As per case facts, a mining contract was awarded to the Respondent firm for sand extraction, which required security deposit and monthly payments. The Respondent defaulted on payments, leading to ...
2026 INSC 678 C.A. No.1345-1346 of 2012 Page 1 of 20
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs.3145-3146 OF 2012
STATE OF HARYANA & ORS. …APPELLANTS
VERSUS
M/S. JAI DURGAA FINVEST P. LTD. …RESPONDENTS
J U D G M E N T
V. MOHANA, J.
1. These appeals arise out of the judgement and order dated 21.03.2009 in
LPA No. 215 of 2006 and subsequent order dated 19.03.2010 in Review
Application No. 5 of 2010 passed by the Division Bench of the High Court of
Punjab and Haryana at Chandigarh. The only issue that arises for consideration
in these appeals is whether the amount of security deposit given by the
Respondent-contractor will carry interest despite there being a contract to the
contrary between the Appellant and the Respondent.
C.A. No.1345-1346 of 2012 Page 2 of 20
BRIEF FACTS:-
2. The Punjab Minor Minerals Concession Rules, 1964 (for short “the
Rules”) were notified on 25.04.1964 under the Mines & Minerals (Regulation
and Development) Act, 1957. Rule 33 of the Rules provides for execution of
a contract. When a bid is confirmed or a tender is accepted, the bidder or
tenderer shall execute an agreement in Form-L within one month. As per
Clause 1 of Form-L the contractors shall, during the subsistence of the contract,
pay in advance to the Government the contract money in respect of the land
given to them on a monthly basis. As per Clause 2 of the Form-L, if the
contractor fails to pay instalment of contract money or any part thereof, under
the terms and conditions of the contract, on the due date without written
permission of the Director in that behalf, he will be liable to pay interest thereon
at the rate of 24 percent per annum till such amount is paid. Clause 17 stipulates
that the contract may be terminated by the Government if considered by it to
be in public interest by giving one-month notice. Clause 16 stipulates that in
case of default in the due observance of the terms and conditions of the contract
or in payment of the contract money on the due date, the contract may be
terminated by the Government or by any officer authorised by the Government
in this behalf, by giving one-month notice, with forfeiture of security deposit
as also the instalment, paid in advance, if any. The contractor shall deliver the
C.A. No.1345-1346 of 2012 Page 3 of 20
possession of the quarry / mine to the mining officer concerned within seven
days of the receipt of order of termination of contract.
3. In the very same Form, there is a Clause 19 which stipulates that the
security deposited by the contractor(s) shall not carry any interest. It shall be
refunded to the contractor within three months from the date of the expiry or
sooner determination of the contract.
4. In the instant case, an auction notice was given for the extraction of
Yamuna sand from Bega Murthal Sand Zone on 26.03.1998. The auction was
held on 06.04.1998 for grant of contract for the extraction of sand and the
Respondent firm was the highest bidder for Rs.1.48 crores per annum for a
mining contract which was for a period of 3 years i.e., up to 31.03.2001. The
bid was accepted by the Appellant. On 30.11.1998, a contract was executed
between the parties in terms of the aforementioned Form-L. As per the said
contract the Respondent was to deposit the contract money in advance to the
Government on a monthly basis and the amount was also stipulated in the
contract. There were also stipulations about interest on delayed payment and
penalty for default.
5. After the agreement the Respondent had also given an affidavit to the
Appellant that they will take the lands from the owners at their own level.
Subsequently, the records show that the Respondent has been defaulting in
C.A. No.1345-1346 of 2012 Page 4 of 20
their instalment due to the Appellant from the month of September, 1999 and
a notice was issued on 19.01.2000 for termination of the contract as prescribed
in Clause 16 of the contract and the Respondent was called upon to give
possession of the land.
6. On 09.03.2000, after affording due opportunity to the Respondent and
after perusing the reply, the contract was terminated by the Director of Mines
and Geology and the security amount was also forfeited for non-observance of
the terms of the agreement. By this order, the Respondent was also directed to
immediately handover the possession of the Bega Murthal Sand Zone to the
Mining Officer, Sonepat as per the terms of the contract.
