As per case facts, the respondents entered into three contracts with the appellant, each containing an arbitration clause. Disputes arose before full execution, leading to three new settlement contracts. The ...
No Acts & Articles mentioned in this case
S.C.R. SUPREME COURT REPORTS
THE UNION OF INDIA
v.
KISHORILAL GUPTA AND BROS.
493
(.JAFER !:MAM, A. K. SARKAR and K. SuBBA RAO, JJ.)
Contract--Arbitration clause-Cancellation of contract-Settle
ment of disputes by mutual agreement-Arbitration clause, if sur
vives-Award
based on such
clause-Validity;
The respondents entered into thre~ several contracts with
the appellant, for the fabrication and supply
of diverse military
stores, each
of which contracts contained an arbitration clause.
Before the contracts had been fully executed disputes arose
between the parties, one alleging
that the other was committing
a breach
of the contract. The parties then entered into three
fresh contracts on successive dates purporting to settle these
dis
putes on the terms therein contained. By the first two of
these settlement contracts the respondents agreed to pay to the
appellant certain moneys in settlement respectively
of the
dis
putes relating to the first two original contracts. By the last
of these settlement contracts the respondents agreed to pay to
the appellant in specified instalments certain moneys in settle
ment
of the disputes relating to the third original contract as
also the moneys which had then become due on the first two
settlement contracts and had not been paid and further under
took to hypothecate certain properties to secure the due repay
ment
of these moneys. The third settlement contract provided:
"The contracts stand' finally concluded in terms of the settle
ment and
no party will have any further or other claim against
the
other."
The respondents paid some of the instalments but failed to
pay the rest. They also failed to create the hypothecation. The
appellant then referred its claims for breach
of the three origi
nal contracts to arbitration under the •arbitration clauses con
tained in them.
On this reference an award for a total sum of
Rs.
1,16.446-n-5 was made against the respondents in respect of
the appellant's claim on the first and the third original contracts,
the claim in respect
of the second original contract having been
abandoned by the appellant, and this award was filed in the
High Court
at
Calcutta. The respondents applied to the High
Court for a declaration
that the arbitration clauses in the original
contracts had ceased to
have any effect and the contracts stood
finally determined as a result
of the settlement contracts and
for
an order setting' aside the award as void and nullity. The
High
Court held that the first original contract had not been
abrogated by the settlement in respect of it,
but the third original
contract and the arbitration clause contained in
it had ceased to
exist as a result
of the last settlement and the arbitrator had no
jurisdiction to arbitrate under
that arbitration clause.
It further
63
494 SUPREME COURT REPORTS [1960\l)]
z95~ held that as the award was a single and inseverable award the
whole of it was null and void. In this view the High Court set
The Union of India aside the award.
v. Held (per Imam and Subba Rao, JJ., Sarkar J .. dissenting),
Kishorilal Gupl• that the third settlement, properly construed, left no manner of
& Bros. doubt that it was for valid consideration and represented the
common intention of the parties to substitute it for the earlier
contracts between them. It gave rise to a new cause of action by
obliterating the earlier cocytracts and the parties could look to it
alone for the enforcement of their claims. There could, there
fore, be no question that the arbitration clause which, whether a
substantive or a collateral term, was nevertheless an integral
part of the said contracts, must be deemed to exist along with
them as a result of the said settlement.
Hirji Mulji v. Cheong
Yue Steamship Company, [1926]
A.C. 502 and Heyman v. Darwin Ltd., [1942] l All E.R. 337,
referred to.
Tolaram
Nathmull v. Birla Jute Manufacturing Co. Ltd.,
I.L.R. (1948) 2 Cal. 171, distinguished.
Held, further, that it was well settled that the parties to an
original contract could by mutual agreement enter intoa new
contract in substitution of the old one.
Payana Reena
Saminathan v. Pana Lana Palaniappa, [1914]
A.C. 618: Norris v. Baron and Company, [1918] A.C. land British
Russian Gazette and Trade Outlook Ltd.
v.
Associated Newspaper,
Limited,
[1933] 2 K.B. 616, referred to. Per Sarkar, J.-The award was valid and could not be set
aside as the third settlement neither expressly put an end to the
arbitration clause nor, considered as an accord and satisfaction,
did it have that effect.
An accord
and satisfaction is only a ·method of discharge of
a contract.
It does not annihilate the contract but only makes
the obligation arising
fro~ it unenforceable.
An arbitration clause stands
apart
froµi the rest of the
contract in .which it is contained. It does not impose on the one
plty an obligation in favour of the other; it only embodies an
agreement that if any dispute arises with regard to any obliga
tion which one party has undertaken to the other, such dispute
shall
be settled by arbitration. An accord and satisfaction,
which is concerned with the obligations arising from
the contract,
does
not affect an arbitration clause contained in it.
Heyman v. Darwins [1942] A.C. 356 and British Russian
Gazette and Trade Outlook Ltd. v. Associated Newspapers Ltd. [1933]
2 K.B. 616, referred to. ' .
The settlement of February 22, 1949, did not, 'in the circum
stances of the case, amount to an accord and satisfaction.
Civu. APPELLATE JURISDICTION: Civil Appeal No.
250of1955.
S.C.R. SUPREME COURT REPORTS 495
Appeal
by special leave from the
order dated February 11, 1953, of the
Court, in Award No. 254 of 1949.
judgment
and z959
Calcutta High T'-u -. -
1
_ _,.
-mono [,...•a
H. N. Sanyal, Additional Solicitm·-General of India,
B. Sen, R. H. Dhebar and T. M. Sen, for the
appellant.
0. B. Aggarwala and Sukumar Ghose, for the respond
ent.
1959. May 21.
The judgment of Jafer Imam and
Subba Rao, JJ., was delivered by Subba Rao, J.
Sarkar, J., delivered a separate judgment.
v.
K islwrilal Gupta
IS-Bros.
SUBBA RAO J.-This appeal by 'special leave raises SubbaRao J.
the question of survival of an arbitration clause in a
contract after the said contra.ct is superseded by .a
fresh one. The respondent-firm, styled as " Kishorilal
Gupta & Brothers", entered into the following three
contracts with
the Governor-General-in-Council
through the Director General oflndustries and
Supplies,
hereinafter called the Government : (i) contract dated
April 2, 1943, foi: the supply of 43,000 "Ladles Cook" ;
(ii) contract dated September 15, 1944, for the supply
of 15,500 "Bath Ovals"; and (iii) contract dated
September 22, 1944, for the supply of 1,00,000 "Kettles
Camp". Each of the said contracts contained an
arbitration clause, the material part of which was as
follows:
" In the event of any question of dispute arising
under these conditions
or any special
·conditions of
contract or in connection with this contract (except
as to any matters the decision of which is specially
provided for by these conditions)
the same shall be
referred
to the award of an arbitrator to be
nomi
nated by the purchaser and an arbitrator to be
nominated
by the contractor ........
"
Under the terms of the said three contracts, the
Government supplied certain raw-materials to the
respondents and the latter also delivered some of the
goods to the former. On May 21, 1945, the contract
dated April 2, 1943, hereinafter called the first contract,
was cancelled by the Government. The Government
496 SUPREME COURT REPORTS [1960(1)]
z959 also demanded cerlain sums towards the price of the
~·-u -. -,,
1
a· materials supplied by them to the respondents. On
""~ ttionoJ n io
v the same day, the Government cancelled the contract
Ki•horil~ Gupta dated September 15, 1944, hereinafter called the second
.s-B,.., contract, and made a claim on the respondents for the
price of the raw-materials supplied to them. The
Svbba Raa J. respondents made a counter-claim against the Govern
ment for compensation for breach of the contract. On
March 9, 1946, the Government cancelled the contract
dated September 22, 1944, hereinafter called the third
contract. Under that contract there were mutual
claims-by the Government for the raw-material
supplied to the contractors and by the latter for
compensation for breach
of contract. The disputes
under the three contracts were amicably settled. The
outstanding disputes under the first and the second
contracts were settled on September 6, 1948, and two
separate documents were executed to evidence the said
settlement. As the decision, to some extent, turns
upon the comparative study of the recitals in the said
documents
of settlement, it will be convenient to read
the material part of the recitals contained therein.
