No Acts & Articles mentioned in this case
W.P.(C).No.1479/2024 :: 1 ::
2024:KER:69161
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE DR. JUSTICE A.K.JAYASANKARAN NAMBIAR
&
THE HONOURABLE MR. JUSTICE SYAM KUMAR V.M.
FRIDAY, THE 13
TH
DAY OF SEPTEMBER 2024/22ND BHADRA, 1946
W.P(C).NO.1479 OF 2024
PETITIONER(S):
V.D. SATHEESAN M.L.A,
AGED 59 YEARS
S/O.DAMODARAMENON, LEADER OF OPPOSITION, MEMBER,
KERALA LEGISLATIVE ASSEMBLY, RESIDING AT DEVARAGAM,
KESARI JUNCTION, PERUVARAM WEST, NORTH PARAVUR P.O.,
PARAVUR, ERNAKULAM DISTRICT, PIN - 683513
BY ADV.SRI.GEORGE POONTHOTTAM (SR.)
BY ADV.SMT.NISHA GEORGE
BY ADV.SRI.A.L.NAVANEETH KRISHNAN
BY ADV.SRI.J.VISHNU
BY ADV.SMT.KAVYA VARMA M. M.
BY ADV.SRI.ANSHIN K.K
BY ADV.SRI.SIDHARTH.R.WARIYAR
RESPONDENT(S):
1 THE STATE OF KERALA,
REPRESENTED BY THE CHIEF SECRETARY,
GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM,
PIN - 695001
2 THE ELECTRONICS AND INFORMATION TECHNOLOGY DEPARTMENT,
GOVERNMENT OF KERALA, SECRETARIAT, THIRUVANANTHAPURAM,
REPRESENTED BY THE SECRETARY, PIN - 695001
3 THE DEPARTMENT OF FINANCE,
GOVERNMENT OF KERALA, REPRESENTED BY THE ADDITIONAL
CHIEF SECRETARY, GOVERNMENT SECRETARIAT,
W.P.(C).No.1479/2024 :: 2 ::
2024:KER:69161
THIRUVANANTHAPURAM, PIN – 695001
4 KERALA STATE ELECTRONICS DEVELOPMENT CORPORATION LTD.
(DELETED),
[KELTRON], KELTRON HOUSE, VELLAYAMBALAM P.O.,
THIRUVANANTHAPURAM, REPRESENTED BY ITS MANAGING
DIRECTOR. E-MAIL : KELTRON @ KELTRON.ORG.
PIN - 695033
[R4 IS DELETED FROM THE PARTY ARRAY AS PER ORDER DATED
05/08/2024 IN WP(C)].
5 KERALA STATE INFORMATION TECHNOLOGY INFRASTRUCTURE LTD.,
1ST FLOOR, SANKETHIKA, PF ROAD, VRINDAVAN GARDENS,
PATTOM P.O, THIRUVANANTHAPURAM, REPRESENTED BY ITS
MANAGING DIRECTOR, PIN - 695004
6 THE KERALA STATE ELECTRICITY BOARD LIMITED,
VYDYUTHIBHAVAN, PATTOM PALACE POST,
THIRUVANANTHAPURAM, REPRESENTED BY ITS CHAIRMAN,
PIN - 695004
7 BHARAT ELECTRONICS LIMITED (BEL),
MEDICAL COLLEGE - NAD ROAD, KINFRAHITECH PARK,
HMT COLONY, KALAMASSERY, KOCHI, REPRESENTED
BY ITS DIRECTOR, PIN – 683503.
8 M/S.SRIT INDIA PVT. LTD,
SRIT HOUSE, #113/1B,ITPL MAIN ROAD, KUNDALAHALLI,
BANGALORE, KARNATAKA STATE, REPRESENTED BY ITS
MANAGING DIRECTOR, E-MAIL: HARISHKUMAR@RENAISSANCE-IT.COM ,
PIN - 560037
9 M/S.ASHOKA BUILDCON LTD,
S.NO - 861, ASHOKA HOUSE, ASHOKAMARG,ASHOKA NAGAR,
13B, GULSHAN COLONY, NASHIK, MAHARASHTRA, REPRESENTED
BY ITS MANAGING DIRECTOR, PIN - 422011
10 PRESADIO TECHNOLOGIES PRIVATE LIMITED,
2ND FLOOR, 2/2525-B8, OLIVE ARCADE, MALAPARAMBA
JUNCTION, KOZHIKKODE, REPRESENTED BY ITS MANAGING
DIRECTOR., EMAIL:ADMIN@PRESADIOTECHNOLOGIES.COM,
PIN - 673009
11 RAILTEL CORPORATION OF INDIA LTD.,
PLATE-A, 6TH FLOOR, OFFICE BLOCK TOWER-2,
EAST KIDWAI NAGAR, NEW DELHI, REPRESENTED
BY ITS DIRECTOR, PIN - 110023
W.P.(C).No.1479/2024 :: 3 ::
2024:KER:69161
12 M/S CUBE FIBERNET PRIVATE LIMITED,
D.NO-6-3-645/2/A/5, FLAT NO-103, ROAD NO-1, BANJARA
HILLS, HYDERABAD,TELENGANA,REPRESENTED BY THE MANAGING
DIRECTOR. E-MAIL:SHIVA.RAILWIRE@GMAIL.COM, PIN - 500034
13 M/S LIGHT WAVE TECHNOLOGIES PRIVATE LIMITED,
FLAT NO-A-205,SUBHADRAAPPARTMENTPATIA, CHANDRASEKHAR
PUR, BHUBANESWAR, ORISSA, REPRESENTED BY THE MANAGING
DIRECTOR., E-MAIL: LWDN@LIGHTWAVEINDIA.IN,
PIN - 751030
14 M/S. AKSHARA ENTERPRISES INDIA PRIVATE LIMITED,
3-6-182/1&2, STREET NO-17, URDU HALL LANE, TS STATE,
AP STATE HOUSING BOARD, HIMAYATNAGAR, HYDERABAD,
TELANGANA,REPRESENTED BY ITS MANAGING DIRECTOR.
E-MAIL: SREEDHAR@AKSHARAGS.COM, PIN - 500029
15 CITSA TECHNOLOGIES PVT LTD,
GOTHURUTH BRIDGE ROAD, KOOTTUKADU, MADAPLATHURUTH,
MALIYANKARA, ERNAKULAM DISTRICT, REPRESENTED BY ITS
MANAGING DIRECTOR, PIN - 683516
16 THE CENTRAL BUREAU OF INVESTIGATION,
6TH FLOOR, LODHI ROAD, PLOT NO.5-B, JAWAHARLAL NEHRU
STADIUM MARG, CGO COMPLEX, NEW DELHI, DELHI,
REPRESENTED BY ITS DIRECTOR, PIN - 110003
17 CENTRAL BUREAU OF INVESTIGATION,
COCHIN UNIT, CBI ROAD, KATHRIKADAVU, KALOOR,
ERNAKULAM, REPRESENTED BY THE SUPERINTENDENT,
PIN - 682017
BY SRI.K.GOPALAKRISHNA KURUP (SR.), ADVOCATE GENERAL
BY SRI.N.MANOJ KUMAR, STATE ATTORNEY
BY SRI.V.MANU, SENIOR GOVERNMENT PLEADER
BY SRI.K.A.ABDUL SALAM, SC, KERALA STATE IT INFRASTRUCTURE
LTD. KSITIL
BY ADV.SRI.ANTONY MUKKATH
BY ADV.SRI.REGI MATHEW
BY SRI.B.PRAMOD, SC, KSEB
BY SRI.SREELAL N.WARRIER, SPL. PUBLIC PROSECUTOR CBI
BY SMT.M.A.ZOHRA, SC, KELTRON
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 09.09.2024, THE COURT ON 13.09.2024 DELIVERED THE
FOLLOWING:
W.P.(C).No.1479/2024 :: 4 ::
2024:KER:69161
'C.R.'
J U D G M E N T
D r . A.K. Jayasankaran Nambiar, J.
This writ petition is styled as a Public Interest Litigation and has been
instituted by the petitioner who is the Leader of the Opposition of the Kerala
Legislative Assembly. The petitioner essentially challenges the award of the
contract for implementation of the Kerala Fibre Optic Network [KFON] project
to the consortium comprising of Bharat Electronics Limited, RailTel
Corporation of India Limited, Sobha Renaissance Information Technology Pvt.
Ltd and LS Cable India Private Limited [hereinafter referred to as the “BEL
Consortium”] for an amount of Rs.1628.35 Crores, after finding their quote to
be the lowest among the three qualified consortium bidders that had
participated in the tender process. It might be relevant to observe at the
outset that none of the unsuccessful tenderers have challenged the award of
the contract to the BEL Consortium.
2. The prayers in the writ petition are essentially to call for the records
leading to Ex.P7 sanction order and to quash the same, as also to quash all the
consequential orders and decisions taken following Ext.P7 order. There is a
further prayer for a writ of mandamus to direct the Central Bureau of
Investigation [CBI] to initiate an enquiry into the KFON project, including the
Project Monitoring Agency tender and the tenders for selecting the Managed
W.P.(C).No.1479/2024 :: 5 ::
2024:KER:69161
Service Provider [MSP] and the Internet Service Provider [ISP] for KFON. The
writ petition was filed on 11.01.2024 when the KFON project was well
underway in terms of implementation. The project had received the necessary
administrative sanction from the State Government as early as on 18.05.2017.
The tender process for the project was initiated by Kerala Fibre Optic Network
Limited on 14.06.2018 when a Request for Proposals [RFP] was published for
selection of a Project Monitoring Agency. The technical evaluation of the
received tenders commenced on 21.12.2018 and the Financial bids were
opened on 26.12.2018. As already noticed, the BEL Consortium was identified
as the lowest bidder, and after negotiating with them they were appointed as
the Project Monitoring Agency by accepting their offer of Rs.1628.35 Crores.
Shortly thereafter, Ext.P6 Master Service Agreement was entered into on
09.03.2019 between Kerala State Information Technology Infrastructure
Limited [KSITIL] on behalf of Kerala Fibre Optic Network Limited and BEL.
The formal approval of the State Government to the selection of BEL
Consortium was obtained through Ext.P7 G.O. dated 15.07.2019. It is clear,
therefore, that the writ petition was filed more than four years after work had
started on the KFON project.
3. The provocation for filing the writ petition appears to have been the
remarks made by the Comptroller & Auditor General [CAG] casting doubts on
the legality/propriety of the award of the contract to the BEL Consortium. The
audit queries posed by the CAG in 2023 form the basis of the allegations and
grounds in the writ petition, to seek the prayers aforementioned. The main
allegations raised in the writ petition, as re-iterated and urged by the learned
W.P.(C).No.1479/2024 :: 6 ::
2024:KER:69161
Senior Counsel Sri.George Poonthottam, on behalf of the petitioner, can be
summarised as follows:
●There was gross irregularity in awarding the contract to the BEL
Consortium at Rs.1628.35 Crores which was more than 10% in excess of
the figure of Rs.1028 Crores for which administrative sanction was
granted by the State Government in May 2017. Placing reliance on
Ext.P4 G.O. dated 06.02.2017 that dealt with delegation of powers to
departmental officers for sanctioning of tender excess/below estimate
rates, it is pointed out that the award of the contract to BEL Consortium
was at a rate that was far in excess of what was permissible. Referring to
Ext.P5 note dated 16.02.2019 issued from the IT Secretary of the State
Government to KSITIL, it is further suggested that the contract was
awarded to the BEL Consortium solely at the instance of the IT Secretary
and after by-passing the established procedure.
●The KFON project was conceived with the twin goals of (i) setting up
a State-wide core optical fibre network that would provide connectivity
to 30,000 + Government institutions and (ii) providing free internet to 20
Lakh economically backward families and subsidised internet for others
by leveraging the KFON infrastructure. The project, however, has
suffered serious setbacks and is now lagging behind in implementation
and is not expected to complete the work undertaken under the contract
within a reasonable time. This is largely on account of the delays
W.P.(C).No.1479/2024 :: 7 ::
2024:KER:69161
occasioned by the Consortium partners in meeting deadlines for the
supplies/deliverables envisaged under the contract.
●As per the tender conditions, the company supplying Optical Ground
Wires [OPGW] should have manufactured them in India, in keeping with
the ‘Make in India’ initiative of the Central Government and, further, has
to have facilities to test the manufactured cables in India. It has also to
satisfy the requirement of having manufactured and laid a minimum of
250 KM of cable in India in the past five years. In the instant case, the
remarks made by the CAG suggest that LS Cable India Private Limited
imported the optical unit of the OPGW from China and effected minimal
value addition thereto in India. It is also suggested that they do not have
the required testing and service facilities in India.
●The CAG has also pointed out that an interest free mobilisation
advance was granted to BEL Consortium without there being any
provision for granting the same under the contract entered into with
them. This has resulted in the BEL Consortium securing a financial
advantage through the award of the contract through terms that were
not envisaged in the tender process and were not made known to the
other bidders at the time of considering their bids.
4. Through counter affidavits filed on behalf of respondent Nos.1, 2 and
5, and documents produced at the time of hearing by the learned Advocate
General Sri. Gopalakrishna Kurup, appearing on behalf of the respondents, the
W.P.(C).No.1479/2024 :: 8 ::
2024:KER:69161
allegations above have been answered as follows:
●The alleged irregularities in the matter of award of the contract to
the BEL Consortium cannot be gone into at this belated stage of
implementation of the project. It is pointed out that none of the other
bidders had any grievance with regard to the award of the contract, and
further, no such irregularity has been occasioned by the respondents
while finalising the tender process. It is further pointed out that the lead
partner in the BEL Consortium is a Navaratna PSU under the Ministry of
Defence and has executed a number of high profile projects in defence
communication in India. That M/s RailTel, the other Consortium partner,
is a Miniratna PSU under the Ministry of Railways, that is one of the
largest telecom infrastructure providers in the country owning a pan
India optical fibre network on exclusive right to way along railway
tracks. The third Consortium partner, M/s LS Cable is one of the leaders
in OPGW market across the globe. There was therefore no reason to
doubt the credentials of the BEL Consortium, or their ability to perform
their obligations under the contract, at the time of award of the contract
to them.
●ln the initial Administrative Sanction [AS] issued in 2017, the
recurring Operational Charges of Rs.104.40 Crore for one year alone
was [for core and access network] reckoned instead of seven years and
thus the total AS amount was limited to Rs.1028.20 Crore. The amount of
W.P.(C).No.1479/2024 :: 9 ::
2024:KER:69161
Rs.1028.20 Crore mentioned in the petition is the first administrative
sanction [AS] issued by the Government. This includes the
implementation cost and one year Operation & Maintenance cost only.
However, the tender was floated for the implementation and seven years
Operation and Maintenance of the project as O&M [Operation &
Maintenance] is an integral part of the project. The bid amount for
KFON project after a discount of Rs.17 Crores offered by M/s BEL was
Rs.1531.68 Crore (excluding taxes). This bid amount was arrived at by
considering the operations and maintenance period of the project as
seven years, resulting in variation from the amount for which initial
Administrative Sanction was accorded. The Departmental Purchase
Committee, constituted as per the Stores Purchase Manual, which was
chaired by the Additional Chief Secretary, Finance Department approved
the selection of Consortium of M/s Bharat Electronics Limited, the LI
bidder, as the agency for implementation of KFON project. In the initial
Administrative Sanction an amount of Rs.16.40 Crores was allotted for
the cost of establishment to Special Purpose Vehicle [SPV] and
operations. Therefore, in addition to the tendered value [Rs.1531.68
Crore], Rs.16.40 Crore was also required for meeting the expenses in
connection with the operations and establishment of the SPV. Hence,
revised Administrative Sanction was accorded for the KFON project at a
total cost of Rs.1548.08 Crore + Taxes as applicable. The allegation
raised that the tender value is 58.5% higher than the estimated value is
not true and without understanding the facts and figures. The tender for
the selection of agency for the implementation of Kerala Fiber Optic
W.P.(C).No.1479/2024 :: 10 ::
2024:KER:69161
Network & Reliable Communication and Data Acquisition Network was
floated without an estimate value because the KFON was a first of its
kind project implemented in the State by the Government of Kerala.
Therefore, through competitive bidding process a price was discovered.
Tender was awarded based on the discovered price for implementing the
project in the entire State of Kerala. Further, at the time of issuance of
AS, what was contemplated was only one year's operation and
maintenance expenditure, whereas, Exhibit P3 Request for Proposal was
floated for 7 year's Operation and Maintenance expenditure. In these
circumstances, Exhibit P4 Government Order does not have any
application in the facts and circumstances of the case.
●As regards the alleged delay in implementation of the project, it is
argued that the project timeline was extended due to the following
reasons:-
COVID-19 and Flood Disruptions
Since March 2020, the construction work had faced disruptions due to
the impacts of both COVID-19 and floods, leading to a discontinuity in
the construction process for several months. Consequently, the
completion period for the construction project had to be extended.
Right-of-Way (RoW)
Delays are being encountered in the process of obtaining permissions
for the installation of fiber at railway crossings and bridges. Much time
was required for obtaining the required clearances for installing and
maintaining fiber on bridges and their surroundings from the Railways.
Impact of Road Widening
The process of widening highways frequently necessitates the
suspension or diversion of our fiber installation, resulting in a direct
delay in project progress. After the installation of fiber and the
establishment of the Point of Presence (POP), the ongoing road
widening leads to damages at sites where construction works have
been completed.
KSEBL Shutdown Permissions
W.P.(C).No.1479/2024 :: 11 ::
2024:KER:69161
The fiber network in KFON is established using KSEI3L's transmission
and distribution lines. Construction work involves suspending the
distribution of electricity in these areas. However, during emergencies,
pre-scheduled tasks have to be rescheduled due to the discontinuation
of electricity distribution, which depends on various factors. This poses
challenges to the timely completion of construction work.
●As regards the alleged breach of tender conditions regarding
adherence to the Make in India concept, the following submissions are
made:
As regards the averments and allegatins with regard to the Optical
Ground Wire [OPGW] cables have been supplied to KFON from L.S
Cables, an Indian firm which is a member of the consortium led by
Bharat Electronics Limited. The Galvanized Iron wire presently used by
KSEBL in the existing transmitter lines is only for the earthing and
protection of lines from lightning. It is made up of aluminium conductor
with steel reinforcement at the centre. But in the case of OPGW the
conductor can be used for protection as well as for the communication.
It is made up of 4 tubes of aluminium with 12 fibres in each tube by
replacing the steel wire. The dimension of the OPGW will also be in
higher size. So definitely the cost of OPGW will be higher than that of
GI wire because of this additional 4 Aluminium tubes with 48 fibres. At
the time of tender, no specification was prescribed for categorizing
OPGW as a "Make in India" product. However, the notification issued by
Department of Telecommunication (DOT), Government of India dated
29.08.20 18 contained "Make in India" stipulations for Optical Fiber
Cable (OFC). Therefore, the specification given for Optical Fiber Cable
was considered as a benchmark for categorizing the product as "Make
in India" whereby the local content should be a minimum of 55%. In
this regard, the System Integrator (BEL) produced a certificate from
the Chartered Accountant certifying that the local content used for
manufacturing of OPGW in terms of cost of production is 58%. Meeting
of the Technical Committee of KFON held on 19.12.2019 examined the
CA certificate and found the product satisfying the condition of Make in
India and LS Cables India Pvt Ltd satisfies the RFP condition of 'the
product shall be from an Indian manufacturer'. LS Cable India Private
Limited has submitted a performance warranty certificate of OPGW for
25 years. 2600 Km OPGW has been supplied under KFON in 6 lots. For
each lot, Factory Acceptance Test (FAT) of the OPGW has been
conducted in the factory of LS Cable India Pvt Ltd, I3awal, Haryana and
witnessed by KSEBL/ KSITIL officials. The equipment required for
conducting the FAT of OPGW are available in the factory. Most of the
type test of OPGW and fibre was conducted in India and only a few
tests, for which facilities were not available in India, was conducted in
China. Hence no tender condition was violated.
