contract law
0  09 Sep, 2009
Listen in 1:03 mins | Read in 54:00 mins
EN
HI

Steel Authority of India Ltd. Vs. Gupta Brother Steel Tubes Ltd.

  Supreme Court Of India Civil Appeal /5241/2002
Link copied!

Case Background

The case revolves around a dispute between the Steel Authority of India Ltd. (SAIL) and the respondent concerning an arbitration award related to a contract for the supply of materials. ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 5241 OF 2002

Steel Authority of India Ltd. …Appellant

Versus

Gupta Brother Steel Tubes Ltd. …Respondent

JUDGEMENT

R.M. Lodha, J.

Steel Authority of India Ltd. (SAIL) has preferred

this appeal by special leave aggrieved by the judgment of

High Court of Punjab and Haryana passed on May 15, 2001

whereby the learned Single Judge dismissed Revision Petition

preferred by the present appellant against the judgment dated

September 1,1999 passed by District Judge, Chandigarh

affirming the judgment and order dated May 9, 1994 passed by

the Court of Sub-Judge, 1

st

Class, Chandigarh dismissing the

objections preferred by the present appellant under Sections

30/33 of the Indian Arbitration Act, 1940 and the award dated

September 7, 1993 given by the sole arbitrator was made rule

of the Court.

2. Brief narration of facts is necessary before we embark

upon the contentions raised on behalf of the appellant. On April

18, 1988, SAIL formulated a scheme entitled “Full Requirement

Supply Scheme” (for short, ‘the Scheme’). The said scheme is

said to have been designed for meeting the full requirements of

HR Coils/Skolps to the customers. Those who wanted to avail

the said material as per the scheme were required to register the

requirements with SAIL. The scheme further stipulated that those

who wanted material over and above what was likely to be

available from indigenous sources and were willing to accept

imported HR Coils were required to register the requirements

separately. The scheme was in operation in respect of two

quarters, namely, (i) July to September, 1988 and (ii) October to

December, 1988.

2

3. The case of the respondent is that pursuant to the

terms of said scheme, they submitted an application for 1500

metric tones of imported material for the first quarter(July to

September, 1988). It is also their case that they furnished the

financial cover in terms of the said scheme.

4. On September 15, 1988, SAIL informed their inability

to arrange for the import against the indent for reasons beyond its

control.

5. The respondent, thereafter, indented for supply of

1500 metric tonnes of imported material for the second quarter

(October to December, 1988). The indent was accepted by SAIL.

The respondent furnished securities in terms of bank guarantee

in lieu of irrevocable letter of credit and took physical delivery of

the goods on March 7, 1989 and made payment for the same on

February 15, 1989.

6. It appears that dispute/differences arose between the

parties and the respondent lodged its claim to the appointing

authority on March 11, 1989. Initially, one Shri K. Janardhana was

appointed as Arbitrator but he resigned later on and in his place

Shri K.P. Bhaumik was appointed arbitrator.

3

7. It may be noticed here that an application was made

by the respondent before the arbitrator on September 12, 1991 for

quantification of claims under the heads ‘A’, ‘AA’ and ‘AAA’ and

thereby they made a total claim of Rs. 1,75,41,359/- alongwith

interest @ 21 per cent against SAIL before the arbitrator.

8. The claimant – respondent in support of its claim

produced oral as well as documentary evidence. In opposition,

SAIL also produced oral as well as documentary evidence before

the arbitrator.

9. The arbitrator seems to have had fifty sittings and

after hearing the parties and taking into consideration the

documentary as well as oral evidence passed an award on

September 7, 1993. The award runs into almost 290 foolscap

pages.

10. The objections to the award were filed by SAIL before

Sub-Judge, Ist Class, Chandigarh raising diverse grounds, inter

alia; that the arbitrator was biased in favour of the claimant; that

he committed a jurisdictional error in adjudication of claims for the

period from July to September, 1988 and granting claim in this

regard when there was no pre-existing dispute; that the arbitrator

4

entertained claim in respect of future disputes i.e. disputes not

existing at the time of reference; that he went into constitutional

questions such as discrimination, etc. which he had no

jurisdiction to decide; that he ignored the terms of contract and

returned the findings contrary to the express terms thereof; that

the arbitrator failed to call for material documents and gave the

award which is perverse and based on no evidence and that he

committed jurisdictional error by ignoring the express term of the

contract, particularly Clause 7.2 and the provisions of the Contract

Act.

11. The Sub-Judge, Ist Class, Chandigarh, after hearing

the parties overruled the objections raised by SAIL and made the

award rule of the Court on May 9, 1994. The Sub-Judge, Ist

Class, Chandigarh directed that claimant shall be entitled to

interest @ 12% per annum from the date of the judgment until

realization.

12. SAIL challenged the judgment and order dated May 9,

1994 passed by the Sub-Judge, Ist Class, Chandigarh by filing an

appeal before the District Judge, Chandigarh who by its decision

dated September 1, 1999 dismissed the appeal.

5

13. SAIL preferred revision petition before the High Court

of Punjab & Haryana against the aforesaid decisions. It is

pertinent to notice here that before the High Court on behalf of

SAIL, two contentions were raised, namely, (i) that the arbitrator

had committed error of jurisdiction when he entered a time barred

claim and (ii) that the Arbitrator had awarded damages to the

claimant under category ‘A’, ‘AA’ and ‘C’ by exercising his power

beyond Clause 7.2 of the agreement. It was thus submitted that

the arbitrator committed misconduct by going beyond the terms of

the contract (7.2) and violating the provisions of the Contract Act.

