As per case facts, the plaintiffs (appellants) sought specific performance of an unregistered agreement, which was dismissed by the trial court. They appealed, arguing the agreement was valid despite their ...
In the High Court at Calcutta
Civil Appellate Jurisdiction
Appellate Side
The Hon’ble Mr. Justice Sabyasachi Bhattacharyya
And
The Hon’ble Mr. Justice Supratim Bhattacharya
F.A.T. No. 209 of 2022
IA No: CAN 3 of 2025
Burhanur Rahaman and Others
-Versus-
Nurul Islam and others
For the appellants : Mr. Gopal Chandra Ghosh, Sr. Adv.,
Mr. Arnab Roy,
Mr. Satyam Mukherjee, ... Advs.
For the respondent nos.1 & 2 : Mr. Pralay Kar,
Ms. Debasree Dhamali,
Ms. Riya Ghosh,
Ms. Debolina Ghosh, … Advs.
For the
respondent nos.2(a) & 2(b) : Mr. Aniruddha Chatterjee, Sr. Adv.,
Mr. Abir Lal Chakraborty, ... Advs.
Heard on : 02.07.2026
Reserved on : 02.07.2026
Judgment on : 08.07.2026
2
Sabyasachi Bhattacharyya, J.:-
1. The present appeal has been filed at the behest of the plaintiffs in a suit for
specific performance of an unregistered agreement dated April 8, 2009,
against the dismissal of the said suit.
2. Learned senior counsel appearing for the appellants contends that although
the plaintiffs/appellants did not sign the agreement -in-question, such
omission does not vitiate the agreement, since it was duly signed by the
vendors/principal respondents and the appellants were all along ready and
willing to perform their part of the contract. Moreover, the appellants, by
filing the suit for specific performance, have also expressed their intention to
have the agreement performed.
3. Learned senior counsel further argues that although it was stipulated in
Clause (2) of the agreement that the purchase shall be completed within
three months from the date of execution of the agreement, the said Clause
was subject to the rider that a good and marketable title is made out and
the vendors make the property free from all encumbrances, claims and
demands. However, the vendors/principal respondents did not hand over to
the purchasers the title deeds, municipal bills and other papers necessary to
ascertain such marketable title. As such, the stipulated period of three
months was not treated by the principal respondents themselves to be the
outer limit of performing the agreement. By not performing their part of the
contract, it is argued, the principal respondents/vendors diluted the time-
3
limit and, as such, it cannot be said that time was the essence of the
contract.
4. Moreover, in their letter dated May 4, 2010 (marked as Exhibit-2 in the suit)
written to the vendors/principal respondents, the appellants asserted that
although the appellants were always ready and willing to pay the balance
consideration amount, the principal respondents did not perform their part
of the contract by supplying the parcha of the present owner, existing
sanction plan and related deeds. No reply was given to the said letter by the
vendors/principal respondents, thereby admitting such allegations. As
such, it should be construed to be an admitted position that only due to the
principal respondents not performing their part of the contract, the deed
could not be executed within the stipulated period of three months pursuant
to the contract.
5. Learned senior counsel for the appellants next contends that Clause (2) of
the agreement contemplated receipts to be issued upon the deeds and other
documents, including municipal bills relating to the subject-property, being
handed over to the appellants. The principal respondents could not produce
any such receipt before the Trial Court. Rather, DW -1, in his cross-
examination, admitted that he had no document to show that the original
deed, khajna receipts, tax receipts and other connected papers relating to
the subject property were delivered to the plaintiffs/appellants.
6. Learned senior counsel further argues that the principal respondents, in
their written objection to the application filed by the plaintiffs/appellants for
amendment of the plaint, admitted that a meeting was held on July, 2010
4
between the plaintiffs, the principal defendants and the proforma defendant,
where the members of the said meeting requested the p rincipal
defendants/respondents to complete the registration of sale deed after
payment of balance consideration, but the principal defendants refused to
do so. Thus, it is evident from the records that an offer was made by the
plaintiffs even after the expiry of the stipulated period of three months and
that the principal defendants/respondents had agreed to a joint meeting to
resolve the issue. Accordingly, it is contended that time was never the
essence of the contract.
7. Learned senior counsel appearing for the appellants further argues that the
plaintiffs/appellants were all along ready and willing to perform their part of
the contract. It is argued that as per the amended Section 16(c) of the
Specific Relief Act, 1963, there is no necessity to plead readiness and
willingness in the plaint. Thus, the said requirement has been diluted by
the Legislature.
8. Furthermore, from Exhibit-2, the notice issued by the plaintiffs on May 4,
2010, it would be evident that the plaintiffs/appellants were ready and
willing to pay the balance consideration amount to have the agreement
performed at all points of time. By choosing not to reply to the said letter,
the principal defendants/respondents tacitly consented to such position.
9. Furthermore, in the written objection to the application for amendment of
plaint, the principal respondents themselves admitted having held a joint
meeting with the plaintiffs for resolution of the dispute regarding
performance of the agreement, where the plaintiffs offered to pay the balance
5
consideration amount but the principal defendants/respondents refused to
accept the same.
10. Thus, the fact that the plaintiffs/appellants were ready and willing to
perform the agreement at all points of time cannot be disputed.
11. Learned senior counsel appearing for the appellants next submits that the
principal defendants/respondents admittedly did not inform the
plaintiffs/appellants about execution of the sale deed in favour of the added
respondents/subsequent purchasers till after execution of the same.
Moreover, in the deed executed by the principal respondents in favour of the
subsequent purchasers, the principal respondents falsely gave out that
there was no prior agreement in respect of the suit property, thereby
suppressing the existence of the subject agreement to the subsequent
purchasers. In the said deed, there is a clause which provides that the
subsequent purchasers may resile from the deed in the event it is found that
any material fact was suppressed or incorrectly stated therein. Thus, the
said transaction is itself vitiated by the aforementioned suppression.
12. That apart, the appellants argue, the subsequent purchasers were fully
aware of the prior agreement between the principal respondents and the
appellants, to cover up which the deed deliberately included the clause of
there being no prior agreement. Hence, by resorting to such falsehood, the
principal respondents and the added respondents now seek to make out a
case that the latter were unaware of the prior agreements, being thus bona
fide purchasers for value without notice, which is contrary to facts.
6
Accordingly, it is submitted that the agreement is fully enforceable against
the subsequent purchasers/added respondents as well.
13. Lastly, learned senior counsel argues that merely because the proforma
respondent (one of the original intending purchasers) subsequently resiled
from the agreement, the agreement cannot be said to have been vitiated on
such count alone. The appellants submit that they had paid the share of
the consideration amount of the proforma responden t to him, which
tantamounts to the proforma respondent assigning his role as an intending
purchaser to the plaintiffs/appellants. It is pointed out that in the
description of parties in the subject agreement, “assigns” of the purchasers
were also included within the definition of “purchasers”. Hence, the learned
Trial Judge ought to have directed specific performance of the agreement in
favour of the appellants, both in their own capacity and in the capacity of
assignees of the proforma respondent.
14. In reply, learned counsel for the principal respondent nos. 1 and 2 argues
that the plaintiffs/appellants were not ready and willing to perform their
part of the contract, which is a sine qua non for grant of a decree of specific
performance, at any relevant point of time.
15. In his cross-examination, DW-1 admitted that he had no document to show
that the plaintiffs/appellants had the balance consideration amount of
Rs.25.50 lakh during the three months immediately following the execution
of the agreement. Thus, even at the relevant juncture, the appellants could
not have performed their part of the agreement by paying the balance
consideration amount as per the agreement. Accordingly, it is argued that
7
the lack of readiness and willingness on the part of the plaintiffs/appellants
debarred them from claiming specific performance of the contract.
16. Secondly, learned counsel for the principal respondents argues that the
agreement-in-question did not contain the signature of the intending
purchasers/appellants, thus rendering the same invalid in the eye of law.
17. Thirdly, in view of the proforma respondent (one the original intending
purchasers) having withdrawn from the agreement, the said agreement, in
its original form, was rendered void and inexecutable. In the event specific
performance was to be granted by the learned Trial Judge, the court would
have to re-write the contract and direct performance of a new contract
without the proforma respondent, which is not permissible in law.
18. That apart, the learned Trial Judge, in the impugned judgment and decree,
directed the earnest money to be returned by the principal respondents to
all the intending purchasers, including the proforma respondent, thus
indicating that the alleged assignment of the rights of the proforma
respondent to the appellants was never recognised by the learned Trial
Judge.
19. In support of his contenting relating to readiness and willingness, learned
counsel for the principal respondents cites Mohammed Khaleel (D) Through
LRs & Ors. Vs. Jayamma [Civil Appeal No. 2187 of 2011], where the Hon’ble
Supreme Court reiterated the principle of readiness and willingness and
observed that the relief of specific performance is one based on equity for
enforcing contractual obligation undertaken by the parties and Section 16(c)
of the Specific Relief Act required the person seeking specific performance to
8
specifically aver and prove his continuous readiness and willingness to
perform his obligations. A failure to satisfy these requirements would
ultimately make him disentitled for the relief of specific performance. The
term ‘readiness’, it was held, refers to the financial capacity, and the term
‘willingness’ reflects the conduct and intention of the party seeking the relief
to perform the contract, and both these conditions cumulatively have to be
seen for making out a case of specific performance. In the present case,
since the appellants failed on both counts, the relief of specific performance
could not be granted in their favour.
20. Learned senior counsel for the added respondents/subsequent purchasers,
while adopting the arguments of the principal respondents, adds that
Section 19(b) of the Specific Relief Act specifically excludes bona fide
purchasers for value without notice from the purview of specific performance
of contracts. It would be evident from the purchase deed of the added
respondents that the principal respondents (vendors therein) clearly stated
in the deed that there was no prior agreement in respect of the subject-
property. Not a single document has been produced by the appellants to
prove that the added respondents had any knowledge of the prior agreement
between the parties. Thus, the relief of specific performance cannot be
granted against the subsequent purchasers. Any prior knowledge of the
agreement on the part of the added respondents has also been denied in
Paragraph No. 9 of the written statement of the added respondent nos.2(a)
and 2(b), it is submitted.
9
21. In support of his contentions, learned senior counsel appearing for the
added respondents cites Maharaj Singh and others v. Karan Singh (dead)
Through Legal Representatives and others, reported at (2024) 8 SCC 83,
where the principle embodied in Section 19(b) was reiterated.
22. Upon hearing learned counsel for the parties, the following issues come up
for consideration in the present appeal:
(i) Whether the subject-agreement was vitiated due to absence of the
signatures of the intending purchasers/appellants;
(ii) Whether time was the essence of the contract; if so, whether the same
debars the claim for specific performance;
(iii) Whether the appellants could prove their readiness and willingness to
perform their part of the contract;
(iv) Whether the unwillingness of the proforma respondent to act in terms of
the agreement operates as a bar to specific performan ce of the
agreement;
(v) Whether the relief of specific performance can be granted in view of
subsequent sale of the subject -property to the added
respondents/subsequent purchasers.
23. The above issues are decided as follows:
10
(i) Whether the subject-agreement was vitiated due to absence of
the signatures of the intending purchasers/appellants
24. From the Agreement dated April 8, 2009 (Exhibit-9), it is evident that the
same contains only the signatures of the intending vendors/principal
respondents; the signatures of the intending purchasers/appellants are
conspicuous by their absence. However, such fact, per se, does not vitiate
the agreement. No law mandates that an agreement, to be binding on one of
the parties thereto, has to mandatorily contain the signature of the other
party. It would suffice that the execution of the agreement is not disputed by
any of the parties and is duly proved by evidence. The question which arises
in the present case is whether the agreement was enforceable against the
intending vendors. Since the same contained the signatures of the principal
respondents/vendors, the agreement is binding on the principal
respondents and, as such, they cannot raise any objection to the binding
effect of the same merely due to absence of the appellants’ signature. In any
event, since the appellants have, although at a belated stage, written to the
principal respondents on May 4, 2010 (Exhibit-2) indicating their intention
to purchase the property and have also filed the suit for specific
performance of the same, by their conduct they have relied on the
agreement. Thus, mere absence of the signature of the appellants on the
agreement does not render the same void, nor vitiated in any manner.
