contract law, government law
 18 Feb, 2026
Listen in 02:00 mins | Read in 22:00 mins
EN
HI

Cantonment Board, St. Thomas Mount & Pallavaram Vs. M/S.Babuji Civil Constructions

  Madras High Court Arb.O.P.(Com.Div.) No.693 of 2022
Link copied!

Case Background

As per case facts, the Petitioner invited e-tenders, and after the Respondent's bid was accepted, an agreement was signed, security deposit remitted, and a work order issued. However, the Respondent ...

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Arb.O.P.(Com.Div.) No.693 of 2022

In the High Court of Judicature at Madras

Reserved on:

09.2.2026

Delivered on:

18.2.2026

Coram:

The Honourable Mr.Justice N.ANAND VENKATESH

Arbitration O.P.(Com.Div.) No.693 of 2022

Cantonment Board,

St.Thomas Mount &

Pallavaram, rep.by its

Chief Executive Officer,

Chennai-16 …Petitioner

Vs

M/s.Babuji Civil Constructions,

Rep.by its Proprietor

C.Saravanan, No.50/1,

Bajanai Koil Street,

Mambalapattu, Villupuram.

602309 …Respondent

PETITION under Section 34 of the Arbitration and Conciliation

Act, 1996 praying to set aside the arbitral award in O.P.No.342 of

2020 dated 16.8.2022 passed by the learned Arbitrator and direct the

respondent to bear the costs herein.

For Petitioner : Mr.C.Mohan &

Ms.Rexy Josephine Mary for

M/s.King & Patridge

1/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

For Respondent: Mr.A.K.Sriram, SC for

Mr.K.J.Parthasarathy

ORDER

This petition has been filed under Section 34 of the Arbitration

and Conciliation Act, 1996 (for short, the Act) challenging the award

dated 16.8.2022 passed by the sole Arbitrator.

2. Heard both.

3. The facts leading to filing of this petition are as follows:

(i) The petitioner invited e-tenders dated 24.3.2017 for the work

of maintenance and repairs to miscellaneous and public improvement

during the year 2017-18. The earnest money deposit (EMD) was fixed

as 1% of the estimated cost and the EMD would be returned to the

unsuccessful tenderer. The security deposit of 5% of the contract

value would also be received from the successful tenderer at the time

of award of the contract.

(ii) The respondent/claimant participated in the tender and their

bid was accepted by the petitioner vide letter dated 12.6.2017.

Further, the respondent/claimant was directed to deposit the security

2/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

deposit of Rs.8.5 lakhs and execute an agreement with the petitioner.

The petitioner and the respondent/claimant entered into an agreement

on 29.6.2017 and the respondent/claimant remitted a sum of Rs.8.50

lakhs towards security deposit and the work order was issued to the

respondent/claimant.

(iii) The respondent/claimant had to complete the work on or

before 31.3.2018. It was alleged that the respondent/claimant did not

show any progress in the work and numerous complaints were

received from the public. Hence, a show cause notice came to be

issued by the petitioner to start/speed up the work, failing which, the

respondent company/claimant would be blacklisted and the EMD and

the security deposit would be forfeited. In turn, the respondent/

claimant gave reply and took a stand, which was not agreeable for the

petitioner.

(iv) Ultimately, the petitioner, through letter dated 17.8.2017,

terminated the contract thereby the respondent/claimant was

blacklisted and both the EMD as well as the security deposit were also

forfeited. The respondent/claimant, through letters C.8 to C.10, sought

for refund of the security deposit and thereafter initiated the

arbitration proceedings, pursuant to which, the dispute was referred to

3/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

the sole Arbitrator.

(v) Before the sole Arbitrator, the respondent/claimant filed a

statement of claim seeking for refund of the security deposit of

Rs.8.50 lakhs along with interest.

(vi) Before the sole Arbitrator, the petitioner filed a statement of

defence and took a stand that the respondent/claimant failed to carry

out the work and thereby violated Clause 6 of the agreement, that

there was absolutely no improvement in the work for more than one

month from the date of the contract, that therefore, the petitioner had

no other alternative except to terminate the contract and blacklist the

respondent/claimant and also forfeit the security deposit and that such

forfeiture was enabled in the agreement under Clause 3. Ultimately,

the petitioner sought for dismissal of the statement of claim. The

petitioner also made a counter claim for the loss sustained by them

due to re-tender and increase in costs.

(vii) The sole Arbitrator framed the following issues for

consideration:

“1) Whether the forfeiture of security deposit

of Rs.8,50,000/- by the respondent from the

claimant is tenable and valid in law?

4/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

2) Whether the claimant is entitled for

refund of the security deposit of Rs.8,50,000/- as

per the terms of the contract?

