No Acts & Articles mentioned in this case
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 1 of 40
REPORTABLE
* IN THE HIGH COURT OF DELHI AT NEW DELHI
I.A. No.1938/2009 in CS(OS) No.1447/2008
Date of Decision: August 20, 2009
UTTAM SUCROTECH INTERNATIONAL PVT. LTD.
..... Plaintiff
Through Mr. A.S. Chandhiok, Senior Advocate
with Ms. Pragyan Sharma, Ms. Shweta Kakkad
and Mr. Arjun Pratap, Advocates
versus
M/S OVERSEAS INFRASTRUCTURE ALLIANCE(I) PVT. LTD &
ANR ..... Defendants
Through Mr. Arun Bhardwaj, Sr. Advocate
with Mr. Manish Sharma, Advocate for D-1.
Mr. Sunil Gupta, Sr. Advocate with
Mr. Jatin Zaveri, Advocate for proposed
defendant No.3.
Mr. P.P.Malhotra, ASG with Mr. Sudarsh
Menon, Advocate for proposed defendant
No.4.
CORAM:
HON'BLE MISS JUSTICE REKHA SHARMA
1. Whether the reporters of local papers may be allowed to see the
judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported in the „Digest‟? Yes
REKHA SHARMA , J.
Three applications, one under Order 6 Rule 17 read with Order
1 Rule 10, another under Order 39 Rules 1 & 2 and the third under
Order 39 Rule 4 of the Code of Civil Procedure (hereinafter referred
to as the Code) seemingly simple have been a witness to ma rathon
sessions of arguments. Mercifully , arguments on the application
under Order 6 Rule 17 read with Order 1 Rule 10 of the Code have
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 2 of 40
concluded and though the other two applications are still to see
conclusion of arguments, I am proceeding with the order on the
application seeking amendment of the plaint and impleading of two
new parties namely Walchandnagar Industries Ltd. and the Export -
Import Bank of India (hereinafter referred to as the EXIM Bank). But
first, the background.
The Government of Ethiopia decided to establish at Addis Ababa
new Sugar factories and expansion of existing Sugar factories for
three Sugar Projects, namely, Tendaho Sugar Factory, Finchaa Sugar
Factory and Wonj/Shoa Sugar Factory. Each factory project was
sub-divided into major packages of plant and machinery like Juice
Extraction Plant, Steam Generation Plant, Power Generation Plant,
Process House Equipments, Plant Water Systems, Civil Work, Effluent
Treatment Plants and other utilities etc. The project is being funded
by the Government of India through EXIM Bank to the tune of
US $ 122,000,000 (Dollars one hundred twenty two million) on certain
terms and conditions which were reduced into writing by means of a
Dollar Credit-line Agreement dated October 04 , 2007 between the
Government of the Federal Democratic Republic of Ethiopia and EXIM
Bank. In order to give effect to the project, defendant No.2, namely,
Tendaho Sugar Factory Project which is a company incorporated
under the laws of Ethiopia and is owned and controlled by the
Government of the Federal Democratic Republic of Ethiopia , invited
tenders for Juice Extraction Plant, Steam Generation Plant, Power
Generation Plant, Process Home Plant and related modernization
packages. The plaintiff and some othe r companies including
defendant No.1, namely, M/s. Overseas Infrastructure Alliance (India)
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 3 of 40
Pvt. Ltd. responded to the invitation of tenders by submitting their
respective bids. The bid of the plaintiff was accepted for Process
House vide a communication from defendant No.2 , dated
December 7, 2007. In so far as defendant No.1 is concerned , it
succeeded in procuring two contracts, namely, Juice Extraction Plant
and Power Generation Plant. This acceptance of two bids of
defendant No.1 brought into play the „EXIM Bank Disbursement
Schedule‟, under which it was necessary to proceed through a single
Engineering, Projects Management and Construction (hereinafter
called the EPC) Contract method. As per this method, any bidder who
won two or more bid packages became eligible to act as a `Single EPC
Contractor”. Since defendant No.1 had won two bids , it was
appointed to act as `Single EPC Contractor‟. The plaintiff was
informed about this appointment of defendant No.1 by defendant No.2
through a communication dated December 07 , 2007. The plaintiff
was also informed that, “being a winning bidder of Process House, it
will be retained as a sub-contractor to the main EPC Contractor
without any alteration in the agreed technical and commercial aspects
including the time schedule, as already negotiated and finalized.” On
the same date defendant No.2 also sent a letter to defendant No.1
intimating it about its appointment as „Single EPC Contractor‟, with
the stipulation that the winning bidders of other packages were to be
retained as sub-contractors without any alteration in the agreed
technical and financial aspects as already finalized with individual
bidders.
It is thus the case of the plaintiff that it was to act as a
sub-contractor to the EPC contractor, that is, defendant No.1 without
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 4 of 40
any alterations in the agreed financial and technical aspects which, as
per it, stood already finalized with defendant No.2. It is also its‟ case
that in order to finalize the type of contract agreement to be signed
between the EPC contractor and the winning bidders of other
packages, a joint meeting between the plaintiff, defendant No.1 and
defendant No.2 was held on 19
th
& 20
th
December, 2007 at Addis
Ababa in which it was categorically agreed that a contract would be
entered into between defendant No.1 and the sub -contractors which
would be seamless and address all issues as per the original tender
documents including General Conditions of Contract , Special
Conditions of Contract and other financial conditions. Thereafter, as
per the plaintiff, a ‘Contract Agreement’ dated February 20, 2008 was
executed between defendant No.1 and defendant No.2 and one of the
clauses of the said contract agreement was that the appendices listed
in the attached list of appendices shall be deemed to form an integral
part of the agreement. Referring to Appendix-5, it is pointed out that
it contained a list of approved sub-contractors where the name of the
plaintiff appeared at serial No.7 against „Process House‟ and it was
mentioned therein that, “the Contractor, to the extent possible, shall
have seamless contracts with the sub-contractors.”
It is alleged that notwithstanding the obligation cast upon
defendant No.1 to enter into an agreement with the plaintiff withou t
effecting any changes in the financial and technical aspects of its bid
which stood already accepted by defendant No.2 and inspite of having
agreed to abide by those terms and conditions in the joint meeting of
19
th
& 20
th
December, 2007 and in the contract agreement dated
February 20, 2008, referred to above, defendant No.1 insisted upon
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 5 of 40
the plaintiff to reduce its price by 15%, on the pretext that it was
required to be paid to it to discharge its obligation of a lead
contractor. In other words, as per the plaintiff, defendant No.1
attempted to re-negotiate the contract price which it legally could not
do and that when it refused to give in to the alleged illegal demand of
defendant No.1, it threatened to introduce a new sub-contractor in its
place. It is this threat which has given birth to this suit for mandatory
injunction wherein the plaintiff has pleaded that it has a concluded
contract with defendant No.2 and that defendant No.1 is bound to and
liable to give effect to the concluded contract. It is also pleaded that
the status of defendant No.1 is no better than that of the plaintiff, as
the tenders of both the plaintiff and defendant No.1 have been
accepted by defendant No.2 with the only difference that defendant
No.1 has been described as an EPC or a lead contractor, for the sole
reason that it succeeded in securing two contracts. The plaintiff ,
thus, has alleged that defendant No.1 by threatening to introduce
another sub-contractor in its place is tortuously interfering in its
contract with defendant No.2. Accordingly , it has prayed for the
following reliefs:-
“(a) grant a decree of perpetual injunction restraining
defendant No.1 from interfering in the contract/award
of contract between plaintiff and defendant No.2;
(b) grant perpetual injunction restraining defendant
No.1 from modifying any technical and/or commercial
terms including price agreed/finalized between the
plaintiff and defendant No.2;
(c) grant perpetual injunction restraining the
defendant no.1 from engagi ng any third party in
respect of the Process House Project.
(d) grant a decree of mandatory injunction directing
defendant No.1 to execute the obligation of signing a
formal contract with the plaintiff in accordance with
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 6 of 40
the terms and conditions agreed between the plaintiff
and defendant No.2 as contained in letter dated
December 7, 2007;
(e) costs; and
(f) pass such further order/ as this Hon‟ble Court
may deem fit and proper in the facts and circumstances
of the case.”
Along with the suit, the plaintiff also filed an application under
Order 39 Rules 1 & 2 of the Code, on which a learned Single Judge of
this Court passed an order dated July 30, 2008 restraining defendant
No.1 from taking any measures to introduce a third party in respect of
the tender floated by defendant No.2 for Process House for which the
plaintiff has been accepted by defendant No.2 as a successful bidder.
In response to the summons , defendant No.1 has filed written
statement while defendant No.2 has chosen to remain absent d espite
service of summons upon it.
It is alleged by defendant No.1 that there is no concluded
contract between the plaintiff and defendant No.2, as the detailed
terms and conditions governing the construction of the plant were
never settled and they never entered into any formal contract. It is
further alleged that as the plaintiff was delaying the finalization of the
terms of the sub-contract to be awarded in its favour this was brought
to the notice of defendant No.2 who authorized defendant No.1 to
write a letter to the sub-contractors giving them a last chance to
finalize the contract agreement between the EPC contractor and the
sub-contractors within a week and submit the document on
June 28, 2008 failing which defendant No.1 could approach defendant
No.2 with an alternative sub-contractor. The case of defendant No.1 is
that in furtherance of the said direction given by defendant No.2, it
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 7 of 40
addressed an e-mail dated June 21, 2008 to the plaintiff informing it
that defendant No.2 had given a dead line of June 27, 2008 as the
date by which it was expected to resolve all the pending issues as well
as signing of the contract. As per defendant No.1, the plaintiff failed
to meet the dead-line and settle the terms of the said contract and as
a result defendant No.1 entered into a „Memorandum of
Understanding‟ dated July 08, 2008 with Walchandnagar Industries
Ltd. for the construction of ‘ Process House‟ followed by a sub-
contract agreement dated July 12 , 2008. It is also the case of
defendant No.1 that the plaintiff was fully aware of said sub-contract
agreement and yet it chose to suppress this fact and obtained an
order dated July 30, 2008. It may not be out of place to mention here
that defendant No.1 has also challenged the territorial jurisdiction of
this court not only on the ground that the project is to be executed
outside the territorial limit of this court but also on the ground that no
part of action has arisen at Delhi. Of-course, it is further alleged that
as per clause-6 of the General Conditions of Contract contained in the
EPC Contract document, any dispute of any kind whatsoever between
the employer and the contractor in connection with or arising out of
the contract shall be referred in writing by either party to an
Arbitrator. It is further stated that the reliefs claimed are in the
nature of enforcement of specific performance of a contract and
cannot be granted in view of Sections 41(e) & 41(h) of Specific Relief
Act, 1963.
Having provided with the necessary backg round, let me revert
back to the application of the plaintiff under Order 6 Rule 17 and
under Order 1 Rule 10 of the Code. The plaintiff alleges therein that
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 8 of 40
the so-called „Memorandum of Understanding‟ dated July 08 , 2008
between defendant No.1 and Walchan dnagar Industries Ltd. and
pursuant thereto the alleged definite contract signed between them
on July 12, 2008 are forged and fabricated documents which have
been antedated to frustrate and over-reach the above-referred interim
order passed by this Court on July 30, 2008 which was duly served on
defendant No.1. It is further stated that the fabrication and forgery
committed by defendant No.1 in connivance with Walchandnagar
Industries Limited can be seen through from the fact that though the
alleged „Memorandum of Understanding‟ dated July 08 , 2008 was to
remain valid for a period of 30 days, yet, within just four days of the
signing of the „Memorandum of Understanding‟ , a purported definite
contract was, allegedly, signed on July 12, 2008. As for the
sub-contract dated July 12, 2008 allegedly entered into between
defendant No.1 and Walchandnagar Industries Limited , it is stated
that it makes even those documents to be part of the contract which
had not been finalized and were only proposed , such as, “Minutes of
Package Negotiations meeting (proposed) to be held between the
Employer and Sub -contractor (WIL) for the Package Facilities on
technical aspects”, showing thereby, that the sub-contract was
prepared after receiving the ex-parte order passed by this Court.
That the said documents are forged is further sought to be proved
from the fact that as late as on August 05, 2008 in a meeting held
between defendant No.1 and defendant No.2 , there was no mention
that a definite contract had been signed with Walchandnagar
Industries Ltd. Reference in this regard has been made to the
Minutes of the meeting dated August 05, 2008 which, it is alleged, go
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 9 of 40
to show that defendant No.1 merely informed defendant No.2 that
only negotiations were bein g conducted with Walchandnagar
Industries Limited. Reference has also been made to a letter dated
August 05, 2008 from defendant No.1 to defendant No.2 , though its
authenticity is being disputed. It is stated that as per this letter,
assuming the same to be correct, it was on August 05, 2008 that
defendant No.1 had accepted the proposal of defendant No.2 to
substitute Walchandnagar Industries Limited, showing again that the
alleged „Memorandum of Understanding‟ dated July 08 , 2008 and the
purported definite contract dated July 12, 2008 are forged documents.
In a nutshell, the case of the plaintiff is that defendant no.1 in concert
with and Walchandnagar Industries Ltd., is clandestinely introducing
Walchandnagar Industries Ltd. as a sub-contractor in its place. Since
Walchandnagar Industries Ltd. will be effected by the present
proceedings, it is also being sought to be impleaded as one of the
defendant.
The impleadment of EXIM Bank as defendant No.4 is sought on
the ground that since the approval and disbursal of funds would be
done through EXIM bank, it is important that the same be also
impleaded as a party in the suit.
The facts contained in the application for
„amendment-cum-impleadment‟ are sought to be incorporated in the
original plaint by adding paragraph 7 A after paragraph 7, 16 A after
paragraph 16 and paragraphs 20 (A ) to 20 (W) after paragraph 20.
The said paragraphs run as under:-
Para 7 A:- As is evident from the internal letter
dated 03.12.2007 issued by TSFT to TSFP
Management Board Addis Abava, defendant no.1
have been trying to defeat the rights of the
plaintiff at very stage so as to oust the plaintiff
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 10 of 40
from the subject project completely. The said
letter clearly reveals that apart from the process
house package which was allotted to the plaintiff,
vide defendant no. 2‟s letter dated 07.12.2007, the
plaintiff was also the lowest bidder in the power
generation plant which was also ought to have
been awarded to the plaintiff. So plaintiff was
awarded both the process h ouse and power
generation plant bid and was eligible to be
appointed as a EPC contractor. However,
strangely, just about four days later i.e. on
7.12.2007, facts and records were illegally pruned
to a large extent and the plaintiff was declared
winning bidder only in the process house package
and not in the power generation package.
Para 16A:-
The defendant no.2 is also acting malafide and is
acting in concert with other defendants to
perpetrate a fraud on the plaintiff and defeat and
disobey the orders of this Hon‟ble Court.
Para 20 A:-
In the agreement between defendant no.1 and
defendant no.2 and/or the plaintiff, there exist a
positive covenant coupled with an implied
negative covenant which the defendant no.1 is
threatening to breach. The Hon‟ble Court ought to
grant injunction to perform the negative covenant.
The implied negative covenant is contained in
letter dated 07.12.2007 from defendant no.2,
which is the same letter, by which the defendant
no.1 takes on its responsibilities as a single EPC
contractor. It is further submitted that these
responsibilities and conditions were integral to the
defendant no.1 being appointed the EPC
contractor by the defendant no.2. The relevant
portion has been extracted hereunder:-
“The winning bidders of other packages are to be
retained as sub-contractors without any alteration
in the agreed technical and financial aspects as
already finalized with individual bidders.”
Further in letter dated 07.12.2007 from defendant
no. 2 to plaintiff it is stated:-
“You as winning bidder of process house bid,
Tender No.TSFP-F/007/07/PH, will be retained as
sub-contractor to be main EPC contractor without
any alteration in the agreed technical and
commercial process including the time schedule,
as per a bid document and su bsequent
clarifications given by our consultant, JPMA.”
Further it is evident from the joint meeting, inter-
alia, plaintiff, defendant no.1 and defendant no. 2:-
“All winning bidders were informed that as per the
directive from Government of Ethopia, the
Management of TSFP and FSF intend to appoint
one single EPC contractor and all other winner
bidders shall work as sub -contractor to the
proposed single EPC contractor.”
“Contract agreement between EPC contractor and
winner bidder shall be seamless and ad dress all
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 11 of 40
issues as per original tender documents including
GCC, SCC and other financial conditions.”
The aforesaid clauses clearly stipulates that the
defendant no.1 by way of an implied negative
covenant was not permitted to modify and/or
attempt to m odify any agreed technical,
commercial including price aspects already
finalized between the plaintiff and defendant no.2.
20B. that the purported MOU dated 8
th
July, 2008
and sub-contract agreement of 12
th
July, 2008
between defendant no.1 and Walchan dnagar
Industries Ltd. are clearly antedated and have
been fabricated with a view to frustrate and/or to
overreach the injunction order dated 30.07.2008
passed by this Hon‟ble Court.
20C. That in the written statement filed by the
defendant no.1 it has b een alleged that a
Memorandum of Understanding was signed
between defendant no.1 and Walchandnagar
Industries Ltd. on 8
th
July, 2008, and thereafter, a
definite purported contract was signed on 12
th
July, 2008, that is within four days of the MOU
despite the MOU being valid for a period of 30
days, and not withstanding that the defendant no.1
proposed the name of defendant no.3 to defendant
no.2 long after 12
th
July, 2008.
20D. The alleged sub-Contract Agreement dated
12
th
July, 2008 filed by defendant no.1, defendant
nos.1 and 3 have purported to create a definition
of “Contract documents” which includes
documents that have not yet been finalized but are
only „proposed‟. One of the documents forming
part of contract documents is “minutes of package
negotiations meeting (proposed) to be held
between employer and sub -contractor (WIL), for
the package facilities on technical aspects”.
Firstly, there cannot be a meeting or minutes of a
meeting which are qualified as “proposed”.
Secondly, there cannot be minutes of a meeting
which is yet “to be held”. It is obvious that
documents have been prepared in a hurry only to
be produced before this Hon‟ble Court, with a view
to mislead this Hon‟ble Court and to frustrate and
overreach the orders of this Hon‟ble Court.
20E. In fact, defendant no.1 as itself subsequently
filed a letter dated 5
th
August, 2009 purportedly
issued by defendant no.2 permitting the defendant
no. 2 to substitute the plaintiff (though the
authenticity of the said letter is denied). The said
letter clearly reveals that even as late as on 5
th
August, 2008, in the meeting between defendant
no.1 and defendant no.2, there is no mention that
a definite contract has been signed with
Walchandnagar Industries Ltd. in fact defendant
no.1 informed defend ant no.2 that only
negotiations were being conducted with
Walchandnagar Industries Ltd.
20F. That the contents and tenor of the letter
dated 5.08.2008 issued by defendant no.2 to
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 12 of 40
defendant no.1 clearly substantiates the fact that
the alleged MOU dated 8.0 7.2008 and also the
alleged sub-contract agreement dated 12.07.2008
have been fabricated and anti dated with malafide
intention. The letter dated 05.08.2008 specifically
states that it was only in a joint meeting dated
10.7.2008 held under the Chairmanship of the
Minister of Trade, that it was decided to consider
substitute sub-contractor proposed by OIA. The
letter clearly states thus:
“We refer to the joint meeting dated July
10, 2008, held under the Chairmanship of his
Excellency the Minister of Tra de and Industry,
whereby it was decided to consider substitute sub-
contractors/consortium partners proposed by OIA
and conduct technical evaluation of substitute
offers for the subject packages.”
However, as stated by defendant no.1 themselves
in their written statement they had entered into an
MOU on 8.07.2008 (which is even two days pr ior
to the proposed decision to substitute, which was
only taken on 10.07.2008). It is submitted that the
decision to consider substitute sub -
contractors/consortium partners was taken only on
10.07.2008 and thus there could have been no
MOU on 8.07.2008 between defendant no.1 and
WIL in as much as the defendant no.1 had no
authority to enter into any agreement with WIL
prior to the alleged approval of defendant no. 2 for
changing the sub-contractor. Therefore this clearly
reveals that the alleged MOU was illegal and void
ab-initio.
20G. That, the letter dated 5.08.2008 states as
under:
“In line with the above, TSFP has given original
bid documents and invited OIA to sub mit
substitute technical offers for subject packages on
July 11, 2008. Substitute offers were opened in
the presence of Tender Committee of TSFP,
consultant‟s and bidder‟s representatives on July,
18, 2008.”
Strangely defendant no.2 gave the original bi d
documents and invited/directed the defendant no.
1 to submit substitute technical offers for
packages on 11.07.2008 i.e. just one day after
defendant no. 2 decided to consider sub -
contractors.
20H. The letter further states thus,
“TSFP is pleased t o inform you that Art of
management is hereby accepted your substitute
technical offer dated 18
th
July, 2008 for above
packages with Walchandnagar Industries Ltd.
(WIL) as sub-contractor abiding to technical
specification given in our bid documents and
minutes of technical negotiation meeting held on
August 4 and 5 2008, for turnkey supply, erection
and commissioning with manpower training for
both phase I and II of the project”.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 13 of 40
As stated above the sub-contractor agreement was
allegedly executed on 12.07.2008. The technical
offer allegedly accepted only on 05.08.2008.
Glaring infirmities and illegalities in the alleged
agreement dated 12.7.2008 and further
highlighted by the fact that offers of WIL bidding
as OIA‟s sub-contractor was opened and accepted
by the defendant no.2 only on 5.8.2008, so how
could a contract between defendant no.1 and WIL
(defendant no.3) as contractor and sub contractor
can claimed to have been entered into on
12.07.2008 which is completely arbitrary and
devoid of any merits. This clearly demonstrates
that the defendant no. 1 has filed a false affidavit
and has committed an act of perjury. This further
reveals the glaring infirmities and illegalities in
the alleged sub -contractor agreement dated
12.7.2008.
20L. Furthermore, the contract dated 12.07.2008
is only antedated, it is void inasmuch as it fraught
with false and misleading contents, which is
clearly evident from Clause 4 of the said
agreement, which provides as under:-
“Article 4 Technical Conditions
The technical aspects of the project as already
agreed between the Employer and the Sub -
contractor shall not be altered and shall be
adhered to by the sub-contractor”.
The said clause portrays as if the technical aspects
had already been agreed upon prior to 12.7.2008,
whereas allegedly the technical aspects of the
project was agreed only allegedly vide the Letter
dated 5.8.2008. This fact clearly demonstrates that
the said sub-contract was antedated in as much as
on 12.7.2008, the technical aspects of the project
between the Employer and the sub-contractor qua
the project in question was never accepted.
20J. That even as late as on 4
th
or the 5
th
August,
2008, in the meeting between the defendant no.1
and defendant no.2, there is no mention that a
definite agreement had been signed with
Walchandnagar Industries ltd. In fact the letter
dated 5.8.2008 clearly states that the technical
negotiation meetings were held on August 4 and 5,
2008 with OIA-WIL experts. It is further revealed
from the minutes of tender committee meeting
dated 5.08.2008, that on 5.08.2008, the evaluation
report submitted by the consultants was
forwarded to the General Manager for approval of
substitute offers of defendant no.1 – defendant
no.3. Therefore, there is no way in which a definite
contract could have been entered into with WIL
And even if assuming but not admitting that a
contract was entered into between OIA and WIL
such a contract prior to 5.8.2008, would be illegal,
null and void in the eyes of law.
20K. The minutes of the tender committee
meeting dated 5.8.2008 further record as follows:
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 14 of 40
“e) Detailed technical & commercial
negotiations were held thoroughly between OIA -
WIL, TSFP technical committee members and
consultants team regarding the deviations
specified in the tender documents by OIA.
Therefore, this clearly reveals that the defendant
no.1 has been deliberately violating the stay order
dated 30.07.2008 passed by this Hon‟ble Court
and in complete violation of the same has been
taking active measures to substitute defendant
no.3 instead of the plaintiff. It is further pertinent
to mention herein that the defendants actively
participated in the technical negotiations meeting
held on 4.08.2008 and the minutes of the said
meeting clearly bears the signatures of the
representatives of the defendant no.1 and the
stamp of the defendant no.1.
20L. That assuming but not conceding the alleged
sub-contract agreement dated 12.7.2008, as per
its own terms and conditions could not become
effective without approval from the employer,
which was allegedly granted only on 5.8.2008. The
said approval on the face of it is Nullis juris and in
the teeth of the injunction operating.
20M. That Article 3 of the alleged agreement
dated 12.7.2008 clearly demonstrates that the
same has been ante -dated. In fact, the said
agreement has not become effective even today
and hence has no legal validity. Article 3 has been
extracted hereunder to illustrate the point further:
“Article 3 Effective Date
The subcontract agreement shall become effective
when all of the following conditions are fulfilled to
the satisfaction of the EPC contractor:
a) This Contract Agreement has been duly and validly
executed by both parties and a duly authorized
counter copy is exchanged between the parties
hereto.
b) The subcontractor has submitted to the Employer
(through the EPC Contractor) the Performance
Security and the Advance Payment Guarantee as
specified in Appendix 9-10 attached herein for the
value defined in SCC and GCC;
c) The EPC contractor has paid 10% of the Contract
value to the sub-contractor as the advance
payment.
d) Technical and commercial approval of WIL by the
Employer”
It is submitted that Sub-Clause (b), (c) and (d) of
the said Article 3 is yet to be fulfilled till date in as
much as inter-alia the performance security and
the advance payment as stipulated under the
Agreement has not been made and neither have
the technical and commercial approvals as
required been granted. It is submitted that the
alleged technical approval was as required under
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 15 of 40
the clause was granted if at all, only on 5.8.2008
and not before and the same was in blatant
disregard and violation of the order dated
30.7.2008 passed by this Hon‟ble Court. No
commercial approval of the appropriate value was
granted. No payment has been made by the
Defendant no. 2 to WIL.
20N. Furthermore, despite being specifically
restrained by this Hon‟ble Court, the defendant
no.1, in furtherance of its malafide intentions of
appointing M/s Walchandnagar Industries ltd.
deliberately violated the said Order and attended
the technical negotiation meetings on 4
th
and 5
th
August, 2008. The Minutes of the meeting dt.
4.8.2008 bears the signatures of representatives of
the defendant no.1 and the Delhi office stamp of
the Defendant no.1. Therefore, the alleged
technical approval dated 5.8.2008 being in clear
disregard to the Order passed by this Hon‟ble
Court is illegal and bad in law, which consequently
also implies that another essential criteria
stipulated under Article 3 (d) of the agreement
dated 12.7.2008 also has not been fulfilled.
20O. That further, assuming but not conceding
that the alleged contract dated 12.7.2008 had
been entered into, and the approval was granted
on 5.8.2008, yet the said contract is invalid and
null and void in the eyes of law. It is submitted
that the alleged approval dated 5.8.2008 clearly
states that the prices for the substitute packages
shall be as per the main contract dated 10
th
January 2008 executed between defendant no.2
and defendant no.1, which is admittedly US $ 65
million, however under the said agreement dated
12.7.2008 it has been specifically provided under
Clause 2.1 as only 2.1 Million. Therefore, there are
huge discrepancies and contradictions between
the terms of the approval and the contract dated
12.07.2008 and it is not known as to where would
these monies which are actually public Indian
funds be used for is not known.
20P. That clearly the said letter dated 5
th
August,
issued by defendant no.2 permitting the defendant
no.2 to substitute the plaintiff shows that there
could be no contract between defendant no.1 and
the said Walchandnagar Industries Ltd. prior
thereto and further that defendant no.1 and 2
were acting in concert and were completely aware
of the order dated 20
th
July, 2009 passed by this
Hon‟ble Court which is in force even till date.
20Q. Further, and in any event, the defendant no.2
has not been shown to have ever authorized till
end June/July 2008, appointment of the said
Walchandnagar Industries Ltd. as a sub-contractor
in substitution of the plaintiff. This is also apparent
form the letter dated 30.6.2008 written by
defendant no.2 to its board of Management on
30.6.2008 which clearly reveal that the minutes
dated 19.6.2008 and 20.6.2008 and the letter
dated 16.6.2008 sought to be relied upon by the
defendant no.1 did not constitute any approval of
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 16 of 40
substituting the plaintiff as alleged by the
defendant no.1. The defendant no.1 is clearly
suppressing all material facts as the aforesaid
documents are within the knowledge of defendant
no.1 who has chosen to conceal the same from this
Hon'ble Court. Assuming without conceding,
neither the negotiations nor the minutes and/or
any alleged MOU could have been entered into or
be given effect to in view of clear restraint
imposed by the order dated 30.7.2008 passe d by
this Hon'ble Court and the defendant no.1 ought
not to be permitted to defeat the bonafide rights of
the plaintiff and/or overreach this Hon'ble Court.
20R The petitioner recently discovered that a
consortium Agreement dated 16.7.2008 was
entered into between the defendant no.1 and
defendant no.3, wherein it was agreed that the
parties would enter into a definitive transaction
agreement subsequently. The relevant clause of
the said Consortium Agreement has been
extracted hereunder;
“3) The parties shall enter into a
“definitive transaction agreement” on being
qualified by the Employer. The “definitive
transaction agreement” shall include all terms and
conditions to implement the packages including
the payment mechanisms”.
Therefore, a bare perusal of the said Consortium
agreement clearly reveals that prior to 16.7.2008
no agreement had come into existence and in fact
a subsequent agreement had to be entered into,
which never happened. In fact, the agreement
dated 16.7.2008 has actually been notarized on
28.7.2008, which is the date on which it becomes
effective. The consortium agreement further
reveals that till 28.7.2008 no price had been
agreed to between the parties, whereas in the
alleged contract dated 12.7.2008, the price has
been specified under clause 2.1 and 2.2 therein.
20S. That in furtherance of their illegal designs
and malafide intentions defendant no. 1 and 2 on
15.9.2008 made amendment in the contract
agreement dated 10.1.2008 allegedly entered into
inter-se in an attempt to oust the plaintiff from the
entire project. The name of the plaintiff has been
allegedly substituted by joint names of defendant
no.1 and defendant no.3. in the garb of defendant
no.3, it is defendant no.1 who has attempted to
substitute the plaintiff.
20T. It is relevant to note that in a similar
contract, which relates to another Govt. of
Ethiopia company known as Wonji Shoa Sugar
Factory, where the plaintiff has been appointed as
the EPC Contractor, it has entered into contracts
with the sub-contractors without making any
demand for 15% of contract price for discharge of
its obligations as a lead EPC/Contractor.
It has subsequently, now come to the knowledge of
the plaintiff that defendant no.1 was not even
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 17 of 40
entitled to become the EPC contractor and the
defendant no.1 and 2 have manipulated records to
make defendant no.1 become the EPC contractor
who is demanding unreasonable and absolutely
uncalled for 15% of the contract price from
plaintiff and other similarly placed sub -
contractors. It is further submitted that defendant
nos.1,2 and the said Walchandnagar Industries
Ltd. are acting in concert and are attempting to
defeat the order of this Hon'ble Court and
perpetrate a fraud which they cannot be permitted
to do.
20U. The attempt of defendant no.1 of
clandestinely introducing the purported sub -
contractor who did not even participate in the
tender, is not only contrary to the entire tender
process but is also mala fide and an attempt to
over-reach the orders passed by this Hon'ble
Court. Further, till date no termination of
plaintiff‟s sub-contract has ever been
communicated.
20V. The aforesaid facts clearly reveal that the
purported sub-contract agreement dated 12
th
July,
2008, which was allegedly entered into within four
days of signing the Memorand um of
Understanding which were valid for 30 days is
clearly ante-dated with a view to defeat the
injunction order passed by this Hon'ble Court. The
said purported sub-contract agreement cannot be
permitted to be implemented and be proceeded
with and being in complete violation of the order
dated 30
th
July, 2008 is void ab-initio. Even the
purported permission dated 5
th
August, 2008
cannot be acted upon and is void ab -initio as
defendant no.2 was also informed of the order
dated 30
th
July, 2008.
20W. That defendant nos.1, 2 and 3 are acting in
concert and are attempting to over -reach the
issues pending before this Hon'ble Court and
perpetrate a fraud which they cannot be permitted
to do.
The plaintiff is also seeking to amend paragraphs 2, 10, 11, 12,
15, 17 and 20. Those paragraphs run as under:
Para 2:-
That the defendant no.1 is a company incorporated
under the Companies Act 1956 having its
registered office at 1205, Surya Kiran Building, 19,
Kasturba Gandhi Marg, New Delhi -110001. The
defendant no.2 incorporated under the laws of
Ethopia having its principle office at Addis Ababa
and/or controlled by Government of Federal
Democratic Republic of Ethopia. The defendant
no.3 is a company incorporated under the
Company Act, and having its registered office at 3
Walchand Terracescopp Air Conditioned Market,
Tardeo, Mumbai, Maharashtra -40034 and branch
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 18 of 40
office at 201, Milap Niketan (2
nd
Floor), 8-A,
Bahadur Shah Zafar Marg, New Delhi: 110002.
That the defendant no.4 is the EXIM bank having
its registered office at Centre One Building, Floor
21, World Trade Centre Complex, Cuffe Parade,
Mumbai.
xxxxxxxx
xxxxxxxx
Para 10:-
That therefore the defendant no.1 clearly agreed
to the unanimous decision taken in the
aforementioned meetings dated 19
th
and 20
th
of
December to the effect that the contract shall be
seamless and that the rights of the winning
bidders and their bid award prices shall be
adequately protected in the sub -contractor
agreement. In view thereof, the defendant no.1 ,
was under a legal obligation to finalize the modus
of implementing all the various packages (sub -
contracts) of the project along with his own award
of work/contract. The defendant no.1 was further
required to do so at the earliest and one the same
terms and conditions as agreed to between the
parties to the said meetings inter alia the plaintiff,
defendant no.1 and the defendant no.2 in the
aforementioned meetings. Further an agreement
dated 10.1.2008 was entered into between the
defendant no.1 and defendant no.2, wherein the
name of the plaintiff was clearly mentioned as a
sub contractor albeit only for Process House
Package. The said contract contains Technical Bid
Commitments and Tender Bid Prices, which have
been clearly conducted between the plaintiff and
the defendant no.2, and which form an integral par
of the said contract between the defendant no.1
and defendant no.2. In fact, in the Process House
Packages Technical and commercial annexures, it
is clerly stated that these are as submitted by
USIPL (short for Utta Suc rotech International
Private Limited) and form an integral part of the
contract. In the said contract it had been
specifically agreed that there shall be a contract
between the contractor and the sub contractor and
that the agreement shall be entered into without
any alteration in the agreed technical and
commercial aspects of the original tender
documents including the price of the bids. It has
been alleged that the terms of the sid Agreement
dated 10.01.2008, were changed without the
consent of the plaintiff vide an Addendum No.1
dated 21.2.2008. Therefore, without prejudice, the
mother contract of 10.1.2008 could not have been
altered vide any addendum as alleged without
involving the plaintiff and obtaining its consent,
and any such addendum subsequentl y altering the
terms and conditions of the said agreement is
illegal, null and void.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 19 of 40
Para 11:-
“That subsequently it was also revealed that on
20
th
February, 2008 a contract was executed
between the defendant no.2, Ethiopia on behalf of
Government of Federal Democratic Republic of
Ethiopia and the defendant no.1. In the said
agreement also it has been agreed that there shall
be a contract between the contractor and the sub
contractor and that the agreement shall be
entered into without any alternation in the agreed
technical and commercial aspects of the original
tender documents including the price of the bids.
Para 12:-
That therefore in accordance with the procedure
agreed and settled on 19
th
December and 20
th
December, 2007 and also in view of the directions
of the defendant no.2, a formal seamless contract
was required to be entered into between the
plaintiff and defendant no.1 at the earliest, on the
same terms and conditions as those of the original
tender documents. It is further pertinent t o
mention herein that a binding contract had already
come into existence between the defendant no.2
and the plaintiff vide the letter dated 712.2007
which was preceded by detailed technical and
commercial meetings between defendant no.2 and
plaintiff and also the contract dated 10.1.2008 on
the same terms and conditions as per the original
bid documents on the basis of which the plaintiff
had prepared and pt in its bid. Therefore, no
alternations whatsoever could have been made in
the same.
xxxxxxxx
xxxxxxxx
Para 15:-
“That the plaintiff, vide their letter dated
26.3.2008 replied to the aforesaid letter dated
6.3.2008 issued by the defendant no.1 specifically
stating that the demand of the defendant no.1
directing the plaintiff to discount its offer price at
least by 15% , is absolutely illegal and contrary to
the terms agreed between the parties including
the defendant no.1,2 and the plaintiff in the
meetings dated 19
th
December and 20
th
December,
2007 and also vide the letter dated 7.12.2007,
which created a formal concluded and binding
contract between the plaintiff and the defendant
no.2 in terms of the instruction to Bidders issued
along with the tender documents.
Para 17:-
“That even, the draft of agreement received from
the defendant no.1 by the plaintiff on 16.4.2008,
failed to consider the submissions made by the
plaintiff. The said draft was contrary to the
agreement arrived at the joint Session Meeting
held on 19
th
and 20
th
December, 2007, and the
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 20 of 40
same was pointed out to the defendant no.1 by the
plaintiff. The defendant no. 1 most significantly,
attempted to renegotiate the contract price to be
able to receive a part thereof for discharging its
obligation of a lead contractor. Not only the
renegotiation of price was contrary to the mandate
of defendant no.2 and the agreement between the
plaintiff and the Sugar Factor Project as well as
the minutes of 19
th
and 20
th
December, 2007, and
also the letter dated 7.12.2007 but also the
defendant no.1 is stopped from claiming any
moneys from the plaintiff to discharge his own
obligations to the defendant no.2 as a lead
contractor after having accepted the said
contract/duty without recourse to additional
consideration from the plaintiff expressly and/or
by conduct.”
XXXXXX
XXXXXX
Para 20:-
That plaintiff submits that there is already a
concluded contract between the defendant no.2
and the plaintiff and the defendant no.1 cannot
renegotiate the terms thereof. In any event, the
defendant no.1‟s consideration for managing the
entire project as a lead co ntractor must
necessarily be included entire project as a lead
contractor must necessarily be included in his
consideration of the contract with the defendant
no.2 and defendant no.1 cannot insist on
consideration from the plaintiff as execution of a
contract between the plaintiff and the defendant
no.1 is a mere formality for due implementation of
a project and/or a condition imposed by the
defendant no.2 which has been accepted by the
defendant no.1 without any protest or demur.
Further and/or in any even t the consideration
received by defendant no.1 from defendant no.2
includes the discharge of obligation by defendant
no.1 as a lead contractor. Without prejudice, it is
further submitted that the same is a matter
between the defendant no.1 and the defenda nt
no.2 and the plaintiff is neither involved nor
concerned with it, however, the same cannot be
allowed to prejudicially affect the plaintiff. The
defendant no.1 is stopped from claiming to the
contrary. The defendant no.1 is attempting to
jeopardize the agreement between the plaintiff
and the said defendant no.2 and cause irreparable
loss including loss of reputation of the plaintiff.
The defendant no.1 tortuously by attempting to
deliberately induce a third party instead, which
the defendant no.1 is no t entitled to do. The
defendant no.1 is bound and liable to give effect to
the concluded contract between the plaintiff and
defendant no.2 and sign the formal contract
between the plaintiff and defendant no.1. in regard
thereto. The plaintiff has spent huge amount of
monies and man -power time in preparation of
discharge of its obligations including more than 25
man-visits by Senior Officers to Ethiopia at
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 21 of 40
exorbitant cost. The defendant no.1 cannot
jeopardize the interest of the plaintiff. It is further
submitted that the if the defendant no.1 is allowed
to proceed in its malafide intention it would not
only be illegal, it would also render the plaintiff
without any remedy whatsoever for the colossal
losses that would be caused to it.
The plaintiff is further seeking to substitute paragraph 24 by the
following paragraphs:-
24. The defendant no.1 is having its corporate
office in New Delhi and is described to carry its
business with the local limits of the jurisdiction of
this Hon'ble Court. The defendan t no.3 and the
defendant no.4 has its office within the local limits
of jurisdiction of this Hon'ble Court. It is further
submitted that several meetings between the
parties have been held within the jurisdiction of
this Hon'ble Court. Several pertinent documents
including the letter dated. 7.12.2007 have been
issued and received by the defendant no.1 from its
Delhi Office and several agreements including the
agreement dated 20.2.2008 and 10.1.2008 have
been entered into between the defendants within
the jurisdiction of this Hon'ble Court. The alleged
minutes of meeting dated 4.8.2008 also bear the
Delhi Stamp of the defendant no.1 and is thus
within the jurisdiction of this Hon'ble Court. The
alleged amendment dated 15.09.2008 to the
10.1.2008 contract has also been entered into
within the jurisdiction of this Hon'ble Court and
therefore the cause of action cannot be split
inasmuch as the acts have been taken place within
the jurisdiction of this Hon'ble Court. The
defendants therefore reside and work for gain in
Delhi. It is further submitted that without
prejudice and in any event, if this Hon'ble Court
holds otherwise, in best interest of justice, leave
may be granted under Section 20 of the Code of
Civil Procedure.
The value of the suit for the purpose of jurisdiction
and court fees is as follows:-
(a) For grant of a decree of mandatory injunction
direction defendant no.1 to execute the
obligation of signing a formal contract with the
plaintiff in accordance with the terms and
conditions agreed between the plaintiff and
defendant no.2 as contained in letter dated 7
th
December, 2007, at Rs.20,05,000/ - and the
court fee of Rs.21,915/- is affixed thereon.
(b) For grant of a decree of perpetual injunction
restraining the defendant no.1 and defendant
no.3 from interfering in the contract/award of
contract between plaintiff and defendant no.2
as contained in letter dated 7
th
December,
2007, including appointing/engaging any third
party in respect of the Process House Project;
the relief is valued for the purpose of court fee
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 22 of 40
and jurisdiction is at Rs.200/- and a court fee of
Rs.20/- is affixed thereon
(c) For grant of perpetual injunction restraining
the defendant no.1 from committing a breach
of the negative covenant enumerated in para
20 A above and restrain the defe ndant no.1
from modifying and technical and/or
commercial terms including price
agreed/finanlized between the plaintiff and the
defendant no.2, the relief is valued for the
purpose of court fee and jurisdiction is at
Rs.200/- and a court fee of Rs.20/- is affixed
thereon.
(d) For grant of decree of mandatory injunction,
directing the defendants to undo the
contemptuous and illegal acts and restore
status quo ante as on 30.7.2008; the relief is
valued for the purpose of court fee and
jurisdiction at Rs.200/- and a court fee of
Rs.20/- is affixed thereon.
(e) For the grant of decree of perpetual injunction
restraining defendant no.4, EXIM Bank from
disbursing the funds for the Tendaho Sugar
Factory Project in the Line of Credit opened by
it from the Government of Ethopia; the relief is
valued for the purpose of court fee and
jurisdiction at Rs.200/- and court fee of Rs.20/-
is affixed thereon.
(f) For grant of decree of perpetual injunction
restraining the defendant no.1 from modifying
and technical and/or commerci al terms
including price agreed/finalized between the
plaintiff and the defendant no.2; the relief is
valued for the purpose of court fee and
jurisdiction at Rs.200/- and court fee of Rs.20/-
is affixed thereon.
(g) For grant of a decree of perpetual injunction
restraining the defendant no.1, 2 and 3 from
proceeding with and/or acting upon in any
manner whatsoever on the purported sub -
contract Agreement dated 12
th
July, 2008; or
on any subsequent date; the relief is valued for
the purpose of court fee and jur isdiction at
Rs.200/- and court fee of Rs.20/- is affixed
thereon.
(h) For that the purported sub-contract Agreement
dated 12
th
July, 2008 between defendant no.1
and defendant no.3 is invalid and void ab initio;
the relief is valued for the purpose of court fee
and jurisdiction at Rs.200/- and court fee of
Rs.20/- is affixed thereon.
(i) For declaration that the consortium agreement
dated 16.7.2008 entered into between the
defendant no.1 and the defendant no.3 is
illegal and void; the relief is valued for the
purpose of court fee and jurisdiction at
Rs.200/- and court fee of Rs.20/- is affixed
thereon.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 23 of 40
(j) For declaration that the purported permission
granted vide letter dated 5.8.2008 issued by
the defendant no.2 to defendant no.1 is invalid
and/or void ab initio; the relief is valued for the
purpose of court fee and jurisdiction at
Rs.200/- and court fee of Rs.20/- is affixed
thereon.
(k) For declaration that the addemdum no.1 dated
21.2.2008 the agreement dated 10.1.2008 is
illegal and void ab-initio; the relief is valued for
the purpose of court fee and jurisdiction at
Rs.200/- and court fee of Rs.20/- is affixed
thereon.
(l) For declaration that the alleged amendment
dated 15.09.2008 toe the Agreement dated
10.1.2008 is illegal and void ab-initio; the relief
is valued for the purpose of court fee and
jurisdiction at Rs.200/- and court fee of Rs.20/-
is affixed thereon.
(m) Grant of decree of perpetual injunction
restraining the defendant no.1 and 2 from
taking any steps in furtherance of the
amendment dated 15.09.2008 illegally made to
the contract agreement dated 10.1.2008
allegedly entered into between defendant no.1
and defendant no.2 or creating any rights in
favour of defendant no.3; the relief is valued
for the purpose of court fee and jurisdiction at
Rs.200/- and court fee of Rs.20/- is affixed
thereon.
(n) Grant of decree of permanent injunction
restraining the defendant nos.1, 2 and 3 from
taking any action pursuant to the purported
letter dated 5.8.2008; the relief is valued for
the purpose of court fee and juris diction at
Rs.200/- and court fee of Rs.20/- is affixed
thereon.
Thus, the suit is valued for the purpose of court fee
and jurisdiction at Rs.20,05,400/- and a court fee
of Rs.21,995/- has already affixed thereon.
Additional court fee of Rs.200/- is being paid
herein. The plaintiff craves leave to affix any
additional court fee if so required by this Hon'ble
Court or otherwise.
The plaintiff is also seeking to amend the prayer clause . The
proposed amended prayers read as under: -
Prayer clause:-
(a) Grant of decree of perpetual injunction
restraining the defendant no.1 and defendant
no.3 from interfering in the contract/award of
contract between plaintiff and defendant no.2
as contained in letter dated 7
th
December,
2007 including appointing/engaging any third
party in respect of the Process House Project.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 24 of 40
(b) Grant perpetual injunction restraining the
defendant no.1 from committing a breach of
the negative covenant enumerated in Para
20A above and restrain the defendant no.1
from modifying any technical and/o r
commercial terms including price
agreed/finanlized between the plaintiff and
defendant no.2.
(c) Grant a decree of mandatory injunction
directing defendant no.1 to execute the
obligation of signing a formal contract with
the plaintiff in accordance with the terms and
conditions agreed between the plaintiff and
defendant no.2 contained in letter dated 7
th
December, 2007.
(d) Grant perpetual injunction restraining the
defendant no.1 from modifying and technical
and/or commercial terms including price
agreed/finanlized between the plaintiff and
defendant no.2.
(e) Grant a decree of declaration that the
purported sub-contract Agreement dated 12
th
July, 2008 between defendant no.1 and
defendant no.3 is invalid and void ab initio;
and cancel the said contract Agreement dated
12
th
July, 2008.
(f) Declare that the alleged consortium
agreement dated 16.7.2008 entered into
between the defendant no.1 and the
defendant no.3 is illegal and void ab-initio and
cancel the said Consortium Agreement dated
16.7.2008.
(g) Declare that the addendum no.1 dated
21.2.2008 to the agreement dated 10.1.2008
is illegal void ab initio and cancel the said
Addendum No.1 dated 21.2.2008 to the
agreement dated 10.1.2008.
(h) Declare that the Amendment dated 15.9.2008
to the agreement dated 10.1.008 is illegal and
void ab-initio and cancel the said Amendment
dated 15.09.2008 to the agreement dated
10.01.2008.
(i) Grant a decree of perpetual injunction
restraining the defendant no.1 and 2 from
taking any steps in furtherance of the
amendment dated 15.09.2008 il legally made
to the contract agreement dated 10.01.2008
allegedly entered into between defendant
no.1 and defendant no.2 or creating any
rights in favour of defendant no.3.
(j) Grant a decree of perpetual injunction
restraining defendant no.1, 2 and 3 from
proceeding with and/or acting upon in any
manner whatsoever on the purported sub -
contract Agreement dated 12
th
July, 2008; or
on any subsequent date.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 25 of 40
(k) Grant a decree of declaration that the
purported permission granted vide letter
dated 5.8.2008 issued by the defendant no.2
to defendant no.1 is invalid and/or void ab
initio and cancel the said permission dated
5.8.2008.
(l) Grant a decree of permanent injunction
restraining the defendant nos.1, 2 and 3 from
taking any action pursuant to the purported
letter dated 5.8.2008.
(m) Grant of decree of mandatory injunction,
directing the defendant no.1 and 2 to undo
the contemptuous and illegal acts done and
status quo ante as on 30.7.2008 be restored;
(n) Grant a decree of perpetual injunction
restraining defendant no.4 from disbursing
any funds in the line of credit opened by it
from the Government of Ethiopia.
(o) Costs; and
(p) Pass such further order/as this Hon'ble Court
may deem fit and proper in the facts and
circumstances of the case.
The plaintiff also seeks to change the title of this suit as Uttam
Sucrotech International Pvt. Ltd Versus The Overseas Infrastructure
Alliance (I) Pvt. Ltd and Ors and the nature of the Suit from a “Suit for
Mandatory Injunction” to a “Suit for Mandatory Injunction and
Declaration”.
It is time now to come straight to the application for
„amendment and impleadment‟. Should it be allowed? As far as the
prayer for amendment is concerned, it need not detain me for long
and the reason is that after the application had suffered lengthy
arguments, for and against, the learned counsel for defendant No.1
conceded that the amendments sought could be allowed subject to
liberty to it to raise such objections as may be available to it and to
this, it may be noted, the learned counsel for the plaint iff had no
objection. Keeping this in view and keeping also in view the nature of
the amendments and so also the fact that the amendments have their
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 26 of 40
seed in subsequent developments, the amendments sought are
allowed. Of-course, it would be open to defendan t No.1 to take in
response to the amendments, the pleas legally open to it. With the
question of amendment over, the next question which craves for an
answer relates to the impleadment of Walchandnagar Industries Ltd.
and the EXIM Bank. Should not the impl eadment follow the
amendments?
Before I venture to answer it, let us have a look at the power of
the Court to strike out or add a party in an ongoing proceeding. The
power as we all know flows from Order 1 Rule 10(2) of the Code.
It says that “the Court may at any stage of the proceedings, either upon or
without the application of either party, and on such terms as may appear to the
Court to be just, order that the name of any party improperly joined, whether as
plaintiff or defendant, be struck out, and that the name of any person who ought to
have been joined, whether as plaintiff or defendant, or whose presence before the
Court may be necessary in order to enable the Court effectually and completely to
adjudicate upon and settle all the questions involved in the suit, be added.” This
then is the foundation head of all the power. We also know that a
necessary party is one without whom no order can be made effectively
and, a proper party is one in whose absence an effective order can be
made but whose presence is necessary for a complete and final
decision on the question involved in the proceeding. [ See Udit
Narain Singh Malpaharia Versus Additional Member Board of
Revenue, Bihar and another reported in AIR 1963 Supreme Court
786]. In a relatively recent judgment of the Apex Court in the case of
Kasturi Versus Iyyamperumal and others, 2005(6) Supreme Court
Cases 733, two tests have been laid down to determine who is a
necessary party. These tests are that (1) there must be a right to
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 27 of 40
some relief against such party in respect of controversies involved in
the proceedings, and (2) no effective decree can be passed in the
absence of such party. Reference may also be made to a judgment of
this court in the case of Madhupuri (Ms.) and another v. Sh. Moti Lal
Puri and others reported in 2005 VIII AD (Delhi) 737. “It says that Order
1 Rule 10 of the Code has been expressly provided in the Code to meet with
situations so as to implead all the parties which may be affected by any litigation so
that the rendering of justice is not hampered. It further says that plaintiff is
dominus-litus and he is bound to sue every possible adverse claimant to avoid
multiplicity of suit and needless expenses.”
The principle is thus clear and it is that while deciding whether a
person ought to be made a party to the suit , what needs to be
examined is, whether the controversy raised in the plaint can be
effectively and finally set at rest in the absence of the person sought to
be impleaded and if not , then that person must n ecessarily be
impleaded as a party or else it will leave scope for further litigation and
may also lead to multiplicity of proceedings.
The law of impleadment being what has been noticed above, are
Walchandnagar Industries Ltd. and EXIM Bank necessary and proper
parties in the suit? I shall first deal with Walchandnagar Industries Ltd.
but before I do that, let me notice the objections raised by it to its
impleadment. It says that it is a stranger to the proceedings. It has no
privity of contract with the plaintiff and that it has entered into an
independent contract with defendant No.1 dated July 12 , 2008 with
which the plaintiff has no right to interfere. It further says that the
foundation of the original suit is the alleged concluded contract
between the plaintiff and defendant No.2 and that the plaintiff by way
of an application for „amendment -cum-impleadment‟ cannot be
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 28 of 40
allowed to change the contours of the original plaint where it does not
figure at all. As per it, it is not the relief sought against it which should
form the basis for its impleadment but the averments made in the
plaint. Those averments, it is stated, give rise to disputes, if any,
between the plaintiff, defendant No.1 and defendant No.2. It has also
taken an objection that assuming there is an agreement between the
plaintiff and defendant No.1, such an agreement is not capable of
being specifically enforced and that the only remedy available to the
plaintiff is to sue for the alleged breach of the contract. Hence, it is
argued that it is neither a necessary or a proper party, and in support,
reliance was placed on Anil Kumar Singh Vs. Shivnath Mishra alias
Gadasa Guru reported in (1995) 3 Supreme Court Cases 147 . The
facts of that case were that one Daulat Singh, father of the petitioner
filed a suit for specific performance of an agreement of sale of some
land said to have been executed in his favour by one Shiv Nath Mishra.
Pending decision in the suit, Daulat Singh died. The petitioner came
on record as legal representative of Daulat Singh. He filed an
application under Order 6 Rule 17 of the Code seeking leave to amend
the plaint and seeking to implead the respondent also as a party-
defendant in the suit. The contention of the petitioner was that
Shivnath Mishra, the vendor, had colluded with his sons and wife and
had obtained a collusive decree in a suit under Section 229-B of the
U.P. Zamindari Abolition and Land Reforms Act and by operation of the
said decree, they became co-sharers of the property to be conveyed
under the „Agreement to Sell‟ and, therefore, the respondent was a
necessary and proper party to effectuate the ultimate decree of the
specific performance that may be granted in favour of the petitioner.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 29 of 40
The Apex Court declined the relief on the ground that the suit of the
plaintiff was based on the „Agreement to Sell‟ said to have been
executed by the vendor and that the person who was sought to be
impleaded as a respondent had acquired interest in the property by an
independent decree which decree was not the subject matter of the
suit and hence, without assailing the validity of the decree, those who
acquired the right through the decree could not be dragged into the
litigation.
Reliance was also placed on Sarvinder Singh Vs. Dalip Singh and
others reported in (1996) 5 Supreme Court Cases 539. In the said case
Sarvinder Singh had already obtained a decree of declaration, that he
was the owner of the suit property on the basis of a registered Will
executed by his mother. In that suit the daughters of Hira Devi, were
impleaded as defendants. One of the daughters was Rajinder Kaur.
Subsequent to that decree which had became final, Sarvinder Singh
filed another suit for declaration of his ownership on the basis of the
same Will against the heirs of Rajinder Kaur. Since the said heirs of
Rajinder Kaur alienated the self same lands to X and Y, the said X and
Y moved an application under Order 1 Rule 10 of the Code for being
impleaded as defendants. The Supreme Court observed that though it
may be open to the heirs of the Rajinder Kaur to resist the suit on any
legally available or tenable grounds, those grounds were not available
to the applicants. It was further made clear that the earlier decree on
the basis of the Will having become final and as the applicants were
claiming title only through the heirs of Rajinder Kaur who was a party
to that decree they could not legally challenge the legality and validity
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 30 of 40
of the said Will. It was for these reasons that the applicants were held
to be neither necessary nor proper parties to the suit.
As would be borne out from above both the judgments relied
upon by learned counsel for Walchandnagar Industries Ltd. bear no
parallel to the facts of the present case.
Having regard to the facts of the present case as borne out from
the plaint as well as from the amendments which, I have allowed,
some of the issues which are likely to fall for consideration are, firstly,
whether the plaintiff and defendant No.2 had a concluded contract and
if so, could defendant No.1 renegotiate the price with the plaintiff in
contravention of alleged express understanding arrived at between the
plaintiff, defendant No.1 and defendant No.2 in the joint meeting held
on 19
th
& 20
th
December, 2007 and in contravention of the alleged
contract-agreement dated February 20, 2008 between defendant No.1
and defendant No.2; and secondly, was defendant No.1 authorized by
defendant No.2 or even otherwise legally entitled to oust the plaintiff
from the project and induct in its place anoth er sub-contractor,
namely, Walchandnagar Industries Ltd.? Not only this, the
amendments sought to be introduced in the plaint challenge the
existence, legality and validity of the so called binding contract with
Walchandnagar Industries Ltd. vide “Memor andum of Understanding”
dated July 08, 2008 and the sub-contract dated July 12, 2008. It may
be recalled that as per the application for amendment the said
documents were forged and fabricated by defendant No.1 in concert
with defendant No.2 and Walchandnagar Industries Ltd.
This certainly is not the stage to go into merits. That stage has
not yet come. At this stage, what is to be seen is whether in view of
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 31 of 40
what is pleaded, a person sought to be impleaded is a necessary or a
proper party or not and whether the totality of the averments made
against the person sought to be impleaded give rise to a cause of
action against that person and if they do, should that person be not
treated as a necessary or proper party? This being the position, should
Walchandnagar Industries Ltd. be kept out of the proceedings? Should
it be heard to say that it had entered into an independent contract with
defendant No.1 and that the plaintiff has no right to challenge its
contract? The effect of the alleged contract with Wa lchandnagar
Industries Ltd. on the alleged rights of the plaintiff is obvious. It has
the effect of ousting the plaintiff from the project of setting-up Sugar
Factory at Addis Ababa by Walchandnagar Industries Ltd. The plaintiff
has challenged not only the very existence of that contract but its
legality and validity too. Whether the plaintiff had a concluded
contract with defendant No.2 and if so, whether it was wrongly ousted
by defendant No.1 and rightly replaced by Walchandnagar Industries
Ltd., who is a direct beneficiary from the ouster of the plaintiff are
questions which have been raised and these questions will have to be
determined. And, if so, and it being so, Walchandnagar Industries Ltd.
becomes a necessary party. The loss of the plaintiff is the gain of
Walchandnagar Industries Ltd. It has allegedly stepped into the shoes
of the plaintiff. It cannot be allowed to watch the proceedings from the
side-lines. It must enter the fray and justify its induction, more so,
when it is being accused of making its way to the contract by forging
and fabricating documents. More than the plaintiff, it will be in its own
interest to do so, for in case, it remains out of the proceedings and
assuming any adverse order is passed in its absence , it may cause
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 32 of 40
irreparable loss to it and in all likelihood may lead to further litigation.
Therefore, in my opinion, Walchandnagar Industries Ltd. is a necessary
and proper party. I, therefore, allow the prayer for impleading it as a
party.
This brings me to the prayer for impleadment of EXIM Bank. As
already noticed above, the project for development of Sugar Factory at
Addis Ababa is being funded by the said bank. It has entered into an
agreement dated October 04, 2007 with the Government of Federal
Democratic Republic of Ethiopia, called the „Dollar Credit-line
Agreement‟ and it is under the terms of the said agreement that it has
to release the funds to the Government of Ethiopia who has been
described as the “borrower”.
It is the case of the EXIM Bank that the agreement dated
October 04, 2007 has been entered into between two sovereign
countries and the Bank is under legal obligation to remit the amount
to defendant No.2 by opening the line of credit. As per the Bank, it is
not at all concerned with the contract entered into between defendant
No.1 and defendant No.2 or any alleged sub -contract having been
entered into between defendant No.1 and Walchandnagar Industries
Ltd. or any dispute arising between the parties to the said contracts.
It says that its obligation to release funds to defendant No.2 is
independent of all these transactions and that the plaintiff who is a
complete stranger to the Dollar Credit Line Agreement dated
October 04, 2007 has no right to seek any injunction vis-à-vis the said
agreement. According to the counsel for defendant No.1 and the
EXIM Bank, all that the bank is required to do before it remits the
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 33 of 40
amount, is to ensure that it is done in terms of Clause 3 of the „Dollar
Credit Line Agreement‟. The Clause runs as under:-
3. Eligibility of contract to be financed out of
the credit.
3.1 A contract shall not be eligible to be financed out
of the Credit unless:-
(a) it is for the import of the Eligible Goods into the
Borrower‟s Country and in case of any contract which
includes rendering of consultancy services, it provides
for sourcing consultancy services from India;
(b) the contract price is specified in Dollars and is not
less than $50,000/- (Dollars fifty thousand only) or such
amount as may from time to time be agreed upon
between the Borrower and EXIM Bank;
(c) the contract requires the Buyer to make payment to
the Seller of 100% (one hundred per cent) of
FOB/CFR/CIF contract price of the Eligible Goods ( other
than services), pro-rata against shipments, to be covered
under an irrevocable and non -transferable letter of
credit in favour of the Seller;
(d) in the case of Services to be rendered by a Seller in
the Borrowers Country, or where the contract requires
advance payment to be made by the Buyer to Seller
which needs to be financed out of the Credit, the
contract provides for the Buyer to cause the Borrower to
issue a Payment Authorisation to EXIM Bank to enable
the Seller to claim payment from EXIM Bank of the
Eligible Value apportionable to the amount of invoice for
such services or, as the case may be, the amount of
advance payment;
(e) the contract contains a provision that the Eligible
Goods shall be inspected before shipment on behalf of
the Buyer and the documents to be furnished by the
Seller to the Negotiating Bank under the letter of credit
arrangement referred to in sub-clause(c) herein shall
include an inspection certificate;
(f) the contract also contains a provision to the effect
that EXIM Bank shall not be liable to the Buyer or the
Seller for not being able to finance purchase of the
Eligible Goods or any portion thereof by reason of
suspension or cancellation of any undrawn amount of the
Credit in terms of this Agreement;
(g) the Borrower has sent to EXIM Bank for its approval
brief details of the contract in the format at Annexure-I
and such other documents and information as EXIM
Bank may require in this behalf, and EXIM Bank has, in
writing, approved of the contract as being eligible
indicating the Eligible Value thereof.
Reference was also made to the definition of Eligible Goods as
given in Clause 1 of the agreement which says “Eligible Goods” in respect
of an Eligible Contract means “any goods and services (including consultancy
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 34 of 40
services from India) relating to projects for the development of sugar industry in the
Borrower‟s Country, agreed to be financed by EXIM Bank under this Agreement, out
of which goods and services of the value of at least 85% of the contract price shall
be supplied by the Seller from India, and the remaining goods and services (other
than consultancy services) may be procured by the Seller for the purpose of the
Eligible Contract from outside India.”
In view of these clauses, it was contended by the learned
counsel for the EXIM Bank that the bank is not concerned as to who is
the Contractor and will release the funds to the Contractor whoever
he may be on the instructions of the borrower , provided the
conditions laid down in the Dollar Credit Line Agreement are found to
have been fulfilled.
The plaintiff, on the other hand, has sought impleadment of
EXIM Bank as defendant No.4 on the ground that defendant No.2 , i.e.
Tendaho Sugar Factory Project is proceeding with modernization
essentially financed by credit line from the EXIM Bank of India and
the said Bank being a State is bound to act fairly and not in violation
of the order of this Court. On the basis of the averments so made, the
prayer clause is also sought to be amended seeking a decree of
perpetual injunction restraining EXIM Bank from disbursing any funds
in the line of credit opened by it from the Government of Ethiopia.
What needs to be noticed at this stage is that the plaintiff herein
had filed a Writ Petition No.2002 of 2008 in the Bombay High Court
feeling aggrieved by the appointment of M/s. Overseas Infrastructure
Alliance (India) Pvt. Ltd. as Single EPC Contractor by virtue of its
having secured two contracts, namely, Power Generation Plant and
Juice Extraction Plant and further feeling aggrieved by the approval
granted by the EXIM Bank to the appointment of M/s Overseas
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 35 of 40
Infrastructure Alliance (India) Pvt. Ltd. as Single EPC Contractor. In
the said Writ Petition, it prayed for the following reliefs:-
(a) this Hon‟ble Court may graciously be pleased to call
for the records of the case from respondent No.1 and after
examining the same issue a writ of Certiorari or a Writ in
the nature of Certiorari or any other appropriate Writ ,
order or direction quashing or setting-aside the approval
dated 21.4.2008 granted by respondent No.1 to contract
dated 28.2.2008 entered into between respondent no.2 and
respondent No.3.
(b) this Hon‟ble Court may further be pleased to issue a
Writ of Mandamus or any other appropriate Writ , order or
direction, directing respondent No.1 to take all the
necessary steps and actions to ensure that (i) the contract
for Power Generation Package be awarded to petitioner
No.1 being the lowest eligible bidder and (ii) respondent
No.3 is removed as the Single EPC Contractor.
(c) pending the hearing and final disposal of the
petition, respondent No.1 be restrained from
approving/signing of letter of credit, and/or disbursing any
funds in any manner towards the said line of credit in
favour of the respondent No.3 as Single EPC Contractor for
Tendaho Sugar Factory Project or as a successful bidder for
the Juice Extraction and Power Generation Packages.
(d) pending the hearing and final disposal of the
petition, respondent No.3 be restrained from acting as
Single EPC Contractor.
(e) cost of the petition be provided for.
(f) any other and further orders as this Hon‟ble Court
deems fit in the nature and circumstances of the case be
passed.
The Bombay High Court vide judgment dated October 07, 2008
dismissed the Writ Petition. In the present application for
impleadment, the relief that is being sought against the EXIM Bank is
in effect the same as was claimed before the Bombay High Court by
way of prayer (c) noticed hereinabove. In this view of the matter, it
will be appropriate to reproduce what Bombay High Court has said in
relation to prayer (c). It has held as under:-
“The clause which requires EXIM Bank to approve the
contract requires that EXIM Bank must consider whether
the approved contract has become eligible and indicating
the eligible value thereof. For the purpose of considering
the eligibility what respondent No.1 must consider as set
out in their affidavit in reply and the contract terms is to
examine, whether the terms of the contract conform to the
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 36 of 40
terms of the LOC agreement. In this exercise it only
satisfied itself that the terms of the contract viz. such as
Eligible Goods, Seller, Eligible Value, Terminal Date for
Opening Letters of Credit and Terminal Date for
Disbursement conforms to the terms of the LOC Agreement
entered into between respondent No.1 and the Government
of Ethiopia. The stand of respondent No.1 that it does not
involve itself in the process of selecting the exporter,
neither does it sanction the bidding process which will be
conducted in our opinion is right. This is as it should be.
The contracts are invited by the Government of Ethiopia
and/or its agency, in the present case respondent No.2.
Neither the respondent No.1 nor the respondent No.3 has
any control over the said bidding process.”
What also needs to be noticed is that another company namely,
Saraswati Industrial Syndicate Ltd. had also responded to the
invitation of tenders floated by Tendaho Sugar Factory Project and in
response thereto, it was awarded the contract for Steam Generation
Plant. And what further needs to be noticed, is that like the plaintiff,
Saraswati Industrial Syndicate Ltd. has also filed a suit in this Court
being CS(OS) No.1368 of 2008 for perpetual and mandatory
injunction, alleging therein that it has been wrongly ousted from the
project by awarding the cont ract of Steam Generation Plant to
Walchandnagar Industries Ltd. Along with the suit, it had filed an
application under Order 39 Rules 1 & 2 of the Code on which similar
interim order as was passed in this case was passed restraining M/s
Overseas Infrastructure Alliance (India) Pvt. Ltd. from introducing a
third party in respect of the tender floated for Steam Generation
Plant. M/s. Saraswati Industrial Syndicate Ltd. also filed an
application for „amendment -cum-impleadment‟ and another
application under Order 39 Rules 1 & 2 of the Code seeking
ad-interim ex parte order restraining EXIM Bank from taking any
steps including approving the substitution of Walchandnagar
Industries Ltd. or any other party in its place and/or opening the line
of credit and/or disbursing any moneys to M/s Overseas Infrastructure
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 37 of 40
Alliance (India) Pvt. Ltd. and Tendaho Sugar Factory Project. The
learned Single Judge passed no interim order on the said application
whereupon Saraswati Industrial Syndicate Ltd. preferred a n appeal
before a Division Bench of this Court which was registered as
FAO(OS) No.472 of 2008 and was disposed of on December 17 , 2008.
The Division Bench declined the relief basing itself on the submissions
of learned counsel for the EXIM Bank and also relied upon the
aforesaid judgment of the Bombay High Court dated
October 07, 2008.
The relevant paragraphs of the judgment of the Division Bench
run as under:-
We may also note at this stage that the appellant has
also filed Civil Contempt under Order 39 Rule 2 A of the
CPC alleging violation of orders dated 23.07.2008. It is the
submission of the appellant in the said application that in
spite of injunction granted by the aforesaid order, the
respondent no.1 had gone ahead and had taken measures to
introduce the respondent no.3 to the respondent no.2 in
place of the appellant. The submission of the learned
counsel for the appellant is that when there was an
injunction passed on 23.07.2008 whereby the respondent
no. 1 was restrained from taking any measures to introduce
a third party in place of the appellant, any action taken by
the respondent no.1 after 23.07.2008 and introducing
respondent no.3 to the respondent no.2 and substituting it in
place of the appellant is contemptuous a s it constitutes
violation of order dated 23.07.2008. In these circumstances,
submits the counsel, the learned Single Judge, should have
granted injunction as prayed for in I.A. 14363/2008.
Mr. P.P. Malhotra, Additional Solicitor General of
India has appeared on behalf of the EXIM Bank. He has
pointed out that an agreement has been entered into
between the Government of Federal Domestic Republic of
Ethiopia and the EXIM Bank, which is dated 04.10.2007.
Copy of that agreement is placed before us. He submitted
that in pursuance to the said agreement between the two
sovereign countries, the EXIM Bank is under a legal
obligation to remit the amount to the respondent no.2 by
opening Letter of Credit. It was further submitted that the
EXIM Bank is not at all concerned with the contract entered
into by the respondent no.2 with respondent no. 1 or for that
matter, any disputes which arose out of those contracts. It is
not even a part to the said contracts. The obligation of the
EXIM Bank qua respondent no.2 is independent of all these
transactions. We find merit in this submission of Mr.
Malhotra.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 38 of 40
We may note that a similar issue had arisen in the
Bombay High Court in the case of M/s. Uttam Sucrotech
International Pvt. Ltd. v. EXIM Bank (Writ Petition
Lodging No. 2002/2008) and vide judgment dated
07.10.2008 rendered by a Division Bench of that court,
similar prayer to restrain the EXIM Bank, though in
different factual context, was turned down in the following
manner:-
“10. In our opinion, it is not necessary to refer the
other contentions except the limited contention of
respondent no.3, that the project in question is a
sovereign understanding between two countries. The
petitioners by the present petition, it is contended are
seeking to challenge the tender process of another
sovereign country or its nominee without invoking the
judicial process of that country or without first
seeking remedy through the procedure given in the
bid document issued by that country. The bid
document and the main contract dated 10
th
January,
2008 and the contract dated 20
th
February 2008 clearly
provides for all disputes to be covered by the laws of
Ethiopia. The petition also it is submitted does not
disclose any violation of Articles 14, 19 and 21 of the
Constitution of India. The issues raised are not in
public interest but are purely beneficial to the
petitioner and only in its self interest.
xxxxxxxx
xxxxxxxx
xxxxxxxx
The clause which requires EXIM Bank to approve the
contract requires that EXIM Bank must consider
whether the approved contract has become eligible
and indicating the eligible value thereof. For the
purpose of considering the eligibility what respondent
No.1 must consider as set out in their affidavit in reply
and the contract terms is to examine, whether the
terms of the contract conform to the terms of the LOC
agreement. In this exercise it only satisfied itself that
the terms of the contract viz. such as Eligible Goods,
Seller, Eligible Value, Terminal Date for Opening
Letters of Credit and Terminal Date for Disbursement
conforms to the terms of the LOC Agreement entered
into between respondent No.1 and the Government of
Ethiopia. The stand of respondent No.1 that it does
not involve itself in the process of selecting the
exporter, neither does it sanction the bidding process
which will be conducted in our opinion is right. This is
as it should be. The contracts are invited by the
Government of Ethiopia and/or its agency, in the
present case respondent No.2. Neither the respondent
No.1 nor the respondent No.3 has any control over the
said bidding process.
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 39 of 40
After noticing the aforementioned paragraphs from the
judgment of the Bombay High Court , the Division Bench further held
as under:-
“The Special Leave Petition against the said judgmen t has
also been dismissed by the Supreme Court on December 15 ,
2008. Therefore, in so far as restrain order sought against
EXIM Bank is concerned, this relief cannot be granted to the
appellant.”
The learned counsel appearing for EXIM Bank and learned
counsel for defendant No.1 have heavily relied upon the judgment of
the Bombay High Court as well as on the judgment of the Division
Bench. On the other hand, it was argued by learned counsel for the
plaintiff that the issue before the Bombay High Court w as different
and reliance upon the same by the Division Bench was misplaced. In
support of his submission, reliance was placed upon a judgment of the
Apex Court in Workmen of Cochin Port Trust Vs. Board of Trustees of
the Cochin Port Trust and another, reported in (1978) 3 Supreme
Court Cases 119, which is to the effect that a non-speaking order of
dismissal without indicating the grounds or reasons of its dismissal
must, by necessary implication, be taken to have decided only that it
was not a fit case where special leave should be granted but that may
be due to various reasons.
I fail to see how the above judgment of the Supreme Court
comes to the rescue of the plaintiff.
What after-all is the purpose of the plaintiff in seeking to
implead EXIM Bank as a party to the suit? It is to restrain the Bank
from granting approval to substitute the plaintiff by Walchandnagar
Industries Ltd. or to proceed with funding of the Steam Generation
Plant. I feel that the judgment of the Bombay High Court provides the
I.A. No.1938/2009 in CS(OS) No.1447/2008 Page 40 of 40
answer. It appears that the EXIM Bank has no role to play in the
process of selecting a sub-contractor. In fact it has nothing to do with
even the selection, approval or appointment of sub-contractors. It has
also no role to play in the substitution or retention of sub-contractors.
Its role is confined only to disbursement of the fund. This is how I
look at it and in support I have not only the judgment of the Bombay
High Court but also the judgment of the Division Bench of this Court.
For the fore-going reasons, the application for amendment is
allowed and the prayer for impleadment of Walchandnagar Industries
Ltd. with consequential reliefs sought against it is also allowed.
However, application, in so far as it relates to the EXIM Bank is
dismissed.
REKHA SHARMA , J.
AUGUST 20, 2009
Ka/g
Legal Notes
Add a Note....