consumer law, real estate
 10 Sep, 2025
Listen in 2:02 mins | Read in mins
EN
HI

Ambika Realcon Pvt. Ltd. Vs. National Consumer Disputes Redressal Commission And Others

  Punjab & Haryana High Court CWP-26895-2025 (O&M)
Link copied!

Case Background

As per case facts, the petitioner-company, Ambika Realcon Pvt. Ltd., significantly delayed handing over possession of units to the respondents, even after sale deeds were executed. The respondents sought and ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

CWP-26869-2025 (O&M) and connected cases                            1                         

 

IN THE HIGH COURT OF PUNJAB & HARYANA AT 

CHANDIGARH   

  

112                                                                CWP-26869-2025 (O&M)  

 Date of decision: 10.09.2025  

    

 

Ambika Realcon Pvt. Ltd.                              ..... Petitioner  

 

VERSUS 

 

National Consumer Disputes Redressal Commission and others 

 

                             ..... Respondents 

 

113                                                                CWP-26889-2025 (O&M)  

 

 

M/s Ambika Realcon Pvt. Ltd.                            ..... Petitioner  

 

VERSUS 

 

National Consumer Disputes Redressal Commission and others 

  

                             ..... Respondents 

 

114                                                        CWP-26891-2025 (O&M)  

  

 

Ambika Realcon Pvt. Ltd.                              ..... Petitioner  

 

VERSUS 

 

National Consumer Disputes Redressal Commission and others 

 

                             ..... Respondents 

 

115                                                        CWP-26895-2025 (O&M)  

  

 

Ambika Realcon Pvt. Ltd.                              ..... Petitioner  

 

VERSUS 

 

National Consumer Disputes Redressal Commission and others 

 

                             ..... Respondents 

 

CWP-26869-2025 (O&M) and connected cases                            2                         

 

 

CORAM:   HON’BLE MR. JUSTICE GURVINDER SINGH GILL 

HON’BLE MR. JUSTICE DEEPINDER SINGH

 NALWA  

 

Present:   Mr. Munish Gupta, Advocate  

for the petitioner (in all petitions) 

 

***** 

 

DEEPINDER SINGH NALWA, J.

   

 

1.    All  the  present  writ  petitions  involve  common  question  of 

law based on common set of facts and therefore, are being disposed of by 

one and common judgment.    

2.    Challenge in the abovesaid writ petitions is to the impugned 

order  dated  20.03.2025  (Annexure  P-6)  passed  by  the  State  Consumer 

Disputes Redressal Commission, U.T Chandigarh (hereinafter referred to 

as the ‘SCDRC’) and order dated 10.06.2025 (Annexure P-8) passed by 

the  National  Consumer  Disputes  Redressal  Commission,  New  Delhi 

(hereinafter  referred  to  as  the  ‘NCDRC’),  whereby  respondents-

complainants were held entitled for compensation by way of interest @ 

9% per annum from the date of due date of possession onwards till the 

date of delivery of the possession on the entire received sale consideration 

in respect of the units in question along with lumpsum compensation to 

the  tune  of  Rs.75,000/-  on  account  of  mental  agony and  harassment, 

deficiency  in  providing  service  and  also  compensation  to  the  tune  of 

Rs.35,000/- on account of litigation cost.   

CWP-26869-2025 (O&M) and connected cases                            3                         

 

3.    Brief facts of the case are that respondents-complainants, in 

the  abovementioned  writ  petitions,  despite  the  fact  that  they  are  in 

possession  of  their  respective  units  and  sale  deeds  have  also  been 

executed between the parties, yet, the petitioner-company has failed to 

pay the compensation for the period of delay in delivery of possession of 

the said units.  The respondents-complainants had filed complaints before 

the SCDRC claiming compensation on account of delay in delivery of 

possession of the respective units by the petitioner-company.  The details 

of  date  of  possession,  execution  of  sale  deeds,  payments  made  by 

respondents-complainants,  due  date  of  possession  and  possession 

delivered, are reproduced in the chart below:- 

 

CC No.  Complaint 

No.60/2024 

(CWP-26891-

2025) 

Complaint 

No.62/2024 

(CWP-26889-

2025) 

Complaint 

No.63/2024  

(CWP-26869-

2025) 

Complaint 

No.64/2024 

(CWP-26895-

2025) 

Project  Florence  Park, 

New 

Chandigarh  

Florence  Park, 

New 

Chandigarh 

Florence  Park, 

New 

Chandigarh 

Florence  Park, 

New 

Chandigarh 

Unit No.  ORCHID/B/1

201 

ORCHID/B/30

ORCHID/B/30

ORCHID/B/12

04 

Area  of 

unit 

1400  sq.ft. 

carpet  area 

and  2080  sq. 

ft. super area 

1400  sq.ft. 

carpet  area  and 

2080  sq.  ft. 

super area 

1640  sq.ft. 

carpet  area  and 

2480  sq.  ft. 

super area 

1400  sq.ft. 

carpet area  and 

2080  sq.  ft. 

super area 

Total  cost 

as 

mentioned 

in 

agreement  

8154266.00  & 

7731943.20 

(after  credit 

note) 

8144928.00  & 

7723104.00 

(after  credit 

note) 

10487284.00  & 

9852160.00 

(after  credit 

note) 

8745984.00  & 

8216292.00 

(after  credit 

note) 

Amount 

paid  

Full  and  final 

payment  paid 

Full  and  final 

payment paid as 

Full  and  final 

payment paid as 

Full  and  final 

payment  paid 

CWP-26869-2025 (O&M) and connected cases                            4                         

 

as  admitted  in 

letter  dated 

29.06.2022, 

Annexure C-6 

admitted  in 

letter  dated 

16.09.2022, 

Annexure C-6 

admitted  in 

letter  dated 

22.07.2022, 

Annexure C-6 

as  admitted  in 

letter  dated 

20.08.2022, 

Annexure C-6 

Agreement 

dated 

13.04.2018 

(Ann. C-3) 

16.05.2018 

(Ann. C-3) 

29.01.2021 

(Ann. C-3) 

18.01.2021 

(Ann. C-3) 

Due  date 

of 

possession  

30.09.2020 

(Clause  7.1  of 

agreement) 

30.09.2020 

(Clause  7.1  of 

agreement) 

30.09.2021 

(Clause  7.1  of 

agreement) 

30.09.2021 

(Clause  7.1  of 

agreement) 

Possession 

delivered 

on 

30.06.2022  21.10.2022  24.07.2022  12.10.2022 

Sale  deed 

executed  

25.01.2023 

(Ann. R-1/6)  

Not  placed  on 

record  

Not  placed  on 

record  

29.09.2022 

(Ann. R-1/7) 

Delay  in 

delivery of 

possession  

21  months  as 

mentioned  in 

the complaint.  

