State of Orissa Vs. Dandasi Sahu

  Supreme Court Of India Civil Appeal /1389/1988
Link copied!

Case Background

As per case facts, a construction project led to a dispute regarding claims for extra work. After an initial payment, the respondent sought arbitration, leading to an award that was ...

Bench

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9

PETITIONER:

STATE OF ORISSA

Vs.

RESPONDENT:

DANDASI SAHU

DATE OF JUDGMENT22/07/1988

BENCH:

MUKHARJI, SABYASACHI (J)

BENCH:

MUKHARJI, SABYASACHI (J)

RANGNATHAN, S.

CITATION:

1988 AIR 1791 1988 SCR Supl. (1) 562

1988 SCC (4) 12 JT 1988 (3) 364

1988 SCALE (2)285

CITATOR INFO :

R 1990 SC1128 (5)

ACT:

Constitution of India, 1950: Article 136-Decision of

larger bench pending on the question of unreasoned award-

Plea to await that decision-Whether could be allowed.

Arbitration Act, 1940: Section 14-Unreasoned award-Not

perse bad-Plea to await decision of larger bench-Whether

justified.

Sections 16 and 30- Whether award becomes bad merely

because the amount awarded is quite high-Factors to be

considered-only if there is error apparent on the face of

award, can be remitted or set aside-Validity of award-

Whether the points, upon which arbitrator adjudicated,

covered, by the exception clause in the contract.

Section 29-Interest pendente lite-Whether arbitrator

has jurisdiction to award.

HEADNOTE:

The construction of the Irrigation Project was

entrusted to the respondent. As per the contract the work

commenced on 4th May, 1973 and was actually completed on

30th December, 1975, the stipulated date being 4th November,

1974. According to the appellant, the respondent accepted

the final payment and was duly paid a sum of Rs.23,74,001

for the work done by him including the extra work. The last

payment was alleged to have been made to the respondent in

September, 1976. A 'nil' bill was the last bill prepared.

Thereafter, the respondent raised a claim and gave notice

for appointment of an arbitrator. One Nanda was appointed as

the arbitrator by the Chief Engineer. But on an application

made by the respondent, the Subordinate Judge removed Nanda

and appointed one Patnaik as the arbitrator. Again an

application for removal of the arbitrator was made, but was

dismissed.

The Respondent filed his claims before the arbitrator.

These claims were for the alleged extra work in respect of

which the decision of the Superintending Engineer under

clause 11 of the contract was final and the same was

excluded from the purview of the arbitration

563

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9

clause. The appellant initially contended that the

arbitrator had no jurisdiction to deal with such claims but

later filed a counter claim, and denied all the claims of

the respondent. While the application for removal of the

arbitrator was pending, an adjournment was sought for from

the arbitrator and it was refused. After hearing the parties

and considering the evidence produced, the arbitrator made a

non-speaking and non-reasoned award for Rs.15,23,657 plus

interest @ 10% in favour of the respondent. Objections to

the award were filed in the Court. The Subordinate Judge

upheld the objection and set aside the award. On appeal, the

High Court set aside the judgment of the Subordinate Judge

and made the award rule of the Court, and directed payment

of future interest at 6%.

In this appeal, by special leave, against the High

Court judgment, the appellant-State submitted that the award

is without any reason. It also suggested that since the

validity of the non-reasoned award is being gone into by a

larger Bench of this Court, that decision should be awaited.

Dismissing the appeal,

^

HELD: 1.1 The law as it stands today is that award

without reasons is not bad per se. Indeed, an award can be

set aside only on the ground of misconduct or an error of

law apparent on the face of the award. [567F]

1.2 In the instant case, the plea that the award was

bad being an unreasoned one, was neither mooted before the

learned Subordinate Judge nor before the High Court. It was

also not raised in the objection to the award, filed

originally. It is only in the special leave petition that

such a plea has been raised for the first time. Arbitration

is restored to as a speedy method of adjudication of

disputes. Stale and old adjudication should not be set at

naught, or examination of that question kept at bay on the

plea that the point is pending determination by a larger

Bench of this Court. Even if it is held ultimately that the

unreasoned award per Se is bad, it is not sure whether such

a decision would upset all the awards in this country which

have not been challenged so far. Certainly, in the exercise

of discretion under Article 136 of the Constitution, and in

view of the facts and circumstances of the present case, it

would not be justified in allowing the party to further

prolong or upset adjudication of old and stale dispute.