The settlement in respect of the first contract
contain
ed the following reCitals :
"(1) The contractor expressly agrees to pay the
Government the sum of'Rs. 3,164-8 as. only on this
contract.
(2) The contract on payment of the amount men
tioned in clause (1) shall stand finally determined."
The recitals in the settlement of the second contract
are as follows :
"(1) The ccmtract9r expreHsly agrees to pay to
the Government the sum of tis. 36,276. If D. G. I.
&. S. has recovered any amount under the contract
out of the sum due credit will be given to the con
tractor.
(2) The contract stands finally determined and no
party will have any further claim against the
oth-er."
One prominent difference in the phraseology used in
the two settlements may be noticed at this stage.
S.C.R. SUPREME COURT REPORTS 497
While under the settlement of the first contract, the z959
contract should stand finally determined only on pay-Th ri .-
11 4
.
d b
"d h G t nion o n ••
ment of the a.mount agree to e pa1 to t e overn- v.
ment by the contractor, under the settlement of the Kisllorilal Gupta
second contract, the contract stood finally determined & Bros.
on the date of the settlement itself. The third contract
was settled on February 22, 1949,
and the material
Subba Rao J.
part of the recitals therein is as follows :
"(1) The firm will pay a sum of Rs. 45,000 in full
and final settlement of the amount due to the
Government in respect of raw mat.erials received
against
the contract and their claims for compensa
tion for cancellation
of the same contract.
(2) The firm will retain all surplus partly fabric
ated and fully fabricated stores lying with them.
(3) The firm agrees to pay the abovementioned
sum
of Rs.
45,000 only together with the sums owing
by them to the Government under the settlements
reached in two other cases A/T Nos. MP/75762/R-61/
78 dated 15th September 1944 and MP/50730/8/R-l/
90 dated 2nd April 1943 in monthly instalments for
Rs. 5,000 only for the first three months, first instal
ment being payable on 10th March, 1949, and further
instalments
of Rs.
9,000 per month till the entire
dues payable
to Government are paid.
(4) In the event of default of any monthly instal
ments interest will
b~ charged by Government on the
amount as defaulted at the rate of 6% per annum
from the first day of the month in which the instal
ment shall be due. If the instalments defaulted
exceed two in number
the Government will have the
right to demand the entire
~ala.nee of the money
payable
by the firm together with interest thereon
at the rate abovementioned on that balance and
take such steps to recover from them from the
security to be offered.
(5) In order to provide cover for the money
p'ay
able to the Government the firm undertakes to
hypothecate their moveable and immoveable pro
perty in Bamangachi Engineering Works together
with all machinery sheds
and leasehold interest in
498 SUPREME COURT REPORTS [1960(1))
I959
The Union of India
land measuring about 5·75 acres in Mouja Bamung
achi in Howrah. The firm further undertakes to
execute the necessary stamped documents for the
v.
K ishorilal Gupta
&Bros.
Subbo Rao].
purpose as drafted by the Government Solicitor at
Calcutta.
(6) The contracts stand finally concluded in terms
of the settlement and no party will have further or
other claim against the other."
Broadly speaking, this settlement was a comprehen
sive one including therein the earlier settlements and
providing for the recovery of the amounts agreed to
be paid under the said two earlier settlements. The
concluding paragraph is more analogous to that of
the settlement of the second contract rather than that
of the first. Under the final settlement, between
Ortober 28, 1948, and January 17, 1949, the respond
ents paid a total sum of Rs. 9,000 to the Government
under the first two settlements of the contracts. Bet
ween March 10, 1949, and October 31, 1949, the res
pondents paid a total sum of Rs. 11,000 in instalments
to the Government, though the amounts paid were less
than the amount payable in accordance with the
agreed instalments. Some correspondence passed
between
the Government and the respondents, the
former demanding the balance of the amount
pay
able under the instalments and the latter putting it off
on one ground or other. Finally on August 10,
1949, the Government wrote a letter to the respond
ents demanding the payment of Rs. 1,51,723 payable
to them under the three original contracts, ignoring
the three settlements. The Government followed that
letter with another one of the same date informing
the respondents that they had appointed Bakshi Shiv
Charan Singh as their arbitrator and calling upon the
respondents to nominate their arbitrator. The res
pondents did not co-operate in the scheme of arbitr
ation and instead Kishori Lal Gupta as sole prop
rietor of the respondent-firm made an application
under s. 33 of the Arbitration Act, 1940, in the Origi
nal Side of the High Court of Calcutta for a declara
tion that the arbitration agreement was no longer
in existence. That application was dismissed by
S.C.R. SUPREME COURT REPORTS 499
Banerjee, J., of the said High Court on the ground that r959
it was not maintainable as the two other partners of -
the respondent-firm were not made parties to the said The Union of India
proceeding. But in the course of the judgment, the Kishori;~ 1 Gupta
learned Judge made some observation on the merits &·Bros.
of the case. Thereafter the Government filed their
statement ~ffacts before the arbitrator and the respond-Subba Rao /.
ents filed a counter-affidavit challenging the arbitr-
ator's jurisdiction and also the correctness of the
cla,ims made by the Government. On July 31, 1951,
the arbitrator made an award in favour of the Govern-
ment for a
total sum of Rs. 1,16,446-11-5 in respect
,of
tne first aud the third contracts and gave liberty to
the Government to recover the amount due to them
under the second contract in a suit. The award was
duly filed
in the High
Court, and, on receiving the
notice, the respondents filed an application in the High
Court for setting aside the award and in the alter-
native for declaration that the arbitration clause in
the three contracts ceased to have any effect and stood
finally determined
by the settlement of the disputes
between
the parties. Bachawat, J., held that the first
contract was to be finally determined only on payment
in terms of the settlement, and, as such payment was
not made, the original contract and its arbitration
clause continued to exist. As regards the third con-
tract,
the learned Judge came to the conclusion that
by the third settlement, there was accord and satis-
faction
of the original contract and the substituted
agreement discharged
the existing cause of action and
therefore
the arbitrator had no jurisdiction to entertain
any claim with regard to that contract. As the a.ward
on
the face of it was a lump sum award, the learned
Judge lield that it was not severable and therefore the
whole award
waw bad. In the result, he gave the
declaration that the arbitration clause contained in the
contract dated September 22, 1944, for "Kettles Camp"
had ceased to exist since the settlement con tract dated
February 22, 1949, and that the entire award was void
and invalid. The present appeal by special leave was
filed
by the Government against the said order of the
High
Court.
500 SUPREME COURT REPORTS [1960(1)]
'959 At the outset, a preliminary objection taken by
The Union of India Shri Aggarwal, the learned Counsel for the respond-
v. ents, may be disposed of. The learned Counsel contends
Kishorilal GuP•• that the special leave granted by this Court should be
o;. Bros. revoked on the ground that an appeal Jay against the
order of the learned Judge to an appellate bPnch of
St4bbaRAoj. H h C b h 1 f L
the same ig ourt ot under c . 15 o the etters
Patent and s. 39 of the Arbitration Act. It is not, and
cannot be, contended that this Court has no jurisdic
tion to entertain an appeal against the order of a Court
when an appeal lies from that order to another Court.
The provisions of Art. 136 of the Constitution are not
circumscribed by any such limitation. But what is
argued,
in our view legitimately, is that when an
appeal lay to the appellate bench of the
Calcutta High
Court, this Court should not have given special leave
and thereby short-circuited the legal procedure pres
cribed. There is much force
in this argument.
lf'the
application for revoking the special leave had been
taken at the earliest point of time and if this Court
was satisfied that an appeal lay to an appellate bench
of the Calcutta High Court, the leave obtained without
mentioning that fact would have been revoked. But
in the present case, the special leave was granted on
March 29, 1954, and the present e.pplication for revok
ing the leave \'\'as made five years after the grant of
special leave and the learnad Counsel could not give
any valid reason to explain this inordinate delay. In
the circumstances, if we revoked the special leave, the
appellant would be prejudiced, for if this objection
had been taken at the earliest point of time, the ap
pellant would have had the opportunity to prefer a
Letters Patent appeal to the appellate bench of tl;ie
Calcutta High Court. The appellant cannot be made
to suffer for the default of the respondents. In the
circumstances, we did not entertain that application
for revoking the special leave and did not express our
opinion on the merits of the question raised by the
learned Counsel.
Now coming to the merits, the main contentions of
the parties may be stated at the outset. The argu
ment of the Additional Solicitor-General for the
S.C.R. SUPREME COURT REPORTS 501
appellant may .be summarized in the following pro- z959
positions: (1) The jurisdiction of the arbitrator depends -. - .
upon
the scope of the arbitration agreement or sub- The
Union of Ind
11
•
mission ; (2) its scope would depend upon the language Kishori;~ 1 Gupt
11
of the arbitration clause ; (3) if the arbitration agree-& Bros.
ment in question is examined, it indicates that the
dispute whether the original contracts have come to Subba Rao J.
an end or not is within its scope; (4) on the facts of
the case, there had Qeen no novation or substitution
of the original contracts; and (5) if there had been a
novation
of the original contracts, the non-perform-ance of the terms of the new contract revived the
original contracts and therefore the parties to the
original contracts could enforce their terms including
the arbitration clause. The submission of Shri Aggar-
wal, Counsel for
the respondents, may be stated thus :
(1)
Upon the facts of the case, there had been a reces-
sion
of the old contracts and substitution of a new,
legally enforceable
and unconditional contract, which
came into immediate effect;
(2) the new contract can
be legally supported either under
s. 62 or s. 63 of the
Indian Contract Act or under the general law of con-
tracts; (3) the non-performance of the terms of the
new contract did not have the effect of reviving the
rights and obligations under the old contracts as they
did not remain alive for any purpose ; and (6) even if
the arbitration clause did not remain alive after the
new contract, the
-arbitrator was bound to decide the
case in terms of the new contract, and he having not
done so,
the error is apparent on the face of the
record
and therefore the award is liable to be set aside.
So
stated the controversy covers a much wider field
than that necessary to solve the problem presented in
this case. It would, therefore,
be·convenient at this
stage to clear the ground. Subtle distinctions sought
to be made between the provisions of s. 62 and s. 63 of
the Indian Contract Act need not detain us ; nor need
we consider
the question whether the
settlepient con
tract in question falls under s. 62 or is covered by s. 63
of the Indian Contract Act, or is governed by the
general principles of the law of contracts, for the
validity of the said contract is not questioned by either
64
502 SUPREME COURT REPORTS [1960(1)]
z959 party and indeed both rely upon it-one to contend
Th• u .
11
d. that it wholly superseded the earlier ones and the
nio;
0
n "'other to rely upon its terms to bring out its contingent
m,horilal Gupta character. If so, the only two outstanding questions
& Bros. are: (i) what is the legal effect of the contract dated
February 22, 1949, on the earlier contracts? ; and (ii)
Subba Rao f. does the arbitration clause in the earlier contracts
survive
after the settlement contract ?
The law on the first point is well-settled.
One of the
modes by which a contract can be discharged is by the
same process which created it, i.e., by mutual agree
ment; the parties to the original contract may enter into
a. new contract in substitution of the old one. The legal
position was clarified
by the Privy
Council in Payana
Reena Saminathan
v. Pana Lana Palaniappa (
1
). Lord
Moulton defined the legal incidents of a substituted
contract in
the following terms at p. 622:
"The 'receipt' given by the appellants, and
accepted by the respondent, and acted on by both
parties proves conclusively that all the parties
agreed
to a settlement of all their existing disputes
by the arrangement formulated in the 'receipt'. It
is a clear example of what used to be well known in
common law pleading as
"accord and satisfaction
by a substituted agreement". No matter what were
the respective rights of the parties inter se they are
abandoned in consideration of the acceptance by all
of a new agreement. The consequence is that when
such
an accord and Batisfaction takes place the prior
rights of the parties are extinguished. They have
in fact been exchanged for the new rights; and the
new agreement becomes a new departure, and the
rights of all the parties arc fully represented by it.
"
The House of Lords in Norris v. Barcrn and Company(•)
in the context of a contract for sale of goods brought
out clearly the distinction between a contract which
varies
the terms of the earlier contract and a contract
which rescinds the earlier one, in the following passage
at p. 26: " In the first case there are no such executory
clauses
in the second arrangement as would enable. (1) [1914] A.C. 618, 622. (2) [1918] A.C. 1. 26.
S.C.R. SUPREME COURT REPORTS 503
you to sue upon that alone if the first did not exist; x959
in the second you could sue on the second arrange- TL u . ,
1
d"
1 d h fi
, 'd f . h ne nion o, n "'
ment a one, an t e rst contract is got n o e1t er v.
by express words to that effect, or because, the Kisharilal Gupta
second dealing with the same subject-matter as the & Bras.
first but in a different way, it is impossible that the
two should be both performed. " Subba Rao J.
Scrutton, L.J., in British Russian Gazette and Trade
Outlook Limited v. Associated Newspaper, Limited (
1
),
after referring to the authoritative text-books on the
subject, describes the concept of " accord and satisfac
tion " thus at p. 643 :
" Accord and satisfaction is the purchase of a
release from
an obligation whether arising under
contract or
tort by means of any valuable
considera
tion, not being the actual performance of the
obligation itself. The accord is the agreement by
which the obligation is discharged. The satisfaction
is
the consideration which makes the agreement
operative. Formerly
it was necessary that the
consideration should be executed . . . . . . . . . . Later
it was conceded that the consideration might be
executory . . . . . . . . .
The consideration on each side
might be
an executory promise, the two mutual
promises making an agreement enforceable in law,
a contract . . . . . . . . . ' An accord, with mutual
promises
to perform, is good, though the thing be
not performed at the time of action; for the party
has a remedy to compel the performance', that is to
say, a cross action on the contract of accord ...... .
If, however, it can be shown that what a creditor
accepts in satisfaction is merely his debtor's promise
and not the performance of that promise, the
original cause of action is discharged from the date
when
the promise is
made."
The said observations indicate that an original cause
of action can be discharged by an executory agreement
if the intention to that effect is clear. The modern
rule is
stated by Cheshire and Fifoot in their La.w of Contract, 3rd Edn., at p. 453:
"The modern rule is, then, that if what the
creditor has accepted in satisfaction is merely his
ll) [1933] a K.B. 616, 643, 6,H·
TM Union of India
"·
Kishorilal Gupta
cS-B1os.
Subba Rao].
504 SUPREME COURT REPOltTS [1960(1))
debtor's promise to give consideration, and not the
performance of that promise, the original cause of
action is discharged from the date when the agree
ment is made.
This, therefore, raises a question
of construction
in each case, for
it has to
'be decided as a fact
whether
it was the making of the promise itself or
the performance of the promise that the creditor
consented
to take by
way of satisfaction. "
So too, Chitty in his book on Contracts, 31st Edn.,
states
at p. 286 :. "The plaintiff may agree to accept the perform
ance of a substituted consideration in satisfaction,
or he
may agree to. accept the
promise of such
performance.
In the former there is no satisfaction
until performance,
and the debtor remains liable .
upoI the original claim until the satisfaction is
executed. .
In the latter, if the promise be not
performed, the plaintiff's remedy is by action for the
breach of the substituted agreement, and he has no
right of resort to the original
claim." _
From the aforesaid authorities it is· manifest that a
cont.ract may be discharged by the parties thereto by
a substituted agreement and thereafter the original
cause
of action arising under the earlier contract is
discharged
and the parties are governed only by the
terms of the substituted contract. The ascertainment of
t>he intention of the parties is essent.ially a question of
fact to be decided on the facts and circumstances of
each case.
We
have already given the sequence of event.a that
led to the making of the contract dated February 22,
194!). To recapitulate briefly, the original three
contracts were cancelled bv the Government on
May 21, 1945, May 21,
1945, and Match 9, 1946,
respectively. Under the first contract, the Govern
ment made a claim for the price of the raw-materials
supplied
and there was no counter-claim by the
respondents.
Under the second and third contracts,
there were
counter-claims-the Government claiming
amounts for the raw-materials supplied and the
respondents claiming damages for the breach thereof.
S.C.R. SUPREME COURT REPORTS 505
The disputes under the first two contracts were settled 1959
on the same day. As the claim was only on the part Th u . .11
_~·
c nion OJ 7Htlll
of the Government, the amount due to them was v.
ascertained at Rs. 3,164-8,0 and the first contract was Kishortlal Gupta
expressly agreed to be finally determined on payment .s. Bros.
of that amount. The express terms of the settlement
leave no room to doubt
that the contract was to be
Subba Rao J.
determined only after the payment of the ascertained
amount.
But under the second settlement, which was a. compromise of disputed claims, a sum of Rs. 36,276
was fixed as
the amount due from the respondents to
the Government, presumably on taking into considera-
tion the conflicting claims and on adjusting all the
amounts ascertained to be due from one to the other.
The parties in express terms agreed that the earlier
contract stood finally determined
and that no party
would have any claim thereunder against the other.
A comparative
study of the terms of the said two
settlement contracts indicates
that under the first
settlement
the original contract continued to govern
the rights of the parties till payment, while under the
second settlement contract, the original contract was
determined
and the rights and liabilities of the parties
depended thereafter
on the substituted contract.
Coming to the third settlement, it was in the pattern
of the second settlement. On the breach ,£>f the third
contract, there were mutual claims, the Government
claiming a large
amount for raw-materials supplied to
the respondents, and the latter on their side setting
up a claim for damages. Further, though the earlier
two contracts were settled on
September 6, 1948, the
a.mounts payable under the said two settlements were
not paid. .A, comprehensive settlement, therefore, of
the outstanding claims was arrived at between the
parties, and the· rights and liabilities were attempted
to be crystallized and a suitable procedure designed for
realising
the amounts. In full and final settlement of
the amounts due to the Government in respect of the
raw-materials received against the contracts and the
respondents' claim for compensation for cancellation
of the contracts, it was agreed that the respondents
should
pay a sum of Rs. 45,000 to the Government
506 SUPREME COURT REPORTS [1960(1))
'95• and that the respondents should retain all the material,
Th u -. -
1
Ind' partly fabricated and fully fabricated stores lying with
• ni";
0
"'them. Clauses 3, 4 and 5 provide for the realisation
Kishoril~I Gupta of the entire amounts covered by the three settle-
& Bros. ments. Under cl. 3 the respondents agreed to pay
the total amount payable under the three settlements
Subba Rao f. in monthly instalments for the first three months
commencing from March IO, 1949, at a sum of
Rs. 5,000 and thereafter at a sum of Rs. 9,000 per
month till the entire amount was paid. Clause 4
prescribed
that in case of default of any monthly
instalment interest would be charged at
tjle rate
of 6% per annum and if the instalments defaulted
exceeded two
in number the Government was given
the right to realise the entire amount payable
under the three contracts with interest not only
from
the security but. also otherwise.
Under cl. 5
it was stipulated that the respondents should
hypothecate
their moveable and immoveable
proper
ties described thereunder to provide cover for the
moneys payable to the Government. Clause 6 in
express terms declared that the contracts should
be finally concluded in terms
of the settlement and
no party would have any claim against the other.
Is there any justificaj;ion for the contention that the
substituted
• contract should either come into force
after the hypothecation bond was executed or that it
should cease to be effective if the said bond was not
executed within a reasonable time from the date of
the settlement? We do not find any justification for
this contention either
in the express terms of the
contract or in the surrounding circumstances
where
under the document came to be executed. It was a
self-contained document; it did not depend upon the
earlier contracts for its existence or enforcement.
The liability was ascertained
and the mode of
re
covery was provided for. The earlier contracts were
superseded
and the rights and liabilities of the parties
were regulated thereunder. No condition either
precedent
or subsequent was expressly provided; nor
was there any scope for necessarily implying one or
other either. The only argument in this
direction.
S.C.R. SUPREME COURT REPORTS 507
namely, that it is impossible to attribute any inten-z959
tion to the Government to take a mere promise o!1 The Union of India
the part of the respondents to hypothecate their v.
properties "as satisfaction " and therefore it should [(isltorilal Gupta ·
lbe held that the intention of the parties was that & Bros.
there would be no satisfaction till such a document
was executed, does not appeal to us. We are con-Subba Rao f.
cerned with the expressed intention of the parties and
when
the words are clear and unambiguous-they are
undoubtedly clear in this
case-there is no scope for
drawing upon hypothetical considerations or supposed
intentions
of the parties; nor. are we attracted by the
argument that the description of the properties intend-
ed to be hypothecated was not made clear and there-
fore
the presumed intention was to suspend the
rights under the new contract till a valid document
in respect
of
a definite and specified property was
executed. Apart from
the fact that we are not
satisfied with the argument that the description was
indefinite,
we do not think that such a flaw either
invalidates a document or suspends its operation till
the defect is rectified or the ambiguity clarified. The
substituted agreement gave a new cause
of action and
obliterated the earlier ones and if there was a valid
defence against
the enforcement of the new contract
in whole or in
part, the party affected must take the
consequences. We
ha,ve, therefore, no doubt that the
contract dated :February 22, 1949, was for valid con-
sideration
and the common
int.ention of the parties
was
that it should be in
sub;.'ltitution of the earlier
ones
and the parties thereto should thereafter look to
it alone for enforcement of their claims. As the docu-
ment does not disclose any ambiguity, no scrutiny of
the subsequent conduct of the parties is called for to
ascertain their intention.
If so, the next question is whether the arbitration
clause
of the original contracts survived after the
execution of the settlement contract dated February
22, 1949. The learned Counsel for the appellant
contends
that· the terms of the arbitration clause are
wide and comprehensive, and any dispute on the
question whether the said contract was discharged by
any of the ways known to law came within its fold.
508 SUPREME COURT REPORTS (1960(1)]
z959 Uninfluenced by authorities or case.Jaw, the logical
n u -. -
1 1
d' outcome of the earlier discussion would be that the
' n•o;
0
n •a arbitration clause perished with the original contract.
Kishor11:1 Gupta Whether the said clause was a substantive term or a
<5-Bros. collateral one, it was none the less an integral part of
the contract, which had no existence de hors the
Subba Rao J. contract. It was intended to cover all the disputes
arising under
the conditions of, or in connection with,
the contracts. Though the phraseology was of the
widest amplitude, it is inconceivable that the parties
intended
its survival even after the contract was
mutually rescinded
and substituted by a new
agree
ment. The fact that the new contract not only did
not provide for the survival of the arbitration clause
but also the circumstance that it contained both
substantive and procedural terms indicates that the
parties gave up the terms of the old contracts, includ
ing the arbitration clause. The case.Jaw referred
to by the learned Counsel in this connection does not,
in our view, lend support to his broad contention and
indeed the principle on which the said· decisions are
based is a pointer to the contrary.
We shall now notice some
of the authoritative
state
ments in the text-books and a few of the cases bearing
on the question raised : In Chitty on Contract, 21st
Edn.,
the scope of an arbitration clause is stated thus, at p. 322:
"So that the law must be now taken to be that
when an arbitration clause is unqualified Ruch a
clause will
apply even if the dispute involve an
assertion that circumstances had arisen whether
before or
after the contract had been partly per
formed which have the effect of discharging one or
both parties from liability, e.g., repudiation by one
· party accepted by the other, or frustration."
In "Russel on Arbitration'', 16th Edn., p. 63, the
following test is laid down to ascertain whether an
arbitration clause survives after the contract is deter-
mined: .
"The test in such cases has been said to be
whether
the contract is determined by something
outside itself, in which case
the arbitration clause
S.C.R. SUPREME COURT REPORTS 509
is determined with it, or by something arising out r959
of th~ contrac~, in "'hich case the arbitration clause The Union of India ,
remams effective and can be enforced." v. •.
The Judicial Committee in Hirji Mulji v. Cheong Yue Kisho•iltll Gupt•
Steamship Company (
1
) gives another test at p. 502 : .s. Bros.
" That a person before whom a complaint is Subba Rao J.
brought cannot fuvest himself with arbitral jurisdic-
tion to decide it is plain. His authority depends on
the existence of some submission to him by the
parties of the subject matter of the complaint. F'or
this purpose a contract that has determined is in
the same position as one that has never been
concluded
at all. It founds no
jurisdiction."
