As per case facts, the plaintiff-society executed reconditioning work for the defendant department after submitting a tender, and the work was completed and approved. Despite this, the department withheld payment, ...
RSA-4237-2010 Page 1 of 22
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
226
RSA-4237-2010(O&M)
Date of decision: 21.07.2025
The Pandori Sidhwan Co-operative Labour & Construction Society Ltd.
...Appellant(s)
Vs.
The Punjab State & Others
...Respondent(s)
CORAM: HON’BLE MS. JUSTICE NIDHI GUPTA
Present:- Mr. Dheeraj Mahajan, Advocate
for the appellant.
Mr. M.S. Teji, AAG Punjab.S
***
NIDHI GUPTA, J.
CM-3389-C-2016
This is an application under Section 41 Rule 27 read with
Section 151 CPC for permission to produce judgment and decree,
Annexures A1 to A4, as additional evidence.
After going through the contents of the application, which is
supported by affidavit of the applicant, the same is allowed, subject to all
just exceptions and Annexures A1 to A4, are taken on record.
MAIN CASE
Present Second Appeal has been filed by the plaintiff against the
judgment of reversal passed by the learned Additional District Judge,
Amritsar thereby allowing the Civil Appeal filed by the
respondents/defendants against the judgment and decree dated 16.12.2008
RSA-4237-2010 Page 2 of 22
passed by learned Civil Judge (Junior Division), Amritsar, decreeing the suit
for recovery filed by the appellant.
2. Brief facts of the case are that the appellant/plaintiff-society is
a Registered cooperative society. The amended suit was filed by the plaintiff
for recovery of Rs.1,46,858/- as amount to be paid by the
respondents/defendants for the works executed by the appellant; along with
interest @ 18% per annum with costs of the suit. It was the pleaded case of
the appellant that the respondents had issued notice inviting tenders in
respect of work order namely “Reconditioning of Amritsar Disty R.D. 615568
to 71750” in response to which the plaintiff had submitted the tender rates.
As rates of the appellant were lowest, the aforesaid work was allotted to the
plaintiff by the defendant department. In that respect a work order No.81,
Book no.47 dated 11.5.2000 with estimate cost of Rs. 1,50,000/ - was issued.
After the allotment of work, the plaintiff started work in right earnest manner
and completed the same subject to the satisfaction of the concerned
authorities/officials of the department as per the terms and conditions of the
work order. The aforesaid work in question was executed within stipulated
period. After completion of the same, the plaintiff requested the department
orally as well as in writing to release the payment of the executed work, but
the department without any sufficient reason and cause did not release the
same despite receiving funds from the higher officials. The plaintiff-Society
accordingly served legal notices dated 27.12.2002 and 28.03.2005 upon the
RSA-4237-2010 Page 3 of 22
respondents. Despite that, Department did not make any payment to the
plaintiff. Accordingly, the plaintiff filed the present suit on 20.05.2005.
3. Upon notice, the defendants appeared and filed written
statement resisting the suit by raising various preliminary objections. On
merits it was averred that payment was not released to the plaintiff as there
were no funds. Respondent department took the stand that work was not
approved and in the absence of contract no work can be legally implemented.
It was further stated that the plaintiff society had offered a tender in respect
of work "Reconditioning of Amritsar Distributory R.D.61558 to 71750” but
the same was not approved by the competent authority of the defendant-
department and plaintiff was never instructed by competent authority to
start the work as work was not allotted to the society. It was also stated that
the alleged work order No.61 book No.47 dated 11.5.2000 was never
executed between the defendant and plaintiff because the same was neither
signed by the then Sub Divisional Officer, Khalra Subdivision, UBDC, Amritsar
nor the same was signed by Approval Authority i.e. defendant No.3.
Moreover, no work order can be legally implemented or enforced unless the
contract is complete i.e. there should be an offer from the department and
acceptance of the contractor. Therefore, the plaintiff society was not
authorised to start the alleged work. It was also submitted that the alleged
work orders bears the signatures of plaintiff but it clearly shows that plaintiff
in-connivance with Sh.Bachan Singh and Sh.Rachhpal Singh (both J.Es. ) had
RSA-4237-2010 Page 4 of 22
got wrongly prepared the alleged work order and thereafter made wrong
entries regarding completion of alleged work in the M.B.s. Denying all other
averments, prayer for dismissal of the suit was made.
4. Replication was filed by the plaintiff wherein all averments of
the written statement were denied and those of the plaint were reiterated.
5. On the basis of pleadings of the parties, following issues were
framed: -
“1. Whether the plaintiff is entitled to a decree for recovery of
Rs.1,46,858/- as prayed for? OPP.
2. Whether the plaintiff is also entitled to interest, if so at what
rate? OPP.
3. Whether the suit is bad for non joinder of necessary parties?
OPD.
4. Whether the plaintiffs have no cause of action to file the
present suit? OPD.
5. Whether the suit is within limitation? OPP.
6. Relief.”
6. Upon appraisal of oral as well as documentary e vidence
adduced by the parties, the learned Civil Judge (Junior Division), Amritsar
vide judgment and decree dated 16.12.2008 decreed the suit of the plaintiff.
Against the above-said judgment and decree of the learned trial Court, Civil
Appeal No.32 dated 28.02.2009 was filed by the respondents. Vide the
impugned judgment and decree dated 06.05.2010, the learned Additional
District Judge, Amritsar has allowed the appeal of the respondents. Hence,
present Second Appeal by the plaintiff.
RSA-4237-2010 Page 5 of 22
7. It is inter alia submitted by learned counsel for the plaintiff that
the learned Lower Appellate Court was in patent error in allowing the
respondents’ appeal as in doing so, it ignored that notice inviting tender
dated 9.3.2000 (Ex.P17) related to 99 items of work including 10 items of
reconditioning of Amritsar distributory. The work orders were prepared on
11.5.2000 and the contractors were instructed to start the work, while formal
approval of the authority has been sought. As the work was of urgent nature,
the works were started by all the tenderers on instructions of the
Department. Approval to the work done by the plaintiff-society was granted
by the Superintending Engineer vide letter dated 4.9.2000 (Ex.P18) approving
estimated cost of work as Rs. 1,46,858/-. The work was completed, and
entries were made in the MB and Bills for any payments that were made.
Liability for the work done is included in the List of Liabilities prepared on
6.1.2003 (Ex. P22). It is contended that once the work has been done, the
plaintiff-Society was entitled to payment for the work done as the same was
never done gratuitously. The trial court decreed the suit holding that the
plaintiff-Society is entitled to payment of the amount for the work done as
per provision of Section 70 of the Contract Act. But the Id. First Appellate
Court has reversed the finding without making reference to any of the
exhibited documents and correspondence, inter se, between the
departmental authorities approving the work done by the plaintiff-society
and entitlement for payment of the work done. Findings of the Additional
RSA-4237-2010 Page 6 of 22
District Judge, therefore, suffer from perversity as material documentary
evidence in the form of Ex.P7 to P24 were completely ignored while reversing
findings recorded by the trial court. The impugned judgment and decree
passed by Additional District Judge, therefore, cannot be sustained.
8. Ld. Counsel further submits that the findings of the Additional
District Judge that the work order and entries in the Measurement book are
not in accordance with the provision of Irrigation Manual of Orders and as
such the plaintiff is not entitled to payment of the work done, cannot be
sustained. It is argued that the preparation of documents is internal
arrangement of the Department. Even if documents are not prepared in
accordance with the Rules, payment of the plaintiff cannot be withheld.
9. It is further submitted by learned counsel for the appellant that
the Additional District Judge further ignored that tender notice was not with
respect to one work, but with respect to 99 different items of work for which
separate tenders for each item had been submitted. Notice inviting tenders
included 10 works relating to reconditioning of Amritsar Distributory; and
plaintiff was allotted work only with respect to one work out of 10. The
departmental authorities have already made payment of work done relating
to other items including reconditioning of Amritsar Distributary. Same
procedure was followed in case of all items of work. In all tenders, work
orders were prepared, approval of estimates were obtained subsequently,
and works started, and on completion of works, payments have been made
RSA-4237-2010 Page 7 of 22
to the contractors. Thus, plaintiff-Society cannot be deprived payment of
work done by it. In this regard, learned counsel for the appellant refers to the
judgments and decrees (Annexure A1 to A4), whereby similar suits as the
present one filed by the similarly placed plaintiffs were decreed. No
appeals/second appeals were filed by the respondents and the said decrees
had attained finality; in pursuance to which, payments have also been
released to the similarly placed plaintiffs. Ld. counsel submits that this fact
has been admitted by the respondents in their reply filed to the above-said
application for additional evidence. It is contended that accordingly, no
ground is made out to deny payment to the plaintiff.
10. It is further contended that the findings of the Additional District
Judge that it is impossible to carry out the work of berm cutting of channel
on 22.7.2000 cannot be sustained. This finding is beyond pleading. It was not
the case of the parties that the work was done after 140 cusecs of water was
left in the channel or it was impossible to carry out the work of berm cutting.
Thus, finding of the Additional District Judge is not only beyond pleading, but
is also beyond evidence and as such cannot be sustained. It is submitted that
therefore, the impugned judgment and a decree cannot be sustained being
contrary to the evidence on record and settled principles of law as also being
beyond the pleadings.
11. Per contra, learned counsel for the respondent-State submits
that the impugned judgment and decree of the learned First Appellate Court
RSA-4237-2010 Page 8 of 22
does not suffer from any infirmity. It is submitted that no doubt, the appellant
had placed on record the Work Order (Ex.PX/2) and Measurement Book
(Ex.PX/3, Ex.PX/10), however, Rules do not approve such like practice and
same is against the provision of Paragraph 1.10 of Chapter-1 of Irrigation
Manual of Orders. It is further submitted that the learned First Appellate
Court correctly opined that it is impossible to carry out any work of berm
cutting of the channel on 22.07.2000 because 140 cusecs of water was
running in the channel of that from it.
12. Learned State Counsel further contends that the plaintiff in
connivance with two JEs namely Bachan Singh and Rachhpal Singh had
executed the work without the sanction of the defendant-Department. It is
submitted that the said JEs have even been charge-sheeted and the amounts
have been subtracted from their salary. It is further submitted that the
learned trial Court in passing the judgment dated 16.12.2008 had not taken
into account the evidence of DW2 and Document (Ex.D2).
13. Learned State Counsel further submits that payments were
released to other persons/plaintiffs similarly situate as the present appellant,
in view of the fact that their Work Orders were found to be genuine. Learned
counsel accordingly prays for dismissal of the present appeal.
14. Learned counsel for the appellant in rebuttal submits that DW1
in his cross-examination has admitted the Work Order as also the Work
executed by the plaintiff. It is further submitted that the submission of
RSA-4237-2010 Page 9 of 22
learned State Counsel that payments have been given to other plaintiffs
because their Work Orders were genuine, is contrary to the evidence led by
the respondents themselves. It is further submitted that the submissions of
the learned State Counsel are beyond the pleadings as the ostensible reason
cited by the respondents for not making payment to the appellant was that
no money was released by the Government. Learned counsel accordingly
reiterates his prayer that present appeal be allowed.
15. No other argument is made on behalf of the parties.
16. I have heard learned counsel and perused the case file in detail.
I have given my thoughtful consideration to the rival submissions made on
behalf of both the parties. I find merit in the submissions made on behalf of
the appellant/plaintiff.
17. The reasons for which the learned Lower Appellate Court has
reversed the findings of the learned trial Court are contained in Para 10 of
the impugned judgment and decree, which reads as follows: -
“10. In order to appreciate the rival contentions, I have gone
through the relevant provisions of the Public Works Department
Code, placed on record by the appellants-defendants
department. Rule 2.79 of Chapter VIII of the said Code title as
"Piece Works" shows that the piece works should be in the form
of works orders. Such agreements are not "Contracts". Sanction
regarding the above said piece works or work orders is not be
given without the prior permission of the Superintending
Engineer or Divisional Officer. In the instant case no sanction has
RSA-4237-2010 Page 10 of 22
been taken from the competent authority i.e. Superintending
Engineer or Divisional Officers. The Sub Divisional Officer has
authority to sanction the work orders only to the extent of
Rs.5000/- and as such the instant work was to be approved by
the Divisional Officer for the latter's counter signatures before
the commencement of the work, as has been mentioned in
paragraph 2.22(4)©. Thus, when the work order was not
approved by the competent authority then the respondent
society was not having any authority to commence or execute
the work in question.”
18. First and foremost, the above said reasoning of the learned
Additional District Judge is unsustainable being beyond the pleadings. It is
no one’s case that the Work Order was a “Piece Work” and not a contract.
The written statement filed by the respondents to the suit reveals that no
objection regarding “Piece Works” was taken by them. In fact, the reason
given by the respondents in the written statement, for not releasing
payment to the appellant was that funds had not been released by the
Government. Nowhere has it been pleaded by the respondents that as per
the Public Works Department Code ‘Piece Works’ are required to be in the
form of work orders and are not ‘Contracts’. As such, in non-suiting the
appellant, the learned 1st Appellate Court has gone beyond the pleadings.
Such a judgment /decree cannot be sustained.
19. The said reason of the learned 1st Appellate Court is also
contrary to the record, and therefore unsustainable. From a perusal of the
RSA-4237-2010 Page 11 of 22
comprehensive documentary evidence produced by the appellant as well
as the respondents it is irrevocably established that defendants had allotted
the Work Order No.81 dated 11.05.2000 to the plaintiff. This fact has been
admitted by DW1 Balwinder Singh (SDO present sting operation) in his
cross-examination that the Work in question was allotted to the plaintiff-
Society by Kulwinder Singh, the then SDO of the defendants-Department.
DW1 has also proved Ex.P22 (wrongly mentioned as Ex.P21 in the
impugned judgments) viz the Official Letter of the respondent-Department
along with the Liability List. In the Liability List dated 6.1.2003/Ex.P-22
(available at page 325 of the LCR), the name of the appellant is found at
item No.36 (at page 331 of the LCR); and it is recorded in the said Liability
List that a sum of Rs.1,46,858/- is due against the appellant and Department
has not yet paid the amount due to non-receiving of funds from the
Government. It is, but trite that if the aforesaid amounts were not due to
the appellant, then why is the name of the appellant and the liability against
him, mentioned in the Liability List. Learned counsel for the respondents is
unable to explain this. DW1 has further proved that the Work allotted to
the plaintiff was never cancelled. DW1 has further stated in his cross-
examination that no Letter was written by the Department to the plaintiff-
Society directing them not to execute the Work or to stop the Work.
Relevant extract of the cross-examination of DW1 Balwinder Singh, SDO
(available at page 179 of the LCR) is reproduced hereinbelow:-
RSA-4237-2010 Page 12 of 22
“The work in question which the plaintiff's society executed,
was executed on the tenure of Sh. Kulwinder singh, the then
SDO of the defendant department after its allotment. I have
seen Ex.P21, the official letter of the deptt. alongwith the
liability list and as per this liability list dated 6.1.2003, a sum of
Rs./1,46,858/- is due and department has not paid yet due to
non receiving of funds from the Govt.It is correct that It is the
sole responsibility of the deptt.to procure the funds of every
work. The tender of this work was called by the deptt. Tenders
are called if there is necessity of the work at the site. It is
correct that before calling the tenders, the report was
submitted by the concerned SDO of the deptt. regarding
necessity of work. I have seen Ex. P12 tender notice on the
court file. Same is correct. Work in question is mentioned at
Sr.no.7 of the tender notice. I have seen Ex P12, Ex. P18, Ex. P13,
Ex. P14 on the court file. Same is correct. Estimate of this work
was 146858/-. I have seen Ex. P9 on the court file regarding
approval of rates by the Higher authorities of the deptt. I have
seen Ex.P10 on court file in which the execution of work was
recorded by concerned official of the deptt. It is correct that
without recording the entry in the measurement book,
payment cannot be made. It is correct that once the entry is
recorded in the measurement book of execution of work, deptt.
is bound to make the payment. It is correct that measurement
book in original always remain in the custody of the concerned
J.E of the deptt. and it is the responsibility of the concerned J.E
to make entry of execution of work in the same. It is further
correct that original work order book always remain in the
custody of the deptt. and it is the responsibility of the
RSA-4237-2010 Page 13 of 22
concerned SDO to sign the same after getting signatures of the
contractor on the work order. No such letter was written by the
local deptt.to the Head office showing the willingness of not
getting the work executed. I cannot say whether the work was
executed as per terms and conditions of the work order or not.
This work order which the deptt. issued in favour of plaintiff's
society was never cancelled thereafter by the deptt. or by the
then SDO till date. No any report was given by the then SDO
regarding the validity of the work order. As per the
departmental record entry the work has been executed by
society. I have seen Ex.P23 on the court file. It bears signature
of Sh. Rakesh Anand then Executive Engineer of Majitha
Division. I have also seen Ex. P24 on the court file. Same is
correct. ………”
20. Thus, from the own evidence of the respondents, it is proved
that the plaintiff has rendered services to the defendants. In this
circumstance, reference may be made to judgment of the Hon’ble Supreme
Court in Food Corporation of India v. Vikas Majdoor Kamdar Sahkari
Mandli Ltd., (SC) : Law Finder Doc ID # 133369; wherein it is held that: -
“A. Contract Act, 1872, Section 70 - A person who does work or
who supplies goods under a contract, if no price is fixed, is
entitled to be paid a reasonable sum for his labour and the
goods supplied.
Xxx
C. Contract Act, 1872, Section 70 - Obligation of person
enjoying benefit of non-gratuitous act - Contractual matters -
RSA-4237-2010 Page 14 of 22
Work done beyond the terms of the Contract - If a party to a
contract has done additional construction for another not
intending to do it gratuitously and such other has obtained
benefit - The former will be entitled to compensation under
Section 70 - The question whether a particular work is extra
will depend upon the terms of conditions of the contract.”
21. Reference may also be made to judgment of this Court in
Market Committee v. M/s. General Trade Supplies, (P&H) : Law Finder Doc
ID # 79538; wherein it is held that:-
“C. Contract Act, Section 70 - Punjab Agricultural Produce
Markets Act, 1961, Section 22 - Breach of contract -
Compensation for breach of contract - Irrespective of the fact
that legally no contract was executed between the parties, the
compensation under Section 70 of the Contract Act is to be
granted on the basis of fact that something done by a party for
another has been voluntarily accepted by the other party - The
accepting party have to compensate the other for the work
done.”
22. Thus, the legal position is very clear that irrespective of
whether any contract was executed between the parties, all that has to be
seen is whether any services have been rendered by the contractor. If yes,
contractor is liable to be compensated for the work done. The aforesaid
case laws apply ipso facto to the facts of the present case. The reasoning of
the learned Lower Appellate Court that as the Work Order in question was
not sanctioned/approved by the Authority, and therefore, the
RSA-4237-2010 Page 15 of 22
appellant/Society was not having any authority to commence/execute the
work, is ill-founded in view of the above-said judgment of the Hon’ble
Supreme Court. Moreover, in this regard reference may be made to Ex.P11
(wrongly mentioned as Ex.P13 in the judgment of the Lower Court dated
04.09.2000; and available at page 271 of the LCR) issued by the
Superintendent Engineer to the Executive Engineer giving approval to the
Work Order allotted to the plaintiff.
23. Learned counsel for the respondent-State has relied upon the
evidence of DW2 Harjeet Singh (concerned SDO of the Work). However,
even Harjeet Singh in his cross-examination has admitted the document
(Ex.P13) which is the attested copy of the Estimate of Work in question,
which was passed by the Department. DW2-Harjit Singh also admitted in
the cross-examination that he did not sign the work order due to its non-
sanctioning, however further admitted that the estimate of this work was
later on sanctioned by the Chief Engineer and this fact is crystal clear from
the approval of rates on 21.03.2002 Ex.P9 whereas the work order Ex.P8 is
dated 11.05.2000. However, this evidence has been ignored by the learned
1st Appellate Court. In fact, a perusal of the impugned judgment and decree
of the First Appellate Court also shows that there is no discussion on the
voluminous documentary evidence adduced by the plaintiff.
24. Learned counsel for the respondents-State has stated that
payments were made to persons similarly placed as the present plaintiff, as
RSA-4237-2010 Page 16 of 22
their Work Orders were found to be in order. However, record reveals that
the stand of the respondents-State in not releasing payments to the
plaintiff is that funds had not been released from the Government. As such,
there is also discrimination against the present plaintiff. The said argument
of the respondents is also misconceived in view of the above referred
Ex.P11 issued by the Superintendent Engineer to the Executive Engineer
giving approval to the Work Order allotted to the plaintiff. Even otherwise,
there is no truth/correctness to the above stand of the respondent – State.
The plaintiff/appellant has filed CM No.3389-C of 2016 for additional
evidence in which the notice was issued by this Court on 31.03.2016 for
bringing on record certified copies of judgments and decrees passed in the
suits filed by identically situated societies who executed the same work and
were denied payment by the department by taking a similar stand. In
similar cases, it is clarified as follows: –
25. In respect of work pertaining to RD No. 71750 to 81500 which
is a part of same tender notice dated 09.03.2000 Ex.P17, work was allotted
to the Bhojian Cooperative Labour and Construction Society Limited. Civil
Suit No.273 dated 26.11.2007 was duly decreed on 07.01.2013. No further
appeal has been filed and rather the appeal filed by the concerned society
claiming the grant of interest from the date of suit till its realization was
allowed vide judgment and decree dated 17.02.2014 by the learned ADJ,
Amritsar and the payment has also been released to the said society.
RSA-4237-2010 Page 17 of 22
26. Similarly in case of Gandiwind Cooperative Labour and
Construction Society Limited filed civil suit.No.219/2009 in respect of work
for RD No.93308 to 100980 which was duly decreed on 15.11.2011 and
further appeal filed by the department was also dismissed on 02.02.2013.
27. The identically situated society Thathgarh Labour and
Construction Society Limited filed civil suit No.346 of 2009 which was also
decreed on 06.02.2013 and no further appeal was filed by the State.
28. The certified copies of the judgment are perse admissible and
the same clearly demolishes the stand of the department and further
shows how the plaintiff has been discriminated by the department with
respect to the amount to which he is lawfully entitled in respect of the work.
29. Relevant findings of the learned trial Court are contained in
Para 16 of the judgment dated 16.12.2008, which reads as follows: -
“16. The defendant department invited tenders in respect of
work namely "Reconditioning of Amritsar Disty RD 61558 to
71750". The plaintiff submitted the tender rates and after
found to be lowest the work was allotted to the plaintiff by the
defendant department in respect of work under No.81, Book
No.47, dated 11.5.00, with estimate cost of Rs. 1,50,000/-
issued/ executed. The work was executed within stipulated
period of time and after that plaintiff requested the defendant
for payment, but the defendant did not release the same. The
President of Society proved on record resolution Ex.P1, legal
notice served by the Society upon the defendant Ex.P2,
acknowledgment Ex.P3, postal receipts Ex.P4 to Ex.P6, another
RSA-4237-2010 Page 18 of 22
notice Ex.P7, work order Ex. P8. The document Ex.P8
apparently shows that the work executed by Pandori Sidhwan
Society - plaintiff or "Reconditioning of Amritsar Disty RD
61558 to 71750. The plaintiff has also proved official letter of
defendant deptt. Ex.P9, entries made in the M.B. Ex. P10 which
reveals that the name of the plaintiff company figure in this
document which the document of defendant department letter
Ex.P11 written by the Superintendent Engineer to Executive
Engineer dated 4.9.00 estimate of work by the department
Ex.P12 passed by the defendant, Ex.P13 and estimate for
reconditioning of Amritsar disty. RD 61558 to 71750 Ex.P14.
This witness also proved representation dated 12.6.04
submitted to the defendant Ex.P15, letter dated 17.12.2003 ex.
P16, attested copy of tender notice Ex. P17, attested copy of
representation dated 4.9.00 Ex.P18, representation dated
12.8.04 Ex. P19, letter dated 17.12.03 Ex.P20 and letter No.645
Ex.P21 and liability Chart Ex. P22, Other witness PW2 Bachan
Singh proved that the defendant department executed the
work to the plaintiff. From the perusal of document produced
by the defendant as well as evidence produced by the plaintiff
reveals that the defendant had allotted the work order No.81
dated 11.5.00 to the plaintiff. Ld. counsel for the plaintiff
contended that work in question was allotted by the defendant
to the plaintiff society and the same has been executed well
within time. The defendant witness i.e. DW1 Balwinder Singh
in his cross examination has admitted that the work in question
was executed to the plaintiff society by Sh.Kulwinder. Singh, the
then SDO of defendant department. Meaning thereby, this
witness has admitted this fact that the defendant had executed
RSA-4237-2010 Page 19 of 22
the work to the plaintiff company. The witness also proved
Ex.P21 i.e. official letter of the department alongwith the
liability list and as per this liability list dated 6.1.2003, a sum of
Rs. 1,46,658/- is due and department has not paid yet due to
non receiving funds from the Govt. This witness has
categorically stated in his cross examination that the tenders
are called and the report regarding this was submitted to the
SDO of the department. He also proved Ex.P12 tender notice.
He further deposed that the work the question is mentioned of
Sr.No.7 of the tender notice. He also proved document Ex. P12,
Ex.P18 Ex.P13 and Ex.P14. This witness also admitted that
estimate of this work was 1,46,858/-. This witness also proved
document Ex.P11. This witness also proved that the work
allotted to the plaintiff never cancelled till today. This witness
also proved documents Ex.P24 and Ex.P23. This witness also
specifically stated in his cross examination that no letter was
written by the department to the society not to execute the
work or to stop the same. Therefore, it is admitted that plaintiff
had rendered service to the defendant and plaintiff had
executed the work in question. DW2 Harjit Singh in his cross
examination also admitted the document Ex. P13 and Ex.P14
which is related to his department. This witness also admitted
the approval of rates.
Ld. counsel for the plaintiff has also placed reliance upon the
authoritative pronouncement 2005(1) RCR (Civil) pg.19 titled
as Market Committee and another Vs. M/s. General trade
Supplies in which it is held that "Contract Act Section 70-Punjab
agricultural Produce Markets Act, 1961, Section 22-Breach of
contract-Compensation for breach of contract-irrespective of
RSA-4237-2010 Page 20 of 22
the fact that legality no contract was executed between the
parties, the compensation under section 70 of the Contract Act
is to be granted on the basis of fact that something done by a
party for another has been voluntarily accepted by the other
party-The accepting party have to compensate the other for
the work done."
It is also clear under this decision that if in pursuance of the
said void contract, the plaintiff has performed its part and the
defendants have received the benefit of the performance of
contract by the plaintiff, section 70 of the contract Act would
justify the claim made by plaintiff against the defendants.
Section 70 of the Contract Act enables, the person who actually
supplies goods or renders services not intending to do so
gratuitously to claim compensation from the person who
enjoys the benefit of the supply made or services rendered. It
is the liability which arises on equitable grounds even through
express agreement or a contract may not be proved. I rely upon
the case law cited supra by plaintiff. In the present case, the
plaintiff society has lawfully rendered services by the
defendants department while rendering such services, the
plaintiff society was not intending to act gratuitously and the
defendant department had received services of the plaintiff.
Therefore, in terms of the previsions of section 70 of the
contract Act, the defendants department have liability to
compensate the plaintiff society with the price of work in
question. The plaintiff society has claimed interest 18% p.a. on
the amount, but the aforesaid interest is exorbitant and is not
reasonable. The plaintiff has the failed to prove any
documentary evidence in this regard. Therefore, plaintiff is
RSA-4237-2010 Page 21 of 22
entitled to interest @ 9% p.a. on amount of Rs. 146858/-.
Therefore, finding on the above-said issues is returned in
favour of the plaintiff and against the defendants.” (emphasis
added).
30. Thus, even if the contract was not signed by the Sub-Divisional
Officer, however, the attendant circumstances show that the appellants had
executed the work in question as is clear from the Measurement Books on
record, duly approved by the JEs of the Department. From the evidence led
by the plaintiff it categorically stands proved on record that the work was
allotted, which was duly executed by the appellant, entitling them to claim
the amount of the executed work in terms of Section 70 of the Contract Act.
Even the entire case of the plaintiff has been admitted by the
defendant/witnesses in their cross examination. As such, the appellant-
Society is entitled to receive payment in lieu of the work done by them as
held by the Hon’ble Supreme Court in the above-cited judgment. A perusal
of the impugned judgment and decree of the First Appellate Court shows
that there is no discussion on the voluminous documentary and other
evidence adduced by the plaintiff.
31. Keeping in view the above-said factual and legal position,
present Second Appeal stands allowed. Suit of the plaintiff is decreed; and
the plaintiff is held entitled to recover Rs.1,46,858/- from the defendants
along with interest @ 6% per annum from the date of institution of suit till
realisation.
RSA-4237-2010 Page 22 of 22
32. Pending application(s) if any also stand(s) disposed of.
21.07.2025 (Nidhi Gupta)
Sunena Judge
Whether speaking/reasoned: Yes/No
Whether reportable: Yes/No
Legal Notes
Add a Note....