As per case facts, the Petitioner (Port Trust) issued a tender for restoration work, which the Respondent completed with significant delay. The Petitioner withheld liquidated damages, leading the Respondent to ...
2026:MHC:563Arb.O.P.(Com.Div.) No.119 of 2023
In the High Court of Judicature at Madras
Reserved on
03.2.2026
Delivered on:
09.2.2026
Coram :
The Honourable Mr.Justice N.ANAND VENKATESH
Arbitration O.P. (Com.Div.) No.119 of 2023
The Chairman,
Chennai Port Trust,
No.1, Rajaji Salai,
Chennai-1. ...Petitioner
Vs
Mr.A.Manicavassalou,
Proprietor, M/s.A.
Manicavassalou, registered
engineering contractor, No.10,
Vellavari Street, Mariya Tower,
II Floor, Carmel Convent,
Muthialpet, Puducherry-3. ...Respondent
PETITION under Section 34(2)(b) of the Arbitration and
Conciliation Act, 1996 praying to set aside the award dated
06.4.2022 passed by the Arbitral Tribunal.
For Petitioner : Mr.Haja Mohideen Gisthi,
Standing Counsel
For Respondent : Mr.D.Vivekanandan
1/29
https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
ORDER
This petition has been filed by the petitioner under Section 34
of the Arbitration and Conciliation Act, 1996 (for short, the Act)
against the award dated 06.4.2022 passed by the learned Arbitrator
to the extent the claims made by the respondent/claimant were
allowed.
2. Heard both.
3. The facts leading to filing of this petition are as follows:
(i) The petitioner issued a tender dated 24.2.2013 for
restoration of the damaged revetment structure at east of east quay
due to cyclones ‘Thane’ and ‘Nilam’. The respondent submitted his
tender and was declared as a successful bidder, pursuant to which,
the parties entered into an agreement on 03.10.2013. The work
involved as many as 11 kinds of work and the respondent took over
the site and commenced the work on 18.10.2013. As per the
agreement, the time for completion of work was 10 months from the
date of taking over the site and it was expected to be completed on
17.8.2014. However, the work was completed only on 24.9.2016
2/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
after extension of time was granted by the petitioner. Thus, there
was a delay of 768 days in completing the work.
(ii) The petitioner sought to recover the liquidated damages
from the respondent and withheld a sum of Rs.49,19,960/- towards
the same. Apart from that, the respondent also had other claims
against the petitioner. The trigger notice was issued and a petition
was filed before this Court in O.P.No.763 of 2018 by the respondent.
Pursuant to the order dated 06.12.2018 passed in the said original
petition, the learned Arbitrator was appointed by this Court.
(iii) In the claim statement filed before the learned Arbitrator,
the respondent/claimant made the following claims against the
petitioner:
“A. To repay/return the liquidated
damages to an extent of Rs.49,19,960/- (Rupees
Forty Nine Lakhs Nineteen Thousand Nine
Hundred and Sixty Only) wrongfully deducted
from the claimant together with 18% interest
per annum as mentioned in Annexure – A;
B. To return the Service Tax of a sum of
Rs.7,23,754/- (Rupees Seven Lakhs Twenty
Three Thousand Seven Hundred and Fifty Four
Only) deducted contrary to the agreement from
the claimant together with 18% interest per
3/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
annum as mentioned in Annexure – B;
C. To return a sum of Rs.2,18,836/-
(Rupees Two Lakhs Eighteen Thousand Eight
Hundred and Thirty Six Only) wrongly deducted
towards the room rent charges from the
claimant together with 18% interest per annum
as mentioned in Annexure – C;
D. To pay a sum of Rs.1,06,60,000/-
(Rupees One Crore Six Lakhs and Sixty
Thousand Only) towards the rental charges of
the machinery viz., Excavator Ex 220 and a
container for the extended period as mentioned
in Annexure – D;
E. To pay a sum of Rs.29,38,000/-
(Rupees Twenty Nine Lakhs and Thirty Eight
Thousand Only) towards the salaries paid to the
employees for the extended period as mentioned
in Annexure – E;
F. To pay a sum of Rs.36,48,147.40/-
(Rupees Thirty Six Lakhs Forty Eight Thousand
Hundred and Forty Seven and Forty Paise Only)
towards the escalation of materials procurement
cost incurred during the extended period to the
claimant as mentioned in Annexure – F;
G. To pay a sum of Rs.2,54,002/- (Rupees
Two Lakhs Fifty Four Thousand and Two Only)
towards the renewal of insurance charges which
was time and again renewed by the claimant as
mentioned in Annexure G;
4/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
H. To pay a sum of Rs.1,03,423.30/-
(Rupees One Lakh Three Thousand Four
Hundred and Twenty Three and Thirty Paise
Only) towards the renewal of bank guarantee
charges which was time and again renewed by
the claimant as mentioned in Annexure – H';
I. To pay a sum of Rs.1,20,000/- (Rupees
One Lakh and Twenty Thousand Only) towards
the rental cost for the container which was
wrongly retained by the respondent even after
the completion of work (from 24.9.2017 to
24.9.2018) together with 18% interest per
annum as mentioned in Annexure-I;
J. To pay a sum of Rs.49,25,543.52/-
(Rupees Forty Nine Lakhs Twenty Five Thousand
Five Hundred and Forty Three and Fifty Two
paise Only) towards the rental cost for the
Machinery Excavator 220 which was wrongly
retained by the respondent even after the
completion of work (from 24.9.2016 to
24.9.2017) together with 18% interest per
annum as mentioned in Annexure – J;
K. To reimburse/repay a sum of
Rs.9,63,900/- (Rupees Nine Lakhs Sixty Three
Thousand and Nine Hundred Only) towards the
rent of genset utilized for electricity purpose
incurred by the claimant together with 18%
interest per annum as mentioned in Annexure K;
5/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
L. To pay a sum of Rs.29,875/- (Rupees
Twenty Nine Thousand Eight Hundred and
Seventy Five Only) towards the interest for the
delayed payment of the final bill as mentioned in
Annexure – L;
M. To pay a sum of Rs.41,43,841/-
(Rupees Forty One Lakhs Forty Three Thousand
Eight Hundred and Forty One Only) towards the
incentive/bonus to the claimant;
N. To a sum of Rs.1,00,00,000/- (Rupees
One Crore Only) towards damages incurred for
the loss of business to the claimant from
17.8.2014 till 24.9.2017; and
O. To pay the cost of the Arbitration.”
(iv) In turn, the petitioner filed a statement of defence and
took a stand that the delay in completion of work was attributable
only to the respondent/claimant and that the agreement itself
contemplated a pre-estimated sum as liquidated damages for the
delay in completion of the work. That apart, the petitioner denied
the various claims made by the respondent/claimant.
(v) The learned Arbitrator, after considering the pleadings
on either side, framed the following issues:
“1. Whether the extension of the contract
period for the work was approved/consented by
the respondent as claimed in the statement of
6/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
claim?
2. Who is responsible for the delay in
completion of the contract? Whether the
claimant or the respondent?
3. Whether the respondent impliedly
approved the extension of the time to carry on
the work by the claimant?
4. Whether the respondent is liable to pay
the claims listed out in para 73-A to O of the
statement of claim?
5. To what relief the parties are entitled
to?”
(vi) The respondent/claimant examined C.W.1 and Ex.A.1 to
Ex.A.90 were marked. The petitioner examined R.W.1 and marked
Ex.R.1 to Ex.R.41.
(vii) The learned Arbitrator, on considering the facts and
circumstances of the case and on appreciation of evidence, passed
an award in the following terms:
“a) the respondent is liable to re-pay/
return the liquidated damages to an extent of
Rs.49,19,960/- along with interest which works
out to Rs.20,38,332/- for different periods as
calculated in paragraph 140-142. Therefore, as
far as the claim covered by para 73A is
concerned, the liquidated damages to be
released and that is payable by the respondent
7/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
to the claimant along with interest to be
calculated at the rate of 14.3% works out to a
sum of Rs.69,58,792/- (Rs.49,19,960 +
Rs.20,38,832), which the respondent is directed
to pay within 6 weeks from the date of passing
of this award along with interest calculated at
the rate of 6% per annum from the date of claim
statement i.e., from 21.3.2019 till the date of
payment. If the respondent fails to effect the
payment as directed above, the respondent shall
be liable to pay penal interest, in addition,
calculated at the rate of 2% p.a. from the date
of expiry of the 6 weeks' time fixed under this
award till the date of actual payment;
b) the respondent is liable to pay the
Service Tax amount deducted, namely
Rs.7,23,754/- and the interest on that amount,
which works out to Rs.2,99,207/-, the total claim
comes to Rs.10,22,961/-. The respondent is
therefore directed to pay the said sum of
Rs.10,22,961/- along with interest at the rate of
6% p.a. from the date of claim statement and
effect the payment within 6 weeks from the date
of pronouncement of this award. If the
respondent fails to effect the payment as
directed within the said 6 weeks' time, the
respondent will be liable to pay penal interest, in
addition, calculated at the rate of 2% p.a. from
the date of expiry of the 6 weeks' time till the
8/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
date of payment;
c) the respondent is liable to pay the sum
of Rs.2,18,836/-, the room rent charges wrongly
deducted along with interest which works out to
Rs.70,154/-, in all a total sum of Rs.2,88,990.
Accordingly, the respondent is directed to pay
the said sum of Rs.2,88,990/- along with
interest at the rate of 6% p.a from the date of
claim statement and effect the payment within 6
weeks from the date of pronouncement of this
award. If the respondent fails to effect the
payment as directed within the said period of 6
weeks, the respondent will be liable to pay penal
interest, in addition, calculated at the rate of 2%
p.a. from the date of expiry of the 6 weeks' time
till the date of payment;
d) the respondent is liable to pay the sum
of Rs.9,63,900/- towards rental charges for the
genset hired by the claimant by way of
reimbursement along with interest to be
calculated at the rate of 14.3% p.a. for the
period 10.10.2013 to 03.10.2016, totalling to a
sum of Rs.13,75,147.27. The respondent is
directed to make the said payment of
Rs.9,63,900/- along with interest calculated at
the rate of 14.3% p.a. for the above said period
and effect the said payment within six weeks
from the date of the passing of this award failing
which the respondent would be liable to further
9/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
pay a penal interest at the rate of 2% p.a. over
and above 14.3% from the expiry of the said six
weeks period till the date of actual payment; and
e) the respondent is liable to pay the sum
of Rs.29,875/- by way of interest for the delayed
payment of final bill along with interest to be
calculated at the rate of 14.3% p.a. from the
date of filing of the statement of claim i.e.,
21.3.2019 within 6 weeks from the date of
pronouncement of this award, failing which, the
respondent would be liable to pay interest at the
rate of 2% p.a from the date of expiry of the 6
weeks period directed in this Award till the date
of payment.”
(viii) The other claims made by the respondent/claimant were
rejected. Aggrieved by that portion of the award passed by the
learned Arbitrator granting the relief to the respondent/claimant, the
above petition has been filed by the petitioner.
4. The learned Standing Counsel appearing for the petitioner
focused his arguments only in so far as the issue of refund of
liquidated damages ordered by the learned Arbitrator was
concerned.
10/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
5. It was submitted on the side of the petitioner that the
respondent/claimant was expected to complete the work by
17.8.2014 whereas the work was completed only on 24.9.2016 with
a delay of 786 days, that Clause 49.1 of the General Conditions of
Contract provides that the petitioner would be entitled to levy
liquidated damages for the delay, that therefore, considering the
delay that was attributable to the respondent/claimant and after
condoning 18 days towards inclement weather conditions, the
liquidated damages were confined to 750 days, that the learned
Arbitrator, after rendering a finding that the respondent/claimant
was solely responsible for the delay, ordered for the refund of the
liquidated damages to the tune of Rs.49,19,960/- with interest,
which is contrary to law and that consequently, this finding suffers
from patent illegality.
6. In order to substantiate his submissions, the learned
Standing Counsel appearing for the petitioner, placed reliance upon
the latest common order passed by me in M/s.Prime Store, Rep.
by its Partner Mr.S.Kaarthi & others Vs. Sugam Vanijya
Holdings Private Limited & others [Arb.O.P. (Com.Div.) Nos.
11/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
257 of 2021 & 209 of 2022 dated 08.10.2025].
7. Per contra, the learned counsel appearing for the
respondent/claimant submitted as follows:
The learned Arbitrator had taken into consideration the
relevant clause in the General Conditions of Contract namely Clause
49.1 and found that the petitioner had not duly followed the
procedure provided under the said clause in a proper perspective.
The learned Arbitrator found that the liquidated damages retained
by the petitioner were not reasonable and it was not a genuine pre-
estimate of damages. Therefore, the learned Arbitrator came to the
conclusion that the action of the petitioner in deducting the
liquidated damages was in violation of the judgment of the Hon’ble
Apex Court in Kailash Nath Associates Vs. Delhi Development
Authority [reported in 2015 (4) SCC 136] . In the absence of the
petitioner proving the actual loss sustained by them, the petitioner
would not be entitled to retain the amount towards liquidated
damages. Accordingly, the learned counsel justified the award
passed by the learned Arbitrator and sought for dismissal of this
petition.
12/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
8. This Court has carefully considered the submissions of the
learned counsel on either side and perused the materials available
on record and more particularly the impugned award passed by the
learned Arbitrator.
9. Since the entire focus was bestowed only on the issue of
retention of amount by the petitioner towards the liquidated
damages, it will suffice to render a finding on this issue.
10. Before dealing with this issue, it will be relevant to extract
Clauses 1.10 and 49 of the General Conditions of Contract as
hereunder:
“Clause 1.10:
The Contract Price is the price stated in
the Letter of Acceptance and thereafter as
adjusted in accordance with the provisions of the
contract.”
…………..
“Clause 49: Liquidated Damages
49.1 In case of delay in completion of the
contract, liquid damages (L.D) may be levied at
the rate of 1/2% of the contract value per week
of delay or part thereof, subject to a maximum
13/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
of 10 per cent of the contract price.
(i) The owner, if satisfied, that the works
can be completed by the contractor within a
reasonable time after the specified time for
completion, may allow further extension of time
at its discretion with or without the levy of L.D.
In the event of extension granted being with
L.D, the owner will be entitled without prejudice
to any other right or remedy available in that
behalf, to recover from the contractor as agreed
damages equivalent to half per cent (1/2%) of
the contract value of the works for each week or
part of the week subject to the ceiling defined in
Sub-Clause-49.1;
(ii) The owner, if not satisfied that the
works can be completed by the contractor and in
the event of failure on the part of the contractor
to complete work within further extension of
time allowed as aforesaid, shall be entitled,
without prejudice to any other right or remedy
available in that behalf, to rescind the contract;
(iiii) The owner, if not satisfied with the
progress of the contract and in the event of
failure of the contractor to recoup the delays in
the mutually agreed time frame, shall be entitled
to terminate the contract;
(iv) In the event of such termination of
the contract as described in Clauses-49.1(ii) &
49.1(iii) or both the owner shall be entitled to
14/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
cover L.D up to ten per cent (10%) of the
contract value and forfeit the security deposit
made by the contractor besides getting the work
completed by other means at the risk and cost of
the contractor;
(v) In case part/portions of the work can
be commissioned and Port operates the portion
for commercial purposes, the rate of L.D will be
restricted to the uncompleted value of work, the
maximum LD being on the entire contract
value.”
11. The learned Arbitrator, while dealing with issue No.2,
rendered a finding that the delay in the completion of the contract
was attributable only to the respondent/claimant. After having
rendered such a finding, the learned Arbitrator went into the issue of
the levy of liquidated damages by the petitioner. The learned
Arbitrator, while interpreting Clause 49 of the agreement, rendered
a finding that five sub-clauses (i to v) of Clause 49.1 must be read
in consonance with the opening clause in Clause 49.1 and not in
isolation. Having found so, the learned Arbitrator rendered a finding
that the Authority must establish that there was a genuine
application of mind before any action was contemplated for levy of
15/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
liquidated damages and must satisfy itself that such a levy was
imperative. Hence, the Authority must exercise the discretion at the
very threshold of satisfaction being arrived at that the works
completed by the contractor were within a reasonable time after the
time specified.
12. The learned Arbitrator thereafter proceeded to refer
various exhibits namely the correspondences that had taken place
between the parties and also the meeting that was held between the
parties and came to the conclusion that the petitioner was extending
the time so as to enable the respondent/claimant to complete the
work and did not choose to terminate the contract under Clause 58.
The learned Arbitrator also took into consideration Ex.A.24, which
was a show cause notice issued to the respondent/claimant and for
this purpose, the respondent/claimant also gave a reply and on
receipt of the same, the petitioner did not proceed further with the
show cause notice. Ultimately, the work completion certificate
marked as Ex.A.36 was taken into consideration wherein the
petitioner had acknowledged that the respondent/claimant had
executed the work to the complete satisfaction even though they
16/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
had taken more time to complete the work.
13. In the entire process, only in the letter dated 25.1.2016
marked as Ex.A.25, the petitioner mentioned about the levy of
liquidated damages. This is nearly after one year and five months
from 17.8.2014. The petitioner informed the respondent/claimant
that they levied the liquidated damages to the tune of
Rs.28,47,989/- and that the balance recovery amount of
Rs.19,74,572/- would be withheld and considered for release
depending upon the performance of the respondent/claimant.
Thereafter, on 29.11.2016, the petitioner expressed its decision to
affirm the levy of liquidated damages and informed the respondent/
claimant that a sum of Rs.39,91,535/- has already been recovered
and that the balance amount would be recovered from the final bill.
14. The learned Arbitrator thereafter took into consideration a
very important aspect, which ultimately lead to denying the
retention of liquidated damages. The learned Arbitrator found that
the contract value was fixed at Rs.4,82,15,608/- whereas the entire
work was completed though with some delay, for a lesser value of
17/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
Rs.4,14,54,674/-. Thus, as a matter of fact, the learned Arbitrator
found that the petitioner certainly did not suffer any loss or damage
even though the delay in the completion of work was attributed to
the respondent/claimant and that on the other hand, the petitioner
was able to save to the tune of Rs.67,60,934/- in this project.
15. The learned Arbitrator also took into consideration the fact
that the levy of liquidated damages resorted to by the petitioner was
for the total value of contract work by fixing the figure at
Rs.4,91,99,600/- and 10% of this amount was calculated and
appropriated as the liquidated damages to the tune of
Rs.49,19,960/-. However, even as per Ex.A.56, the total value of
work completed by the respondent/claimant was Rs.4,14,38,412/-
and in spite of the same, the petitioner imposed levy on the value
that was quoted by the respondent/claimant in his bid and that such
levy was neither on the contract price of Rs.4,82,15,608/- nor on
the actual value of execution to the tune of Rs.4,14,38,412/-.
Hence, the learned Arbitrator reached a conclusion that the very
levy of the liquidated damages was in violation of Clause 1.10 read
with Clause 49.1 of the General Conditions of Contract.
18/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
16. Keeping these facts in mind, the learned Arbitrator applied
the ratio laid down by the Hon’ble Apex Court in Kailash Nath
Associates and came to the conclusion that withholding the amount
of Rs.49,19,960/- was illegal and hence, directed this amount to be
released along with interest. While fixing the interest, the learned
Arbitrator once again assigned reasons.
17. The decision relied upon by the learned Standing Counsel
for the petitioner in M/s.Prime Store, Rep. by its Partner
Mr.S.Kaarthi & others will have no application to the facts of the
present case. Firstly, the learned Arbitrator rendered a factual
finding that the petitioner, in fact, did not incur any loss and on the
contrary, was able to save a sum of Rs.67.60 lakhs in this particular
project. The learned Arbitrator also found that the liquidated
damages levied by the petitioner were unreasonable since such a
levy was made on the value of the bid amount whereas what was
permissible under the contract was the value of the contract price
after its final adjustment.
19/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
18. In the decision in M/s.Prime Store, Rep. by its Partner
Mr.S.Kaarthi & others, I have held that in a case covered by
Section 74 of the Indian Contract Act and the parties have agreed to
a pre-estimated sum named in the contract towards the liquidated
damages and also the Court finds that such pre-determination is a
reasonable sum and due to the breach of contract, one party has
suffered a legal injury i.e loss or damage, it is not necessary that
the party must once again prove the actual loss or damage. This law
was further confirmed while dismissing Rev.A.Nos.1 and 2 of
2026 by a common order dated 03.2.2026.
19. The decision of a learned Single Judge of the Bombay High
Court relied upon by the learned Standing Counsel for the petitioner
in Hindustan Petroleum Corporation Limited Vs. G.R.
Engineering Private Limited [Commercial Arbitration Petition
No.984 of 2018 dated 18.6.2025] will also not apply to the facts
of the present case.
20. In the light of the above discussions, this Court does not
find any perversity or patent illegality in the findings rendered by
20/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
the learned Arbitrator on the issue of liquidated damages. In so far
as the other claims awarded in favour of the respondent/claimant
are concerned, no arguments were put forth by the learned
Standing Counsel for the petitioner and in any event, the learned
Arbitrator rendered findings by assigning sufficient reasons towards
each claim that was awarded in favour of the respondent/claimant
and they certainly do not suffer from perversity or patent illegality.
Further, the case in hand does not fall within any of the eight pigeon
holes available under Section 34 of the Act.
21. In the result, the above original petition stands dismissed.
No costs.
09.2.2026
Index : Yes
Neutral Citation : Yes
RS
21/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
N.ANAND VENKATESH,J
RS
Arb.O.P.(Com.Div.) No.119 of 2023
09.2.2026
22/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
In the High Court of Judicature at Madras
Dated: 12.2.2026
Coram:
The Honourable Mr.Justice N.ANAND VENKATESH
Arbitration O.P. (Com.Div.) No.119 of 2023
The Chairman,
Chennai Port Trust,
No.1, Rajaji Salai,
Chennai-1. ...Petitioner
Vs
Mr.A.Manicavassalou,
Proprietor, M/s.A.
Manicavassalou, registered
engineering contractor, No.10,
Vellavari Street, Mariya Tower,
II Floor, Carmel Convent,
Muthialpet, Puducherry-3. ...Respondent
PETITION under Section 34(2)(b) of the Arbitration and
Conciliation Act, 1996 praying to set aside the award dated
06.4.2022 passed by the Arbitral Tribunal.
For Petitioner : Mr.Haja Mohideen Gisthi,
Standing Counsel
For Respondent : Mr.D.Vivekanandan
ORDER
After the final order in the above petition was pronounced by
23/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
this Court on 09.2.2026, the learned Standing Counsel appearing for
the petitioner submitted that at paragraph 20 of the order dated
09.2.2026, this Court recorded as if no arguments were put forth
with respect to the other grounds and also as if the only issue that
was argued pertained to liquidated damages. He further submitted
that the objections raised regarding the other grounds were filed by
way of short notes and that the same were not taken into
consideration.
2. At paragraph 20 of the order dated 09.2.2026, this Court
did render a finding to the effect that even in so far as the other
findings rendered by the learned Arbitrator were concerned, there
are no grounds made out to interfere with the award. Therefore, it is
not as if this Court only focussed on the issue of liquidated damages
and did not consider the other grounds. What was recorded was that
at the time of oral arguments, the main focus of arguments on the
side of the petitioner touched upon only the liquidated damages.
3. In the light of the above clarification sought for by the
learned Standing Counsel for the petitioner, this Court does not
24/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
want to give an impression that the other grounds raised were not
considered. Therefore, the following reasoning for rejecting the
other grounds are given in this clarificatory order:
(i) The first issue pertains to the interest awarded by the
learned Arbitrator for the liquidated damages withheld by the
petitioner. The learned Arbitrator placed reliance upon Clauses 43.3,
43.6 and 43.7 of the agreement and calculated interest at the rate
of 14.3%, which worked out to Rs.20,38,832/- and added the same
to the liquidated damages to arrive at a total sum of Rs.69,58,792/-
and this amount was directed to be paid within six weeks from the
date of passing the award along with interest at the rate of 6% per
annum from the date of the claim statement till the date of
payment. It was also made clear that if the payment was not made
within the time stipulated, it would further carry a penal interest at
the rate of 2% per annum from the date of expiry of six weeks’ time
fixed by the learned Arbitrator. This finding rendered by the learned
Arbitrator does not suffer from any perversity.
(ii) The next issue pertains to the relief granted on service tax
on the liquidated damages withheld for certain bills to the total tune
of Rs.7,23,754/-. For this purpose, Clause 43 of Section 3 of Ex.A.4
25/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
series was relied upon and the petitioner was directed to pay a total
sum of Rs.10,22,961/- along with interest at the rate of 6% per
annum from the date of the claim statement within a period of six
weeks. The above issue also pertains to the liquidated damages,
which was confirmed and hence, was more consequential to the
issue of liquidated damages that was found in favour of the
respondent/claimant.
(iii) The third issue pertains to the relief granted for deduction
of room rent. The learned Arbitrator found that under Ex.R.5,
nothing was stated as to the payment of any rent for the usage of
the site for office purpose and even Clause 25 of Section 5 of Ex.A.4
series did not specify any payment of rent while granting
permission. Apart from that, Clause 2 of Section 5 of Part I, which
provided for general description of work and other conditions, made
it clear that no rental charges would be levied. In view of the same,
the learned Arbitrator rendered a finding that there was no
justification for the petitioner to deduct the rental charges.
Therefore, that claim was ordered in favour of the respondent/
claimant along with interest. The finding rendered by the learned
Arbitrator certainly does not suffer from any perversity.
26/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
(iv) The fourth issue pertains to the relief of rent for the
genset hired by the respondent/claimant by way of reimbursement.
The learned Arbitrator found from Ex.A.74 and Ex.A.75 series that
the respondent/claimant hired genset and utilized the same between
the period from 18.10.2013 to 03.10.2016 since electricity was not
provided by the petitioner. Accordingly, a sum was calculated and
awarded and the same does not require the interference of this
Court.
(v) The last issue pertains to the payment of interest for the
delayed payment of final bill. The learned Arbitrator found that the
petitioner had already deducted the liquidated damages and in spite
of the same, a further deduction was made towards the entire final
bill amount. Thus, it was factually found that there was excess
deduction of Rs.98,399/- and hence, the same was interfered and a
sum of Rs.29,875/- was directed to be paid by way of interest for
the delayed payment of the final bill. This finding also does not
suffer from any perversity or patent illegality.
12.2.2026
27/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
Index : Yes
Neutral Citation : Yes
RS
28/29 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.119 of 2023
N.ANAND VENKATESH,J
RS
Arb.O.P.(Com.Div.) No.119 of 2023
12.2.2026
29/29 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....