0  26 May, 2017
Listen in mins | Read in 41:00 mins
EN
HI

Ashok Chauhan Vs. State of Himachal Pradesh & others

  Himachal Pradesh High Court Civil Writ Petition No.880/2017
Link copied!

Case Background

The following issues arise for consideration in the present petition – (a) as to whether work executed by a contractor, in his capacity as a sub-contractor, can be considered to ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

High Court of H.P.IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA

Civil Writ Petition No.880/2017

Reserved on : 19.5.2017

Date of Decision : May 26, 2017

Ashok Chauhan ...Petitioner.

Versus

State of Himachal Pradesh & others ...Respondents.

Coram:

The Hon’ble Mr. Justice Sanjay Karol, Acting Chief Justice.

The Hon’ble Mr. Justice Ajay Mohan Goel, Judge.

Whether approved for reporting?

1 Yes.

For the Petitioner : Mr. Suneet Goel, Advocate.

For the Respondents : Mr. Shrawan Dogra, Advocate

General with Mr. Romesh Verma,

and Mr. Anup Rattan, Additional

Advocate General.

Sanjay Karol, Acting Chief Justice

The following issues arise for consideration in

the present petition – (a) as to whether work executed by a

contractor, in his capacity as a sub-contractor, can be

considered to have been executed by “a contractor” as

defined under sub-clause (iii) of clause (2) of Conditions of

Contract, and (b) whether work so executed by the

petitioner that of “Open Excavation of Roads and Barrage”

Whether reporters of the local papers may be allowed to see the judgment?

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…2…

and “underground excavation work of Head Race Tunnel

with concrete lining and other allied works” as a contractor

can be construed to be similar to the “work”, “contracted to

be executed”, so defined under sub-clause (1) of Clause 2

of the Conditions of Contract.

2. The Himacha l Pradesh Public Works

Department invited tenders for construction of following

work, with an estimated cost of `22,00,32,747/-:

“NAME OF WORK Construction of Rajiv Gandhi

Multipurpose Sports Stadium at Katasani Shimla,

Tehsil and District Shimla, H.P. (Sh. Construction

of Building portion, WS and SI, Site Development

Rain harvesting tank, Septic Tank and approach

road and C/o sitting steps.”

3. The tender document prescribes both

“General Rules and Directions” as also the “Conditions of

Contract”, containing the definition clause.

4. The relevant clauses of the tender document,

with which we are concerned, for the purpose of

convenience and ready reference, are extracted as

under:

“General Rules and Directions”

………….

19. The contractor shall submit list of works which are

completed/in hand (progress) in the following form:

Work Done Detail: In last five years with base year

indicated in performs of schedule “F”

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…3…

Sr.

No.

Name of

HP Govt.

Division

or State

or

Central

PSU’s

Name

of

work

Cost of completion Remarks

(Indicate in %

of completion

of awarded

components)

Awarded

amount

Completi

on

amount

Penalty if any

and amount

paid

thereunder

1. 2. 3. 4. 5.

Work in hand Detail

Name

of

work.

Name of

HP Govt.

Division or

State or

Central

PSU’s

where

work is

executed

Amount of work completed Position of

works in

progress

(indicate in %

of completion

of awarded

components)

Stipulated

date of

completion

Rema

rks

Awarded

amount

Amount

of work

done

upto

last

running

bill

Penalty if

any and

amount

pain

thereafter.

1 2 3 4 5 6

These statements should be countersigned by the Engineer in

charge, not below the rank of an Executive Engineer or

equivalent in State/Central Govt. PSU’s with his seal.”

“28. Eligibility criteria:

28.1 (This eligibility condition shall be applicable for

those works of amount put to tender is up to Rs.50.00

lacs) As per Govt notification the contractor should not

have more than two contracts at a time each of

Rs.100.00 lacs or more in any HPPWD circles. The

contractor has to submit the list of incomplete works in

hand on the proforma mentioned at S.No.19 of General

Rules and Directions.

28.2 (This eligibility condition shall be applicable for

those works of amount put to tender is more than 50.00

lacs)

28.2.a :Bidding Capacity:- Bidders who meet the

minimum qualification criteria will be qualified only if

their assessed available bid capacity for construction

works is equal to or more than the total bid value. The

available bid capacity will be calculated as under:

Assessed Available Bid capacity = (A x N x M – B)

where

A=Maximum value of civil engineering works executed

in any one year during the last five years (updated to

the price level of the financial year in which bids are

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…4…

revised at the rate of 8 percent a year) taking i nto

account the completed as well as works in progress.

Lasst Five years

(excluding current

year)

Amount of

work done

in each

financial

year

Total annual valume

of civil engineering

construction work

executed and

payments received in

the last five years

preceding the year in

which bids are

invited (Attach/

upload certificate

from Chartered

Accountant)

(Rs. In lakhs)

Year-2011-12

Year-2012-13

Year-2013-14

Year-2014-15

Year-2015-16

N = Number of years prescribed for completion of the

works for which bids are invited (period up to 6 months

to be taken as half-year and more than 6 months as one

year).

M = 2

B = Value, at the current price level, of existing

commitments and on -going works to be completed

during the period of completion of the works for which

bids are invited. The details should be on the formats

indicated in condition no 19.

28.2.b: Minimum work done condition: - Minimum one

similar work done of amount not less than 40% (forty

percent) of the estimated cost (without Liquidated

Damage or compensation) in last five years”.

(Emphasis

supplied)

5. “Conditions of Contract”

“2. In the contract, the following expressions

shall, unless the context otherwise requires, have

the meanings hereby respectively assigned to

them:-

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…5…

(i) The expression works or work shall, unless

there be something either in the subject or

context repugnant to such construction, be

construed and taken to means the works by

or by virtue of the contract contracted to be

executed whether temporary or permanent,

and whether original, altered, substituted or

additional.

(ii) ………

(iii) The Contractor shall mean the individual,

firm or company, whether incorporated or

not, undertaking the works and shall include

the legal personal representative of such

individual or the persons composing such

firm or company, or successors of such firm

or company and the permitted assignees of

such individual, firm or company.”

(Emphasis supplied)

6. Petitioner, who is a Class-A Contractor, has

executed works, certificates whereof, relevant for

adjudication of the present lis, are extracted as under:

(1) Certificate No.1

“ WORK DONE CERTIFICATE

Name of Sub Contractor -: Ashok Chauhan & Co.

……………

Name of work-: Contract agreement no.SK/CII-

HRT Balance work, da ted

25/11/2014 for construction of

5.0m Dia-Shaped Head Race

Tunnel (HRT) form RD-0.00 to

RD-11145.00 complete in all

respect – Balance works for

Sawra Kuddu HEP (111 MM) in

Distt. Shimla (HP) Inida.

Agreement-: SC/100/3351/LOI/01, Dated

15/03/2015

Value of work Executed:- 55,93,61,306.14

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…6…

Work executed-: Feb’2017

M/s Ashok Chauhan & Co. sub contractor of HCC has executed

the Underground excavation work of Head Race Tunnel with

concrete lining & other allied works as per above mentioned

agreement are as under:-

S.N Description Unit Quantity

1 Underground

Excavation

Cum 39,795,629

2 Removal of slush Cum 13601.533

3 Hauling of excavated

material

Cum 5586.109

4 Structural steel works MT 278.015

5 Rock bolting & Rock

Anchoring

RMT 10,082.00

6 Drilling holes RMT 10,415.284

7 Steel reinforcement MT 1,62.188

8 Grouting MT 2445.89

9 Shotcrete Cum 6,43.443

10 Concrete Cum 63,719.374

11 Admixtures Kg 5,02,359.073

12 Dewatering Kwh 2,60,997.30

The certificate is issued to M/s. Ashok Chauhan & Co. on their

request for their future Tendering purpose only.”

(2) Certificate No.2

“Certificate Regarding Performance of Contractor

Name of Contractor - Ashok Chauhan & Co.

Permanent Address - Durga Niwas, Below HIMFED

Building, BCS, New Shimla, HP

Name of work - Award of “Construction of Civil

Works” for (Package-II) Chanju-

1 Hydroelectric Project Head

Race Tunnel.

Date of Award - 12-08-2011.

Criteria for Award - Lowest bidder in terms of unit

rate.

Value of Work Awarded - Rs.29,87,19,150/-

Value of work Executed - Rs.18,83,08,601 (Scope

reduced by client)

Status of Work - Completed in June,15

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…7…

Agreement No.- IA Energy/Chanju-1/Package-II/

2011-438

They have executed the Road works, underground excavation

of Head Race Tunnel, HRT Adit, and all Other allied works. The

breakups of items as per above mentioned agreement no. are

as under:-

Sl.

No.

Description of items Unit Quantity Remarks

1 Open Excavation in Roads

and Barrage

1.1 Soft Rock Cum 6707.29

1.2 Hard Rock Cum 5308.38

2 Underground excavation in

Tunnelling

Cum 52265.502

3 Rock Bolt and Rock Anchor Rmt 3977.70

4 Drilling holes Rmt 3775.33

5 Structural Steel Works MT 109.277

6 Shotcrete Cum 3.108

7 Wire mesh Sqm 8.00

8 G.I. Gabion Blocks (Wire

crates)

Cum 4469.80

9 Dewatering Kwh 290947.39

10 Cement Concrete works. Cum 1801.095

Liquidated damages or anynay other

Panel action if imposed - No

Comments on the capabilities of the contractor:-

Technical Proficiency Very Good

Financial Soundness Excellent

Mobilization of T&P Very Good

General Behaviour Excellent

The excavation was completed by Contractor with in time. His

mobilization of men, material & machinery is also very good.

Contractor is very serious & prompt while performing his

duties. The quality of the work and management at the site is

very appreciable. He will certainly be assets of any

organization of any organization for performing time bound

and quality works of the tunnel Excavation.”

(3) Certificate No.3

“Certificate Regarding Performance of Contractor

Name of Contractor - Ashok Chauhan & Co.

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…8…

Permanent Address - Durga Niwas, Below HIMFED

Building, BCS, New Shimla, H.P.

Name of work: Award of “Construction of Civil

Works” (Package-1) for Chanju-

1 Hydroelectric Project (River

Diversion Feeder Tunnel and

Desilting Chamber and Head

Race Tunnel up RD 0 -518

including Adit-1.

Date of Award - 13-09-2011

Criteria for Award - Lowest Bidder in terms of unit

rate.

Value of Work Awarded - Rs.18,58,97,200/-

Value of Work Executed - Rs.22,68,00,793/-

Status of Work - Completed in June, 15

Agreement No. - IA Energy/Chanju -1/Package-

1/2011-458

They have executed the Road works, underground excavation

of Head Race Tunnel, Diversion works, HRT Adit, Silt Flushing

Tunnel, De-silting Chamber, Adit to SFT, Adit to Gate Shart,

Adit to Gate Hoist Chamber, Transition between De -silting

chamber, Silt connection Tunnel & all other allied works. The

breakups of items as per above mentioned agreement no. are

as under:

Sl.No. Description

of Items

Unit Quantity Remarks

1 Open

Excavation

in Roads and

Barrage

1.1. Soft Rock Cum 356325.87

1.2 Hard Rock Cum 86340.17

2 Underground

excavation

in Tunnelling

Cum 31863.16

3 Rock Bolt

and Rock

Anchor

Rmt 13288.25

4 Drilling holes Rmt 12848.00

5 Structural

Steel works

MT 42.113

6 Shotcrete Cum 462.082

7 Wire mesh Sqm 4412.59

8 G.I. Gabion

Blocks (Wire

crates)

Cum 7527.31

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…9…

9 Dewatering Kwh 42190.80

Liquidated damages or any other

Panel action if imposed - No

Comments on the capabilities of the contractor:-

Technical Proficiency Very Good

Financial Soundness Excellent

Mobilization of T&P Very Good

General Behaviour Excellent

The excavation was completed by Contractor with in time. His

mobilization of men, material & machinery is also very good.

Contractor is very serious & prompt while performing his

duties. The quality of the work and management at the site is

very appreciable. He will certainly be assets of any

organization of any organization for performing time bound

and quality works of the tunnel Excavation.”

7. At this point in time, we may also observe

that the contractor stands awarded work, similar to the

work, subject matter of lis, for a sum of approximately `3

crores, which we have not considered , for the simple

reason that such information never came to be furnished

alongwith the technical bid.

8. Petitioner executed the works, in relation to

Certificate No.1 (supra), as a Sub-Contractor, for a Public

Sector Undertaking, and works in relation to Certificates

No.2 & 3 (supra) stand executed by him as a Contractor,

for a private enterprise.

9. It is not in dispute that finding the petitioner

to be ineligible, only for the reason that he had not

executed any work, that of the Government/Public Sector

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…10…

Undertaking, as a Contractor, technical bid, so submitted

by him, stands rejected by the respondents.

10. Respectfully, we are not in agreement with

the submission made by the learned Advocate General

that Condition No.19 is essential, and that it is required to

be read with or as a condition prescribed under Clause

28, prescribing the eligibility criteria. Conditions No.19 &

28 fall under that part of the tender document, which

prescribes “General Rules and Directions”. Save and

except for Condition No.19, there is nothing in the

document, more so in the clause prescribing the eligibility

criteria, that only such of those contractors, who

executed work for “last five years”, and that too only of

the State of Himachal Pradesh or any other State/ Central

Public Sector Undertaking, shall be eligible. Conversely,

there is nothing to exclude such of those contractors,

who never ever execut ed any work that of the

Government or Public Sector Undertaking . Conditions of

the tender document are evidently and unambiguously

clear. In fact Condition No.28, that of the eligibility

criteria, stipulates a condition, debarring a contractor

who is simultaneously executing two contracts of the

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…11…

State Government, having value of more than `1 crore.

This perhaps is to break monopoly and to ensure that a

contractor does not have more work in hand than that

can be executed ordinarily. Reference of Conditions

No.19 in condition No.28.1 is only for ascertaining such

qualification/ disqualification. Clause 28.1, exclusionary

in nature, debars certain category of contractors. It is

clause 28.2 which stipulates the eligibility criteria. The

crux lies in this clause.

11. Expression “work” in the definition clause is

only with reference to the work, subject matter of the

contract and not the previous work so executed by the

concerned contractor.

12. “Contractor” so defined is only to mean an

entity and in this case the individual, who is engaged for

undertaking the “works”, so stipulated “under the

contract”.

13. What is contemplated in the tender is that

there has to be a contractor who has capacity to

undertake and execute the work for which tender stands

issued and also to ensure that previously he had carried

out similar works of at least 40% of the total sanctioned

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…12…

value of the work for which the tender is issued. Of

course, he must not fall within the limitations of clause

28.1.

14. There is no dispute that once a per son

participates in a tender process, thereafter he cannot be

allowed to challenge the said process, more so for the

reason that he has been declared unsuccessful.

However, in this case, petitioner has not challenged the

conditions of tender, on the basis of which he

participated in the process. Grievance of the petitioner is

that respondents have misread , misconstrued and

misapplied Clauses 19 & 28.2.b of the tender document

and thus erroneously and illegally rejected his technical

bid.

15. It is not in dispute that the petitioner, in his

own capacity, as a contractor has executed works worth

`18,83,00,000/- (Approx.) and `22,68,00,000/- (Approx.),

Though this work stands executed by him for private

parties, yet it remains a fact that the works executed are

of civil nature, may be for a hydroelectric project.

Besides this, work done certificate, issued in favour of the

petitioner by a Public Sector Undertaking , also

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…13…

acknowledges execution of the work , executed by the

petitioner, in his capacity as a sub-contractor. It is

relevant to take note that though the primary contractor

was HCC, but however, HPPCL acknowledged factum of

satisfactory completion of the actual work by the

petitioner. Also, the work done certificate has not been

issued in favour of the primary contractor, but the

present petitioner, certifying that petitioner executed the

works and not the Primary Contractor. Significantly, this

work done certificate is not being ignored by the

respondents on the ground that the works so executed by

the petitioner is not similar to the work for which the

tender has been issued. Objection of the respondents is

that the said work was not executed by the petitioner in

his capacity as a contractor but that as a sub-contractor.

In other words, it is evident that had the said work been

executed by the petitioner in his capacity as a contractor,

then technically, he would have qualified for further

participation in the bidding process.

16. Further, if one were to carefully peruse the

works, which were executed by the p etitioner as a sub-

contractor/contractor, we do not find any major

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…14…

difference in the works so executed, with the “works”

required to be executed. In fact works executed by him in

his capacity as a contractor and sub -contractor are

similar in nature. Therefore, in the absence of any

specific clause in the tender document that work

experience of a contractor gained under the private party

shall not be looked into for the purposes of determining

the eligibility, ignoring the said experience of the present

petitioner, is an arbitrary action of the respondents.

17. Terms and conditions of a tender document

have to be read as they are. Neither of the parties can

either add something or subtract anything therefrom. In

the absence of there being an express rider contained in

the tender document itself, that experience gained by a

contractor with a private body shall not be taken into

consideration or that experience gained by a contractor

as a sub-contractor shall not be taken into consideration,

for the purposes of assessing eligibility, the experience so

gained by a contractor cannot be discarded arbitrarily by

the other party on its whims and fancies.

18. Subject matter of lis is that of civil

construction, including water supply, sewerage, site

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…15…

development, rain water harvesting, approach road,

which we find is similar to the work already executed by

the petitioner with the execution of works, namely open

excavation in roads and barrage and underground

excavation work of head race tunnel with concrete lining

and other allied works.

19. Careful perusal of certificates reproduced

supra (Pages 122, 123 & 124) would reveal that the

major component of the work executed by the contractor

is of concrete; steel re-enforcement; structural steel

works; excavation and removal of s lush; and cement

concrete works.

20. To emphasize on construction of the

agreement making Condition No.19 to be essential, our

attention is invited to the response filed by the State

(Page 152 of the Paper Book), wherein the terms of

PMGSY works bidding docume nt is referred to, which

averment, we extract as under:

“……….Moreover, in the state PWD

works wherever sub -contractor are

allowed/considered to participate in the

bidding process, it is clearly mentioned in the

tender document as in the state PMGSY works

bidding document (clause 4.4A(b) of

Instructions to Bidders (ITB), Section 2) of

which states as under:

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…16…

“Satisfactorily completed, as prime

Contractor or sub-contractor, at least

one similar work equal in value to one-

third one-fourth in case of Naxal/LWE

affected districts) of the estimated cost

of work………….”

Similarly, had it been mentioned in the

bidding document of this work that sub -

contractor can participate in the bidding

process, the bid of the petitioner would have

definitely been allowed/considered…..”

21. We are afraid, such condition cannot be

imported into the contract in question for two reasons –

(a) work sought to be executed is not under PMGSY

Scheme, (b) it is not one of the conditions of the contract.

For proper construction of the contra ct, which is

unambiguously clear, aid cannot be taken that of a totally

separate and a different contract, for had it been the

intent of the Department to create a distinction between

the prime contractor and a sub -contractor, reference

thereof should have been made accordingly.

22. We take support from the decision rendered

by the Hon’ble Supreme Court of India, in M.R. Engineers

and Contractors Private Limited v. Som Datt Builders

Limited, (2009) 7 SCC 696, wherein it is observed as

under:

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…17…

“16. There is a difference between reference to

another document in a contract and incorporation

of another document in a contract, by reference.

In the first case, the parties intend to adopt only

specific portions or part of the referred document

for the purposes of the contract. In the second

case, the parties intend to incorporate the

referred document in entirety, into the contract.

Therefore when there is a reference to a

document in a contract, the court has to consider

whether the reference to the document is with the

intention of incorporating the contents of that

document in entirety into the contract, or with the

intention of adopting or borrowing specific

portions of the said document for application to

the contract.

17. We will give a few instances of incorporation

and mere reference to explain the position

(illustrative and not exhaustive). If a contract

refers to a document and provides that the said

document shall form part and parcel of the

contract, or that all terms and conditions of the

said document shall be read or treated as a part

of the contract, or that the contract will be

governed by the provisions of the said document,

or that the terms and conditions of the said

document shall be incorporated into the contract,

the terms and conditions of the doc ument in

entirety will get bodily lifted and incorporated into

the contract. When there is such incorporation of

the terms and conditions of a document, every

term of such document, (except to the extent it is

inconsistent with any specific provision in the

contract) will apply to the contract. If the

document so incorporated contains a provision for

settlement of disputes by arbitration, the said

arbitration clause also will apply to the contract.

18. On the other hand, where there is only a

reference to a document in a contract in a

particular context, the document will not get

incorporated in entirety into the contract. For

example if a contract provides that the

specifications of the supplies will be as provided in

an earlier contract or another purchas e order,

then it will be necessary to look to that document

only for the limited purpose of ascertainment of

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…18…

specifications of the goods to be supplied. The

referred document cannot be looked into for any

other purpose, say price or payment of price.

Similarly if a contract between X and Y provides

that the terms of payment to Y will be as in the

contract between X and Z, then only the terms of

payment from the contract between X and Z, will

be read as part of the contract between X and Y.

The other terms, say relating to quantity or

delivery cannot be looked into.”

23. By now, it is well settled that normally Courts

do not interfere in the tender/contractual matters, while

exercising its power of judicial review. Petitioner is

required to show – (a) that the authority has acted with

malafide, (b) that the decision is so arbitrary and

irrational that no responsible authority, acting

reasonably, could have arrived at such conclusion, (c)

public interest is involved. (Transfer Case (Civil) Nos.43 of

2015, 64 of 2015, 65 of 2015 (SC), Reliance Telecom Ltd.

& Anr. V. Union of India & Anr., decided on 12.1.2017;

State of Jharkhand v. M/s CWE -SOMA Consortium, AIR

2016 SC 3366; Central Coalfields Limited v. SLL-SML

(Joint Venture Consortium), (2016) 8 SCC 622; Michigan

Rubber (Inida) Limited v. State of Karnataka and others,

(2012) 8 SCC 216; Air India Ltd. v. Cochin Internal Airport

Ltd, (2000) 2 SCC 617; and Tata Cellular v. Union of

India, (1994) 6 SCC 651.

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…19…

24. In Tata Cellular (supra), the apex Court has

observed as under:

“(1) The modem trend points to judicial restraint

in administrative action.

(2) The court does not sit as a court of appeal but

merely reviews the manner in which the decision

was made.

(3) The court does not have the expertise to

correct the administrative decision. If a review of

the administrative decision is permitted it will be

substituting its own decision, without the

necessary expertise which itself may be fallible.

(4) The terms of the invitation to tender cannot be

open to judicial scrutiny because the invitation to

tender is in the realm of contract. Normally

speaking, the decision to accept the tender or

award the contract is reached by process of

negotiations through several tiers. More often

than not, such decisions are made qualitatively by

experts.

(5) The government must have freedom of

contract. In other words, a fair play in the joints is

a necessary concomitant for an administrative

body functioning in an administrative sphere or

quasi-administrative sphere. However, the

decision must not only be tested by the

application of Wednesbury principle of

reasonableness (including its other facts pointed

out above) but must be free from arbitrariness not

affected by bias or actuated by malafides.

(6) Quashing decisions may impose heavy

administrative burden on the administration and

lead to increased and unbudgeted expenditure.

Based on these principles we will examine the

facts of this case since they commend to us as the

correct principles.

25. The principles, so enunciated by the apex

court, stand referred to and relied upon, by this Court in

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…20…

CWP No.9337 of 2013, titled as Ashok Thakur v. State of

Himachal Pradesh & others, decided on 6.5.2014; and

CWP No.359 of 2017, titled as M/s Zenith Event and

Service and another v. State of H.P. and others, decided

on 19.4.2017, the decisions relied upon and referred to

by the learned Advocate General, during the course of

hearing.

26. We clarify that reference of the decisions was

only for inviting our attention to the aforesaid principles.

27. In any case, we have gone through the said

decisions and find them not to have adjudicated or

decided the issue with which we are concerned.

28. Recently, the apex Court in Civil Appeal

No.12065 of 2016, titled as CRRC Corporation Ltd. v.

Metro Link Express for G andhinagar & Ahmedabad

(MEGA) Company Ltd., decided on 15.5.2017, has

observed as under:

“………But where a decision is taken

that is manifestly in consonance with the

language of the tender document or sub -

serves the purpose for which the tender is

floated, the court should follow the principle

of restraint. Technical evaluation or

comparison by the court would be

impermissible. The principle that is applied to

scan and understand an ordinary instrument

relatable to contract in other spheres has to

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…21…

be treated differently than interpreting and

appreciating tender documents relating to

technical works and projects requiring special

skills. The owner should be allowed to carry

out the purpose and there has to be

allowance of free play in the joints.”

29. Also, in Central Coalfields Limited & another

v. SLL-SML (Joint Venture Consortium) & others, (2016) 8

SCC 622, the apex Court observed as under:

“47. The result of this discussion is that the issue

of the acceptance or rejection of a bid or a bidder

should be looked at not only from the point of

view of the unsuccessful party but also from the

point of view of the employer. As held in Ramana

Dayaram Shetty the terms of the NIT cannot be

ignored as being redundant or superfluous. They

must be given a meaning and th e necessary

significance. As pointed out in Tata Cellular there

must be judicial restraint in interfering with

administrative action. Ordinarily, the soundness of

the decision taken by the employer ought not to

be questioned but the decision making process

can certainly be subject to judicial review. The

soundness of the decision may be questioned if it

is irrational or mala fide or intended to favour

someone or a decision "that no responsible

authority acting reasonably and in accordance

with relevant law could have reached" as held in

Jagdish Mandal followed in Michigan Rubber.

48. Therefore, whether a term of the NIT is

essential or not is a decision taken by the

employer which should be respected. Even if the

term is essential, the employer has the inherent

authority to deviate from it provided the deviation

is made applicable to all bidders and potential

bidders as held in Ramana Dayaram Shetty.

However, if the term is held by the employer to be

ancillary or subsidiary, even that decision should

be respected. The lawfulness of that decision can

be questioned on very limited grounds, as

mentioned in the various decisions discussed

above, but the soundness of the decision cannot

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…22…

be questioned, otherwise this Court would be

taking over the function of the tender issuing

authority, which it cannot.”

(Emphasis supplied)

30. The rules of construction of a contract stand

reiterated by the apex Court , though in a case of

Insurance Policy, in Rahee Industries Limited v. Export

Credit Guarantee Corporation of Inida Limited & another,

(2009) 1 SCC 138, as under:

“15. In this case the entire controversy revolves

around interpretation of Clause 16 of the Policy. It

is well-settled rule of construction that words in a

contract (Policy herein) are to be understood in

their ordinary meaning. However, this ordinary

meaning will not prevail in two cases, namely,

where a word has technical or legal meaning and

secondly where the context requires otherwise.”

(Also: United India Insurance Co. Ltd. v.

Pushpalaya Printers, (2004) 3 SCC 694)

31. In Harmony Innovation Shipping Limited v.

Gupta Coal India Limited & another, (2015) 9 SCC 172,

the apex Court observed as under:

“48. …………When the aforesaid stipulations are

read and appreciated in the contextual

perspective, "the presumed intention" of the

parties is clear as crystal that the juridical seat of

arbitration would be London. In this context, a

passage from Mitsubishi Heavy Industries Ltd. v.

Gulf Bank, 1997 1 Lloyd’s Rep 343 is worth

reproducing:

"It is of course both useful and frequently

necessary when construing a clause in a

contract to have regard to the overall

commercial purpose of the contract in the

broad sense of the type and general

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…23…

content, the relationship of the parties and

such common commercial purpose as may

clearly emerge from such an exercise.

However, it does not seem to me to be a

proper approach to the construction of a

default clause in a commercial contract to

seek or purport to elicit some self-contained

'commercial purpose' underlying the clause

which is or may be wider than the ordinary

or usual construction of the words of each

sub-clause will yield."

49. In Cargill International S.A. v. Bangladesh

Sugar & Food Industries Corpn , 1998 1 WLR 461,

Potter, L.J. balanced the two approaches and said

(All ER pp.412h-j&413b):

"….In this connection [counsel] has

rightly made the point that, when

construing the effect of particular words in a

commercial contract, it is wrong to put a

label on the contract in advance and this to

approach the question of construction on

the basis of a pre-conception as to the

contact's intended effect, with the result

that a strained construction is placed on

words, clear in themselves, in order to fit

them within such pre-conception...On the

other hand, modern principles of

construction require the court to have

regard to the commercial background, the

context of the contract ad the

circumstances of the parties, and to

consider whether, against that background

and I that context, to give the words a

particular or restricted meaning would lead

to an apparently unreasonable and unfair

result."

32. In Bharat Aluminium Company v. Kaiser

Aluminium Technical Services Inc., (2016) 4 SCC 126, the

apex Court observed:

“10. In the matter of interpretation, the court has

to make different approaches depending upon the

instrument falling for interpretation. Legislative

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…24…

drafting is made by experts and is subjected to

scrutiny at different stages before it takes final

shape of an Act, Rule or Regulation. There is

another category of drafting by l awmen or

document writers who are professionally qualified

and experienced in the field like drafting deeds,

treaties, settlements in court, etc. And then there

is the third category of documents made by

laymen who have no knowledge of law or

expertise in the field. The legal quality or

perfection of the document is comparatively low

in the third category, high in second and higher in

first. No doubt, in the process of interpretation in

the first category, the courts do make an attempt

to gather the purpose of the legislation, its

context and text. In the second category also, the

text as well as the purpose is certainly important,

and in the third category of documents like wills,

it is simply intention alone of the executor that is

relevant. In the case before us, being a contract

executed between the two parties, the court

cannot adopt an approach for interpreting a

statute. The terms of the contract will have to be

understood in the way the parties wanted and

intended them to be. In that context, particularly

in agreements of arbitration, where party

autonomy is the grundnorm, how the parties

worked out the agreement, is one of the

indicators to decipher the intention, apart from

the plain or grammatical meaning of the

expressions and the use of the expressions at the

proper places in the agreement.

11. Contextually, it may be noted that in the

present case, the respondent had invoked the

provisions of English law for the purpose of the

initiation of the unsettled disputes. It has hence,

while interpreting an agreement, to be kept in

mind that the parties, intended to avoid

impracticable and inconvenient processes and

procedures in working out the agreement. Potter J.

made a similar observation in Cargill International

S.A. v. Bangladesh Sugar and Food Ind ustries

Corporation, 1998 1 WLR 461 (WR p.468):

"As Saville, J. observed in another

context in Palm Shipping Inc. v. Kuwait

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…25…

Petroleum Corpn. , 1988 1 Lloyd’s Rep 500

at 502:

‘….It is not a permissible method of

construction to propound a general or

generally accepted principal ... and then….

to seek to force the provisions of the (the

contract) into the straightjacket of that

principle…..’

On the other hand, modern principles of

construction require the court to have regard to

the commercial background , the context of the

contract and the circumstances of the parties and

to consider whether, against that background and

in that context, to give the words a particular or

restricted meaning would lead to an apparently

unreasonable and unfair result."

(Emphasis supplied)

33. In Vishnu (Dead) by LRs. V. State of

Maharashtra & others, (2014) 1 SCC 516, the apex Court

observed:

“35. Before concluding, we may observe that

circulars issued by the State Government may

provide useful guidance to the authorities

involved in the implementation of the project but

the same are not conclusive of the correct

interpretation of the relevant clauses of the

agreement and, in any case, the Government's

interpretation is not binding on the Courts. In the

result, the appeals are dismissed.”

34. In the instant case, we find the respondents-

authorities to have made redundant the eligibility criteria,

which is impermissible in law to do. The goal post is

sought to be changed, confining eligibility qua limited

persons, thus carving out a class for contractors having

worked only for the Government, which is neither the

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…26…

intent nor the prescription of the tender document. Thus,

the scope of judicial review is certainly within the

parameters laid down by the apex Court.

35. Submission of the learned Advocate General

that the respondents understand the difference between

a prime contractor and a sub-contractor, is not based on

correct interpretation, for the document does not create

any such distinction, more so that of the eligibility clause.

36. Only with the rejection of the technical bid,

petitioner approached this Court, but then, as already

stands clarified, petitioner does not lay any challenge to

the terms of the tender document. It is the mis -

interpretation, resulting into erroneous rejection of the

technical bid, which prompted the contractor to approach

this Court.

37. On 2.5.2017, by way of interim order, this

Court directed the respondents to allow the petitioner to

participate in the financial bid, which however, was

directed to be kept in a sealed cover and that tender be

not allotted to anyone without leave of the Court.

Learned Advocate General clarified that the process of

tender is computerized. In fact, it is an E-Tender. In our

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

High Court of H.P.

…27…

considered, view such fact would not make any

difference. Process of bidding has to relegate back to the

stage of rejection of technical bid(s), both of the

petitioner or anyone else, only on account of

misconstruction of such of the terms of the tender

document.

38. Hence, for all the aforesaid reasons, decision

of the authorities, in rejecting the technical bid of the

petitioner, being illegal, is quashed and as such the

respondents-authorities are directed to consider the

technical bid, as also the financial bid, of the petitioner,

alongwith other bidders, in accordance with law.

In view of the above discussion, present

petition stands disposed of, so also pending

application(s), if any.

( Sanjay Karol ),

Acting Chief Justice

( Ajay Mohan Goel ),

May 26, 2017(sd) Judge.

::: Downloaded on - 08/10/2022 10:21:35 :::CIS

Reference cases

Description

Legal Notes

Add a Note....