W.P.(C).No.1479/2024 :: 12 ::
2024:KER:69161
● Regarding the allegation that interest free mobilisation advance had
been given to the BEL Consortium, it is submitted that the Master
Service Agreement entered into with BEL envisaged that payments to
BEL were to be in accordance with the schedule to the RFP. Annexure IV
to the RFP was modified to incorporate a clause sanctioning a
mobilisation advance against BEL furnishing a Bank Guarantee for a like
amount, over and above the Performance Bank Guarantee already
furnished as per the RFP. It was also envisaged there under that
payments to BEL would be required to be made only to the extent of 40%
of the material cost on delivery. The balance payment of material
delivery cost was to be only in stages till the commissioning of the work.
It is contended therefore that there was no undue material advantage
that was obtained by the BEL Consortium in view of the mobilisation
advance that was sanctioned to them in terms of the contract.
● Lastly, it is submitted that merely because there was an audit
observation by the CAG, that by itself cannot form the basis for seeking a
CBI enquiry into the allegations raised against the respondents. In
support of the said contention, reliance is placed on the judgments in All
India Institute of Medical Sciences Employees' Union v. Union of
India – [1996 KH 3671] , State of W.B. And Others v. Committee for
Protection of Democratic Rights West Bengal and Others – [2010
(1) KHC 841], Kunga Nima Lepcha and Others v. State of Sikkim
and Others – 2010 KHC 4202], Secretary, Minor Irrigation and
Rural Engineering Services, U.P. v. Sahngoo Ram Arya – [2002
W.P.(C).No.1479/2024 :: 13 ::
2024:KER:69161
KHC 1280]; M/s. Karnataka EMTA Coal Mines Limited and
Another v. Central Bureau of Investigation – [2024 INSC 623];
Arun Kumar Agrawal v. Union of India and Others – [(2013) 7 SCC
1]; Sakiri Vasu v. State of U.P. And Others – [2008 (2) KHC 13] and
Sathyan Naravoor v. Union of India and Others – [2017 KHC 162] .
5. We have also heard the learned State Attorney Sri.N.Manoj Kumar on
behalf of the respondents.
6. On a consideration of the rival submissions, we are of the view that
the central issue to be considered in these cases is whether or not the
petitioner has made out a prima facie case warranting an interference by us
with the decision taken by the State Government to award the contract in
question to the BEL Consortium and/or, whether there is any material brought
to our notice in these proceedings that would warrant a direction to the CBI to
enquire into the matter to see whether there is any substance in the
allegations raised by the petitioner in the matter of implementation of the
KFON project by the respondents?
7. While considering the said issue we have to remind ourselves of the
nature of the jurisdiction that we exercise under Article 226 of the
Constitution of India, even in writ petitions that are in the nature of Public
Interest Litigations. It is trite that the nature of the exercise undertaken by
the High Court under Article 226 of the Constitution is one of judicial review.
Under ordinary circumstances, the review contemplated is a secondary review
W.P.(C).No.1479/2024 :: 14 ::
2024:KER:69161
where the court considers the legality, rationality or procedural propriety of a
decision already taken by a primary decision maker. In such an event, the
reviewing court looks merely at whether or not the decision taken by the
primary decision maker is one that he was empowered to take in terms of the
statutory provisions or executive orders having the force of law, and further
whether the decision taken by him is one of many possible views that he can
legally take. If not, the reviewing court would set aside the decision of the
primary authority, after stating the reasons for the same, and require the said
authority to take a fresh decision in the matter. In exceptional cases, where the
decision taken by the primary decision maker is one that infringes a
constitutional right of a citizen, whether fundamental or otherwise, or is one
that fails the test of proportionality in law, the reviewing court can resort to a
primary review and substitute its views for that of the primary authority.
8. Public Interest Litigations have been filed before our courts to invoke
the court’s power of primary review especially when the factual situation, that
affects the public at large, calls for emergent action or is such that an
adjudication of the matter before another authority would entail financial or
temporal challenges for the particular litigant espousing a cause on behalf of
the general public. In many such cases, the intervention by our courts has
ensured a safeguarding and preservation of our environment, and the securing
of justice to the many who cannot approach any legal forum for a redressal of
their grievances. Over the years, however, the jurisdiction has also been
invoked by a concerned citizenry to halt erring state action during its initial
stages so that a continuation of such action may not lead to irreparable harm,
W.P.(C).No.1479/2024 :: 15 ::
2024:KER:69161
or cause irretrievable damage or pecuniary loss to the public at large. In the
present case, for instance, it is the perception of an unwise or irregular award
of a contract, maybe one that has the propensity to cause financial stress to an
already beleaguered state exchequer, that has spurred the petitioner to move
this court. In our view, what is required of the court in such instances is to look
at the materials produced before it and determine whether there is sufficient
cause to interfere with the action taken by the State or not? If the answer to
that question is in the negative, then prudence demands that we permit the
state action to continue till fruition of its stated objective. The scheme of
separation of powers that is ingrained in our Constitution requires us to
accord such deference to actions of the State Executive.
9. In the instant case, the allegations raised in the writ petition stem
from the observations made by an audit party that had enquired into the
matter at the instance of the CAG. We are told that, to the many observations
made by the audit party, the respondents have preferred detailed replies that
would possibly allay the doubts and suspicions entertained by the audit party.
At any rate, the findings of the CAG on the issues raised by the audit party, if
adverse to the respondents herein, would be placed before the legislative
assembly for its scrutiny and comment. The petitioner being the Leader of the
Opposition of the Kerala Legislative Assembly would then have sufficient
opportunity to seek explanations from the State Executive for such actions as
are flagged as irregular or improper by the CAG. As was observed by the
Supreme Court in the recent decision in M/s. Karnataka EMTA Coal Mines
Limited and Another v. Central Bureau of Investigation - Neutral
W.P.(C).No.1479/2024 :: 16 ::
2024:KER:69161
Citation – [2024 INSC 623], following the decision in Arun Kumar Agrawal
v. Union of India and Others – [(2013) 7 SCC 1], the CAG report is subject
to scrutiny by the Legislature concerned and the Government can always offer
its views on the said report. Merely because the CAG is an independent
constitutional functionary does not mean that after receiving a report from it,
and on the Public Accounts Committee [PAC] scrutinising the same and
submitting its report, the legislature concerned will automatically accept the
said report. The legislature may agree or disagree with the report, or it may
accept it as it is or in part. In either event, the views taken by the CAG as
regards any loss caused to the exchequer remains only a viewpoint and cannot
be accepted as decisive. In the present case, there is no report drawn up by
the CAG as yet. Under the circumstances, we are of the view that the writ
petition itself, to the extent it raises allegations regarding the manner in which
the KFON project is being implemented, is premature. This is aside from the
fact that the writ petition, in its challenge to the award of the contract to the
BEL consortium, is hopelessly belated.
10. What remains to be considered is whether the petitioner has
produced any material that would persuade us to direct a CBI enquiry into the
issues flagged by the CAG and forming the basis of the allegations raised in
the writ petition regarding the manner of implementation of the KFON project.
It is by now well settled through a catena of decisions of the Supreme Court
that the High Court cannot mechanically direct a CBI investigation based on
allegations made in a writ petition. Rather, the court has to record a prima
facie case, based on the material on record, against the person against whom
W.P.(C).No.1479/2024 :: 17 ::
2024:KER:69161
such CBI enquiry is ordered [Secretary Minor Irrigation and Rural
Engineering Services U.P. v. Sahngoo Ram Arya – [(2002) 5 SCC 521];
State of W.B and Ors. v. Committee for Protection of Democratic Rights
West Bengal and Ors. – [(2010) 3 SCC 571]] . The material available before
us does not persuade us to arrive at a prima facie finding regarding any
illegality or irregularity on the part of the respondents in the matter of
implementation of the KFON project. On the contrary, the prima facie view
that emerges, after considering the explanation offered by the learned
Advocate General on behalf of the respondents, is that the KFON project
appears to be well on course towards realisation of its stated objectives of (i)
setting up a State-wide core optical fibre network that would provide
connectivity to 30,000 + Government institutions and (ii) providing free
internet to 20 Lakh economically backward families and subsidised internet for
others by leveraging the KFON infrastructure. This is more so because we are
told that as of now connectivity through the optical fibre network already laid
under the project, has been provided to 20,336 Government offices and free
internet has been provided to 5484 economically backward families till date.
Thus, we see no reason to interfere with the decisions taken by the
respondents that are impugned in this writ petition or to interdict the
respondents from implementing the project. We also do not see it necessary to
entrust an investigation into the allegations raised by the petitioner to the CBI
at this stage. As already noticed above, the report of the CAG, as and when
made available, can certainly be scrutinized by the Legislature/PAC and
appropriate action taken based on their comments thereon. At this stage of the
proceedings, we find that no grounds have been made out warranting an
W.P.(C).No.1479/2024 :: 18 ::
2024:KER:69161
interference with the KFON project by this court in exercise of its powers
under Article 226 of the Constitution of India. The writ petition fails and is
accordingly dismissed.
Sd/-
DR. A.K.JAYASANKARAN NAMBIAR
JUDGE
Sd/-
SYAM KUMAR V.M.
JUDGE
prp/
W.P.(C).No.1479/2024 :: 19 ::
2024:KER:69161
APPENDIX OF W.P(C).NO.1479/2024
PETITIONER EXHIBITS:
Exhibit P1 TRUE COPY OF THE RELEVANT PORTION OF THE BUDGET
SPEECH OF THE MINISTER FOR FINANCE DATED
03.03.2017.
Exhibit P2 TRUE COPY OF G.O.(MS) NO.10/2017/ITD DATED
18.05.2017.
Exhibit P3 TRUE COPY OF G.O.(MS)NO.10/2018/ITD DATED
10.05.2018 ISSUED BY THE ELECTRONICS AND
INFORMATION TECHNOLOGY DEPARTMENT.
Exhibit P3(a) TRUE COPY OF THE REQUEST FOR PROPOSAL FOR
SELECTION OF PROJECT MONITORING AGENCY (PMA) OF
KERALA FIBRE OPTIC NETWORK (KFON) AND RELIABLE
COMMUNICATION AND DATA ACQUISITION NETWORK
DATED JULY 2019, BY KSITIL FOR THE KFON PROJECT
AS AVAILABLE IN KFON WEBSITE
(HTTPS://KFON.KERALA.GOV.IN/WP-
CONTENT/UPLOADS/2021/02/KFON-PMA-RFPV314.PDF).
Exhibit P4 TRUE COPY OF G.O.(P) NO.16/2017/FIN DATED
06.02.2017 ISSUED BY THE FINANCE (INDUSTRIES &
PUBLIC WORKS) DEPARTMENT.
Exhibit P5 TRUE COPY OF THE LETTER ISSUED BY THE IT
SECRETARY TO THE M.D, KSITIL, DATED 16.02.2019.
Exhibit P6 TRUE COPY OF THE MASTER SERVICE AGREEMENT
BETWEEN BEL AND KSITIL DATED 09.03.2019.
Exhibit P7 TRUE COPY OF THE SANCTION ORDER G.O.
(MS)NO.14/2019/ITD DATED 15.07.2019, ISSUED BY
THE ELECTRONICS AND IT DEPT.
Exhibit P7(a) TRUE COPY OF THE ANSWER GIVEN BY THE MINISTER
TO UNSTARRED LEGISLATIVE QUESTION NO.48 DATED
08-08-2023 IN THE KERALA LEGISLATIVE ASSEMBLY.
Exhibit P8 TRUE COPY OF ACKNOWLEDGEMENT RECEIPT DATED
09.10.2019 FROM ASHOKA BUILDCON FOR RECEIPT OF
ORDER FROM SRIT.
Exhibit P9 TRUE COPY OF THE PURCHASE ORDER NO.11055449
DATED 13.11.2019, ISSUED BY ASHOKA BUILDCON TO
PRESADIO.
W.P.(C).No.1479/2024 :: 20 ::
2024:KER:69161
Exhibit P10 TRUE COPY OF THE RELEVANT PAGES OF THE 22ND
ANNUAL REPORT 2021-22 OF RAILTEL EVIDENCING ITS
RELATIONSHIP WITH SRIT IN KSWAN.
Exhibit P10(a) TRUE COPY OF THE DOCUMENT DOWNLOADED FROM
RAILTEL WEBSITE SHOWING THEIR MSPS IN VARIOUS
CIRCLES.
Exhibit-P11 TRUE COPY OF THE CAG'S OBSERVATIONS PERTAINING
TO PROCUREMENT OF OPGW FROM CHINA IN VIOLATION
OF TENDER CONDITIONS DATED 16.05.2023 WITH ITS
TYPED LEGIBLE COPY.
Exhibit P12 TRUE COPY OF THE REQUEST FOR PROPOSAL FOR THE
SELECTION OF MANAGED SERVICE PROVIDER FOR KFON
PROJECT BEARING TENDER REF NO:
KSITIL/KFON/2022-23/7184 DATED JANUARY, 2023.
Exhibit P13 TRUE COPY OF THE TENDER SUMMARY REPORT WITH
REGARD TO SELECTION OF MANAGED SERVICE PROVIDER
FOR KFON PROJECT DATED 02.05.2023.
Exhibit P14 TRUE COPY OF THE DOCUMENT DOWNLOADED FROM
RAILTEL WEBSITE SHOWING M/S CUBE FIBERNET
PRIVATE LIMITED AS THE MSP OF RAILTEL IN
ANDHRAPRADESH.
Exhibit-P15 A TRUE COPY OF THE DOCUMENT DOWNLOADED FROM
RAILTEL WEBSITE SHOWING M/S LIGHTWAVE
TECHNOLOGIES PRIVATE LIMITED AS THE MSP OF
RAILTEL IN ODISHA
Exhibit -P16 A TRUE COPY OF THE WORK ORDER ISSUED BY KSITIL
TO SRIT AS MSP DATED 24.03.2023 WITH ANNEXURES.