25. Accordingly, this issue is decided in favour of the appellants.
11
(ii) Whether time was the essence of the contract; if so, whether the
same debars the claim for specific performance
26. Clause (2) of the agreement for sale dated April 8, 2009, clearly stipulates
that the purchase shall be completed within months from the d ate of
execution of the agreement, provided a good marketing title is made out and
the vendors and the vendors make the property free from all encumbrances,
claims and demands whatsoever.
27. The appellants have not been able to establish, nor have pleaded that the
principal respondents/intending vendors did not have a good and
marketable title and that the property was not free from encumbrances,
claims and demands. Thus, the stipulation of three months cannot be
diluted on such count. In Clause (3) of the agreement, it is specifically
stipulated that time for the said performance would be deemed to be the
essence of the contract. Hence, the parties intended the stipulated period of
three months to be the essence of the contract.
28. The appellants argue that due to the non-handing over of the deeds and
other papers, including municipal bills, relating to the property by the
respondent nos.1 and 2 to the appellants, which was to be done
simultaneously with the execution of the agreement, the period of three
months stood extended, as the appellants could not ascertain the
marketable title within such period.
29. However, it is to be noted that during the said three months, not a single
communication made by the appellants to the principal respondents has
been brought on record to indicate that the appellants ever raised such
12
objection or intimated the same to the principal respondents during the
stipulated period of three months.
30. In his cross-examination, DW-1 merely admitted that he had no document
to show that the title deeds and other papers relating to the property were
handed over to the appellants. Undoubtedly, Clause (2) of the agreement
envisages accountable receipts for delivery of the deeds and other related
papers, and the principal respondents have failed to produce any such
receipts. However, mere absence of receipts cannot automatically give rise
to the conclusion that the documents were not handed over in reality. In
fact, by their own conduct, the appellants have belied their objection on
such score, since no such objection was raised contemporaneously in that
regard at all. It remains unexplained as to what prevented the appellants
from demanding such documents in the event those were not handed over,
during the stipulated three months from the execution of the agreement.
31. Although Clause (2) of the agreement stipulates that such deeds and other
papers relating to the property were to be delivered by the vendors to the
appellants simultaneously with the execution of the agreement, there was
no default clause, diluting the mandatory period of three months for the
execution of the deed in pursuance of the agreement in the event such
documents were not handed over.
32. The appellants further argue that since the principal respondents did not
reply to the notice dated May 4, 2010 (Exhibit-2), issued by the plaintiffs
alleging that the principal respondents were silent during the relevant period
as to the performance of their part of the agreement, it cannot be overlooked
13
that such post facto notice, issued one year after the expiry of the stipulated
three months from the execution of the agreement dated April 8, 2009,
cannot ipso facto validate the inaction of the appellants during such period.
33. Mere absence of any reply to the said notice by the principal respondents
cannot automatically imply any admission on the part of the principal
respondents as to the contents of the same. The said letter was neither any
affidavit nor any pleadings in a litigation, that the doctrine of non-traverse
would be applicable thereto.
34. The contents of the written objection of the respondent nos. 1 and 2 to the
application for amendment of plaint filed by the appellants do not indicate in
any manner that time was no t the essence of the contract. As per the
averments made therein, much subsequent to the stipulated mandatory
period of three months and even after execution of the sale deed in respect
of the property in favour of the added respondents, a meeting was convened
by well-wishers of the parties. However, such averments do not amount to
an admission that the stipulated time limit for performance of the agreement
was extended; rather, it is categorically averred in the said written objection
that the earnest money was sought to be returned by the principal
respondents after such period, which was refused by the appellants, and
that the principal respondents denied to perform the agreement between the
parties at that juncture. Such post facto developments cannot be construed
to have diluted or extended the mandatory period of three months from the
date of execution of the agreement.
14
35. Hence, this Court comes to the conclusion that as per the terms of the
agreement, time was the essence of the contract and there is nothing on
record to indicate that the parties resiled from such position.
36. Accordingly, the claim for specific performance of the agreement is debarred
on such count alone.
(iii) Whether the appellants could prove their readiness and
willingness to perform their part of the contract
37. The argument of the appellants that post-amendment of Section 16 (c) of the
Specific Relief Act, 1963, no averment is required to be made in respect of
readiness and willingness, does not come to the aid of the appellants. We
say so because even the amended Section 16(c) mandates that the plaintiffs
in a suit for specific performance have to prove their readiness and
willingness. Only the requirement of an averment being made to that effect
in the plaint has been deleted from the statute, but not the necessity to
prove such fact.
38. Coming to the facts of the instant case, PW-1, in his cross-examination,
categorically admitted that he did not have any document to prove that the
appellants were in possession of the balance consideration amount of
Rs.2.50 lakh within the three months following the execution of the
agreement. Thus, the readiness and willingness of the plaintiffs/appellants
at the relevant juncture, when it was most required, was not only not proved
by the appellants, but disproved by such admission of PW-1 in his cross-
examination.
15
39. Learned senior counsel appearing for the appellants submits that the
balance consideration was deposited by the appellants. However, admittedly,
such deposit was made much later, only pursuant to the direction of this
court in connection with the appeal, and nowhere near the relevant period
when it was to be paid.
40. The so-called readiness and willingness of the appellants cannot be said to
be vindicated by the notice dated May 4, 2010 (Exhibit-2), issued about
more than one year after execution of the agreement, and/or the subsequent
attempts at reconciliation under the intervention of common well-wishers of
the parties. Such post facto attempts cannot justify the appellants’ plea that
they have established their readiness and willingness at all material points
of time.
41. As reiterated in Mohammed Khaleel (D) Through LRs (supra)
1
, proof of
readiness and willingness has to be continuous, from the execution of the
agreement till the suit for specific performance is disposed of. ‘Readiness’, as
explained in the said decision, refers primarily to the financial capacity of
the intending purchasers, which was disproved by the evidence of PW 1 and
not established by any cogent evidence whatsoever by the appellants. Even
on ‘willingness’, during the stipulated three months, or even much
thereafter, not a single correspondence or other material evidence has been
brought on record to indicate that the plaintiffs/appellants were even willing
to perform their part of the agreement during the relevant period, when it
1
Mohammed Kh aleel (D) Through LRs & Ors. Vs. Jayamma [Civil Appeal No. 2187 of
2011]
16
mattered most. Exhibit A-series in the suit indicates that the principal
defendants/respondents cancelled the agreement by their letter to the
appellants dated April 15, 2009, after waiting for the stipulated three
months’ period, which was proved to have been served on the appellants.
Even thereafter, the appellants waited till as late as May 4, 2010 to give a
notice to the principal respondents as to their intention to honour the
agreement.
42. Thus, in absence of any contemporaneous proof to show the readiness an d
willingness of the appellants at all points of time, the suit for specific
performance was rightly dismissed on such ground as well by the learned
Trial Judge.
43. This issue, thus, is decided against the appellants.
(iv) Whether the unwillingness of the profor ma respondent to act in
terms of the agreement operates as a bar to specific
performance of the agreement
44. The proforma respondent, one of the original intending purchasers,
subsequently resiled from the said agreement. Thus, the principal
respondents are justified in arguing that the agreement, in its present form,
could not be performed, since a decree for a deed to be executed after the
abstention of the proforma respondent would necessarily mean that the
court would have to re-write the agreement, by directing a sale deed to be
executed by the principal respondents only in respect of the
17
plaintiffs/appellants, without the proforma respondent being a party
thereto.