3) Whether the respondent is entitled to the

counter claim of Rs.5,00,000/- for loss and

additional cost incurred by them?

4) Whether the claimant is entitled for

interest from the date of termination till the date of

award at PLR plus 2%?

5) Whether the claimant is entitled for

interest at 18% per annum from the date of award

till the date of actual payment? and

6) Whether the parties are entitled to the

costs of the proceedings before the Arbitral

Tribunal?”

(viii) Both parties did not let in any evidence, but they relied

upon certain documents. The respondent/claimant relied upon C.1 to

C.12 and the petitioner relied upon D.1 to D.3.

(ix) The sole Arbitrator, on considering the facts and

circumstances of the case and on appreciation of evidence, directed

the petitioner to refund the security deposit of Rs.8.50 lakhs with 9%

simple interest from 17.8.2017 till the date of actual payment and

rejected the counter claim made by the petitioner. Aggrieved by that,

the above petition has been filed before this Court.

5/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

4. Learned counsel appearing on behalf of the petitioner

submitted as follows:

(a) The respondent/claimant did not show any progress of work

for more than a month and therefore, a show cause notice was issued

and thereafter, the contract was terminated. The contract itself

provided for forfeiture of the security deposit. It was a pre-estimated

compensation that was fixed in the contract itself and in so far as the

loss sustained by the petitioner was concerned, the respondent/

claimant had quoted at the rate of 55.77% above the Military Engineer

Services Standard Schedule of Rates, 2010 (MES SSR 2010). But,

after termination of the contract, this cost escalated to 68% above the

MES SSR 2010.

(b) Apart from that, considering the fact that the respondent/

claimant did not even commence the work, it was not possible for the

petitioner to demonstrate the actual loss. In view of the same, the

claim made by the respondent/claimant was liable to be rejected and

the counter claim must be ordered in favour of the petitioner.

5. Per contra, the learned Senior Counsel appearing on behalf of

the respondent/claimant submitted as follows:

6/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

(a) The contract was terminated hardly within 30 days from the

date of commencement and the petitioner proceeded to forfeit the

security deposit, which amounted to penalty and therefore, unless the

petitioner proved the loss sustained by them, they would not be

entitled to forfeit the security deposit.

(b) In order to substantiate this submission, he relied upon the

judgment of the Hon’ble Apex Court in Kailash Nath Associates Vs.

Delhi Development Authority [reported in 2015 (4) SCC 136].

(c) The petitioner did not prove any loss or damages suffered by

them by means of examining any witness or filing any documents.

Therefore, they were not entitled to the counter claim made by them.

Accordingly, the learned Senior Counsel sought for dismissal of this

petition.

6. This Court has carefully considered the submissions of the

learned counsel on either side and perused the materials available on

record and more particularly the impugned award.

7. The agreement contemplated completion of work within a

period of one year from the date of issuance of the work order. The

7/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

agreement under Clause 11 also provided that in the event of the work

remaining incomplete or uncommenced for more than 15 days from

the date of issuance of the work order, the petitioner would be at

liberty to terminate or rescind the contract. Clause 15 provided that

where the contract was rescinded, the petitioner would be entitled to

forfeit whole or part of the security deposit.

8. On carefully going through C.4, which was the work order, it

is seen that the nature of works have been defined and that those

works would have to be completed on or before 31.3.2018.

9. The petitioner issued a communication dated 08.8.2017 (C.5)

informing that the respondent/claimant had not even started the work,

that there was absolutely no progress in the work and that several

complaints were received by the petitioner. Hence, the respondent/

claimant was informed that they should commence the work

immediately, failing which, the contract would be cancelled, the

security deposit would be forfeited and the respondent/claimant would

also be blacklisted.

8/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

10. On receipt of the notice, the respondent/claimant gave a

reply dated 14.8.2017 (C.6) informing about the progress of work and

undertaking to complete the work in all respects within the stipulated

agreement time. The petitioner, not being satisfied with the progress

of work made by the respondent/claimant, issued the letter of

termination dated 17.8.2017 (C.7), terminated the agreement with

immediate effect, blacklisted the respondent/claimant and forfeited the

EMD and the security deposit as per the tender conditions.

11. The respondent/claimant, after nearly 8 months, gave a

reply dated 13.4.2018 (C.8) and sought for refund of the security

deposit to the tune of Rs.8.5 lakhs. Thereafter, further

communications were sent by the respondent/claimant and it did not

evoke any response from the petitioner.

12. The sole Arbitrator came to the conclusion that time was

allowed upto 31.3.2018 for completion of work. Clause 3 of the

agreement provided for the forfeiture of security deposit only where

the work remained uncommenced and unfinished after the stipulated

date. The stipulated date in this case is 31.3.2018.

