As per case facts, the Petitioner, granted land in 1959, claimed adverse possession of an open space and garden, which was later transferred to the BMC. Despite an injunction against ...
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.7981 OF 2026
The Deccan Co-operative Housing
Society Limited,
1079 B, Union Park,
Khar (West), Mumbai – 400 052..... Petitioner
Vs.
1. The State of Maharashtra,
through its Principal Secretary,
Revenue Department, Mantralaya,
Mumbai – 400 032
2. The Collector,
Mumbai Suburban,
Administrative Building, 10
th
Floor,
Government Colony, Bandra (East),
Mumbai – 400 051 .... Respondents
WITH
INTERIM APPLICATION NO. 4651 OF 2026
IN
WRIT PETITION NO.7981 OF 2026
Jasani Realty Private Limited
A Company registered under the
Companies Act, 1956
Having its registered address at
23, Morvi House, 28/30, Goa Street,
Ballard Estate, Mumbai – 400 038 … Applicant
In the matter between :
1/24
901 WP 7981.26+IA.doc Dusane
The Deccan Co-operative Housing
Society Limited,
1079 B, Union Park,
Khar (West), Mumbai – 400 052..... Petitioner
Vs.
1. The State of Maharashtra,
through its Principal Secretary,
Revenue Department, Mantralaya,
Mumbai – 400 032
2. The Collector,
Mumbai Suburban,
Administrative Building, 10
th
Floor,
Government Colony, Bandra (East),
Mumbai – 400 051 .... Respondents
----
Mr. Pravin Kumar Samdani, Senior Advocate a/w Mr. Bhushan
Deshmukh, Ms. Neha Mehta, Mr. Aditya Miskita, Mr. Umair
Merchant, Ms. Aayushi Gohil, Ms. Rima Ajmerwalla and Daryl
Alemao i/b M.T. Miskita & Co. for Petitioner in WP.
Mr. Mayur Khandeparkar a/w Mr. Amogh Singh, Mr. Devansh Shah,
Mr. Santosh Pathak, Mr. Nimish Lotlikar, Ms. Archana Karmakar,
Ms. Khushi Jain i/b Law Origin for Applicant in IA No. 4651 of
2026.
Mr. Yuvraj D. Patil, AGP for Respondent Nos. 1 and 2 – State.
CORAM : ARUN R. PEDNEKER, J.
RESERVED ON : 28
th
August 2026
PRONOUNCED ON : 10
th
September 2026
2/24
901 WP 7981.26+IA.doc Dusane
JUDGMENT :
1. The Interim Application is allowed. Rule. Rule is made returnable
forthwith. Heard finally.
2. By the present Writ Petition, the Petitioner challenges the legality,
validity and propriety of the Impugned Order dated 17
th
March 2026, passed
by Respondent No. 2 – Resident Deputy Collector, Mumbai Suburban
District (“the Collector”), directing removal of gates installed on the
Government land, used as an access by the Petitioner.
3. The Petitioner-Society also challenges the action taken pursuant to the
impugned order dated 17
th
March 2026 passed by Respondent No. 2 –
Collector. Pursuant thereto, Respondent No. 2- Collector and its officers, on
23
rd
March 2026, 27
th
March 2026 and 1
st
April 2026, visited the property
which is the subject matter of the present Writ Petition and attempted to
demolish the existing gate, which has been in the exclusive and
uninterrupted possession and use of the Petitioner-Society for over 45 years.
4. The case of the Petitioner in the Writ Petition is briefly set out
hereunder:-
By Order dated 23rd September 1959, land admeasuring 17,780 per
sq. mtrs. bearing Plot nos. 15 to 22 and 23.37, out of survey nos. 323 and
289/B, situated at Danda, Bombay Suburban District (“the Larger Land”)
3/24
901 WP 7981.26+IA.doc Dusane
was granted on permanent basis by the Collector, Mumbai in favour of
Petitioner, subject to certain terms and conditions stipulated therein.
Accordingly, the land vested in the Petitioner. It is further stated that the
portion of land, approximately admeasuring 7,075.07 sq. mtrs., was reserved
as open space under the sanctioned Development Plan for Greater Mumbai.
The BMC, through its officer, i.e. the Deputy City Engineer, Development
Plan, addressed a letter dated 6th March 1978 to the Petitioner’s Architect
with respect to the proposed temporary access road through the property
reserved as open space. As per the said letter, the Petitioner was permitted to
access a 30-feet-wide strip of the D.P. road through the Government
property.