[567C-E]

2. Clause 11 of the contract between the parties makes

the deci-

564

sion of the Engineer-in-Charge final in respect of some

issues. Proviso of Clause 11 stipulates that in case of

dispute about the rates and time for completion of the work

and any dispute as to proportion that the additional work

bears to the original contract work, the decision of the

Superintending Engineer of the Circle would be final. The

points upon which the arbitrator in the instant case has

adjudicated are not those which are excepted or covered by

Clause 11 of the agreement. ID that view of the matter, this

clause has no application in the instant controversy. [570B-

D]

Bombay Housing Board (now the Maharashtra Housing

Board) v. Kharbase Naik & Co., Sholapur, [1975] 3 SCR 407;

Chief Administrator, Dandakaranya Project, koraput, Orissa &

Anr. v. M/s. Prabartak Comercial Corpn. Ltd. Calcutta, AIR

1975 MP 152 and Food Corporation of India. v. P.L. Juneja,

AIR 1981 Delhi 43 distinguished.

State of orissa v. Gokulchandra Kanungo, [1981] 52 Cut

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9

LT 416 referred to.

3.1 It is well-settled that when the parties choose

their own arbitrator to be the judge in the dispute between

them, they cannot, when this award is good on the face of

it, object to the decision either upon law or on facts.

Therefore, when arbitrator commits a mistake either in law

or in fact in determining the matters referred to him, where

such mistake does not appear on the face of the award and

the documents appended to or incorporated so as to form part

of it, the award will neither be remitted nor set aside.

[571F-G]

3.2 The fact that merely the award amount is quite high

or that a large amount has been awarded, does not vitiate

the award as such. If' there is any evidence of malady of

racket of arbitration, the Court may scrutinise the award

carefully in each such case. [572A-B]

3.3 It is clear from the facts of this case that the

arbitrator is a highly qualified person having several

Indian and foreign Degrees and at the relevant time was

acting as Chief Engineer-in-Charge of the State Government.

Having regard to the nature of claims involved, and the fact

that the additional work has been done for which large

amounts have been-paid in this case, it is evident that all

due opportunities were given to the parties to adduce all

evidence. It cannot be said that the award was so

disproportionate as to shock the conscience of the Court

leading it to hold that the award was bad per Se. The High

Court was

565

right in dismissing the challenge to the award on this

ground. [572C-D]

Union of India v. Bungo Steel Furniture Pvt. Ltd.,

[1967] 1 SCR 324 and Allen Berry & Co. (P) Ltd. v. Union of

India, [1971] 3 SCR 282 relied on.

State of Orissa & Ors. v. Gangaram Chhapolia & Anr.,

AIR 1982 Orissa 277 referred to.

4.1 It is now well-settled that the interest pendente

lite is not a matter within the jurisdiction of the

arbitrator. [572G-H]

4.2 In the instant case, the order of the High Court is

modified to the extent that the award is confirmed subject

to the deletion of the interest pendente lite. It is made

clear that interest for the period from 26.9.1981 to

18.3.1983 (the date of the award) is deleted. However, the

interest granted by the High Court from the date of the

decree is sustained. [573A-B]

Executive Engineer (Irrigation), Balimella & Ors. v.

Abhaduta Jena, [1988] 1 SCC 418, followed.

JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1389 of

1988.

From the Judgment and order dated 6.7.1987 of the

Orissa High Court in C.M.C. No. 375 of 1984.

R.K. Mehta and Miss Mona Mehta for the Appellant.

G.L. Sanghi and Vinoo Bhagat for the Respondents.

