1
AFR
RESERVED
Court No.39
Case :- WRIT - C No. - 43934 of 2017
Petitioner :- Vijay Singh Tyagi And 25 Others
Respondent :- State Of U.P. And 3 Others
Counsel for Petitioner :- Shiv Kant Mishra
Counsel for Respondent :-C.S.C., Ms. Meenakshi Singh, Anoop Trivedi
Hon'ble Dilip Gupta,J.
Hon'ble Dinesh Kumar Singh-I,J.
(Delivered by Hon'ble Dilip Gupta, J.)
This petition has been filed for quashing the award dated 19
November 2013 made by the Additional District Magistrate (Land
Acquisition)
1
under Section 11 of The Land Acquisition Act, 1894
2
as
also the amended award dated 4 March 2014 that seeks to make
corrections under Section 12-A(1) of the 1894 Act in the aforesaid award
dated 19 November 2013. A further relief that has been claimed is that
compensation should, thereafter, be determined in accordance with the
proviso to Section 24(2) of the Right to Fair Compensation and
Transparency in Land Acquisition Rehabilitation and Resettlement Act,
2013
3
.
The petitioners claim to be owners of 0.165 hectares of land
situated in Khasra No. 126 in village Rasulpur, Yaqoobpur, Tehsil and
District Ghaziabad. A notification under Section 4(1) of the 1894 Act
read with sub-sections (1) and (4) of Section 17 of the 1894 Act was
issued on 16 October 2004 for acquisition of 68.537 hectares of land
1'ADM (LA)'
2'the 1894 Act'
3the 2013 Act
Neutralt:itationtNoqtltDwm8YB’:Ym)Dm6(lx&
2
situated in village Rasulpur, Yakoobpur, including 0.165 hectares of land
situated in Khasra No.126, for construction of a residential colony by the
Ghaziabad Development Authority, Ghaziabad
4
under a Planned
Development Scheme. This was followed by a declaration made under
Section 6 of the 1894 Act on 28 October 2005. The award was made
under Section 11 of the 1894 Act by the ADM(LA) on 19 November
2013. Possession of 61.522 hectares of land was taken on 18 May 2006;
of 1.971 hectares of land on 21 March 2009; of 0.747625 hectares on 31
December 2009 and of 4.2607375 hectares on 2 June 2010. It needs to be
stated that the award was made under Section 11(1) of the 1894 Act for
6.648125 hectares of land, while the award for 19.214875 hectares of
land was made under Section 11 (2) of the 1894 Act under the provisions
of The Land Acquisition (Determination of Compensation and
Declaration of Award by Agreement) Rules, 1997
5
. The award for the
remaining 42.585 hectares of land was not made because of the interim
orders passed by the Court. However, as there were clerical mistakes in
the award dated 19 November 2013, the Collector on his own motion
corrected the same on 4 March 2014.
Learned counsel for the petitioners submitted that there were no
clerical or arithmetical mistake in the award dated 19 November 2013
and, therefore, the date of award should be treated as 4 March 2014, on
which date the amended award was made. The submission is that the
compensation for the land should, therefore, have been determined in
accordance with the provisions of the 2013 Act as is provided for under
4'the Development Authority'
5'the 1997 Rules'
3
Section 24(1)(a). In the alternative, learned counsel for the petitioners
submitted that all the beneficiaries specified in the notification for
acquisition of land are entitled to receive compensation in accordance
with the provisions of the 2013 Act as contemplated under the proviso to
Section 24(2) of the 2013 Act since compensation in respect of a majority
of the land holdings was not deposited in the account of the beneficiaries.
To support this submission, learned counsel for the petitioners placed
reliance upon the decision of a Full Bench of the Bombay High Court
(Nagpur Bench) in Writ Petition No.3447 of 2015
6
; a Division Bench
judgment of the Delhi High Court in Writ Petition (C) No.8596 of 2014
7
which was subsequently followed by the Division Benches of the Delhi
High Court in Writ Petition (C) No. 5095 of 2014; Writ Petition (C)
No. 8273 of 2014
8
and Writ Petition (C) No.1103 of 2016
9
. It has,
therefore, been submitted that the award dated 19 November 2013 should
be set aside and it should be made in accordance with the principles set
out in the proviso to Section 24(2) of the 2013 Act.
Ms. Meenakshi Singh, learned Standing Counsel appearing for the
State respondents and Sri Anoop Trivedi learned counsel appearing for
the Development Authority, however, submitted that the date of the
award would continue to remain as 19 November 2013 even if some
corrections were subsequently made on 4 March 2014 and, therefore, the
provisions of the 2013 Act so far as they relate to payment of
6'Dayaram Bhondu Koche & Ors., Vs. The State of Maharashtra, & Ors., decided on 5 December
2016
7Tarun Pal Singh & Anr. Vs. Lt. Governor, Govt. of NCT of Delhi & Ors., decided on 21 May 2015
8Guru Nanak Vidya Bhandar Trust Vs. Union of India & Ors., decided on 4 January 2017
9Mahendra Vs. Union of India & Ors., decided on 30 August 2017
4
compensation would not apply. Learned counsel for the respondents
further submitted that the proviso to Section 24(2) of the 2013 Act would
apply to only those awards that were made five years or more prior to 1
January 2014, which is the date of commencement of the Act and,
therefore, it would have no application to the case of the petitioners since
the award was made on 19 November 2013.
We have considered the submissions advanced by learned counsel
for the parties.
In order to appreciate the first contention advanced by learned
counsel for the petitioners, it would be appropriate to reproduce Section
12-A of the 1894 Act as inserted by UP Amendment on 19 November
1954 and the same is as follows:
“12A. Power to correct award.-(1) The
Collector may, at any time but not later than six
months from the date of award, or where a reference is
required to be made under section 18, before making
of such reference, correct any clerical or arithmetical
mistake in the award either on its own motion or on
the application of any person interested.
(2) The Collector shall give immediate notice of
any correction made in the award to all persons
interested and, where the acquisition of land is not for
the purposes of the Union, also to the State
Government.
(3) Where any excess amount is provided to
have been paid to any person as a result to the
correction made under sub-section (1), such person
shall be liable to refund the excess, and if he defaults
or refuses to pay, the same may be realised as an
arrear of land revenue.”
The submission advanced by learned counsel for the petitioners is
that the date of the award made under Section 11 of the 1894 Act should
5
be treated as 4 March 2014 and not 19 November 2013. The Court had
required the ADM (LA) to explain what clerical or arithmetical
corrections were required to be carried out in the award dated 19
November 2013. A detailed affidavit has been filed by the ADM (LA)
explaining the corrections that were required to be made. The corrections
are basically with regard to wrong dates or spelling mistakes or wrong
area of the land mentioned in the award dated 19 November 2013. The
mistakes are all covered under Section 12-A(1) of the 1894 Act and were
corrected within six months from the date of the award. The date of the
award would continue to remain as 19 November 2013, even if certain
corrections were subsequently carried out on 4 March 2014. In this view
of the matter when the award under Section 11 of the 1894 Act was made
on 19 November 2013 prior to the commencement of the 2013 Act, the
provisions of Section 24(1)(a) of the 2013 Act would not apply and
compensation was not required to be determined under the provisions of
the 2013 Act. The first submission advanced by learned counsel for the
petitioners, therefore, cannot be accepted.