45. The appellants vociferously argue that the proforma respondent assigned his
part of the agreement to the plaintiffs/appellants, thus bringing the
appellants within the purview of “assigns” which is included in the definition
of “purchasers” in the agreement.
46. However, no material evidence has been brought on record to establish the
fact that the appellants have actually paid the proforma respondent’s share
of the consideration amount/earnest money to him and/or any agreement
between the appellants and the proforma respondent regarding assignment.
In the absence of any proof as to such assignment, fact remains that the
agreement, as it originally stood, could not be performed after the proforma
respondent backed out from the same. Hence, the unwillingness of the
proforma respondents, one of the intending purchasers, to act on the
agreement debars the relief of specific performance of such agreement as it
originally stood.
(v) Whether the relief of specific performance can be granted in
view of subsequent sale of the subject -property to the added
respondents/subsequent purchasers
47. Section 19(b) of the Specific Relief Act, 1963 provides that specific
performance of a contract may be enforced against any other person (than a
party to the agreement) claiming under the parties to the agreement by a
title arising subsequently to the contract. However, the said provision
18
carves out an exception to the same in respect of a transferee for value who
has paid his money in good faith and without notice of the original contract.
48. In the present case, not an iota of evidence has been brought on record by
the appellants to establish that the added respondents/subsequent
purchasers had any knowledge of the prior agreement between the
appellants and the principal respondents at the time of purchase. On the
contrary, in the sale deeds executed in favour of the subsequent purchasers
on September 8, 2010, which has been brought in evidence by the principal
defendants/respondents (Exhibits-C and D), it would be evident that it was
stated in the sale deeds that the subject-property of the sale was not
encumbered by any prior agreement for sale in favour of any third party and
it was denied therein that any earnest money was received by the vendors
(principal respondents) from any third party. Thus, from the very contents
of the transfer deed executed in favour of the added respo ndents, it is
clinched that the subsequent purchasers/added respondent nos.2(a) and
2(b) did not have any knowledge of the prior agreement between the
plaintiffs/appellants and the principal defendants/respondents.
49. The agreement-in-question dated April 8, 2009 is admittedly an unregistered
agreement. Thus, it cannot also be said that the subsequent purchasers had
deemed notice of the same in view of its registration.
50. Accordingly, not only have the appellants failed to prove any prior knowledge
of the subsequent purchasers in respect of the subject-agreement dated
April 8, 2009, such prior knowledge has been disproved by the contents of
the deed executed in favour of the subsequent purchasers.
19
51. As reiterated in Maharaj Singh (supra)
2
, Section 19(b) specifically excludes
the enforcement of contracts by specific performance against bona fide
purchasers for value paid in good faith and without notice of the original
contract. Since the subsequent purchasers/added respondents squarely fall
within such exempted category, the subject-agreement is not specifically
enforceable against them. As the subsequent purchasers are the current
owners of the property, no effective decree can thus be passed in the
appellants’ suit for specific performance of the agreement dated April 8,
2009.
52. Hence, this issue is also held in favour of the respondents and against the
appellants.
CONCLUSION
53. In view of the above findings, this Court does not find any error of law or
fact in the impugned judgment and decree, whereby the learned Trial Judge
refused to grant specific performance of the Agreement dated April 8, 2009,
in favour of the plaintiffs/appellants. For the sake of completeness, we also
take note of the fact that, at best, the remedy of the plaintiffs/appellants
might have lay in damages against the principal respondents for the latter
having transferred the subject-property in favour of the third parties/added
respondents by suppressing the existence of the prior agreement for sale.