18  months  as 

mentioned  in 

the complaint.  

10  months  as 

mentioned  in 

the complaint.  

13  months  as 

mentioned  in 

the complaint.  

 

4.    The petitioner-company duly filed separate written statements 

in the complaints filed by respondents-complainants. The objections taken 

by  the  petitioner-company  in  the  complaints  filed  by  respondents-

complainants are reproduced below:- 

    “

(i)  that the complainants have concealed material facts 

from this Commission;  

    (ii)  that  the  complainants  being  investors  did  not  fall 

within the definition of consumers; 

    (iii)  that  permission  to  file  joint  respective  complaints 

has not been filed by the complainants and as such, the same are 

liable to be dismissed on this ground alone; 

    (iv)  that  this  Commission  is  not  vested  with  territorial 

and pecuniary jurisdiction to decide these complaints; 

CWP-26869-2025 (O&M) and connected cases                            5                         

 

    (v)  that in the face of arbitration clause contained in the 

agreements  to  settle  all  the  dispute  arising  out  of  the  unit  in 

question  through  arbitration,  this  Commission  is  having  no 

jurisdiction to entertain these complaints; 

    (vi)  that  although  as  per  Clause  7.1  of  the  agreement, 

possession of the unit in question was to be delivered, as per dates 

given in the chart above, yet, it was delayed because the opposite 

party suffered force majeure circumstances due to COVID-19; 

    (vii)  that  the  Competent  Authority  vide  circular  dated 

28.10.2020,  Annexure  R-1/1,  granted  extension  of  period  of  6 

months for ongoing project, where the completion date was due 

on or before 15.03.2020 and, as such, the said period of 6 months 

was to be added in the period of delivery of possession of the units 

in question to the complainants; 

    (viii)  that  occupation  and  partial  completion  certificates 

in  respect  of  the  unit/tower  in  question  have  been  received  by 

opposite  party  from  competent  authorities  and  thereafter 

possession  of  the  respective  units  were  handed  over  to  the 

complainants and even sale deeds also stood executed; 

    (ix)  that delay if any was on the part of the comp etent 

authorities  in  issuing  occupation  and  partial  completion 

certificates,  therefore,  for  that  the  company  cannot  be  held 

responsible; 

    (x)  that at the time of obtaining NOC from the op posite 

party,  the  complainants  have  recorded  their  satisfaction 

regarding amenities, additional area etc.; 

    (xi)  that  once  possession  of  the  respective  units  have 

been taken over without any protest and also the sale deeds have 

also  been  executed,  now  the  complainants  are  stopped  from 

claiming  any  compensation,  as  the  same  stands  waived off  by 

them; 

CWP-26869-2025 (O&M) and connected cases                            6                         

 

    (xii)  that  the  principle  of  estoppels  and  waiver  are 

completely applicable to the present cases after execution of sale 

deeds and the complainants cease to be consumer; 

    (xiii)  that  whatever  amount  was  charged  from  the 

complainants  was  strictly  as  per  terms  and  conditions  of  the 

respective agreements; 

    (xiv)  that  the  complainants  were  defaulters  in  making 

payment, which resulted into delay in delivery of possession of the 

respective units; 

    (xv)  that since the complainants have made payment  in 

installments and major chunk of amount has been paid at the time 

of delivery of possession, therefore, they cannot seek interest on 

the entire amount paid from the date of payment; 

    (xvi)  that  the  complaint  is  bad  for  misjoinder  and 

nonjoinder of necessary parties, as the financial institutions from 

which loan has been obtained has not been made party.”      

5.    On  consideration  and  the  evidence  led  by  the  respective 

parties, the SCDRC vide order dated 20.03.2025 allowed the complaints 

filed  by  respondents-complainants.    As  per  the  order  of  the  SCDRC, 

respondents-complainants were held entitled for interest @ 9% per annum 

from the due date of possession onwards till the date of delivery of the 

possession on the entire received sale consideration in respect of the units 

in  question  within  a  period  of  30  days  from  the  date  of  receipt  of  a 

certified copy of the order. The respondents-complainants were also held 

entitled for compensation to the tune of Rs.75,000/- on account of mental 

agony, harassment and deficiency in service along with cost of litigation 

CWP-26869-2025 (O&M) and connected cases                            7                         

 

to the tune of Rs.35,000/-.  Relevant extract of the order dated 20.03.2025 

passed by the SCDRC is reproduced below:- 

     “

In Consumer  complaint  bearing  no.60  of  2024,  the 

opposite party is directed to :- 

    (i)  To pay to the complainants, compensation by w ay of 

interest @ 9% p.a. from 29.06.2021 (due date of possession as 

discussed  above)  onwards  till  30.06.2022  (date  of  delivery  of 

possession) on the entire received sale consideration in respect of 

the unit in question, within a period of 30 days from the date of 

receipt of a certified copy of this order, failing which the entire 

accumulated  amount  of  compensation  from  29.06.2021  to 

30.06.2022 aforesaid shall carry interest @ 12 % p.a. from the 

date of default till this entire accumulated amount is paid to the 

complainants.  

    (ii)  To  pay  lumpsum  compensation  to  the  tune  of 

Rs.75,000/-  for  causing  them  (complainants)  mental  agony  & 

harassment,  deficiency  in  providing  service  and  also  cost  of 

litigation to the tune of Rs.35,000/-, within a period of 30 days, 

from the date of receipt of a certified copy of this order, failing 

which the said amounts shall carry interest @ 9% p.a. from the 

date of default till realization.  

In Consumer  complaint  bearing  no.62  of  2024,  the 

opposite party is directed to :- 

    (i)  To pay to the complainants, compensation by w ay of 

interest @ 9% p.a. from 29.06.2021 (due date of possession as 

discussed  above)  onwards  till  21.10.2022  (date  of  delivery  of 

possession) on the entire received sale consideration in respect of 

the unit in question, within a period of 30 days from the date of 

receipt of a certified copy of this order, failing which the entire 

accumulated  amount  of  compensation  from  29.06.2021  to 

CWP-26869-2025 (O&M) and connected cases                            8                         

 

21.10.2022 aforesaid shall carry interest @ 12 % p.a. from the 

date of default till this entire accumulated amount is paid to the 

complainants.  

    (ii)  To  pay  lumpsum  compensation  to  the  tune  of 

Rs.75,000/-  for  causing  them  (complainants)  mental  agony  & 

harassment,  deficiency  in  providing  service  and  also  cost  of 

litigation to the tune of Rs.35,000/-, within a period of 30 days, 

from the date of receipt of a certified copy of this order, failing 

which the said amounts shall carry interest @ 9% p.a. from the 

date of default till realization.  

In Consumer  complaint  bearing  no.63  of  2024,  the 

opposite party is directed to :- 

    (i)  To pay to the complainants, compensation by w ay of 

interest @ 9% p.a. from 30.09.2021 (due date of possession as 

discussed  above)  onwards  till  24.07.2022  (date  of  delivery  of 

possession) on the entire received sale consideration in respect of 

the unit in question, within a period of 30 days from the date of 

receipt of a certified copy of this order, failing which the entire 

accumulated  amount  of  compensation  from  30.09.2021  to 

24.07.2022 aforesaid shall carry interest @ 12 % p.a. from the 

date of default till this entire accumulated amount is paid to the 

complainants.  

    (ii)  To  pay  lumpsum  compensation  to  the  tune  of 

Rs.75,000/-  for  causing  them  (complainants)  mental  agony  & 

harassment,  deficiency  in  providing  service  and  also  cost  of 

litigation to the tune of Rs.35,000/-, within a period of 30 days, 

from the date of receipt of a certified copy of this order, failing 

which the said amounts shall carry interest @ 9% p.a. from the 

date of default till realization.  

In Consumer  complaint  bearing  no.64  of  2024,  the 

opposite party is directed to :- 

CWP-26869-2025 (O&M) and connected cases                            9                         

 

    (i)  To pay to the complainants, compensation by w ay of 

interest @ 9% p.a. from 30.09.2021 (due date of possession as 

discussed  above)  onwards  till  12.10.2022  (date  of  delivery  of 

possession) on the entire received sale consideration in respect of 

the unit in question, within a period of 30 days from the date of 

receipt of a certified copy of this order, failing which the entire 

accumulated  amount  of  compensation  from  30.09.2021to 

12.10.2022 aforesaid shall carry interest @ 12 % p.a. from the 

date of default till this entire accumulated amount is paid to the 

complainants.  

    (ii)  To  pay  lumpsum  compensation  to  the  tune  of 

Rs.75,000/-  for  causing  them  (complainants)  mental  agony  & 

harassment,  deficiency  in  providing  service  and  also  cost  of 

litigation to the tune of Rs.35,000/-, within a period of 30 days, 

from the date of receipt of a certified copy of this order, failing 

which the said amounts shall carry interest @ 9% p.a. from the 

date of default till realization.  

 

 

6.    A perusal of the order passed by the SCDRC would show it 

has been held by SCDRC that in the absence of any express discharge 

voucher  or  consent  received  from  respondents-complainants  by  the 

petitioner-company  before  execution  of  the  sale  deed  qua  waiver  or 

delayed  compensation,  the  objection  raised  by  the  petitioner-company 

that respondents-complainants have waived off the compensation at the 

time of execution of the sale deed cannot be accepted.  It was also held 

that even the contents of the sale deed does not clarify, as to whether, the 

delay waived of is regarding execution of sale deed or relating to delay in 

delivery of possession of the said unit or of the delayed compensation. 

CWP-26869-2025 (O&M) and connected cases                            10                         

 

Relevant  extract  of  order  dated  20.03.2025  passed  by  the  SCDRC  is 

reproduced below:- 

“Compensation  for  the  period  of  delay  in  delivery  of 

possession of the respective units:- 

14.  It  may  be  stated  here  that  since  admittedly  the 

complainants are in possession of their respective units and sale 

deeds have also been executed between the parties, therefore, the 

only question which needs to be decided by this Commission is, as 

to whether, the complainants are entitled to get any compensation 

for delay in delivery of possession or not? It may be stated here 

that though the opposite party has raised objection to the effect 

that  since  the  complainants  themselves  have  waived  off  any 

compensation at the time of execution of sale deeds and they have 

specifically  agreed  vide  clause  1  (h)  that  vacant  and  physical 

possession of the said Unit has been handed over by the Vendor to 

the  Vendee(s)  herein  at  the  time  of  execution  of  this  Deed  of 

Conveyance/Sale  Deed  and  the  Vendee(s)  acknowledges having 

taken over the possession of the same to the Vendee(s)'s complete 

satisfaction  with  respect  to  amongst others,  the  quality,  design, 

specifications  &  materials  of  the  earthquake  resistant  structure 

constituting  the  building  of  which  the  said  Unit  is  integrated/ 

integral part and the Vendee(s) agree/s that the Vendee(s) shall 

have no claim whatsoever against the Vendor with regard to any 

defects or deficiency in construction, quality of materials used or 

on  account  of  any  delays,  yet,  in  our  considered  opinion  this 

objection  is  not  sustainable,  in  the  absence  of  any express 

discharge voucher or consent received from the complainants by 

the opposite party before execution of the sale deeds qua waiver 

of  delayed  compensation.  Even  otherwise,  a  bare  perusal  of 

contents of clause I (h) of the said deed (ibid) also did not clarify, 

as to whether, the delay waived off, is regarding execution of sale 

CWP-26869-2025 (O&M) and connected cases                            11                         

 

deed or relating to delay in delivery of possession of the said unit 

or of delayed compensation. A similar question has already been 

dealt  with  by  this  Commission  in  Madan  Lal  Kansal  Vs. Dlf 

Homes Panchkula Pvt. Ltd., CC No.805 of 2017 decided on 14 

March, 2019 wherein also despite the fact that sale deed has been 

executed,  compensation  for  the  period  of  delay  in  delivery  of 

possession  was  awarded  by  this  Commission.  The  builder 

challenged  the  said  order  dated  14.03.2019,  by  way  of  filing 

Appeal No.783 of 2019 before the Hon'ble National Commission. 

However, the order dated 14.03.2019 stood upheld by the Hon'ble 

National  Commission  vide  order  dated  22.07.2022,  with 

modification  and  only  the  rate  of  interest  on  delayed 

compensation was decreased from 12% p.a. to 9% p.a. 

Furthermore,  in  the  present  case,  there  is  nothing  on 

record that any express discharge voucher qua non payment of 

compensation for the period of delay in delivery of possession as 

envisaged in Clause 7.6 of the agreement was furnished by the 

complainants to the opposite party.  Under similar circumstances, 

in 'P. Dasa Muni Reddy Vs. P. Appa Rao, 1974 AIR (SC) 2089, 

the  Hon'ble  Supreme  Court  of  India  in  Para  13  has  held  as 

under:- 

"....13.  Abandonment  of  right  is  much  more  than  mere 

waiver, acquies-cence or laches. The decision of the High Court 

in the present case is that the appellant has waived the right to 

evict the respondent. Waiver is an intentional relinquishment of a 

known  right  or  advantage,  benefit,  claim  or  privilege  which 

except for such waiver the party would have enjoyed. Waiver can 

also be a voluntary surrender of a right. The Doctrine of waiver 

has been applied in cases where landlords claimed forfeiture of 

lease  or  tenancy  because  of  breach  of  some  condition  in  the 

contract  of  tenancy.  The  doctrine  which  the  courts  of  law  will 

recognise  is  a  rule  of  judicial  policy  that  a  person  will  not  be 

CWP-26869-2025 (O&M) and connected cases                            12                         

 

allowed to take inconsistent positions to gain advantage through 

the aid of courts. Waiver sometimes partakes of the nature of an 

election. Waiver is consensual in nature. It implies a meeting of 

the minds. It is a matter of mutual intention. The doctrine does not 

depend  on  misrepresentation.  Waiver  actually  requires  two 

parties,  one  party  waiving  and  another  receiving  the benefit  of 

waiver.  There  can  be  waiver  so  intended  by  one  party  and  so 

understood by the other. The essential element of waiver is that 

there  must  be  a  voluntary  and  intentional  relinquishment  of  a 

right. The voluntary choice is the essence of waiver. There should 

exist an opportunity for choice between the relinquishment and an 

enforcement of the right in question. It cannot be held that there 

has  been  a  waiver  of  valuable  rights  where  the  circumstances 

show that what was done was involuntary. There can be no waiver 

of a non-existent right. Similarly, one cannot waive that which is 

not  one's  as  a  right  at  the  time  of  waiver.  Some  mistake  or 

misapprehension as to some facts which constitute the underlying 

assumption  without  which  parties  would  not  have  made the 

contract may be sufficient to justify the court in saying that there 

was no consent......” 

In this view of the matter, objection taken by the opposite 

party in this regard rejected.”

  

7.    Further, the objection raised by the petitioner-company as to 

the  delay  in  delivery  of  possession  was  on  account of force  majeure 

circumstances due to Covid-19, it has been held by the SCDRC that the 

petitioner-company had failed to offer and deliver possession of the units, 

not only within the promised time frame, but even beyond the extended 

period of nine months that was granted due to Covid-19 pandemic. Thus, 

the petitioner-company had demonstrated a clear deficiency in its service.   

CWP-26869-2025 (O&M) and connected cases                            13                         

 

8.    Aggrieved against the order dated 20.03.2025 passed by the 

SCDRC, the petitioner-company filed first appeals before the NCDRC, 

New Delhi.  The appeals came up for consideration before the NCDRC 

on 10.06.2025 and were accordingly dismissed, by upholding the order 

passed by the SCDRC.    

9.    A  perusal  of  the  order  dated  10.06.2025  passed by  the 

NCDRC would reveal that as per the NCDRC, the letter dated 24.06.2022 

will not act as waiver on the part of respondents-complainants and will 

not attract the principle of estoppel as contended. It was also held that the 

abovesaid letter, by no means, can be construed as a waiver or agreement 

between the parties for waiving the entitlement of delayed compensation. 

Even if, the sale deeds have been executed between the parties, it does not 

debar  respondents-complainants  from  the  legitimate entitlement  of 

delayed compensation.  Relevant extract of the order dated 10.06.2025 

passed by the NCDRC is reproduced below:- 

“In  the  present  cases,  possession  of  the  respective  units 

have already been given and Sale Deeds have also been executed 

between the parties. The main issue is with respect to the delay 

compensation.  Vide  impugned  order,  the  State  Commission  has 

directed the payment of delay compensation from the due date of 

possession till the date of possession in all the cases. Counsel for 

the Appellants submits that as per the Agreement, the committed 

date  of  possession  on  30.09.2020  but  due  to  Covid,  certain 

extensions were granted and hence, he does not dispute the due 

date of possession as recorded in the impugned order passed by 

the State  Commission.  He  further admits  that  the  possession  in 

CWP-26869-2025 (O&M) and connected cases                            14                         

 

question  was  handed  over  on  30.06.2022  and  the  fact  that  the 

partial  Occupancy  Certificate  was  handed  over  on  29.06.2022 

and final Occupancy Certificate on 29.07.2022. It is also admitted 

that prior to the date of possession i.e. 29.07.2022, there was no 

other offer of possession. The only ground on which payment of 

delay compensation has been objected to by the Appellants herein 

is that (a) the Complainants have entered into a settlement vide 

which, they have waived off all their rights and hence, no delay 

compensation  is  payable.  Extract  of  one  such  letter  dated 

24.06.2024 in FA/290/2025 is reproduced below: 

 Date-24-06-2022 

To,  

The Commercial Department,  

Ambika Realcon Private Limited,  

Chandigarh. 

Subiect:- Request to issue No Dues Certificate for unit no. 

FP/ORCHID/B/1201 

Dear Sir, 

With  Reference  to  my  apartment  bearing  No. 

FP/ORCHID/B/1201, I hereby request you to kindly issue a "No 

dues certificate" of my apartment, as all accounts (payables and 

receivables) with the company, as per the terms and conditions of 

the agreement dated 13-Apr-2018 stands settled and now nothing 

is  due  against  each  other  and  its  includes  future  claims  also 

except maintenance charges, as explained hereinafter. I am fully 

aware and satisfied with the various facilities which the company 

is  providing at  present.  Besides  it,  I  am  fully  satisfied  with  the 

construction  and  finishing  quality  in  my  flat.  I  understand  that 

proper  maintenance  of  any  society  is  very  important  for  safe, 

comfortable and happy living and I undertake that I will pay my 

CWP-26869-2025 (O&M) and connected cases                            15                         

 

maintenance  charges  fixed/demanded  by  the  company  or  its 

nominee, in timely manner. 

Yours Faithfully. 

(Vivek Bhardwaj & Promila Raita)" 

5.  Similar letters are there in other cases. In their written 

version  before  the  State  Commission,  they  have  objected the 

Complaint inter-alia on following grounds: 

"(xi) that once possession of the respective units have been 

taken over without any protest and also the sale deeds have also 

been executed, now the complainants are stopped from claiming 

any compensation, as the same stands waived off by them; 

(xii)  that  the  principle  of  estoppels  and  waiver  are 

completely applicable to the present cases after execution of sale 

deeds and the complainants cease to be consumer, 

6. The State Commission has considered at length various 

objections of the Opposite Party (Appellant herein) with respect 

to  the  territorial  jurisdiction,  pecuniary  jurisdiction,  the 

Complainants not being consumers, force majeure circumstances 

etc. and have passed appropriate orders. These aspects have not 

been contested by the Appellants herein before us in the Appeals 

and the only issue raised is entitlement of delay compensation to 

the Respondents with respect to the delay compensation. The issue 

of entitlement of delay compensation has already been dealt with 

in detail by the State Commission in its order and the relevant 

paras are reproduced below: 

"Compensation  for  the  period  of  delay  in  delivery  of 

possession of the respective units:- 

 

CWP-26869-2025 (O&M) and connected cases                            16                         

 

14.  It  may  be  stated  here  that  since  admittedly  the 

complainants are in possession of their respective units and sale 

deeds have also been executed between the parties, therefore, the 

only question which needs to be decided by this Commission is, as 

to whether, the complainants are entitled to get any compensation 

for delay in delivery of possession or not? It may be stated here 

that though the opposite party has raised objection to the effect 

that  since  the  complainants  themselves  have  waived  off  any 

compensation at the time of execution of sale deeds and they have 

specifically  agreed  vide  clause  1  (h)  that  vacant  and  physical 

possession of the said Unit has been handed over by the Vendor to 

the  Vendee(s)  herein  at  the  time  of  execution  of  this  Deed  of 

Conveyance/Sale  Deed  and  the  Vendee(s)  acknowledges having 

taken over the possession of the same to the Vendee(s)'s complete 

satisfaction  with  respect  to  amongst others,  the  quality,  design, 

specifications  &  materials  of  the  earthquake  resistant  structure 

constituting  the  building  of  which  the  said  Unit  is 

integrated/integral  part  and  the  Vendee(s)  agree/s  that  the 

Vendee(s)  shall  have  no  claim  whatsoever  against  the Vendor 

with regard to any defects or deficiency in construction, quality of 

materials used or on account of any delays, yet, in our considered 

opinion  this objection  is  not  sustainable,  in  the  absence of any 

express  discharge  voucher  or  consent  received  from  the 

complainants by the opposite party before execution of the sale 

deeds  qua  waiver  of  delayed  compensation.  Even  otherwise,  a 

bare perusal of contents of clause 1(h) of the said deed (ibid) also 

did not  clarify  as  to whether  the  delay  waived off  is regarding 

execution  of  sale  deed  or  relating  to  delay  in  delivery  of 

possession of the said unit or of delayed compensation. A similar 

question has ready beet dealt with by this Commission in Madan 

Lal Kansal vs DLF Homes Panchkula Pvt. Ltd., CC No. 805 of 

2017 decided on 14 March, 2019 wherein also despite the fact 

that sale deed has been executed, compensation for the period of 

CWP-26869-2025 (O&M) and connected cases                            17                         

 

delay in delivery of possession was awarded by this Commission. 

The builder challenged the said order dated 14.03.2019, by way 

of  filing  Appeal  No.  783  of  2019  before  the  Hon'ble National 

Commission. However, the order dated 14.03.2019 stood upheld 

by the Hon'ble National Commission vide order dated 22.07.2022, 

with  modification  and  only  the  rate  of  interest  on  delayed 

compensation was decreased from 12% p.a. to 9% p.a. 

Furthermore,  in  the  present  case,  there  is  nothing  on 

record that any express discharge voucher qua non payment of 

compensation for the period of delay in delivery of possession as 

envisaged in Clause 7.6 of the agreement was furnished by the 

complainants to the opposite party. Under similar circumstances, 

in 'P. Dasa Muni Reddy Vs. P. Appa Rao, 1974 AIR (SC) 2089, 

the Hon'ble Supreme Court of India in Para 13 has held as under- 

"....13.  Abandonment  of  right  is  much  more,  than  mere 

waiver, acquiescence or laches. The decision of the High Court in 

the present case is that the appellant has waived the right to evict 

the  respondent.  Waiver  is  an  intentional  relinquishment of  a 

known  right  or  advantage,  benefit,  claim  or  privilege  which 

except for such waiver the party would have enjoyed. Waiver can 

also be a voluntary surrender of a right. The Doctrine of waiver 

has been applied in cases where landlords claimed forfeiture of 

lease  or  tenancy  because  of  breach  of  some  condition  in  the 

contract  of  tenancy.  The  doctrine  which  the  courts  of  law  will 

recognise  is  a  rule  of  judicial  policy  that  a  person  will  not  be 

allowed to take inconsistent positions to gain advantage through 

the aid of courts. Waiver sometimes partakes of the nature of an 

election. Waiver is consensual in nature. It implies a meeting of 

the minds. It is a matter of mutual intention. The doctrine does not 

depend  on  misrepresentation.  Waiver  actually  requires  two 

parties,  one  party  waiving  and  another  receiving  the benefit  of 

waiver.  There  can  be  waiver  so  intended  by  one  party  and  so 

CWP-26869-2025 (O&M) and connected cases                            18                         

 

understood by the other. The essential element of waiver is that 

there  must  be  a  voluntary  and  intentional  relinquishment  of  a 

right. The voluntary choice is the essence of waiver. There should 

exist an opportunity for choice between the relinquishment and an 

enforcement of the right in question. It cannot be held that there 

has  been  a  waiver  of  valuable  rights  where  the  circumstances 

show that what was done was involuntary. There can be no waiver 

of a non-existent right. Similarly, one cannot waive that which is 

not  one's  as  a  right  at  the  time  of  waiver.  Some  mistake  or 

misapprehension as to some facts which constitute the underlying 

assumption  without  which  parties  would  not  have  made the 

contract may be sufficient to justify the court in saying that there 

was no consent...... 

In this view of the matter, objection taken by the opposite 

party in this regard Chan stands rejected. 

15.  Now  the  question  arises,  as  to  what  compensation 

should  be  granted  to  the  complainants  for  delay  in  delivery  of 

possession  of  the  unit  in  question?  It  may  be  stated  here that 

Consumer  Protection  Act  has  been  made  to  safeguard  the 

consumer rights in the present case failure of opposite party to 

offer and deliver possession of the unit in question, in a timely 

manner as discussed above amounts to deficiency in service. In 

the  case  titled  as  Lucknow  Development  Authority  M.K. Gupta 

[1994] 1 SCC 243, the Hon'ble Supreme Court discussed about 

the extent of the jurisdiction of the Consumer Fora to award just 

and  reasonable  compensation  for  the  harassment  and  agony 

suffered  by  a  consumer.  In  DLF  Homes  Panchkula  Pvt.  Ltd. 

Versus Himanshu Arora, Civil Appeal No. 11097 of 2018, decided 

on 19 November, 2018 under similar circumstances, the Hon'ble 

Supreme  Court  of  India  has  upheld  the  order  of  the  Hon'ble 

National Commission awarding Interest @ 9% p.a. for the period 

of delay in delivery of actual physical possession. Thereafter also, 

CWP-26869-2025 (O&M) and connected cases                            19                         

 

similar rate of interest i.e. 9% p.a. was granted by the Hon'ble 

Supreme Court in DLF Homes Panchkula (P) Ltd. Versus Sushila 

Devi,  Civil  Appeal  Nos.  2285-2330  of  2019,  decided on  26 

February, 2019 by making reference to the earlier order passed 

by it in Himanshu Arora's case (supra). Furthermore, in Nagesh 

Maruti Utekar Vs. Sunstone Developers Joint Venture, Consumer 

Case No. 12 of 2017 decided on 04 May 2022 also, the Hon'ble 

National  Commission  awarded  interest  @9%  p.a.  from  the 

committed  date  of  delivery  till  actual  physical  possession  is 

delivered. In Shreya Kumar & 11 Ors Vs. M/s Ansal Housing & 

Construction Ltd. & 3 Ors., Consumer Case No. 1021 of 2017, 

decided  on  05  May  2022,  the  Larger  Bench  of  the  Hon'ble 

National Commission has awarded interest @ 9% p.a. from the 

committed  date  of  delivery  till  actual  physical  possession  is 

delivered. 

Under these circumstances, if we grant interest @9% p.a. 

to  the  complainants  on  the  entire  amount  deposited  by them 

towards  their  on  respective  units  from  due  dates  onwards,  as 

discussed  above,  till  possession  of  the  unit  in  question  has 

actually been delivered to them, after deducting the period of 9 

months due to COVID-19, that will meet the ends of justice. 

Complainants are consumers even after execution of sale 

deeds:- 

16. As far as objection taken by the opposite party to the 

effect  that  the  complainants  ceased  to  be  consumers,  after 

execution of sale deeds, it may be stated here that this objection 

does  not  merit  acceptance,  in  view  of  law  laid  down  by  the 

Hon'ble  Supreme  Court  in  the  case  of  Debashis  Sinha  vs  M/s 

R.N.R Enterprise, Civil Appeal No.3343 of 2020 February 9 2023, 

wherein it was held that the mere fact that possession has been 

taken over by the consumer and sale deed has been registered, 

CWP-26869-2025 (O&M) and connected cases                            20                         

 

cannot forfeit his/her right to claim the services promised by the 

project proponent." 

7.  After  careful  consideration  of  all  the  facts  and 

circumstances of the case and considering that the possession was 

given to the Complainant with valid Occupancy Certificate after a 

delay  beyond  the  committed  date,  hence,  the 

Complainants/Respondents  herein  are  entitled  to  delay 

compensation. The so called Agreement/Letter dated 24.06.2022 

cited will not act as a waiver on the part of the Complainants and 

will not attract the principal of estoppel as contended. The above 

stated  letter  by  no  means  can  be  construed  as  any  waiver or 

agreement  between  the  parties  for  waiving  the  entitlement  of 

delay  compensation.  Even  the  contention  of  the  Appellant  that 

Sale Deeds have since been executed, will not come to their help 

as subsequent execution of Sale Deeds also does not debar the 

Complainants  from  their  legitimate  entitlement  of  delay 

compensation. Counsel for the Appellant placed reliance on the 

following judgments: CC No.203 of 2018 Sh. Om Prakash Gupta 

& Anr. Vs. M/s Ansal Properties & Industries dated 04.05.2021 

and  V.  Anantha  Raju  &  Anr.  Vs.  T.M.  Narasimhan  &  Ors. 

(2021) 17 SCC 165. 

8. After a careful consideration of the orders of the State 

Commission,  we  are  of  the  considered  view  that  the  State 

Commission  has  passed  a  well-reasoned  order  and  we  find  no 

reason to interfere with the same. There is no illegality, material 

irregularity  or  jurisdictional  error  in  the  orders  of  the State 

Commission. Hence, the said order is upheld and accordingly, all 

the four First Appeals covered under this order are dismissed.” 

10.    Aggrieved against the order dated 20.03.2025 (Annexure P-6) 

passed by the SCDRC and the order dated 10.06.2025 (Annexure P-8) 

CWP-26869-2025 (O&M) and connected cases                            21                         

 

passed by the NCDRC, the petitioner-company has filed the present writ 

petitions.  

11.    The  only  argument  addressed  before  us  by  the  learned 

counsel  appearing  on  behalf  of  the  petitioner-company  is  that  once, 

respondents-complainants had made a request for issuance of No Dues 

Certificate  for  unit  and  had  mentioned  that  all  the  accounts  with  the 

petitioner-company,  as  per  terms  and  conditions  of agreement,  stand 

settled and there was nothing due from the petitioner-company, as such,  

respondents-complainants are not entitled to claim any compensation on 

account  for  delay  in  giving  the  possession  of  the  unit  to  respondents-

complainants by the petitioner-company.   

12.    We have heard the learned counsel appearing on behalf of the 

petitioner-company  and  gone  through  the  documents  available  on  the 

record.  

13.    A perusal of the facts of the present cases would show that it 

is an admitted fact that there was a delay in giving the possession of unit 

to respondents-complainants by the petitioner-company. The petitioner-

company applied for Occupation and Partial Completion Certificates in 

the year 2022 only i.e. after a significant delay of about two years from 

the committed due date of possession.  It is well settled law that it is 

builder’s responsibility to compensate delay in giving possession of the 

unit.  Request for No Dues Certificate or issuance of No Dues Certificate 

CWP-26869-2025 (O&M) and connected cases                            22                         

 

does not absolve the builder from his responsibility to give possession of 

the unit to the buyers in time.  It is also well settled law that there cannot 

be any estoppel against the law. Buyers are entitled for compensation on 

account of delay in delivery of the possession of the unit/units.  

14.    Reliance  has  been  placed  upon  case  titled  as Santhosh 

Narasimha Murthy and Ors. Vs. M/s Mantri Castles Private Limited 

and Anr, 2025(2) SCC 243,  decided on 25.07.2023, wherein it has been 

held  by  the  Hon’ble  Apex  Court  that  home  buyers  are  entitled  to 

compensation  for  delayed  possession.  The  relevant  contents  are 

reproduced as follows:- 

“10.   Clause  6.1  of  the  agreement  stipulates  that  the 

developer shall construct for the purchaser, the apartment which 

was contracted for and possession would be handed over in terms 

of  Annexure  B-1.  Clause  6.4  contains  a  force  majeure  clause. 

Annexure B-1 contains the assured date of possession.  

11.   For  the  purpose  of  these  proceedings,  counsel 

appearing on behalf of the home buyers and the first respondent-

developer have proceeded on the basis of the dates of possession 

as indicated in Annexure P-14 to the Civil Appeal. Having due 

regard  to  Clause 14.5  of  the agreements,  each  of  the  sixty-two 

home buyers is entitled to compensation at the rate of Rs. 3 per 

square foot per month for the delay of nearly six to seven years in 

granting possession. The compensation shall be payable for each 

home buyer from the date on which possession was assured (as 

reflected  in  Annexure  P-14)  until  19  February  2023  when 

possession was handed over by the developer. 

12.   The NCDRC has awarded interest at the rate of 6% 

per annum on the deposits made by the complainants with effect 

CWP-26869-2025 (O&M) and connected cases                            23                         

 

from 28 February 2018 till the offer of possession. This has been 

questioned on behalf of the home buyers on the ground that they 

are  entitled  to  interest  with  effect  from  the  respective  dates  on 

which the deposit of consideration was made with the developer. 

Moreover, it has been submitted that interest at the rate of 6% per 

annum must be enhanced to 9% per annum. 

13.   On  the  other  hand,  counsel  for  the  developer 

submits that the developer had, in addition, paid EMIs on behalf 

of the home buyers.  

14.   The home buyers have submitted that the EMIs were 

paid in terms of the scheme which was agreed upon and were paid 

only for some of the home buyers. 

15.   The home buyers are entitled to interest with effect 

from the assured dates of possession until the offer of possession 

was made on 19 February 2023.  

16.   In the facts of the present case, we affirm the award 

of interest at the rate of 6% per annum by the NCDRC subject to 

the modification that interest shall be payable with effect from the 

respective  dates  prescribed  in  the  agreements  for  delivery  of 

possession. 

17.   We accordingly allow the appeal filed by the home 

buyers in the following terms : 

(i)  The  home  buyers  shall  be  paid compensation  on 

account of delayed possession at the rate of Rs 3 per square foot 

per month in terms of clause 14.5 of the buyer agreements. 

(ii)  For  computing  the  amount  due  under  clause  14.5  in 

terms of (i) above, the assured dates of possession, as reflected in 

Annexure  P-14,  shall  be  the  dates  with  effect  from  which  the 

payment would be computed. The compensation shall be payable 

until 31 January 2023. 

(iii) The home buyers shall be entitled to interest at the rate 

of 6% per annum with effect from the respective dates fixed for 

handing over possession, as reflected in Annexure P-14; and 

CWP-26869-2025 (O&M) and connected cases                            24                         

 

(iv) The amounts which are due and payable in the above 

terms shall be paid over on or before 30 September 2023. 

18.   The appeal is accordingly allowed.” 

 

15.    Further,  in  case  of Wg.  Cdr.  Arifur  Rahman  Khan  and 

Aleya  Sultana  and  Ors.  Vs.  DLF  Southern  Homes  Pvt. Ltd.  (now 

known as BEGUR OMR Homes Pvt. Ltd. and Ors. 2020 (16) SCC 

512,  decided on 24.08.2020, the Hon’ble Supreme Court has held that 

flat  purchasers  who  have  obtained  possession  or  executed  deeds  of 

conveyance do not lose their right to make a claim for compensation for 

delay in handing over of the flats.  Relevant contents are reproduced as 

follows:- 

“24.  A failure of the developer to comply with the 

contractual  obligation  to  provide  the  flat  to  a  flat 

purchaser within a contractually stipulated period amounts 

to a deficiency. There is a fault, shortcoming or inadequacy 

in the nature and manner of performance which has been 

undertaken to be performed in pursuance of the contract in 

relation to the service. The expression ‘service in 

Section 2 

(1) (o) means a service of any description which is made 

available  to  potential  users  including  the  provision  of 

facilities in connection with (among other things) housing 

construction. Under Section 14(1)(e), the jurisdiction of the 

consumer  forum  extends  to  directing  the  opposite  party 

inter  alia  to  remove  the  deficiency  in  the  service  in 

question.  Intrinsic  to  the  jurisdiction  which  has  been 

conferred to direct the removal of a deficiency in service is 

the provision of compensation as a measure of restitution 

to a flat buyer for the delay which has been occasioned by 

the developer beyond the period within which possession 

CWP-26869-2025 (O&M) and connected cases                            25                         

 

was to be handed over to the purchaser. Flat purchasers 

suffer agony and harassment, as a result of the default of 

the developer. Flat purchasers make legitimate assessments 

in regard to the future course of their lives based on the flat 

which  has  been  purchased  being  available  for  use  and 

occupation. These legitimate expectations are belied when 

the developer as in the present case is guilty of a delay of 

years  in  the  fulfilment  of  a  contractual  obligation. To 

uphold the contention of the developer that the flat buyer is 

constrained by the terms of the agreed rate irrespective of 

the nature or extent of delay would result in a miscarriage 

of  justice.  Undoubtedly,  as  this  court  held  in  Dhanda, 

courts ordinarily would hold parties down to a contractual 

bargain. Equally the court cannot be oblivious to the one-

sided nature of ABAs which are drafted by and to protect 

the  interest  of  the  developer. Parliament  consciously 

designed  remedies  in  the  CP  Act 1986  to  protect 

consumers. Where, as in the present case, there has been a 

gross delay in the handing over of possession beyond the 

contractually  stipulated  debt,  we  are  clearly  of  the  view 

that the jurisdiction of the consumer forum to award just 

and reasonable compensation as an incident of its power to 

direct  the  removal  of  a  deficiency  in  service  is  not 

constrained by the terms of a rate which is prescribed in an 

unfair bargain. 

  xxxx   xxxx    xxxx    xxxx   

35.  The  flat  purchasers  invested  hard  earned 

money.  It  is  only  reasonable  to  presume  that  the  next 

logical step is for the purchaser to perfect the title to the 

premises which have been allotted under the terms of the 

ABA.  But  the  submission  of  the  developer  is  that  the 

purchaser forsakes the remedy before the consumer forum 

by  seeking  a  Deed  of  Conveyance.  To  accept  such  a 

CWP-26869-2025 (O&M) and connected cases                            26                         

 

construction  would  lead  to  an  absurd  consequence  of 

requiring the purchaser either to abandon a just claim as a 

condition  for  obtaining  the  conveyance  or  to  indefinitely 

delay  the  execution  of  the  Deed  of  Conveyance  pending 

protracted consumer litigation. 