The second submission of learned counsel for the petitioners is that
the petitioners are entitled to receive compensation in accordance with the
provisions of the 2013 Act as contemplated under the proviso to Section
24(2) of the 2013 Act since compensation in respect of a majority of land
holdings was not deposited in the account of the beneficiaries. It is,
however, important to note that details to substantiate that compensation
in respect of the majority of land holdings was not deposited in the
6
account of the beneficiaries have not been provided by the petitioners and
only a bald statement has been made.
To appreciate the contention, it would be appropriate to refer to
some of the relevant provisions of the 2013 Act. Section 11 deals with
publication of a preliminary notification. It provides that whenever, it
appears to the appropriate Government that land in any area is required or
likely to be required for any public purpose, a notification (called
preliminary notification) to that effect along with details of the land to be
acquired shall be published. Section 15 provides for hearing of objections
by any person interested in the land which has been notified under
Section 11(1) as being required or likely to be required for a public
purpose, within sixty days from the date of the publication of the
preliminary notification. Section 19 deals with publication of declaration
and summary of Rehabilitation and Resettlement. It provides that when
the appropriate Government is satisfied, after considering the report, if
any, made under Section 15(2) that any particular land is needed for a
public purpose, a declaration shall be made to that effect which shall be
published in the manner provided for in sub-section (4) of Section 19.
Section 21 (1) provides that the Collector shall publish public notice on
his website and cause public notice to be given at convenient places on or
near the land to be taken, stating that the Government intends to take
possession of the land and claims to compensation and rehabilitation and
resettlement for all interests in such land may be made to him. Section 23
provides that the Collector shall proceed to enquire into the objections (if
7
any), which any person interested has stated pursuant to a notice given
under Section 21 and shall make an award.
Section 24, on which reliance has been placed by learned counsel
for the petitioners, is reproduced hereinbelow:
“24. Land acquisition process under Act No.
1 of 1894 shall be deemed to have lapsed in certain
cases:–
(1) Notwithstanding anything contained in this Act, in
any case of land acquisition proceedings initiated
under the Land Acquisition Act, 1894 (1 of 1894), -
(a) where no award under Section 11 of the said
Land Acquisition Act has been made, then, all
provisions of this Act relating to the
determination of compensation shall apply; or
(b) where an award under said Section 11 has
been made, then such proceedings shall
continue under the provisions of the said Land
Acquisition Act, as if the said Act has not been
repealed.
(2) Notwithstanding anything contained in sub-section
(1), in case of land acquisition proceedings initiated
under the Land Acquisition Act, 1894 (1 of 1894),
where an award under the said section 11 has been
made five years or more prior to the commencement
of this Act but the physical possession of the land has
not been taken or the compensation has not been paid
the said proceedings shall be deemed to have lapsed
and the appropriate Government, if it so chooses, shall
initiate the proceedings of such land acquisition afresh
in accordance with the provisions of this Act:
Provided that where an award has been made
and compensation in respect of a majority of land
holdings has not been deposited in the account of the
beneficiaries, then, all beneficiaries specified in the
notification for acquisition under section 4 of the said
Land Acquisition Act, shall be entitled to
compensation in accordance with the provisions of
this Act.”
Section 26 deals with the determination of the market value of the
land by the Collector and Section 27 deals with determination of amount
8
of compensation. It provides that the Collector having determined the
market value of the land to be acquired shall calculate the total amount of
compensation to be paid to the land owner by including all assets attached
to the land.
Section 30 (1) deals with award of solatium and is as follows:-
“30. Award of solatium.-(1) The Collector
having determined the total compensation to be paid,
shall, to arrive at the final award, impose a “Solatium”
amount equivalent to one hundred per cent of the
compensation amount.
Explanation.- For the removal of doubts it is
hereby declared that solatium amount shall be in
addition to the compensation payable to any person
whose land has been acquired.
(2) The Collector shall issue individual awards
detailing the particulars of compensation payable and
the details of payment of the compensation as
specified in the First Schedule.
(3) In addition to the market value of the land
provided under Section 26, the Collector shall, in
every case, award an amount calculated at the rate of
twelve per cent per annum on such market value for
the period commencing on and from the date of the
publication of the notification of the Social Impact
Assessment study under sub-section (2) of Section 4,
in respect of such land, till the date of the award of the
Collector or the date of taking possession of the land,
whichever is earlier.”
Section 77 of the 2013 Act which deals with payment of
compensation or deposit of the same in the Authority is reproduced
below:
“77.Payment of Compensation or Deposit of
Same in Authority (1) On making an award under
section 30, the Collector shall tender payment of the
compensation awarded by him to the persons
interested entitled thereto according to the award and
shall pay it to them by depositing the amount in their
9
bank accounts unless prevented by someone or more
of the contingencies mentioned in sub-section (2).
(2) If the person entitled to compensation shall not
consent to receive it, or if there be no person
competent to alienate the land, or if there be any
dispute as to the title to receive the compensation or as
to the apportionment of it, the Collector shall deposit
the amount of the compensation in the Authority to
which a reference under section 64 would be
submitted:
Provided that any person admitted to be interested
may receive such payment under protest as to the
sufficiency of the amount:
Provided further that no person who has received the
amount otherwise than under protest shall be entitled
to make any application under sub-section (1) of
section 64:
Provided also that nothing herein contained shall
affect the liability of any person, who may receive the
whole or any part of any compensation awarded under
this Act, to pay the same to the person lawfully
entitled thereto.”
Section 114 of the 2013 Act deals with repeal and savings and is
reproduced below:
“114. Repeal and savings.-(1) The Land
Acquisition Act, 1894, (1 of 1894) is hereby repealed.
(2) Save as otherwise provided in this Act the
repeal under sub-section (1) shall not be held to
prejudice or affect the general application of section 6
of the General Clauses Act, 1897 (10 of 1897) with
regard to the effect of repeals.”
It is in the light of the aforesaid provisions of the 2013 Act that the
second submission of learned counsel for the petitioners, based on the
proviso to Section 24(2) of the 2013 Act, is required to be examined.
Section 24(1) of the 2013 Act deals with land acquisition
proceedings that have been initiated under the provisions of the 1894
Act. Clause (a) of Section 24(1) of the 2013 Act provides that where no
10
award under Section 11 of the 1894 Act has been made, then, all the
provisions of the 2013 Act relating to the determination of compensation
shall apply. Clause (b) of Section 24 (1) of the 2013 Act, however,
provides that where an award under Section 11 of the 1894 Act has been
made, then such proceedings shall continue under the provisions of the
1894 Act, as if the said Act has not been repealed.
Sub-section (2) of Section 24 also deals with acquisition
proceedings initiated under the provisions of the 1894 Act. It provides
that notwithstanding anything contained in sub-section (1) of Section 24,
where an award under Section 11 of the 1894 Act has been made five
years or more prior to the commencement of the 2013 Act, but the
physical possession of the land has not been taken or the compensation
has not been paid, the said proceedings shall be deemed to have lapsed
and the appropriate Government, if it so chooses, shall initiate the
proceedings of such land acquisition afresh in accordance with the
provisions of the 2013 Act.
The proviso to Section 24(2) stipulates that where an award has
been made and compensation in respect of a majority of land holdings
has not been deposited in the account of the beneficiaries, then, all
beneficiaries specified in the notification for acquisition under section 4
of the 1894 Act, shall be entitled to compensation in accordance with the
provisions of the 2013 Act.