Exhibit-P17 A TRUE COPY OF THE REQUEST FOR PROPOSAL OF
SUPPLY, INSTALLATION, TESTING & COMMISSIONING
OF ISP HARDWARE AND SOFTWARE FOR KERALA FIBRE
OPTIC NETWORK BEARING TENDER REF NO:
KSITIL/KFON/2022-23/18 DATED JANUARY, 2023,
PUBLISHED BY KERALA STATE INFORMATION
TECHNOLOGY INFRASTRUCTURE LIMITED
Exhibit-P18 A TRUE COPY OF THE OFFICE MEMORANDUM DATED
25.07.2016 ISSUED BY THE MINISTRY OF FINANCE,
DEPARTMENT OF EXPENDITURE GIVING RELAXATION TO
START-UP COMPANIES
Exhibit-P19 A TRUE COPY OF THE E-MAIL LETTER SENT BY
AKSHARA ENTERPRISES TO KSITIL DATED 09.03.2023
W.P.(C).No.1479/2024 :: 21 ::
2024:KER:69161
Exhibit-P20 A TRUE COPY OF LETTER ISSUED BY RAILTEL TO
KSITIL DATED 10.03.2023
Exhibit-P20(a) TRUE COPY OF LETTER ISSUED BY RAILTEL TO KSITIL
DATED 11.03.2023
Exhibit-P21 A TRUE COPY OF THE REPLY COMMUNICATION DATED
15.03.2023 SENT BY KFON LTD TO M/S. AKSHARA
ENTERPRISES PVT. LTD.
Exhibit-P21(a) A TRUE COPY OF THE REPLY COMMUNICATION DATED
15.03.2023 SENT BY KFON LTD TO RAILTEL
CORPORATION OF INDIA
Exhibit-P22 A TRUE COPY OF THE REQUEST FOR PROPOSAL OF
SUPPLY, INSTALLATION, TESTING & COMMISSIONING
OF ISP HARDWARE AND SOFTWARE FOR KERALA FIBRE
OPTIC NETWORK BEARING TENDER REF NO:
KSITIL/KFON/2023-24/7608 DATED MAY, 2023,
Exhibit-P22(a) A TRUE COPY OF THE REPORT DATED 12.07.2023
SUBMITTED BY THE PRINCIPAL ACCOUNTANT GENERAL
AUDIT-II WITH ITS TYPED LEGIBLE COPY
Exhibit-P22(b) A TRUE COPY OF THE REPORT OF CAG DATED
13.06.2023 ALONG WITH ITS TYPED LEGIBLE COPY
Exhibit-P22(c) A TRUE COPY OF THE CAG REPORT DATED 08.06.2023
Exhibit P23 A TRUE COPY OF THE ANSWER GIVEN BY THE HON'BLE
CHIEF MINISTER IN THE LEGISLATIVE ASSEMBLY ON
08.08.2023, WITH ITS ENGLISH TRANSLATION
RESPONDENT EXHIBITS
Exhibit R5(a) A true photocopy of the Make in India (MII)
notifications. As per Public Procurement
(Preference to Make in India) Order 2017 dated
15.06.2017 issued by the Department of
Industrial Policy and Promotion, Ministry of
Commerce and Industry, Government of India
Exhibit R5(b) A true photocopy of the Public Procurement
(Preference to Make in India), Order 2017 dated
28.05.2018 issued by the Department of
Industrial Policy and Promotion, Ministry of
Commerce and Industry, Government of India
Exhibit R5(c) A true photocopy of the Public Procurement
(Preference to Make in India), Order 2017-
Notification of Telecom Products, Services or
W.P.(C).No.1479/2024 :: 22 ::
2024:KER:69161
Works dated 29.08.2018 issued by the Department
of Telecommunications, Ministry of
Communication, Government of India
Exhibit R5(d) A true photocopy of the Company Incorporation
Certificate issued by the Registrar of
Companies, Government of India
Exhibit R5(e) A true photocopy of the Factory License issued
by the Chief Inspector of Factories, Haryana
Exhibit R5(f) A true photocopy of the Certificate No.
5157/ETDC/5/TD/405/LS dated 10.10.2018 issued
by the Superintending Engineer of the Uttar
Pradesh Power Transmission Corporation Limited,
an Uttar Pradesh Government undertaking,
proving the experience of LS cable
Exhibit R5(g) Operational acceptance certificate dated
10.03.2015 issued by the Chief Manager, Power
Grid Corporation of India to LS Cable
Exhibit R5(h) A true photocopy of the Supply, Installation
and Commissioning Certificate dated 07.12.2015
issued by the Managing Director, Jaiprakash
Power Ventures Ltd proving the experience of LS
cable in OPGW
Exhibit R5(i) A true photocopy of the Minutes of the 9th
Meeting of KFON Technical Committee held on
19th December 2019
Exhibit R5(j) A true photocopy of the letter dated 03.01.2020
from the Chief Engineer (Trans-SO), KSEBL to
the Chief Engineer (IT, CR and CAPs), KSEBL
(who is the member of the KFON Technical
Committee)
Exhibit R5(k) A true photocopy of the Corrigendum No.
KSITIL/MD/KFON/18/CRM-12(1)/2014 with regards
to payment terms mentioning the mobilization
advance.
//TRUE COPY//
P.S. TO JUDGE
Legal Notes
Add a Note....