The Judgment of the Court was delivered by

SABYASACHI MUKHARJI, J. This is an appeal by special

leave from the judgment and order of the High Court of

orissa, dated 6th July, 1987. It arises out of a contract

entered into between the State and the respondent for the

construction of certain projects for irrigation. During

1973-74 the respondent was entrusted with the job of

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9

'Construction of Ramaguda Minor Irrigation project in

Kukudakhandi Block' vide agreement No. 4-F-2. The value of

the work was Rs.9,99,510. The work pursuant to the contract

commenced on 4th May, 1973 and 4th November, 1974 was the

stipulated date of com-

566

pletion of the work. However, on 30th December, 1975 the

work was actually completed. It is asserted by the appellant

that the respondent contractor accepted the final payment

and was duly paid a sum of Rs.23,74,001 for the work done by

him including the extra work. Thereafter, no amount was due

to the respondent, according to the appellant, and he did

not raise any claim whatsoever before the Department. On

28th September, 1976 the last payment was alleged to have

been made by the respondent. On 30th October, 1976 the last

bill was prepared which was nil one. The respondent,

thereafter, raised a claim and gave notice for appointment

of an arbitrator. Consequently, the Chief Engineer appointed

one Shri A.N. Nanda as the arbitrator in terms of the

arbitration clause. However, on the application of the

respondent the learned Subordinate Judge removed Shri A.N

Nanda and appointed one Shri B. Patnaik as the arbitrator.

It may be mentioned that the application was made for

removal of the arbitrator Shri B. Patnaik but the same was

ultimately dismissed. Before the arbitrator, the respondent

filed the claim raising some claims which, according to the

appellant, were fictitious and baseless. These claims were

for the alleged extra work in respect of which the decision

of the Superintending Engineer under clause 11 of the

contract was final and the same was excluded from the

purview of the arbitration clause.

It was contended on behalf of the appellant that the

arbitrator had no jurisdiction to deal with such claims. The

appellant filed a counter claim for Rs.2,11,400, denying all

the claims of the respondent. All the documents and relevant

papers were produced before the arbitrator. It is stated

that as the application for removal of Shri B. Patnaik as

arbitrator was pending, an application had been made before

Shri S. Patnaik to adjourn the proceeding which was refused

and the award was made. This award was claimed to have been

made virtually ex parte. This, however, was not so and it

appeared that the arbitrator on hearing the parties and

considering the evidence produced before him made the award.

The arbitrator made the said award on 18th March, 1983 but

the same was a non-speaking and nonreasoned award for a lump

sum of Rs.15,23,657 plus interest @ 10% from 9.9.1975 till

the date of payment or decree. Objections to the said award

were filed in the Court. The learned Subordinate Judge

upheld the objection to the award and set aside the award on

15th September, 1984. There was an appeal to the High Court

and the High Court set aside the judgment of the learned

Subordinate Judge and made the award of the arbitrator, rule

of the Court. It also directed payment of further interest

at 6%.

567

Being aggrieved thereby the State of Orissa has

preferred this appeal. In support of this appeal, it was

submitted that the award in question was a lump sum af money

and it was without any reason, in favour of the respondent.

It was also submitted that the validity of the non-reasoned

award is awaiting determination by a larger Bench of this

Court. Hence, it was urged that this question should await

decision of the larger Bench. In the facts and circumstances

of the case, we are of the opinion that we would not be

justified in acceding to this request on the part of the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9

appellant. In this case the submission that the award was

bad being an unreasoned one, was neither mooted before the

learned Subordinate Judge nor before the High Court. This

contention was also not raised in the objection to the

award, filed originally. It is only in the special leave

petition that such a plea has been raised for the first

time. Arbitration is resorted to as a speedy method of

adjudication of disputes. Stale and old adjudication should

not be set at naught or examination of that question kept at

bay on the plea that the point is pending determination by a

larger Bench of this Court. Even if it is held ultimately

that the unreasoned award per se is bad, it is not sure

whether such a decision would upset all the awards in this

country which have not been challenged so far. Certainly, in

the exercise of our discretion under Article 136 of the

Constitution and in view of the facts and circumstances of

this case, we would not be justified in allowing the party

to further prolong or upset adjudication of old and stale

disputes.

