0  08 Mar, 2019
Listen in 1:33 mins | Read in 29:00 mins
EN
HI

Tejpal Singh And 5 Others Vs. State Of U.P. And 3 Others

  Allahabad High Court WRIT C No. 7218 of 2019
Link copied!

Case Background

Heard Sri Shri Krishna Mishra, learned counsel for the petitioners and Sri Suresh Singh, learned Additional Chief Standing Counsel appearing for the State respondents.

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

AFR

Court No. ­ 3

Case :­ WRIT ­ C No. ­ 7218 of 2019

Petitioner :­ Tejpal Singh And 5 Others

Respondent :­ State Of U.P. And 3 Others

Counsel for Petitioner :­ Shri Krishna Mishra

Counsel for Respondent :­ C.S.C.,Kaushalendra Nath Singh

Hon'ble Pankaj Kumar Jaiswal,J.

Hon'ble Dr. Yogendra Kumar Srivastava,J.

(Per : Dr. Yogendra Kumar Srivastava,J.)

1.Heard Sri Shri Krishna Mishra, learned counsel for the

petitioners   and   Sri   Suresh   Singh,   learned   Additional   Chief

Standing Counsel appearing for the State respondents.

2.By means of the present writ petition, a direction has been

sought to respondent no.4/Additional District Magistrate (Land

Revenue) Noida, Gautam Budh Nagar to take a decision on the

application   of   the   petitioners   dated   26.09.2014   filed   under

Section   28A   of   the   Land   Acquisition   Act,   1894

1

  within   a

stipulated period and a further direction to the respondents to

redetermine the compensation awarded to the petitioners at the

rate of Rs.297/sq. yard i.e. the rate determined in terms of the

judgment and order passed in First Appeal No.326 of 2009.

3.The brief facts of the case are set out herein below.

4.Pursuant to a notification dated 22.03.1983 issued under

Section 4(1) of the Act, 1894 an award was made on 09.05.1985

by the Special Land Acquisition Officer, Ghaziabad in respect of

certain land parcels situate in Village Chhalera Khadar, Pargana

and   Tehsil   Dadri,   District   Ghaziabad   (now   part   of   District

Gautam Budh Nagar).

1The Act, 1894

Neutral Citation No. - 2019:AHC:219310-DB

2

5.It is submitted by the learned counsel for the petitioners

that against the award dated 09.05.1985 the predecessors in

interest of the petitioners did not file any application under

Section 18 of the Act, 1894. However, against the award certain

other persons filed applications giving rise to land acquisition

references which were decided by the District Judge, Gautam

Budh Nagar vide order dated 31.01.2003, and the compensation

amount was redetermined.

6.Against the the judgment and order dated 31.01.2003

passed by the District Judge, Gautam Budh Nagar in the land

acquisition references, a First Appeal No.326 of 2009 was filed

before this Court which came to be decided vide judgment dated

24.07.2014   and   the   compensation   amount   was   again

redetermined. Claiming the benefit of the redetermination of

compensation amount in terms of the judgment and order dated

24.07.2014   passed   in   First   Appeal   No.326   of   2009,   an

application under Section 28A was filed by the petitioners on

26.09.2014   making   a   prayer   for   granting   them   benefit   of

redetermination of compensation amount in terms of the order

passed in First Appeal No.326 of 2009. The present writ petition

has been filed seeking a direction to respondent no.4 to take a

decision   on   the   application   dated   26.09.2014   filed   by   the

petitioners under Section 28A and for redetermination of the

compensation awarded to the petitioners and payment of the

same on the basis of rates redetermined in terms of the judgment

and order passed in First Appeal No.326 of 2009 decided on

24.07.2014.

7.Learned   counsel   for   the   petitioners   submits   that   the

application   under   Section   28A   of   the   Act,   1894   filed   on

26.09.2014, was within the three months period of limitation

from the date of the judgment/order dated 24.07.2014 passed in

3

First Appeal No.326 of 2009, and accordingly, the respondent

no.4 be directed to decide the pending application under Section

28A. In this regard, reliance has been placed upon a judgment of

this Court in  First Appeal No.522 of 2009 (Pradeep Kumar Vs.

State   of   UP   &   Anr.)  and   connected   appeals   decided   on

21.04.2016 to contend that the Court as referred under Section

28A would necessarily include the first appellate court as the

appeal   under   Section   54   is   a   continuation   of   the   original

proceedings.

8.Per   contra,  learned   Additional   Chief   Standing   Counsel

submits that the three month period of limitation provided to file

an application under Section 28A of the Act, 1894 is to be

reckoned from the date of the award made by Reference Court,

and in this case the Reference Court having made the award on

31.01.2003,   the   application   dated   26.09.2014   filed   by   the

petitioners was highly time barred, and no direction as sought by

the petitioners could be issued.

9.In order to appreciate the controversy, we may refer to the

relevant statutory provision as contained under Section 28­A of

the Act, 1894.

“28A. Re­determination of the amount of compensation on

the basis of the award of the Court.—

(1) Where in an award under this Part, the Court allows to the

applicant any amount of compensation in excess of the amount

awarded by the Collector under section 11, the persons interested

in all the other land covered by the same notification under

section 4, sub­section (1) and who are also aggrieved by the

award of the Collector may, notwithstanding that they had not

made an application to the Collector under section 18, by written

application to the Collector within three months from the date of

the award of the Court require that the amount of compensation

payable to them may be re­determined on the basis of the amount

of   compensation   awarded   by   the   Court:   Provided   that   in

computing   the   period   of   three   months   within   which   an

application to the Collector shall be made under this sub­section,

the   day   on   which   the   award   was   pronounced   and   the   time

requisite for obtaining a copy of the award shall be excluded.

4

(2) The Collector shall, on receipt of an application under sub­

section (1), conduct an inquiry after giving notice to all the

persons interested and giving them a reasonable opportunity of

being heard, and make an award determining the amount of

compensation payable to the applicants.

(3) Any person who has not accepted the award under sub­section

(2) may, by written application to the Collector, require that the

matter be referred by the Collector for the determination of the

Court and the provisions of sections 18 to 28 shall, so far as may

be, apply to such reference as they apply to a reference under

section 18.”

10.The core question which arises in the present case is as to

whether the three months limitation for filing the application

under Section 28A of the Act, 1894 is to be reckoned from the

date of the award made by the Reference Court or the date of

the judgment of the High Court in the first appeal.

11.A plain reading of Section 28A would show that where in

an award under Part III, the Court allows to the applicant any

amount of compensation in excess of the amount awarded by the

Collector under Section 11, the persons interested in all the

other land covered by the same notification under section 4, sub­

section (1) and who are also aggrieved by the award of the

Collector   may,   notwithstanding   that   they   had   not   made   an

application   to   the   Collector   under   section   18,   by   written

application to the Collector within three months from the date of

the award of the Court require that the amount of compensation

payable to them may be redetermined on the basis of the amount

of compensation awarded by the court.

12.The expression “Court” has been defined under Section

3(d) of the Act, 1894 to mean “a principal Civil Court of original

jurisdiction”.

13.It is thus clear that the redetermination can be claimed

only in reference to an award passed by the “Court” under Part

III of the Act, 1894 which comprises Sections 18 to 28A. The

5

expression “Court” which has been referred under Section 28A is

the Court as defined under Section 3(d) to mean “a principal

Civil Court of original jurisdiction”. It clearly goes to show that

the award which is being referred to under Section 28A(1) is the

award made by Reference Court alone. The application under

Section   28A   thus   cannot   be   filed   for   redetermination   of

compensation on the basis of the award as made by the High

Court in the first appeal.

14.In this regard we may refer to the judgment in the case of

Babua Ram & Ors. Vs. State of UP & Anr.

2

, the relevant portion

of which is being extracted below:­

“19. The next question is as to when the period of limitation of

three months begins to run under Section 28­A and whether

successive awards made by civil court at different times in respect

of the land covered by the same notification furnish separate

causes of action for making applications under Section 28­A. Let

us consider the meaning of the words “an award under this part”

referred to in Section 28­A(1) which is Part III of the Act. The

heading   to   that   part   begins   by   reference   to   court   and   its

procedure. The ‘court’ means a principal civil court of original

jurisdiction or a special judicial officer appointed to perform the

functions of the court under the Act as becomes clear as is noticed

already. What are the matters to be considered in determining the

compensation on a reference made to it under Section 18, is

detailed   in   Section   23   while   matters   to   be   neglected   in

determining such compensation are indicated in Section 24. By

operation   of   sub­section   (2)   of   Section   26,   the   award   made

determining the amount of compensation shall be deemed to be a

decree while the statement of the grounds of every such award is

deemed to be the judgment, for the purpose of Code of Civil

Procedure. The above perspectives from Part III make it clear that

the award of the court is that of the civil court of original

jurisdiction in that part. It is a decree for the purpose of an appeal

under   Section   54   which   falls   in   Part   VIII   of   the   Act

(Miscellaneous). The decree as defined in Section 2(2) CPC is the

decree   of   the   High   Court,   which   shall   be   appealable   to   the

Supreme Court under Articles 132, 133 and 136 read with Order

45 CPC. Hence, the award of the court referred to in sub­section

(1) of Section 28­A is only the award of the civil court of original

jurisdiction or of judicial officer performing the functions of such

court under the Act on reference received by it under Section 18

and an award and decree pronounced under Section 26 of the Act.

2(1995) 2 SCC 689

6

Since, the judgment and decree of the High Court under Section

54 or of this Court do not come in Part III of the Act, they stand

excluded   from   an   award   envisaged   under   sub­section   (1)   of

Section   28­A.   The   aggrieved   interested   person,   therefore,   is

entitled to the right and remedy of making an application under

Section 28­A for redetermination of compensation for his acquired

land only on the basis of the award of the civil court or judicial

officer which is a judgment and decree under Section 26 when

such award grants compensation in excess of the amount awarded

by the Collector under Section 11. When such an application is

made in writing by the aggrieved person, notwithstanding the fact

of his having received compensation under Section 31 without

protest and of not availing the right and remedy of the reference

under Section 18, the redetermination of the compensation under

Section 28­A(1) is required to be done.”

15.The aforementioned judgment was followed in the case of

Union of India & Ors. Vs. Karnail Singh & Ors.

3

, and it was

held   that   the   limitation   of   three   months   for   making   an

application   for   redetermination   of   compensation   must   be

computed from the date of earliest award made by the Civil

Court and not the judgment of the Appellate Court. The relevant

observations in this regard are as follows:­

“5. Thus, it would be clear that cause of action for making an

application under Section 28­A would arise when an award has

been made by the civil court, on a reference under Section 18,

enhancing the compensation over and above the amount awarded

by the Collector in his award under Section 11 and the earliest of

the successive awards would furnish the starting period of the

limitation of three months as provided in the proviso to Section

28­A(1). It is seen that the earliest award was made on 31­7­

1979 by which date the Amendment Act had not come into force.

The Land Acquisition (Amendment) Act, 1984 (68 of 1984) has

given   prospective   operation   to   Section   28­A   from   24­9­1984.

Therefore, it does not furnish any right to the claimants to make

any application after the Act has come into force. The latter

award dated 15­3­1990 does not give any fresh right or cause of

action to file an application under Section 28­A(1). The question

then is whether the claimants are entitled to make an application

after the appeal was allowed by this Court from appeals arising

from one of the references. This question also was considered in

the same judgment and it was held that it does not furnish any

cause of action. This was also the view of another three­Judge

Bench of this Court in Scheduled Castes Cooperative Land Owning

Society v. Union of India (1991) 1 SCC 174. Therefore, we are of

3(1995) 2 SCC 728

7

the   firm   view   that   the   judgment   and   order   of   this   Court

enhancing the compensation on 24­8­1987 does not furnish any

cause of action to make the application under Section 28­A.”

16.We   may   take   note   of   the   fact   that   in   a   subsequent

judgment a three­Judge Bench of the Supreme Court in Union of

India & Anr. Vs. Pradeep Kumari & Ors.

4

 disagreed with the

view   expressed   in  Babua   Ram  (supra)   and  Karnail   Singh

(supra) and it was held that the benefit of redetermination of the

amount of compensation under Section 28A can be availed of on

the basis of any of the awards that had been made by the Court.

The relevant observations made in the judgment are as follows:­

“12. We are, therefore, unable to agree with the view expressed in

Babua Ram [(1995) 2 SCC 689] and Karnail Singh [(1995) 2

SCC   728]   that   application   under   Section   28­A   for

redetermination of compensation can only be made on the basis of

the first award that is made after the coming into force of Section

28­A. In our opinion, the benefit of redetermination of amount of

compensation under Section 28­A can be availed of on the basis of

any one of the awards that has been made by the court after the

coming into force of Section 28­A provided the applicant seeking

such benefit makes the application under Section 28­A within the

prescribed period of three months from the making of the award

on the basis of which redetermination is sought...”

17.In the aforementioned judgment the Court also laid down

the conditions which were required for filing an application

under Section 28A. The observations made in the judgment are

being extracted below:­

“10.   ...The   object   underlying   Section   28­A   would   be   better

achieved by giving the expression “an award” in Section 28­A its

natural meaning as meaning the award that is made by the court

in Part III of the Act after the coming into force of Section 28­A. If

the said expression in Section 28­A(1) is thus construed, a person

would   be   able   to   seek   redetermination   of   the   amount   of

compensation payable to him provided the following conditions

are satisfied:

(i) An award has been made by the court under Part III

after the coming into force of Section 28­A;

(ii) By the said award the amount of compensation in

excess   of   the   amount   awarded   by   the   Collector   under

4(1995) 2 SCC 736

8

Section   11   has   been   allowed   to   the   applicant   in   that

reference;

(iii) The person moving the application under Section 28­A

is interested in other land covered by the same notification

under Section 4(1) to which the said award relates;

(iv) The person moving the application did not make an

application to the Collector under Section 18;

(v) The application is moved within three months from the

date   of   the   award   on   the   basis   of   which   the

redetermination of amount of compensation is sought; and

(vi) Only one application can be moved under Section 28­A

for redetermination of compensation by an applicant.”

18.In Jose Antonio Cruz Dos R. Rodriguese & another. Vs.

Land Acquisition Collector & another

5

 a three­Judge Bench of

the Supreme Court held that the limitation of three months for

making application for redetermination of compensation must be

computed from the date of award of Reference Court on the

basis of which redetermination is sought and not from the order

of the Appellate Court dealing with the appeal against the award

of   the   Reference   Court.   We   may   refer   to   the   relevant

observations made in this regard:­

“2. The question which arises for determination in these two

appeals is whether the period of three months prescribed for

making  an application for  redetermination of the amount of

compensation under Section 28­A of the Land Acquisition Act,

1894  (hereinafter   called  'the  Act')   begins  to   run  against  the

applicant from the date of the award under Section 18 of the Act

or even from the date of the decision of the appeal, if any,

preferred against the award...       

3.  Before examining the decisions of this Court on which the High

Court has placed reliance, we deem it appropriate to first examine

the plain language of Section 28­A extracted earlier. Section 28­A

was inserted as the last section in Part III entitled “Reference to

Court and Procedure thereon” by Act 68 of 1984. Part III begins

with Section 18 which provides that if an interested person does

not accept the award made by the Collector under Section 11 of

the Act, he may, by a written application to the Collector, require

that the matter be referred for determination of the court. Section

2(d) defines the expression ‘Court’ to mean the principal civil

court of original jurisdiction unless a Special Judicial Officer has

been appointed. Therefore, the court referred to under Section 18

5(1996) 6 SCC 746

9

can only mean the principal civil court of original jurisdiction.

Section   23   then   sets   out   the   matters   to   be   taken   into

consideration in determining the compensation to be awarded for

the acquired land, and Section 24 indicates the matters to be

omitted from consideration. Section 26 provides that the award

shall be in writing signed by the Judge which shall be deemed to

be a decree within the meaning of clauses (2) and (9) of Section 2

of the Civil Procedure Code, 1908. Section 27 provides for costs to

be awarded and Section 28 provides for payment of interest on

excess compensation. We then come to Section 28­A. The first part

of the section begins with the words “Where in an award under

this   part,   Court   allows   to   the   applicant   any   amount   of

compensation in excess of the amount awarded by the Collector

under Section 11” which clearly indicate that the legislature was

talking of an award made under the provisions of Part III, i.e., an

award under Section 11 and therefore, in that context, reference

to ‘Court’ can only mean the court to which a reference is made by

the Collector under Section 18. This position is further clarified

when the section refers to compensation awarded in excess of the

amount awarded under Section 11 of the Act. The second part of

the section then addresses “the persons interested in all the other

land   covered   by   the   same   notification   …   and   who   are   also

aggrieved by the award” and permits them to make a written

application to the Collector “within three months from the date of

the award of the Court” requiring him to redetermine the amount

of compensation on the basis of the amount awarded by the

Court,   notwithstanding   the   fact   that   they   had   not   sought   a

reference under Section 18 of the Act. Thus, the newly added

section seeks to give the same benefit, which a person who had

sought a reference and had secured the Court's award for a higher

amount of compensation had received, to those who had, on

account   of   ignorance   or   financial   constraints,   not   sought   a

reference under Section 18. In the latter part of the section also,

reference is to the award under Section 11 and later, to the award

of the Reference Court under Section 18 of the Act. Therefore, the

court referred to therein is again the court referred to in Section

2(d)   of   the   Act,   i.e.,   the   principal   civil   court   of   original

jurisdiction.   The   plain   language   of   Section   28­A,   therefore,

prescribes the three months' period of limitation to be reckoned

from the date of the award by the Court disposing of the reference

under Section 18, and not the appellate court dealing with the

appeal against the award of the Reference Court.”

19.The contention that Section 28A of the Act, 1894 would

also apply to a judgment made by the High Court under Section

54 was repelled in the case of Union of India Vs. Bant Ram

6

and it was reiterated that redetermination of compensation can

6(1996) 4 SCC 537

10

be claimed only on the basis of an award under Section 18 and

not the judgment passed by the High Court under Section 54,

and it was held as follows:­

“4. ...the learned Senior Counsel for the respondent has contended

that Section 28­A would apply not only when an award is made

by the court under Section 26 but also when judgment is made by

the High Court under Section 54 of the Act. We find no force in

this   contention.   Section   28­A   itself   specifically   refers   to

applicability of Chapter III; in other words, Chapter III would be

applicable to a reference made under Section 18 to the court. The

marginal note indicates redetermination of the compensation on

the basis of the award of the court. Section 3(d) defines ‘court’ to

mean a principal civil court of original jurisdiction or a Court of

Special Judicial Officer. Sub­section (1) of Section 28­A envisages

“allowing   applications”,   i.e.,   reference   application   filed   under

Section 18 in Part III. Moreover Section 54 falls in Chapter VIII of

the   Act.   Therefore,   judgment   and   decree   of   the   appellate

court/High Court does not encompass the award of the court

referred to in Section 28­A. The controversy is no longer res

integra. Babua Ram v. State of U.P. [(1995) 2 SCC 689] and

hosts of other decisions following that, cover the field. Therefore,

the   conclusion   is   inevitable   that   the   application   for

redetermination of the compensation under Section 28­A would

not lie after the judgment of the High Court under Section 54 of

the Act.”

20.The view that Section 28A does not apply to an order made

by   the   High   Court   and   that   the   claimant   could   seek

redetermination of the compensation only on the basis of the

award of the Reference Court and not the judgment of the High

Court was reiterated in Bhagti (Smt.) (deceased) Vs. State of

Haryana

7

.   It   was   further   held   that   an   application   for

redetermination of compensation that was filed within three

months from the date of the judgment of the High Court but

beyond   the   limitation   from   the   date   of   the   award   of   the

Reference Court, was not maintainable. The observations made

in this regard in the aforesaid judgment are being extracted

below:­

“6. Thus only those claimants who had failed to apply for a

reference under Section 18 of the Act are conferred with the right

7(1997) 4 SCC 473

11

to apply for redetermination under Section 28­A(1). But all those

who had not only sought a reference under Section 18 but had

also filed an appeal in the High Court against the award made by

the Reference Court are not entitled to avail of the remedy under

Section 28­A. Equally, the right and remedy of redetermination

would be available only when the Reference Court under Section

18 has enhanced the compensation in an award and decree under

Section 26. Within three months from the date of the Reference

Court excluding the time taken under the proviso, the applicant

whose land was acquired under the same notification but who

failed to avail of the remedy under Section 18, would be entitled

to avail of the right and remedy under Section 28­A. The order

and judgment of the High Court does not give such right. Thus,

this Court held that Section 28­A does not apply to an order made

by the High Court for redetermination of the compensation. Thus,

we hold that the question of reference to the Constitution Bench

does   not   arise.   The   claimants   are   not   entitled   to   make   an

application for redetermination of compensation under Section

28­A(1)   after   the   judgment   of   the   High   Court;   nor   are   the

claimants entitled to avail of that award which is more beneficial

to the claimants, i.e., the High Court judgment.”

21.The view taken in the judgments of Bant Ram (supra) and

Bhagti (supra) has been followed in a subsequent judgment in

State of Orissa & Ors. Vs. Chitrasen Bhoi

8

, and it was stated as

follows:­

“11. In Bhagti v. State of Haryana [(1997) 4 SCC 473] this

Court   held   that   a   claimant   can   seek   redetermination   of

compensation on the basis of the award of the Reference Court

and not the judgment of the High Court and further held that

only those claimants who had failed to apply for a reference under

Section 18 of the Act are conferred with the right to apply for

redetermination under Section 28­A(1) of the Act. The same view

has been reiterated in Union of India v. Bant Ram [(1996) 4 SCC

537].”

22.We may also refer to the judgments in Smt. Kamla Tomar

Vs. State of UP & 2 Ors.

9

 and Dheer Singh & 3 Ors. Vs. State of

UP & 3 Ors.

10

, wherein Coordinate Division Benches of this

Court have taken the same view.

23.The aforementioned proposition of law that an application

under   Section   28A   can   be   made   only   on   the   basis   of   the

8(2009) 17 SCC 74

92017 (3) ADJ 659

102017 (3) ADJ 545

12

judgment made by the Reference Court was thereafter reiterated

in  Bharatsing & Ors. Vs. State of Maharashtra and Ors.

11

following the judgments in the case of Pradeep Kumari (supra)

and  Jose Antonio Cruz (supra).

24.The precise question as to whether an application under

Section   28A   of   the   Act,   1894   for   redetermination   of

compensation can be filed within the period of three months

from the date of judgment of the High Court or the Supreme

Court passed in appeal under Section 54 of the Act, 1894 fell for

consideration in a recent judgment in the case of Ramsingbhai

(Ramsangbhai) Jerambhai Vs. State of Gujrat & Anr.

12

, and it

was held as follows:­

“1. ...Whether an application under Section 28A of the Land

Acquisition Act, 1894 (for short “the Act”) for redetermination

of the compensation can be filed within a period of 3 months

from the date of judgment of the High Court or Supreme Court

passed in appeal under Section 54 of the Act is the question that

arises for consideration in this case.

         2.  Section 28­A(1) of the Act reads as follows:

“28­A.   Redetermination   of   the   amount   of

compensation on the basis of the award of the Court.

—(1) Where in an award under this Part, the Court allows

to the applicant any amount of compensation in excess of

the amount awarded by the Collector under Section 11, the

persons interested in all the other land covered by the same

notification under Section 4 sub­section (1) and who are

also   aggrieved   by   the   award   of   the   Collector   may,

notwithstanding that they had not made an application to

the Collector under Section 18, by written application to

the Collector  within three months from the date of the

award   of   the   Court  require   that   the   amount   of

compensation payable to them may be redetermined on the

basis of the amount of compensation awarded by the Court:

Provided that in computing the period of three months

within which an application to the Collector shall be made

under this sub­section, the day on which the award was

pronounced and the time requisite for obtaining a copy of

the award shall be excluded.”

(emphasis supplied)

11(2018) 11 SCC 92

12(2018) 16 SCC 445

13

3. It is clear from the opening words of the provision that the

redetermination under Section 28­A is available only in respect of

an “award” passed by the “court” under Part III of the Act,

comprising Sections 18 to 28­A (both inclusive). The “Court”

referred to in Section 28­A of the Act is the Court as defined under

Section 3(d) to mean “… a Principal Civil Court of Original

Jurisdiction …”. Thus, the judgment of the appellate court is not

within the purview of Section 28­A. It is also to be noted that the

appellate courts under Section 54 are under Part VIII of the Act

whereas   the  redetermination  is  only in  respect  of  the  award

passed by the Reference Court under Part III of the Act. [See Jose

Antonio Cruz Dos R. Rodriguese v. LAO [(1996) 6 SCC 746]. In

its   recent   judgment   in   Bharatsing   v.   State   of   Maharashtra

[(2018) 11 SCC 92 : (2018) 5 SCC (Civ) 44], this Court has

surveyed   the   decisions   on   this   issue   and   reiterated   the   legal

principle.

4. What the appellant seeks is redetermination of compensation

under the Act in terms of the judgment in Ramsingbhai v. State of

Gujarat [2014 SCC OnLine Guj 5840 : 2015 AIR CC 1046] of the

High Court passed under Section 54 of the Act. In view of the

settled   legal   position   which   we   have   explained   above,   the

appellant is not entitled to such a relief; his entitlement, if any, is

only in terms of Section 28­A of the Act based on the award of the

Reference Court.”

25.In view of the aforesaid discussion, it is legally well settled

that the application under Section 28A for redetermination of

compensation is to be filed on the basis of the award passed by

the Reference Court and not on the basis of the judgment of the

High Court in first appeal.

26.In the case at hand, the application under Section 28A

having admittedly been filed on 26.09.2014 after the petitioners

came to know of the judgment dated 24.07.2014 passed in First

Appeal No.326 of 2009, the application was clearly much beyond

the prescribed period of three months from the date of the award

of the Reference Court i.e. 31.01.2003.

27.The question which now falls for consideration is as to

whether the application filed under Section 28A of the Act, 1894

can be entertained even if it is filed beyond the prescribed time

period of three months from the date of award of the Reference

14

Court.

28.The proviso to sub­section (1) of Section 28A only provides

for exclusion of the time requisite for obtaining a copy of the

award, and does not provide for extension of the time period on

any other ground. This issue was considered in the case of State

of A.P. Vs. Marri Venkaiah and Ors.

13

, and it was held that the

limitation of three months period would not commence from the

date of acquisition of knowledge of the award. The relevant

observations made in the judgment are as follows:­

“7. Plain language of the aforesaid section would only mean that

the period of limitation is three months from the date of the

award of the court. It is also provided that in computing the

period   of   three   months,   the   day   on   which   the   award   was

pronounced and the time requisite for obtaining the copy of the

award   is   to   be   excluded.   Therefore,   the   aforesaid   provision

crystallizes that application under Section 28­A is to be filed

within three months from the date of the award by the court by

only excluding the time requisite for obtaining the copy. Hence, it

is difficult to infer further exclusion of time on the ground of

acquisition of knowledge by the applicant.

x x x x x 

10. In our view, with regard to the first contention that Section

28­A   is   a   beneficial   provision,   there   cannot   be   any   dispute.

However,   the   advantage   of   the   benefit   which   is   conferred   is

required to be taken within the stipulated time. A landowner may

be poor or illiterate and because of that he might not have filed

reference application but that would not mean that he could be

negligent in not finding out whether other landowners have filed

such applications. Whosoever wants to take advantage of the

beneficial   legislation   has   to   be   vigilant   and   has   to   take

appropriate action within the prescribed time. He must at least be

vigilant in making efforts to find out whether the other landowner

has filed any reference application and if so, what is the result. If

that is not done then the law cannot help him. Admittedly, in the

present case, award enhancing the compensation was pronounced

by the civil court by order dated 29­11­1984 and applications

were filed on 27­11­1989 i.e. after a lapse of 5 years. In such

case, as the applicant was having an opportunity of knowing the

award and/or he was required to make efforts of knowing about

such proceedings, he must be presumed to have had knowledge of

the   award.   If   the   contention   of   the   learned   counsel   for   the

respondents   is   accepted,   it   will   create   total   vagueness   and

13(2003) 7 SCC 280

15

uncertainty as the landowners can claim that they have come to

know of the award after a long lapse of time and, therefore, the

application even though beyond time may be entertained. If such

applications are entertained, there may not be any finality to the

award and payment of compensation. Result may be that such

proceedings may adversely affect where land is acquired by the

Government for a project which is to be carried out by local

bodies.

11.   The  learned   counsel  for   the   respondents   relied   upon   the

decision of this Court in Raja Harish Chandra Raj Singh v. Dy.

Land Acquisition Officer [AIR 1961 SC 1500 : (1962) 1 SCR

676] which is approved by a three­Judge Bench in State of Punjab

v. Qaisar Jehan Begum [AIR 1963 SC 1604 : (1964) 1 SCR 971].

In that case, the Court interpreted the proviso to Section 18 of the

Act and held that clause (a) of the proviso was not applicable in

the said case because the person making the application was not

present or was not represented before the Collector at the time

when he made his award. The Court also held that notice from

the Collector under Section 12(2) was also not issued, therefore,

that part of clause (b) of the proviso would not be applicable. The

Court, therefore, referred to the second part of the proviso which

provides that such application can be made within six months

from the date of the Collector's award. In the context of the

scheme of Section 18 of the Act, the Court held that the award by

the Land Acquisition Officer is an offer of market price by the

State for purchase of the property. Hence, for the said offer,

knowledge, actual or constructive, of the party affected by the

award was an essential requirement of fair play and natural

justice. Therefore, the second part of the proviso must mean the

date when either the award was communicated to the party or

was known by him either actually or constructively.

12.   The   aforesaid   reasoning   would   not   be   applicable   for

interpretation of Section 28­A because there is no question of

issuing notice to such an applicant as he is not a party to the

reference proceeding before the court. The award passed by the

court cannot be termed as an offer for market price for purchase

of the land. There is no duty cast upon the court to issue notice to

the   landowners   who   have   not   initiated   proceedings   for

enhancement of compensation by filing reference applications;

maybe, that their lands are acquired by a common notification

issued under Section 4 of the Act. As against this, under Section

18 it is the duty of the Collector to issue notice either under

Section 12(2) of the Act at the time of passing of the award or in

any case the date to be pronounced before passing of the award

and  if  this  is   not  done  then  the  period  prescribed  for   filing

application under Section 18 is six months from the date of the

Collector's award.”

29.In the aforementioned case the judgments in Jose Antonio

16

Cruz Dos R. Rodriguese and another Vs. Land Acquisition

Collector and another, Union of India Vs. Mangatu Ram

14

 and

Tota Ram Vs. State of UP

15

  were relied upon and the earlier

judgments in Harish Chandra Raj Singh Vs. Land Acquisition

Officer

16

 and State of Punjab Vs. Qaisar Jehan Bagum

17

 were

distinguished.

30.The question with regard to applicability of Section 5 of

the Limitation Act, 1963

18

  to proceedings before the Collector

under Section 28A of the Act, 1894 was considered in the case of

Popat   Bahiru   Govardhane   and   Ors.   Vs.   Special   Land

Acquisition Officer and another

19

, and it was reiterated that the

Act, 1963 applied to courts and not to quasi judicial authorities.

It was also held that it was not permissible to extend the period

of limitation on equitable grounds if the statute does not permit

the same. The relevant observations made by the Supreme Court

in the aforementioned case are as follows:­

“8. The sole question for the consideration of the Court is whether

limitation for filing the application for redetermination of the

compensation under Section 28­A of the Act would commence

from the date of the award or from the date of knowledge of the

court's award on the basis of which such application is being

filed?

x x x x x

10.   The   issue   involved   herein   is   no   more   res   integra.   The

appellants' case before the High Court as well as before us has

been   that   the   limitation   would   commence   from   the   date   of

acquisition   of   knowledge   and   not   from   the   date   of   award.

Though, Shri Gaurav Agarwal, learned counsel for the appellants,

has fairly conceded that there is no occasion for this Court to

consider the application of the provisions of the Limitation Act,

1963   (hereinafter   called   “the   1963   Act”)   inasmuch   as   the

provisions of Section 5 of the said Act.

x x x x x

13. This Court in Union of India v. Mangatu Ram [(1997) 6 SCC

14(1997) 6 SCC 59

15(1997) 6 SCC 280

16AIR 1961 SC 1500

17AIR 1963 SC 1604

18The Act, 1963

19(2013) 10 SCC 765

17

59 : AIR 1997 SC 2704] and Tota Ram v. State of U.P. [(1997) 6

SCC 280] dealt with the issue involved herein and held that as the

Land Acquisition Collector is not a court and acts as a quasi­

judicial authority while making the award, the provisions of the

1963 Act would not apply and, therefore, the application under

Section 28­A of the Act, has to be filed within the period of

limitation as prescribed under Section 28­A of the Act. The said

provisions require that an application for redetermination is to be

filed within 3 months from the date of the award of the court. The

proviso further provides that the period of limitation is to be

calculated excluding the date on which the award is made and the

time requisite for obtaining the copy of the award.

14. In State of A.P. v. Marri Venkaiah [(2003) 7 SCC 280 : AIR

2003 SC 2949] , this Court reconsidered the aforesaid judgments

including the judgment in Harish Chandra Raj Singh [AIR 1961

SC 1500] and held that the statute provides limitation of 3

months from the date of award by the court excluding the time

required for obtaining the copy from the date of award. It has no

relevance so far as the date of acquisition of knowledge by the

applicant is concerned. In view of the express language of the

statute, the question of knowledge did not arise and, therefore,

the plea of the applicants that limitation of 3 months would begin

from the date of knowledge, was clearly unsustainable and could

not be accepted. The Court also rejected the contention of the

applicants that a beneficial legislation should be given a liberal

interpretation observing that whosoever wants to take advantage

of the beneficial legislation has to be vigilant and has to take

appropriate action within the time­limit prescribed under the

statute. Such an applicant must at least be vigilant in making

efforts to find out whether the other landowners have filed any

reference application and if so, what is the result thereof. If that is

not done then the law cannot help him. The ratio of the judgment

in Harish Chandra Raj Singh [AIR 1961 SC 1500] was held to be

non­applicable in case of Section 28­A of the Act.

“11. …In that case, the Court interpreted the proviso to

Section 18 of the Act and held that clause (a) of the proviso

was not applicable in the said case because the person

making   the   application   was   not   present   or   was   not

represented before the Collector at the time when he made

his   award.   The   Court   also   held   that   notice   from   the

Collector   under   Section   12(2)   was   also   not   issued,

therefore, that part of clause (b) of the proviso would not

be applicable. The Court, therefore, referred to the second

part of the proviso which provides that such application

can   be   made   within   six   months   from   the   date   of   the

Collector's award. In the context of the scheme of Section

18 of the Act, the Court held that the award by the Land

Acquisition Officer is an offer of market price by the State

for purchase of the property. Hence, for the said offer,

knowledge, actual or constructive, of the party affected by

18

the award was an essential requirement of fair play and

natural justice. Therefore, the second part of the proviso

must   mean   the   date   when   either   the   award   was

communicated to the party or was known by him either

actually or constructively.

12. The aforesaid reasoning would not be applicable for

interpretation of Section 28­A because there is no question

of issuing notice to such an applicant as he is not a party to

the reference proceeding before the court. The award passed

by the court cannot be termed as an offer for market price

for purchase of the land. There is no duty cast upon the

court   to   issue   notice   to   the   landowners   who   have   not

initiated proceedings for enhancement of compensation by

filing reference applications; maybe, that their lands are

acquired by a common notification issued under Section 4

of the Act. As against this, under Section 18 it is the duty of

the Collector to issue notice either under Section 12(2) of

the Act at the time of passing of the award or in any case

the date to be pronounced before passing of the award and

if this is not done then the period prescribed for filing

application under Section 18 is six months from the date of

the Collector's award.”

A similar view has been reiterated by this Court in Des Raj

[(2004) 7 SCC 753 : AIR 2004 SC 5003] and Chitrasen Bhoi

[(2009) 17 SCC 74].

x x x x x

16. It is a settled legal proposition that law of limitation may

harshly affect a particular party but it has to be applied with all

its rigour when the statute so prescribes. The court has no power

to extend the period of limitation on equitable grounds. The

statutory provision may cause hardship or inconvenience to a

particular party but the court has no choice but to enforce it

giving full effect to the same. The legal maxim dura lex sed lex

which means “the law is hard but it is the law”, stands attracted

in   such   a   situation.   It   has   consistently   been   held   that,

“inconvenience is not” a decisive factor to be considered while

interpreting a statute. “A result flowing from a statutory provision

is never an evil. A court has no power to ignore that provision to

relieve what it considers a distress resulting from its operation.”

(See Martin Burn Ltd. v. Corpn. of Calcutta [AIR 1966 SC 529],

AIR p. 535, para 14 and Rohitash Kumar v. Om Prakash Sharma

[(2012) 13 SCC 792 : AIR 2013 SC 30].”

31.In   the   present   case,   the   petitioners   in   terms   of   their

application dated 26.09.2014 have sought redetermination of

compensation under Section 28A of the Act, 1894 in terms of the

judgment of the High Court dated 24.07.2014 passed in First

19

Appeal No.326 of 2009.

32.In view of the legal position which we have discussed

above, the petitioners are not entitled to such a relief, inasmuch

as entitlement, if any, in terms of Section 28A is to be based on

the award of the Reference Court. Moreover, the Reference

Court having made the award on 31.01.2003, the application

dated 26.09.2014 filed by the petitioners under Section 28A is

much beyond the three months period provided for making the

application.

33.Accordingly, no direction as sought by the petitioners in

terms of the relief clause of the present writ petition can be

granted. The writ petition is devoid of merits and is dismissed.

Order Date :­ 8.3.2019

Shahroz

(Dr. Y.K. Srivastava,J.)    (Pankaj Kumar Jaiswal,J.)

Reference cases

Description

Legal Notes

Add a Note....