14. The High Court was not persuaded by the two

submissions made on behalf of the SAIL and dismissed Civil

Revision Petition on May 15, 2001.

15. It is appropriate at this stage to reproduce the

arbitration clause in the agreement and Clause 7.2. which is

material for deciding this appeal.

“ARBITRATION CLAUSE:

i) In the event of any question, dispute or difference

arising under the conditions referred to above or any special

conditions or Contract or in connection with this Contract

(except as to any matters, the decision of which is

specifically provided for in the conditions referred to above

or the special conditions) the same shall be referred to the

Sole Arbitration of the Chief Executive (by whatever name

6

he may be designated at the relevant time) of the Central

Marketing Organisation, Steel Authority of India Ltd.

(CMO/SAIL) for short) or his nominee. It will be no objection

that the Arbitrator is a company’s (CMO/SAIL) employee

and/or that he had to deal with the matters to which the

Contract relates or that in the course of his duties as a

company’s employees, he has expressed views on all or

any of the matters in dispute or difference. The award of the

Arbitrator shall be find and binding on the parties to this

contract.

ii)In the event of the Arbitrator dying, neglecting or

refusing to act or resigning or being unable to act for

any reason or his award being set aside by the court

for any reason, it shall be lawful for the Chief

Executive of the Central Marketing Organisation,

Steel Authority of India Ltd. to adopt/nominate another

arbitrator in place of the outgoing arbitrator in the

manner aforesaid.

iii)It is further a term of his contract that no person other

than the Chief Executive of the Central Marketing

Organisation, Steel Authority of India Ltd. or his

nominee as aforesaid, shall act as Arbitrator and that,

if for any reason that is not possible, the Chief

Executive of the Central Marketing Organisation,

Steel Authority of India Ltd. shall have the right to

nominate/appoint another person as second Arbitrator

and if the second Arbitrator also fails to arbitrate for

any reason, what so ever the matter is not to be

referred to Arbitration to all.

iv)The arbitrator may from time to time, with the

consent of all the parties to the contract enlarge the

time for making the award.

v) Upon every and any such reference, the assessment

of costs incidental to the reference and award

respectively shall be in the discretion of the Arbitrator.

vi)Subject as aforesaid, the Arbitration Act, 1940 and

the Rules thereunder and any statutory modifications

thereof, for the time being proceedings under this

clause.

7

vii)If the value of the claim in a reference exceeds Rs.1

lakh, the Arbitrator shall give reasoned award.

viii)The value of Arbitration shall be the place where the

contract was concluded or at Calcutta, being the

headquarters of the Central Marketing Organization,

as it may be fixed by the Arbitrator at his discretion

and the place so fixed by the Arbitrator shall be final

and binding upon the parties to the contract.

ix)In this clause, the expression, the Chief Executive

of the Central Marketing Organisation, Steel

Authority of India Ltd. means the Chief Executive of

the Central Marketing Organization (by whatever

name he may be designated at the relevant time) for

the time being and includes, if there be no Chief

Executive, or the Chief Executive is on leave or he is

absent from duty or is not available for any reason

whatsoever, the officer looking after the duties of the

Chief Executive of the Central Marketing

Organisation whether in addition to his other

“functions or otherwise”.

Clause 7.2

“SAIL shall supply materials as described in the

offer/work order(s)/Delivery order(s) issued by SAIL from

time to time. SAIL, however, shall have a period of one

month after expiry of the indicated quarter/quarters as grace

period for the purpose of supply or supplies. In the event of

SAIL’s failure(s) to deliver the indicated quantities even

after the expiry of the grace period, SAIL shall pay to the

customer(s) compensation @0.25% (quarter per cent) per

month or part thereof on the value of the materials of the

supplies delayed beyond the quarter/quarters plus the grace

period(s) subject to a maximum of 3% (three per cent ) of

the value of the delayed supplies. The value for this

purpose shall be worked out on the same basis as

mentioned in note (iii) to para 3.1 regarding calculation of

Initial Financial Cover. The aforesaid compensation shall be

paid within three months from the date of completion of

order. In case an order is not executed within 12 months

from the expiry date of the grace period, the order would be

treated as closed after payment of applicable compensation,

if and as due. Delay(s) caused in effecting supplies on

account of or all of the force majuere conditions and/or on

8

account of the failure/non-observance of the required

formalities by the customer(s) shall be accepted the SAIL

shall not bear any liability for such period(s).”

16. With regard to the question relating to Clause 7.2 of

General Terms and Conditions of the Contract, the arbitrator

considered the matter thus:

“19.14 I have given my careful consideration to the

arguments of the counsels for the parties. I find that the

compensation was to be paid by the Respondent within a

period of three months from the date of completion of the

transaction. In case the order is not executed within 12

months from the expiry of the grace period, the same was

treated as closed after payment of compensation as due. It

is proved on record that no supply was made for July-

September 1988 quarter against the duly registered indent

demand placed by the claimant and within 15 days of the

beginning of the quarter itself i.e. 15.7.1988, the

Respondent intimated that the material will not be supplied

to the claimant. The case, therefore, cannot fall within the

ambit of the relevant terms contained in the compensation

Clause reproduced above whereby, in case the order is not

executed within 12 months after the expiry of the grace

period the same was to be treated as closed and that too

after payment of applicable compensation. Neither, it is a

case of delayed supply (for July September 1988 quarter’s

booked).