9/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

13. In the case in hand, the contract was terminated much

before the stipulated date and the security deposit was forfeited.

Therefore, a finding was rendered that unless and otherwise the party

complaining proved the loss they suffered, the security deposit could

not be forfeited.

14. Clause 15 provided that where the contract was rescinded in

accordance with any of the conditions of the contract, the petitioner

would be at liberty to forfeit whole or a part of the security deposit

when any penalty or any other amount due from the contractor was

recovered from the security deposit of the contractor.

15. In the case in hand, the contract was terminated within one

month and three days from the date of issuance of the work order.

Therefore, the only question that had to be answered by the sole

Arbitrator was as to whether the petitioner could have forfeited the

entire security deposit in view of the premature termination of the

contract.

10/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

16. It was contended on the side of the petitioner that the

contract could be rescinded where the work remained incomplete or

uncommenced for more than 15 days from the date of issuance of the

work order and that there was no defect in the power vested with the

petitioner to cancel/rescind the contract.

17. The only issue is as to whether it can further lead to

forfeiture of the security deposit.

18. The sole Arbitrator took into consideration the above two

clauses and came to the conclusion that the petitioner was not entitled

to forfeit the security deposit. Thereafter, the sole Arbitrator went into

the issue of proof of loss if such forfeiture of security deposit was in

the nature of penalty. The sole Arbitrator rendered a finding that the

respondent/claimant did not let in any evidence to show that they had

sustained the loss.

19. The learned counsel appearing on behalf of the petitioner

submitted that the respondent/claimant had not challenged the

termination or the blacklisting of the respondent/claimant, that the

11/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

only relief that was sought for was refund of the security deposit and

that therefore, unless the termination was challenged, the

consequences of termination namely forfeiture of the security deposit

could not be challenged.

20. In the considered view of this Court, it is not necessary for

the respondent/claimant to challenge the termination of contract if

they are not inclined and the respondent/claimant will be entitled to

seek for refund of the security deposit if they are satisfied with that

relief.

21. The premature termination of the contract will not

automatically entitle the petitioner to forfeit the entire security

deposit. The Hon’ble Apex Court in the decision in Kailash Nath

Associates made it clear that if the pre-estimated compensation is in

the nature of penalty, the party has to necessarily prove the loss,

failing which, the requirements under Section 74 of the Indian

Contract Act will not be satisfied.

12/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

22. The sole Arbitrator considered all the relevant judgments on

this issue and also took into consideration the fact that the

respondent/claimant did not let in any evidence for sustaining the loss

and therefore, ordered for the refund of the security deposit with

interest. This finding rendered by the sole Arbitrator certainly does not

suffer from any perversity or patent illegality.

23. In so far as the rejection of counter claim was concerned, the

learned counsel appearing on behalf of the petitioner submitted that

the rate submitted by the respondent/claimant was 55.77% above the

MES SSR 2010 whereas at the time of re-tender, the cost escalated to

68% above the MES SSR 2010 and that therefore, the petitioner

certainly sustained the loss.

24. The sole Arbitrator, while dealing with this issue, rendered a

finding that the petitioner had neither let in oral evidence nor any

documentary evidence to prove that they sustained loss. Hence, the

sole Arbitrator refused to award the counter claim sought for by the

petitioner. This finding certainly does not suffer from any perversity or

patent illegality.

13/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

25. Even in so far as the award of interest was concerned, only

9% interest had been awarded from 17.8.2017 till the date of actual

payment and the same is reasonable and does not warrant the

interference of this Court.

26. In the light of the above discussions, this Court does not find

any ground to interfere with the award passed by the sole Arbitrator

dated 16.8.2022 under Section 34 of the Act.

27. Accordingly, the above petition stands dismissed with

costs of Rs.25,000/- (Rupees twenty five thousand only)

payable by the petitioner to the respondent/claimant.

18.2.2026

RS

14/15 https://www.mhc.tn.gov.in/judis

Arb.O.P.(Com.Div.) No.693 of 2022

N.ANAND VENKATESH,J

RS

Arb.O.P.(Com.Div.) No.693 of 2022

18.2.2026

15/15 https://www.mhc.tn.gov.in/judis

Description

Termination vs. Forfeiture: A Judicial Analysis of Section 74 in Cantonment Board vs. M/S Babuji Civil Constructions

In the landmark judgment of Cantonment Board, St. Thomas Mount & Pallavaram Vs. M/S. Babuji Civil Constructions, the Madras High Court provides a definitive clarification on whether the termination of a contract automatically permits the forfeiture of a security deposit. This analysis, now featured on CaseOn, explores the intricate balance between contractual autonomy and statutory limitations under the Indian Contract Act. As a pivotal CaseOn entry, this ruling serves as a vital resource for legal professionals navigating the complexities of arbitration and compensatory damages.

Issue: The Central Questions Before the Court

The primary questions that required judicial determination were:

  • Whether termination of the contract automatically entitled the employer to forfeit the entire security deposit?

  • Whether forfeiture of security deposit, when treated as a penalty, required proof of actual loss under section 74 of the Indian Contract Act, 1872?

  • Whether the arbitral award refund of the security deposit suffered from perversity or patent illegality warranting interference under section 34?

Rule: Statutory Framework and Judicial Precedents

The legal foundation of this case rests on the interplay between contract law and arbitration statutes:

  • Section 74 of the Indian Contract Act, 1872: The court reaffirmed that the forfeiture when operating as a penalty must prove actual loss in terms of Section 74 of the Indian Contract Act, 1872.
  • Section 34 of the Arbitration and Conciliation Act, 1996: While exercising jurisdiction under Section 34 of the Arbitration and Conciliation Act, 1996, the court examined whether a contracting authority could automatically forfeit a security deposit upon termination of a contract.
  • The Kailash Nath Doctrine: The decision was based on the case of Kailash Nath Associates vs. Delhi Development Authority where it was held by the apex court that even where a contract provides for forfeiture, section 74 of the Contract Act mandates proof of loss unless the loss is demonstrably evident.

Analysis: From Tender to Termination

1. Factual Timeline of the Dispute

The dispute arose from an e-tender invited on 24 March 2017 by the petitioner for maintenance and repairs to miscellaneous and public improvement during the year 2017-2018. The security deposit of 5% of the contract value would be received from the successful tenderer at the time of award of the contract. On 12 June 2017, the bid was accepted and the respondent was directed to deposit the security of 8.5 lakhs and execute an agreement, which was entered into on 29 June 2017.

The respondent had to complete the work on or before 31 March 2018; however, it was alleged that the respondent did not show any progress. Consequently, a show cause notice was issued, the respondent company was blacklisted, and the EMD and security deposit were forfeited on 17 August 2017.

2. Arguments and Counterclaims

Before the Arbitral tribunal, the petitioner—Cantonment board—placed heavy reliance on specific contractual clauses:

  • Clause 6: Required the contractor to commence and diligently proceed with work.

  • Clause 3 & 15: Empowered the petitioner to forfeit the security if the work remained uncommenced or unsatisfactory.

  • Counterclaim: The petitioner alleged that re-tendering the work required a higher rate, resulting in financial loss.

The respondent-Contractor contested that forfeiture attracts Section 74 of the Indian Contract Act. They argued that since the termination occurred on 17 August 2017—well before the 31 March 2018 expiry—the petitioner had no right to forfeit the deposit.

Professional Insight: Staying updated on complex timelines and clauses is easier than ever. CaseOn’s 2-minute audio briefs help legal professionals analyze these specific rulings and catch key details like the Section 74 implications while on the go.

3. The Arbitral and Judicial Review

The sole Arbitrator took into consideration the fact that the petitioner did not let in any evidence for sustaining the loss and therefore ordered the refund of the security deposit with an interest of 9% from 17 August 2017 to the date of actual payment.

Upon review, the Madras High Court did not re-examine the contractual controversy but confined itself to testing whether the award suffered from perversity or patent illegality. Finding none, it upheld the award.

Conclusion: Termination is Not Forfeiture

The Madras High Court clarified a crucial principle in contractual jurisprudence: termination of a contract does not grant an automatic right to penal forfeiture without proof of loss. The court solidified that contractual autonomy is not absolute and remains subject to statutory limitations.

Why This Judgment is a Must-Read

  • For Practitioners: The ruling deepens the understanding that even where forfeiture is contractually permitted, it remains subject to the statutory limitation of Section 74. It reinforces a foundational principle of contract enforcement that every well-informed practitioner must internalize.
  • For Law Students: The case bridges theory and reality by demonstrating how Section 74 operates beyond textbooks. It concretely illustrates the distinction between termination and penalty, and shows how arbitral awards are tested under Section 34. The judgment transforms abstract doctrine into practical judicial reasoning.

     


About the Author

Shreya Sharma is a Bsc.llb. student at NLIU Bhopal. This analysis aims to simplify complex judicial pronouncements for the benefit of law students and young professionals. This analysis was curated and formatted by the CaseOn Editorial Team.

Disclaimer: This case study is for educational purposes only and does not constitute legal advice.

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter