As per case facts, the Petitioner placed purchase orders with the Respondent. The Petitioner withheld payment for the first purchase order, citing alleged fraudulent payment for a second purchase order ...
901-ARBP-221-2023.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO. 221 OF 2023
Union of India, through Principal Chief
Engineer / Deputy Chief Engineer,
having office At Central Railway,
represented by Dy. CE/TP, Central
Railway, CSMT, Mumbai. … Petitioner
Vs.
M/s. Bridge Track And Tower Pvt. Ltd.
(earlier known as M/s. Manish Forgings
Pvt. Ltd.), a private ltd. company
having its office at 6
th
floor 18 R. N.
Mukherjee Road, Kolkata- 700 001.
And also having address at:-
Shed No. 2, Plot No. 10, Sector-A, Urla
Industrial Estate, Raipur- 492 221. … Respondent
Mr. Chetan C. Agrawal a/w Saurabh Gori for the
Petitioner/Applicant.
Mr. Aseem Naphade a/w Deepanjali Mishra a/w A. P. Singh i/b
A. P. Singh & Co. for the Respondent.
CORAM : GAURI GODSE, J
RESERVED ON : 17
th
OCTOBER 2025
PRONOUNCED ON : 4
th
FEBRUARY 2026
Page no. 1 of 21
rrpillai
RAJESHWARI
RAMESH
PILLAI
Digitally
signed by
RAJESHWARI
RAMESH
PILLAI
Date:
2026.02.04
15:09:37
+0530
901-ARBP-221-2023.doc
JUDGMENT:
1. This arbitration petition is filed under Section 34 of the
Arbitration and Conciliation Act, 1996 (“Arbitration Act”), to set
aside the arbitral award passed by the sole arbitrator. The
claim in the arbitration is based on a purchase order placed by
the petitioner with the respondent (claimant) for the fabrication
and supply of 344 fans weighing 60 kg, shaped switches, as
per the contract between the parties. By the arbitral award, the
respondent’s claim is granted for non-payment of Rs.
24,93,462/- towards the cost of supply of 45 sets of contract
goods, and the PVC amount of Rs. 6,38,932/-, which was
withheld by the respondent.
Basic Facts:
2. The petitioner had placed a purchase order with the
respondent for the fabrication and supply of 344 sets of 60 kg,
overriding fan-shaped switches. The petitioner placed another
purchase order for the supply of 1014117 ERC. The petitioner
alleged that, without supplying the goods, the respondent, in
collusion with some railway staff, fabricated the record showing
delivery of the goods and fraudulently received the payment.
Hence, criminal proceedings were initiated, and the CBI in
Page no. 2 of 21
901-ARBP-221-2023.doc
Pune commenced an investigation. A charge sheet was filed
for the offence of forgery and cheating. By relying on Clause
No. 2401 of the Indian Railways Standard Conditions of
Contract (“IRS terms and conditions”), the petitioner withheld
the amount payable to the respondent towards the first
purchase order.
3. The arbitral tribunal opined that, under Clause No. 2401
of the IRS terms and conditions, before withholding or retaining
any payable amount, the petitioner was required to notify the
contractor of such withholding or retention. Since the petitioner
failed to submit any evidence to prove that a show cause notice
or an intimation was served upon the respondent, the onus of
proving the same was not discharged, and thus the petitioner
was not entitled to withhold the amount on the ground of
pending adjudication of the criminal proceedings. Being
aggrieved by the award directing the release of the payment,
the original respondent has filed this petition to set aside the
award.
4. The following are the admitted dates and events
regarding the contract between the parties:
Page no. 3 of 21
901-ARBP-221-2023.doc
a)On 22
nd
July 2011, the petitioner floated a tender for the
fabrication and supply of 60 kg (UIC) overriding fan-
shaped switches. The respondent submitted a quotation
in response to the tender. The petitioner issued a letter of
acceptance to the respondent on 17
th
November 2011.
Accordingly, the petitioner issued a purchase order on 9
th
February 2012 for the fabrication and supply of 60 kg
(UIC) fan-shaped overriding switches. The contract value
of the purchase order was Rs. 1,98,21,758/-. The second
purchase order dated 17
th
July 2012 was issued by the
petitioner for the supply of 10,14,117 Elastic Rail Clips
(“ERC”).
b)Thus, based on the letter of acceptance dated 17
th
November 2011, two purchase orders were placed. The
first purchase order was on 9
th
February 2012, and the
second was on 17
th
July 2012.
c)The respondent accordingly raised three invoices totalling
Rs. 6,38,932/-. Three separate invoices dated 21
st
December 2013 were raised. Two invoices for an amount
of Rs. 9,41,976/- each, for the supply of 17 sets of the
said goods and 11 sets of the said goods, respectively.
Page no. 4 of 21
901-ARBP-221-2023.doc
The third invoice was for Rs. 6,09,514/- for the supply of
11 sets of the said goods.
d)Out of the total invoices raised by the respondent, the
above-referred invoices for a total sum of Rs. 31,32,396/-
were unpaid by the petitioner. Hence, the respondent
initiated arbitration proceedings.
Submissions On Behalf Of The Petitioner:
5. Learned counsel for the petitioner submitted that the
adjudication on the second purchase order should have been
done by the learned arbitrator, as the papers and proceedings
of the CBI enquiry were brought on record before the learned
arbitrator. The award grants the petitioner permission to notify
the lien and also awards interest, which is contrary to clauses
2401 and 2403 of the IRS terms and conditions. The petitioner
has already notified the lien on 6
th
August 2019, and a copy of
the same is filed on the record of this arbitration petition in the
application for stay. Thus, the lien notified by the petitioner
must continue till the final decision of the CBI enquiry.
6. Learned counsel for the petitioner, therefore, submits that
when the CBI enquiry is initiated and is pending in respect of
Page no. 5 of 21
901-ARBP-221-2023.doc
the illegal release of the amount towards the invoice of the
second purchase order, the petitioner would be entitled to have
a lien on the amount payable towards the first purchase order.
The learned arbitrator has also permitted the petitioner to notify
the lien. Thus, under the award, once the petitioner is permitted
to notify a lien on the amount due and payable under the first
purchase order, the award directing the petitioner to release
the payment would be illegal and unsustainable in law.
7. Learned counsel for the petitioner submits that the
petitioner had a right to withhold the amount from any other
contract in view of the pending CBI enquiry. To support his
submissions, learned counsel for the petitioner relied upon the
decision of the Hon’ble Apex Court in the case of M/s. H.M.
Kamaluddin Ansari & Co. Vs. Union of India & Others
1
.
Learned counsel for the petitioner submitted that after the
amounts were illegally released by the officers of the petitioner
in connivance with the respondent, a CBI enquiry was initiated
and is pending adjudication. A charge sheet has already been
filed, and copies of the papers and proceedings of the CBI
enquiry were placed on record before the learned arbitrator.
Hence, in view of the pending CBI enquiry into the illegal
1 (1983) 4 SCC 417
Page no. 6 of 21
901-ARBP-221-2023.doc
release of the amount under the second purchase order, the
petitioner is entitled to continue with the lien already notified, in
view of the liberty granted by the learned arbitrator. Hence,
until the CBI enquiry is concluded, the lien shall continue;
therefore, the award directing payment needs to be set aside.
Submissions On Behalf Of The Respondent:
8. Learned counsel for the respondent supports the
impugned award. According to the learned counsel for the
respondent, the defence raised by the petitioner is based on a
lien until the CBI enquiry is concluded. Thus, the petitioner
contends that withholding the amount is subject to the outcome
of the CBI enquiry. Learned counsel for the respondent
submitted that the findings in the criminal Court would not be
binding in the civil proceedings. Therefore, in the present case,
the result of the CBI enquiry would not have any bearing on the
release of the amount withheld by the petitioner as per the
invoices in lieu of the first purchase order.
9. So far as the petitioner’s contention on the right to keep a
lien on the amount payable for the material supplied as per the
first purchase order on the ground of pending CBI enquiry is
concerned, learned counsel for the respondent submits that in
Page no. 7 of 21
901-ARBP-221-2023.doc
the CBI enquiry the issue as to whether the goods were
actually supplied and whether the amount is payable for the
first purchase order would not be adjudicated. Hence, the
allegation that the amount released under the second purchase
order was illegal, without the actual supply of the material,
cannot be a ground for withholding payments for the goods
admittedly supplied under the first purchase order.
10. According to the learned counsel for the respondent,
withholding an amount during the pendency of the CBI enquiry
is contrary to the law laid down by the Hon’ble Apex Court in
the case of Vishnu Dutt Sharma Vs. Daya Sapra(Smt)
2
and
Shanti Kumar Panda Vs. Shakuntala Devi
3.
.