19.15 In the instant case even otherwise, in this

Clause is to be brought into play the cut off date would be

30

th

October, 1989 (i.e. July-September 1988 + one month

grace period (October 1988) + 12 months i.e. upto 30

th

October, 1989 i.e. to say that after 30

th

October, 1989 in the

event of non-supply, the order was to be treated as closed,

but that too after the payment of applicable compensation

i.e. 3%, as limited under Clause 7.2. In the instant case

what has happened that on 15

th

July, 1988 itself the

Respondent regretted inability to supply the material (vide C-

5, C-7 and C-9) despite confirmed and duly registered

demand (C-3) by the claimant. No reference of any

compensation Clause (7.2) was made nor any cheque for

9

the amount of compensation at the given rate was sent nor

the account of claimant was credited with the amount as per

Clause 7.2. Obviously the case is a case of deliberate act of

non-supply as ‘reasons’ beyond control as intimated in C-5,

C-7 and C-9 have not been proved by the Respondent,

inspite of rigorous cross-examination by the claimant’s

advocate and more than the ample time and opportunity, at

the disposal of the Respondent. What has been

contemplated in the compensation Clause is where the force

majuere Clause is not invoked, there is complete lull or

silence on the part of the parties and a period of 12 months

expires after the expiry of grace period. In the instant case

even the said date would have been 30.10.1989 and even

then the Respondent should/must have paid the

compensation as stipulated if they wanted to bring the case

within the ambit of Clause 7.2, only thereafter the liability of

Respondent would have extinguished.

19.16 There is thus, substance in the contention of

the claimant that the compensation Clause as discussed

hereinabove cannot be made applicable in the fact and

circumstances duly proved on record. The alternate

argument of the Claimant regarding unconscionability of the

contract/particular term thereof vis-à-vis the present Clause

7.2 and relying on AIR 1986 SC 1571 need not be gone into.

Under issue No.15, I have attempted to set out various

clauses of document C-2, including the present Clause and

giving a finding that the Scheme C-2 is in favour of the

Respondent, but since the findings under the present issues

are that the Clause, even otherwise, is not applicable in the

case of non-supply of material for July-September, 1988

quarter I leave the matter to rest without going into the

question of unconscionability.”

17. The Sub-Judge, Ist Class, Chandigarh while dealing

with the objections of the appellant with regard to Clause 7.2

considered the matter thus:

“51.If the above observations of the arbitrator are read

carefully it would become clear that he never out stepped the

confines of the contract, he has remained inside the

parameters of the contract and has construed the clause 7.2

10

thereof. If he has committed any error in the construction of

the contract, that is an error within his jurisdiction.

Therefore, the authority of law in Associated Engineering Co.

vs. Government of Andhra Pradesh (ibid) is of no help to the

objector. In that case the error had arisen not by mis-

reading or mis-construing or by mis-understanding the

contract but by acting contrary of what was agreed. In that

case the arbitrator had traveled outside the permissible

territory not by construction of the contract but by merely

looking at the same. It was held by Hon’ble Supreme Court

that if the arbitrator remained inside the parameters of the

contract and has construed the provisions of the contract,

his award be interfered with unless he has given reasons for

the award disclosing an error apparent on the fact of it. In

the present case the arbitrator has reached the conclusion

by interacting the contract. The conclusion cannot be

termed as conscious disregard of the law or the provisions of

the contract. The findings of the arbitrator that clause 7.2 of

the scheme is not applicable on the facts and circumstances

of the case is not perverse but based on reasoning.

Similarly there is no error apparent on the face of record

which would vitiate the award. In Sudarsan Trading Co. vs.

Government of Kerala And Anr., AIR 1989 SC 890 (ibid) it

was held that if on a view taken of a contract, the decision

of the arbitrator on certain amounts awarded is a possible

view though perhaps not the only correct view, the award

cannot be examined by the court and that the court has no

jurisdiction to substitute its own evaluation of the conclusions

of law or fact to come to the conclusion that the arbitrator

had acted contrary to the bargain between the parties. It

was further held that by purporting to construe the contract

the court cannot take upon itself the burden of saying that

this was contrary to the contract. Therefore, there is no

substance in the contention of the objector that the arbitrator

has exceeded his jurisdiction by traveling outside the bounds

of the contract and by ignoring clause 7.2 of the terms and

conditions.

52. The next objection of the objector is that the

arbitrator not only ignored the provisions of Clause 7.2 of the

contract but he also ignored the provisions of Section 74 of

the Contract Act wherein it has been specified that if a sum

named in the contract is the amount to be paid in case of

breach, or if the contract conditions any other stipulation by

way of penalty, the party complaining of the breach is only

entitled to receive from the party who has broken the

11

contract a reasonable compensation not exceeding the

amount so named. Learned counsel argued that the

arbitrator knowingly went against this provision of law. He

further argued that in Sir Chuni Lal V. Mehta & Sons vs.

Century Spinning and Manufacturing Co. AIR 1962 SC 1314,

the Apex Court has held that where the parties have

deliberately specified the amount of liquidated damages,

there can be no presumption that they at the same time

intends to allow the party who had suffered by the breach to

say good bye to the sums specified and claim instead a sum

of money which was not ascertained at the date of breach.

Learned counsel further argued that the arbitrator proceeded

contrary to the settled principle of law that damages for

breach of contract by seller by failure to deliver goods are

confined to the difference between the contract price of the

goods and the market price of the goods if the same are

available in the market. Learned counsel pointed out that in

the present case the claimant has specifically admitted that

the goods were available in the market. It was, therefore,

the duty of the claimant to purchase the said goods from the

market and the SAIL could have only been made liable for

the difference if any between the contractual price and

market price.

53. To my mind, in view of my above finding, there

is no substance in the contention of the objector that the

arbitrator ignored the provisions of Section 74 of the

Contract Act. Once the arbitrator held that clause 7.2 of the

Contract was not applicable on the facts and circumstances,

there can be no question of any liquidated damages.

Resultantly it cannot be said that provisions of Section 74 of

the Contract Act have been ignored. The authority of law in

Chuni Lal V. Mehta (ibid) would have been applicable only if

it was held that clause 7.2 of the Contract was applicable. In

Hindustan Tea Co. vs. M/s K. Shashikant & Co. AIR 1987

SC 81, it was held that where a reasoned award is

challenged on the ground that the arbitrator acted contrary to

the provisions of Section 70 of the Contract Act, it would

be not ground for settling aside the award. On the same

analogy, even if the contention of the objector is accepted,

the present award cannot be set aside merely on the ground

that the arbitrator acted contrary to the provisions of Section

74 of the Contract Act. In the similar way the contention

that the provisions of Sale of Goods Act were not followed is

also devoid of any merit because the arbitrator gave due

12

weight to the respective contention of the parties and

reached the conclusion which cannot be termed as absurd.”

18. When the matter came to the District Judge in

appeal, he after taking into consideration the findings recorded

by the arbitrator and the Sub-Judge, Ist Class, Chandigarh,

recorded his findings:

“18.On careful reading of these observations of the

arbitrator, it would be clear that he never outstepped the

parameters of the contract. He remained inside the

Laxman Rekha of the contract and construed clause 7.2

thereof in a reasonable manner. If he has committed any

error in the construction of the contract, it was error within

his jurisdiction. Therefore, the authority reported as AIR

1992 SC 232 Associated Engineering Co. vs. Government of

Andhra Pradesh does not help the Appellant. In that case,

the error had arisen not by mis-reading or misconstruing or

misunderstanding the contract, but by acting contrary to

what was agreed. In that case, the arbitrator had traveled

outside the permissible territory not by construction of the

contract but by merely looking at the same. So it was held

by Hon’ble Supreme Court that if the arbitrator remained

inside the parameters of the contract, and has construed the

provisions of the contract, his award cannot be interfered

with, unless he has given reasons for the award disclosing

an error apparent on the face of it. In the present case, the

arbitrator does not appear to have showed any conscious

disregard of the law or the provisions of the contract. So the

findings of the arbitrator that the provisions of clause 7.2 of

the scheme are not applicable to the facts and

circumstances of the present case, cannot be said to be

perverse. These are manifestly based on sound reasoning

which cannot be said to be perverse. Surely there is no

error apparent on the face of the record.

19.In AIR 1989 SC 890 Sudarsan Trading Co vs.

Government of Kerala, it inter-alia ruled that if on a view

taken of a contract, the decision of the arbitrator on certain

amounts awarded is a possible view though perhaps not the

only correct view, then the award cannot be examined by

13

the Court, and the Court has got no jurisdiction to substitute

its own evaluation of the conclusion of law or fact to come to

the conclusion that the arbitrator had acted contrary to the

bargain between the parties. It was further ruled ibid that by

purporting to construe the contract, the Court cannot take

upon itself the burden of saying that this was contrary to the

contract. So the learned trial Court was justified in holding

that the arbitrator had not exceeded his jurisdiction, nor he

had traveled outside the bounds of the contract while

interpreting clause 7.2 of the scheme.

20.Surely the quantum of damages is closely inter-

related with the interpretation of clause 7.2 of the scheme.

But as demonstrated above, the arbitrator concluded, and

not perversely or unreasonably, that clause 7.2 of the

scheme was not applicable to the facts of the case in hand.

Therefore, it proceeded to examine the question of

damages in paras 52 and 53 of the impugned judgment.

21.The contention of the learned counsel for the

appellant is that not only has the arbitrator ignored the

provisions of clause 7.2 of the contract, but he had also

ignored the provisions of section 74 of the Contract Act

wherein it has been stipulated that if a sum named in the

contract is the amount to be paid in case of breach, or if the

contract conditions or any other stipulation by way of

penalty, the party complaining of the breach is only entitled

to receive from the party who has broken the contract, a

reasonable compensation not exceeding the amount so

named. It is submitted by the Id. Counsel for the appellant

that the arbitrator intentionally and knowingly went against

the provisions of Section 74 of the Contract Act. Ld. Counsel

for the appellant has also relied on AIR 1962 SC 1314 Sir

Chuni Lal V. Mehta & Sons vs. Century Spinning and

Manufacturing co. where it was inter-alia held that where the

parties had deliberately specified the amount of liquidated

damages, there can be no presumption that they at the

same time intended to allow the party who had suffered by

the breach to say good-bye to the sums specified and claim

instead a sum of money which was not ascertained at the

date of breach. He has further contended that the arbitrator

proceeded contrary to the settled principle of law that

damages for breach of contract by seller by failure to deliver

goods are defined to the difference between the contract

price of the goods and the market price of the goods if the

same are available in the market. He has pointed out that in

14

the present case, the Respondent has specifically admitted

that the goods were available in the market and therefore, it

was the duty of the Respondent to purchase the said goods

from the market and the SAIL could have been made liable

for the difference, if any, between the contractual price and

the market price.

22.However, in para 53 of the impugned judgment, the

learned Trial Court inter alia observed that once the

arbitrator held that clause 7.2 of the contract was not

applicable on the facts and circumstances of this case,

there was no question of any liquidated damages and

resultantly it cannot be said that the provisions of Section 74

of the Contract Act had been ignored. According to the

learned trial Court, the authority of Chuni Lal V. Mehta case

(ibid) would have been applicable only if it was held that

clause 7.2 of the contract was applicable. It is further

observed by it that in AIR 1987 SC 81 Hindustan Tea Co. vs.

M/s K. Shashikant & Co., it was ruled that where a reasoned

award is challenged on the ground that the arbitrator acted

contrary to the provisions of Section 70 of the Contract Act, it

could be no ground for setting aside the award. Therefore,

on the same analogy, the learned trial Court was not

unjustified in concluding that even if the contention of the

Appellant is accepted, the present award cannot be set

aside merely on the ground that the arbitrator acted contrary

to the provisions of Section 74 of the Contract Act.”

19. Learned single Judge of the High Court while

dealing with the second contention (concerning clause 7.2) put

forth before him on behalf of SAIL recorded finding thus:

“ Thus, a reading of the above clause which has

been relied upon by the learned counsel for the petitioner,

makes it abundantly clear that this clause has only covered

one exigency regarding the delivery or non-delivery or late

delivery of the goods. This clause gives power to the

Arbitrator to award compensation starting from 0.25% to the

upper limit of 2.01%. This clause never debars the Arbitrator

from entertaining the contract and consequential losses

which had been suffered by the respondent on account of

non-delivery or late delivery of the goods. If on account of

15

the act of the petitioner, the respondent-firm had suffered

huge losses to itself for the benefit of its customers,

certainly it has a right to recover the same. Be that as it

may, I am not to look at the merits of the case but I have to

examine whether the Arbitrator had exceeded beyond the

realm of arbitration clause or clauses of the contract. If he

had not, the civil court will not impose its

impression/judgment or opinion over the opinion of the

arbitrator, but I had already held that the Arbitrator is the

master of facts as well as of law. Even his erroneous

interpretation of the contract so long as he acts within the

contract, is not supposed to be interfered by the civil court

much less by the High Court, in the exercise of its revisional

jurisdiction.”

20. Mr. Jagdeep Dhankar, learned senior Counsel for

the appellant urged that the stipulation in Clause 7.2 is in

consonance with Section 74 of the Indian Contract Act 1872

and in that clause compensation is provided in respect of

supplies made beyond specified period; that the said clause

provides for maximum cap of liquidated damages by way of

compensation “to a maximum of three per cent of the value of

the delayed supplies” and that Clause 7.2 is a complete

answer to any breach of the contract for whatsoever reason

and, therefore, under no situation the quantum of damages can

exceed the stipulation in the liquidated damages clause. The

learned senior Counsel would, thus, urge that the arbitrator

exceeded his jurisdiction in disregarding well settled principle

16

that where the contract incorporates liquidated damages

clause, for breach of contract under no circumstances

the quantum of damages be awarded in excess of the cap

provided therein. He strongly relied upon two Constitution

Bench decisions of this Court in the case of Sir Chunilal V.

Mehta & Sons Ltd. vs. Century Spinning and Manufacturing

Co., Ltd.

1

and Fateh Chand vs. Balkishan Dass

2

. He also

relied upon decisions of this Court in Oil & Natural Gas

Corporation Ltd. vs. Saw Pipes Ltd.

3

and Tarapore & Co. vs.

State of M.P.

4

.

21. In Chunilal V. Mehta & Sons, the Constitution

Bench considered Section 74 of the Contract Act and held that

right to claim liquidated damages is enforceable under Section

74 of the Contract Act and where such a right is found to exist,

no question of ascertaining damages really arises. It was held

that where parties have deliberately specified the amount of

liquidated damages there can be no presumption that they, at

the same time, intended to allow the party who has suffered by

1

AIR 1962 SC 1314

2

AIR 1963 SC 1405

3

(2003) 5 SCC 705

4

(1994) 3 SCC 521

17

the breach to give a go-by to the sum specified and claim

instead a sum of money which was not ascertained or

ascertainable at the date of the breach. While construing

Clause 14 therein, the Court held that by providing for

compensation in express terms, the right to claim damages

under the general law is necessarily excluded.

22. Section 74 of the Indian Contract Act fell for

consideration before the Constitution Bench again in the case

of Fateh Chand. The Constitution Bench held thus:

“8….……………………………………………………. .

The Section is clearly an attempt to eliminate the sometime

elaborate refinements made under the English common law

in distinguishing between stipulations providing for payment

of liquidated damages and stipulations in the nature of

penalty. Under the common law a genuine pre-estimate of

damages by mutual agreement is regarded as a stipulation

naming liquidated damages and binding between the parties:

a stipulation in a contract in terrorem is a penalty and the

Court refuses to enforce it, awarding to the aggrieved party

only reasonable compensation. The Indian Legislature has

sought to cut across the web of rules and presumptions

under the English common law, by enacting a uniform

principle applicable to all stipulations naming amounts to be

paid in case of breach, and stipulations by way of penalty.

9………………………………………………………………..

10. Section 74 of the Indian Contract Act deals with the

measure of damages in two classes of cases (i) where the

contract names a sum to be paid in case of breach and (ii)

where the contract contains any other stipulation by way of

penalty. We are in the present case not concerned to decide

whether a contract containing a covenant of forfeiture of

deposit for due performance of a contract falls within the first

class. The measure of damages in the case of breach of a

stipulation by way of penalty is by Section 74 reasonable

18

compensation not exceeding the penalty stipulated for. In

assessing damages the Court has, subject to the limit of the

penalty stipulated, jurisdiction to award such compensation

as it deems reasonable having regard to all the

circumstances of the case. Jurisdiction of the Court to award

compensation in case of breach of contract is unqualified

except as to the maximum stipulated; but compensation has

to be reasonable, and that imposes upon the Court duty to

award compensation according to settled principles. The

section undoubtedly says that the aggrieved party is entitled

to receive compensation from the party who has broken the

contract, whether or not actual damage or loss is proved to

have been caused by the breach. Thereby it merely

dispenses with proof of “actual loss or damage”; it does not

justify the award of compensation when in consequence of

the breach no legal injury at all has resulted, because

compensation for breach of contract can be awarded to

make good loss or damage which naturally arose in the

usual course of things, or which the parties knew when they

made the contract, to be likely to result from the breach.