A very interesting discussion on the scope of an arbi
tration clause in the context of a dispute arising on the
question of repudiation of a contract is found in the
d.ecision of the House of Lords in Heyman v. Darwine
Ltd.(
2
) There a contract was repudiated by one party
and accepted as such by the other. The dispute arose in
regard
to damages under a number of heads covered
by the contract. The arbitration clause provided that
any dispute between the parties in respect of the
agreement or any of the provisions contained therein
or anything arising thereout should be referred to
arbitration. The House of Lords held that the dispute
was one within
the arbitration clause. In the speeches
of the Law
Lords· a wider question is discussed and
some of the relevant principles have been succinctly
stated. Viscount Simon L.C. observed
at p. 343 thus: "An arbitration clause is a written submission,
agreed
to by the parties to
'the contract, and, like
other written submissions to arbitration, must ht>
construed according to its language and in the light
of the circumstances in which it is made. If the
dispute is as to whether the contract which contains
the clause has ever been entered into at all, that
issue cannot go to arbitration under the clause, for
the party who denies that he has ever entered into
the contract is thereby denying that he has ever
joined
in the submission.
Similarly, if one party to
(I) [1926] A.C. 497, 502.
65
(2) [1942] l All E.R. 337, 343-345, 347, 350.
I959
Thi Union of India
v.
K isho1'ilal Gupta
cf,. Bros.
Subba Rao].
510 SUPREME COURT REPOR.TS [1960(1)]
the alleged contract is contending that it is void
ab initio (because, for example, the making of such a
contract is illegal), the arbitration clause cannot
operate, for on this view the clause itself is also
void.
If, however, the parties are at one in asserting that
they entered into a binding contract, but a difference
has arisen between them as to whether there has been
a
breach by one side or the other, or as to whether
circumstances have arisen which have discharged one
or both parties from further performance, such differ
ences should be regarded
as differences which have
arisen
" in respect of", or " with · regard to ",
or" under" the contract, and an arbitration clause
which uses these, or similar, expressions, should be
construed accordingly.
By the law of England (though
not, as I understand, by the law of Scotland) such an
arbitration clause would also confer authority to
assess damages for breach even though it does not
confer upon
the1arbitral body express power to do so.
I do
not agree that an arbitration clause expressed
in such terms as above ceases to have any possible
application merely because
the contract has
"come to
an end", as, for example, by frustration. In such
cases it is the performance of the contract that has
come to an end."
The learned Law Lord commented on the view expres
sed
by Lord Dunedin at p. 344 thus : "The reasoning of Lord Dunedin applies equally
to both cases. It is, in my opinion, fallacious to say
that, because the contract has " come to an end"
before performance begins, the situation, so far as
the arbitration clause is concerned, is the same as
though the contract had never been made. In such
case a
binding contract was entered into, with a
valid submission to arbitration contained in its arbi
tration clause, and, unless the language of the arbi
tration clause is such as to exclude its application
until performance bas begun, there seems no reason
why the arbitrator's jurisdiction should not cover
the one case as much as the
other."
S.C.R SUPREME COURT REPORTS 511
Lord Macmillan made similar observations at p. 345 : r959
"If it appears that the dispute is as to whether The Union of India
there has ever been a binding contract between the v.
parties, such a dispute cannot be covered by an Kislsorilal Gupta
arbitration clause in the challenged contract. If & Bros.
there has never been a contract at all, there has
never been
as part of it an agreement to arbitrate;
Subba Rao J.
the greater includes the less. Further, a claim to set
aside a contract on such grounds as fraud, duress or
essential error cannot be
the subject matter of a
reference under
an arbitration clause in the contract
sought
to be set aside. Again, an admittedly binding
contract containing a general arbitration clause
may
stipulate that in certain events the contract shall
come
to an end. If a question arises whether the
contract has for
any such reason come to an end, I
can .-.ee no reason why the arbitrator should not
decide that question. It is clear, too, that the par-
ties
to
a contract may agree t.o bring it to an end to
all intents and purposes and to treat it as if it had
never existed.
In such a case, if there be an arbitra-
tion clause in
the contract, it perishes with the
contract. If the parties substitute a new contract
for
the contract which they have abrogated, the
arbitntion clause in the abrogated contract cannot
be invoked for
the determination of questions under
the new agreement. All this is more or less elemen-tary."
These observations throw considerable light on the
question whether an arbitration clause can be invoked
in
the case
qf a dispute under a superseded contract.
The principle is obvious; if the contract is supersed
ed by another, the arbitration clause, being a compo
nent ·part of the earlier contract, falls with it. The
learned Law Lord pin-points the principle underlying
his conclusion
at p. 347: "I am accordingly of opinion that what is com
monly called repudiation or total breach of a contract,
whether acquiesced in
by the other party or not,
does
not abrogate
a contract, though it may relieve
the injured party of the duty of further fulfilling the
obligations which he has by a contract undertaken
1959
TM Union of Jniia
v.
Kishorilal Gupta
©-Bros.
Subbo Rao
J.
512 SUPREME COURT REPORTS [1960(1))
•
to the repudiating party. The contract is not put
out of existence, though all further performance of
the obligations undertaken by each party in favour
of the other may cease. It survives for the purpose
of measuring the claims arising out of the breach,
and the arbitration clause survives for determining
the mode of their settlement. The purposes of the
contract have failed, but the arbitration clause is not
one of the purposes of the contract."
Lord Wright, after explaining the scope of the word
" repudiation '1' and the different meanings its bears,
proceeded
to state at p.
350 :
" In such a case, if the repudiation is wrongful and
the rescission is rightful, the contract is ended by
the rescission ; but only as far as concerns future
performance. It remains alive for the awarding of
damages, either for previous breaches, or for the
breach which constitutes the repudiation. That is
only a particular form of contract breaking and
WO!!ld generally, under an ordinary arbitration
clause, involve a dispute under the contract like any
other breach of contract."
This decision is not directly in point; but the·princi
ples laid down therein are of wider application than
the actual decision involved. If an arbitration clause
is couched
in widest terms as in the present case, the
dispute, whether there is frustration or repudiation of
the contract, will be covered by it. It is not because
the arbitration clause survives, but because, though
such repudiation ends the liability of the parties to
perform the contract, it does not put an end to their
liability to pay damages for any breach of the contract.
The
contract is still in existence for certain purposes.
But where the dispute is whether the said contract is
void.ab
initio, the arbitration clause cannot operate
on
those disputes, for its operative force depends upon
the existence of the contract and its validity. So too,
if the dispute is whether the contract is wholly super
seded or not by a new contract between the parties,
such a dispute
must fall outside the arbitration clause,
for,
if it is
supl)rseded, the arbitration clause falls with
it. The argument, therefore, that the legal position is
S.C.R. SUPREME COURT H.EPORTS 513
the same whether
the dispute is in respect of repudia- z959
tion or frustration or novation is not borne out by Th
r; -. -
11
dill
these decisions. An equally illuminating judgment of e mo;
0
n
Das, J., as he then was, in Tol,aram Nathm.ull v. Birla J>ishorilalGupla
Jute Manufacturing Go. Ltd.(
1
)
is strongly relied upon
& Bros.
by the learned Counsel for the a.ppellant. There the
question was whether an arbitration clause which was Subba Rao f.
expressed in wide terms would take in a dispute raised
in that case. It was contended on one side that the
contract was void ab initio a.ad on the other side that,
even on the allegations in ihe plaint, the contract
was
not ab initio void. The learned Judge, on the
facts of that
case, held that no case had been made
out for staying the suit and therefore dismissed the
application filed by the defendant for stay of the
suit. The learned Judge exhaustively considered the
case-law on the subject and deduced the principles and
enumerated them at p. 187. The learned Judge was
not called upon to decidtt the present question, namely,
whethor
an arbitration clause su:rvived in spite of sub-
stitution
of the earlier contract containing the arbitra-
tion clause by a fresh one, and therefore we do not
think that it is necessary to express our opinion on the
principles culled out and enumerated in that decision.
The following principles
relev11nt to the present case
emerge from
the aforesaid discussion: (1) An
arbitra
tion clause is a collateral term of a contract as distin
guished from its substantive terms ; but none the less
it is an integral part of it; (2) h<>wever comprehensive
the terms of an arbitration clause may be, the existence
of the contract is a necessary condition for its opera
tion; . it perishes with the contract; (3) the contract
may be non est in the sense that it never came legally
into existence or it was void ab initio; (4) though the
contract was validly executed, the parties may put an
end to it as if· it had never existed and substitute a
new contract for
it solely governing their rights and
liabilities thereunder; (5) in the former case, if the
original contract has no legal existence, the arbitration clause also can.not operate, for along with the original
contract,
it is also void; in 1;he latter case, as the (1) I.L.R. [1948) s Cal. 171.
514 SUPREME COURT REPORTS [1960(1))
x959 original contract is extinguished by the substituted
The u -. -
1
d' one, the arbitration clause of the original contract
m';,
0 1
"
••perishes
with it; and (6) between the two falls many
Kishorilal Gupta categories of disputes in connection with a contract,
<f.. Bro.<. ~uch as the question of repudiation, frustration, breach
etc. In those cases it is the performance of the contract
Subba Rao J. that has come to an end, but, the contract is still in
existence for certain purposes in respect of disputes
arising
under
it. or in connection with it. As the
contract subsists for certain purposes, the arbitration
clause operates in respect of these purposes.
Sarkar].
We have held that the three cont.racts were settled
and the third settlement contract was in substitution of
the thrP.e contracts; ,.nd, after its execut~on, all the
earlier contracts were extillguished and the arbitration
dause contained therein also perished along with them.
\Ve have also held that the new contract was not a
conditional
one and after its execution t.he parties
should work out their rights only under its terms. In
this view, the judgment
of the High Court is c-orrect.
This appeal fails and is dismissed with costs.
SARKAR J.-On different dates in 1943 and 1944, a
firm
of contractors of the name of Kishorilal Gupta &
Brothers entered into three contracts with the
appel
lant. to fabricate and supply certain milita.1·y stores.
The first eontraut was for 43,000 ladles cook, the
second for 15,500 bath ovals and the third for 1,00,000
kettles camp. Each of these contracts contained an
arbitratfon clause. The last mentioned contract pro
vided that the appellant would supply materials for
the fabrication
of the articles to be delivered under it.
Before
the contracts
had been finally executed,
disputes arose between die parties. These disputes
were settfad by mutual agreements which were con
tained in three separate doeuments. The settlement
in respect of the ladles cook contract which was made
on September 6, 1948, provided that the contractors
would pay to the appellant a sum of Rs. 3,164-8-0 and
on such payment that contract would stand finally
determined. Under the settlement in respect of
the bath ovals contract which also was made on
S.C.R. SUPREME COURT HEPORTS 515
September 6, 1948, the contractors agreed to pay to the z959
appellant Rs. 36,276 and it provided that "the con-h u -. -,
1
d'
. · T e n1on o tJ ia
tract stands finally determmed and no party shall have v. ·
any further claim against the other ". The terms of Kishorilal Gupta
the settlement of the kettles camp contract are set out & Bros.
below in full, for, this case depends on them:
"Dated the 22nd February 1949.
Messrs. Kishorilal Gupta
& Bros., Calcutta.
Subs:-A.T. No.
MP/75442/R-1/397 dated the 22nd
Septem her 1944.
Dear Sir,
Reference discussion held on 5th February 1949
between your Proprietor Mr. Kishorilal Gupta and
General Manager J.B. Breiter and the Claims Com
mittee of the Directorate General. I herebv confirm
the following terins of settlement arrived at in the
meeting. The settlement has received the approval
of Director General of Industries and Supplies, New
Delhi.
I. The firm will pay a sum of Rs.
45,000 in full
and final settlement of the amount due to the
Government in respect of raw materials received
against
the contract and their claims for
compensa
tion for cancellation for the same contract.
2. The firm will retain all imrplus partly fabric
ated and fully fabricated stores,. lying with them.
3. The firm agree
to pay the above-mentioned
sum
of Rs.
45,000 only together with the sums owing
by them to the Government under the settlements
reached in two other cases A/T Nos. lUP/75762/R-61/78
dated 15th September 1944 and l\'IP/50730/8/R-1/90
dated 2nd April 1943 in monthly instalments for
Rs. 5,000 only for the first three months, first instal
ment being payable on 10th :March 1949 and fm:ther
instalments of Rs. 9,000 per month till the entire
dues payable to Government are paid.
4. In the event of default of any monthly
instalments interest will be charged
by Government
on
the amount as defaulted
itt the rate of 6% per
annum from
the first day of
the month in which the
instalment shall due. If the iu.stalments defaulted
Sarkar].
z959
The Union of India
v.
Kishorilal Gupta
& Bros.
Sarkar).
516 SUPREME COURT REPORTS [1960(1)]
exceed two in number, the Government will have
the right to demand the entire balance of the money
payable by the firm together with interest thereon
at the rate abovementioned on that balance and take
such steps to recover from the Security to be offered
by the firm, in terms of the settlement or otherwise.
5.
In order to provide cover for the monies
payable to the Government the firm undertakes to
hypothecate their movable and immoveable property
in Bamangachi Engineering Works,
together with
all machinerv sheds and lease-hold interest in land
measuring about 5·75 acres at Mouja Bamangachi
in Howrah. The firm further undertakes to execute
~he necessary stamped documents for the purpose as
drafted by the Government Solicitor at Calcutta.
6.
The contracts stand finally concluded in terms
of the settlement and no party will
have any further
or other claim against the other.
Please acknowledge receipt.
Yours faithfully,
Sd. R. B. L. Mathur
Director of Supplies (Claims)
for and on behalf of the Governor General."
The contract referred to in cl. (1) of this document is
the contract No. MP/75442/R-l/397 mentioned at the
top of the letter and concerned the kettles camp. The
contracts referred to in cl. (3) are the contracts con
cerning ladles cook
and bath ovals which
had been
settled earlier
but the amounts due in respect of the
settlements concerning them had not been paid in full.
After the settlement of February 22, 1949, the con
tractors made certain payments aggregating Rs.
11,000,
the last payment made being on October 31, 1949.
These
payments
had not been made as provided in
cl. (3). The contractors also failed to execute the
hypothecation deed mentioned in cl. (5). Certain
correspondence appears to have taken place but with
no tangible result. The appellant was unable to obtain
payments or the hypothecation deed in terms of the
settlement.
S.C.R. SUPREME COURT REPORTS 517
In these circumstances the appellant made a claim z959
against the contractors under the three original con-
1
•11 u -. -.,
1
d"
. l . e nion OJ n ict.
tracts amountmg to Rs. 1,52,723 and referrea it to v.
arbitration under the arbitration clauses contained in Kishorilal Gupta
them. The appellant nominated an arbitrator and &-Bros.
called upon the contractors to nominate the other, the
Sarkar ].
arbitration clause providing that the arbitration shall
be
by two arbitrators, one to be nominated by each
party. The contractors did not nominate any arbit-
rator, contending
that the matter
had" already been
nel;'Otiated to a settlement " and that there were " no
out.standing disputes
to be referred to arbitration
".
The appellant then appointed the person nominated
by it as the sole arbitrator under the provisions of tho
Arbitration Act
and an arbitration was held by him in
which
the contractors joined. In the arbitration pro-
ceedings, for reasons with which
we are not concerned,
the appellant abandoned its claim in respect of the
bath ovals contract.
On July 31, 1951, the arbitrator
made an award in favour of the appellant in the sum
of Rs. 1,16,446-11-5 in respect of its claim on the ladles
cook
and kettles camp contracts.
Being aggrieved
by the a ward, the respondent
Kishorilal Gupta, who is
a partner of the contractors'
firm, made
an application to the High
Court at Cal
cutta in its Original Jurisdiction for a declaration that
the arbitration clauses in the original contracts had
ceased to have any effect and the contracts stood finally
determined as a result
of the settlements earlier referred
to and for an order setting aside the award as void and a nullity.
I wish to
draw attention here to the
fact that the
application was really concerned with the contracts for
ladles cook
and kettles camp. It had nothing to do
with the bath ovals' contract for the appellant
with
drew its claim under it from arbitration and no a.ward
was made in respect
of it.
So in this appeal we are not
really concerned with that contract.
Bachawat,
J., who heard the application held that
the contract for ladles cook had not been abrogated by
the settlement in respect of it for reasons which it is
unnecessary
to state here as this part of the decision
f6
518 SUPREME COURT RE.PORTS [1960(1)]
x959 of the learned Judge has not been challenged before us.
Th u -:----rm1· We h,ave therefore to proceed on the basis that the
e ni:n of '"arbitration clause contained in the ladles cook contract
Kishoril~l Gupta continued in force in spite of the settlement in respect
& Bros. of it.
Sarkar ].
The learned Judge however held that the contract
for kettles camp including the arbitration clause con
tained in it had ceased to exist as a result of the
settlement of February 22, 1949, and the arbitrator
had consequently no jurisdiction to make any award
purporting to act under that arbitration clause. He
then proceeded to hold that as the award was a single
and iuseverable award in respect of the claims under
the ladles cook as well as the kettles camp contracts,
the whole award became invalid. In the result the
learned J urlge made an order declaring that the arbi
tration clause contained· in the kettles camp contract
had ceased to exist and setting aside the a ward as a
whole.
It is against this judgment that the present appeal
has been filed with leave granted by this
Court. It
was contended on behalf of the respondent that the
leave should not have been granted as the appellant
had a right of appeal to the High Court itself. We
were on this basis asked to revoke the leave. It
appears that there are some cases of the Calcutta High
Court which create a good deal of doubt as to whether
an appeal lay to that High Court from an order of the
kind made in this case. The appellants therefore were
legitimately
in difficulty in deciding whether an appeal
Jay to the High
Court. Again, leave was granted by
this Court as far back as March 29, 1954, and the res
pondent at no stage earlier than the hearing of the
appeal before us took any objection to that leave. It
is too late now to allow him to do that. So to do
would leave
the appellant entirely without remedy as
an appeal to the High
Court would in any event be
now barred. I feel therefore that no question of
revoking the leave should be allowed to be raised.
It is useful to remind ourselves before proceeding
further that what was referred to arbitration in this
case was a claim by the appellant for damages for
S.C.R. SUPREME COURT REPORTS 519
breach of the contracts said to have been committed z959
by the contractors. That indeed is the respondent'srk ·u -. -,,
1
_.,.
W
. h d h
"t f th" l
· th • nion °
1
,...,a
case. it regar to t e mer1 s o 1s c aim e v.
Court has no concern. But it is import'ant to note that Kishorilal Gupta
those claims were clearly within the arbitration clause & Bros.
in the contracts ; about this there does not appear to
be any dispute. No question therefore arises in this Sarkar J.
appeal that the claims referred to arbitration were
not within the arbitration clauses.
What is in dispute in this case is whether the arbit
ration clause had ceased to exist as a result of settle
ment. In considering the question it is not necessary
however
to concern ourselves with the settlements
regarding
the ladles cook contract or the bath ovals
contract. The
bath ovals contract is not the subject
matter of the award. As regards the ladles cook
contract,
the Court below has held that that settlement
did
not affect the relative arbitration clause and
tha.t
decision has not been challenged before us.
The real question
that we have to consider is
whether
the settlement of February 22, 1949, altogether
put out of existence the arbitration clause in the
kettles camp contract. If it did, the arbitration in
this case was clearly without jurisdiction and the
award resulting from it a nullity, for on that basis
there would be .no.arbitration agreement under which
an arbitration could be held.
An, arbitration agree
ment, of course, is the creature of an agreement and
what is created by agreement may be destroyed by
agreement. Lord Macmillan considered it elementary
" that the parties to a contra.ct may agree to bring it
to an end to a.II intents and purposes and to treat it
as if it had never existed" and that " In such a -case if
there be an arbitration clause in the contract it peri
shes with the contra.ct"-: Heyman v. Darwins (1).
Now it is clear that the settlement of February 22,
1949, does not expressly make the arbitration clause
non-existent.
It is however said that the settlement
of February 22, 1949, operated as
an accord and
sa.tisfa.ction and therefore the arbitration cla.use in the
relat~ve original contract was brought to an end by it.
(1) (194:1] A.C. 356, 371.
520 SUPREME COURT REPORTS [1960(1)]
z959 It is said that such a settlement amounts to a substi-
Th u -. -
11
d" tuted agreement which abrogated the original contract
' "'':'.'.
0
"
"'and
the arbitration clause contained in it perished
T<ishorilal Gupta with it.
& Bros. I venture to think that this view is wrong and
originates from a misapprehension of the real nature
Sarkar J. of accord and satisfaction and an arbitration clause in
a contract. It must here be stated that the appellant
disputes that the settlement of February 22, 1949,
amounted to an accord and satisfaction. I will examine
the appellant's contention later and shall for the
present assume that the settlement constituted an
accord and satisfaction.
Now what is an accord and satisfaction ? It is only
a method of discharge of a contract. It ouly means
that the parties are freed from their mutual obligations
under the contract : ·see Cheshire and Fifoot on Cont
racts, 3rd edn., p. 433. " It is a good defence to an
action for the breach of any contract, whether made
by parol or specialty, that the· cause of action has
been discharged by accord and satisfaction, that is to
say, by an agreement after breach whereby some con
sideration other than his legal remedy is to be accept
ed by the party not in fault ": Chitty on Contracts,
21st edn., p. 286. In British Russian Gazette and
Trade Outlook. Ltd. v. Associated Newspapers Ltd. (')
Sorutton, L.J., said, "Accord and satisfaction is the
purchase of the release from an obligation whether
arising under contract or tort by means of any valu
able consideration, not being the actual performance
of the obligation itself. The accord is the agreement
by which the obligation is discharged. The satisfac
tion is the consideration which makes the agreement
operative."
The effect of au accord and satisfaction is therefore
to secure a release from an obligation a.rising under a.
contra.ct. Now it is difficult to conceive of an obliga
tion a.rising from a. contract uules the contract existed.
An accord and satisfaction which secures a release
from
such an obligation is really based on the existence
of the contra.ct instead of treating it
as non-existent.
(r) (1933] 2 K.B. 616, 643-4.
f
J
S.C.R. SUPREME COURT REPORTS 521
The contract is not annihilated but the obligations z959
under it cease to be enforceable. Therefore it is that Th u -. -,,
1
~·
h t . · b ht ~ th · t d e mon °' ""'" w en an ac ion is roug 1or e appropria e reme y v. .
for non~performance of these obligations that an Kisho~ilal Gupia
accord and satisfaction furnishes a good defence. The &-Bros.
defence is not that the contract has come to an end
but that its breach has been satisfied by accord and Sarkar f.
satisfaction and therefore the plaintiff in the action is
not entitled to the usual remedy for the breach.
It would clearly appear from the terms of the settle
ment that it dealt with remedies for the breach of the
kettles camp contract. Clause (1) shows that the
parties were making cross-claims against each other
for breach of that. contract and these were settled by
mutual agreement upon the term that the contractors
would
pay to the appellant Rs.
45,000. Clauses (3), (4)
and (5) state how this sum was to be paid and how the
payment of it was to be secured. Clause (6) provides
that the contract stands finally concluded in terms of
the settlement. The parties therefore were only
intending to decide the dispute as to cross-claims mltde
on the basis of the breach of the contract. So they
were assuming the existence of the contract, for there
could be no breach
of it unless it existed.
Now I come
to the nature of an arbitration clause.
It is well settled that such a clause in a contract
stands apart from the rest of the
contract. Lord
Wright said in Heyman's case (
1
) t,ha.t an arbitration
clause "is collateral to the substantial stipulations of
the contract. It is merely procedural and ancillary, it
is a mode of settling disputes,................... All this
may be said of every agreement to arbitrate, even
though npt a separate bargain, but one incorporated
in the general contract." Lord Macmillan also made
some
very revealing observations on the nature of an
arbitration clause in the same case. He said at
pp. 373-4: " I venture to think that not enough attention
has been directed to the true nature and function of
an arbitration clause in a contract. It is quite
distinct from
the other clauses. The other clauses
(1) [1942] A.C. 356, 371.
'959
1'/ie Union of India
v.
Kislwn'tal Gupta
& Bros.
Sarkar J.
522 SUPREME COURT REPORTS [1960(1)]
set out the obligations which the parties undertake
towards ea.ch other hinc in</,e, but the arbitration
clause does not impose on one of the parties an
obligation in favour of the other. It embodies the
agreement of both the parties that, if any dispute
arises
with regard to the obligations which the one
party has undertaken to the other, such dispute
shall be settled
by a tribunal of their own
constitu
tion. And there is this very material difference,
that whereas in an ordinary contract the obligations
of the parties to each other cannot in general be
specifically enforced
and breach of them results only
in damages,
the arbitration clause can be
specifica:lly
enforced by the machinery of the Arbitration Act.
The appropriate remedy for breach of the agreement
to
arbitrate is not damages, but its
enforcement."
It seems to me that the respective nature of accord
and satisfaction and arbitration clause makes it·
impossible for the former to destroy the latter. An
accord and satisfaction only releases the parties from
the obligations under a contract but does not affect
the arbitration clause in it, for as Lord Macmillan
said, the arbitration clause does not impose on one of
the parties an obligation in favour of the other but
embodies an agreement that if any dispute arises with
regard to the obligations which the one party has
undertaken to the other, such dispute shall be settled
by arbitration. A dispute whether the obligations.
under a contract have been discharged by an accord
and satisfaction· is no less a dispute regarding the
obligations under the contra.ct. Such a dispute has
to be settled by arbitration if it is within the scope of
arbitration clause and either party wants that to be
done.
That cannot be unless the arbitration clause
survives
the accord and satisfaction. If. that dispute
is
not within the arbitration clause, there can of course
be no
arbitration, but the reason for that would not
be that the
arbitration clause has ceased to exist but
that the dispute is outside its scope. I am not saying
that it is for the arbitrator to decide whether the
arbitration clause is surviving; that may in many
cases have to be decided by the Court. That would
S.C.R. SUPREME COURT REPORTS 523
depend on the form of the arbitration agreement and r959
on that aspect of the matter it is not necessary to say
1
.11
~-
d'
th
. .c h t' d t · e Union of In •a
any mg now .ior t e ques ion oes no arise. v.
In my view therefore an accord and satisfaction Kishorilal Gupta
does not destroy the arbitration clause. An examina- & Bros.
tion of what has been called the accord and satisfaction
in
this
ca.se shows this clearly. ]'rom what I have Sarkar J.
earlier said about the terms of the settlement of
February 22, 1949, it is manife8t that it settled the
disputes between the parties concerning the breach of
the contract for kettles camp and its consequences.
All
that it said was that the contract had been broken
causing damage
and the claim to the damages was to
be satisfied
" in terms of the settlement ". It did not
purport to annihilate the contract or the arbitration
clause in it. I feel
no doubt therefore that the
arbitration clause subsisted
11-nd the arbitrator was
competent
to
arbitrate. The award was not, in my
view, a nullity.
The position is no different if the matter is looked
at from the point of view of s. 62 of the Contract Act.
That section is in these terms :
" Section 62. If the parties to a contract agree
to substitute a new contract for it, or to rescind or
alter it, the original contract need not be per
formed."
The settlement cannot be said to have altered the
original contra.ct or even to have rescinded it. It only
settled
the dispute
as to the breach of the contract
and its consequences. For the same reason it cannot
be said to substitute a new contra.ct for the ·old one.
As I have earlier
stated it postulates the existence
of the
contra.Qt and only decides the incidence of its
breach.
It remains now to express my views on the question
whether
the settlement of February 22, 1949, amounted
to
an accord and ~tisfa.ction. I have earlier stated
that an accord and satisfaction is the purchase of a
release from an obligation under a contra.ct. This
release is purchased by an agreement.which is the
accord. But this agreement like all other agreements
must be supported by consideration. The satisfaction
524 SUPREME COURT REPORTS (1960(1)]
z
9
s9 is that consideration. It was formerly thought that
Tiu Unicm of India the consideration had to be executed. In other words,
v. the consideration _for which the release was granted
Kishol'ilol Gupta had to be received by the releasor before the release
& Bros. could become effective. The later view is that the
consideration may be executory; that the release may
Sarkar /. become effective before the consideration has been
received
by the releasor if he has agreed to accept the
promise of the releasee to give the consideration.
Whether it is the
on~ or the other depends on the
agreement of the parties. It is a question of intention.
And where, as in the present case, the agreement is
expressed in writing, the question is one of construc
tion of a document .. So much is well settled.
The question then is, Is it the prpper construction
of the settlement of February 22, 1949, that the appel
lant agreed to accept the promise of the contractors
to pay the moneys and create the security in discharge
of their obligations ? Or is, it the proper construction
that the contractors were not to be discharged till they
had carried out their promises contained in the settle
ment. The High Court held, accepting the respondent's
contention, that cl. (6) of the settlement showed that
the appellant had accepted the promise of the contrac
tors to pay the moneys and to execute a hypotheca
tion bond in full discharge of their obligations under
the contract. That clause states that " The contracts
stand finally concluded in terms of the settlement."
It is said that these words show that it was intended
to accept the promise of the contractors and thereup
on to give them a discharge from their obligations
under the contract.
Now it seems to me that the words "stands finally
concluded
in terms of the
settlement" do not neces
sarily mean concluded by the promise of the con
tractors contained in the settlement. It appears to
me to be capable of the meaning that the contract is
to stand concluded when its terms have been carried
out. The words are not, " stand finally concluded by
the terms of. the settlement " but they are, " stand
finally concluded in terms of settlement ''. These
terms are that the contractors would pay certain
S.C.R. SUPREME COURT REPORTS 525
moneys by certain instalments and would secure these
1
959
payments by a hypothecation bond. So it wou~d The un-::::-Of India
appear that the contract was not to be concluded till v.
the terms had been carried out, for otherwise it would Kishorilal Gupta
not be a conclusion "in terms of the settlement." & Bros.
That seems to me to be also the reasonable inter
pretation to put on the document in view of the
circumstances of the case. The appellant was to
receive a substantial sum under the settlement. It
gave the contractors quite a long time in which to pay
it. It bargained for a security to be furnished to be
sure
of receiving the payments. The discharge was
to be by the payments. The promise to make these
payments
may conceivably in proper circumstances,
itself
amount to a discharge. But I wholly fail to see
that when there is an additional promise to secure the
payments by a hypothecation, the parties could have
intended that there would be a discharge before the
hypothecation had been made. It does not seem
reasonable
to hold that. the parties so intended. Nor
do I think that the words
"stand finallv concluded in
terms
of the settlement
" are so strong·· as to impute
such
an intention to the
parties. These words are
capable
of the meaning that the contract was to stand
concluded upon the terms of the settlement being
carried
out and, for the reasons just mentioned, that
is the
proper meaning to give to those words. In my
view, therefore, the settlement did not amount to an
accord and Ratisfaction. Till the terms of it had been
carried out,
the appellant retained all its rights under
the contract.
There was one
other point argued ou behalf of the
respondent which l think I should notice. It was said
that the award was in any event liable to he
set aside
inasmuch
as it disclosed an error on the face of it. This
error,
it was said, consisted in awarding damages larger
than those which the appellant had agreed to take by
the settlement. Now this depends on whether the
settlement amounted to
an accord and satisfaction; if
it did not, the appellant's claim for damages could not
be confined
to the amount mentioned in the
settlement.
Sar,~ar ].
526 SUPREME COURT REPORTS [1960(1))
z959 I have already said that in my opinion it did not
T"' u .. ,.,. of India amount to an accord and satisfaction. So there was
v. no error apparent on the face of the award. It further
Kishoril.Z Gupta seems to me that it is not open to the respondent to
<1.Bros. contend that the award is liable to be set aside as dis
Sarkar].
closing the error mentioned above on the face of it. I
do not find that such a case was made in the applica
tion
out of which this appeal arises. It was said that
the case had been made in paragraphs 34 and 35 of ,the respondent's petition to the High Court. I do not
think it was there made. These paragraphs refer to
the arbitrator's decision that he had jurisdiction to
arbitrate as the settlement had not destroyed the arbit
ration clause
and the contention there made was that
this decision
was erroneous on the face of it. This has
nothing to do with the question that the award was
wrong oli"Lhe face of it as it awarded a sum in excess
of the amount fixed by the settlement. Whether the
arbitrator was right or not in his decision that the
arbitration clause had not been superseded is irrelevant
for that is the question that the Court was called upon
to decide
in the application.
In my view therefore
tho nppeal should succeed and
the order of the High Court set aside. I would order
accordingly and award the costs here and below to the
appellant.
ORDER
In accordance with the opinion of the. majority this
appeal fails and is dismissed with costs.
Legal Notes
Add a Note....