In that view of the matter, we think that the pendency

of this point before the larger Bench should not postpone

the adjudication and disposal of this appeal in the facts of

this case. The law as it stands today is that award without

reasons are not bad per se. Indeed, an award can be set

aside only on the ground of misconduct or on an error of law

apparent on the face of the award. This is the state of law

as it is today and in that context the contention that the

award being an unreasoned one is per se bad, has no place on

this aspect as the law is now. This contention is rejected.

It was next contended that in view of clause 11 of the

contract the matters upon which the arbitrator has

adjudicated were excluded and these were not arbitrable. It

was submitted that clause 11 of the contract between the

parties made on these matters the decision of the Engineer

Incharge final and binding. Hence, inasmuch as the

arbitrator has purported to act upon this field which was

only to be decided by the Engineer-in-charge, the award was

bad. The disputes over which the arbitrator has purported to

make an award, were regarding

568

works covered by the agreement. lt was submitted that the

provision to clause 11 af the agreement categorically

provided that in the event of dispute over a claim for

additional work, the decision of the Superintending Engineer

of the Circle would be final and, hence, the arbitrator by

entertaining the additional claim of the contractor had

exercised a jurisdiction not vested in him and, as such,

misconducted himself.

In order to judge this contention, therefore, it is

Imperative first to refer to clause 11 of the agreement. It

provides as follows:

"Clause 11-The Engineer-in-charge shall have the

power to make any alteration in or additions to

the original specifications, drawings designs, and

instructions that may appear to him necessary or

advisable during the progress of work and the

contractor shall be bound to carry out the work in

accordance with any instructions which may be

given to him in writing signed by the Engineer-in-

charge and such alteration shall not invalidate

the contract. Any additional work which the

contractor may be directed to do in the matter

above specified as part of the work, shall be

carried out by the contractor on the same

conditions in all respects on which he agreed to

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9

do the main work and at the same rates as are

specified in the tender for the main work. The

time for the completion of the work shall be

extended in the proportion that the additional

work bears to the original contract work and the

certificates of the Engineer in charge shall be

conclusive as to such proportion and if the

additional work includes any class of work shall

be carried out at the rates entered in the

sanctioned schedule of rates of the locality

during the period when the work being carried on

and if such last mentioned class of work is not

entered in the schedule of the rate of the

district, then the contractor shall within 7 days

intimate the rate which it is his intention to

charge for such class of work and if the Engineer-

in-charge does not agree to this rate he shall by

notice in writing be at liberty to cancel his

order to carry out such class of work and arrange

to carry such class of work and arrange to carry

out in such manner as he may consider advisable.

No deviation from the specification stipulated in

the contract or additional items of work shall

ordinarily be carried by the contractor and should

any altered, additional or substituted work be

carried out by him unless the rates of the

substituted, altered or additional

569

items have been approved as fixed in writing by

the Engineer-in-charge.

The contractor shall be bound to submit his

claim for any additional work done during any

month or before the 15th day of the following

months accompanied by the copy of the order in

writing of the Engineer-in-Charge for the

additional work and that the contractor shall not

be entitled to any payment in respect of such

additional work if he fails to submit his claim

within the aforesaid period.

Provided it always that if the contractor

shall commence work or incur any expenditure in

regard thereof before the rates will have been

determined as lastly herein before mentioned, then

in such case he shall only be entitled to be paid

in respect of the determination of the rates as

aforesaid accordingly to such rate of rates as

shall be fixed by the Engineer-in-Charge. In the

event of a dispute the decision of the

Superintending Engineer of the Circle will be

final. "

This clause has to be read in conjunction with the

arbitration clause i.e. clause 23, which provides as

follows:

"Clause 23: Except where otherwise provided in the

contract all questions and disputes relating to

the meaning of the specifications, designs and

instructions hereinbefore mentioned and as to the

quality of workmanship or materials used on the

work or as to any other question, claim, right

matter, or thing whatsoever in any way arising out

of, or relating to the contract, designs, drawing

specifications, estimates, instructions, orders or

these conditions or otherwise concerning the works

or the execution or failure to execute the same

whether arising during the progress of work, or

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9

after the completion or abandonment thereof shall

be referred to the sole arbitration of a

Superintending Engineer of the Circle. It will be

no objection to any such appointment that the

arbitrator so appointed is a Government servant.

The award of the arbitrator so appointed shall be

final. conclusive and binding on all parties to

this contract.

The learned Subordinate Judge was inclined to hold that

the

570

arbitrator had no jurisdiction to arbitrate on disputes

which he has purported to do but in view of the Bench

decision of the High Court of Orissa in State of orissa v.

Gokulchandra Kanungo, [1981] 52 CLT 416, he held that he was

not free to decide that the dispute was not arbitrable and

rejected this plea. The High Court also did not entertain

this objection. It was canvassed before us and submitted

that in view of clause 11, the matters in dispute and the

amount due for the alleged additional work, were not

arbitrable at all. We have noticed clause 11 which makes the

decision of the Engineer-in-Charge final in respect of some

issues. In this connection, it is important to refer to the

proviso of Clause 11 which states that in case of dispute

about the rates and time for completion of the work and any

dispute as to proportion that the additional work bears to

the original contract work, the decision of the

Superintending Engineer of the Circle would be final. The

points upon which the arbitrator in the instant case has

adjudicated are not those which are excepted or covered by

Clause 11 of the agreement. In that view of the matter, this

clause has no application in the instant controversy.

Our attention was drawn to certain observations of this

Court in Bombay Housing Board (Now the Maharashtra Housing

Board) v. Karbhase Naik & Co., Sholapur, s

[1975] 3 SCR 407. There in view of clause 14 of the said

contract, it was open to the respondent to make claim on the

basis of the rates quoted. There, Clause 14 was more or less

identical to Clause 11 in the present case. This particular

contention, however, did not arise in that case. The Court

held that the respondent there being contractor, was not

bound to carry out additional or altered work and there was

no reply to the notice stating the rates intended to be

charged and the respondent there was not free to commence

and complete the work on the basis that since the rates

quoted were not accepted, it would be paid at such rates to

be fixed by the Engineer-in-charge and that if it was

dissatisfied with the rate or rates fixed by the Engineer-

in-charge, it could raise a dispute before the

Superintending Engineer and that the time limit for

completion would be extended in all cases. This Court

observed that only the rates were settled by the agreement.

The respondents were under no obligation to carry out the

additional or altered work but that is not the dispute

before us in the present case. On the construction of Clause

11 of the contract, we are unable to accept the contention

but on the points that the arbitrator has awarded in this

case, were excluded by Clause 11 of the contract herein.

Shri Mehta, however, strongly relied on certain observations

of a Bench decision of Madhya Pradesh High Court in case of

the Chief Administrator, Dandakaranya Project,

571

Koraput, Orissa & Anr. v. M/s. Prabartak Commercial Corpn.

Ltd. Calcutta, AIR 1975 MP 152, wherein while considering

Clause 13A of the agreement there the High Court held that

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9

the dispute whether charges for stone chips could be

adjudicated, was not arbitrable. That was a case of rates

which was within the jurisdiction of the Engineer-in-charge

by Clause 13A of the bargain between the parties. In the

instant case it is not the rate which is in dispute. The

Madhya Pradesh High Court referred to several decisions of

this type and came to the conclusion on the construction of

Clause 13A in that case that the dispute that had arisen

between the parties in arbitration, was excluded by Clause

13A of the agreement. In view of the Clause in the instant

case and the nature of the dispute which had arisen, we are

of the opinion that such decisions also cannot give much

assistance to the appellant. Reliance was also placed on

certain observations of the Delhi High Court in the case of

Food Corporation of India v. P.L. Juneja, AIR 1981 Delhi 43.

There the Division Bench of the High Court was concerned

with the questions which were to be decided by the Court and

not by the arbitration. There also the Clause was very much

dissimilar to the present one which is set out hereinbefore.

Clause 15(c) provided that the question whether a particular

service is or is not to be covered by any of the services

specifically described and provided for the contract, or is

or is not material to any such services shall be decided by

the Regional Manager whose decision shall be final and

binding. It was not the case whether any additional work was

done and if so, the extent of such work. In the aforesaid

view of the matter it is not possible to hold that in view

of nature of instant dispute, the matters at issue were not

excluded and the arbitrator did not commit any wrong in

proceeding with the arbitration.

It was next contended that an amount of Rs.15,23,657

has been granted for additional work over and above the

payment of Rs.23,74,001 and this was disproportionately high

and the award for this amount was per se bad. It is well-

settled that when the parties choose their own arbitrator to

be the judge in dispute between them, they cannot, when the

award is good on the face of it, object to the decision

either upon law or on facts. Therefore, when arbitrator

commits a mistake either in law or in fact in determining

the matters referred to him, where such mistake does not

appear on the face of the award and the documents appended

to or incorporated so as to form part of it, the award will

neither be remitted nor set aside. The law on this point is

well-settled. See in this connection the observations of

this Court in Union of lndia v. Bungo Steel Furniture P.

Ltd., [1967] 1 SCR 324 and Allen Berry & Co. (P) Ltd. v.

Union of India, [1971] 3 SCR

572

282. It was, however, contended that the amount of the award

was shockingly high that it shocked the conscience of the

Court and the award must be set aside. The fact that merely

the award amount is quite high as commented by the High

Court or that a large amount has been awarded, does not

vitiate the award as such. In the instant case the original

award was for Rs.9,99,510. Admittedly, additional work was

done and payment for such work was determined at

Rs.23,74,001 and claim for further additional work was made

for Rs. 15,23,657. One has to judge whether the amount of

the award was so disproportionately high to make it per se

bad in the facts and circumstances of a particular case. It

is clear from the facts that the arbitrator is a highly

qualified person having several Indian and foreign Degrees

and at the relevant time was acting as Chief Engineer-in-

charge of the State Government. Having regard to the nature

of claims involved and the fact that the additional work has

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9

been done for which large amounts have been paid and in this

case it is evident that all due opportunities were given to

the parties to adduce all evidence, we are unable to accept

the submission that the award was so disproportionate as to

shock the conscience of the Court and, as such, it cannot be

held that the award was bad per se. In our opinion, the High

Court was right in dismissing the challenge to the award on

this ground.

In support of the submission that the award must be

held to be bad in this case, Mr. Mehta drew our attention to

certain observations of Orissa High Court in State of Orissa

& Ors. v. Gangaram Chhapolia & Anr., AIR 1982 Orissa 277,

where at page 279 the learned Judge observed the malady of

the racket of arbitration was rampant in Orissa. Though the

learned Judge was apparently heeding to the observations of

Justice Holmes of America observed that the Court should

take note of "the felt necessities of the time".

In our opinion, the evidence of such state of affairs

should make this Court scrutinise the award carefully in

each particular case but that does not make the Court

declare that all high amounts of award would be bad per se.

As mentioned hereinbefore, it cannot be said that the amount

of award was disproportionately high to hurt the conscience

of the Court in this case.

It is now well-settled that the interest pendente lite

is not a matter within the jurisdiction of the arbitrator.

In this connection reference may be made to the observations

of this Court in Executive Engineer (Irrigation), Balimela &

Ors., v. Abhaduta Jena & Ors., [1988] 1 SCC 418 where this

Court held that the arbitrator could not

573

grant interest pendente lite. In the aforesaid view of the

matter this A direction in the award for the payment of such

interest must be deleted from the award. The order of the

High Court is modified to the extent that the award is

confirmed subject to deletion of the interest pendente lite.

We make it clear that in the facts of this case interest for

the period from 26.9.81 to 18.3.83, the date of the award be

deleted. The High Court has, however, granted interest from

the date of the decree. That is sustained.

The appeal is, therefore, dismissed except to the

extent indicated above. In the facts and circumstances of

the case the parties will pay and bear their own costs.

G.N. Appeal dismissed.

574

Reference cases

Description

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter