unit(s) Completion Date,
Scheduled Facility Completion Date and the Contract
Schedule and required reasonable adjustments to one or
more of the Contract Price, the Terms of Payment and any
relevant terms and conditions of this Agreement, as
appropriate. If such suspension continues uninterrupted
for at least four months, or if two or more suspensions exist
for an aggregate of at least six months, Supplier may
terminate this Agreement; provided that Supplier shall give
the Financing Parties a further 60 days prior written
notice, and opportunity to cure, before terminating this
Agreement. In the event of such a termination by Supplier,
Owner shall pay to Supplier (or Supplier may retain) such
amounts as are required pursuant to Article 4.4 hereof.”
(Emphasis supplied)
38. The bare perusal of the aforesaid clauses indicates that the EPC contract
could have been terminated by either of the parties. Clause 14.1 provides that
the appellant may terminate the EPC contract subject to a notice of 30 days
to the respondent and clearing of the respondent’s dues for the works already
completed. Alternatively, Clause 14.1.1 empowers the appellant to suspend
a portion of works and defer their completion upon provision of a notice of
15 days to the respondent.
C.A. No. 876 of 2021 Page 30 of 62
39. Clause 14.2 provides for two tier of actions by the respondent. First, if the
appellant fails to make payments as per the payment schedule to the EPC
contract for more than 25 days after the written notice, the respondent has
the right to stop the performance of its obligations under the contract till the
time payment is received. Secondly, if the period of suspension is prolonged
due to non-payment of the respondent’s dues for a period of at least four
months, the respondent is conferred with the right to terminate the EPC
contract. It is worth noting that termination by the Supplier or the respondent
herein is not automatic when the suspension period crosses more than four
months. The usage of the word ‘may’ indicates that an option has been
provided to the respondent to terminate.
40. In the present matter, neither the appellant nor the respondent elected to
terminate the EPC contract despite severe delays in fulfilment of obligations.
Since the agreement between the parties is silent on whether time is the
essence of the contract, we say without any manner of doubt that the parties
intended for the EPC contract to subsist.
41. As regards the appellant’s contention that the EPC contract got frustrated due
to efflux of time, the same is liable to be rejected. We say so because there
C.A. No. 876 of 2021 Page 31 of 62
can be no frustration due to efflux of time. The expression “effluxion of time”
is used to describe situations in which a particular contract comes to a close
automatically upon completion of all obligations thereunder or with the
expiry of the time period stipulated for the operation of the agreement.
42. On the other hand, the doctrine of frustration of contract is triggered when a
supervening event results in the automatic discharge of liability of parties to
the contract. This is because such supervening event makes it impossible or
unlawful for the contract to be performed. Unlike effluxion of time which is
natural and foreseen mode of discharge of obligations, frustration is
discharge of the contract because of an unforeseen extraneous event.
Therefore, it would be incorrect to say that there can be frustration of contract
due to efflux of time.
43. Further, the perusal of the EPC contract and the conduct of the parties at the
material time, indicate that the contractual obligations stipulated in the
contract remained unfulfilled. We find it apposite to clarify at the outset that
we are not concerned with the causes due to which the appellant did not make
payments in consonance with the payment schedule, as the substantive
dispute in that regard cannot be adjudged in a statutory appeal from the
C.A. No. 876 of 2021 Page 32 of 62
NCLAT. However, there is no gainsaying that the works were suspended
because of such non-payment.
44. In our considered view, the suspension of works cannot be considered as a
supervening impossibility as per the requirement under Section 56 of the
Indian Contract Act, 1872 for the doctrine of frustration to apply. This Court
in Boothalinga Agencies v. V.T.C. Poriaswami Nadar, reported in 1968
SCC OnLine SC 135 observed that a circumstance brought about by a
party’s election cannot frustrate the contract. The relevant paragraph reads
thus:
“12. (…) We think the principle of this case applies to the
Indian law and the provisions of Section 56 of the Indian
Contract Act cannot apply to a case of “self-induced
frustration”. In other words, the doctrine of frustration of
contract cannot apply where the event which is alleged to
have frustrated the contract arises from the act or election
of a party. (…)”
(Emphasis supplied)
45. Since the suspension of works by the respondent arose from the non-
performance of obligations under the EPC contract, the same cannot be
categorized as a supervening impossibility that was outside the control of the
C.A. No. 876 of 2021 Page 33 of 62
parties. Therefore, there was no question of the EPC contract being
frustrated.
46. Further, it must be clarified that since the parties did not complete their
respective obligations under the EPC contract, it cannot be said that the
agreement came to a natural close. This is especially so because the EPC
contract itself provides no strict timeline for the completion of works.
Furthermore, the provisions regarding extension of time and performance
guarantee tests indicate that the EPC contract could not have come to a close
without completion of works or final inspection of the facility to be
constructed. Therefore, in our considered view, the principle of efflux of time
is also not applicable to the case at hand.
47. In view of the aforesaid, we say without any manner of doubt that the EPC
contract continued to subsist.
(ii) Amount claimed by the respondent is operational debt
48. The appellant had submitted before the NCLAT that the amount claimed by
the respondent was not in the nature of ‘operational debt’ under Section 5(21)
of the IBC. In our considered view, the material on record shows that the
respondent in its legal notices had claimed monies under two broad heads:
C.A. No. 876 of 2021 Page 34 of 62
• Payment of the amounts due under the first, second, third and fourth
milestones in the payment schedule to the EPC contract;
• Suspension and demobilization charges and interest thereupon.
49. Before we deal with the question whether the above-mentioned heads can be
the subject matter of an application under Section 9 of the IBC, it is apposite
to understand the meaning and scope of ‘operational debt’ under Section
5(21) of the IBC.
50. Section 5(21) of the IBC defines ‘operational debt’ as “a claim in respect of
the provisions of goods or services, including employment or a debt in
respect of the [payment] of dues arising under any law for the time being in
force and payable to the Central Government, any State Government or any
local authority.”
51. A bare textual reading of the provision indicates that any amount that accrues
to an operational creditor on account of the goods and services provided by
it to an operational creditor would be treated as operational debt. There is no
doubt that the EPC contract is a works contract which involves procurement
of goods as well as construction of the natural gas facility. Therefore, all
payments that the parties agreed to pay upon completion of the stages of the
C.A. No. 876 of 2021 Page 35 of 62
works as mentioned in the payment schedule to the EPC contract, can be
categorized as operational debt once they become payable.
52. Insofar as the amount claimed under the heads of suspension and
demobilization charges is concerned, there is no gainsaying that the same
would be in the nature of damages. It is a settled position of law that
damages, whether liquidated or unliquidated, cannot be treated as
operational debt unless and until they are assessed and crystallized by way
of adjudication by a court of competent jurisdiction. We say so because the
NCLT and NCLAT are not the appropriate fora for determination of disputes.
Their functions and powers are for the purpose of ensuring survival of a
particular company and alternatively, to ensure maximization of repayment
capabilities in the event of liquidation.
53. Therefore, disputes that arise from breach of the contract cannot give rise to
an operational debt till the time the debt becomes crystallized and legally
enforceable. In the present matter, it was argued that the suspension, idling
and demobilization charges accrued to the respondent due to the appellant’s
alleged breach of contract by failure to pay in terms of the EPC contract.
Since, there is no record of a suit or arbitration that assessed, adjudicated and
C.A. No. 876 of 2021 Page 36 of 62
crystallized these claims, the amounts claimed under these heads cannot be
treated as operational debt.
54. However, the amounts required to be paid by the appellant to the respondent
as per the EPC contract and the payment schedule thereto, qualify as
operational debt as they were supposed to be fulfilled as a consideration for
the works undertaken by the respondent in terms of the EPC contract.
(iii) Pre-existing dispute between the parties
55. The third leg of the appellant’s argument was that there was pre-existing
dispute between the parties on the date when the respondent sent the statutory
demand notice under Section 8 of the IBC and filed an application under
Section 9 thereof.
56. It is a settled position of law that an insolvency application under the IBC
cannot be filed for such amounts/debts that are the subject matter of a dispute
between the parties. Such dispute must be substantive and must be a matter
of clear contestation by both the parties.
57. This Court in Mobilox Innovations (P) Ltd. v. Kirusa Software (P) Ltd.,
reported in (2018) 1 SCC 353 held that a Section 9 application under the
C.A. No. 876 of 2021 Page 37 of 62
IBC is liable to be rejected if it was found that there was a pre-existing
dispute between the parties in respect of the same claims as raised by the
operational creditor in its insolvency application.
58. As regards the question, when the dispute would be considered to be pre-
existing before the application under Section 9 of the IBC, it was observed
that in terms of Section 8(2) of the IBC, it would be necessary for the
corporate debtor to respond to the statutory demand notice sent by the
operational creditor under Section 8(1) of the IBC within ten days. In such
reply, the corporate debtor must bring to the notice of the operational
creditor, inter alia, the existence of a dispute or record of the pendency of
the suit or arbitration proceedings filed before the receipt of the statutory
demand notice. Section 8 of the IBC reads thus:
“8. Insolvency resolution by operation creditor––
(1) An operational creditor may, on the occurrence of a
default, deliver a demand notice of unpaid operational
debtor copy of an invoice demanding payment of the
amount involved in the default to the corporate debtor in
such form and manner as may be prescribed.
(2) The corporate debtor shall, within a period of ten days
of the receipt of the demand notice or copy of the invoice
mentioned in sub-section (1) bring to the notice of the
operational creditor
C.A. No. 876 of 2021 Page 38 of 62
(a) existence of a dispute, if any, or record of the pendency
of the suit or arbitration proceedings filed before the
receipt of such notice or invoice in relation to such dispute;
(b) the
payment of unpaid operational debt
(i) by sending an attested copy of the record of electronic
transfer of the unpaid amount from the bank account of the
corporate debtor; or
(ii) by sending an attested copy of record that the
operational creditor has encashed a cheque issued by the
corporate debtor.
Explanation.--For the purposes of this section, a "demand
notice" means a notice served by an operational creditor
to the corporate debtor demanding payment of the
operational debt in respect of which the default has
occurred.”
(Emphasis supplied)
59. It is worth noting that the word ‘or’ in Section 8(2)(a) was inserted after the
pronouncement of the judgment in Mobilox (supra) to give effect to its
observations that the existence of dispute cannot be determined solely on,
whether the parties had instituted a suit or arbitration proceeding. It was held
in Mobilox (supra) that the existence of a prior dispute irrespective of
whether it had already progressed to the stage of civil suit or arbitration,
C.A. No. 876 of 2021 Page 39 of 62
would be a bar to insolvency proceedings pursuant to Section 9 of the IBC.
The rationale for holding thus was that allowing insolvency proceedings in
respect of claims that had already been disputed through notices or otherwise
could result in multiplicity of proceedings. The insolvency process would be
delayed as there would be no bar on the parties to pursue the resolution of
the dispute by way of a suit or arbitration. Therefore, there is no requirement
that the parties must show that a pre-existing dispute was being litigated or
was the subject matter of an arbitration. The relevant observations in
Mobilox (supra) read thus:
“38. It is, thus, clear that so far as an operational creditor
is concerned, a demand notice of an unpaid operational
debt or copy of an invoice demanding payment of the
amount involved must be delivered in the prescribed form.
The corporate debtor is then given a period of 10 days from
the receipt of the demand notice or copy of the invoice to
bring to the notice of the operational creditor the existence
of a dispute, if any. We have also seen the notes on clauses
annexed to the Insolvency and Bankruptcy Bill of 2015, in
which “the existence of a dispute” alone is mentioned.
Even otherwise, the word “and” occurring in Section
8(2)(a) must be read as “or” keeping in mind the
legislative intent and the fact that an anomalous situation
would arise if it is not read as “or”. If read as “and”,
disputes would only stave off the bankruptcy process if they
are already pending in a suit or arbitration proceedings
and not otherwise. This would lead to great hardship; in
that a dispute may arise a few days before triggering of the
C.A. No. 876 of 2021 Page 40 of 62
insolvency process, in which case, though a dispute may
exist, there is no time to approach either an Arbitral
Tribunal or a court. Further, given the fact that long
limitation periods are allowed, where disputes may arise
and do not reach an Arbitral Tribunal or a court for up to
three years, such persons would be outside the purview of
Section 8(2) leading to bankruptcy proceedings
commencing against them. Such an anomaly cannot
possibly have been intended by the legislature nor has it so
been intended. We have also seen that one of the objects of
the Code qua operational debts is to ensure that the
amount of such debts, which is usually smaller than that of
financial debts, does not enable operational creditors to
put the corporate debtor into the insolvency resolution
process prematurely or initiate the process for extraneous
considerations. It is for this reason that it is enough that a
dispute exists between the parties.”
(Emphasis supplied)
60. This Court in Mobilox (supra) further held that the inquiry into whether a
dispute already existed between the parties qua the claim amount, it is
necessary to ascertain the genuineness of the same. In other words, the
dispute whose existence is sought to be evidenced should not be spurious,
hypothetical, illusory or misconceived. We also find it apposite to reiterate
the observation in Mobilox (supra) that the court’s function is restricted to
perceiving the genuineness of the dispute and it cannot travel beyond to make
C.A. No. 876 of 2021 Page 41 of 62
observations as regards the merits of the dispute. The relevant paragraphs in
Mobilox (supra) are reproduced below:
“51. It is clear, therefore, that once the operational creditor
has filed an application, which is otherwise complete, the
adjudicating authority must reject the application under
Section 9(5)(i)(d) if notice of dispute has been received by
the operational creditor or there is a record of dispute in
the information utility. It is clear that such notice must
bring to the notice of the operational creditor the
“existence” of a dispute or the fact that a suit or
arbitration proceeding relating to a dispute is pending
between the parties. Therefore, all that the adjudicating
authority is to see at this stage is whether there is a
plausible contention which requires further investigation
and that the “dispute” is not a patently feeble legal
argument or an assertion of fact unsupported by evidence.
It is important to separate the grain from the chaff and to
reject a spurious defence which is mere bluster. However,
in doing so, the Court does not need to be satisfied that the
defence is likely to succeed. The Court does not at this
stage examine the merits of the dispute except to the extent
indicated above. So long as a dispute truly exists in fact
and is not spurious, hypothetical or illusory, the
adjudicating authority has to reject the application.”
(Emphasis supplied)
61. What is discernible from the aforesaid exposition is that it is not necessary
that a suit or arbitration proceeding be pre-existing to evidence a dispute.
Rather, what is required to be highlighted is that there was a pre-existing
C.A. No. 876 of 2021 Page 42 of 62
dispute between the parties vide the conduct of the parties, communication,
etc.
62. We may now proceed to consider the appellant’s submission that a dispute
was evident from the respondent’s legal notices dated 25.07.2014,
16.09.2014 and 15.07.2015 respectively. We may be tempted to hold that
there was a pre-existing dispute if we constrain ourselves to the aforesaid
legal notices and the observations made in Mobilox (supra). However, what
is also required to be seen is the conduct of the appellant as the corporate
debtor. It is an admitted fact that the appellant responded to none of the
notices sent by the respondent. It also did not reply to the statutory demand
notice dated 02.07.2018 to highlight that the legal notices by the respondent
indicated a dispute as regards the amount being claimed.
63. Before we make observations as regards the conduct of the appellant, we find
it apposite to clarify that as a general rule, silence cannot be considered to be
an indicator of no dispute. However, in the present matter, the appellant’s
total and consistent silence across multiple legal notices sent prior to the
filing of the Section 9 application is strong evidence to support the
C.A. No. 876 of 2021 Page 43 of 62
respondent’s submission that there was no dispute that in fact existed at the
relevant time.
64. Further, in our considered view, the fact that the appellant placed its defence
for the first time in the reply to the Section 9 application and disputed the
respondent’s claims without anchoring such defence in its conduct at the
material time indicates that there was no dispute that existed before the
Section 9 application, as far as the appellant was concerned. Such conduct,
in our opinion, was an afterthought to resist exposure to the insolvency
process. Hence, the issue as regards the existence of a prior dispute between
the parties must be answered in the negative.
(iv) Respondent’s claim is barred by limitation
65. In the present matter, the respondent’s claim crystallized in 2012 when the
invoices with the BBU were acknowledged by the appellant in its
communication to the Chief Engineer, IRP Division, Central Electricity
Authority. It is apposite to mention that the debt (partial amount which can
be categorized as operational debt in view of the aforesaid part of this
judgment) arising from non-payment of amount due under the payment
schedule, remained unpaid since February 2011 and February 2012
respectively.
C.A. No. 876 of 2021 Page 44 of 62
66. The respondent was constrained to issue the notice of suspension of works
on 30.07.2011 after it did not receive payments even after completion of the
first, second and third milestone in the payment schedule to the EPC contract.
The right to suspend works by the respondent, as discussed in the aforesaid
part of this judgment, arose from Clause 14.2 of the EPC contract. However,
despite suspension of works, subsequent idling and demobilization of the site
and the consistent non-payment of dues by the appellant, none of the parties
elected to terminate the EPC contract in terms of Clause 14.1 and 14.2
respectively. Therefore, the contract continued to subsist.
67. The respondent sent legal notices dated 25.07.2014, 16.09.2014 and
15.07.2015 respectively after the lapse of more than four years since its claim
crystallized and the right to sue accrued to it. The learned senior counsel
appearing for the appellant would argue that the legal notices raised the
dispute as regards the non-payment of the amounts specified in the payment
schedule after the limitation period of three years had already passed.
Further, the statutory demand notice under Section 8 of the IBC was sent by
the respondent after the lapse of more than seven years since the default
occurred and its claim crystallized.
C.A. No. 876 of 2021 Page 45 of 62
68. The learned counsel appearing for the respondent would argue that its
statutory demand notice dated 02.07.2018 was within a period of three years
from its last legal notice dated 15.07.2015. Even otherwise, the limitation
period would not start running as the continuity of the EPC contract provided
continuous cause of action.
69. In such circumstances referred to above, could it be said that because the
contract continued to subsist, the respondent had continuous cause of action?
In other words, would the subsistence of the EPC contract result in the
extension of the limitation period beyond the statutory three years period
provided in Article 137 of the Limitation Act, 1963 for the purpose of filing
an application under Section 9 of the IBC? In our considered view, the
answer to the aforesaid question must be an emphatic ‘No’.
70. We say so because Section 238A of the IBC states that the provisions of the
Limitation Act, 1963, as far as maybe, would apply to the proceedings or
appeals before, inter alia, the Adjudicating Authority/ NCLT or NCLAT.
Therefore, the ‘right to sue’ accrues on the date when the default takes place.
Section 3(12) of the IBC defines ‘default’ which reads thus:
“(12) "default" means non-payment of debt when whole or
any part or instalment of the amount of debt has become
C.A. No. 876 of 2021 Page 46 of 62
due and payable and is not paid by the debtor or the
corporate debtor, as the case may be;”
71. In the present matter, the operational debt became due and payable on the
date of the default, i.e., on 15.02.2011 and 13.07.2011. The liability to pay in
respect of both the defaults came to be acknowledged by the appellant on
05.01.2012 and 03.02.2012 respectively.
72. A default arising out of non-payment of the due and payable amount,
provides cause of action on the date when the default occurs and cannot serve
as a continuing cause of action. We say so because though an unpaid debt
may cause continuous damage, yet it does not cause continuing legal injury.
In other words, the legal default itself happens only once even though its
consequences may be continuing in nature. Therefore, the respondent’s
assertion that the subsistence of contract would provide it with continuing
cause of action is incorrect and liable to be rejected.
73. The “default” envisaged under Section 3(12) of the IBC occurs on non-
payment of debt when whole or any part/instalment of the debt becomes due
and payable but is not paid by the debtor. Thus, Section 3(12) grounds the
occurrence of default at a singular point in time. The mere subsistence of the
C.A. No. 876 of 2021 Page 47 of 62
EPC contract will not give continuing cause of action in respect of the
defaulted amount.
74. This Court in Next Education India (P) Ltd. v. K12 Techno Services,
reported in 2023 SCC OnLine SC 1117, has held that the Adjudicating
Authority must consider invoices for payment in respect of which the default
occurred during the three years preceding the date of filing the application
under Section 9. This implies that to determine whether the application under
Section 9 is within limitation or not, one would have to consider whether the
default had occurred within three years of filing the application. The relevant
portion of the judgment reads thus:
“2. At the outset, it is required to be noted that, in fact, the
appellant herein, who claimed to be the "operational
creditor" raised 187 different invoices for the digital
classroom solution services provided for the period
between March 12, 2011 and June 30, 2017. The amounts
under different invoices were unpaid, which gave rise to
the appellant to initiate the proceedings under section 9 of
the IBC before the NCLT. The NCLT considering the
starting point of limitation as March 12, 2011 held that the
claim is barred by limitation. However, the NCLT did not
take into consideration the subsequent invoices at least
preceding three years from the date of filing of section 9
application, which ought to have been considered. Under
the circumstances, the NCLT ought to have considered the
invoices at least for the period preceding three years from
C.A. No. 876 of 2021 Page 48 of 62
the date of the application under section 9, rather than
considering the starting point of limitation as March 12,
2011. Under the circumstances, the order(s) passed by the
NCLT and affirmed by the NCLAT are unsustainable.”
(Emphasis supplied)
75. The aforesaid exposition of law clarifies that under the IBC, the Adjudicating
Authority cannot treat all invoices for payment in aggregate and consider the
date on which the first invoice came to be issued as the starting point for
limitation in respect of the entire set of invoices for which the claim was
filed.
76. For the purpose of determining the starting point of limitation, the governing
principle is that each invoice generates its own date of default when it
becomes due and payable. What is discernible from the exposition in Next
Education (supra) is that where the claim is founded on multiple invoices
spanning several dates of defaults, the invoices that fall within the three years
preceding the date of application ought to be considered. What has been said
in so many words is that limitation is tied to each invoice’s own due date.
Where the claim arises from multiple invoices, it cannot be said that
limitation would start from the date of the first invoice or the last invoice as
per the wishes of the applicant. Put simply, the decision in Next Education
C.A. No. 876 of 2021 Page 49 of 62
(supra) lends to the understanding that all invoices must be considered
separately when determining the date of default.
77. In the present matter, the default arises from non-payment of dues despite
completion of the first, second and third milestones in the payment schedule
to the EPC contract. Further, as regards the fourth milestone, the respondent
sent to the appellant its BBU. After acknowledgment in January and
February 2012 by the appellant, the limitation in respect of the aforesaid
defaults started afresh. These dates have also been mentioned by the
respondent in its demand notice dated 02.07.2018 as the dates when the
default occurred.
78. At this juncture, we may refer to Form 3 provided in the Insolvency and
Bankruptcy (Application to Adjudicating Authority) Rules, 2016 (the
“Rules, 2016”) that stipulates the form in which the demand notice under
Section 8 of the IBC is supposed to be issued. Form 3, inter alia, requires
that the statutory demand notice should specify the date from which the debt
fell due, i.e., the date on which the default occurred.
79. This Court in B. Prashanth Hegde v. SBI, reported in 2026 SCC OnLine
SC 197 (wherein one of us, namely Manoj Misra, J., was a part of the Bench)
C.A. No. 876 of 2021 Page 50 of 62
observed in the context of applications made under Section 7 of the IBC, that
the forms prescribed in the Rules, 2016 serve the purpose of bringing out the
necessary ingredients for presentation of the insolvency application. As
regards the requirement of providing the date on which the debt became due,
it was observed that specifying the date of default helps the Adjudicating
Authority to assess whether the debt has become time-barred or not. The
relevant observations in Prashanth Hegde (supra) read thus:
“40. In our view, a conjoint reading of sub-sections (1), (2)
and (5) of section 7 makes it clear that an application
under section 7 of a financial creditor for initiating the
corporate insolvency resolution process of the corporate
debtor hinges on a default on part of the corporate debtor
of financial debt of an amount exceeding the specified
threshold. The form prescribed for making the application
inter alia serves the purpose of bringing out the necessary
ingredients for presentation of an application under
section 7(1) of the Insolvency and Bankruptcy Code. The
purpose of providing the date of default is to show that the
debt is due and payable, i.e., it has not become time barred.
Therefore, in our view, if the application is substantially in
conformity with the prescribed form and discloses the
necessary ingredients for making an application under
sub-section (1) of section 7 and provides the relevant
materials/information to substantiate those ingredients,
the purpose of adhering to the form is served, and such
application is not liable to be rejected under clause (b) of
sub-section (5) of section 7 of the Insolvency and
Bankruptcy Code on the ground of any insignificant
C.A. No. 876 of 2021 Page 51 of 62
omission or error in the application. The aforesaid view
finds support from use of the expression “may” before
“reject” in section 7(5)(b) of the Insolvency and
Bankruptcy Code. This means that if the Adjudicating
Authority is satisfied from the materials placed before it in
the application that all the necessary ingredients are
satisfied for presentation of an application under section
7(1) of the Insolvency and Bankruptcy Code, it may not
reject the application for an insignificant omission or non-
adherence to the form.”
(Emphasis supplied)
80. In our considered view, the observations of this Court in the aforesaid
decision are applicable on the demand notice to be issued for making an
application under Section 9 of the IBC. The respondent itself mentioned in
its demand notice dated 02.07.2018 that the debt fell due on 25.02.2011. The
portion of the debt amount mentioned in the demand notice that would
qualify as operational debt, was acknowledged by the appellant in January
and February 2012. Therefore, the respondent was supposed to bring action
on these defaults within three years from January and February, 2012.
However, the same was not done.
81. Subsequently, after a lapse of four years, the respondent sent three legal
notices dated 25.07.2014, 16.09.2014 and 15.07.2015 respectively.
However, no response was given by the appellant. In such a scenario, could
C.A. No. 876 of 2021 Page 52 of 62
it be said that the act of sending legal notices would reset the period of
limitation and commence the cause afresh? In our considered view, the
answer to this question must be an emphatic ‘No’.
82. The benefit of extension of limitation by way of acknowledgment in terms
of Section 18 of the Limitation Act is available only where, before the
expiration of the prescribed period, an acknowledgment of liability has been
made in writing by the party against whom the claim stands. In the absence
of any such acknowledgment, mere service of a notice of demand would
neither revive a time-barred claim nor would give rise to a fresh cause of
action.
83. It is apposite to clarify that though the statutory demand notice dated
02.07.2018 was issued within the period of three years from the last legal
notice dated 15.07.2015 sent by the respondent, yet it would still be outside
the bounds of limitation considering that the legal notice dated 15.07.2015
could not have reset the clock by itself in the absence of any acknowledgment
of liability.
84. This Court in Babulal Vardharji Gurjar (supra) summarized and clarified
the scope of the IBC after Section 238A was enacted. It was observed that it
C.A. No. 876 of 2021 Page 53 of 62
was not the intention of the IBC to give a new lease of life to the debts that
were already time-barred. Further, default occurs on the date of actual non-
payment by the corporate debtor when the debt becomes due and payable. If
application is filed beyond the period of three years from the date of default,
the application would, without a doubt, be time-barred. The relevant
observations in Babulal Vardharji Gurjar (supra) read thud:
“32. When Section 238-A of the Code is read with the
above noted consistent decisions of this Court
in Innoventive Industries [Innoventive Industries
Ltd. v. Icici Bank, (2018) 1 SCC 407 : (2018) 1 SCC (Civ)
356] , B.K. Educational Services [B.K. Educational
Services (P) Ltd. v. Paras Gupta & Associates, (2019) 11
SCC 633 : (2018) 5 SCC (Civ) 528] , Swiss Ribbons [Swiss
Ribbons (P) Ltd. v. Union of India, (2019) 4 SCC 17] , K.
Sashidhar [K. Sashidhar v. Indian Overseas Bank, (2019)
12 SCC 150 : (2019) 4 SCC (Civ) 222] , Jignesh
Shah [Jignesh Shah v. Union of India, (2019) 10 SCC 750
: (2020) 1 SCC (Civ) 48] , Vashdeo R. Bhojwani [Vashdeo
R. Bhojwani v. Abhyudaya Coop. Bank Ltd., (2019) 9 SCC
158 : (2019) 4 SCC (Civ) 308] , Gaurav Hargovindbhai
Dave [Gaurav Ha rgovindbhai Dave v. Asset
Reconstruction Co. (India) Ltd., (2019) 10 SCC 572 :
(2020) 1 SCC (Civ) 1] and Sagar Sharma [Sagar
Sharma v. Phoenix ARC (P) Ltd., (2019) 10 SCC 353 :
(2020) 1 SCC (Civ) 175] respectively, the following basics
undoubtedly come to the fore:
C.A. No. 876 of 2021 Page 54 of 62
(a) that the Code is a beneficial legislation intended to put
the corporate debtor back on its feet and is not a mere
money recovery legislation;
(b) that CIRP is not intended to be adversarial to the
corporate debtor but is aimed at protecting the interests of
the corporate debtor;
(c) that intention of the Code is not to give a new lease of
life to debts which are time-barred;
(d) that the period of limitation for an application seeking
initiation of CIRP under Section 7 of the Code is governed
by Article 137 of the Limitation Act and is, therefore, three
years from the date when right to apply accrues;
(e) that the trigger for initiation of CIRP by a financial
creditor is default on the part of the corporate debtor, that
is to say, that the right to apply under the Code accrues on
the date when default occurs;
(f) that default referred to in the Code is that of actual non-
payment by the corporate debtor when a debt has become
due and payable; and
(g) that if default had occurred over three years prior to
the date of filing of the application, the application would
be time-barred save and except in those cases where, on
facts, the delay in filing may be condoned; and
(h) an application under Section 7 of the Code is not for
enforcement of mortgage liability and Article 62 of the
Limitation Act does not apply to this application.”
(Emphasis supplied)
85. We may say, on the strength of the aforesaid exposition, that the respondent
ought to have brought its claim within the period of three years from the date
C.A. No. 876 of 2021 Page 55 of 62
of default before a civil court for recovery of money. The IBC proceedings
cannot be used to provide a fresh timeline for the period of limitation to run.
As such, the NCLT should not have admitted the petition without condoning
the delay and therefore, the impugned order upholding the admission was
erroneous.
86. We agree that when it comes to complex contracts like those for engineering,
procurement and construction, the question of limitation is also complicated.
It is a settled principle of law that in EPC contracts, a fresh ‘right to sue’ may
accrue when the final bill is being reconciled or the works are being finally
tested, even though the initial cause of action may have arisen at the time of
intermediate payments [See: Union of India v. West Coast Paper Mills Ltd.,
reported in (2004) 2 SCC 747].
87. However, in our considered view, ‘default’ as envisaged in Section 3(12) of
the IBC means the date when the default of non-payment came to
crystallized. The substantive dispute whether the amount is payable or not,
is not in question in IBC proceedings. Therefore, the understanding of
limitation in cases of EPC contracts for the purpose of contesting substantive
C.A. No. 876 of 2021 Page 56 of 62
claims by way of either a civil suit or arbitration, is not applicable for
insolvency applications under Section 9 of the IBC.
88. In such view of the matter, we may say without any manner of doubt that the
admission of the Section 9 IBC application of the respondent was erroneous,
and the same could not have been done without condonation of delay as per
Section 5 of the Limitation Act, 1963.
E. DETERMINATION OF THE ISSUES IDENTIFIED
I. Whether the EPC contract entered into by and between the
appellant and respondent was frustrated by the efflux of time?
89. The issue as regards the frustration of the EPC contract due to efflux of time,
is answered in the negative. We have said so because though the EPC
contract was suspended by the respondent due to non-payment by the
appellant of the amount claimed in the Section 9 application, yet none of the
parties had gone further to even express, let alone act on the intention to
terminate the EPC contract in terms of Clause 14 thereof.
90. Further, the EPC contract could not have reached its natural completion due
to effluxion of time for the reason that the performance of the contract
remained suspended, the obligations required to be fulfilled by the appellant
C.A. No. 876 of 2021 Page 57 of 62
remained incomplete and there was no provision in the EPC contract which
indicated that time was of the essence to the contract. Therefore, the EPC
contract continued to subsist.
91. Insofar as the appellant’s argument that the EPC contract got frustrated, is
concerned, we find the same to be incorrect. We have said so because Section
56 of the Indian Contract Act, 1872 envisages frustration of contract to
happen due to some supervening impossibility which was unforeseen by the
parties to the contract. We have relied on this Court’s decision in
Boothalinga (supra) that frustration of contract cannot apply to a case of
“self-induced frustration”. In other words, the contract cannot be deemed to
be impossible because of the breach of one of the parties to the contract.
Therefore, there is no gainsaying that in the present matter, the EPC contract
could not have gotten frustrated as it was the actions and conduct of the
contracting parties that led to stalling of the performance of the same.
I. Whether the monies claimed by the respondent in the application
under Section 9 of the IBC constitute ‘operational debt’ as defined
under Section 5(21) of the IBC?
92. The question whether the amounts claimed in the Section 9 application were
in the nature of operational debt, is partially answered in the affirmative. We
C.A. No. 876 of 2021 Page 58 of 62
have said so because the amounts required to be paid by the appellant to the
respondent as per the EPC contract and the payment schedule thereto, would
qualify as operational debt. Such payments are the consideration for the
works undertaken by the respondent in terms of the EPC contract and non-
payment thereof would be treated as a claim in respect of the provisions of
goods and services, as per Section 5(21) of the IBC.
93. However, the amount claimed under the heads of suspension, idling or
demobilization charges would be in the nature of damages as they arise from
the alleged breach of the EPC contract by the appellant. It is a settled position
of law that damages, whether liquidated or unliquidated, cannot be treated as
operational debts unless and until they are assessed and crystallized by way
of adjudication by a court of competent jurisdiction. Therefore, these
portions of the respondent’s claims cannot be treated as operational debt for
the purpose of adjudication of an application under Section 9 of the IBC.
II. Whether there existed a prior dispute in respect of the claims of
respondent?
94. We have answered the aforesaid issue in the negative. The jurisprudence on
the pre-existing dispute in respect of same claims as those in the Section 9
application being a bar to insolvency proceedings, is well settled by this
C.A. No. 876 of 2021 Page 59 of 62
Court in Mobilox (supra). It was held therein that the corporate debtor must
show that there existed a genuine dispute between the parties irrespective of
whether the same had progressed to the stage of arbitration or suit. In cases
where the dispute had not escalated to the stage of a civil suit or arbitration
proceedings, the corporate debtor would be required to highlight the pre-
existing dispute vide the conduct of the parties and the communications
between them.
95. In the present matter, there was no material placed on the record to show that
the parties were litigating or arbitrating any dispute in respect of the claims
under Section 9 application. Further, the appellant consistently maintained
total silence across all legal notices sent by the respondent asserting their
right to be paid in terms of the EPC contract. We find it apposite to clarify
that silence by itself cannot be considered to be an indicator of whether the
dispute existed or not. However, in cases such as the present matter, wherein
the silence was consistent and total, over a period of seven years, it can be
considered as a strong evidence of the appellant’s intention to not dispute the
respondent’s claims.
C.A. No. 876 of 2021 Page 60 of 62
96. Therefore, we have come to the conclusion that there was no pre-existing
dispute that would bar the respondent’s application under Section 9 of the
IBC.
III. Whether the application filed by the respondent under Section 9 of
the IBC was time-barred in respect of the dues amounting to
‘operational debt’?
97. We have answered the aforesaid question in the affirmative. In our
considered view, the respondent’s claims crystallized on 05.01.2012 and
03.02.2012 when the liability to pay was acknowledged by the appellant.
However, the respondent took no action to pursue its claims within three
years from the said dates.
98. The respondent sent legal notices dated 25.07.2014, 16.09.2014 and
15.07.2015 respectively after the lapse of more than four years. However,
the legal notices sent by the respondent could not have extended the period
of limitation as Section 18 of the Limitation Act, 1963 requires
acknowledgment of the liability to be by the person or entity against whom
the action is instituted.
99. In the present matter, the appellant gave no reply to the legal notices of the
respondent. Therefore, the clock of limitation continued to run its course and
C.A. No. 876 of 2021 Page 61 of 62
there was no action by the parties that reset it. We find ourselves constrained
to restate the observation of this Court in Babulal Vardharji Gurjar (supra)
that the intention of the IBC is not to give a new lease of life to debts which
are time-barred. Therefore, the respondent ought to have pursued its claims
within the period of limitation before a civil court or pleaded for condonation
of delay before the NCLT.
100. As a result, we say without any manner of doubt in our minds that the default
had occurred over three years prior to the date of filing of the application
and, therefore, the application is clearly time barred. The NCLAT committed
an error in upholding the admission of Section 9 application.
F. CONCLUSION
101. In the result, the appeal succeeds and is hereby allowed. The impugned
judgment passed by the NCLAT is hereby set aside. The order passed by the
NCLT is also hereby set aside.
102. However, considering the peculiar facts in the present litigation, we give
liberty to the respondent to approach the appropriate dispute resolution
forum as provided in the EPC contract to contest its claims.
C.A. No. 876 of 2021 Page 62 of 62
103. Pending applications, if any, shall stand disposed of.
104. Registry shall forward one copy of this Judgment to the National Company
Law Appellate Tribunal, Principal Bench, New Delhi who, in turn, shall
forward one copy each to all the NCLTs across the country.
………………………………J.
(J. B. PARDIWALA)
………………………………J.
(MANOJ MISRA)
New Delhi.
12
th
August, 2026.
Legal Notes
Add a Note....