As per case facts, the plaintiff claimed an oral agreement with the defendant to purchase land for an industrial park, alleging subsequent part performance through land transfers and a development ...
HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
APPELLATE SIDE
PRESENT:
THE HON’BLE JUSTICE SABYASACHI BHATTACHARYYA
AND
THE HON’BLE JUSTICE SANDIP KUMAR DE
FMA 916 OF 2025
With
CAN 2 of 2020
With
CAN 3 of 2021
With
CAN 4 of 2026
Alok Niwas Private Limited
Vs
Debasish Pal and Ors.
For the appellant: Mr. Indranil Ray, Sr. Adv.,
Mr. Sanjoy Mukherjee, Adv.,
Mr. Suvradal Chowdhury, Adv.
For the respondent nos. 1 & 2.: Mr. Kushal Chatterjee, Adv,
Mr. Tauhid Khan, Adv,
Mr. Atanu Haldar, Adv.
Last heard on: 27.08.2026
Judgement on: 03.09.2026
2
SANDIP KUMAR DE, J.:
1. The present appeal has been filed against the judgment and order dated
October 3, 2019 passed by the learned Civil Judge (Senior Division),
1
st
Court at Howrah in connection with an application under Order 39
Rules 1 and 2 read with Section 151 of the Code of Civil Procedure in
Title Suit No.187 of 2019. By the order impugned the learned trial court
had rejected the application for temporary injunction filed by the
plaintiff.
2. The plaint case is that the plaintiff purchased several plots to construct
and set up an industrial park situate at the scheduled properties
mentioned in Part 1 of the schedule of the plaint. For such purpose, the
plaintiff purchased several plots of land from defendant Nos.6 to 26
(“the Pal family” for short). The plaintiff entered into an oral agreement
with the defendant No.1, the respondent No.1 herein, to the effect that
the defendant No.1 shall convey the total area of 3.8680 acres of land,
both demarcated as well as undivided in favour of the plaintiff for an
agreed consideration of Rs.6,88,22,217/-. Out of the said area, the
partitioned area of 151.46 decimals of land held by defendant No.1
exclusively, shall be conveyed subject of reciprocal obligations. In that
case, the plaintiff would convey to the defendant No.1 65.640 decimals
of land in several plots within Mouza Bipannapara, JL No.27, P.S
Domjur, District Howrah upon payment of consideration of Rs. 1.24
crore. Upon such transfer of 65.640 decimals of land, the
defendant No.1 would convey and transfer 6.540 decimals of land in
several plots both in Mouza Mohiary totaling 53.99 decimals
3
demarcated along with undivided 1/2
nd
share in different areas at Mouza
Bipannapara and Mouza Mohiary totaling 11.65 decimals for
consideration of Rs.1.46 crores. Upon such mutual transfer of land, the
defendant No.1 would then convey and transfer all partitioned and
demarcated land held by the defendant No.1 in several plots described
in paragraph No.4(c) (iii) of the plaint in favour of the plaintiff at an
agreed consideration of Rs.3,36,88,554/-. It was further agreed between
the plaintiff and defendant No.1 and that upon conveying the said area
of 65.64 decimals of land the plaintiff would facilitate development of
the said land and would also provide electricity and drainage
installations. It was also agreed that while conveying 65.64 decimals of
land, the plaintiff would also permit usage of company passage of the
defendant No.1 to enable him to ingress and egress to and from the said
65.640 decimals of land. On the basis of the said oral agreement, the
defendant No.1 executed five several deeds of conveyances in favour of
the plaintiff company totaling to 2.2543 acres of land consisting of both
his undivided share as well as his exclusive area including his
proportionate right in the common passage. Meanwhile, defendant
Nos.6 to 32 also executed several conveyances on various dates in
respect of both divided and undivided portion of the property including
the undivided share of common passage in favour of the plaintiff. The
plaintiff also discharged his reciprocal obligations by executing and
registering a deed of conveyance for 65.640 decimals of land in favour
of defendant No.1 on 1
st
November, 2015.
3. The further plaint case is that despite the plaintiff discharging its
reciprocal obligation, the defendant No.1 delayed discharging his
4
reciprocal obligation in terms of the said agreement as also execution of
registration of the conveyance in respect of 151.46 decimals of land on
several pretexts. The plaintiff called upon the defendant No.1 to transfer
the said plot of land as agreed upon to be transferred in favour of the
plaintiff by a letter dated 23
rd
September,2016 and subsequently, by
reminders dated 15
th
February,2017 and 2
nd
November,2017. The plaint
case further states that the plaintiff has started construction of setting up
the industrial park upon obtaining permission from various authorities
and due to non-performance of his part of the agreement by the
defendant No.1 the plaintiff is suffering as the project of setting up the
industrial park is not being completed. The plaintiff prayed for a decree
for specific performance for transfer of suit property with a direction
upon the defendant No.1 to register and execute the sale deed in favour
of the plaint upon acceptance of the agreed consideration of
Rs.3,36,88,544/- within time limit to be specified by the learned trial
court, in the alternative for a prayer of decree for damages of Rs.127
crore, enquiry in terms of order 20 Rule 12 of the Civil Procedure Code,
decree for permanent injunction restraining defendant No.1 from
changing the nature and character of the suit property till disposal of the
suit and restraining them from restricting free ingress and egress of the
plaintiff from the common entrance and National Highway 6 to the suit
property as also to the plots of land owned by the plaintiff along with
the ancillary reliefs.