11. Before turning to the question about the compensation

which may be awarded to the plaintiff, it is necessary to

consider whether Section 74 applies to stipulations for

forfeiture of amounts deposited or paid under the contract. It

was urged that the section deals in terms with the right to

receive from the party who has broken the contract

reasonable compensation and not the right to forfeit what

has already been received by the party aggrieved. There is

however, no warrant for the assumption made by some of

the High Courts in India, that Section 74 applies only to

cases where the, aggrieved party is seeking to receive some

amount on breach of contract and not to cases where upon

breach of contract an amount received under the contract is

sought to be forfeited. In our judgment the expression “the

contract contains any other stipulation by way of penalty”

comprehensively applies to every covenant involving a

penalty whether it is for payment on breach of contract of

money or delivery of property in future, or for forfeiture of

right to money or other property already delivered. Duty not

to enforce the penalty clause but only to award reasonable

compensation is statutorily imposed upon courts by Section

74. In all cases, therefore, where there is a stipulation in the

nature of penalty for forfeiture of an amount deposited

pursuant to the terms of contract which expressly provides

for forfeiture, the court has jurisdiction to award such sum

19

only as it considers reasonable, but not exceeding the

amount specified in the contract as liable to forfeiture……”

23. In Oil and Natural Gas Corporation Ltd., while

dealing with the aspects of liquidated damages, this Court

considered the aforesaid Constitution Bench decisions in

Chuni Lal V. Mehta & Sons and Fateh Chand and after

reference to relevant parts of Sections 73 and 74 of the

Contract Act held thus:

“46. From the aforesaid sections, it can be held that when a

contract has been broken, the party who suffers by such

breach is entitled to receive compensation for any loss which

naturally arises in the usual course of things from such

breach. These sections further contemplate that if parties

knew when they made the contract that a particular loss is

likely to result from such breach, they can agree for payment

of such compensation. In such a case, there may not be any

necessity of leading evidence for proving damages, unless

the court arrives at the conclusion that no loss is likely to

occur because of such breach. Further, in case where the

court arrives at the conclusion that the term contemplating

damages is by way of penalty, the court may grant

reasonable compensation not exceeding the amount so

named in the contract on proof of damages. However, when

the terms of the contract are clear and unambiguous then its

meaning is to be gathered only from the words used therein.

In a case where agreement is executed by experts in the

field, it would be difficult to hold that the intention of the

parties was different from the language used therein. In such

a case, it is for the party who contends that stipulated

amount is not reasonable compensation, to prove the same.”

24. In Tarapore & Co., a two Judge Bench of this Court

considered few decisions of this Court including the decisions

20

in the case of M/s Sudarsan Trading Co. vs. Government of

Kerala and Anr.

5

, Associated Engineering Co. vs. Govt. of A.P.

6

and Managing Director, J&K Handicrafts, Jammu vs. Good

Luck Carpets

7

and held that where an arbitrator travels beyond

a contract, the award would be without jurisdiction and the

same would amount to misconduct and such award would

become amenable for being set aside by a Court.

25. In Sudarsan Trading Co., this Court held that an

error by the arbitrator relatable to interpretation of the contract

is not amenable to correction by courts.

26. It is not necessary to multiply the references.

Suffice it to say that the legal position that emerges from the

decisions of this Court can be summarised thus:

(i)In a case where an arbitrator travels beyond the

contract, the award would be without jurisdiction and would

amount to legal misconduct and because of which the

award would become amenable for being set aside by a

Court.

(ii)An error relatable to interpretation of the contract by

an arbitrator is an error within his jurisdiction and such error

is not amenable to correction by Courts as such error is not

an error on the face of the award.

5

(1989) 2 SCC 38

6

(1991)4 SCC 93

7

(1990) 4 SCC 740

21

(iii)If a specific question of law is submitted to the

arbitrator and he answers it, the fact that the answer

involves an erroneous decision in point of law does

not make the award bad on its face.

(iv) An award contrary to substantive provision of law or

against the terms of contract would be patently illegal.

(v)Where the parties have deliberately specified the

amount of compensation in express terms, the party who

has suffered by such breach can only claim the sum

specified in the contract and not in excess thereof. In

other words, no award of compensation in case of breach of

contract, if named or specified in the contract, could be

awarded in excess thereof.

(vi)If the conclusion of the arbitrator is based on a

possible view of the matter, the court should not interfere

with the award.

(vii)It is not permissible to a court to examine the

correctness of the findings of the arbitrator, as if it were

sitting in appeal over his findings.

27. Having noticed the legal position, we now turn to

Clause 7.2 which can be analysed thus:

(i)SAIL shall supply materials as described

in the offer/work order(s)/delivery order(s)

issued from time to time.

(ii)SAIL shall have a period of one month

as grace period for the purpose of

supply or supplies after expiry of the

indicated quarter(s).