36.   It has been urged by the learned counsel of 

the  developer  that a consequence of  the  execution of the 

Deed of Conveyance in the present case is that the same 

ceases  to  be  a  transaction  in  the  nature  of  “supply  of 

services” covered under the CP Act 1986 and becomes a 

mere sale of immovable property which is not amenable to 

the jurisdiction of Consumer Fora. In Narne Construction 

(P) Ltd. v. Union of India (2012) 5 SCC 359 , this Court 

distinguished  between  a  simple  transfer  of  a  piece  of 

immovable property and housing construction or building 

activity carried out by a private or statutory body falling in 

the category of ‘service’ within the meaning of Section 2 

(1) (o) of the CP Act 1986. This Court held that: 

“8.  Having  regard  to  the  nature  of  transaction 

between the appellant Company and its customers involved 

much more than a simple transfer of a piece of immovable 

property it is clear the same constitutes “service” within 

the  meaning  of  the  Act.  It  was  not  the  case  that  the 

appellant Company was selling the given property with all 

its advantages and/or disadvantages on “as is where is” 

basis,  as  was  the  position  in UT  Chandigarh  Admn  v. 

Amarjeet Singh. It is a case where a clear-cut assurance 

was made to the purchasers as to the nature and extent of 

development  that  would  be  carried  out  by  the  appellant 

Company as a part of package under which a sale of fully 

developed plots with assured facilities was made in favour 

of the purchasers for valuable consideration. To the extent 

the transfer of site with developments in the manner and to 

CWP-26869-2025 (O&M) and connected cases                            27                         

 

the extent indicated earlier was a part of the transaction, 

the appellant Company has indeed undertaken to provide a 

service.  Any  deficiency  or  defect  in  such  service  would 

make  it  accountable  before  the  competent  Consumer 

Forum at the instance of consumers like the respondents.” 

 The developer in the present case has undertaken to 

provide  a  service  in  the  nature  of  developing  residential 

flats with certain amenities and remains amenable to the 

jurisdiction of the Consumer Fora. Consequently, we are 

unable  to  subscribe  to  the  view  of  the  NCDRC  that  flat 

purchasers who obtained possession or executed Deeds of 

Conveyance  have  lost  their  right  to  make  a  claim  for 

compensation for the delayed handing over of the flats. 

xxxx    xxxx    xxxx    xxxx 

55.   For the above reasons we have come to the 

conclusion  that  the  dismissal  of  the  complaint  by  the 

NCDRC  was  erroneous.  The  flat  buyers  are  entitled  to 

compensation for delayed handing over of possession and 

for the failure of the developer to fulfil the representations 

made to flat buyers in regard to the provision of amenities. 

The reasoning of the NCDRC on these facets suffers from a 

clear perversity and patent errors of law which have been 

noticed in the earlier part of this judgment. Allowing the 

appeals in part, we set aside the impugned judgment and 

order  of  the  NCDRC  dated  2  July  2019  dismissing  the 

consumer complaint. While doing so, we issue the following 

directions: 

(i)  Save  and  except  for  eleven  appellants  who 

entered  into  specific  settlements  with  the  developer  and 

three appellants who have sold their right, title and interest 

under the ABA, the first and second respondents shall, as a 

measure of compensation, pay an amount calculated at the 

rate of 6 per cent simple interest per annum to each of the 

CWP-26869-2025 (O&M) and connected cases                            28                         

 

appellants.  The  amount  shall  be  computed  on  the  total 

amounts paid towards the purchase of the respective flats 

with effect from the date of expiry of thirty-six months from 

the execution of the respective ABAs until the  date of the 

offer  of  possession  after  the  receipt  of  the  occupation 

certificate; 

(ii)  The  above  amount  shall  be  in  addition  to  the 

amounts  which  have  been  paid  over  or  credited  by  the 

developer at the rate of Rs 5 per square foot per month at 

the time of the drawing of final accounts; and 

(iii)  The  amounts  due  and  payable  in  terms  of 

directions  (i)  and  (ii)  above  shall  be  paid  over  within  a 

period of one month from the date of this judgment failing 

which they shall carry interest at the rate of 9 per cent per 

annum until payment. 

56.   The civil appeals are accordingly allowed in 

the above terms.  

57.  Pending  application(s),  if  any,  shall  stand 

disposed of.” 

     

16.    A perusal of the request made by respondents-complainants 

for grant of No Dues Certificate would show that it nowhere mentions 

that  respondents-complainants  have  waived  off  their  right  to  claim 

compensation on account of delay in giving possession of the unit/units.  

   

17.    A High Court while exercising its power of judicial review 

against the order passed by the NCDRC, exercises a limited revisional 

jurisdiction  and  interferes  only  in  the  cases  where,  there  is  an  error 

apparent in law or there is an illegality, impropriety or perversity in the 

impugned order.   

CWP-26869-2025 (O&M) and connected cases                            29                         

 

18.    Since no defect in the order passed by the NCDRC has been 

pointed out during the course of arguments and there is no evidence to 

hold that the orders suffer from any illegality, impropriety or perversity or 

incorrect  appreciation  of  the  evidence  brought  on  record,  we  find  that 

there are no sufficient grounds existing in the present writ petitions to call 

for any interference in the order dated 20.03.2025 (Annexure P-6)  passed 

by the SCDRC and the order dated 10.06.2025 (Annexure P-8) passed by 

NCDRC.  Accordingly, the present writ petitions are dismissed in limine.   

19.    Pending  miscellaneous  application(s),  if  any, also  stand(s) 

disposed of.   

20.     A photocopy of this order be placed on the files of the other 

connected cases.     

 

        (GURVINDER SINGH GILL)     (DEEPINDER SINGH NALWA) 

                   JUDGE                                            JUDGE 

 

 

10.09.2025    

Ramandeep Singh      

 

 

  

Whether speaking / reasoned            Yes /No  

 

Whether Reportable                           Yes/No    

Reference cases

Description

Legal Notes

Add a Note....