11.Learned counsel for the respondent thus submits that in
the event the petitioner intends to keep a lien on the amounts
payable as per the first purchase order on the ground that the
amounts were illegally released for the goods not supplied as
per the second purchase order can be validly notified only after
the petitioner invokes arbitration and raises a claim for
recovering the alleged illegal release of the amount. He
therefore submits that the petitioner would not be entitled to
2 (2009) 13 SCC 729
3 (2004) 2 SCC 438
Page no. 8 of 21
901-ARBP-221-2023.doc
seek setting aside of the award on the ground that the
petitioner is entitled to keep a lien on the goods actually
supplied to the respondent without raising a claim for its
recovery. He thus submits that the learned arbitrator has rightly
reserved the right of the petitioner to notify a lien pending
adjudication. However, the petitioner, without raising a claim to
recover the alleged illegal release of the amount under the
second purchase order, has simply notified a lien on the
amounts due and payable under the first purchase order. To
support his submissions, learned counsel for the respondent
relied upon the decision of the Board of Trustees of the Port of
Bombay Vs. Sriyanesh Knitters
4
.
12. Learned counsel for the respondent relies on the
definition of ‘lien’ given in Black’s Law Dictionary. He submits
that a lien is not a property in or right to the thing itself but
constitutes a charge for security thereon. Therefore, without
raising a claim to recover the alleged illegal release of the
amount, there would not arise any question of keeping a lien on
the amount due and payable towards the goods that are
admittedly supplied. Learned counsel for the respondent,
4 (1997) 7 SCC 359
Page no. 9 of 21
901-ARBP-221-2023.doc
therefore, submits that there is no ground to invoke the powers
under Section 34 of the Arbitration Act to set aside the award.
Consideration Of The Submissions And Analysis:
13. To consider the rival submissions made on behalf of the
parties, I have carefully perused the facts of the case. The facts
referred to by the learned counsel for the petitioner, as
recorded in the above paragraphs regarding the tender
process, the purchase orders, and the invoices raised, are not
in dispute. It is also undisputed that the goods were supplied
under the first purchase order for which the amounts are
withheld. As for the second purchase order, the petitioner
alleges that the respondent fraudulently received payment
without supplying any material under it. Hence, the CBI has
initiated a criminal prosecution against the respondent's
employees, its directors, and some of the petitioner's
employees. Therefore, according to the petitioner, the amount
payable under the first purchase order can be withheld by
creating a lien on that amount till final adjudication of the
criminal prosecution. However, the petitioner has not raised
any claim for the recovery of the amounts alleged to have been
illegally and fraudulently recovered by the respondent.
Page no. 10 of 21
901-ARBP-221-2023.doc
14. The relevant condition of the IRS terms and conditions for
withholding and keeping a lien in respect of the sums claimed
is in clause 2401, which reads as under:
“2401. Whenever any claim or claims for payment of a
sum of money arises out of or under the contract against
the Contractor, the Purchaser shall be entitled to withhold
and also have a lien to retain such sum or sums in whole
or in part from the security if any, deposited by the
Contractor and for the purpose aforesaid, the Purchaser
shall be entitled to withhold the said cash security deposit
or the security, if any, furnished as the case may be and
also have a lien over the same pending finalisation or
adjudication of any such claim. In the event of the security
being insufficient to cover the claimed amount or amounts
or if no security has been taken from the Contractor, the
Purchaser shall be entitled to withhold and have lien to
retain to the extent of the such claimed amount or amounts
referred to supra, from any sum or sums found payable or
which at any time thereafter may become payable to the
Contractor under the same contract or any other contract
with the Purchaser or the Government pending finalisation
or adjudication of any such claim.
It is an agreed term of the contract that the sum of money
or moneys so withheld or retained under the lien referred
to above, by the Purchaser will be kept withheld or
retained as such by the Purchaser till the claim arising out
of or under the contract is determined by the Arbitrator (if
Page no. 11 of 21
901-ARBP-221-2023.doc
the contract is governed by the arbitration clause) or by the
competent court as prescribed under Clause 2703
hereinafter provided, as the case may be, and that the
Contractor will have no claim for interest or damages
whatsoever on any account in respect of such withholding
or retention under the lien referred to supra and duly
notified as such to the Contractor.”
15. Clause 2403 of the IRS terms and conditions is regarding
keeping liens in respect of claims arising under other contracts.
Even under this clause, the retention of the security deposit or
any payable amount may be withheld by placing a lien during
the adjudication of the purchaser's claim. Thus, raising a claim
to recover a sum is necessary to maintain a lien. In the present
case, the two purchase orders are under the same contract;
therefore, it is not necessary to discuss Clause 2403.
16. Thus, the only controversy to be decided in this
arbitration petition is whether, on the ground of a pending CBI
enquiry and the criminal prosecution regarding the payments
made under the second purchase order, the petitioner would
be entitled to withhold the amount payable under the first
purchase order by keeping a lien on the same.
Page no. 12 of 21
901-ARBP-221-2023.doc
17. Although the petitioner contends that the respondent
received the amounts under the second purchase order
through fraud and without supplying the material, the petitioner
has admittedly not invoked the arbitration clause to recover the
allegedly illegally released amount. The only ground raised by
the petitioner is that the petitioner would be entitled to withhold
the amount by placing a lien on it during the pendency of the
CBI prosecution.
18. The Hon’ble Apex Court in Vishnu Dutt Sharma held that
the judgment of a criminal court in a civil proceedings will only
have a limited application, that is,
inter alia, for the purpose of
determining who was the accused and what was the result of
the criminal proceedings. It is held that any finding in the
criminal proceeding by no stretch of imagination would be
binding in a civil proceeding. The Hon’ble Apex Court in the
case of
Shanti Kumar Panda held that a decision by a criminal
court does not bind the civil court and would be relevant only to
show in evidence the particulars of the dispute.
19. As per Black’s Law Dictionary, “A ‘lien’ is not a property
or right to the thing itself, but constitutes a charge or security
thereon”, and that “The word ‘lien’ is a generic term and,
Page no. 13 of 21
901-ARBP-221-2023.doc
standing alone, includes liens acquired by contract or by
operation of law”.
20. The Hon’ble Apex Court in the case of Board of Trustees
of the Port of Bombay held that the general lien contemplated
by Section 171 of the Contract Act only enables the retention of
the bailed goods as security. It is held that if the payment is not
made by the consignee to the wharfinger, in a case where
Section 171 of the Contract Act applies, the wharfinger can
only retain the goods bailed as security and will have to take
recourse to other proceedings in accordance with law for
securing an order which would then enable the goods to be
sold for realization of the amounts due to it. Thus, as held by
the Hon’ble Apex Court as per Section 171 of the Contract Act,
the retention of goods as security can be held as a lien.
21. In M/s. H.M. Kamaluddin Ansari & Co., the Hon’ble Apex
Court was considering the scope and ambit of Section 41 of the
Arbitration Act, 1940, regarding the procedure and powers of
the court, and the interpretation of Clause 18 of the standard
contract. The Apex Court held that an injunction order
restraining the Union of India from withholding the amount due
under other pending bills to the contractor would amount to a
Page no. 14 of 21
901-ARBP-221-2023.doc
direction to pay the amount to the contractor, and such an
order was clearly beyond the purview of clause (
b) of Section
41 of the Arbitration Act 1940. It was further held that Clause
18 of the standard contract conferred ample power upon the
Union of India to withhold the amount, and no injunction order
could be passed restraining the Union of India from withholding
the amount. However, it was held that Clause 18 merely
provided a mode of recovery and would have no application
where a claim, even though it be for a sum due and payable, is
disputed by the contractor and must be established in a Court
of law or by arbitration. Thus, it was held that Clause 18
applied only where a claim is either admitted or, in case of
dispute, substantiated by resort to the judicial process.
Therefore, when a purchaser had a claim for damages that the
contractor disputed, the purchaser was not entitled under
Clause 18 to recover the amount of its claim by appropriating
other sums due to the contractor until the claim for damages
was adjudicated and culminated in a decree.
22. Therefore, a lien can either be maintained under the
terms and conditions of a contract or by operation of law. In the
present case, the right to maintain a lien is invoked under the
Page no. 15 of 21
901-ARBP-221-2023.doc
terms and conditions of the contract. As per Clause 2401 of the
IRS terms and conditions applicable to the present contract,
whenever any claim or claims for payment of a sum of money
arises out of or under the contract against the contractor, the
purchaser shall be entitled to withhold and also have a lien to
retain such sum pending finalisation or adjudication of any such
claim. The said clause further provides that the sum of money
withheld or retained under the lien by the purchaser will remain
withheld or retained until the claim arising out of or under the
contract is determined by the Arbitrator or by the competent
court. Thus, the terms and conditions of the contract permit the
purchaser to retain a lien on the cash security or the claimed
amount until the claim is finalised or adjudicated. Therefore,
under the terms and conditions of the contract in this case,
filing a claim for adjudication is necessary to maintain a lien on
the security deposit or the sum payable.
23. In the present case, the petitioner has admittedly not
invoked the arbitration clause to recover the amount alleged to
have been released by playing fraud. Pendency of the criminal
prosecution initiated by CBI cannot be termed as adjudication
for recovery of the amount alleged to have been recovered
Page no. 16 of 21
901-ARBP-221-2023.doc
fraudulently by the respondent. In the criminal prosecution, the
petitioner’s entitlement to recover the amount from the
respondent would not be adjudicated. As per the well-settled
legal principles as discussed in the above paragraphs, the
findings recorded in criminal proceedings would not bind the
civil proceedings, if any, initiated by the petitioner to recover
the amount alleged to have been fraudulently recovered by the
respondent. Hence, the petitioner is not entitled to charge a
lien on the amounts due and payable for the goods admittedly
supplied under the first purchase order, by relying upon its right
to keep a lien on the ground that a criminal proceeding is
pending regarding the amounts recovered by the respondent
under the second purchase order.
24. The petitioner has refused to make payment on the
ground of invoking Clause 2401 of the IRS terms and
conditions applicable to the present contract, which provides
that whenever any claim or claims for payment of a sum of
money arises out of or under the contract against the
contractor, the purchaser shall be entitled to withhold and also
have a lien to retain such sum pending finalisation or
adjudication of any such claim. Therefore, for the petitioner to
Page no. 17 of 21
901-ARBP-221-2023.doc
withhold the amount payable to the respondent by keeping a
lien, in view of the terms of the contract, the following
ingredients must be satisfied:
a) A claim for payment of a sum of money arises out of or
under the contract against the contractor.
b) The purchaser, i.e., the petitioner, has filed a claim
invoking the arbitration clause in the contract.
c) A cash security deposit or other security is deposited by
the contractor.
d) If the security is insufficient, or if no security has been
taken from the contractor, the purchaser shall be entitled
to withhold the claimed amount from any sum or sums
found payable, or that may become payable, to the
contractor under the same contract or any other contract
with the purchaser.
25. Thus, it is clear that, as per the agreed terms of the
contract, the petitioner would be entitled to charge a lien on any
amount payable to the respondent under the same contract,
until the adjudication of the claim, provided the petitioner has
filed any claim by invoking the arbitration clause. Therefore, the
Page no. 18 of 21
901-ARBP-221-2023.doc
legal principles settled in M/s. H.M. Kamaluddin Ansari & Co.,
would not be of any assistance to the petitioner. Even in that
decision, the Apex Court, while interpreting the relevant clause
of the contract, held that the clause would apply only where a
claim is either admitted or, in the event of a dispute,
substantiated through the judicial process.
26. By the impugned Award, the arbitral tribunal allowed the
respondent’s claim towards non-payment of the cost of supply
of the material under the first purchase order. Both purchase
orders are under the same contract. Hence, the arbitral tribunal
rightly held that before withholding the payable amount, the
petitioner was required to notify the respondent as per Clause
2401, and the onus was on the petitioner to prove that any
show-cause notice or notification was served upon the
respondent. Since no such evidence was produced by the
petitioner, the arbitral tribunal held that the petitioner can
withhold the amount and have a lien on the due amount after
notifying the respondent in terms of Clause 2401, pending
finalisation or adjudication of the claim.
27. The petitioner has relied upon a copy of the intimation
letter dated 16
th
August 2019 produced in this court; however,
Page no. 19 of 21
901-ARBP-221-2023.doc
the petitioner has not filed any claim by invoking the arbitration
clause to recover the amount. In view of the well-established
legal principles as set out in the preceding paragraphs, the
pendency of the criminal prosecution regarding the alleged
fraudulent recovery of the amount by the respondent under the
second purchase order cannot be construed to mean the
pendency of an adjudication of a claim as per Clause 2401 of
the IRS terms and conditions. Admittedly, the material is
supplied by the respondent under the first purchase order. The
petitioner has not filed any claim to recover the amount alleged
to have been fraudulently recovered by the respondent under
the second purchase order. Therefore, the petitioner's
withholding of the amount by raising a lien on the amount
payable under the first purchase order would neither be valid
under the contract nor valid by operation of law. Thus, such an
intimation cannot be a ground to set aside the award.
28. I therefore find substance in the arguments raised by the
learned counsel for the respondent to support the impugned
award. The arbitral tribunal has adopted a judicious approach
by correctly interpreting Clause 2401 of the IRS terms and
conditions governing the contract between the parties. None of
Page no. 20 of 21
901-ARBP-221-2023.doc
the grounds contemplated under Section 34 of the Arbitration
Act to set aside an award are made out in this petition. Hence, I
see no reason to set aside the award.
29. The Arbitration Petition is therefore dismissed.
(GAURI GODSE, J.)
Page no. 21 of 21
Legal Notes
Add a Note....