However, the said relief is a non -starter, since, in the plaint, the
2
Maharaj Singh and others v. Karan Singh (dead) Through Legal Representatives
and others, reported at (2024) 8 SCC 83
20
plaintiffs/appellants have only claimed made an alternative claim of refund
of their earnest money. Neither any prayer nor any pleading or basis of
claim regarding damages finds place in the plaint. Thus, no relief can be
granted to the plaintiffs/appellants which has not been prayed for by them
in the suit.
54. Even otherwise, it is doubtful as to whether, after expiry of the stipulated
period of three months from the execution of the Agreement dated April 8,
2009, the plaintiffs could have a claim even of damages against the
defendants/respondents as the said agreement no longer operated as an
encumbrance/actionable claim on the subject-property or as a fetter to the
transfer of the same in favour of third parties.
55. Insofar as the suppression of the existence of the prior agreement by the
principal respondents to the subsequent purchasers in the latter’s deed is
concerned, the same, at best, gives rise to a cause of action inter se the
parties to such deed. The appellants cannot, in any manner, claim any
benefit in that regard. The terms of the sale deed in favour of the
subsequent purchasers included an option of the said purchasers to cancel
the deed in the event any suppression by the ir vendors (the principal
respondents) was discovered. As the subsequent purchasers/added
respondents chose to waive such right and went ahead with the transfer in
their favour, it is not for the appellants to claim any advantage on the basis
of the said terms. Also, the appellants would be hit by the doctrine of privity
of contract, not being a party to the transfer deed executed by the principal
respondents in favour of the subsequent purchasers.
21
56. Thus, the only relief which could be granted to the appellants is the refund
of earnest money, as already granted in the impugned judgment and decree.
57. Although not argued by the appellants, we make it abundantly clear that the
appellants could not even claim any interest on the earnest money, from the
initial date of payment of the same, since the appellants have not claimed
any such interest, nor is there any justification to saddle the principal
defendants/respondents with the liability to pay interest for the period from
expiry of three months from the agreement till payment, as they were not at
fault in any manner in refusing to execute the deed in terms of the subject-
agreement after expiry of the stipulated period of three months. The
subsequent purchasers/principal respondents, in any event, cannot be held
liable at all in that regard.
58. The learned Trial Judge, rightly in our opinion, refused the decree of specific
performance and directed refund of the earnest money of Rs.5,00,000/ -
simpliciter, within the period stipulated in the said decree; if not paid within
such period, the same would carry interest at the rate of 7% per annum.
59. However, since the matter was sub-judice in the present appeal, the date of
such refund, if not already paid, is required to be extended.
60. Accordingly, F.A.T. No.209 of 2022 is dismissed on contest, thereby
affirming the impugned judgment and decree dated July 22, 2022 passed by
the learned Civil Judge (Senior Division), First Court at Barasat, District –
North 24 Parganas in Title Suit No.619 of 2010.
61. However, in view of the pendency of the appeal till date, the time for refund
of the earnest money of Rs.5,00,000/ - by the principal
22
defendants/respondents to the plaintiffs/appellants and proforma
defendant/proforma respondent is extended for a period of 60 days from
date, if not already paid.
62. In the event of non-payment of such amount within the said period, the
principal defendants/respondents shall be liable to pay interest at the rate
of 7% per annum on the earnest money to the plaintiffs/appellants and
proforma defendants/proforma respondents , calculated on such amount
from the first day after expiry of 60 days from this date till the date of such
payment.
63. There will be no order as to costs.
64. Accordingly, IA No: CAN 3 of 2025 is also disposed of.
65. Interim orders, if any, stand vacated.
66. A formal decree be drawn up accordingly.
(Sabyasachi Bhattacharyya, J.)
I agree.
(Supratim Bhattacharya, J.)
23
Later:
After the above judgment is passed, it is pointed out by learned
counsel appearing for the appellants that pursuant to an interim order of
this Court, the balance consideration amount had been deposited by the
appellants.
The appellants are permitted to withdraw such amount, subject to
deduction of statutory expenses.
(Supratim Bhattacharya, J.) (Sabyasachi Bhattacharyya, J.)
Legal Notes
Add a Note....