A bare perusal of Section 24(2) of the 2013 Act shows that like
Section 24(1), it also deals with land acquisition proceedings that have
11
been initiated under the provisions of the 1894 Act but it is restricted to
an acquisition in which the award has been made under Section 11 of the
1894 Act five years or more prior to 1 January 2014. It provides that in
such a case, the land acquisition proceedings shall be deemed to have
lapsed if the physical possession of the land has not been taken or the
compensation has not been paid. The proviso to Section 24(2) is preceded
by a grammatical punctuation 'colon'. The submission of learned counsel
for the petitioners is that the proviso to Section 24(2) would, when land
acquisition proceedings have been initiated under the provisions of the
1894 Act, apply to awards made under Section 11 of the 1894 Act within
five years prior to 1 January 2014. The contention of learned counsel for
the respondents, however, is that the proviso has necessarily to cover only
such awards which have been made five years or more prior to 1 January
2014 as is contemplated in Section 24(2).
As noticed above, sub-section (1) of Section 24 of the 2013 Act,
deals with two situations when land acquisition proceedings have been
initiated under the provisions of the 1894 Act. The first situation
contained in clause (a) is when the award under Section 11 of the 1894
Act has not been made prior to 1 January 2014. In such a situation all the
provisions of the 2013 Act relating to determination of compensation
shall apply. The second situation contained in clause (b) is when the
award has been made under Section 11 of the 1894 Act prior to 1 January
2014. In such an event, the proceedings shall continue under the
provisions of the 1894 Act, as if the said Act has not been repealed. Sub-
12
section (2) of Section 24 also deals with land acquisition proceedings
initiated under the provisions of the 1894 Act. It seeks to carve out an
exception to Section 24(1) and provides that notwithstanding anything
contained in sub-section (1), where an award has been made under
Section 11 of the 1894 Act five years or more prior to the commencement
of the 2013 Act but the physical possession of the land has not been taken
or the compensation has not been paid then the land acquisition
proceedings shall be deemed to have lapsed.
The Supreme Court has time and again examined the provisions of
Sections 24(1) and 24(2) of the 2013 Act. It has explained the conditions
under which Section 24(1) of the 2013 Act would apply and the
conditions under which Section 24(2) of the 2013 Act would apply. It has
been observed by the Supreme Court that Section 24(1) of the 2013 Act,
which deals with acquisition proceedings that have been initiated under
the provisions of the 1894 Act, covers situations where either no award
has been made under Section 11 of the 1894 Act, in which case the
beneficial provisions of 2013 Act would apply for determination of
compensation or where an award has been made under Section 11 of the
1894 Act, in which case the provisions of the 1894 Act would apply as if
the said Act has not been repealed. In relation to Section 24(2) of the
2013 Act, it has been pointed out that the State cannot be permitted to
expropriate the property of a citizen if the award has been made and the
necessary steps to complete the acquisition have not been taken for a
period of five years or more. These steps, the Supreme Court explained,
13
include taking physical possession of the land and payment of
compensation. The Supreme Court has also explained that 'compensation'
would be considered as paid if the compensation has been deposited in
the Court where a Reference under Section 18 could be made, in view of
the provisions of Section 31 of the 1894 Act.
In this connection it would be pertinent to refer to the decision of
the Supreme Court in Delhi Development Authority Vs. Sukhbir Singh
& Ors.
10
. While examining the provisions of sub-section (2) of Section
24, the Supreme Court held that in a case where the award under Section
11 of the 1894 Act was made five years or more prior to 1 January 2014,
the acquisition would lapse either when physical possession of the land
has not been taken or compensation has not been paid by 1 January 2014.
It rejected the contention that “or” should be read as “and”. The
observations are as follows:
“11.Section 24(1) begins with a non-obstante clause
and covers situations where either no award has been
made under the Land Acquisition Act, in which case
the more beneficial provisions of the 2013 Act relating
to determination of compensation shall apply, or
where an award has been made under Section 11, land
acquisition proceedings shall continue under the
provisions of the Land Acquisition Act as if the said
Act had not been repealed.
12. To Section 24(1)(b) an important exception is
carved out by Section 24(2). The necessary
ingredients of Section 24(2) are as follows:
(a) Section 24(2) begins with a non-obstante
clause keeping sub-section (1) out of harm’s
way;
(b) For it to apply, land acquisition proceedings
should have been initiated under the Land
Acquisition Act;
10(2016) 16 SCC 258
14
(c) Also, an award under Section 11 should
have been made 5 years or more prior to the
commencement of the 2013 Act;
(d) Physical possession of the land, if not taken,
or compensation, if not paid, are fatal to the
land acquisition proceeding that had been
initiated under the Land Acquisition Act;
(e) The fatality is pronounced by stating that the
said proceedings shall be deemed to have
lapsed, and the appropriate Government, if it so
chooses, shall, in this game of snakes and
ladders, start all over again.
13. The picture that therefore emerges on a
reading of Section 24(2) is that the State has no
business to expropriate from a citizen his property
if an award has been made and the necessary steps
to complete acquisition have not been taken for a
period of five years or more. These steps include the
taking of physical possession of land and payment of
compensation. What the legislature is in effect telling
the executive is that they ought to have put their house
in order and completed the acquisition proceedings
within a reasonable time after pronouncement of
award. Not having done so even after a leeway of five
years is given, would cross the limits of legislative
tolerance, after which the whole proceeding would be
deemed to have lapsed. It is important to notice that
the Section gets attracted if the acquisition proceeding
is not completed within five years after
pronouncement of the award. This may happen either
because physical possession of the land has not been
taken or because compensation has not been paid,
within the said period of five years. A faint
submission to the effect that ‘or’ should be read as
‘and’ must be turned down for two reasons. The
plain natural meaning of the sub-section does not lead
to any absurdity for us to replace language advisedly
used by the Legislature. Secondly, the object of the
Act, and Section 24 in particular, is that in case an
award has been made for five years or more,
possession ought to have been taken within this
period, or else it is statutorily presumed that the
balance between the citizen’s right to retain his
own property and the right of the State to
expropriate it for a public purpose gets so
disturbed as to make the acquisition proceedings
lapse. Alternatively, if compensation has not been
15
paid within this period, it is also statutorily
presumed that the aforesaid balance gets disturbed
so as to free such property from acquisition.”
(emphasis supplied)
It would also be pertinent to refer to the decision of the Supreme
Court in Pune Muncipal Corporation & Anr. Vs. Harakchand
Misirimal Solanki & Ors.
11
. The Supreme Court observed that for the
purposes of Section 24(2), compensation shall be regarded as “paid” if
the compensation has been offered to the person interested and such
compensation has been deposited in the Court where a Reference under
Section 18 can be made on the happening of any of the contingency
contemplated under Section 31 of the 1894 Act. In other words even if
compensation is deposited in the Court, it would be considered as “paid”.
The observations are as follows:-
“17. While enacting Section 24(2), Parliament
definitely had in its view Section 31 of the 1894 Act.
