State of U.P. Vs. M/S Ram Nath International Construction Pvt. Ltd.

  Supreme Court Of India Civil Appeal /6116/1994
Link copied!

Case Background

As per case facts, a contractor working for the State of U.P. claimed higher rates due to significant work increases caused by design changes, a claim the State denied. The ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6

PETITIONER:

STATE OF U.P.

Vs.

RESPONDENT:

M/S. RAM NATH INTERNATIONALCONST. PVT. LTD.

DATE OF JUDGMENT10/11/1995

BENCH:

G.B. PATTANAIK (J)

BENCH:

G.B. PATTANAIK (J)

AGRAWAL, S.C. (J)

CITATION:

1996 AIR 782 1996 SCC (1) 18

JT 1995 (8) 396 1995 SCALE (6)321

ACT:

HEADNOTE:

JUDGMENT:

J U D G M E N T

PATTANAIK, J.

This appeal is directed against the Judgment of the

Allahabad High Court dated 16th December, 1993 in First

Appeal From Order

No. 930 of 1991, arising out of an arbitration proceeding.

The Respondent - contractor had entered into an

agreement with the appellant for construction of non

overflow and overflow sections with bridge spillway and

other appurtenant works of Maudaha Dam in Hamirpur district

in the State of Uttar Pradesh. The agreement was entered

into on 26th August, 1985 and work commenced from 1st

September, 1985. The period stipulated for completion of the

work was 42 months. In the year 1987 in respect of two items

of work namely Items 13 and 15, it is alleged that the

appellant changed the designs and drawings as a result of

which the quantity of work became abnormally high compared

to the estimated quantity of work in the agreement. On

account of such abnormal increase of the quantity of work

the contractor claimed higher rate than what was agreed to

in the agreement. The State having refused to acceed to the

contractor's demand and disputes having arisen between the

parties, the arbitration clause of the agreement was invoked

and dispute was referred to the sole arbitration of the

Joint Secretary and Joint Legal Remembrancer to the

Government of Uttar Pradesh. Before the arbitrator the

respondent - contractor made a claim of Rs. 91,56,750/- for

the increased quantity of work in respect of Item No. 13

executed till 30.4.90 and Rs. 9,92,402.50 for the increased

quantity of work in respect of Item No. 15 executed till

30.4.90 together with interest @ 10% thereon. The entire

basis of the claim of the contractor was that in respect of

the quantity of work in excess of the estimated quantity in

the agreement he is entitled to be paid @ Rs. 453.50 per

cubic meter in place of the agreed rate of Rs. 243.00 for

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6

Item No. 13 and the rate of Rs. 739.55 per cubic meter in

place of agreed rate of Rs. 460.00 for Item No. 15. It was

alleged in the claim petition that the State of Uttar

Pradesh has paid and is paying the agreed rate of Rs. 243.00

per cubic meter in respect of the additional quantity of

work in Item No. 13 and similarly has paid and is paying @

460.00 per cubic meter even in respect of the additional

quantity of work in respect of Item No.15. According to the

respondent contractor, on account of substantial change in

designs and drawings there has been abnormal increase in the

quantities of work compared to the estimated quantity of

work in the original agreement and in respect of such

additional quantity of work he is not bound to be paid at

the agreed rate but at an enhanced rate on the basis of the

analysis of rate submitted by him. It was further averred

that when the drawings and designs were changed, the

contractor had resisted and prayed for the alteration in the

rate but the concerned authorities had assured him orally

for such change though ultimately did not agree to the same.

It was also averred in the claim petition that under the

agreement he was bound to carry out the work as per the

directions of the concerned authorities and accordingly he

has carried out the same.

The appellant - State filed written statement before

the arbitrator denying its liability to pay at the revised

rate as claimed by the contractor. It was admitted that

there has been a change in the drawings and designs relating

to Item Nos. 13 and 15 and on account of such change, the

quantity of work in respect of the aforesaid two items has

increased. But the claimant is not entitled to any enhanced

rate, in view of the different clauses of the agreement

itself. It was also averred in the written statement that

the so called variation in the quantity of work is covered

by clauses 11.25 and 13.1.1 of the agreement and therfore

the contractor is not entitled to any higher rate.

The learned arbitrator after analysing the different

clauses of the agreement, came to the conclusion that the

contractor could not have refused the work in accordance

with the alterations and modifications in the drawings and

designs. He further held that there has been a fundamental

change in the drawings and designs which abnormally

increased the quantum of work than the estimated quantum

indicated in the agreement and under the agreement though

the contractor cannot claim any excess rate for work upto

the excess of 10%, but beyond the same the contractor would

be entitled to claim a higher rate. The arbitrator accepted

the analysis of rate. The arbitrator accepted the analysis

of rate given by the contractor and accordingly in respect

of the quantity of work executed after the date of the

completion of the work indicated in the agreement namely

28.2.1989, he granted as per the rate claimed by the

contractor. In all he awarded a total sum of Rs.

90,21,765.65 together with interest @ 9% per annum from

21.5.90 till the date of the award and further interest @ 6%

per annum from the date of the award till the payment or

till the decree, if any, passed on the basis of the order.

The arbitrator also held that in respect of works executed

after 30th April, 1990 the claimant would be paid at the

same rate i.e. Rs. 453.50 per cubic meter in respect of Item

No. 13 and Rs. 739.55 per cubic meter in respect of Item No.

15 after adjusting the payments already made as per the

rates given in the contract.

The contractor filed an application before the Civil

Judge, Hamirpur for making the award a rule of court which

was registered as Suit No. 53 of 1991. The appellant - State

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6

filed his objections challenging the legality of the award.

The learned Judge being of the opinion that the court has no

jurisdiction to interfere with an award of the arbitrator

since the arbitrator had decided all the issues properly

with detailed analysis as well as after perusing all the

necessary documents, made the award a rule of the Court. The

learned Trial Judge also came to the conclusion that the

arbitrator was fully within his powers to accept the

analysis of rate submitted by the contractor which was

infact not disputed by the State and therefore there is no

error in the award which could be interfered with by the

court. On the question whether the objections filed by the

State could at all be entertained the same having been filed

beyond 30 days the Civil Judge came to the conclusion that

the objections cannot be entertained and perused as the same

was filed beyond the period of 30 days. With these

conclusions the award having been made a rule of court and

the objection of the State having been rejected, the State

preferred an appeal in the High Court of Allahabad under

Section 39 of the Arbitration Act. The High Court set aside

the conclusion of the Trial Judge with regard to the

entertainability of the objection filed by the State and

held that taking into account the magnitude of the claim of

Rs. 1 crore and taking into account that the objection could

not be filed on 23rd March, 1991 was a Sunday, the objection

filed on 25th of March, 1991 has to be considered on

condoning the delay, in the interest of Justice. But so far

as the conclusion of the Trial Judge on merits of the case

is concerned the High Court refused to interfere with the

decision of the Trial Judge on the ground that the

arbotrator has not committed any error in allowing the claim

of the contractor as per the analysis of rates given by it

in respect of the extra quantity of work and it is not

permissible for the court within the parameter for exercise

of its jurisdiction to interfere with the award. Thus appeal

having been dismissed, the State has preferred the present

appeal.

Mr. Sehgal, the learned senior counsel for the

appellant contended that in view of the escalation clause in

the contract itself, the arbitrator had no jurisdiction to

allow the contractor's claim at a new rate on the basis of

the analysis of rates and the award, therefore, is vitiated

on that score. He further contended that even if it was

permissible for the arbitrator to accept the analysis of

rates submitted by the contractor for the excess quantity of

work executed by him beyond the stipulated period of the

contract, yet the arbitrator committed gross error in

allowing the total claim without taking into account the

payments already made to the contractor in accordance with

the escalation clause of the contract and the award is,

therefore, vitiated on that score. Mr. Sanghi, the learned

senior counsel appearing for the respondent on the other

hand contended that the quantity of work executed by the

contractor being far more in excess of the anticipated

quantity of work in the contract and such excess being on

account of alteration of drawings and designs, the

arbitrator was fully within his jurisdiction to accept the

analysis of rates submitted by the contractor and award the

contractor's claim. It was further contended that the State

not having objected to the analysis of rates given by the

contractor, the arbitrator was fully justified in awarding

the claim of the contractor. Mr. Sanghi also contended that

the payments already made to the contractor at the escalated

rate in respect of the extra quantity of work in accordance

with the terms of the contract is of no consequence since

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6

the contractor claimed the change of the basic rate which

the arbitrator has allowed and on such basic rate the

contractor would otherwise be entitled to the escalation in

accordance with the clauses of the contract. According to

Mr. Sanghi, the High Court rightly did not interfere with

the award as no error appears to have been pointed out in

the award itself.

The jurisdiction of the court to interfere with an

award of an arbitrator is undoubtedly a limited one. The

adjudication of the arbitrator is generally binding between

the parties and it is not open to the court to attempt to

probe the mental process by which the arbitrator has reached

his conclusion. Award of an arbitrator can be set aside by a

court only on the grounds indicated in Section 30 of the

Arbitration Act. It is not open to the court to re-assess

the evidence to find whether arbitrator has committed ay

error or to decide the question of adequacy of evidence and

the court cannot sit on the conclusion of the arbitrator by

re-examining and reappreciating the evidence considered by

the arbitrator. At the same time the arbitrator is a

creature of the agreement itself and therefore is duty bound

to enforce the terms of the agreement and cannot adjudicate

a matter beyond the agreement itself. If the arbitrator

adjudicates a claim of a contractor with reference to the

clauses of the agreement itself whereby the agreement gets

engrafted into the award, it will be open to the court to

examine those clauses of the agreement and find out the

correctness of the conclusion of the arbitrator with

reference to those clauses. Bearing in mind the aforesaid

parameters for exercise of jurisdiction by Court in

examining the legality of an award of an arbitrator, the

award in hand as well as the order of the subordinate Judge

and that of the High Court requires scrutiny.

Admittedly under the agreement the completion period of

work was 28.2.1989. The stipulated quantity of work in

respect of Item No. 13 was 57000 cubic meters and in respect

of Item No. 15 it was 3500 cubic meters. In the course of

execution of the contract, drawings and designs were changed

as a result of which there was abnormal increase of the

quantity of work and for such increase of quantity of work

when the contractor claimed a higher rate and gave the

analysis before the arbitrator, which was not disputed by

the State and the arbitrator accepted the rate, the court

will not be justified in interfering with the same. It is

not possible for us to accept the contention of Mr. Sehgal

that under the terms of the agreement the contractor was not

entitled to claim any higher rate. The arbitrator having

considered all the relevant materials and there being no

legal proposition which has formed the basis for acceptance

of a higher rate and no the other hand the same being

arrived at on account of the abnormal increase in the

quantity of work which was on account of change of drawings

and designs, the court will not be justified in interfering

with the same. The first contention of Mr. Sehgal,

therefore, cannot be accepted.

But the second submission of Mr. Sehgal is

unassailable. After expiry of the period stipulated in the

agreement in respect of further quantity of work executed by

the contractor, the State has been praying at a higher rate

by calculating in terms of the escalation clause in the

contract itself. When the claimant filed his claim petition

before the arbitrator an assertion was made in paragraph 27

of the Claim Petition that the opposite party in respect of

the extra quantity of work executed in Item No. 13 has paid

and is paying at the rate of Rs. 243.00 per cubic meter

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6

though the claimant is entitled to a rate of Rs. 453.50 per

cubic meter and hence the claimant is entitled to an

additional amount at the rate of Rs. 210.50 per cubic meter

(Rs. 453.50 - 243.00) and the amount thus comes to Rs.

91,56,750. Similarly, in respect of extra quantity of work

in Item No. 15 it was averred in paragraph 30 of the Claim

Petition that the Opposite party in respect of this extra

quantity has paid and is paying at the rate of Rs. 460/- per

cubic meter though the claimant is entitled to a rate of Rs.

739.55 per cubic meter and hence the claimant is entitled to

an additional amount at the rate of Rs.279.55 per cubic

meter (Rs. 739.55-460.00) and the amount thus comes to Rs.

9,92,402.50. The Claim Petition was filed on May 19, 1990.

But it was brought to our notice in the course of hearing of

this appeal by Mr. Seghal, learned senior counsel appearing

for the appellant that subsequent to 28.2.1989 which was the

period contemplated under the agreement for completion of

work, the contractor - claimant has been paid at an

escalated rate in accordance with the escalation clause in

the agreement itself. Neither the arbitrator nor any of the

forums below have taken note of the aforesaid fact. Mr.

Sanghi, learned senior counsel appearing for the respondent

- contractor, however, vehemently urged that the claim of

Rs. 453.50 per cubic meter in respect of Item No. 13 and Rs.

739.55 per cubic meter in respect of Item No. 15 was the

basic rate claimed by the contractor and therefore any

payment already made for excess quantity of work after the

stipulated period in the agreement in accordance with the

escalation clause in the agreement cannot be taken into

account in adjudicating the claim of the contractor. We are

unable to accept this contention of Mr. Sanghi in as much as

the claimant himself, as has stated earlier unequivocally in

the Claim Petition averred that the claimant has been paid

and is being paid at the old rate stipulated in the

agreement and he is entitled to the higher claim. In respect

of the excess quantity of work executed by the claimant

subsequent to the completion period indicated in the

agreement when the claimant has made the claim at a higher

rate and that claim is allowed by the arbitrator on the

basis of analysis of rates given by him, then the amount

already paid to him by the State in accordance with the

escalation clause in the agreement has to be adjusted and

the claimant would not be entitled to double benefit on that

score. Unfortunately, this position has been lost sight off

by the arbitrator as well as by the subordinate Judge and

the High Court possibly because this has not been brought to

the notice by the State. Mr. Sanghi learned counsel

appearing for the respondent on instruction from his client

does not dispute the position that subsequent to 28.2.1989,

in respect of the quantity of work executed by the

contractor, he has been paid at an escalated rate on the

basis of calculation made in accordance with the escalation

clause in the agreement. This being the position, we would

have ordinarily set aside the award of the arbitrator and

remitted the matter for recalculation. But in the course of

hearing Mr. Sanghi, learned counsel appearing for the

respondent submitted that the matter may be decided by this

Court since a considerable period has lapsed in the meantime

and did not dispute the calculation sheet that was filed by

Mr. Seghal, learned counsel appearing for the State, as well

as the affidavit of Shri Ambika Prasad, Executive Engineer,

Maudha Dam, Construction Division. In the same affidavit

after making necessary adjustments of payment, made at the

escalated rate, it has been stated that the contractor would

be entitled to the amount of Rs. 37,26,917.22 in respect of

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6

Item No. 13 for the extra work executed between 1.3.1989 to

30.4.1990 and a sum of Rs. 1,71,542,41 in respect of extra

quantity of work for Item No. 15 for the period between

1.3.1989 to 30.4.1990 and thus in all the claimant -

contractor would be entitled to Rs. 38,98,459.63 in respect

of the extra quantity of work executed by him for the period

1.3.1989 to 30.4.1990. Since the calculation made in this

affidavit is not disputed and in view of the submission made

by Mr. Sanghi appearing for the claimant contractor, we

modify the award of the arbitrator and direct that the

claimant would be entitled to an additional sum of Rs.

38,98,549.63 in respect of the work executed by him upto

30.4.1990 and the same amount would also carry interest at

the rate of 9% per annum from 21.5.1990 till payment is

made, as awarded by the Arbitrator himself.

The arbitrator has also held in the award that the

claimant would be entitled to be paid at the same rate as

indicated in the award in respect of the work executed

subsequent to 30th April, 1990. Mr. Sanghi, the learned

senior counsel appearing for the contractor submitted that

no reference has been made to the arbitrator as to at what

rate the contractor would be paid in respect of the work

executed subsequent to 30th April, 1990 and infact the

claimant contractor had not made any claim on that score.

And as such the said direction of the arbitrator must be

held to be without jurisdiction. Mr. Sehgal the learned

senior counsel appearing for the State also could not point

out any material to indicate that the reference included the

dispute with regard to the rate at which the contractor

would be paid even subsequent to 30th April, 1990. The

arbitrator obviously cannot entertaion and decide any

dispute which has not been referred to it. In this view of

the matter the direction of the arbitrator must be held to

be without jurisdiction and we accordingly quash that part

of the direction. In the net result, therefore, the appeal

is allowed in part to the extent already indicated. There

will be no order as to costs.

Reference cases

Description

Supreme Court on Arbitrator's Jurisdiction: A Deep Dive into State of U.P. vs. M/S. Ram Nath International Const. Pvt. Ltd.

The landmark 1995 Supreme Court ruling in State of U.P. vs. M/S. Ram Nath InternationalConst. Pvt. Ltd. remains a pivotal judgment for understanding Arbitration Award Jurisdiction and its interplay with complex Contract Law Disputes. This celebrated case, available on CaseOn, clarifies the fine line an arbitrator must walk between interpreting contractual terms and exceeding their mandated authority, particularly when faced with unforeseen and substantial changes in the scope of work.

Case Background: A Dam Project and Drastic Design Changes

The dispute originated from a 1985 contract between the State of Uttar Pradesh (the appellant) and M/s. Ram Nath International Const. Pvt. Ltd. (the respondent) for the construction of the Maudaha Dam. The contract specified quantities and rates for various items of work. However, in 1987, the State significantly altered the designs and drawings for two specific items (Item 13 and Item 15). These changes resulted in an “abnormally high” increase in the quantity of work required, far exceeding the original estimates.

Consequently, the contractor demanded a higher rate of payment for this excess work, arguing that the original agreed-upon rates were no longer viable. When the State refused, the matter was referred to a sole arbitrator as per the agreement's arbitration clause.