5. The Petitioner transferred the ownership/title of the open space/
garden to BMC sometime in the year 1978. The construction of 44-feet-wide
D.P. road, as contemplated in the letter dated 13th March 1978 addressed by
the BMC, was also completed, and the name of the BMC was mutated in the
Property Card and updated in the Land Records sometime in or about the
year 1985.
6. However, from 1985 onwards, the Petitioner has remained in physical
possession of the open space and garden. The Petitioner states that it is in
adverse possession of the said property that they have been using it for a
4/24
901 WP 7981.26+IA.doc Dusane
period of 41 years. It is further stated that the Petitioner has been in physical
control of the property since 1985 including the garden / open space. It is
stated that the garden / open space alongwith the gate thereon has been
exclusive and uninterrupted possession of the Petitioner from 1960 until
1985 when the same was handed over to BMC and the possession was taken
over by the Petitioner in 1985 itself. The Petitioner has incurred various
expenses towards the maintenance of the garden.
7. On 6
th
May 2025, the name of the BMC was updated in the Property
Card/Land Records. Thereafter, the BMC, through its concerned officer,
issued a notice to the Petitioner stating that the garden property was owned
by the BMC, as reflected in the Property Card, and that the Petitioner was
using the said property unauthorisedly. Accordingly, the Petitioner was
called upon to hand over physical possession of the property to the BMC,
remove the locked gate and the security personnel deployed by the
Petitioner, and cease all exclusive activities and/or development being
carried out on the said property.
8. On 6
th
May 2025, the Petitioner responded to the notice issued by the
concerned BMC authority. Thereafter, the Petitioner was constrained to
institute Suit No. 287 of 2025, inter alia, seeking a declaration in respect of
its rights, title and interest in the said property, i.e. the land reserved for
5/24
901 WP 7981.26+IA.doc Dusane
garden and also the gate, as well as a decree of permanent injunction
restraining the BMC from taking any precipitative or coercive action
pursuant to the notices dated 6th May 2025 and 23rd May 2025, and from
dispossessing the Petitioner from the said property without following due
process of law.
9. In the Civil Suit, this Court granted ad-interim reliefs restraining the
BMC from taking any coercive action. The order dated 11
th
June 2025
passed by this court (Coram : R.I. Chagla, J.) is quoted below :
“
1. The Defendant – Brihanmumbai Municipal Corporaton shall file
their Affidavit in Reply to the Interim Applicatoin within a period of two
weeks from today i.e. on or before 25
th
June 2025.
2. The Plaintiff is at liberty to file Affidavit in Rejoinder thereto
within a period of one week therafter.
3. Considering that the Plaintiff has been in possession of the Suit
property for several years, till the next date, the Defendants shall not act
upon the impugned notices dated 6
th
May 2025 and 23
rd
May 2025.
4. Place the Interim Application for further consideration on 4
th
July
2025”.
10. It is stated that the interim protection granted by this Court extends to
the garden area as well as the access area. It is further stated that, during the
pendency of the Suit, Jasani Realty Private Limited, a Company, undertaking
a Slum Rehabilitation Scheme adjacent to the Petitioner’s property, sought to
intervene in the Suit by filing Interim Application (L) No. 30680 of 2025,
6/24
901 WP 7981.26+IA.doc Dusane
inter alia, seeking its impleadment in the Suit. The said Intervention
Application was subsequently withdrawn.
11. It is stated that the said Interim Application was filed by Jasani Realty
Pvt. Limited for two purposes: (i) Jasani sought to ensure that the suit
property, i.e. the garden, was not used exclusively by the Petitioner and was,
presumably, made available for use by the proposed flat purchasers in its
Scheme on the adjoining land; and (ii) Jasani sought to secure better access
to its Scheme on the adjoining property by opening the gate of a pathway
leading to the garden.
12. The Petitioner opposed the said Interim Application, which was
thereafter withdrawn by Jasani pursuant to an Order dated 18
th
February
2026.
13. Against this background, on 23
rd
March 2026, the
officers/representatives of Respondent No. 2 – Collector, visited the
Petitioner’s property without any prior notice and proceeded to attempt the
demolition of an existing gate situated in the garden area of the property, at
the entrance to a small pathway leading to the garden. The said pathway and
the gate have been in the Petitioner’s lawful, settled and uninterrupted
possession and use for over 45 years.
7/24
901 WP 7981.26+IA.doc Dusane
14. Upon being questioned, the officials present at the site stated that the
aforesaid action was purportedly being undertaken pursuant to certain
directions and/or an order issued by Respondent No. 2 – Collector. It was
only in the course of the said attempted demolition that the Petitioner
became aware of the purported directions and/or order issued by Respondent
No. 2 – Collector.
15. No show-cause notice was issued to the Petitioner, nor was any
opportunity afforded to the Petitioner to furnish an explanation prior to the
issuance of the purported directions/order or the attempted demolition
carried out on 23rd March 2026. The said action, having been undertaken
without any authority of law and without reference to or compliance with
any statutory provision, is ex facie arbitrary, illegal and in flagrant violation
of the principles of natural justice.
16. In the aforesaid circumstances, the Petitioner has been constrained to
approach this Hon’ble Court by invoking its jurisdiction under Articles 226
and 227 of the Constitution of India, challenging the illegal and arbitrary
actions of Respondent No. 2 – Collector, including the attempted demolition
of the gate, as well as the impugned order/directions pursuant to which such
action was purportedly undertaken. The impugned action has been taken
without issuance of any notice to the Petitioner, without conducting any
8/24
901 WP 7981.26+IA.doc Dusane
enquiry, and without calling for, receiving or considering any explanation
from the Petitioner.
17. Learned counsel for the Petitioner submits that (i) the garden, along
with the gate, is the subject matter of Civil Suit No. 287 of 2025; (ii) the
injunction order passed by this Court operates against the Respondent No.2-
Collector from taking any coercive steps, although the Collector is not a
party to the Civil Suit, as the injunction operates against the Municipal
Corporation; (iii) the subject property i.e. the installed gates, forms part of
the subject matter of the civil suit; and (iv) Respondent No. 2- Collector
ought not to have passed any order for removal of the gates.
18. Learned counsel for the Petitioner submits that no notice of hearing
was given to the Petitioner and the Petitioner has been in exclusive
occupation of the strip of land/excess strip for a long period of time, i.e.,
about 45 years. As such, without issuing notice to the Petitioner, no action
ought to have been taken by the Collector for removal of the gates. Learned
counsel for the Petitioner submits that the strip, over which access is
claimed, forms part of a larger property, which is owned by the Petitioner by
virtue of the original grant of the year 1953. The learned counsel for the
Petitioner submits that Respondent No. 2- Collector has acted high-handedly
at the instance of the Intervenor and that the Intervenor, having failed to
9/24
901 WP 7981.26+IA.doc Dusane
intervene in the civil suit, has thereafter approached the Collector, who
proceeded to take action bypassing the proceedings in the said Civil Suit.
The Intervenor did not proceed to contest the proceedings before the Civil
Court but withdrew the application and applied to the State.
19. Learned counsel for the Petitioner has taken me through the maps to
substantiate the case of the Petitioner. It is submitted that the strip of land
being used as an access belongs to the Petitioner-Society and that
Respondent No.2 -Collector has no right or authority over the said strip.
20. Learned counsel further submits that the portion of the land claimed
by the Intervenor and State-Respondent No.2 is not a public street.
Consequently, the Municipal Corporation could not have taken any action in
respect of the said property. He further submits that, even assuming that the
property is Government land and that the same is held against the Petitioner,
it cannot be taken over by the authorities without issuance of due notice to
the Petitioner. The Petitioner has been in settled possession of the property
for over 45 years. Therefore, even if it is held that the street access is
situated on Government land, the authorities cannot dispossess the Petitioner
or take over the land without following due process of law and providing
him an opportunity of being heard. In that regard, he relies upon the
judgment delivered by this Court (Coram : Shailesh P. Bramhe, J),
10/24
901 WP 7981.26+IA.doc Dusane
Aurangabad Bench, in the case of Shakuntalabai w/o Shrinivas Dhoot &
Ors. V. The State of Maharashtra & Anr.
1
.
21. An Intervention Application has been filed by the Intervenor, who has
submitted that the Civil Suit does not pertain to the strip of land on which
the Collector has taken action. It is specifically pointed out that, having
regard to the prayers in the Civil Suit, the gate, the removal of which has
been directed does not form part of the subject matter of the Civil Suit.
22. Mr. Khandeparkar, learned counsel appearing for the intervenor,
submitted that the Division Bench of this Court, in Writ Petition No. 2701 of
2019, had specifically appointed a Committee to inquire into the
development of the slum adjoining the petitioner’s plot. Various directions
were issued by this Court to ensure that access to the slum area was kept
open, particularly in view of the highly congested nature of the area. The
said order was also challenged before the Hon’ble Supreme Court; however,
the Special Leave Petition (SLP) came to be dismissed.
23. Learned counsel further submitted that the slum area is densely
populated and has no alternative access. In such circumstances, the existing
public access cannot be permitted to be converted into a private access, as
doing so would adversely affect the residents of the slum and impede their
access to the area.
1 Second Appeal Nos. 118, 119, 120 and 127 of 1999 dt. 8
th
August 2025
11/24
901 WP 7981.26+IA.doc Dusane
24. The Civil Suit pertains to a garden shown in the D.P. Plan, which is
earmarked for a public purpose. According to the Intervenor, the Petitioner is
a land grabber attempting to take over the said garden, and the same is the
subject matter of the Civil Suit.
25. As regards the strip of land on which the Petitioner has erected the
gate, it is submitted that the said strip constitutes Government land being
used as an access. Such access is available to all concerned, and the
Petitioner cannot claim any exclusive right over the same or convert a public
access into an exclusive passage by erecting a gate.
26. The Collector, by merely directing the removal of the gates, has
ensured that the access remains available to all concerned, including the
Petitioner. The Petitioner has no absolute right over the said access. The use
of the access was only temporarily permitted to the Petitioner over
Government land, particularly since the 44 D.P. Road situated on the other
side of the Petitioner's plot had not yet been developed.
27. The access in question is admittedly situated on Government land and
is available to the public at large. The terms of the original letter granting
access itself indicate that, once the 44 D.P. Road was developed and made
available, the Petitioner was expected to discontinue the use of the access
12/24
901 WP 7981.26+IA.doc Dusane
over the strip of land now claimed by the Petitioner. It is submitted that the
44 D.P. Road is admittedly now openly available, and consequently, the
Petitioner has no continuing right to exclusively use the said Government
land as an access.
28. The learned AGP appearing for Respondent No. 2 – Collector submits
that the strip of land in question is Government land and that access over the
said land was permitted to the Petitioner by the Municipal Corporation, as
the Petitioner’s plot was inaccessible at the relevant time and the D.P. Road
connecting the said plot was then under construction.
29. Admittedly, the D.P. Road is now constructed and operational. In any
event, since the strip of land is Government property, over which access is
merely permitted to the Petitioner as well as to others, the Petitioner cannot
erect a gate so as to convert access over Government land into an exclusive
right of possession.
30. Therefore, the action of the Government in directing removal of the
gates and maintaining the access open to all cannot be faulted. The Petitioner
is not in possession of the said property and is merely permitted to use the
strip of land as an access. By erecting up a gate, the Petitioner is, in effect,
attempting to convert public access into private access and thereby encroach
upon and appropriate Government property.
13/24
901 WP 7981.26+IA.doc Dusane
31. Having heard the learned Counsel for the parties, the following
questions arise for my consideration :
(i) Whether the access strip forms part of the subject matter of
Civil Suit No. 287 of 2025 and, consequently, whether the
injunction order passed therein applies to the said access strip,
which has been directed to be kept/opened as open land by
removing the gates installed therein?
(ii) Whether the strip of land on which the gate is installed is
allotted to the Petitioner and form the part of allotment granted in
the year 1959 ? and Whether the Collector was required to issue
a separate notice to the Petitioner before directing the removal of
the gate erected on the access strip?
(iii) Whether the Collector had the jurisdiction and authority to
direct removal of the gate, and whether such direction is beyond
his statutory powers and in violation of the provisions of Section
53 of the Maharashtra Land Revenue Code?
32. In response to the application for Intervention Application filed by the
Intervenor in the Suit No. 287 of 2025, the Petitioner herein specifically
responded to the said application. The relevant statements from the
Petitioner’s Affidavit-in-Reply are set out below:
“3.7. The guarded pleadings in the captioned IA does not even
allege that the Road of 9.15 meters which leads to the suit
property which is a garden in possession of and maintained by
the Plaintiff is the only access available to the property which
the Applicant claims to be developing. This is a reason enough
to conclude that Applicant has absolutely nothing to do with
14/24
901 WP 7981.26+IA.doc Dusane
the lis involved in the present Suit.
3.8. Additionally, the road described as 9.15 meter wide D.P.
Road (albeit incorrectly) by the Applicant is admittedly not
part of the Suit Property. This is one more reason for
warranting dismissal of the captioned IA.
4. ………... IA is nothing but an attempt to seek one more
and better access through 9.15 meter wide existing road which
leads to the Suit Property i.e. garden, which is in possession of
and is maintained by the Plaintiff for last several years as
stated in the Plaint.
. ……..
5.2. …. Firstly, the land beneath 9.15 meter road belongs and
is owned by the Plaintiff society. There is an existing road
which the Plaintiff has constructed at its own cost which leads
to the garden which is subject matter of the present Suit. The
land beneath this 9.15 meter wide existing road which is
owned and is in possession of the Plaintiff since last several
years. This private road was constructed pursuant to obtaining
the permissions of statutory authorities. …………………..
For the sake of clarity, the 9.15 meter wide road is an existing
road and is shown as such in the sanctioned D.P. 2034 and the
land beneath belongs to the Plaintiff. Two assertions in the
paragraph under reference in the IA is therefore incorrect and
therefore denied i.e. 9.15 meter wide road is a D.P. Road and
that it belongs to the Government. I deny that the entries in the
Property Card annexed by the Applicant prove or demonstrate
that the ….
5.13. …….. Fourthly, what the Plaintiff describes as 9.15 meter
wide D.P Road is not the suit property in respect of which the
declaration of ownership by adverse possession is sought.”
15/24
901 WP 7981.26+IA.doc Dusane
33. The relevant prayer in the Civil Suit No. 287 of 2025 filed before this
Court are as under :
“(a) That this Hon'ble Court be pleased to declare that the
Plaintiff has perfected its title and has become the owner of the
Suit Property (described in Ex. D) by way of adverse possession,
and any right, title or interest of Defendant No.1 in the Suit
Property (described in Ex. D) has stood extinguished in view of
Section 27 of the Limitation Act, 1963.”
34. Considering the prayers made in the Civil Suit and the statements of
the Petitioner opposing the Intervention Application, in the Civil Suit, it is
clear that the gate and the strip of land in respect of which the Government
has passed the impugned order do not form part of Civil Suit No. 287 of
2025 and thus, the interim order passed in the said Civil Suit does not apply
to the gates / open access land on which the gates are installed.
35. The next issue for consideration is whether the land on which the gate
is installed is allotted to the Petitioner pursuant to the allotment made in the
year 1959 and whether the Collector was required to issue notice to the
Petitioner before directing the removal of the gate, and whether the Collector
had jurisdiction to remove the gate without following the procedure
prescribed under Section 53 of the Maharashtra Land Revenue Code. In this
regard, it is necessary to consider the Petitioner’s claim over the strip of
land, which is a open plot used as an access road.
16/24
901 WP 7981.26+IA.doc Dusane
36. The earliest communication available on record in this regard is the
letter dated 6
th
December 1976 addressed by the Municipal Corporation of
Greater Mumbai to the Petitioner. From the said communication, it is
apparent that the Petitioner’s plot was landlocked and that the proposed 44-
feet-wide D.P. road on the Eastern side connecting the Petitioners’ plot, had
not yet been constructed. Until the said 44-feet-wide D.P. road was
completed, the Petitioner’s landlocked plot required access. Accordingly, the
Municipal Corporation granted temporary access, 30 feet in width, from the
southern road adjoining the open space reservation, through the Government
land. The said access passed through the Government land.
37. The temporary access was granted over the Government land, subject
to certain specific conditions, which are relevant for the present purpose are
set out hereinbelow:
“1) That the Society shall submit a registered undertaking that
they will discontinue this access as soon as the Development
Plan road is constructed.
2) That the temporary access will be constructed and
maintained at their own cost.”
38. Similarly, on record is the communication dated 6
th
March 1978 issued
by the Corporation to the Architect of the Petitioner, which indicates the
modified conditions. However, there was no change in the condition that the
17/24
901 WP 7981.26+IA.doc Dusane
Petitioner shall discontinue the temporary access through the open space
reservation as soon as the 44-feet-wide D.P. road on the eastern side of the
Petitioner’s property is constructed.
39. It is the contention of the Petitioner that the access road was
developed by the Petitioner and is meant for the exclusive use of the
Petitioner. It is not disputed before me that the 44-feet. D.P. road on the
eastern side has been completed and that the Petitioner is utilising the same.
The BMC had also issued a notice to the Petitioner on 6
th
May 2025 for
removal of the gate from the open access. Thereafter, upon a complaint
being made, the State took action to remove the gate from the open access.
40. From the maps produced by the Petitioner and the communications on
record, it is clear that the strip of land is owned by the Government over
which the temporary access was granted, and that it does not form a part of
allotment made to the Petitioner in the year 1959. On perusal of the
impugned order and the maps on record, it is seen that the State is the owner
of the land and that the land is maintained as an open plot and the access
connects to D.P. road on one side and the public road on the other side. The
Petitioner had put up a gate on the access and thereby, sought to exclusively
use the access to the exclusion of others. The subject land belongs to the
Government and is maintained as an access road. The condition of granting
18/24
901 WP 7981.26+IA.doc Dusane
such access to the Petitioner was that, until the eastern-side access to the
Petitioner’s property through the D.P. road was made available, the
Petitioner could use the said access.
41. This Court finds that, by the impugned order, the Collector has not
taken over the access, rather, by removing the gate, the Collector has keft the
access open for utilisation by all persons. The contention of the Petitioner
that the strip of land over which access is provided constitutes an exclusive
access to the Petitioner and that the Petitioner is entitled to put up a gate on
the said access cannot be accepted. It is Government open land over which
the Petitioner has been granted a right of access. It cannot be exclusive to the
Petitioner merely because the Petitioner had constructed a bitumen road on
the same. The Government land with open access cannot be taken in for the
exclusive utilisation of the Petitioner; and by the impugned order, the
Petitioner’s access over the said land has not been stopped.
42. The Petitioner has no right to put up a gate on a access road. The land
belongs to the Government and connects to the D.P. road. The impugned
order indicates that the Petitioner had put up iron gates. The order also
indicates that the said road has not been allotted to any person and that gates
having been unauthorisedly erected. The Petitioner has no right to erect a
gate on the access granted by the Corporation over the Government’s land.
19/24
901 WP 7981.26+IA.doc Dusane
43. Considering the same, the next issue is whether the Collector could
have taken action only by resorting to Section 50 of the Maharashtra Land
Revenue Code. In this regard, the Petitioner has relied upon the judgment of
this Court in the case of Shakuntalabai (supra), wherein this Court has taken
the view that the State has to exercise its powers under Section 53 of the
Maharashtra Land Revenue Code by issuing notice to evict the occupants in
illegal occupation and that, without issuing such notice, the occupants
cannot be held to be illegally occupying the land. An enquiry under Section
53(1)(a) is mandatory, and a reasonable opportunity has to be granted before
taking over possession. Perusal of the judgment of Shakuntalabai (supra)
indicates that the lands were specifically allotted to the predecessor-in-title
of the applicants therein, and they were occupying the plots based on
certificates of Kabala. In those facts and circumstances, the Court proceeded
to observe that there can be no summary eviction of a person unauthorisedly
occupying land vested in the Government without following the procedure
under Section 53.
44. In the instant case, there is no grant of Government land over which
access is permitted to the Petitioner. The Petitioner has merely been
permitted to use the access on the Government land; however, by erecting up
a gate, the Petitioner is excluding others from using the same and converting
20/24
901 WP 7981.26+IA.doc Dusane
the access into a personal space. By removing the gate, the Collector has not
stopped the access of the Petitioner, and the Petitioner continues to be
entitled to use the said access. If there is any interference with the access of
the Petitioner over the subject land, the State shall issue appropriate notice to
the Petitioner; however, the direction to remove the gate and keep the access
open to all cannot be interfered with. The gate impedes access to the general
public.
45. By the impugned order, the Deputy Collector has held as under :
“ IN TH EGCOUGRCFJDEAB JMB YVLPSVWM ABCB .7, सदर
9T812F 0B6 hMYE9B9B eBc aB V0 no-WNV p-W1. 2F/ ११०५ मधील
eBc JMoV vW . -aW Wu�PWMV gaB. तसेच लोखंडी गेट ९.१५
-F6 dAW G,AWdAW kEBPKW WE JMoV ML GCW kGCWYEC r(.२०
मीटर डी. पी. र��याला जोडतो. M1GRBVB hB.WALBPF b ,AW 9T812F 0B6
बस�वला आहे. ML GCW GRWYV. 9T.W1dAW EWN WMW–F 4.EW
.T5WdAWaF -W05FdAW JVOf10WVB YL9B9W VMlAWyB YLMoV ABCB. ता�प
ML G,AWyW JV3v.ृCN5B YEVWN EWVW EWN aTC JMlAWyBaF YLMoV
येते. ,AW-O…B MwUGRCFC JV3v.ृतपणे बस�वले�या गेटचा ताबा
PWMVW.2B :BjV ML hWhC MOYEvW J3v.W a&WVB( राईट ऑफ वे)
qC .T5WyF -W05F kW’ ;WlAWM ,AWJVOf10WVB G,AWyB eBcWhWhC
YV5SA :B5B P'A aT“9.
C F CoCWSM YEfAW1Y.C Y-….CFCF9 JV3v.ृतपणे बस�वले�या
0B6yW ?.Cxz CWhW YLVW1. ([.०३. (t(] T)FNAOC PWMVW.2B
PAWEW E .B llAW .WASEWaFyW MYEGC JaEW9 AW .WAWS9AWM MWL
करावा.”
21/24
901 WP 7981.26+IA.doc Dusane
English Translation of the above-said portion is as under :-
“In accordance with the above-mentioned factual
position, it appears that the area of the land where the said
iron gate has been installed, is the area from out of the land
bearing City Survey No. D / 1105 and the holder thereof is
the Government of Maharashtra. Moreover, the iron gate is
installed at the entrance of a 9.15-meter road, which
connects to a proposed 12.20 meter Development Plan
(D.P.) road. The institution has illegally installed the said
iron gate. It further appears that the said road was neither
allocated for the use of local residents nor granted pursuant
to any demand raised by any party. However, it is observed
that the said road is being used unauthorizedly and without
permission. Therefore, taking possession of the
unauthorizedly installed gate presently by the Government,
will facilitate to take appropriate decisions regarding the
said area of the road, if any demand regarding the right of
way or easementary rights (Right of Way) is received from
any party in the future.
Therefore, for the time being, ex-parte possession of
the illegally installed gate on the property under subject
shall be taken over by the Government by the date
23.03.2026 and a detailed report of the action taken shall be
submitted to this office.”
46. By merely removing the gate, access has been made open, and the
Petitioner’s access has neither been obstructed nor prevented in any manner
contrary to the original arrangement. However, the observation of the
Collector in the impugned order, to the extent that the road over Government
22/24
901 WP 7981.26+IA.doc Dusane
land is being unauthorisedly used, is incorrect. The said road has been in use
with the permission of the Municipal Corporation.
47. The public spaces/access are required to be guarded, especially in
densely populated areas. The access over the Government land should
remain available to the Petitioner as well as to others. Undisputedly, the
gates have been erected at the entrance to the access road connecting to the
D.P. Road. The Petitioner was, at no point in time, granted exclusive
possession of the Government land. The Petitioner was merely granted
access over the said land. However, by erecting gates, the Petitioner has
sought to convert such limited access into an exclusive right of use, thereby
causing prejudice, obstruction and inconvenience to other persons who are
equally entitled to access the said Government land. In such circumstances,
the directions issued for removal of the gates cannot be faulted with and are
fully justified.
48.The Petitioner cannot claim an exclusive right over the access road,
nor can the Petitioner’s access be stopped without issuing proper notice. The
learned AGP has also submitted that the access is kept open to all.
Considering the same, the action of the State, by the impugned order
directing removal of the gates, is not interfered. However, the State shall not
be entitled to grant exclusive use of the road/access to any other party, as the
23/24
901 WP 7981.26+IA.doc Dusane
said access connects the D.P. Road on one side with the public road on the
other side. Accordingly, the said access shall remain open to the Petitioner as
well as to others.
49. Rule is made absolute accordingly.
50. The Writ Petition is partly allowed in the above terms.
[ ARUN R. PEDNEKER, J. ]
24/24
901 WP 7981.26+IA.doc Dusane
BHALCHANDRA
GOPAL
DUSANE
Digitally signed by
BHALCHANDRA
GOPAL DUSANE
Date: 2026.09.10
19:47:30 +0530
Legal Notes
Add a Note....