4. The plaintiff/appellant also filed an application under Order 39 Rules 1
and 2 read with Section 151 of the Code of Civil Procedure before the
learned trial court praying for an order of injunction restraining the
5
defendant Nos.1 and 2 and their men, agents or servants from changing
the nature and character of the suit property making any construction
thereon and restricting free ingress and egress of the plaintiff from the
common entrance of National Highway 6 of the suit property as also the
plots of land owned by the plaintiff, restraining the defendant Nos.1and
2 and their men, agents and servants from creating any nuisance on the
common passage regarding the suit property and the plots of all lands to
the plaintiff and from parking vehicles on such passage and not creating
any obstruction in any manner whatsoever on the common passage
leading to the suit property and all the plots of land of the plaintiff,
restraining the defendant Nos.1 and 2 from alienating, transferring,
encumbering and/or creating any third party right in respect of the suit
property and ad-interim prayers in terms thereof.
5. Defendant No.1 filed written objection against the application for
temporary injunction filed by the plaintiff. In the written objection, the
defendant No.1 denied the material allegations made by the plaintiff in
the said application. The defendant No.1 flatly denied that there was any
agreement dated 7
th
May,2013 by and between the plaintiff and the
defendant No.1 and the defendant No.1 further stated that he never
responded to the letters referred to by the plaintiff. According to
defendant No.1, the said letters were unilaterally written by the plaintiff.
The defendant No.1 clearly denied that he either agreed to sale the suit
property or entered into any oral agreement with the plaintiff regarding
the arrangements as mentioned in the plaint. The defendant No.2 filed a
separate written objection and the plaintiff filed rejoinder to both the
written objections before the learned trial court. Upon hearing, the
6
Learned Trial Court rejected the temporary injunction application on
contest. Hence, the instant appeal.
6. Learned senior counsel appearing for the plaintiff/appellant referred to
the arrangements and/or reciprocal obligations allegedly entered into by
the plaintiff and the defendant No.1. By virtue of the oral agreement
dated 7
th
May,2013 and narrating the complaint and on consideration of
the fact regarding the setting up of the industrial park by the plaintiff, it
was submitted that the schedule of the plaint very well included the plot
numbers as well as the easement and quasi easement rights together
with all rights, liberties, privileges along with right to free ingress and
egress. It was submitted that the plaintiff, at all material times, has been
ready and willing to perform the obligation and/or reciprocal obligation
being part of the oral agreement dated 7
th
May,2013 entered into
between the plaintiff and defendant No.1. It was further submitted that
the plaintiff filed the suit when no commercial construction was there in
the plots of land. Referring to Annexure B of the list of documents
annexed to the plaint being the sketch map, the learned senior counsel
pointed out that save and except a portion of land being the subject
matter of the present suit, the rest of the entire area has been purchased
by the plaintiff and the construction work for setting up the industrial
part is continuing. The learned senior counsel for the plaintiff/appellant
further referred to the deed of conveyance dated 5
th
November,2015
executed between the defendant No.1 and the plaintiff wherein it was
recorded in the recital of the said deed that the entire common passage
originating from the public road ending with the vendor’s land, i.e., the
land belonging to the defendant No.1 shall be developed at the cost of
7
the second party i.e., the plaintiff. The first party is not under any
obligation to pay any charges or fees for such development and/or
improvement of common road meant for usage of both the parties. The
first party purchaser will cooperate with the second party in all respect
and at the time of development of land belonging to the plaintiff
personally or through the authorized representatives or agents. The
learned senior counsel further referred to the condition recorded in the
said deed to the effect that the purchaser above named i.e., the plaintiff,
declared and confirmed that the vendor i.e., the defendant No.1 has sold
“the said plot of land” in favour of the purchaser. By this deed the
vendor herein shall have the first option to purchase at the highest
market price and/or acquire the same. Referring to the said condition,
the learned senior counsel submitted that the conditions mentioned in
the said deed of conveyance clearly show that there was an oral
agreement entered into by and between the plaintiff and the
defendant No.1. The learned senior counsel then referred to the letter
23
rd
September,2016 being Annexure F to the plaint. The said letter was
written by the plaintiff to the defendant No.1 by which it was recorded
that the defendant No.1 had agreed to sale his other property situated at
Mouza Bippanapara, JL No.27 and Mouza Mohiary, JL No. 28 P.S
Domjur, District Howrah to the plaintiff. The said letter further recorded
that in part performance of the agreement, the defendant No.1
transferred and conveyed in favour of the plaintiff, land measuring
about 170.907 decimals being undivided 1/7
th
share in the joint property
as stated in the said letter. Thereafter, on 1
st
November, 2015, the
defendant No.1 transferred and conveyed a part or portion of the
divided and demarcated portion of land together with 1/7
th
undivided
8
share in the common passage alone together measuring about 65.640
decimals at Mauja Mohari, JL No.28 and 8.11 decimals in Mauja
Bipannapara, JL No. 27 leaving a balance of 156.229 decimals. It was
observed by the defendant No.1 that the remaining portions of land
measuring 150.229 decimals shall be transferred and conveyed as soon
as the sale and transfer of land by other co-owners who has also agreed
to sale their rest undivided share in the said land as well as their divided
and demarcated plots together with each of their undivided share that
the common passage is completed. In the said letter it was requested
that the defendant may consider that the plaintiff has acquired right, title
and interest of co-owner in order to complete the process and further
considering the situation that the plaintiff has already invested a large
sum of money, the defendant was requested to transfer remaining
150.229 Decimals of plot of land in favour of the plaintiff.
Subsequently, the reminders dated 15
th
February,2017 and
2
nd
November, 2017 were also sent to the defendant No.1 by the
plaintiff.
7. Learned senior counsel for the plaintiff/appellant further referred to the
development agreement dated 12
th
July,2016 between the plaintiff and
the defendant No.4 i.e., the developer who developed the industrial
park. Referring to Article 10 Clause 9.1 of the said development
agreement, the learned senior counsel argued that the entire project
is scheduled to be completed in phases.
8. Learned senior counsel for the plaintiff/appellant further referred to the
application for injunction. The learned senior counsel referred to
9
paragraph 29 of the application for temporary injunction wherein the
performance of bhumi puja on the suit property of defendant Nos.1and
2 for the purpose of starting construction in the property has been
shown as the cause of urgency. The learned senior counsel further
referred to the prayers of the application for injunction and submitted
that at that time there was no construction in the suit property.
9. The learned senior counsel for the plaintiff/appellant then referred to the
written objection to the application for injunction by the
defendant No.11. Referring to paragraphs 9, 11 and the written
objection and the letter addressed to Block Land and Land Reforms
Officer,Domjur,Howrah jointly by the plaintiff and the defendant No.1
on 15
th
November,2017, the learned senior counsel for the
plaintiff/appellant argued that the oral agreement or the acceptance of
terms and conditions thereof have not been denied by the
defendant No.1 and as it appears from the conduct of the
defendant No.1, the specific response to the letters written to the
defendant No.1 by the plaintiff seeking specific performance of the oral
agreement was not required.
10. Learned senior counsel for the plaintiff/appellant next referred to
the judgment and order impugned in the present appeal and submitted
that the recording of the learned trial judge that the plaintiff is willing to
purchase a piece of land measuring 151.46 decimals which is referred to
as suit property is not correct factually because easementary rights
which were very much part of the schedule of the plaint, was not
included such recording. It would further appear from the recording of
10
the trial judge that the common passage referred to in the schedule and
shown in Annexure B is not the suit property but the reference to the
boundary of the suit property only is factually wrong and as such, the
learned trial judge committed a material irregularity. Therefore, the
recording of the learned trial judge with regard to the common
passage not being part and parcel of the suit property is absolutely
wrong which led to the decision under challenge. Referring to the
findings of the learned trial judge with regard to the applicability of
Section 10 of the Indian Contract Act, 1872 with regard to the oral
agreement, the understanding of the provision as well as the ratio laid
down in the cited decision reported in the case of Aloka Bose Vs.
Parmatma Devi & Ors. (2009) 2 SCC 582 by the plaintiff, the learned
trial judge fell in error as he misconstrued both the statutory provision
as well as the ratio laid down in the cited decision in the context of the
present case. The learned senior counsel further submitted that the
learned trial judge fell in further error because there was no whisper
with regard payment of stamp duty in respect of the oral agreement and
payment of stamp duty in case of oral agreement is patently
absurd. Therefore, the finding of the learned trial judge with regard to
the prima facie case is palpably misconceived and perverse.
11. Learned senior counsel submitted that the Learned Trial Judge further
fell in error in recording that the learned trial judge could not find any
documentary evidence in relation to the oral agreement. The learned
senior counsel for the plaintiff/appellant further submitted that only the
absence of date of oral agreement in the letter dated
23
rd
September,2016 and subsequent reminders thereof
11
cannot brush aside the existence of oral agreement which is otherwise
clear from the conduct of the parties. He further submitted that the
question raised with regard to the inclusion of defendant No.1 in the
same drive at the instance of the proforma defendant No.5 was not
argued by the parties at all. He further submitted that the learned trial
judge recorded that in the letter dated 23
rd
September,2016 it was
mentioned the oral agreement was referred to but the date, place and
occasion of such agreement was disbelieved by the learned trial judge.
Therefore, the parties agreed and contracted on the basis of oral
agreement was not considered by the learned trial court.
12. With regard to the written objection of defendant No.2, i.e., the
developer, the learned senior counsel for the plaintiff/appellant referred
to the written objection of defendant No.2 and submitted that the
construction made by the defendant No.2 upon getting physical
possession of the property from defendant No.1 and upon execution of
the unregistered development agreement on 1
st
December,2015 between
the defendant nos.1 and 2 are versions of the defendant No.2 which has
no bearing in respect of the conduct of the plaintiff and the
defendant No.1 in connection with the oral agreement. He further
referred to the order dated 7
th
April,2026 passed by this Hon’ble Court
in the present appeal by which this Court restrained the
defendants/respondent Nos.1and 2 and their men and agents by an order
of injunction from making any construction on the common passage as
described in paragraph No.3 of the plaint leading to the suit
property from that date till disposal of the injunction application filed in
the present appeal. He further submitted that this Court was satisfied
12
that there was prima facie case made out by the plaintiff/appellant in the
present case.
13. As such, the learned senior counsel for the plaintiff appellant prayed for
setting aside of the judgment and order impugned and further prayed for
allowing the appeal by restraining the defendant Nos.1 and 2 from
creating any further disturbances in the suit property till the disposal of
the suit.
14. Per contra, the learned counsel for the Defendant/respondent No.1
submitted that while seeking injunction, a case has to be strongly based
on existence of facts and not on presumptions. Referring to paragraph 4
of the plaint, the learned counsel for the defendant/respondent No.1
submitted that the purchase of plot of land from Pal family took place
on or about 25
th
February,2013 whereas the oral agreement has
purportedly and/or allegedly being entered into on May 7,2013. The
learned counsel for the defendant/respondent No.1 submitted that the
case of oral agreement has been made out in such a manner that the
same is brought within the contours of deeds or instruments executed
between the parties. He further submitted that the question of
concessional price as recorded in the recitals of the deed came up
because the defendant No.1 was the middleman in respect of the
execution of the deeds of conveyance amongst the parties. He further
referred to the deed of conveyance dated November 1,2015 executed by
the defendant No.1 as vendor in favour of the plaintiff as the purchaser
and submitted that there is no reference to the oral agreement as being
stated in the plaint. He further referred to the valuation made in respect
13
of the said deed and submitted that market value of the property had
been almost the same as accessed by the Directorate of Registration and
Stamp Revenue and the amount mentioned in the memo of
consideration. As such, there is no question of any concessional price as
sought to be made in the plaint case.