From that one thing is clear that it did not intend
to equate the word “paid” to “offered” or
“tendered”. But at the same time, we do not think
that by use of the word “paid”, Parliament intended
receipt of compensation by the landowners/persons
interested. In our view, it is not appropriate to give a
literal construction to the expression “paid” used in
this sub-section (sub-section (2) of Section 24). If a
literal construction were to be given, then it would
amount to ignoring procedure, mode and manner of
deposit provided in Section 31(2) of the 1894 Act in
the event of happening of any of the contingencies
contemplated therein which may prevent the Collector
from making actual payment of compensation. We
are of the view, therefore, that for the purposes of
Section 24(2), the compensation shall be regarded
as “paid” if the compensation has been offered to
the person interested and such compensation has
been deposited in the court where reference under
Section 18 can be made on happening of any of the
11(2014) 3 SCC 183
16
contingencies contemplated under Section 31(2) of
the 1894 Act. In other words, the compensation may
be said to have been “paid” within the meaning of
Section 24(2) when the Collector (or for that matter
Land Acquisition Officer) has discharged his
obligation and deposited the amount of compensation
in court and made that amount available to the
interested person to be dealt with as provided in
Sections 32 and 33.”
(emphasis supplied)
It, therefore, follows that the land acquisition proceedings initiated
under the provisions of the 1894 Act, in view of the provisions of Section
24(2) of the 2013 Act, shall be deemed to have lapsed where the award
has been made under Section 11 of the 1894 Act five years or prior to 1
January 2014 but the physical possession of the land has not been taken
or the compensation has not been paid. The foremost condition that needs
to be satisfied before the benefit of Section 24(2) of the 2013 Act is
available is that the award should have been made under Section 11 of the
1894 Act five years or more prior to the date of commencement of the
2013 Act i.e. 1 January 2014.
These factors have to be kept in mind to understand what the
proviso to Section 24(2) of the 2013 Act contemplates. Section 24(2) of
the 2013 Act deals with an award made under Section 11 of the 1894 Act
five years or more prior to 1 January 2014. The proviso to Section 24(2)
also talks of an award. It has, therefore, to be examined whether the
award referred to in the proviso is an award made five years or more prior
to 1 January 2014 or to an award made within five years prior to 1
January 2014. It needs to be noted that the proviso to Section 24(2) of the
2013 Act is preceded by a grammatical punctuation “colon”. It would,
17
therefore, be necessary for the Court to first examine the effect of the
grammatical punctuation “colon” before the proviso and then understand
what is the true meaning of a “proviso”.
However, before examining this it would be pertinent to note that
the Supreme Court in State of Gujarat Vs. Reliance Industries Ltd.
12
emphasised the importance placed on punctuation. In Ashwini Kumar
Ghosh Vs. Arabinda Bose
13
, the Supreme Court had earlier also pointed
out that when a statute is carefully punctuated, weight should be given to
the punctuation. In A.K. Gopalan Vs. State of Maharashtra
14
, the
Supreme Court also while construing Article 22(7)(a) of the Constitution,
referred to the punctuation and derived assistance from it in reaching a
conclusion that the Parliament was not obliged to prescribe both the
circumstances under which, and the class or classes of cases, in which a
person may be detained for a period longer than three months, without
obtaining the opinion of the Advisory Board and that the Parliament on a
true construction of the clause could prescribe either or both.
The World Book Encyclopedia Volume IV, defines “Colon” as:
“Colon is a mark of punctuation shown as: Its primary function is
to separate an introduction from what it introduces: a list, a long
quotation, an illustration, or an explanation. A colon is most often used
when the words preceding it form a complete sentence, as in the second
sentence of this article.”
12 Civil Appeal Nos.13047-13048 of 2017, decided on 22 September 2017
13AIR 1952 SC 369
14AIR 1950 SC 27
18
Webster's Encyclopedia Unabridged Dictionary of the English
Language also defines 'Colon' as:
“The sign : used to mark a major division in a sentence, to indicate
that what follows is an elaboration, summation, implication, etc. of what
precedes.”
A colon is used between independent clauses when the second
sentence explains, illustrate, paraphrases, or expands on the first sentence.
The most common use of the word 'Colon' is to inform the reader that
what follows the 'colon' proves, explains, defines, describes or lists
elements of what preceded it. A colon in grammatical use is a punctuation
which is associated with what immediately precedes it. The Colon
introduces the logical consequence, or effect, of a fact stated before.
A Division Bench of this Court presided over by Hon'ble the Chief
Justice Dr. D.Y. Chandrachud, (as His Lordship then was) in Rahul
Upadhyay Vs. Union of India Thru' Ministry of Road Transport & 3
Ors.,
15
explained the use of the grammatical punctuation “Colon” as also
“proviso”. The petitioner had sought to challenge the legality of a
notification issued by the Union Government on 2 January 2015 in
exercise of the power conferred by Rule 3 of the National Highways Fee
(Determination of Rates and Collection) Rules, 2008 by which the
Central Government exempted eight bridges in the State of Uttar Pradesh
from the levy of a user fee. The petitioner placed reliance of Section 7 of
the National Highways Act, 1956. The first submission of the petitioner
was based on the proviso to Section 7(3) of the National Highways Act,
152015(5) ADJ 217
19
1956. The submission that was advanced was that the proviso applies to
the entire Section 7 and not only to Section 7(3). This was repelled by the
Division Bench holding that the proviso which follows is evidently a
proviso to sub-section (3) of Section 7 on a plain language of the proviso
and also because it was preceded by a “colon'. The observations are as
follows:-
“The submission is that the proviso which is
extracted above under which the Central
Government has been empowered to exempt the
payment of fees in public interest leviable on any
bridge is a proviso which applies to the entire
Section 7 and not only to Section 7 (3).
Under Section 7 (1), the Union Government has
been empowered to levy fees at such rates as may be
prescribed by rules made in that behalf for services or
benefits rendered inter alia in relation to the use of
ferries and permanent bridges the cost of construction
of each of which is in excess of rupees twenty-five
lakhs and which are opened to traffic on or after 1
April 1976, as well as temporary bridges and tunnels
on national highways. Sub-section (3) deals with fees
leviable immediately before the commencement of
the Act for services or benefits rendered in relation
to the use of ferries, temporary bridges and tunnels
on any highway specified in the Schedule. These
fees under sub-section (3) were to continue to be
leviable under the Act unless and until they were
altered in exercise of the powers conferred by sub-
section (1). The proviso which follows is evidently a
proviso to sub-section (3) of Section 7. This is
evident from two aspects. The first is the plain
language of the proviso which stipulates that the
Central Government may, if it is of the opinion that it
is necessary in public interest to do so, specify that
fees shall not be leviable "under this sub-section" on
any bridge specified. The expression "under this sub-
section" is in reference to sub-section (3). Secondly,
the proviso which is preceded by a colon. A colon
in grammatical use is a punctuation which is
associated with what immediately precedes it.
Hence, there would be no merit in the submission
that the proviso qualifies the entire Section 7.
20
The power which has been exercised by the
Central Government is under the proviso to Rule 3 (1)
of the Rules of 2008 under which the Central
Government has been empowered to issue a
notification exempting any section of a national
highway, permanent bridge, bypass or tunnel
constructed through a public funded project from the
levy of such fee or part thereof.
(emphasis supplied)
The real nature of a “proviso” also needs to be understood. It has
been explained by Justice G.P. Singh, in “Principles of Statutory
Interpretation-11
th
Edition 2008” in the following words:-
“The normal function of a proviso is to except
something out of the enactment or to qualify
something enacted therein which but for the proviso
would be within the purview of the enactment..........
The proviso may, as LORD MACNAGHTEN laid
down, be “a qualification of the preceding enactment
which is expressed in terms too general to be quite
accurate”. The general rule has been stated by
HIDAYATULLAH, J., in the following words: “As a
general rule, a proviso is added to an enactment to
qualify or create an exception to what is in the
enactment, and ordinarily, a proviso is not interpreted
as stating a general rule”. And in the words of
KAPUR, J., “The proper function of a proviso is that it
qualifies the generality of the main enactment by
providing an exception and taking out as it were, from
the main enactment, a portion which, but for the
proviso would fall within the main enactment.
Ordinarily it is foreign to the proper function of
proviso to read it as providing something by way of an
addendum or dealing with a subject which is foreign
to the main enactment.”
The function of a proviso to a section has been elaborately dealt
with by the Supreme Court in Haryana State Cooperative Land
Development Bank Ltd. Vs. Haryana State Cooperative Land
Development Bank Employees Union
16
. It has been held that the normal
16(2004) 1 SCC 574
21
function of a proviso is to except something out of the enactment or to
qualify something enacted therein which but for the proviso would be
within the purview of the enactment. It has also been held that the proviso
carves out an exception to the main provision to which it has been
enacted as a proviso and to no other.
The learned author Justice G.P. Singh has also explained that a
proviso has to be construed in relation to the section or sections to which
it is appended. The same are as follows:-
“The language of a proviso even if general is
normally to be construed in relation to the subject-
matter covered by the section to which the proviso is
appended. In other words normally a proviso does not
travel beyond the provision to which it is a proviso.”
It would also be pertinent to refer to cases which highlight the
aforesaid position.
The Supreme Court in Ram Narain Sons Ltd. and Ors., Vs. Asst.
Commissioner of Sales Tax and Ors.,
17
observed that a proviso has to
be construed in relation to the subject-matter covered by the section to
which the proviso is appended. The Supreme Court observed that it is a
cardinal rule of interpretation that a proviso to a particular provision of a
statute only embraces the field which is covered by the main provision. It
carves out an exception to the main provision to which it has been
enacted as a proviso and to no other. It, therefore, held that the proviso
appended to Article 286(2) of the Constitution authorising the President
to lift the ban imposed by the said provision was not available for lifting
the ban imposed by Article 286(1).
17AIR 1955 SC 765
22
On the same principle, in CIT Mysore etc. Vs. Indo Mercantile
Bank, Ltd.
18
the first proviso to Section 24(1) of the Indian Income-tax
Act, 1922 was construed as limited in its application to set-off of profits
and losses arising under different heads, a subject dealt with by Section
24(1) and was held inapplicable to set-off of profit and losses dealt with
under sections 7 to 12-B.
In Dwarka Prasad Vs. Dwarka Das Saraf,
19
the Supreme Court
also observed that a proviso must be limited to the subject matter of the
enacting clause and that it is a settled rule of construction that a proviso
must prima facie be read and considered in relation to the principal matter
to which it is a proviso. The Supreme Court also observed that the
golden rule is to read the whole section, inclusive of the proviso, in such a
manner that they mutually throw light on each other and result in a
harmonious construction. The observations are as follows:-
“We may mention in fairness to Counsel that
the following, among other decisions, were cited at the
Bar bearing on the uses of provisos in statutes: CIT
Vs. Indo-Mercantile Bank Ltd.; M/s. Ram Narain
Sons Ltd. Vs. Asstt. C.S.T.; Thompson Vs. Dibdin;
Rex Vs. Dibdin and Tahsildar Singh Vs. State of U.P..
The law is trite. A proviso must be limited to the
subject-matter of the enacting clause. It is a settled
rule of construction that a proviso must prima
facie be read and considered in relation to the
principal matter to which it is a proviso. It is not a
separate or independent enactment. 'Words are
dependent on the principal enacting words, to which
they are tacked as a proviso. They cannot be read as
divorced from their context' . If the rule of
construction is that prima facie a proviso should be
limited in its operation to the subject-matter of the
enacting clause, the stand we have taken is sound. To
expand the enacting clause, inflated by the proviso,
18AIR 1959 SC 713
19AIR 1975 SC 1758
23
sins against the fundamental rule of construction that a
proviso must be considered in relation to the principal
matter to which it stands as a proviso. A proviso
ordinarily is but a proviso, although the golden
rule is to read the whole section, inclusive of the
proviso, in such manner that they mutually throw
light on each other and result in a harmonious
construction.”
(emphasis supplied)
In Vijayalakshamma and Anr. Vs. B.T. Shankar
20
the Supreme
Court pointed out that the proviso and the explanation appended to
Section 7 of the Hindu Adoption and Maintenance Act, 1956 cannot be
permitted to be read in Section 8 of the Act.
It would also be pertinent to refer to the decision of the Supreme
Court in State of Punjab Vs. Kailash Nath
21
. Rule 2.2 of the Punjab
Civil Services Rules reserves to a Government the right of withholding or
withdrawing pension or any part of it, or to order for recovery from
pension if the pensioner is subsequently found guilty of grave misconduct
or negligence during the period of his service in departmental or judicial
proceedings. This rule, however, stipulates that no such judicial
proceedings, if not instituted while the officer was in service, shall be
instituted in respect of a cause of action which arose or an event which
took place more than four years before such institution. The Supreme
Court held that the proviso had to be read as an exception to the main
provision meaning that if the judicial proceeding is not instituted within
the period mentioned in the proviso, the Government will not have a right
to withhold or withdraw the pension and the proviso does not provide a
20(2001) 4 SCC 558
21(1989) 1 SCC 321
24
general embargo on the prosecution of an officer after the expiry of that
period.
Justice G.P. Singh, in “Principles of Statutory Interpretation”
has also explained the consequences of using different words in the same
statute and they are as follows:-
“When in relation to the same subject-matter,
different words are used in the same statute, there is a
presumption that they are not used in the same sense.”
Section 24(2) of the 2013 Act refers to payment of compensation.
The proviso to Section 24(2) of the 2013 Act, as noted above, stipulates
that where an award has been made and compensation in respect of a
majority of land holdings has not been deposited in the account of the
beneficiaries, then all beneficiaries specified in the notification for
acquisition under Section 4 of the 1894 Act shall be entitled to
compensation in accordance with the provisions of the 2013 Act. The
proviso does not use the words “compensation has been paid”. On the
other hand, it uses the words “compensation in respect of a majority of
land holdings has not been deposited in the account of the
beneficiaries”. The Legislature has intentionally used the words
“compensation has not been paid” in Section 24(2) and the words
compensation in respect of a majority of land holdings has not been
deposited in the account of the beneficiaries in the proviso to Section
24(2). The use of different words in the same Section 24 has, therefore, to
be taken into consideration while analyzing the situation covered by the
proviso to Section 24(2) of the 2013 Act.
25
At this stage it would be pertinent to refer to the provisions of
Section 77 of the 2013 Act. It provides that on making an award under
Section 30 of the 2013 Act, the Collector shall tender payment of the
compensation awarded by him to the persons interested entitled thereto
by depositing the amount in their bank accounts unless prevented by
one or more of the contingencies mentioned in sub-section (2). Sub-
section (2) provides that if a person entitled to compensation shall not
consent to receive it, or if there be no person competent to alienate the
land and or if there be any dispute as to the title to receive the
compensation or to the apportionment of it, the Collector shall deposit
the amount of the compensation in the Authority to which a reference
under Section 64 would be submitted. Thus, while Section 24 (2) refers to
payment of compensation in the sense that compensation shall also be
considered to have been paid if deposited in the Court as contemplated
under Section 77(2), the proviso to Section 24 (2) refers to deposit of
compensation in the account of the beneficiaries as contemplated under
Section 77(1) of the 2013 Act.
The proviso to Section 24(2) of the 2013 Act would obviously not
cover a case where the land acquisition proceedings shall be deemed to
have lapsed because then, the tenure holders would not be entitled to any
compensation. The land acquisition proceedings, as contemplated under
Section 24(2) lapse in a case where the award has been made five years or
more prior to 1 January 2014 but the physical possession of the land has
not been taken or the “compensation has not been paid”. Thus, if land
26
acquisition proceedings have not to lapse, the proviso should cover cases
where possession has been taken, (otherwise the acquisition would lapse),
and compensation has been paid (because if it has not been paid the
acquisition would also lapse).
It is, therefore, clear that the proviso would cover a case where in
regard to land acquisition proceedings initiated under the 1894 Act an
award has been made under Section 11 of the 1894 Act five years or more
prior to 1 January 2014 and physical possession of the land has been
taken and compensation has also been paid to the tenure holders either
by actual payment or deposit in the Court but compensation in respect of
a majority of land holdings has not been deposited in the account of the
beneficiaries. It is only in such a situation that the Legislature has
provided that all the beneficiaries specified in the notification for
acquisition under Section 4 of the 1894 Act shall be entitled to
compensation in accordance with the provisions of the 2013 Act.
The situation can also be understood by making reference to the
following illustration. Supposing there are 100 holdings that are acquired
under the provisions of the 1894 Act by issuance of a notification under
Section 4(1) and the declaration under Section 6 of the 1894 Act and the
award has been made under Section 11 of the 1894 Act five years or more
prior to 1 January 2014. For the acquisition not to lapse under Section
24(2) of the 2013 Act, possession of the land must have been taken and
compensation must have been paid to the tenure-holders. Payment of
compensation would include both actual payment by deposit in the
27
account of the beneficiaries as also deposit in a Court where a reference
under Section 18 of the 1894 Act could have been filed. It is possible that
compensation in respect of a majority of land holdings has been deposited
in the account of majority of land holdings or it may not have been
deposited. In case the compensation has not been deposited in the account
of more than 50 land holdings, then in that situation alone compensation
for the acquisition of land would be determined in regard to all the
holdings under the provisions of the 2013 Act. This in fact is an
additional benefit provided to a tenure holder in cases where the land
acquisition proceedings have not lapsed even if the award has been made
more than five years prior to 1 January 2014.
The submission of learned counsel for the petitioners that the
proviso would only cover cases where the award under Section 11 of the
1894 Act has been made within five years from 1 January 2014 can also
be tested by taking a hypothetical case where the award is made on 31
December 2013. It would not be possible to deposit the compensation in
the account of a majority of land holdings in one day. Thus,
compensation in accordance with the provisions of the 2013 Act would
then have to be disbursed to all the beneficiaries specified in the
notification for acquisition under Section 4 of the 1894 Act. This is
certainly not the intention of the Legislature because if it was such, a
provision could have been specifically inserted at the relevant place.
Thus, from the use of the grammatical punctuation 'Colon' coupled
with the meaning assigned to a proviso, the proviso to Section 24(2) of
28
the 2013 Act has to be read in the context of the main enactment and
cannot be read in isolation dehors the provisions of Section 24(2) of the
2013 Act. The “award” referred to in the proviso to Section 24(2) of the
2013 would necessarily refer to an award made five years or more prior to
1 January 2014 as is contemplated under Section 24(2) of the 2013 Act.
There is, therefore, no difficulty in holding that the proviso to Section
24(2) has to, where land acquisition proceedings have been initiated
under the provisions of the 1894 Act, cover only those awards which
have been made five years or more prior to 1 January 2014. The proviso
does not deal with awards made within five years prior to 1 January 2014.
What, therefore, follows from a harmonious construction of the
provision of sub-sections (1) and (2) of Section 24 of the 2013 Act and
the proviso contained to sub-section (2) of Section 24 of the 2013 Act is
as follows;
(1). Under Section 24(1) of the 2013 Act, there can be two
situations when acquisition proceedings have been initiated under the
provisions of the 1894 Act. The first is when an award has not been made
upto 1 January 2014 and the second is when an award has been made. In
case the award has not been made, then all the provisions of the 2013 Act
relating to determination of compensation shall apply but if an award has
been made then the proceedings shall continue under the provisions of the
1894 Act as if the said Act has not been repealed;
(2). Section 24(2) provides that where an award under Section 11
has been made five years or more prior to 1 January 2014 in case of land
29
acquisition proceedings initiated under the provisions of the 1894 Act,
but the physical possession of the land has not been taken or the
compensation has not been paid, the said proceedings shall be deemed to
have lapsed. However, compensation shall be considered as paid to the
tenure holder even if it is deposited in a Court where a Reference can be
filed under Section 18 of the 1894 Act.
(3) However, where an award under Section 11 of the 1894 Act
has been made five years or more prior to 1 January 2014 in case land
acquisition proceedings had been initiated under the 1894 Act and the
physical possession of the land was taken and compensation was paid in
the sense that it was either deposited in the account of the tenure holder or
deposited in the Court but compensation in respect of a majority of land
holdings was not deposited in the account of the beneficiaries, then all the
beneficiaries specified in the notification for acquisition under Section 4
of the 1894 Act shall be entitled to receive compensation in accordance
with the provisions of the 2013 Act.
(4).The benefit of the proviso to Section 24(1) of the 2013
would not be available to a tenure holder if the award is made within five
years prior to 1 January 2014.
The view taken by us finds support from a Division Bench
judgment of the Kerala High Court in Writ Appeal No.2041 of 2015
22
.
The Division Bench presided over by Hon'ble the Chief Justice Ashok
Bhushan (as His Lordship then was), repelled the contention of the
appellant that the proviso to Section 24(2) of the 2013 Act would be
22M.M. Jeevan & Anr. Vs. State of Kerala & Ors., decided on 14 October 2015
30
applicable in regard to those awards which were made within five years
prior to 1 January 2014. It held that if this was the intention of the
Legislature, it could have inserted the proviso to Section 24(1) and not to
Section 24(2). The Division Bench observed that the proviso has to be
interpreted in a manner so as to embrace the field covered by the main
provision. The observations are:-
“12. What is the object and intend of the
proviso appended to Section 24(2) is the core
question to be answered. Whether the proviso is
applicable even in cases where although award was
made prior to the enforcement of the 2013 Act it was
not made prior to five years or more of the
commencement of the 2013 Act as required by
Section 24(2). As noted above under Section 24(1)(b)
it is provided that where an award under Section 11 of
the 1894 Act has been made, then such proceedings
shall be continued under the provisions of the 1894
Act as the said Act has not been repealed. In event
the Legislature wanted to extend the benefit of the
proviso to all cases where award has been made
prior to enforcement of the 2013 Act, proviso could
have been very well appended to Section 24(1).
