No Acts & Articles mentioned in this case
High Court of H.P.IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
Arbitration Case No. 71 of 2017
Reserved on:16.08.2019
Decided on: 23.08.2019.
__________________________________________________________
Tarun Mahindroo ….Petitioner
Versus
H.P. Power Corporation Limited …Respondent
______________
Coram:
The Hon’ble Ms. Justice Jyotsna Rewal Dua, Judge.
Whether approved for reporting?
1
Yes.
__________________________________________________________
For the petitioner : Mr. Suneet Goel, Advocate.
For the respondent : Mr. Sunil Mohan Goel, Advocate.
__________________________________________________________
Jyotsna Rewal Dua, J.
Feeling aggrieved against the award passed by the learned
Arbitrator, instant petition under Section 34 of the Arbitration &
Conciliation, Act 1996, has been preferred by the petitioner/claimant.
The main point to be adjudicated in this case is:- whether
loss of profits and over heads on account of prolongation of the contract,
can be awarded merely on the basis of Hudson formula without the
claimant leading any evidence, be it oral or documentary in respect of
loss, damages suffered by him.
1
Whether reports of Local Papers may be allowed to see the judgment?2
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.2
2. The factual position of this case, can be summarized as
under:-
2(i) The respondent awarded construction work of ‘Bachelor
Accommodation at Sunder Nagar, District Mandi (Civil Work, Internal
WS, SI and Electrical Installation)’ to the petitioner/claimant vide letter
of award dated 25.07.2011 (Annexure C-1). The contracted value of
the work was Rs.1,96, 03,299/-. The work was to be completed within
18 months from 21
st
day after issuance of letter of award dated
25.07.2011. Annexure C-2, contained the terms and conditions
governing the contract duly executed by the parties.
2(ii) Various representations of claimant, addressed to the
respondent, in respect of the contract work have been enclosed at
Annexure C-3 (colly). The details of the same can be summed up
hereunder:-
i)Letter dated 31.08.2011 to the effect that work at
site has been stopped by BBMB, on the ground that
land belongs to BBMB. Request was made for
revised handing over of the site to the
claimant/contractor.
ii)Letter dated 07.11.2011 is a reminder of previous
letter dated 31.08.2011, with respect to handing
over the possession of the site to the claimant.
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.3
iii)Letter dated 09.2.2012, written in continuation to
the previous letters that site had still not been
handed over to the contractor, resultantly, huge loss
on account of setting of cement, payments of
chowkidars for watch and ward of material stacked
at site stores and indirect losses
due to prolongation is being caused to the
claimant/contractor. Request was made for handing
over the possession of the site for starting and
completing the work in time.
iv)Letter dated 09.04.2012, to the effect that the
possession of the site had still not been handed over
to the contractor. Therefore, extension in time by
nine months was requested by the claimant. This
was followed by representation dated 07.01.2013
on the same lines.
v)Letter Dated 15.09.2014, intimating that the
extension of time for completion of the project
granted by the respondent up to 15.08.2014, had
lapsed, however, the site had still not been handed
over to the claimant. Therefore, the second
extension to time from 15.08.2014 to 14.02.2016,
i.e. for a period of 18 months, was sought for.
vi)Letter dated 04.10.2014, to the effect that despite
repeated requests, second time extension had not
been granted and accordingly, prayer was made for
extending the time period for completing the work.
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.4
vii)Letter dated 23.06.2016, requesting the respondent
either to appoint the Arbitrator under Clause-33 of
the Contract or to provide the site for construction
of the building.
2(iii) On 16.12.2016, notice (Annexure C-4), under Clause 36 of
the agreement, was issued by the respondent to the claimant, intimating
that despite best efforts of the respondent, the land ownership issues for
undertaking the construction of the project work, could not be resolved,
therefore, it was decided by the respondent to abandon the work.
2(iv) The Arbitrator was appointed by the order of this Court on
08.03.2017. Claimant preferred his claim before learned Arbitrator
under following heads:-
Sr. No. Heads Amount claimed
1. Loss of profit and over Rs. 29,40,495/-
heads on account of
prolongation of contract.
2. Refund of security. Rs. 10,000/-
3. Refund of earnest money.Rs. 3,43000/-
4. Cost of Arbitration Rs. 1,00,000/-
Proceedings.
5. Interest. 18% per annum.
2(v) The respondent contested the claim and denied that
contractor was put to any loss or harassment and that he had been
intimated and was aware regarding non-availability of land for
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.5
construction from the very beginning. It was denied that claimant
continued to deploy its labour and machinery at site.
2(vi) On consideration of the pleadings and the material
available on the record, learned Arbitrator passed impugned award on
29.07.2017. The award in tabulated form is :-
Sr. No.Heads Amount
claimed
Amount
awarded
1. Loss of profit and
over heads on account
of prolongation of
contract.
Rs.29,40,495/
-
-nil-
2. Refund of security.Rs.10,000/-Rs.10,000/-
3. Refund of earned
money.
Rs.3,43,000/-Rs.3,43,000/
-
4. Cost of Arbitration
Proceedings.
Rs.1,00,000/-Rs.1,11,565/
-
5. Interest 18% P.A. 9%
Thus, learned Arbitrator passed an award of Rs. 5,54,565/-
@ 9% interest payable within one month from the date of the award,
failing which, the respondent had to pay enhance rate of interest @ 12%
till the actual payment.
3. Learned Arbitrator having not find favour with the claim
of Rs. 29,40,495/- regarding alleged loss of profit and over heads on
account of prolongation of the contract, the claimant has preferred
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.6
instant objections under Section 34 of the Arbitration & Conciliation
Act.
4. Contentions:-
4(i) The main plank of the contentions of Mr. Suneet Goel,
learned counsel for the petitioner/claimant is that the claim under this
head was based purely on Hudson formula, where-under, claimant was
not required to prove any actual damage having been caused to him; he
was only required to show that the contract was prolonged, but not
because of any fault on part of the claimant; he is only required to prove
that the contract was extended and could not be completed because of
lapses, actions, inactions on part of the respondent or reasons, which
were attributable and could be sorted out only by the respondent.
His further contentions is that the learned Arbitrator, while
deciding proposition No.1, in the impugned award, had already held
that the prolongation of the contract period was due to the fact that
though the land on which the site was located, was owned and possessed
by the respondent, but the adjoining land required as a passage to reach
the site, was not owned by the respondent. The adjoining land was
owned and possessed by the BBMB and it is on account of this fact that
the construction work at site remained blocked and could not be carried
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.7
out. Accordingly, the contention of learned counsel for the
petitioner/claimant is that after having come to the conclusion that
project work was prolonged on the site because of non-availability of
the adjoining site, which was required as a passage by the claimant for
starting the construction work at site, it was not open for the learned
Arbitrator to have rejected his claim of loss of profit and over heads on
account of prolongation of the contract.
Learned counsel for the petitioner/claimant, in this regard
has relied upon (2006) 11 SCC 181, titled as Mcdermott International
Inc. v. Burn Standard Co. Ltd. and others and (2015) 3 SCC 49, titled
as Associate Builders v. Delhi Development Authority to contend that
Hudson formula is an accepted formula by the Hon’ble Apex Court, for
awarding loss of profit and over heads on account of prolongation of the
contract.
4(ii). Per contra, Mr. Sunil Mohan Goel, learned counsel for the
respondent, has argued that the claimant had executed certain site
development works, for which due and admissible amount of Rs.
1,02,654/- stands released to him.
He further submitted that the land where the building was
to be constructed by the claimant under the awarded work, belonged to
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.8
the State Government and was in possession of the respondent, however,
the approached road to the site was from the land owned and possessed
by BBMB, which objected to carrying out of the construction work vide
their (BBMB) letter dated 24.08.2011 (Annexure-III). Copy of this
objection of BBMB, had been supplied to the contractor and he was
made aware about the site problems; and it is on account of this
objection of BBMB that the work had to be stopped at the site at very
initial stage. The work could have been undertaken only after resolving
the land dispute. It was denied that contractor deployed any labour or
machinery at the site after August, 2011; the land disputes could not be
resolved, therefore, the work was foreclosed vide letter dated
16.12.2016 (Annexure C-4), as per Clause 36 of contract agreement.
Learned counsel further contended that no loss was suffered by the
contractor on account of prolongation of contract due to any reason
whatsoever. Hudson formula, without proof of any actual damage
suffered by the claimant, cannot advance the case of the petitioner for
his claim of profit and over heads on account of prolongation of
contract.
Learned counsel for the respondent relied upon (2010) 13
SCC 377, titled as Oil and Natural gas Corporation Vs. Wig Brothers
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.9
Builders and Engineers Private Limited, (2007) 4 SCC 697, titled as
Food Corporation of India vs. Chandu Constructions, (1999) 9 SCC
283, titled as Rajasthan Mines & Minerals Ltd. v. Eastern Engineering
Enterprises, in support of his contentions.
5. Observations:-
5(i) Stopping of Work:- It is seen from the record that vide
Annexure-III dated 24.08.2011, BBMB, had asked the respondent to
stop the ongoing construction work. It is not in dispute that this letter
was forwarded by the respondent to the petitioner/claimant. This is also
apparent from the fact that petitioner/claimant had himself written a
letter to the respondent as early as on 31.08.2011, regarding stopping of
work by BBMB Authorities on account of the fact that the adjoining
land required as passage by the contractor for carrying out awarded
construction work at site, belonged to BBMB, where-under, the
petitioner/claimant had also requested the respondent for revised
handing over of the site to him. The dispute, thus, had arisen in just
over a period of one month from the date of execution of the contract
agreement. The work had come to stand still in a period little over one
month from the date of execution of the contract agreement and
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.10
contractor was very well aware about the stopping of the work, reasons
for stopping of the work.
5(ii) Hudson Formula:-
5(ii)(a)No proof of actual damage suffered by the
petitioner/claimant has been placed on record. The claimant on
29.06.2017, stated before the learned Arbitrator that but for the
documents appended along with his claim petition, he did not want to
lead any oral or documentary evidence in support of his statement of
claim. There is no proof available on record that claimant deployed men
and machinery etc. at the site. No proof whatsoever has been furnished
by the claimant of having suffered any actual loss due to prolongation of
contract.
5(ii)(b)In my considered view, learned Arbitrator was justified in
turning down the claim of Rs. 29,40,495/- for alleged loss of profits and
over heads on account of prolongation of contract for want of proof of
any actual damage having been suffered by the claimant/contractor.
Hon’ble Apex Court in (2006) 11 SCC 181 titled as
Mcdermott International Inc. v. Burn Standard Co. Ltd. and others,
relied upon by learned counsel for the claimant, has not held that in a
case of instant nature, without there being any proof of any actual
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.11
damage having been caused to the claimant/contractor, in absence of any
oral or documentary evidence in this regard, he has to be held entitled to
15% of the contracted amount on the basis of Hudson formula. The
present is the case wherein just over a period of one month from the date
of execution of the contract agreement, the work had admittedly come to
stand still. Whatever work was done by the claimant, during this period
of little over one month, has been duly paid for by the respondent.
There is no proof of any deployment of any men or machinery or
material to suggest that claimant suffered any loss of profit and over
heads. Formula has to be applied to facts of a case; on the basis of the
evidence led by the claimant. Merely on the basis of an abstract
formula, without furnishing any evidence, any proof whatsoever of any
loss or damage having been suffered by the claimant, claim for loss of
profits and overheads cannot be allowed to him on the ground that
contract period was prolonged.
5(ii)(c)In (2015) 3 SCC 49 titled as Associate Builders v. Delhi
Development Authority, after adverting to an earlier judgment in
Mcdermott International Inc. v. Burn Standard Co. Ltd. and others,
(2006) 11 SCC 181, Hon’ble Apex Court reiterated that decision of
Arbitrator in applying Hudson formula in construction contracts for
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.12
awarding claim for loss of profit and over heads, cannot be interfered
with, in exercise of jurisdiction under Section 34 of Arbitration &
Conciliation Act. However, present is the case where neither there is
any oral nor documentary evidence to show any loss, or any damage
having been caused to the petitioner by prolongation of contract on part
of the respondent. Hudson formula cannot be applied in vacuum. No
details of any men, any machinery deployed on site after August, 2011,
is available. No details of any material loss has been provided. No
books of accounts are there. No details of any watch and ward staff,
supervisors etc. has been given. No material was produced with respect
to nature of practice in the trade. Claim for loss of profits has been
based on abstract Hudson formula and 15% value of contracted work
has been claimed as loss of profits and over heads on account of
prolongation of contract. Learned Arbitrator was justified in not
applying Hudson formula for awarding alleged loss of profits and over
heads in absence of any evidence. In Kalash Nath Associates vs. Delhi
Development Authority & Anr., (2015) 4 SCC 136, it has been held by
Hon’ble Apex Court that while considering the claim under Sections 73
& 74 of Contract Act, where it is possible to prove actual damage or
loss, such proof cannot be dispensed with. Monetary compensation in
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.13
lieu of loss prayed for by claimant cannot be awarded in negation of
Section 73 of Contract Act by penalizing the respondent even though
claimant had not proved any loss suffered by him. Reference can also
be made in this regard to a judgment passed by Bombay High Court in
Case No. 470 of 2012, tilted as Essar Procurement Services Ltd. vs.
Paramount Constructions:-
“101.The question that arises for consideration of this
court is whether the respondent who had made claim for
overhead on the basis that the respondent had
considered 10% towards overhead for the work in
question at the time of finalization of the contract and
had incurred such amount during the contractual period
ought to have proved the said claim by leading evidence
including oral evidence or could have simplicitor rely
upon the Hudson formula and whether in absence of any
evidence of the actual expenditure incurred by the
respondent, the arbitral tribunal could have allowed the
claim for overhead by considering the claim on rough
and ready basis by applying Hudson formula by
dispensing with the proof of the overhead expenditure or
not.
103. It is held that the different formula can be applied
in different circumstances and the question as to
whether damages should be computed by taking
recourse to one or the other formula, having regard to
the facts and circumstances of a particular case, would
eminently fall within the domain of the arbitrator.
Supreme Court noticed that the witness examined by the
contractor had applied the Emden Formula while
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.14
calculating the amount of damages having regard to the
books of account and other documents maintained by
the contractor. The learned arbitrator did not insist that
sufferance of actual damages must be proved by
bringing on record books of account and other relevant
documents. In these circumstances, Supreme Court held
that if the learned arbitrator applied the Emden
Formula in assessing the amount of damages, he could
not be said to have committed an error warranting
interference by this Court. The learned arbitrator had
also referred to other formulae but opined that the
Emden Formula was widely accepted one.
105. Division Bench of this court in case of Edifice
Developers and Project Engineers Ltd. (supra) after
adverting to the judgment of Supreme Court in case of
McDermott International INC. (supra) and in case of
M/s.A.T.Brij Paul Singh and Bros. vs. State of Gujarat,
AIR 1984 SC 1703 which judgments were relied upon by
the arbitral tribunal has held that the appellant in that
case had produced no evidence in support of the claim
for loss of overhead and profit and award of claim was
on the misconceived basis that Hudson Formula must be
applied despite there being no evidence. The Division
Bench also held that no material was produced before
the arbitral tribunal on the nature of the practice in the
trade and claim for loss of profits was based on pure
conjecture and in the absence of any evidence and was
thus rightly set ppn 49 arbp-470.12(j).doc aside by the
learned Single Judge. The Division Bench upheld the
conclusion drawn by the learned Single Judge that the
award of arbitrator proceeded on the manifestly
misconceived notion that a contractor is entitled to
claim overhead losses even in the absence of evidence
on the basis of Hudson's Formula.
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.15
106. In my view the impugned award rendered by the
arbitral tribunal allowing the claim for overhead merely
on the basis of the Hudson Formula and not based on
any evidence is contrary to the principles of law laid
down by this court in case of Edifice Developers and
Project Engineers Ltd. (supra) and shows patent
illegality and is in conflict with public policy.”
No fault can thus be found in the award passed by the
learned Arbitrator in rejecting the claim of the petitioner for loss of
profits and over heads on account of prolongation of contract. The point
is answered accordingly.
6. Rejection of Claim viz-a-viz Terms of Contract:-
6(i) There is yet another reason for rejecting the claim of loss
of profits and over heads on account of prolongation of contract. The
terms of the contract are significant in the instant case. The contract
which has been executed by both the parties and in terms of Clause-33
of which, learned Arbitrator was appointed, also contains Clause-36.
This being relevant for purpose of adjudication of the present petition, is
being reproduced hereinafter:-
“36.1If at any time after acceptance of the tender the
Employer decides to abandon or reduce the scope of the
works for reason whatsoever and hence does not
require the whole or any part of the works to be carried
out, the Engineer-in-Charge shall give notice in writing
to that effect to the contractor, and the Contractor shall
have no claim to any payment of compensation or
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.16
otherwise whatsoever, on account of any profit or
advantage which he might have derived from th
execution of the works in full but which he could not
derive in consequence of the fore-closure of the whole
or part of the works.
The Contractor shall be paid at contract rates for
full amount of the works executed at site and, in
addition,a reasonable amount as certified by the
Engineer-in-Charge for the items hereunder mentioned
which could not be utilized on the works t the full extent
because of the foreclosure:
(a) Any expenditure incurred on preliminary works,
e.g. temporary access roads, temporary labour, huts,
staff quarters and site office; storage accommodation,
workshop, installation and dismantling of Construction
Equipment (batching plant, crushing plant) and water
storage tanks.
(b) i) The Employer shall have the option to take over
Contractor’s materials or any prt thereof, either brought
to site or of which the Contractor is legally bound to
accept delivery from suppliers (for incorporation in or
incidental to the Work), provided, however, the
Employer shall be bound to take over the material or
such portions thereof as the Contractor does not desire
to retain. The cost shall, however, taken into account
purchase price, cost of transportation and deterioration
or damage which may have been caused to materials
whilst in the custody of the Contractor.
ii ) For Contractor’s materials not retained by the
Employer, reasonable cost of transporting such material
from Site to Contractor’s permanent stores or to his
other Works, whichever is less. If materials are not
transported to either of the said places, no cost of
transportation shall be payable.
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.17
(c) If any materials issued by the Employer are
rendered surplus, the same except normal wastage for
the materials used in the works shall be returned by the
Contractor to the Employer.
(d) Reasonable compensation for transfer of T&P from
Site to Contractor’s permanent stores or to his other
works whichever is less. If T&P are not transported to
either of the said places, no cost of outward
transportation shall be payable.
36.2 The Contractor shall, if required by the Engineer-
in-charge, furnish to him books of accounts, wage
books, time sheets and other relevant documents as may
be necessary to enable him to certify the reasonable
amount payable under this condition.”
6(ii) The above Clause empowers the respondent to abandon or
reduce the scope of the work for any reason whatsoever. The contractor
will have no claim, in terms of this Clause, to any compensation on
account of any payment of compensation, on account of any profit or
advantage which he might have derived from the execution of the works
in full, but which he could not derive on account of fore-closure either
of part or whole works.
Clause 36.1, when read in its entirety, though provides that
in case of fore-closure of the contract, the contractor has to be paid at the
contract rates for full amount of the works executed at the site and in
addition, reasonable amount certified by the Engineer-in-Charge for the
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.18
items, which could not be utilized on the works to full extent because of
the fore-closure. The items mentioned in this Clause are in respect of
preliminary works, i.e. temporary access roads, temporary labour huts,
staff quarters, site office, storage accommodation workshop, installation
and dismantling of construction equipment and water storage tanks etc.
Clause also provides for materials in similar way.
6(iii) Thus, in terms of Clause 36.1 of the agreement duly
executed by the parties, claimant cannot have any claim for payment of
compensation for any profit which he couldn’t derive because of
foreclosure of the work. Claimant is though entitled to amount for
works actually carried out at contract rates and for items mentioned
therein lying unused and expenditure incurred over them as provided in
contract. However, in the instant case, there is no evidence whatsoever
available on record that the above said works were actually carried out,
which are yet to be paid for. Therefore, claim for loss of profit and over
heads on account of prolongation of contract could not be allowed, in
view of specific provision of contract agreement.
6(iv) Reference in this regard can also be made to (2010) 13
SCC 377, titled as Oil and Natural Gas Corporation v. Wig Brothers
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.19
Builders and Engineers Private Ltd., in which, Hon’ble Apex Court has
held as under:-
“4. It is now well settled that a court, while
considering a challenge to an award under sections 30
and 33 of Arbitration Act, 1940, does not examine the
award, as an appellate court. It will not reappreciate
the material on record. An award is not open to
challenge on the ground that the arbitrator had reached
a wrong conclusion or had failed to appreciate some facts.
But if there is an error apparent on the face of the award or
if there is misconduct on the part of the arbitrator or legal
misconduct in conducting the proceedings or in making the
award, the court will interfere with the award. Keeping the
said principles in view, we will consider the challenge.
6.The arbitrator has observed that there is no provision
in the contract by which the contractor can be estopped from
raising a dispute in regard to the said claim. But clause 5A
of the contract pertains to extension of time for completion
of work and specifically bars any claim for damages. The
said clause is extracted below :
"In the event of delay by the Engineer-in-Charge
to hand over to the contractor possession of
land/lands necessary for the execution of the
work or to give the necessary notice to the
contractor to commence work or to provide the
necessary drawing or instructions or to do any
act or thing which has the effect of delaying the
execution of the work, then notwithstanding
anything contained in the contract or alter the
character thereof or entitle the contractor to any
damages or compensation thereof but in all such
cases the Engineer-in-Charge may grant such
extension or extensions of the completion date as
may be deemed fair and reasonable by the
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.20
Engineer-in Charge and such decision shall be
final and binding."
7. In view of the above, in the event of the work being
delayed for whatsoever reason, that is even delay which is
attributable to ONGC, the contractor will only be entitled to
extension of time for completion of work but will not be
entitled to any compensation or damages. The arbitrator
exceeded his jurisdiction in ignoring the said express bar
contained in the contract and in awarding the compensation
of Rs.9.5 lakhs. This aspect is covered by several decisions
of this Court. We may refer to some of them.
8.In Associated Engineering Co. v. Government of A.P. -
1991 (4) SCC 93, this Court observed :
"24. The arbitrator cannot act arbitrarily,
irrationally, capriciously or independently of the
contract. His sole function is to arbitrate in terms
of the contract. He has no power apart from what
the parties have given him under the contract. If
he has travelled outside the bounds of the
contract, he has acted without jurisdiction. ..."
9.In Rajasthan State Mines & Minerals Ltd. v. Eastern
Engineering Enterprises – this Court held: (SCC pp. 300 &
310, paras 22-23 & 44)
"22…..The rates agreed were firm, fixed and
binding irrespective of any fall or rise in the cost
of the work covered by the contract or for any
other reason or any ground whatsoever. It is
specifically agreed that the contractor will not be
entitled or justified in raising any claim or dispute
because of increase in cost of expenses on any
ground whatsoever. By ignoring the said terms,
the arbitrator has travelled beyond his
jurisdiction as his existence depends upon the
agreement and his function is to act within the
limits of the said agreement. This deliberate
departure from the contract amounts not only to
manifest disregard of the authority or misconduct
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.21
on his part but it may be tantamount to mala fide
action.
23.It is settled law that the arbitrator is the
creature of the contract between the parties and
hence if he ignores the specific terms of the
contract, it would be a question of jurisdictional
error which could be corrected by the court and
for that limited purpose, agreement is required to
be considered. ....
44.. (h)……..he cannot award an amount which is
ruled out or prohibited by the terms of the
agreement."
10.In Ramnath International Construction (P) ltd. v.
Union of India, a similar issue was considered. This Court
held that clause 11(C) of the General Conditions of
Contract (similar to clause 5A under consideration in this
case) was a clear bar to any claim for compensation for
delays, in respect of which extensions had been sought and
obtained. This Court further held that such a clause
amounts to a specific consent by the contractor to accept
extension of time alone in satisfaction of claims for delay
and not to claim any compensation; and that in view of such
a bar contained in the contract in regard to award of
damages on account of delay, if an arbitrator awards
compensation, he would be exceeding his jurisdiction.
11. In view of the above, the award of the arbitrator in
violation of the bar contained in the contract has to be held
as one beyond his jurisdiction requiring interference.
Consequently, this appeal is allowed in part, as follows :
(a) The judgment of the High Court and that of the civil
court making the award the rule of the court is partly
set aside in so far as it relates to the award of Rs.9.5
lakhs under claim No.(1) and the award of interest
thereon.
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.22
(b) The judgment of the civil court as affirmed by the
High Court in regard to other items of the award is not
disturbed.”
In (2007) 4 SCC 697, titled as Food Corporation of India
v. Chandu Construction and Another, the Hon’ble Apex Court, held
that the arbitrator being a creature of the agreement between the parties,
has to operate within the four corners of the agreement and if he ignores
the specific terms of the contract, it would be a question of jurisdictional
error on the face of the award, falling within the ambit of legal
misconduct which could be corrected by the Court. Arbitrator derives
his authority from the contract and if he acts in disregard of the contract,
he acts without jurisdiction. A deliberate departure from contract
amounts to not only manifest disregard of his authority or a misconduct
on his part, but it may tantamount to a mala fide action.
It is apt to refer to (2015) 3 SCC 49, titled as Associate
Builders v. Delhi Development Authority:-
“31.The third juristic principle is that a decision which is
perverse or so irrational that no reasonable person would
have arrived at the same is important and requires some
degree of explanation. It is settled law that where:-
(i)a finding is based on no evidence, or
(ii) an Arbitral tribunal takes into account
something irrelevant to the decision which it arrives
at; or
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.23
(iii) ignores vital evidence in arriving at its
decision, such decision would necessarily be
perverse.”
In the instant case, learned Arbitrator justly turned down
the claim in view of clear stipulation contained in Clause 36 of the
contract agreement.
7. In view of the above discussion, looking from any angle,
this Court does not find any infirmity in the impugned award passed by
the learned Arbitrator. Hence, the present petition being devoid of any
merit, is dismissed. Pending application(s), if any, also stand disposed
of.
(Jyotsna Rewal Dua)
Judge
23
rd
August, 2019
(reena)
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
High Court of H.P.24
::: Downloaded on - 29/10/2022 16:57:33 :::CIS
Legal Notes
Add a Note....