7. The Respondent took up the matter in appeal before the Appellate
Authority which is the Director of Mines and Geology, Government of
Haryana. By an order dated 10.07.2000, the Appellate Authority disposed of
the appeal by holding that ends of justice would be met if, like in the similar
cases, forfeited security money is adjusted against the outstanding contract
money and the interest. Accordingly, the Appellate Authority ordered that the
department shall raise the demand of contract money and up to date interest
within a period of seven days of the order and the contractor shall deposit the
demanded security within a period of one month in two fortnightly instalments.
The Appellate Authority held that in case they deposit this amount within the
C.A. No.1345-1346 of 2012 Page 5 of 20
stipulated period then the security amount shall be adjusted against the balance
amount, but in case they fail to adhere to the schedule of the payment then the
appeal shall stand rejected without any further notice to the Contractor.
8. The Appellant served a notice upon the Respondent for depositing a sum
of Rs.68,35,298/- out of which the Respondent seems to have deposited a sum
of Rs.26 lakhs and requested for extension of time which was granted.
However, the Respondent instead of depositing the contract money for the
period up to 31.03.2000 deposited only for the period up to 09.03.2000 on
which date the contract was terminated.
9. The Respondent then filed a Writ Petition being CWP No.12114 of 2000
before the Punjab and Haryana High Court at Chandigarh for quashing the
notice to the extent it demanded contract money and interest thereon at the rate
of 24 percent per annum and also challenging the validity of Clause 19 of the
agreement which stipulated that there is no interest payable on the amount of
security deposited by the Respondent and further it prayed for a direction to be
issued to the State to pay interest at the rate of 24 percent per annum on the
amount of security till final adjustment of the outstanding contract money.
10. The learned Single Judge by its judgement dated 07.10.2002 partly
allowed the writ petition. The learned Single Judge held that the demand of a
contract money after 09.03.2000 does not arise since the contract had been
C.A. No.1345-1346 of 2012 Page 6 of 20
terminated on 09.03.2000. However, on the issue of entitlement of interest of
security deposit as per Clause 19 of the agreement the learned Single Judge
held that the firm has voluntarily entered into a contract with an obligation to
deposit some amount as security with full knowledge that the same would not
carry any interest. The learned Single Judge also noted that this plea had been
taken when the major period of contract had already expired and the contractor
has taken it for the first time in the writ petition and he cannot be permitted to
assail the contract as unconscionable and oppressive.
11. The Respondent-contractor thereafter filed a Special Leave Petition
being SLP (C) No. 9491 of 2003 before this Court which was disposed of and
this Court by its order dated 05.01.2004, after referring to various provisions
of the agreement dated 30.11.1998, held that the matter needs to be re-
examined by the High Court and remanded the same.
12. After remand by this Court the learned Single Judge of the High Court
re-examined the entire issue. There were predominantly two issues before the
learned Single Judge. The first issue being whether the State complied with
their statutory obligations when the request was made by the contractor, and if
not, what would be the effect of non-compliance of the statutory obligation of
the State insofar as they did not comply with the contractor’s request which
had a direct bearing on the rights of the contractor. The second issue was
C.A. No.1345-1346 of 2012 Page 7 of 20
whether the security deposited by the Respondent-contractor would carry any
interest after the contract was terminated. The learned Single Judge, on a
detailed examination of the facts and documents, and after analysing the
contentions, came to the conclusion that the contractor has failed to prove that
State has failed to comply with their statutory obligations. The learned Single
Judge also found that there was nothing to show that the contractor was not
permitted to carry out the mining or that the termination was as the result of
non-compliance of statutory obligations by the authorities. Finally, the learned
Single Judge held that the contractor had failed to abide by the terms and
conditions of the agreement dated 30.11.1998 and had failed to pay monthly
instalments, as stipulated, therefore the order of termination of the contract
does not suffer from any illegality. It held that the contractor himself was
responsible for not extracting sand from the licensed land and for his failure to
comply with the provisions of Clause 27 of the agreement. However, the
learned Single Judge held that the demand for the period from 10.03.2000 to
07.04.2000 is not justified as the Respondent herein was denied the right to
extract sand after termination of the contract vide order dated 09.03.2000,
therefore, the claim made by the State for this period was set aside.
13. The learned Single Judge held that Clause 19 is “unsustainable in law”
and directed the Appellant herein to refund the security amount of Rs. 37 lakhs
with interest at the rate of 9 percent per annum from the date of its deposit.
C.A. No.1345-1346 of 2012 Page 8 of 20
14. The Appellants herein filed LPA No.215 of 2006 and the Respondent
herein also filed LPA No.85 of 2007 before the High Court of Punjab and
Haryana at Chandigarh. The Division Bench of the High Court dismissed both
the appeals filed by the parties and upheld the judgement of the learned Single
Judge.
15. The Respondent subsequently filed SLP(C) Nos.9761-9762 of 2009
which were dismissed by this Court by its order dated 08.05.2009. Subsequent
Review Petition and Curative Petition have also been dismissed by this Court
by its orders dated 22.07.2009 and 08.12.2009, respectively.
16. A subsequent SLP was filed by the Appellant herein which was disposed
of by this Court by an order dated 14.12.2009 granting liberty to the Appellant
to file a Review Petition before the High Court. It appears that the Appellant
had filed a Review Petition in the High Court which was also dismissed by the
second impugned order. The Appellant is before us challenging both the
orders.
17. Initially this Court had issued notice on 07.03.2011 and stayed the
operation of the impugned orders. Subsequently, by an order dated 16.03.2012
this Court granted leave and made the interim order absolute till the disposal
of the appeal.
C.A. No.1345-1346 of 2012 Page 9 of 20
18. The only issue that arises in these appeals is whether the security money
deposited by the contractor will carry interest once the contract is determined.
19. Heard Mr. Akshay Amritanshu, ably assisted by Mr. Sarthak Srivastava,
learned counsel for the Appellants, and Mr. Manoj Joshi ably assisted by Ms.
Shikha John and Mrs. Lalita Kaushik, learned counsel for the Respondent, and
perused the documents on record.
20. The Appellant submitted that the High Court could not have rewritten
the contract between the parties nor it could have substituted its own terms in
the agreement that the parties have arrived at. It was further submitted that
Clause 19 was an express term which was unambiguous and it was standard
statutory form accepted by the Respondent in an open commercial tender which
was never challenged by the Respondent during the currency of the agreement
or even when the Respondent filed statutory appeal before the authorities and
the challenge was raised for the first time in the writ petition. It was further
submitted that the security deposit paid by the contractor is always kept in a
non-interest bearing Treasury Head (8443-Civil Deposit and Advances) and
that the department is not doing any banking business and it does not earn
anything from out of the security deposit. The purpose of the security works as
a deterrent for securing performance and finally it was submitted that the
reasoning of the High Court that the interest should be paid on the security
C.A. No.1345-1346 of 2012 Page 10 of 20
because the State charges interest on instalments is not correct as the interest
charged under Clause 2 of the agreement is only as a compensation for the
default of the contractor.
21. Learned Counsel for the Respondent supported the impugned judgment
and he submitted that contract was unconscionable, one sided and in favor of
the State, and that while on the one hand the State is charging interest on the
contractor for delay in payments and for non-performance, it is denying the
contractor interest on his own security. He submitted that the judgment of the
High Court is founded on equity, justice and good conscience and ought not to
be disturbed on technical reasons and that the contract had been frustrated by
failure of the State in procuring the land under Clause 27.
ANALYSIS AND CONCLUSION:-
22. Form-L, prescribed under Rules 28A and 33 of the Rules, prescribes the
form in which a contract will be executed when a bid is confirmed or a tender
is accepted. The relevant clauses in Form-L, which is prescribed under the
Rules, are mentioned below:-
“1. Amount and mode of payment of contract money : The
contractor/contractors shall during the subsistance of the contract pay in
advance to the Government the following contract money in respect of
the said land given to him on contract for the period from _____ to _____
on the dates mentioned below:-
Number of Instalments Amount of
instalments
The date on
which
C.A. No.1345-1346 of 2012 Page 11 of 20
instalments is to
be paid
1 2 3
(a) In case of contract where the
annual contract money does not exceed
Rs. 1000/- in annual instalment after
adjusting Rs. ______ as contract money
for the period from ____ to 31.03.19
_____ remaining amount of Rs. _____
out Rs. _____ (deposited at the time of
auction) is adjustable against the annual
instalment falling due from 1.4.19__
Rs. ______
(annual
contract
money)
1.4.19____
1.4.19____
1.4.19____
1.4.19____
And so on
(b) In case of contract where the
annual contract money exceed Rs.
1000/- and does not exceed Rs. 5 lacs in
quarterly instalments after adjusting Rs.
_____ as contract money for the period
from _____ to ____ remaining amount
of Rs. _____ out of Rs. ____ (Advance
quarterly instalment deposited at the
time of auction) is adjustable against the
quarterly instalment falling due from 1
st
of ______
Rs. ______
(quarterly
instalment
of contract
money)
1.4.19____
1.7.19____
1.10.19____
1.1.19_____
And so on
(c) In case of contract where the
annual contract money exceeds Rs. 5
lacs in monthly instalments after
adjusting Rs. ____ as contract money
for the period from _____ to _____
remaining amount of Rs. _____ out of
Rs. _____ (advance monthly
instalment) is adjustable against the
monthly instalment falling due from
____ 19 _____.
Rs. ______
(monthly
instalment
of contract
money)
1.1.19____
1.2.19____
1.3.19____
1.4.19____
1.5.19____
1.6.19____
1.7.19____
1.8.19____
1.9.19____
1.10.19____
1.11.19____
1.12.19____
And so on
C.A. No.1345-1346 of 2012 Page 12 of 20
Money for the subsequent years of the contract shall be paid by
the contractor/contractors in advance in equal monthly/quarterly/yearly
instalments.]
2. Interest for delayed payment:- If the contractor (s) fails to pay
instalment of contract money or any part thereof due to the Government
under the terms of the conditions of the contract on the due date without
written permission of the Director in that behalf, he/they will be liable to
pay interest thereon at the rate of *[twenty four percent] per annum till
such amount is paid: Provided that no interest shall be payable if the
amount is paid within three days in case the annual contract money does
not exceed five lacs and within 7 days in case the annual contract money
exceed Rs. 5 lacs.
16. Penalty for default:- In case of default in the due observance of the
terms and conditions of the contract or in payment of the contract money
on the due date, the contract may be terminated by the Government or
by any officer authorised by Government in this behalf, by giving one
month's notice, with forfeiture of security deposit as also the instalment,
paid in advance, if any.
18. Recovery of contract money as arrears of land revenue:- Any sum
due from the Contractor/Contractors on account of contract money in
respect of the contract, shall be recovered from him/them as arrears of
land revenue.
19. Security deposit shall carry no interest:- The security deposited by
the Contractor/Contractors shall not carry any interest. It shall be
refunded to the Contractor within three months from the date of expiry
or sooner determination of the contract.”
23. It is well settled that in matters of contract between the parties the
function of a Court is to interpret and enforce the terms as has been agreed
between parties. The Court will not re-write the terms howsoever reasonable
the substituted term may appear to be. In matters of commercial contracts
where the parties stand on equal footing and have committed to certain
C.A. No.1345-1346 of 2012 Page 13 of 20
unambiguous terms, the language of the contract is to be clearly looked into
and parties are bound by the same. Once the parties with their eyes open
without any protest whatsoever and with free will accept certain terms of a
contract they cannot afterwards be permitted to go back on the same merely
because at a later point of time the stipulation proves to be onerous. The agreed
forfeiture/security stipulation is to be enforced according to the terms of the
contract as held in National Highways Authority of India v. Ganga
Enterprises And Another
1
, and Shri Hanuman Cotton Mills and Others Vs.
Tata Aircraft Limited
2
.
24. In Venkataraman Krishnamurthy And Another v. Lodha Crown
Buildmart Private Limited
3
this Court held as under:-
“21. In this regard, we may refer to the Constitution Bench decision
in General Assurance Society Ltd. v. Chandumull Jain , wherein it was
observed that, in interpreting documents relating to a contract of
insurance, the duty of the court is to interpret the words in which the
contract is expressed by the parties because it is not for the court to make
a new contract, however reasonable, if the parties have not made it
themselves. Thereafter, in Rajasthan State Industrial Development &
Investment Corpn. v. Diamond & Gem Development Corporation Ltd,
this Court reiterated that a contract, being a creature of an agreement
between two or more parties, is to be interpreted giving the actual
meaning to the words contained in the contract and it is not permissible
for the court to make a new contract, however reasonable, if the parties
have not made it themselves.
1
(2003) 7 SCC 410
2
(1969) 3 SCC 522
3
(2024) 4 SCC 230
C.A. No.1345-1346 of 2012 Page 14 of 20
22. More recently, in Shree Ambica Medical Stores v. Surat People's
Coop. Bank Ltd., it was observed that, through its interpretative process,
the court cannot rewrite or create a new contract between the parties and
has to simply apply the terms and conditions of the agreement as agreed
between the parties. Again, in GMR Warora Energy Ltd. v. CERC, it was
observed that courts cannot substitute their own view of the presumed
understanding of commercial terms by the parties, if the terms are
explicitly expressed. It was held that the explicit terms of a contract are
always the final word with regard to the intention of the parties.”
25. The Respondent was fully aware of the statutory Rules and Form as per
the terms of which there are certain conditions to be fulfilled and failure thereof
will entail certain consequences. Likewise, the Respondent was also aware that
the security deposited will not carry any interest and it will be refunded within
three months from the date of the expiry of the contract or sooner determination
of the contract. The Respondent had at least two opportunities of perusing the
terms and conditions. Despite knowing the existence of the clause, the
Respondent applied for the bid and became a successful bidder. Secondly
when the Respondent signed the contract/agreement on 30.11.1998 as
prescribed under Form-L, it was conscious of all the clauses, especially Clause
19 which prescribed that the security deposited will not carry any interest. It
is not the case of the Respondent that it had been coerced into signing the
contract nor is it the case that when the contract was signed it was under some
mistake or undue influence. Respondent has voluntarily entered into the
contract by which they were obliged to deposit the amount as prescribed therein
C.A. No.1345-1346 of 2012 Page 15 of 20
and the failure would result in termination. It has been consistently held by the
learned Single Judge and the Division Bench of the High Court that the
termination of the contract was purely by the conduct of the Respondent and it
was the Respondent who is to be blamed for non-performance and for not
depositing the monthly payments on time. The courts below have clearly
examined the conditions and the exchange of letters and notices between the
parties and have finally concluded that there was no failure on the part of the
Appellant for non-performance of the contract by the Respondent.
26. It has been consistently found that the order of termination of the
contract was effected due to the failure of the Respondent in abiding by the
conditions as stipulated in the agreement. It has been noticed that after one year
of the execution of the agreement the Respondent-company sent a letter to the
Appellant stating that they have been obstructed by the land owners and,
therefore, they are unable to carry out the mining. However, it has been found
that the Respondent did not carry out the mining on their own and they have
had made up a false plea with regard to the issuance of a notice in order to
secure benefits from the Department. The Respondent was also required to
submit a monthly return about sand extracted and if it was not extracting any
sand due to problems created by the land owners then it would certainly submit
a monthly report to that effect mentioning therein that extraction of the sand is
Nil. It was clearly found by the High Court that the Respondent was negligent
C.A. No.1345-1346 of 2012 Page 16 of 20
in not reporting the matter though they were working in other villages and
carrying out mining. Though the Appellant had served a notice on the
Respondent calling upon them to make the payment of monthly instalment
failing which contract would be cancelled, Respondent did not abide by the
same and took excuses for not carrying out the obligation. Therefore, it has
been found by the courts below that the order of termination of the contract
does not suffer from any illegality particularly when the Respondent failed to
respond even to the notice of termination. This aspect has also attained finality,
especially in view of order dated 08.05.2009 passed by a coordinate bench of
this Court in SLP(C) Nos.9761-9762 of 2009.
27. The High Court fell into error in declaring Clause 19 as unsustainable in
law and against public policy. The public policy cannot be pressed into service
to set at naught the commercial contract which expressly denies interest on
security deposit. Such a stipulation is neither immoral nor unlawful nor can it
be classified as unsustainable in the legal sense. The Respondent as a
commercial entity had participated in open auction and emerged as the highest
bidder and executed the standard statutory Form-L with full knowledge and
furnished an undertaking to abide by the same. Once parties have voluntarily
accepted a contract they cannot turn around and assail the same as oppressive
after major part of the contract period has gotten over. The reasoning of the
High Court that when State charges interest on belated instalment they should
C.A. No.1345-1346 of 2012 Page 17 of 20
pay interest on the security does not stand scrutiny. The stipulations in Clause
2 and in Clause 19 operate in different fields and they serve different purposes.
While Clause 2 provides for liquidated damages or compensation which is
payable or referable to the contractor’s default on the timely payment which is
a consequence of the contractor’s own breach, the security deposit in Clause
19 is a performance guarantee held by the State and the parties have clearly
agreed that it would carry no interest. There is no reciprocal obligation upon
the State to pay interest on the security. In fact, both the Clauses are seen in
the same contract which has been agreed between both the parties with their
eyes open. To reason otherwise and without interpreting the contract as agreed
but to add new terms which were not admittedly written therein amounts to re-
writing the contract which a Writ Court is not entitled to do.
28. Hence, it is held that Clause 19 is a valid binding term of the agreement
and the finding of the learned Single Judge as affirmed by the Division Bench
that Clause 19 is unsustainable in law and opposed to public policy is set-aside.
29. Having held as above, it is to be seen that Clause 19 of the agreement is
in two parts. Clause 19 is extracted hereinbelow:-
“19. Security deposit shall carry no interest:- The security deposited
by the Contractor/Contractors shall not carry any interest. It shall be
refunded to the Contractor within three months from the date of expiry
or sooner determination of the contract.”
C.A. No.1345-1346 of 2012 Page 18 of 20
The two limbs of the Clause 19 have to be read together, and they are
interdependent. While the first portion states that “it shall not carry any
interest” and second portion of the same clause reads that “shall be refunded to
the contractor within three months from the date of expiry or sooner
determination of the contract.” The correct interpretation of this Clause would
mean the Respondent’s deposit will earn no interest and it will be returned to
the Respondent within three months of the contract coming to an end or within
three months of the termination of the contract. On a proper reading of the
Clause 19 it is clear that the Appellant cannot retain the money which is interest
free, in perpetuity. It does not clothe the Appellant with the power to read the
first portion of the Clause in isolation without any limitation on time, therefore,
while the first portion states that security deposited will carry no interest, the
same clause would read further that it shall be refunded within three months
from the date of expiry or sooner determination of the contract. Once the
contract is determined then it is the obligation upon the State to refund the
security deposit within the period prescribed in the agreement. If the State
retains the security deposit beyond three months the Respondent-contractor is
entitled for interest which is very clear from a proper reading of Clause 19.
While the Clause 19 states that there is no interest from the date of deposit
while securing it, once it is determined, the amount cannot be withheld by the
State beyond three months as provided in the clause itself.
C.A. No.1345-1346 of 2012 Page 19 of 20
30. Therefore, since the contract has been determined on 09.03.2000 and the
period of three months expired on 09.06.2000, the Respondent is entitled to
interest for the period commencing from the expiry of three months from the
determination of the contract that is from 09.06.2000 till the date on which the
security was so adjusted or appropriated towards the dues payable by the
Respondent to the Appellant. The direction of the High Court that the security
deposit will carry interest from the date of deposit is erroneous and is contrary
to the agreed terms of the contract and therefore, the said direction is set aside.
31. Having regard to the above, the rate of interest as fixed by the High Court
at 9 percent per annum is reasonable and we see no reason to disturb the same.
32. In the result the Appeals are partly allowed in the following terms:-
A. The judgment of the learned single Judge dated 04.08.2006 as
affirmed by the Division Bench on 21.03.2009 and the order dated
19.03.2010 dismissing the review insofar as they declare Clause 19 of
the Form-L to be unsustainable in law and granting interest at 9
percent per annum on the security amount from the date of its deposit
is set aside;
B. Clause 19 is declared to be valid and binding in term of the contract and
no interest is payable on security deposit of Rs.37 lakhs for the period
C.A. No.1345-1346 of 2012 Page 20 of 20
up to expiry of three months from the date of determination of the
contract, i.e., up to 09.06.2000;
C. The Respondent shall be entitled to simple interest at the rate of 9
percent per annum on the security deposit for the period commencing
from 09.06.2000 and ending on the date on which the said amount
was appropriated towards the dues or refunded to the Respondent;
and
D. There shall be no order as to cost.
33. The Appeals are allowed and disposed of accordingly.
……………………… …CJI
(SURYA KANT)
………………………… …J.
(V. MOHANA)
New Delhi
July 13, 2026
In a significant decision, the Supreme Court of India has provided crucial clarity on the Security Deposit Interest and Contractual Obligations, partially allowing appeals by the State of Haryana. This ruling, now prominently featured on CaseOn, delves into the enforceability of contract clauses that explicitly deny interest on security deposits while also imposing a time limit for their refund. It underscores the judiciary's approach to interpreting commercial agreements and the principle that courts should not rewrite agreed-upon terms, even when they appear onerous.
The central question before the Supreme Court was whether a contractor's security deposit should accrue interest, especially when the contract explicitly states that it will not. This issue arose in the context of a mining contract where the State (Appellant) had terminated the agreement due to the contractor's (Respondent's) defaults.
The dispute originated from a mining contract awarded to M/s. Jai Durgaa Finvest P. Ltd. (Respondent) by the State of Haryana (Appellant) for sand extraction. The contract, executed in Form-L under the Punjab Minor Minerals Concession Rules, 1964, included several key clauses:
The contractor defaulted on payments, leading to the contract's termination and forfeiture of the security deposit. The contractor challenged this, particularly Clause 19, arguing it was unconscionable.
The Supreme Court reiterated well-established principles of contract law:
Initially, the Single Judge of the High Court, after a remand from the Supreme Court, found that the contractor had indeed defaulted. However, it declared Clause 19, which denied interest on the security deposit, as "unsustainable in law" and directed the State to refund the security amount with 9% interest from the date of deposit. The Division Bench upheld this decision.
The Supreme Court, in its current judgment, meticulously analyzed the High Court's reasoning:
As legal professionals navigate complex rulings like this, tools that simplify understanding are invaluable. CaseOn.in's 2-minute audio briefs provide a concise and clear analysis of such specific rulings, helping lawyers and students quickly grasp the nuances of the judgment and its implications without extensive reading.
While upholding the validity of Clause 19, the Supreme Court provided a crucial interpretation of its two parts:
The Court reasoned that while the money is interest-free during its legitimate holding period, the State cannot retain it in perpetuity after the contract's determination. If the State retains the security deposit beyond the three-month period stipulated for its refund, it becomes liable to pay interest for the period of delayed refund.
The Supreme Court partly allowed the appeals, modifying the High Court's order:
This Supreme Court judgment is a vital resource for legal professionals and students for several reasons:
This ruling serves as a crucial reference for anyone dealing with government contracts, security deposits, and the interpretation of contractual terms, emphasizing precision in drafting and adherence to agreed-upon conditions.
Disclaimer: All information provided is for informational purposes only and does not constitute legal advice.
Legal Notes
Add a Note....