(iii)SAIL shall pay to the customer(s)

compensation @ 0.25 per cent per

month or part thereof on the value of the

materials of the supplies in the event of

its failure(s) to deliver the indicated

quantity even after the expiry of the

grace period subject to maximum of

three per cent of the value of the

delayed supplies.

22

(iv)The compensation shall be paid within

three months from the date of

completion of order.

(v)In case the order is not executed within

12 months from the expiry of grace

period, the order would be treated as

closed after payment of applicable

compensation.

(vi) SAIL shall not bear any liability for such

period where delay caused in effect of

supplies is on account of failure/non-

observance of the required formalities

by the customer.

28. The question that needs to be determined by us is

whether the breaches alleged by the respondent are covered

by the stipulations contained in Clause 7.2. If the answer is in

affirmative, obviously compensation cannot be awarded beyond

what is provided therein. On the other hand, if breaches are

not covered by clause 7.2, cap provided therein with regard to

liquidated damages will not be applicable at all.

29. Insofar as booking of July-September, 1988 quarter

by the respondent is concerned, it is an admitted position that

the appellant (SAIL) declined the supply of materials i.e.

1500MT of 2mm thickness HR coils on the ground of ‘reasons

beyond control’. The arbitrator in the award observed that

SAIL has admitted that the demand was validly registered by

23

the claimant; that material was available in abundance specially

from domestic source and that supplies were made to others

ignoring the claim of the present respondent. The arbitrator

held that the intimation of the SAIL to the present respondent

that the material will not be supplied to the claimant cannot fall

within the ambit of Clause 7.2.

30. Although it has been strenuously urged on behalf of

the appellant that stipulations contained in Clause 7.2 are

comprehensive enough to include all types of breaches, on a

careful consideration thereof, we are unable to accept the

submission made on behalf of the appellant. Can it be said

that SAIL intended to provide for liquidated damages in the

contract even in a situation where they were unable to make

supply of materials for the reasons beyond control or they

declined to supply the materials on one ground or the other.

The answer has to be plainly in the negative. It is well known

that intention of the parties to an instrument has to be gathered

from the terms thereof and that the contract must be construed

having regard to the terms and conditions as well as nature

thereof. Clause 7.2 that provides for compensation to the

24

respondent for failure to supply or delayed supply of the

materials by SAIL was never intended to cover refusal to deliver

the materials of the supplies on the part of the SAIL. Refusal to

supply materials by SAIL resulting in breach is neither

contemplated nor covered in Clause 7.2. There is no

impediment nor we know of any obstacle for the parties to a

contract to make provision of liquidated damages for specific

breaches only leaving other types of breaches to be dealt with

as unliquidated damages. We are not aware of any principle

that once the provision of liquidated damages has been made

in the contract, in the event of breach by one of the parties,

such clause has to be read covering all types of breaches

although parties may not have intended and provided for

compensation in express terms for all types of breaches. It is

not a question of giving restrictive or wider meaning to clause

7.2 but the question is what is intended by the parties by

making a provision such as this and does such clause cover all

situations of breaches by SAIL.

31. A careful consideration of clause 7.2 would show

that it does not prescribe compensation for every type of

25

breach. To name a few, breaches such as: (i) supplies of

materials not in conformity with the contract; (ii) defective

materials of supplies; (iii) deficient or short supply; (iv) different

materials of the supplies are apparently not covered by Clause

7.2. We have indicated these breaches by way of illustration

only to make a point that the provision in the contract for

damages vide clause 7.2 cannot be said to extend to all

situations and all types of breaches. In substance and in form,

the claim of damages by the respondent for the breaches of

contract by SAIL is essentially distinct from the breaches

contemplated by Clause 7.2. In this back-drop, if the High

Court observed that Clause 7.2 is not panacea of all ills, it

cannot be said that High Court fell into an error. Again, the

view of the arbitrator that breach due to refusal on the part of

SAIL to supply materials in July-September, 1988 quarter does

not fall within the ambit of relevant terms contained in the

compensation Clause (7.2), by no stretch of imagination can be

said to be an absurd view. The arbitrator’s view about non-

applicability of Clause 7.2 for refusal to supply materials in

July-September, 1988 quarter and delayed supply of

26

materials for October-December, 1988 quarter is founded on

diverse grounds elaborately discussed in the award. Whether

this is or is not a totally correct view is really immaterial but

such view is a possible view that flows from reasonable

construction of Clause 7.2. The view of the arbitrator being

possible view on construction of Clause 7.2, and having not

been found absurd or perverse or unreasonable by any of the

three Courts, namely , Sub-Judge, District Judge and the High

Court, we are afraid, no case for interference is made out in

exercise of our jurisdiction under Article 136 of the Constitution.

32. Once the arbitrator has construed clause 7.2 in a

particular manner, and such construction is not absurd and

appears to be plausible, it is not open to the courts to interfere

with the award of the arbitrator. Legal position is

no more res integra that the arbitrator having been made the

final arbiter of resolution of disputes between the parties, the

award is not open to challenge on the ground that arbitrator has

reached at a wrong conclusion. The courts do not interfere

with the conclusion of the arbitrator even with regard to

construction of a contract, if it is a possible view of the matter.

27

The words “no award shall be set aside” in Section 30

mandate the courts not to set aside the award on the ground

other than those specified in Section 30. In a case such as

this, where the arbitrator has given elaborate reasons that

compensation clause 7.2 is not attracted for the breaches for

which the compensation has been claimed by the respondent

and such view of the arbitrator is a possible view, we are afraid

in the circumstances award is not amenable to correction by the

court.

33. The arbitrator having taken the view in respect of

Clause 7.2 that claim of damages by the respondent of the

breaches committed by the SAIL for refusal to supply materials

in July-September, 1988 quarter and delayed supply of the

materials for October-December, 1988 quarter did not fall within

the ambit of that clause, his further view that Section 74 of the

Contract Act has no application as the contract does not

determine damages for the breaches in question cannot be said

to be legally flawed. It is true that Section 74 declares the law

as to liability upon breach of contract where compensation is by

agreement of the parties pre-determined. However, in the

28

absence of any agreement specifying damages for the

breaches alleged by the respondent, Section 74, in the facts

and circumstances, is not at all attracted. Seen thus, the two

decisions of the Constitution Bench of this Court in Chunilal V.

Mehta & Sons and Fateh Chand have no application to the

fact situation of the present case.

34. The learned senior counsel for the appellant would

urge that the arbitrator had no jurisdiction whatsoever to

entertain the claim preferred on September 12, 1991 by way of

an application indicating quantification of claims. The

learned senior counsel submitted that the claimant preferred

the claim of about Rs. 64 lacs to the designated authority on

November 3, 1989 in terms of Clause 10 of the Scheme. The

designated authority nominated initially one Shri K.

Janardhana as an arbitrator but later on appointed Shri K.P.

Bhaumik as Shri K. Janardhana submitted his resignation.

Learned senior counsel submitted that the claim submitted on

November 3, 1989, pertained to the first quarter and for the first

time, after the arbitration proceedings had made substantial

headway, the claimant preferred an application designated as

29

quantification of claims thereby trebling the original claim of Rs.

64 lacs to Rs.175 lacs and introducing the claim in respect of

first quarter (July-September, 1988). He, thus, strenuously

urged that arbitrator had no jurisdiction to address the fresh

claims made on September 12, 1991.

35. We are not persuaded by the aforenoted

submission of the learned senior counsel for the appellant for

more than one reason. For one, the aforesaid argument was

not at all canvassed before the High Court. A perusal of the

judgment of the High Court would show that only two

contentions were raised there, namely; (i) that arbitrator

committed error of jurisdiction when he entered a time barred

claim and (ii) that the arbitrator awarded damages to the

claimant under category ‘A’, ‘AA’ and ‘C’ by exercising his

power beyond Clause 7.2 of the agreement. We are afraid the

appellant cannot be permitted to raise a contention before this

Court in an appeal by special leave which was not raised before

the High Court. This contention is not even indirectly or

remotely connected with the plea of limitation that was

canvassed before the High Court. For another, even

30

otherwise, we find no merit in the submission of the learned

senior counsel that fresh claim was made by the respondent on

September 12,1991. In the claim petition filed by the

respondent, in paragraph 18, it has been stated that in view of

non availability of certain details which are in possession of the

respondent and otherwise, the claimant reserves its right to

add, amend and/or modify the statement of claims.

Consequent upon the right already reserved in paragraph 18 of

the claim petition, the respondent quantified the claims,

namely, ‘A’, ‘AA’, ‘AAA’ vide application dated September 12,

1991. We find no merit that by consideration of the claims as

quantified vide application dated September 12, 1991, the

arbitrator exceeded his jurisdiction.

36. The learned senior counsel for the appellant also

urged that claim ‘A’ pertaining to difference in price has come to

be determined by the arbitrator de-hors contract stipulations.

In this regard the learned senior counsel referred to paragraph

20.21 and 20.22 of the award. We are afraid, this contention

too, cannot be permitted to be raised before us since no such

contention was raised before the High Court. There has to be

31

some sanctity and finality attached to the decision of the

arbitrator and new plea cannot be allowed to be raised in an

appeal under Article 136 which was not raised before the High

Court.

37. The learned senior counsel for the appellant

vehemently contended that the present case throws up the

prescribed jurisdiction issue wherein the arbitrator had chosen

to function only outside the confines of the contract and with

total disregard of express stipulations and, therefore, this Court

must interfere in the matter. He relied upon decisions of this

Court in the case of Rajasthan State Mines & Minerals Ltd. Vs.

Eastern Engineering Enterprises & Anr.

8

, Food Corporation of

India vs. Chandu Construction & Anr.

9

, Steel Authority of India

Ltd. vs. J.C. Budharaja, Government & Mining Contractor

10

and

Associated Engineering Co. vs. Govt. of Andhra Pradesh &

Anr.

6

, State of Jammu & Kashmir and Anr. vs. Dev Dutt

Pandit

11

.

8

(1999) 9 SCC 283

9

(2007) 4 SCC 697

10

(1999) 8 SCC 122

11

(1999) 7 SCC 339

32

38. We are afraid none of the decisions cited by the

learned senior Counsel for the appellant has any application to

the facts of the present case. The courts below have

concurrently held that the arbitrator has gone into the issues of

facts thoroughly, applied his mind to the pleadings, evidence

before him and the terms of the contract and then passed duly

considered award and no ground for setting aside the award

within the four corners of Section 30 has been made out. We

have no justifiable reason to take a different view. As noticed

above, only two grounds were urged before the High Court in

assailing the award, one of which relating to time barred claim

was ultimately notessed before us and the only argument

survived for consideration before us related to clause 7.2 of the

contract. In what we have already discussed above, the view

of the arbitrator in this regard is a possible view.

39. Consequently, appeal has no merit and must fail.

The same is dismissed with no order as to costs.

……………………J

(Tarun Chatterjee)

33

…….……………..J

(R. M. Lodha)

New Delhi

September 9, 2009.

34

Reference cases

Description

Legal Notes

Add a Note....