15. Learned Counsel appearing for Defendant No.1/Respondent No.1
submitted that in case of oral agreement, strongest possible case with
regard to the existence of oral agreement is required to be made out. In
this regard the Learned counsel places reliance on paragraph 4 of the
plaint and submitted that oral agreement is dependent on reciprocal
obligations. However, no such indication appears from the deeds of
conveyances referred to in the plaint forming the case of oral agreement.
The Learned Counsel placed the Deed of Conveyances dated November
1,2015 by which the defendant/respondent No.1 purchased the piece and
parcel of land measuring about 65.64 decimals in different Dag numbers
within Mouza Bipannapara JL No.27. The Learned Counsel further
placed the memo of consideration of the said deed of conveyances and
pointing out the consideration amount of Rs1.24 crore, he submitted that
the said price was not concessional price. He further submitted that the
price written in the memo of consideration is Rs.1.24 crore and the
government valuation is Rs.1,24,88,667/- . Thus, difference is not much
and the transaction took place on the basis of market value only. He
further pointed out the recital of the deed of conveyances wherein it is
recorded “that in the premises aforesaid and in pursuance of the said
agreement and in consideration of a sum of Rs.1,24,00,000/- only duly
paid to the vendor by the purchaser on this date of execution of this
14
deed”. It was submitted that the term “said agreement” is not oral
agreement and there has to be an agreement in writing before that deed is
executed. The learned counsel for the defendant/respondent No.1 then
placed another deed dated November 1, 2015, i.e., on the same date
where the defendant/respondent No.1 as vendor transferred the piece and
parcel of land at Mouza Mohiary, both demarcated and undemarcated,
measuring about 65.64 decimals for a consideration of Rupees 1.46
crores. Referring to the said deed of conveyance, the learned Counsel
submitted that the transaction took place on the basis of an independent
proposal upon verification of the market value. There is no oral
agreement connected to the said deed of conveyance and there is no
concessional price and the transaction took place on the basis of agreed
price based on market value.
16. Referring to the deed of conveyance dated 25
th
April 2014, wherein the
defendant /respondent No.1 being the vendor transferred in favour of the
plaintiff /appellant the piece and parcel of land measuring about 62.787
decimals in Mouza Bipannapara for a valuable consideration
of Rs.75,97,200/- , the learned Counsel referred to the recital of the said
deed wherein it was recorded that due to urgency of money the vendor
has agreed to sell the said property.Basis the same, the learned counsel
for the defendant/respondent No.1 argued that the said transaction took
place due to want of money and the same was not in pursuance of an
oral agreement.
17. The learned counsel next referred to the letters and communications from
the record. Placing reliance on letter dated 23
rd
September 2016 written
15
by the plaintiff/ appellant to the defendant/respondent No.1, the Learned
Counsel for defendant/Respondent No.1 argued that the said letter was
written after 3 years from the date of purported oral agreement. In terms
of the purported oral agreement, the reciprocal obligations ended after
two years from the date of the said oral agreement and the letter dated
23
rd
September 2016 was communicated after a period of more than one
year from the date of cessation of reciprocal obligations under the
purported oral agreement. He further argued that in the plaint, there was
no reference to the deed dated 25
th
April 2014, although the same found
place in the later dated 23
rd
September 2016. He further argued that
although in the letter, a reference to altered position or altered agreement
has been mentioned but there is no prayer in the plaint with regard to
such altered position or altered agreement. He submitted that from the
contents and purport of the said letter, it appears that it was merely a
desire of the plaintiff/ appellant to purchase 150.229 decimals of land
with another 65.64 decimals of land aggregating to total 215.869
Decimals of land as was expressed in the said letter dated 23
rd
September
2016, but there was nor oral agreement between the parties to that effect.
The learned counsel for the defendant/respondent No.1 further argued
that non-reply to the said letter did not amount to acceptance or existence
of any concluded contract. Non-denial would not amount to agreeing to
the terms or contracting between the parties. He further submitted that
the contents of the said letter dated 23
rd
September,2016 does not contain
any reference to a deed or oral agreement but contains only a vague
reference to commitment. He further submitted that reminders to the said
letter dated 15
th
February 2017 and 2
nd
November 2017 also did not have
any reference to any oral agreement.
16
18. The Learned Counsel for the defendant/respondent No.1 then referred to
the agreement dated 12
th
July,2016 entered by and between the
plaintiff/appellant and the developers. Referring to clause 4.2 under the
heading “Parties and Object of this Agreement” of the said agreement
dated 12
th
July,2016, the Learned Counsel submitted that in the language
of the clause with regard to inclusion of lands in the industrial park, use
of the word ‘may’ clearly shows that the plaintiff/appellant was not sure
about acquisition and/or purchase of further land in respect of setting up
the industrial park and it was only intention of the plaintiff/ appellant
which would be derived from the said clause. Referring to clause 9.1
under the heading ‘construction and completion’ of the said agreement,
the Learned counsel further submitted that the clause clearly shows that
the setting up of the industrial park would be on the basis of phasewise
acquisition and/or purchase of land and such acquisition and/or purchase
would be independent deals based on considerations. Such acquisition
shows that there was no mention of any oral agreement.
19. The Learned Counsel for the defendant/ respondent No.1 then referred to
the letter dated 15
th
November,2017 jointly written by the plaintiff
/appellant and the defendant/respondent No.1 addressed to the Block
Land and Land Reforms Officer, Domjur Block, District Howrah by
which the parties made a clarification with regard to the mutation of
various plots of land. Referring to the contents of the said letter, the
learned counsel argued that both the parties sat together for the purpose
of mutation only and there was no other purpose mentioned in the said
17
letter with regard the said sitting. It further appears that the said sitting
took place in 2017 only.
20. The Learned counsel for defendant/respondent No.1 then referred to the
map wherefrom it would appear that the plot belongs to respondent
/defendant no.1 and gate also belongs to him. It is a matter of greed of
the plaintiff /appellant to grab the land and indulge the defendant
/respondent no.1 in litigation in order to bring him to the terms of the
plaintiff/ appellant.
21. With regard to the common passage, the learned counsel for defendant/
respondent No.1 next argued that it would be evident from the prayer (a)
of the injunction application that the suit property belongs to
defendant/respondent No.1 and he is in possession of the same. So, such
a prayer to have and/or secure access to defendant/ respondent No.1’s
property cannot be granted as prayer by the plaintiff/appellant. Such
prayer was nothing but a relief at the interim stage sought to be obtained
in circuitous manner which really amounts to final relief. He further
submitted that the passage is a common passage leading to the
construction gate and both the parties park their vehicles in the common
passage. There is nothing to show from the pleadings that the
defendant/respondent No.1 is creating nuisance by parking his
vehicles.
21. Referring to paragraph 14 of the plaint, the learned Counsel for the
defendant/respondent No.1 next submitted that statement regarding the
agreement between the parties on 3
rd
August 2017 to the effect that the
18
defendant would complete the full performance of the contract within a
period of two years, is a unilateral statement made in the plaint and that
is nothing more than intention of the parties,but there was no oral
agreement to that effect. He further submitted that although such
purported agreement has been mentioned in the plaint, there was no
reference to that agreement dated 3
rd
August 2017 in the reminder letter
dated 2
nd
November 2017. He further submitted that as there was no
agreement, the statement with regard to reciprocal obligations as made in
paragraph 16 of the plaint does not and cannot arise.
22. He further submitted although there is a statement with regard to
novation of the contract and/or a new contract dated 3
rd
August 2017 in
paragraph 27 of the plaint, such case has not been pleaded anywhere in
the plaint.
23. With regard to the cause of action of the plaint, the learned counsel for
the defendant/respondent No.1 submitted that paragraph 29 of the plaint
discloses the cause of action wherein it has been mentioned that on
23
rd
September,2016 the defendant No.1 refused to convey the suit
property in favour of the plaintiff as per the purported oral agreement
and subsequently changed agreement dated 3
rd
August 2017. Such
statement is ex-facie absurd because if the defendant /respondent No.1
has refused to transfer the land in favour of the plaintiff on
23
rd
September,2016, there would not have been any question of
reminders subsequent thereto as mentioned in the said paragraph 29 of
the plaint. He further submitted that none of the letters dated
23
rd
September 2016, 15
th
February 2017 and 2
nd
November,2017 record
19
any refusal on the part of the defendant/respondent No.1. Therefore, the
statement of the plaint and content of the letters are different. In the
circumstances, the presumption of non- response as sought to be raised
by the plaintiff’s appellant is immaterial.
24. The learned counsel for the defendant/respondent No.1 then submitted
that the industrial park sought to be set up by the plaintiff/appellant is a
commercial project. In a commercial venture, waiting for a period of
about three years to seek relief is fatal and such delay defeats equity
since the execution of the deeds of conveyances took place in November
2015 and the plaintiff/ appellant waited till April 2019 to file the
suit.There is nothing to show from record that between such period, the
plaintiff/appellant approached the defendant No.1 with regard to the
subject matter.
25. The defendant /respondent No.1 then referred to the prayers of the plaint,
esp., prayer (b) of the plaint and submitted that such prayer has been
made with regard to specific performance for transfer of suit property
and such specific performance is based on the oral agreement according
to the plaintiff but the said prayer does not have any reference to the oral
agreement. Lastly, he submitted that no mutuality between the parties
could be shown from the deed of conveyance as sought to be argued by
the plaintiff/ appellant.
26. The learned counsel for the defendant/ respondent No.1 submitted that
the matter is with regard to a commercial project and as such, the suit
ought to have been filed in Commercial Court and the ordinary civil
20
court could not have entertained the suit having lack of inherent
jurisdiction.
27. In support of his submission, learned counsel for the defendant/
respondent No.1 placed reliance on a decision of the Hon’ble Supreme
Court of India in the case of Brij Mohan & Ors. Vs. Sugar Begum &
Ors.(1990)4 SCC 147. Referring to para 2 of the said report, it was
pointed out that the said case was with regard to oral contract and further
referring to paragraph 16 of the said report, it was pointed out that in that
case, although it was found that there was a meeting between parties but
that does not establish that there was a concluded contract between the
parties on that day because admittedly defendant No.1 was not present at
that point of time. Referring to paragraph 20 of the said report, it was
submitted that in case where the plaintiff is seeking decree of specific
performance of contract of sale of immovable property on the basis of
oral agreement alone, heavy burden lies on the plaintiff to prove that
there was consensus ad idem between the parties for a concluded oral
agreement for sale of immovable property. Whether there was such
concluded oral agreement would be a question of fact to determine in the
facts and circumstances of each individual case. It has to be established
by the plaintiff that vital and fundamental terms of sale of immovable
property were concluded between the parties. A written agreement, if
any, to be executed subsequently would be a fundamental agreement
incorporating such terms which had already been settled and concluded
in the oral agreement.
21
28. The learned counsel for the defendant/ respondent No.1 then relied upon
a decision of the Hon’ble Supreme Court of India in the case of Shivaji
Yallappa Patil Vs.Ranajeet Appasaheb Patil & Ors. (2018)16 SCC
725.Relying on paragraph 16 of the said report, the learned counsel for
defendant /respondent No.1 argued that since the plaintiff pleaded part
performance of the contract, such pleading attracts section 53A of the
Transfer of Property Act,1882 and in case of suit for specific
performance of contract based on part performance, the essential
ingredients and sine qua non for making out a claim under section 53A
of the Transfer of Property Act,1882 have been recorded in the said
paragraph of the said report. From the conditions sine qua non for
claiming part performance, the conditions laid down in the said report
have not been specified by the plaintiff/appellant.Although the plaintiff
pleaded part performance in the plaint, the conditions including the
written agreement as laid down in the said decision as sine qua non is
absent.
29. The learned counsel for the defendant/respondent No.1 then placed
reliance on a decision of the Hon’ble Supreme Court in the case of
Ambalal Sarabhai Enterprises Ltd. Vs.KS Infraspace LLP Ltd.& Anr.
(2020)5 SCC 410 and relying on paragraphs 5,7,15,17 and 21 of the said
report, the learned counsel argued that in commercial dealings with high
stake matters, delay is vital which took place in the instant case also. To
seek a temporary injunction in a suit for specific performance a strong
prima facie case on the basis of undisputed facts are required to be made
out which is also absent in the instant case. There was no mutuality
between the parties much less that they were ad idem as in the present
22
case and the existence of concluded contract between the parties is a
matter of trial, in the instant case, is required to be borne into at the time
of trial. In the cited decision, there were correspondences which formed
the contract whereas in the case at hand, only a letter recording reference
to oral agreement without any acceptance has been pleaded as document
towards oral agreement.
30. The learned counsel for the defendant/respondent No.1 then relied upon
a division bench decision of this court reported in the case of Ramen Roy
Vs.Samriddhi Real Estate Pvt. Ltd. & Ors. 2026 SCC Online Cal 7528
And relying on paragraph 53 of the said report, the learned counsel for
the defendant/ respondent No.1 argued that in case of commercial
matters, the ordinary civil court lack jurisdiction with regard to subject
matter and due to inherent lack of jurisdiction, the ordinary civil court
cannot take up the matter. In the instant case, the matter being
commercial in nature, the learned court being the ordinary civil court
could not have entertained the suit at all.
31. In reply, the learned senior counsel for the plaintiff/appellant referred to
para 29 of the injunction application and submitted that performance of
Bhumi Puja was shown as the cause of action and/or urgency to move
the application for injunction. Referring to the map appearing at page 89
of the IA/CAN 3 of 2021, the learned senior counsel submitted that it
would appear from the said map, that the plot of land belonging to the
defendant No.1 is landlocked. Only due to the transfer of land
measuring about 65.64 decimals in favour of defendant No.1 by the
plaintiff and in exchange, purchase of plot of same size of defendant
23
No.1 by the plaintiff, the land presently belonging to the defendant No.1
measuring about 151.96 decimals wherein the defendant No.1 has been
setting up a garment haat, would get access to the said plot. The
execution of the deeds on the same day shows mutuality between the
parties. From the said map,he further pointed out that ingress and egress
to and from NH 6 through a wide road and then leading to smaller road
on the left hand side gives access to the landlocked piece of land
belonging to defendant No.1 is the subject matter of suit and it is not the
narrow road only, as sought to be pointed out by the
defendant/respondent No.1. Referring to page 63 of IA/CAN 3 of 2021,
the learned senior counsel for the plaintiff/ appellant pointed out that the
deeds were executed as a matter of exchange so that the defendant No.1
can have access to his 151.96 decimals of landlocked plot wherein he has
been constructing the haat although construction of such hut is not on
record. However, at this juncture, it was pointed out that in the affidavit-
of-opposition to IA/CAN 3 of 2021, the defendant/respondent No.1 has
pleaded that construction of the haat is complete and the same is in
operation.
32. Referring to the deeds both dated 1
st
November 2015, the learned senior
counsel for the plaintiff /appellant then submitted that in the deed where
the defendant no.1 is vendor it is recorded that on the basis of ‘agreed
terms’ the deed has been executed whereas in the deed where the
plaintiff is vendor it is recorded that it is on the basis of “highest
available market price”. The learned senior counsel for the
plaintiff/appellant submitted that it is pertinent to note that in both the
24
deeds, the size of land had been the the same and the exchange of land
was made on the same date.
33. Referring to paragraphs 4(iv),(v) and (vi) of the plaint, the learned senior
counsel submitted that it was “agreed between the parties” as pleaded in
the plaint. He further referred to paragraph 14 of the plaint where it was
also mentioned that the parties ‘agreed’ with regard to completion of full
performance of the contract. He further submitted that for the plot of
land measuring about 65.64 decimals of land, another suit is pending
between the parties and an appeal arising out of injunction matter is also
pending. He further submitted that there was no novation of contract as
sought to be pleaded by defendant/respondent No.1 but all the deeds
were to be executed together as per the agreed terms.It is further
submitted that the development agreement was executed with a third
party and there was no requirement of mentioning of any oral agreement
and it was kept open.
34. Distinguishing the judgments as cited by the learned counsel for the
defendant/respondent No.1, the learned counsel for the plaintiff/appellant
submitted that in Brij Mohan(Supra), the facts and circumstances of the
case was different as the matter was decided after a complete trial which
is not the case at hand as the matter arises out of the order passed at the
stage of grant of injunction. With regard to Shivaji Yallappa
Patil(Supra), the condition laid down by the Hon’ble Supreme Court
included element of possession which is absent in the present case, and
as such, Section 53A of 1882 Act cannot come into play in the instant
case. With regard to Ambalal Sarabhai(Supra), he submitted that the case
25
is factually different from the present one and exchange of emails were
considered to be the contract which is not the case at present. The said
case was also decided after a complete trial which is not the case at
present. With regard to Ramen Roy(Supra), the learned senior counsel
for the plaintiff /appellant submitted that the present suit is not a
commercial suit and it is with regard to specific performance for
purchase of ‘Sali’ land. The deeds do not refer to any industrial park. It
is also not related to any development agreement and the suit is for
decree of specific performance simpliciter. Therefore,the ratio of the said
decision is not applicable in the present case.
35. In the circumstances, the learned senior counsel for the
plaintiff/appellant prayed for setting aside of the judgment and order in
impugned and prayed for allowing the appeal by passing appropriate
order granting ingress and egress to and from the said property by the
plaintiff/appellant. The learned counsel for the defendant/respondent
No.1 submitted that the order impugned passed by the Learned Trial
Judge was justified and he prayed for dismissal of the instant appeal.
36. Heard the learned counsel for the respective parties at length and
considered the materials on record. The preliminary question comes to
fore for decision is that whether the suit was a commercial suit or not. In
case it is found that the suit is not a commercial suit, then comes the next
question as to whether the Learned Trial Judge was justified in refusing
injunction in favour of the plaintiff/appellant as prayed for.
26
37. In this context, it is profitable to refer to Section 2(c) of the Commercial
Court Act,2015. The said statutory provision defined “commercial
dispute” which are as follows:
“(c) “commercial dispute” means a dispute arising out of—
(i) ordinary transactions of merchants, bankers, financiers and traders
such as those relating to mercantile documents, including enforcement
and interpretation of such documents;
(ii) export or import of merchandise or services;
(iii) issues relating to admiralty and maritime law;
(iv) transactions relating to aircraft, aircraft engines, aircraft equipment
and helicopters, including sales, leasing and financing of the same;
(v) carriage of goods;
(vi) construction and infrastructure contracts, including tenders;
(vii) agreements relating to immovable property used exclusively in trade
or commerce;
(viii) franchising agreements;
(ix) distribution and licensing agreements;
(x) management and consultancy agreements;
(xi) joint venture agreements;
(xii) shareholders agreements;
(xiii) subscription and investment agreements pertaining to the services
industry including outsourcing services and financial services;
(xiv) mercantile agency and mercantile usage;
27
(xv) partnership agreements;
(xvi) technology development agreements;
(xvii) intellectual property rights relating to registered and unregistered
trademarks, copyright, patent, design, domain names, geographical
indications and semiconductor integrated circuits;
(xviii) agreements for sale of goods or provision of services;
(xix) exploitation of oil and gas reserves or other natural resources
including electromagnetic spectrum;
(xx) insurance and re-insurance;
(xxi) contracts of agency relating to any of the above; and
(xxii) such other commercial disputes as may be notified by the Central
Government.
Explanation.—A commercial dispute shall not cease to be a
commercial dispute merely because—
(a) it also involves action for recovery of immovable property or for
realisation of monies out of immovable property given as security or
involves any other relief pertaining to immovable property;
(b) one of the contracting parties is the State or any of its agencies or
instrumentalities, or a private body carrying out public functions;”
The prayers of the plaint read as follows:
(a) Leave under Order II Rule 2 of the Code of Civil Procedure,
1908;
28
(b) Decree for specific performance for transfer of the suit
property as described in the Schedule hereunder with a direction
to the defendant No.1 to execute and register the sale deed in
favour of the plaintiff on accepting the agreed consideration being
a sum of Rs.3,36,88,544/-;
(c ) A Decree directing the defendant No.1 to execute and register
the sale deed in respect of the suit property within a time as to this
Learned Court may deem fit and proper, failing which the sale
deed be executed and registered according to the provisions of
Order XXIX Rule 34(5) and Rule 6(a) of the Code of Civil
Procedure, 1908;
(d) Alternatively, a decree for damages for Rs.127 crores as
pleaded in paragraph 20 hereof;
(e ) In the further alternative, an enquiry be caused in terms of
Order XX Rule 12 of the Code of Civil Procedure, 1908 to
ascertain the actual amount of damages sustained by the plaintiff
and a decree be passed accordingly;
(f) A decree for permanent injunction restraining the defendant
No.1 from changing the nature and character of the suit property
till the disposal of the instant suit;
29
(g) A Decree of permanent injunction restraining the defendant
No.1 and 2 and/or their men, agents or servants from changing
the nature and character of the suit property, making any
construction thereon and restricting free ingress and egress of the
plaintiff from the common entrance on National Highway-6 to the
suit property as also the plots of land owned by the plaintiff;
(h) A Decree of permanent injunction restraining the defendant
No.1 and 2 and/or their men, agents or servants from creating any
nuisance on the common passage leading to the suit property and
the plots of land of the plaintiff and from parking vehicles on such
passage and creating any obstruction in any manner whatsoever
on the common passage leading to the suit property and the plots
of land of the plaintiff;
(i) A decree for permanent injunction restraining the defendant
nos.1 and 2 from alienating, transferring, encumbering and/or
creating third party rights in respect of the suit property;
(j) Receiver;
(k) Injunction;
(l)(1) Attachment;
(m) Costs;
30
(n) Further and other reliefs;
On a conjoint reading of the aforesaid provision and the
prayers of the plaint, it appears that the plaint and the injunction
application do not fulfil any of the conditions laid down in the
aforesaid definitions contained in Section 2(c)of the Commercial
Courts Act,2015. On a careful reading of the plaint and the
injunction application, it further appears that the plaint contains
prayers relating to decree for specific performance to transfer the
suit property described in the schedule alongwith ancillary reliefs.
The case of the plaintiff further disclosed that the development
agreement has been entered by and between the plaintiff with a
third party, a developer, to develop the property purchased by the
plaintiff and the same is not related to the defendant No.1. Thus, at
the relevant juncture, the subject property of the agreement in
question was not used exclusively in trade or commerce.
Therefore, the suit is not a commercial suit and a suit for specific
performance to transfer the suit property.
38. As such, the present suit is very well maintainable in the ordinary Civil
Court and not before the Commercial Court. As such, the ratio decidendi
of Ramen Roy(Supra) would not be applicable in the facts of the present
case.
39. Since the suit is not a commercial suit and is maintainable in ordinary
civil court, now the second question is required to be gone into whether
the Learned Trial Judge was justified in refusing to grant injunction ion
favour of the plaintiff.
31
40. On a careful reading of the judgment and order impugned dated October
3,2019 passed by the Learned Trial Judge it appears that the Learned
Trial Judge recorded that it is undisputed that the plaintiff is willing to
purchase the suit property and further, the defendant had orally agreed to
sell the said property. Learned Trial Judge further recorded that the suit
property is in possession of the defendant No.1. However, Learned Trial
Judge further recorded that the common passage is not the suit property.
Learned Trial Judge recorded the finding that he did not find any
payment of stamp duty. The Learned Trial Judge further recorded that he
did not find any documentary evidence regarding existence of oral
agreement. The Learned Trial Judge further recorded that he found no
date or place of oral agreement in the letter dated September 23,2016.
The Learned Trial Judge raised question as to why the developer did not
include the defendant No.1 in the development agreement. The Learned
Trial Judge further found that since the plaintiff has prayed for
alternative relief of compensation or damages of Rs.127 Crore, the
plaintiff is not entitled to get an order of injunction as prayed for.
Therefore, the Learned Trial Judge held that none of the three conditions
for grant of injunction, viz., (i)Prima facie case; (ii) Balance of
convenience; and(iii) irreparable loss and injury are in favour of the
plaintiff are in favour of the plaintiff and rejected the payer for
temporary injunction on contest.
41. It is apparent from the text of the judgment and order impugned that the
Learned Trial Judge found that the case of the plaintiff is that the
plaintiff is willing to purchase the suit property and further, the
32
defendant had orally agreed to sell the said property. In such a case, the
plaintiff had very well made out a prima facie case to go for trial and was
very well entitled to an order of injunction. From the conduct of the
parties, as evident from the deeds of conveyances executed between
them, it is clear that the parties were at consensus ad idem regarding the
transfer of plots of land by way of exchange.
42. The findings of the Learned Trial Judge regarding the common passage
being outside the suit property is contrary to the material on record in as
much as the same is, as being evident from the plaint and the schedule
appended to it, within the schedule of property in suit.
43. Further, the finding of the Learned Trial Judge regarding applicability of
the Stamp Act in case of oral agreement is patently absurd and beyond
comprehension of a person of ordinary prudence. We fail to understand
how an oral agreement could be stamped and in what manner. It was also
nobody’s case that the developer should include the defendant No.1 in
the development agreement. The existence of the oral agreement has
been disbelieved merely because there is no date and place mentioned
regarding the same in the letter dated September 23,2016 although such
question requires trial on evidence. The deeds of conveyances
constituted a triable issue for the purpose of grant of injunction and there
was no contemporaneous objection to the letters of the plaintiff by the
defendant No.1.The Learned Trial Judge could not appreciate the real
meaning and purpose of Section 10 of the Indian Contract Act,1872 and
the judgment of Aloka Bose(Supra) in its true perspective. Oral
agreement is not barred under Section 10 of the Indian Contract
33
Act,1872 and the suit for specific performance in respect of oral
agreement is not barred. Existence of oral agreement is apparent from
the conduct of the parties as has been found by the Learned Trial Judge
himself in the judgment and order impugned.
44. Lastly, the finding of the Learned Trial Judge regarding the alternative
prayer for damages for refusing the prayer for temporary injunction is
misdirected, perverse and contrary to law. An alternative prayer cannot
be a bar to seek temporary injunction.
45. We respectfully agree with the ratio decidendi of the decisions cited
before us. However, the decision in Brij Mohan(Supra) was delivered
after a complete trial and such is not the case here as it was at the stage
of temporary injunction. Therefore, the said decision is distinguishable in
the fact situation. In the decision of Shivaji Yallappa Patil(Supra), the
conditions sine qua non for part performance included the element of
possession which is not the case here and as such, the same differs on
facts. The case of Ambala Sarabhai if factually different as in the said
cited decision, exchange of emails were considered as concluded
contract and the same is not the case at hand. Lastly, the case of Ramen
Roy(Supra) would not be applicable in the present case as the present
case is maintainable before the ordinary civil court and it is not a
commercial suit, as we have already held in the earlier paragraphs of this
judgment.
46. We find that by order dated April 7,2026, a coordinate Bench presided
over by one of us (Sabyasachi Bhattacharyya,J.) considered the matter is
34
detail and admitted the appeal. By the said order, the respondents No.1
and 2 and/or their men and agents were restrained by an order of
injunction from making any construction on the common passage as
described in paragraph 3 of the plaint leading to the subject property
from tat date till the disposal of the present appeal. The respondents No.1
and 2 and/or their men and agents were also restrained from creating any
hindrance to the ingress and egress of the plaintiff/appellant in respect of
the suit property over the common passage till disposal of the injunction
application.
47. In the circumstances and in the light of the discussions made above, the
appeal being FMA 916 of 2019 is allowed on contest, thereby setting
aside the judgment and order impugned dated October 3,2019 passed by
Learned Civil Judge (Senior Division)1
st
Court, Howrah. The
Defendants/respondents No.1 and 2 are hereby restrained from changing
the nature and character of the suit property and making any further
construction thereon and from alienating, transferring, encumbering
and/or creating any third party interest in the suit property and from
restricting free ingress and egress through the common passage from
National Highway 6 to the suit property as also the plots of land owned
by the plaintiff and from creating any nuisance and /or obstruction and
/or parking vehicles on the common passage leading to the suit property
till the disposal of the suit.
48. The interim order granted on April 7,2026 is confirmed and modified to
the extent as indicated above.
35
49. Since the suit is of 2019, we request the learned Trial Court to hear and
dispose of the suit expeditiously, preferably within a period of one year
from the date of this judgment without granting unnecessary
adjournment to any of the parties.
50. CAN 2 of 2020, CAN 3 of 2021 and CAN 4 of 2026 are, accordingly,
disposed of.
51. No order as to costs.
52. Urgent Photostat certified copy of this order/judgment if applied for, be
supplied to the parties upon compliance with all requisite formalities.
I Agree. (SANDIP KUMAR DE, J.)
(SABYASACHI BHATTACHARYYA, J.)
Legal Notes
Add a Note....