What is the object of appending the proviso to Section
24(2) is to be found out. In a case where award has
been made five years or more prior to the
commencement of the 2013 Act and physical
possession of the land has not been taken or
compensation has not been paid, the acquisition
proceedings are deemed to be lapsed. In the present
case it is not disputed that petitioners were not paid
compensation prior to enforcement of the 2013 Act
and physical possession was also taken subsequent to
the enforcement of the 2013 Act but the conditions
enumerated in Section 24(2) that award has to be
made five years or more before the enforcement of the
2013 Act is not satisfied. Thus the present case does
not fall in the condition precedent prescribed in
Section 24(2) for lapsing the proceedings.
13. A plain reading of the proviso indicate that
the proviso contemplates that when award has been
made compensation in respect of majority of land
holdings was not deposited in the account of the
31
beneficiaries then all beneficiaries under Section 4(1)
notification shall be entitled to compensation in
accordance with the provisions of the 2013 Act. The
proviso contemplates a situation in which although
award has been made, but in majority of the cases
compensation has not been deposited, then all
beneficiaries are to be given the benefit of the 2013
Act including those with regard to whom
compensation has not been deposited and those
who have received the compensation covered by
the same notification. Thus in the normal
circumstance when compensation has not been
deposited in respect of majority of land holdings, the
acquisition is deemed to be lapsed as per Section 24(2)
but proviso provides that even in those cases
compensation is to be paid in accordance with the
2013 Act, an exception has been carved out in the
proviso where the acquisition is not to be lapsed.
…..................
17. A proviso thus appended to a provision
has to be interpreted in the manner so as to
embrace the field which is covered by the main
proviso. The proviso is only an exception to the main
provision to which it has been enacted and no other. A
proviso deals with the situation which takes something
out of the main enactment to provide a particular
course of action which course of action could not have
been adopted in the absence of the proviso.
18. Proviso appended to Section 24(2)
indicates that it carves out an exception for a
situation where the land acquisition proceedings
shall not be deemed to lapse. Thus for applicability
of the proviso a case has to be covered by Section
24(2), i.e., (i) award has been made five years or more
prior to the enforcement of the 2013 Act and (2) either
physical possession of the land has not been taken or
compensation has not been paid.
19. Proviso contemplates a situation where
majority of the land holders were not paid
compensation nor compensation is deposited in their
accounts meaning thereby that for majority of land
holders acquisition has to lapse but for the proviso.
The proviso in fact extend the benefit even to those
land holders who have received compensation as per
the 1894 Act. Thus all the land holders are to receive
benefit of higher and liberal compensation under
Section 2013 Act. This situation is one where land
acquisition proceedings shall not lapse and are saved.”
32
(emphasis supplied)
In Writ Appeal No.175 of 2015
23
the Gauhati High Court also
took the same view and the observations are:-
“6. The next question to be considered is
whether compensations can be paid to the
appellants in terms of the proviso to Section 24(2)
of the Act of 2013. The submission of Mr. A.M.
Bbuzarbaruah, the learned senior counsel for the
respondents is that inasmuch as the compensation
amounts were not disbursed to the respondents even
after the commencement of the Act of 2013, all the
landowners are entitled to compensations in
accordance with the proviso to Section 24(2) of the
Act of 2013. In my opinion, the learned Senior
Counsel appears to have overlooked the fact that a
proviso cannot be read in isolation, and must be
read in the context of the main enactment. Before
proceeding further, let us first ascertain the meaning
of the term “proviso”. The text of the proviso to
Section 24(2) of the Act of 2013 has already been
extracted earlier. The language of a proviso, even if
general, is normally to be construed in relation to the
subject-matter covered by the Section to which the
proviso is appended. In other words, normally, a
proviso does not travel beyond the provision to which
it is a proviso.
7. In my opinion, the proviso in question will
come into play once it is established that an award
has been made under Section 11 of the Act five
years or more before the commencement of the Act
and possession of the lands of the landowners was
taken but compensation was not paid to majority
of such landowners. In other words, this is a case
where the acquisition proceedings of the land cannot
be deemed to have lapsed under Section 24(2) of the
Act of 2013 but Section 24(1)(b) will apply. As
already noticed, once the criteria for deemed lapsed of
the land acquisition proceedings under Section 24(2)
of the Act of 2013 are fulfilled, then the question of
payment of compensation in terms of the award
already made under Section 11 of the old Act will not
and cannot arise since the land acquisition proceeding
itself will have died a natural death. In such
eventualities, the legislature has left it to the discretion
23 M/s Athena Demwe Power Limited, Vs. Sh. Laideo Tayan and Ors,., decided on 5 January 2016
33
of the State Government whether or not to initiate a
fresh proceeding for acquisition of the same land in
accordance with the Act of 2013. However, as
already noticed, there could be a situation where
the land acquisition proceedings cannot be deemed
to have lapsed under Section 24(2) since the
conditions for the deemed lapsed thereunder are
not satisfied such as when possession of land has
already been taken but compensation has not been
paid even after making of the award five years or
more prior to the commencement of the Act of
2013. In the meantime, the market value of the lands
of such landowners could have increased by leaps and
bounds but, to the misfortune of these landowners, an
award was already made under the old Act on the
basis of the market value obtaining on the date of the
notification under Section 4 of the old Act i.e. five
years or more before the commencement of the Act of
2013. This is most likely to cause heavy loses to the
landowners without their fault. In my judgment, it is
for these landowners that the proviso has been inserted
by the legislature to give protection to such
landowners. Thus, where an award has been made
five years or more prior to the coming into force of
the Act of 2013 but the lands of the landowners
were already taken possession of, but
compensations for majority of the land holdings
have not been deposited in the account of these
landowners, such landowners shall be entitled to
compensation in accordance with the provisions of
the Act of 2013. However, the landowners such as
the private respondents herein, for whom an award
was made within five years of the coming into force of
the Act of 2013, cannot obviously take advantage of
the proviso to Section 24(2) of the Act of 2013 as
there was no delay in making the award for them; to
hold otherwise will amount to conferring upon them
unjust enrichment at the expense of the appellants.
Consequently, neither Section 24(2) nor the proviso to
Section 24(2) of the Act of 2013 can be held
applicable to the facts of these appeals. Thus, to sum
up, the proviso will operate in a field not covered
by Section 24(2) and will operate only when an
award has been made under Section 11 of the old
Act and possession of the land was taken but
majority of the landowners are not paid their
compensations five years or more before the
coming into force of the Act of 2013. Consequently,
34
in the instant case, the land acquisition proceedings
shall be allowed to continue, and compensations to the
appellant paid in accordance with the award made
under the provisions of the Land Acquisition Act,
1894 as if this Act has not been repealed.”
(emphasis supplied)
The Division Benches of both the Kerala High Court and the
Gauhati High Court have taken a view that the proviso to Section 24(2) of
the 2013 Act would cover only such awards that have been made under
Section 11 of the 1894 Act five years or more prior to 1 January 2014.
Reliance has, however, been placed by learned counsel for the
petitioners on a Full Bench decision of the Bombay High Court in
Dayaram Bhondu Koche. The Full Bench considered a case where an
award under Section 11 of the 1894 Act was made within a period of five
years prior to 1 January 2014 as the award was made under Section 11 of
the 1894 Act on 17-11-2010. The benefit of the proviso to Section 24(2)
of the 2013 Act was held to be available where the award was made
within five years prior to 1 January 2014 by reading the proviso as an
exception to Section 24(1)(b) of the 2013 Act. The observations are:-
10. The proviso below sub-section (2) deals
with the subject of applicability of the provisions of
the 2013 Act relating to the determination of
compensation covered by clause (b) of sub-section (1)
of Section 24 therein, subject to the satisfaction of
condition that the compensation in respect of a
majority of land holdings has not been deposited in
the account of the beneficiaries. In our view, the
proviso has to be read as an exception to the
provision of clause (b) in sub-section (1) of Section
24 of the 2013 Act so as to advance the intention of
the Legislature to strike the balance of conflicting
interest between the land holders and the State,
and to award a fair compensation.”
(emphasis supplied)
35
A Division Bench of the Bombay High Court in Writ Petition No.
1923 of 2014
24
with which another Division Bench of the Bombay High
Court had not agreed as a result of which the matter had been referred to
the Full Bench in Dayaram Bhondu Koche, however, observed that the
provisions of Section 24(2) of the 2013 Act would apply only to awards
made five years or more prior to 1 January 2014 and the observations are
as follows:
“On hearing the learned counsel for the parties
and on a perusal of the provisions of the Act of 2013,
it appears that the petitioners would not be entitled to
compensation under the Act of 2013. On a reading of
the provisions of Section 24 of the Act of 2013, it
appears that the provisions of Section 24(2), to
which the proviso is appended, would apply only to
the Awards that are made five years or more, prior
to the commencement of the Act of 2013. The award
was not made five years or more, prior to the
commencement of the Act of 2013. The Award was
made on 09.07.2009 and the Act of 2013 came into
force on 01.01.2014. The Award was not made five
years or more, prior to the commencement of the Act
on 01.01.2014. Since, the proviso appears to have
been appended to sub-section (2) of Section 24 of the
Act of 2013, the petitioners would not be entitled to
seek compensation under the provisions of the new
Act. The object of the proviso is to provide to the
beneficiaries, who have already received the
compensation under the Act of 1894, higher
compensation under the Act of 2013, if the
compensation in respect of the majority of land
holdings has not been deposited in the account of the
beneficiaries. The proviso would come into play
only if the Award is made five years or more, prior
to the commencement of the Act of 2013. For
example, if an Award is made just a day before the
commencement of the Act of 2013 or a fortnight
before its commencement, there is no occasion for
the State Government to deposit the amount of
compensation in the accounts of the beneficiaries as
certain procedure under the Act of 1894 like issuance
24Shrikant Shankarrao Daulatkar & Ors., Vs. State of Maharashtra & Ors., decided on 22 June 2015
36
of notice to the claimants to receive the compensation
and securing necessary documents in respect of their
identification, would be required to be undergone.
Under Section 31 of the Land Acquisition Act, 1894,
after making the Award under Section 11, the
Collector is required to tender payment of the awarded
compensation to the persons entitled to receive it and
if they do not consent to receive it, the Collector is
required to deposit the compensation in the Court.
Also, it is clear from the provisions of Section 24(1)
(b) that where the Award is made under Section 11 of
the Land Acquisition Act, 1894, then such
proceedings shall continue under the provisions of the
Land Acquisition Act, 1894 as if the Act was not
repealed. The provisions of sub-section (2) of Section
24 carve out an exception to the provisions of Section
24(1)(b) of the Act of 2013 and create a class of
acquisitions in respect of the Awards, which have
been made five years or more, prior to the
commencement of the Act of 2013 under the Land
Acquisition Act, 1894, but where the physical
possession of the land is not taken or the
compensation has not been paid, for the purpose of
lapsing. The proviso, being applicable to the
provisions of sub-section (2) of Section 24, the
condition precedent for seeking compensation
under the Act of 2013 would be the making of the
award five years or more prior to the
commencement of the Act of 2013. In the instant
case, the Award is not made five years or more, prior
to the commencement of the Act of 2013. The
petitioners would, therefore, not be entitled to the
compensation under the Act of 2013. Though, the
petitioners are not entitled to compensation under the
Act of 2013, since the petitioners have not received
the compensation determined under the Act of 1894
till date, it would be necessary to direct the
respondents to pay the same to the petitioners along
with the other benefits flowing from the provisions of
the Act of 18894, within a time frame.”
(emphasis supplied)
Reliance has also been placed by learned counsel for the petitioners
on a Division Bench judgment of the Delhi High Court in Tarun Pal
37
Singh & Anr. The Division Bench took the same view as was taken by
the Full Bench of the Bombay High Court and the observations are:-
“7. It is, therefore, clear that in those cases
where the Awards have been made more than five
years prior to the commencement of the Act, section
24(2) would have applicability, subject to the other
conditions being fulfilled. But, in cases where the
Awards have been made within five years of the
commencement of the 2013 Act, section 24(2) would
not apply. It is also clear that once the conditions of
section 24(2) are met, the acquisition itself lapses and
therefore, no occasion would arise for invoking the
first proviso which is set out after section 24(2). This
is so because the first proviso entails a situation where
the acquisition is saved but the compensation is
awarded under the 2013 Act. The proviso cannot
blow life into the acquisition which has lapsed
under the main provision of sub-section (2) of
Section 24 of the 2013 Act. It is for this reason that
we think that the first proviso which has been
placed after section 24(2) is not really a proviso to
section 24(2) but, a proviso to Section 24(1)(b). The
said first proviso and Section 24(1)(b) can easily be
read together. Section 24(1)(b) in effect relates to
all cases where awards have been under the 1894
Act except those which are covered under Section
24(2). Clearly, awards made less than five years
prior to the commencement of the 2013 Act would
fall under Section 24(1)(b). As such, the general rule
in such cases is that the provisions of the 1894 Act
would continue to be applicable, as if the 1894 Act
had not been repealed. However, the said first proviso
carved out an exception to this general rule by
providing that in cases where compensation in respect
of a majority of land holdings has not been deposited
in the account of the beneficiaries, then, all
beneficiaries specified in the notification for
acquisition under Section 4 of the 1894 Act shall be
entitled to compensation in accordance with the
provisions of the 2013 Act. This is a provision for the
benefit of landowners inasmuch as even in cases of
completed acquisitions, if the conditions stipulated
under the said first proviso stand satisfied, the
compensation would have to be provided under the
more beneficial provisions of the 2013 Act.
38
8. Thus, while the said first proviso can
harmoniously exist when read as a proviso to
Section 24(1)(b), it cannot so exist when sought to
be read as a proviso to Section 24(2) of the 2013
Act.”
(emphasis supplied)
For all the reasons stated above, it is not possible to accept the view
taken by the Full Bench of the Bombay High Court in Dayaram Bhondu
Koche or the Division Bench of the Delhi High Court in Tarun Pal
Singh. The proviso to Section 24(2) of the 2013 Act cannot be read as an
exception to Section 24(1)(b) of the 2013 Act. In fact, the award under
Section 11 of the 1894 Act should have been made five years or more
prior to 1 January 2014. In the present case, the award was made within
five years prior to 1 January 2014. The petitioners would not be entitled
to the benefit of the proviso to Section 24(2) of the 2013 Act.
There is, therefore, no merit in the second contention advanced by
learned counsel for the petitioners.
Thus, for all the reasons stated above, the writ petition deserves to
be dismissed and is, accordingly, dismissed.
Date :-6 November 2017
NSC
(Dilip Gupta, J.)
(Dinesh Kumar Singh-I, J.)
Legal Notes
Add a Note....