The Arbitrator's Award and Subsequent Legal Challenges

Before the arbitrator, the contractor claimed over ₹1 crore, presenting a new rate analysis to justify the higher payment. The arbitrator accepted this analysis, noting the fundamental change in the work's scope. He awarded the contractor a sum of ₹90,21,765.65 with interest. Crucially, the arbitrator also directed that any work executed after April 30, 1990, should also be paid at this newly determined higher rate.

The State's objections were dismissed by the Civil Judge, who made the award a rule of the court. The Allahabad High Court, on appeal, upheld the arbitrator's award on its merits, reiterating the limited scope of judicial interference in arbitral decisions. This led the State to appeal to the Supreme Court.

IRAC Analysis of the Supreme Court's Judgment

Issue

The Supreme Court examined three primary legal questions:

  1. Did the arbitrator exceed his jurisdiction by awarding a new, higher rate instead of adhering to the escalation clause already present in the contract?
  2. Did the arbitrator commit a grave error by failing to deduct the payments already made to the contractor under the contract’s escalation clause, thereby potentially allowing a double benefit?
  3. Was the arbitrator empowered to issue directions regarding the payment rates for future work that was not part of the referred dispute?

Rule of Law Applied

The Court's decision was anchored in established principles of arbitration law:

  • The Arbitrator is a Creature of the Contract: An arbitrator's authority is derived solely from the contract. They cannot adjudicate matters beyond the terms of the agreement or the scope of the dispute referred to them.
  • Limited Judicial Review: Under the Arbitration Act, 1940 (Section 30), a court cannot re-evaluate the evidence or substitute its own judgment for the arbitrator's. Interference is only permitted on specific grounds like misconduct or an error of law apparent on the face of the award.
  • Principle Against Unjust Enrichment: A party cannot be unjustly enriched by receiving double payment for the same claim. Any amounts already paid towards a claim must be duly accounted for in the final award.

Court's Analysis

The Supreme Court meticulously analyzed each aspect of the dispute. It upheld the arbitrator’s decision to grant a higher rate, concluding that the “abnormal increase” in work due to design changes justified a rate revision beyond the standard escalation clause. Since the State had not disputed the contractor’s rate analysis during arbitration, the Court found no reason to interfere with this finding.

However, the Court found the State’s second argument—regarding double payment—to be “unassailable.” It was brought to the Court’s attention that after the original contract period expired, the contractor had already been receiving payments at a higher, escalated rate as per the contract's own escalation mechanism. The arbitrator, in his award, had calculated the due amount by subtracting the original base rate from the new rate he determined, completely ignoring the escalated payments already made. This was a clear error, as it allowed the contractor to benefit twice for the same period of work.

For legal professionals short on time, understanding the nuances of how the court differentiated between permissible rate revision and impermissible double-counting is crucial. CaseOn.in's 2-minute audio briefs on rulings like this provide a quick and effective way to grasp such key distinctions.

Finally, the Court addressed the arbitrator's direction for future work. It held that the dispute referred to arbitration was confined to work executed up to April 30, 1990. Therefore, the arbitrator had no jurisdiction to decide the rates for work performed after this date. This part of the award was deemed to be beyond the scope of the reference and was struck down.

Conclusion

The Supreme Court partially allowed the appeal. Instead of remitting the case for recalculation, and with the consent of both parties, the Court modified the award. It re-calculated the payable amount by properly accounting for the escalated payments the contractor had already received. The final award was reduced to ₹38,98,459.63 with interest. The direction concerning payments for future work was quashed entirely.

Final Summary of the Judgment

The Supreme Court affirmed that while an arbitrator has the authority to award higher rates in cases of fundamental contractual changes, this power is not absolute. An arbitrator cannot ignore payments already made under existing contractual clauses, such as escalation provisions. Furthermore, an arbitrator must strictly confine their award to the specific disputes referred to them and cannot issue directives on matters, such as future work, that fall outside that scope.

Why This Judgment is an Important Read for Lawyers and Students

This case serves as a critical lesson in arbitration practice. For lawyers, it underscores the importance of meticulously presenting all facts, including interim or escalated payments, to prevent errors in arbitral awards. It also provides a clear precedent for challenging parts of an award that exceed the arbitrator's jurisdiction.

For law students, it is a quintessential example of the delicate balance between the finality of an arbitral award and the necessity of judicial oversight. It brilliantly illustrates the concept of an arbitrator as a “creature of the contract” and demonstrates the tangible consequences of an arbitrator straying beyond the contractual and jurisdictional boundaries.

Disclaimer: This article is for informational purposes only and does not constitute legal advice. Readers are advised to consult with a qualified legal professional for any specific legal issues.

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter