construction dispute, contract law, commercial litigation, breach of contract, remedies
0  11 Feb, 2021
Listen in 01:59 mins | Read in 46:05 mins
EN
HI

Chintels India Ltd. Vs. Bhayana Builders Pvt. Ltd.

  Supreme Court Of India Civil Appeal /4028/2020
Link copied!

Case Background

This appeal arises from a certificate issued under Article 133 along with Article 134A of the Indian Constitution by the Delhi High Court in its ruling dated December 4, 2020

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 4028 OF 2020

CHINTELS INDIA LTD. …Appellant

Versus

BHAYANA BUILDERS PVT. LTD. …Respondent

J U D G M E N T

R.F. Nariman, J.

1. This appeal arises out of a certificate issued under Article 133 read with

Article 134A of the Constitution of India by the High Court of Delhi in the

impugned judgment dated 04.12.2020. The question raised in this appeal

is whether a learned single Judge’s order refusing to condone the

Appellant’s delay in filing an application under section 34 of the Arbitration

and Conciliation Act, 1996 (“Arbitration Act, 1996”) is an appealable

order under section 37(1)(c) of the said Act. After considering, in particular,

two judgments of this Court, the High Court held:

“18. We have considered the rival contentions. Though, as

observed by us in the hearing on 5th November, 2020, in view

of BGS SGS Soma JV supra having referred to the grounds

2

under Section 34 in entirety and not confined to Section 34(2)

only, we were inclined to differentiate between a case of return

of an application under Section 34 on the ground of the Court to

which it is presented not having territorial jurisdiction, on the one

hand and rejection of an application under Section 34 on the

ground of having not been filed within the prescribed time, on

the other hand, but in view of the Supreme Court having been

approached against Ramdas Construction Co. supra, expressly

holding an appeal as the one before us, to be not maintainable

under Section 37, and having dismissed the appeal with a

speaking order, though not expressing any opinion on the

maintainability of the appeal, we consider ourselves bound

thereby and hold this appeal to be not maintainable.

19. We may however observe that Section 37(1)(b) also, while

providing for the appealable orders, refers to Section 34 in

entirety and not to Section 34(2); though BGS SGS Soma JV

supra has held that the order which is appealable thereunder is

an order testing the arbitral award on the grounds set out in

Section 34 but in our humble opinion if the intention of the

legislature was to confine the appeals only to grounds under

Section 34(2), nothing prevented them from, instead of referring

to Section 34 generally in Section 37(1)(c), referring only to

Section 34(2). We are of the view that sub-section (3) of Section

34, by use of the words ‘but not thereafter’, as interpreted in

Union of India Vs. Popular Construction Co. (2001) 8 SCC 470,

restricts the power otherwise vested in Court to condone the

delay beyond thirty days, the same also creates a ground of

time bar for refusing to set aside the award and is part of the

self-contained code for setting aside of the award; thus, refusal

to set aside an award on the ground of the said time bar, would

be a refusal within the meaning of Section 37 and appealable

under Section 37. There is also merit in the contention of Mr.

Rajshekhar Rao, Advocate for the appellant that refusal to

condone the delay also entails affirmation of the underlying

order. Mention in this regard may be made of Section 27 of the

Limitation Act, 1963 which, though in the context of suit for

possession of any property, extinguishes the right to property at

the determination of the period prescribed for instituting the suit

for possession thereof. However we need not discuss further

since, as aforesaid, we are bound by the dicta in BGS SGS

Soma JV and Ramdas Construction Co. supra.

3

20. We may also consider another aspect. By reading Section

37 as not permitting an appeal against refusal to condone the

delay in applying for setting aside of the award, the persons

aggrieved by the award are left with no remedy but to approach

the Supreme Court by way of a petition under Article 136 of the

Constitution of India. The refusal to set aside the award may not

necessarily be by the Commercial Division of the High Court but

may also be by the Commercial Courts of the country. No other

remedy would be available to the persons aggrieved by the

award, against the decision of any Commercial Court in the

country refusing to condone the delay in applying for setting

aside of the award, leaving such persons either with the option

of accepting / remaining bound by the award even if having

excellent grounds for setting aside of the same or of

approaching the Supreme Court under Article 136 of the

Constitution of India, thereby putting an avoidable burden on the

Supreme Court which, as per the scheme of the Constitution of

India, was envisaged to hear limited number of matters entailing

constitutional issues and not to hear matters of condonation of

delay. Though undoubtedly the scheme of expediency and

limited judicial intervention is ingrained in the Arbitration Act but

at the same time it cannot be forgotten that the Act nevertheless

provides remedies against the arbitral award and it is felt that to

vest the order, of any Commercial Court in the country refusing

to condone the delay in applying for setting aside of the award,

and which delay can be for varying reasons as diverse as the

social, geographical and economic conditions prevalent in this

country, and not even providing any opportunity to the High

Courts to have a look therein, would be a very harsh outcome.

21. Thus, while dismissing the appeal as not maintainable,

being bound by the dicta of the Supreme Court in BGS SGS

Soma JV and in Ramdas Construction Co. supra, we grant

certificate under Article 133 read with Article 134A of the

Constitution of India to the appellant.”

2. It may be noted that the learned single Judge of the High Court dismissed

the application for condonation of delay in an application filed under

section 34 of the Arbitration Act, 1996 to set aside an award dated

4

03.05.2019 vide its judgment dated 04.06.2020, and consequently

dismissed the section 34 application itself.

3. Shri Rajshekhar Rao, learned Advocate appearing on behalf of the

Appellant, has relied strongly upon the judgment of this Court in Essar

Constructions v. N.P. Rama Krishna Reddy (2000) 6 SCC 94, which

was a judgment delivered under section 39 of the Arbitration Act, 1940.

His argument is that since section 39 of the 1940 Act is in pari materia with

section 37 of the Arbitration Act, 1996, in that an appeal lies where a single

Judge refuses to condone delay, resulting in an order refusing to set aside

an arbitral award, the ratio of Essar Constructions (supra) would apply

on all fours to the same provision contained in section 37. This being so,

he argued that it is clear that refusal to condone delay would result in a

refusal to set aside an award, an appeal against such order being

maintainable under section 37 of the Arbitration Act, 1996. He also

strongly relied upon the judgments of this Court in Chief Engineer of

BPDP/REO Ranchi v. Scoot Wilson Kirpatrick India (P.) Ltd. (2006) 13

SCC 622 and Fuerst Day Lawson Ltd. v. Jindal Exports Ltd. (2011) 8

SCC 333 to buttress his submission that section 39 of the 1940 Act was a

pari materia provision to section 37 of the Arbitration Act, 1996. He then

5

relied upon judgments of the Madhya Pradesh

1

, Bombay

2

, Karnataka

3

,

Delhi

4

and Calcutta

5

High Courts to argue that an order refusing to

condone delay stands on a completely different footing from an order

which condones delay, as the latter order cannot be said to impart any

finality to the proceeding, as, when an order condones delay, it cannot be

said that the court has refused to set aside an award as it may ultimately

set aside the aforesaid award on the grounds mentioned in section 34(2)

of the Arbitration Act, 1996. He further argued that the judgment of the

Allahabad High Court in Union of India v. Radha Krishna Seth and Anr.,

2005 SCC OnLine All 8400 and that of the Bombay High Court in State of

Maharashtra v. Ramdas Construction Co. 2006 (6) Mah. L.J. 678 did

not state the law correctly and ought to be overruled by this Court. He

argued that where a right of appeal is granted by statute, a dismissal on a

preliminary ground is nevertheless a dismissal of the appeal, since it

cannot be heard thereafter. He also argued that a right of appeal, once

1

Bisleri International Pvt. Ltd. and Ors. v. Sun Petpack Jabalpur Pvt. Ltd. and

Anr. 2009 (4) M.P.L.J. 514.

2

E-Square Leisure Pvt. Ltd., Pune v. K.K. Dani Consultants and Engineers Pvt.

Ltd. 2013 (3) Mh.L.J. 24; Jayshri Ginning & Spinning Pvt. Ltd. v. C.A. Galiakotwala

& Company Pvt. Ltd. 2016 SCC OnLine Bom 5067.

3

M/s Crompton Greaves Ltd. v. M/s Annapurna Electronics and Ors. ILR 2015

KAR 4199.

4

Harmanprit Singh Sidhu v. Arcadia Shares & Stock Brokers Pvt. Ltd. (2016) 234

DLT 30.

5

Damodar Valley Corporation v. Sanjay Singh Rathor 2018 SCC OnLine Cal 4014.

6

granted, ought not to be limited by statutory interpretation where the words

used are capable of a wider construction. In particular, referring to the

language of section 37(1)(c) of the Arbitration Act, 1996, he argued that

there must be refusal to set aside an arbitral award “under section 34”,

which includes section 34(3), under which a court may refuse to condone

delay in filing an application under section 34. Coming to the two Supreme

Court judgments referred to in the impugned judgment, it was his

contention that the focus of this Court in BGS SGS Soma JV. v. NHPC

Limited (2020) 4 SCC 234, was on a completely different question,

namely, as to whether an application to set aside an award under section

34 should be returned to the proper court dependent upon where the seat

of arbitration was located. It was only in the course of discussion relatable

to this question that this Court approved certain observations made in the

decision of the Delhi High Court in Harmanprit Singh Sidhu v. Arcadia

Shares and Stock Brokers Pvt. Ltd. 2016 SCC OnLine Del 5383, in

which a learned single Judge of the Delhi High Court allowed an

application for condonation of delay, a Division Bench then holding that an

appeal against such an order was not maintainable under section 37 of

the Arbitration Act, 1996. He contended that it is only in this context that

paragraph 17 of BGS SGS Soma (supra) approved of the observations

made in Harmanprit Singh Sidhu (supra), inasmuch as it cannot be said

that the Court has refused to set aside the award under section 34, as it

7

may yet do so if any of the grounds contained in section 34(2) are made

out. So far as this Court’s order dated 12.04.2017 in State of Maharashtra

and Anr. v. M/s Ramdas Construction Co. and Anr. [C.A. Nos. 5247-

5248 of 2007] is concerned, he argued that this Court did not go into the

maintainability aspect at all, but ultimately dismissed the Civil Appeals on

the ground that the District Judge, Nagpur had held that the period of delay

being beyond four months, the court had no jurisdiction to entertain the

application for condonation of delay or the application on merits under

section 34 of the Arbitration Act, 1996.

4. Shri Mukul Rohatgi, learned Senior Advocate appearing on behalf of the

Respondent, strongly refuted the fact that section 37 of the Arbitration Act,

1996 is in pari materia with section 39 of the 1940 Act. According to him,

section 39 of the 1940 Act is materially different, and concerns itself with

grounds that were made out under section 30 of the said Act, which

grounds were completely different from the grounds that could be made

out under section 34(2) and (2A) of the 1996 Act. Therefore, Shri Rohatgi

argued that section 37 needs to be interpreted on its own terms, and that

consequently, this Court’s judgment in Essar Constructions (supra)

would not be applicable. He relied strongly upon section 5 of the Arbitration

Act, 1996, by which it was statutorily made clear that judicial intervention

is to be minimal in the arbitration process. For this purpose he also relied

upon the Statement of Objects and Reasons for enacting the Arbitration

8

Act, 1996. He then went on to state that section 37 of the Arbitration Act,

1996 in fact carries out this object. He stressed that this object was

reinforced first, by the non-obstante clause contained in section 37(1); and

second, by the fact that the grounds of appeal contained in section 37 are

exhaustive, and makes explicit that an appeal shall lie only from the

following orders “and from no others”. He also stressed the fact that the

word “namely” makes it clear that it is only from the orders set out in

section 37 that an appeal can be filed. He went on to argue that an appeal,

being a creature of statute, has to be read as the statute provides without

expanding any of the words used. According to him, section 37(1)(c) is

clear and without any ambiguity – the expression “under Section 34” has

to be read with the preceding words “setting aside or refusing to set aside

an arbitral award”, and when so read, it is clear that the refusal to set aside

the award can only be on merits and not on some preliminary ground which

would then lead to a refusal to set aside the award. He relied strongly upon

the fact that this Court in BGS SGS Soma (supra) had approved of

Harmanprit Singh Sidhu (supra), and stated exactly this in paragraph 17

thereof. He then strongly relied upon the judgment in Union of India v.

Simplex Infrastructures Ltd. (2017) 14 SCC 225 for the proposition that

whether delay is or is not condoned, the same result ensues – it cannot

be said that by condoning or refusing to condone delay, an arbitral award

either gets or does not get set aside. He ended by saying that in point of

9

fact the Bombay High Court Division Bench judgment in Ramdas

Construction Co. (supra) was the correct enunciation of the law, and that

we should accept this enunciation and overrule the judgments of the other

High Courts.

5. Having heard learned counsel for the parties, it is important to first set out

section 37 of the Arbitration Act, 1996 which is as follows:

“37. Appealable orders.—(1) Notwithstanding anything

contained in any other law for the time being in force, an appeal

shall lie from the following orders (and from no others) to the

Court authorised by law to hear appeals from original decrees

of the Court passing the order, namely:—

(a) refusing to refer the parties to arbitration under section 8;

(b) granting or refusing to grant any measure under section 9;

(c) setting aside or refusing to set aside an arbitral award under

section 34.

(2) Appeal shall also lie to a court from an order of the arbitral

tribunal—

(a) accepting the plea referred to in sub-section (2) or sub-

section

(3) of section 16; or

(b) granting or refusing to grant an interim measure under

section 17.

(3) No second appeal shall lie from an order passed in appeal

under this section, but nothing in this section shall affect or

takeaway any right to appeal to the Supreme Court.”

6. Since we are directly concerned with section 37(1)(c), it is important to

advert to the language of section 34 as well. Section 34(1) reads as

follows:

“34. Application for setting aside arbitral award.— (1)

Recourse to a Court against an arbitral award may be made

10

only by an application for setting aside such award in

accordance with sub-section (2) and sub-section (3).”

7. Section 34(2) and (2A) then sets out the grounds on which an arbitral

award may be set aside. Section 34(3), which again is material for decision

of the question raised in this appeal, reads as follows:

“(3) An application for setting aside may not be made after three

months have elapsed from the date on which the party making

that application had received the arbitral award or, if a request

had been made under section 33, from the date on which that

request had been disposed of by the arbitral tribunal:

Provided that if the Court is satisfied that the applicant was

prevented by sufficient cause from making the application within

the said period of three months it may entertain the application

within a further period of thirty days, but not thereafter.”

8. A reading of section 34(1) would make it clear that an application made to

set aside an award has to be in accordance with both sub-sections (2) and

(3). This would mean that such application would not only have to be within

the limitation period prescribed by sub-section (3), but would then have to

set out grounds under sub-sections (2) and/or (2A) for setting aside such

award. What follows from this is that the application itself must be within

time, and if not within a period of three months, must be accompanied with

an application for condonation of delay, provided it is within a further period

of 30 days, this Court having made it clear that section 5 of the Limitation

Act, 1963 does not apply and that any delay beyond 120 days cannot be

condoned – see State of Himachal Pradesh v. Himachal Techno

Engineers and Anr. (2010) 12 SCC 210 at paragraph 5.

11

9. We now come to section 37(1)(c). It is important to note that the expression

“setting aside or refusing to set aside an arbitral award” does not stand by

itself. The expression has to be read with the expression that follows -

“under section 34”. Section 34 is not limited to grounds being made out

under section 34(2). Obviously, therefore, a literal reading of the provision

would show that a refusal to set aside an arbitral award as delay has not

been condoned under sub-section (3) of section 34 would certainly fall

within section 37(1)(c). The aforesaid reasoning is strengthened by the

fact that under section 37(2)(a), an appeal lies when a plea referred to in

sub-section (2) or (3) of section 16 is accepted. This would show that the

Legislature, when it wished to refer to part of a section, as opposed to the

entire section, did so. Contrasted with the language of section 37(1)(c),

where the expression “under section 34” refers to the entire section and

not to section 34(2) only, the fact that an arbitral award can be refused to

be set aside for refusal to condone delay under section 34(3) gets further

strengthened.

10. In Essar Constructions (supra), a judgment rendered under section 39

of the 1940 Act, this Court was faced with the same question as is raised

in the appeal before us. In order to appreciate the ratio of this judgment, it

is necessary to first set out section 39 of 1940 Act, which reads as under:

“39. Appealable orders:- (1) An appeal shall lie from the

following orders passed under this Act (and from no others) to

12

the Court authorised by law to hear appeals from original

decrees of the Court passing the order:

An order –

(i) superseding an arbitration;

(ii) on an award stated in the form of a special case;

(iii) modifying or correcting an award;

(iv) filing or refusing to file an arbitration agreement;

(v) staying or refusing to stay legal proceedings where there is

an arbitration agreement;

(vi) setting aside or refusing to set aside an award;

Provided that the provisions of this section shall not apply to any

order passed by a Small Cause Court.

(2) No second appeal shall lie from an order passed in appeal

under this section, but nothing in this section shall affect or take

away any right to appeal to the Supreme Court.”

11. The question which the Court was required to answer was set out as

follows:

“5. But was the Civil Judge's order dismissing the respondent's

application under Section 5 at all revisable under Section 115

of the Code or did an appeal lie from it under Section 39 of the

Arbitration Act, 1940? The answer is of moment as the powers

of an appellate court are wider than those available under

Section 115. Section 39(1)(vi) of the Arbitration Act, 1940 says

that an appeal shall lie inter alia from an order “refusing to set

aside an award”.

6. To arrive at a conclusion as to whether the order passed by

the Senior Civil Judge, Kakinada was an order “refusing to set

aside the award”, we have to consider the facts.”

12. After setting out the order of the Senior Civil Judge, who refused to

condone delay in filing an application for setting aside the award, the Court

then held:

13

“11. The outcome of the order in effect was that the prayer for

setting aside the award was refused on the ground of delay.

12. The “effect test” was applied by the High Court of Andhra

Pradesh in Babumiyan & Mastan v. K. Seethayamma [AIR

1985 AP 135] which said:

“In the light of the rulings in G. Gopalaswami v. G.

Navalgaria [AIR 1967 Mad 403] and the decision of the Bench

in CMA No. 612 of 1977 dated 3-4-1978, the legal position may

be enunciated as follows: The order refusing to condone the

delay in filing the claim petition has the effect of finally disposing

of the original petition. Such an order can, therefore, be treated

as an award and hence it is appealable.”

13. Again a Division Bench of the Assam High Court

in Mafizuddin Bhuyan v. Alimuddin Bhuyan [AIR 1950 Ass 191]

has said:

“Whether objections to an award are dismissed on the merits or

they are dismissed on the ground that they are filed beyond

time, the Court by dismissing them in effect refuses to set aside

the award, and an order refusing to set aside an award is clearly

appealable under Section 39.”

14. In some High Courts, no separate application is filed under

Section 5 of the Limitation Act and the prayer for condonation

of delay is included along with the prayers made for substantive

relief. Courts have entertained appeals from an order

dismissing an application on the ground of limitation. Thus,

in State of W.B. v. A. Mondal [AIR 1985 Cal 12 (DB)] where an

application under Section 30 of the Arbitration Act was

dismissed on the ground of limitation, an appeal was

entertained. (See also Damodaran v. Bhaskaran [(1988) 2 KLT

753].)

15. The procedure appears to have been approved by the

Supreme Court in the case of Union of India v. Union

Builders [AIR 1985 Cal 337 (DB)] where on an appeal to the

Supreme Court from an order dismissing an application under

Section 30 on the ground of delay, the appeal was remanded to

the High Court to be disposed of.

14

16. The position should be no different in courts where a

separate application under Section 5 of the Limitation Act is

required to be filed. If the various High Courts' decisions noted

earlier are correct, then the application under Section 5 being

dismissed, the application under Section 30 would

consequently also have to be dismissed although this might be

a mere formality. The end result would be the same.

xxx xxx xxx

21. Section 39(1)(vi) of the Arbitration Act, 1940 does not

indicate the grounds on which the court may refuse to set aside

the award. There is nothing in its language to exclude a refusal

to set aside the award because the application to set aside the

award is barred by limitation. By dismissing the application

albeit under Section 5, the assailability of the award is

concluded as far as the court rejecting the application is

concerned. Ultimately therefore, it is an order passed under

Section 30 of the Arbitration Act though by applying the

provisions of the Limitation Act.”

13. The Court ultimately concluded:

“25. Reading Section 39(1)(vi) and Section 17 together, it would

therefore follow that an application to set aside an award which

is rejected on the ground that it is delayed and that no sufficient

cause has been made out under Section 5 of the Limitation Act

would be an appealable order.”

14. It will be noticed that so far as the present question is involved, section

39(1)(vi) of the 1940 Act is in pari materia to section 37(1)(c) of the

Arbitration Act, 1996. This was in fact held in two of the judgments of this

Court. In Chief Engineer of BPDP/REO Ranchi (supra), this Court when

considering a similar question held as follows:

“5. Section 37(1)(b) of the Act is in pari materia with Section

39(1)(vi) of the Arbitration Act, 1940 (in short “the old Act”). The

provisions in the Acts read as follows:

15

1996 Act

“37. (1) An appeal shall lie from the following orders (and from

no others) to the court authorised by law to hear appeals from

original decrees of the court passing the order, namely—

***

(b) setting aside or refusing to set aside an arbitral award under

Section 34.”

1940 Act

“39. Appealable orders.—(1) An appeal shall lie from the

following orders passed under this Act (and from no others) to

the court authorised by law to hear appeals from original

decrees of the court passing the order:

An order—

***

(vi) setting aside or refusing to set aside an award:”

15. Having so held, this Court then referred to and followed the judgment in

Essar Constructions (supra) and the judgment contained in Union of

India v. Manager, Jain and Associates (2001) 3 SCC 277, ultimately

holding:

“8. The decision in Popular Construction case [(2001) 8 SCC

470] did not deal with specific issues in this case. In that

decision it was held that in respect of “sufficient cause cases”

the provisions of Section 34(3) of the Act which are special

provisions relating to condonation of delay override the general

provisions of Section 5 of the Limitation Act, 1963 (in short “the

Limitation Act”). The position was reiterated in the Western

Builders case [(2006) 6 SCC 239] and also in Fairgrowth

Investments Ltd. v. Custodian [(2004) 11 SCC 472] . There can

be no quarrel with the proposition that Section 5 of the Limitation

Act providing for condonation of delay is excluded by Section

34(3) of the Act.

9. But the question in the instant case is not about the

applicability of Section 5 of the Limitation Act, and the question

really is whether the appeal was maintainable. The High Court

16

did not consider this aspect. The appeal is clearly maintainable.

Therefore, the order of the High Court is set aside. The High

Court shall deal with the matter and examine the respective

stand on merits treating the appeal to be maintainable.”

16. Likewise, in Fuerst Day Lawson Ltd. (supra) this Court held:

“37. These general principles are culled out from the decisions

of this Court rendered under Section 104 CPC and various other

Acts, as noted above. But there is another set of decisions of

this Court on the question under consideration rendered in the

context of Section 39 of the 1940 Act. Section 39 of the erstwhile

Act contained the provision of appeal and provided as follows:

“39.Appealable orders.—(1) An appeal shall lie from the

following orders passed under this Act (and from no others) to

the court authorised by law to hear appeals from original decree

of the court passing the orders:

An order—

(i) superseding an arbitration;

(ii) on an award stated in the form of a special case;

(iii) modifying or correcting an award;

(iv) filing or refusing to file an arbitration agreement;

(v) staying or refusing to stay legal proceedings where there

is an arbitration agreement;

(vi) setting aside or refusing to set aside an award:

Provided that the provisions of this section shall not apply to any

order passed by a Small Cause Court.

(2) No second appeal shall lie from an order passed in appeal

under this section, but nothing in this section shall affect or take

away any right to appeal to the Supreme Court.”

(Insofar as relevant for the present, Section 37 of the 1996 Act,

is very similar to Section 39 of the previous Act as quoted

above.)”

17

17. It then referred to an argument of counsel that there would be no material

difference between the provisions of section 39 of Arbitration Act, 1940

and section 37 of the Arbitration Act, 1996 vis-à-vis section 50 of the 1996

Act, as follows:

“43. Mr Dave, in reply submitted that the words “(and from no

others)” occurring in Section 39 of the 1940 Act and Section 37

of the 1996 Act were actually superfluous and seen, thus, there

would be no material difference between the provisions of

Section 39 of the 1940 Act or Section 37 of the 1996 Act and

Section 50 of the 1996 Act and all the decisions rendered on

Section 39 of the 1940 Act will apply with full force to cases

arising under Section 50 of the 1996 Act.”

18. So far as section 37 of the Arbitration Act, 1996 and section 39 of the

Arbitration Act, 1940 were concerned, this Court agreed with counsel’s

argument, but disagreed with the submission insofar as section 50 of the

1996 Act was concerned, as follows:

“52. Having regard to the grammatical use of brackets or

parentheses, if the words “(and from no others)” occurring in

Section 39 of the 1940 Act or Section 37 of the 1996 Act are

viewed as “an explanation or afterthought” or extra information

separate from the main context, then, there may be some

substance in Mr Dave's submission that the words in

parenthesis are surplusage and in essence the provisions of

Section 39 of the 1940 Act or Section 37 of the 1996 Act are the

same as Section 50 of the 1996 Act. Section 39 of the 1940 Act

says no more and no less than what is stipulated in Section 50

of the 1996 Act. But there may be a different reason to contend

that Section 39 of the 1940 Act or its equivalent Section 37 of

the 1996 Act are fundamentally different from Section 50 of the

1996 Act and hence, the decisions rendered under Section 39

of the 1940 Act may not have any application to the facts arising

under Section 50 of the 1996 Act. But for that we need to take

a look at the basic scheme of the 1996 Act and its relevant

provisions.”

18

19. The reasoning in Essar Constructions (supra) commends itself to us,

being on a pari materia provision to that contained in section 37(1)(c) of

the Arbitration Act, 1996. We may only add that the reasoning of the

aforesaid judgment is further strengthened by our analysis of the additional

words “under section 34” which occur in section 37(1)(c), and which are

absent in section 39(1)(vi) [the pari materia provision to section 34 of the

Arbitration Act, 1996 being section 30 of the Arbitration Act, 1940].

20. In point of fact, the “effect doctrine” referred to in Essar Constructions

(supra) is statutorily inbuilt in section 37 of the Arbitration Act, 1996 itself.

For this purpose, it is necessary to refer to sections 37(1)(a) and 37(2)(a).

So far as section 37(1)(a) is concerned, where a party is referred to

arbitration under section 8, no appeal lies. This is for the reason that the

effect of such order is that the parties must go to arbitration, it being left to

the learned Arbitrator to decide preliminary points under section 16 of the

Act, which then become the subject matter of appeal under section

37(2)(a) or the subject matter of grounds to set aside under section 34 an

arbitral award ultimately made, depending upon whether the preliminary

points are accepted or rejected by the arbitrator. It is also important to note

that an order refusing to refer parties to arbitration under section 8 may be

made on a prima facie finding that no valid arbitration agreement exists,

or on the ground that the original arbitration agreement, or a duly certified

19

copy thereof is not annexed to the application under section 8. In either

case, i.e. whether the preliminary ground for moving the court under

section 8 is not made out either by not annexing the original arbitration

agreement, or a duly certified copy, or on merits – the court finding that

prima facie no valid agreement exists – an appeal lies under section

37(1)(a).

21. Likewise, under section 37(2)(a), where a preliminary ground of the

arbitrator not having the jurisdiction to continue with the proceedings is

made out, an appeal lies under the said provision, as such determination

is final in nature as it brings the arbitral proceedings to an end. However,

if the converse is held by the learned arbitrator, then as the proceedings

before the arbitrator are then to carry on, and the aforesaid decision on

the preliminary ground is amenable to challenge under section 34 after the

award is made, no appeal is provided. This is made clear by section 16(5)

and (6) of the Arbitration Act, 1996 which read as follows:

“16. Competence of arbitral tribunal to rule on its

jurisdiction.—

xxx xxx xxx

(5) The arbitral tribunal shall decide on a plea referred to in sub-

section (2) or sub-section (3) and, where the arbitral tribunal

takes a decision rejecting the plea, continue with the arbitral

proceedings and make an arbitral award.

(6) A party aggrieved by such an arbitral award may make an

application for setting aside such an arbitral award in

accordance with section 34.”

20

22. Given the fact that the “effect doctrine” is part and parcel of the statutory

provision for appeal under section 37, and the express language of section

37(1)(c), it is difficult to accede to the argument of Shri Rohatgi.

23. We now come to the judgment in Simplex Infrastructures Ltd. (supra).

In this judgment, what was argued before this Court is set out with

reference to the Division Bench judgment under appeal as follows:

“11. The Division Bench of the High Court, however, made a

fine distinction by holding that the judgment of the learned

Single Judge of condoning delay in filing of the petition under

Section 34 of the Act was without jurisdiction and not in terms

of the provisions of the Act. It is not possible to countenance this

approach. The Division Bench, in our opinion, was not right in

observing that the decision in Tanusree Art Printers [Tanusree

Art Printers v. Rabindra Nath Pal, 2000 SCC OnLine Cal 217]

being of a Special Bench of three Judges of the same court,

was binding, in spite of having noticed the decision of this Court

in Fuerst Day Lawson Ltd. [Fuerst Day Lawson Ltd. v. Jindal

Exports Ltd., (2011) 8 SCC 333] — which is directly on the point

and was pressed into service by the appellant. Neither the

Division Bench of the High Court of Calcutta which dealt

with Modi Korea Telecommunication Ltd. [Modi Korea

Telecommunication Ltd. v. Appcon Consultants (P) Ltd., 1999

SCC OnLine Cal 19] nor the three-Judge Bench which

decided Tanusree Art Printers, had the benefit of the judgment

of this Court in Fuerst Day Lawson Ltd., which is later in time.”

24. In stating that the Division Bench was wrong, as a judgment of a single

Judge condoning delay in the filing of a petition under section 34 cannot

be said to be without jurisdiction, the Court then held:

“12… On a bare reading of this provision, it is noticed that the

remedy of the appeal has been provided only against an order

of setting aside or refusing to set aside an arbitral award under

Section 34. No appeal is provided against an order passed by

21

the court of competent jurisdiction condoning the delay in filing

the petition under Section 34 of the Act as such. The Division

Bench in the impugned judgment, therefore, rightly noted that

remedy of appeal against the impugned order of the learned

Single Judge was not otherwise available under Section 37 of

the Act.

13. In our opinion, the issue is squarely answered against the

respondent by the decision of this Court in Fuerst Day Lawson

Ltd. [Fuerst Day Lawson Ltd. v. Jindal Exports Ltd., (2011) 8

SCC 333] In that, the judgment of the learned Single Judge

dated 27-4-2016 [Union of India v. Simplex Infrastructures Ltd.,

2016 SCC OnLine Cal 12045], was passed on an application

purported to be under Section 34(3) of the Act, for condoning

delay in filing of the petition for setting aside the arbitral award.

Hence, the remedy of letters patent appeal against that decision

is unavailable. The question as to whether the learned Single

Judge had rightly exercised the discretion or otherwise, could

be assailed by the respondent before this Court by way of

special leave petition. But, certainly not by way of a letters

patent appeal under Clause 15. For, even if the learned Single

Judge may have committed manifest error or wrongly decided

the application for condonation of delay, that judgment is

ascribable to exercise of jurisdiction under Section 34(3) of the

Act. In other words, whether the prayer for condonation of delay

can be accepted or whether the application deserves to be

rejected, is a matter well within the jurisdiction of that court.”

25. This judgment does not in any manner militate against what has been held

by us. In answer to the question as to whether a single Judge’s judgment

condoning delay in filing an application under section 34 was without

jurisdiction, this Court correctly held that such an order is in exercise of

jurisdiction conferred by the statute. This judgment therefore cannot be

said to be an authority for the proposition that, as the converse position to

the facts contained in the present appeal before us has been held to be

not appealable, it must follow that even where delay is not condoned, the

22

same position obtains. This would fly in the face of the reasoning

contained in this judgment, as well as the reasoning contained in Essar

Constructions (supra), which has commended itself to us.

26. We now come to this Court’s judgment in BGS SGS Soma (supra). As

correctly pointed out by Shri Rao, the question before this Court in BGS

SGS Soma (supra) was a completely different one, being set out in

paragraph 1 of the judgment as follows:

“1. Leave granted. Three appeals before us raise questions as

to maintainability of appeals under Section 37 of the Arbitration

and Conciliation Act, 1996 (hereinafter referred to as “the

Arbitration Act, 1996”), and, given the arbitration clause in these

proceedings, whether the “seat” of the arbitration proceedings

is New Delhi or Faridabad, consequent upon which a petition

under Section 34 of the Arbitration Act, 1996 may be filed

dependent on where the seat of arbitration is located.”

27. In answering this question, the Court first went into the interplay between

section 37 of the Arbitration Act, 1996 and section 13 of the Commercial

Courts Act, 2015, holding that section 37 of the Arbitration Act alone

provides grounds for appeal, section 13(1) of the Commercial Courts Act

providing the procedure thereof. In the course of discussion, this Court

then referred to a judgment of the Delhi High Court as follows:

“16. Shri Chowdhury also referred to another Delhi High Court

judgment reported as Harmanprit Singh Sidhu v. Arcadia

Shares & Stock Brokers (P) Ltd. [(2016) 234 DLT 30], in which

a learned Single Judge of the Delhi High Court allowed an

application for condonation of delay in filing a Section 34

petition. The Division Bench, in holding that an appeal against

such an order would not be maintainable under Section 37 of

23

the Arbitration Act, 1996, read with the Commercial Courts Act,

2015 held:

“10. Coming to Section 37(1), it is evident that an appeal can lie

from only the orders specified in clauses (a), (b) or (c). In other

words, an appeal under Section 37 would only be maintainable

against (a) an order refusing to refer the parties to arbitration

under Section 8 of the A&C Act; (b) an order granting or refusing

to grant any measure under Section 9 of the A&C Act; or (c) an

order setting aside or refusing to set aside an arbitral award

under Section 34 of the A&C Act. The impugned order [Arcadia

Shares & Stock Brokers (P) Ltd. v. Harmanprit Singh Sidhu,

2016 SCC OnLine Del 6625] is clearly not relatable to Section

8 or 9 of the A&C Act. It was sought to be contended by the

learned counsel for the appellant that the present appeal would

fall within Section 37(1)(c) which relates to an order “setting

aside” or “refusing to set aside” an arbitral award under Section

34. We are unable to accept this proposition. By virtue of the

impugned order, the arbitral award dated 10-9-2013 has not

been set aside. Nor has the court, at this stage, refused to set

aside the said arbitral award under Section 34 of the A&C Act.

In fact, the appellant in whose favour the award has been made,

would only be aggrieved if the award were to have been set

aside in whole or in part. That has not happened. What the

learned single Judge has done is to have condoned the delay

in re-filing of the petition under Section 34. This has not, in any

way, impacted the award.”

17. The reasoning in this judgment in Harmanprit Singh

Sidhu commends itself to us, as a distinction is made between

judgments which either set aside, or refuse to set aside, an

arbitral award after the court applies its mind to Section 34 of

the Arbitration Act, 1996, as against preliminary orders of

condonation of delay, which do not in any way impact the

arbitral award that has been assailed.”

28. It is well settled that judgments are not to be construed like Euclid’s

theorems (see Amar Nath Om Prakash v. State of Punjab (1985) 1 SCC

345), but all observations made therein must relate to the context in which

they were made. In that case, the Court put it thus:

24

“10. There is one other significant sentence in Sreenivasa

General Traders v. State of A.P [(1983) 4 SCC 353] with which

we must express our agreement, it was said:

“With utmost respect, these observations of the learned Judge

are not to be read as Euclid's theorems, nor as provisions of a

statute. These observations must be read in the context in which

they appear.”

We consider it proper to say, as we have already said in other

cases, that judgments of courts are not to be construed as

statutes. To interpret words, phrases and provisions of a statute,

it may become necessary for Judges to embark into lengthy

discussions but the discussion is meant to explain and not to

define. Judges interpret statutes, they do not interpret

judgments. They interpret words of statutes; their words are not

to be interpreted as statutes.

In London Graving Dock Co. Ltd. v. Horton [1951 AC 737, 761]

Lord MacDermott observed:

“The matter cannot, of course, be settled merely by treating

the ipsissima verba of Willes, J., as though they were part of an

Act of Parliament and applying the rules of interpretation

appropriate thereto. This is not to detract from the great weight

to be given to the language actually used by that most

distinguished Judge....

In Home Office v. Dorset Yacht Co. Ltd. [(1970) 2 All ER 294]

Lord Reid said:

“Lord Atkin's speech [Donoghue v. Stevension, 1932 All ER

Rep 1, 11] ... is not to be treated as if it was a statutory definition.

It will require qualification in new circumstances.”

Megarry, J. in (1971) 1 WLR 1062 observed:

“One must not, of course, construe even a reserved judgment

of even Russell, L.J. as if it were an Act of Parliament.”

And, in Herrington v. British Railways Board [1972 AC 877

(HL)] Lord Morris said:

25

“There is always peril in treating the words of a speech or a

judgment as though they were words in a legislative enactment,

and it is to be remembered that judicial utterances are made in

the setting of the facts of a particular case.”

11. There are a few other observations in Kewal Krishan Puri

case [(1980) 1 SCC 416] to which apply with the same force all

that we have said above. It is needless to repeat the oft-quoted

truism of Lord Halsbury that a case is only an authority for what

it actually decides and not for what may seem to follow logically

from it.”

29. The context in which paragraph 17 of BGS SGS Soma (supra) was made,

was a context in which an application under section 34 would have to be

returned to the Court which had jurisdiction to decide a section 34

application, dependent upon where the seat of the arbitral tribunal was

located. In this context, it was held that a mere preliminary step, which did

not lead to the application being rejected finally, cannot be characterised

as an order which would result in the application’s fate being sealed once

and for all. The Court’s focus was not on the language of section 37(1)(c),

nor were any arguments addressed as to its correct interpretation. As a

matter of fact, Harmanprit Singh Sidhu (supra) itself went on to hold:

“13. In sum, the impugned order does not fall within the category

of appealable orders specified in Section 37(1) of the A&C Act.

Therefore, even if the provisions of Section 37(1) are read with

Section 13 of the Commercial Courts Act, the present appeal is

not maintainable. This, however, does not mean that the

appellant cannot take up the ground that is sought to be urged

before us if the decision in OMP 294/2014 (under Section 34 of

the A&C Act) goes against him. In other words, if the arbitral

award is set aside in part or in whole and the appellant is

aggrieved thereby, he may prefer an appeal under Section 37

of the A&C Act on merits as also on the ground that the delay in

26

re-filing ought not to have been condoned. This is in line with

the scheme of the A&C Act of not, in any way, stalling the

proceedings thereunder. For example, under Section 13(4) of

the A&C Act, if a challenge to an arbitrator is not successful, the

arbitral tribunal is required to continue the arbitral proceedings

and make an arbitral award and, in such an instance, as

provided in Section 13(5) of the A&C Act, the party challenging

the arbitrator may make an application for setting aside such an

arbitral award in accordance with Section 34. In other words,

recourse to a remedy for an unsuccessful challenge to an

arbitrator is deferred till the stage of the making of the award.

Similarly, under Section 16, an arbitral tribunal may rule on its

jurisdiction. In a case where the arbitral tribunal rejects a plea

with regard to its jurisdiction, it is enjoined by Section 16(5) of

the A&C Act to continue with the arbitral proceedings and to

make the arbitral award. Section 16(6) stipulates that a party

aggrieved by such an arbitral award may make an application

for setting aside the award in accordance with Section 34. Here,

too, the unsuccessful party, who challenges the jurisdiction of

an arbitral tribunal, is asked to wait till the award is made. The

remedy of questioning the decision of the arbitral tribunal with

regard to the arbitrator's jurisdiction in such a case is not

extinguished but is merely deferred till the making of the arbitral

award. In similar vein, in the present case, the remedy of

challenging the decision of condoning the delay in re-filing is not

extinguished but is deferred till the final decision of the court on

the pending Section 34 petition.”

30. Obviously therefore, an observation of this Court torn out of its context

cannot be said to conclude the issue that is now before us.

31. We now come to the sheet anchor of Shri Rohatgi’s case, namely,

Ramdas Construction Co. (supra). In this judgment, a Division Bench of

the Bombay High Court held:

“9. Sub-section (3) of section 34 of the Act provides that an

application for setting aside may be made after three months

have elapsed from the date on which the party making such

application had received the arbitral award or, if a request had

been made under section 33, from the date on which that

27

request had been disposed of by the arbitral tribunal, provided

that if the Court is satisfied that the applicant was prevented by

sufficient cause from making the application within the said

period of three months, it may entertain the application within a

further period of thirty days, but not thereafter. This provision of

law expressly reveals that the legislature has provided a specific

period of limitation for filing an application for setting aside of

the award and simultaneously the Court has been given

discretion to extend such period only by thirty days, and not

beyond the said period of thirty days. The provision is very clear

in that regard. However, the scope of enquiry under sub-section

(3) is restricted to the cause for delay in filing the application but

it does not relate to the merits of the application for setting aside

of the award. Being so, an order which is to be passed in

exercise of powers under sub-section (3) of section 34 of the

Act cannot extend to the subject matter of the application for

setting aside of the award but has to restrict to the aspect of

delay in filing such application only. Such an order is not

contemplated to be an appealable order within the meaning of

the said expression under section 37 of the Act. It is very clear

from the fact that section 37 refers to the orders dealing with the

aspect of setting aside or refusing to set aside an arbitral award.

It does not refer to the proceedings preceding the enquiry in

relation to the issue of setting aside or refusing to set aside an

arbitral award. The subject-matter of delay in filing an

application and the condonation thereof relates to the

proceedings preceding the enquiry for setting aside or refusing

to set aside an arbitral award. Once it is clear that section

37(1)(b) does not contemplate any order passed in such

proceeding relating to the matter preceding the enquiry in

relation to setting aside or refusing to set aside an arbitral

award, such an order cannot be considered as an appealable

order within the meaning of the said expression under section

37 of the Act.

10. Undoubtedly the impugned order while rejecting the

application for condonation of delay, clearly observes:

“Consequently, application under section 34 of the Arbitration

and Conciliation Act, 1996 for setting aside the award is also

rejected being barred by time.”

28

In other words, the Court has not dealt with the application for

setting aside of the award on merits and the same has been

disposed of solely as a consequence of rejection of the

application for condonation of delay and there has been no

enquiry as regards the rights of the parties on the issue of

setting aside of the award. The appealable order which is

contemplated for the purpose of exercise of appellate

jurisdiction is the one which deals with the merits of the case in

relation to the claim for setting aside or refusing to set aside an

arbitral award. As already stated above, the appellate powers

under section 37 are not in relation to the proceedings which

precedes the enquiry regarding setting aside or refusing to set

aside an arbitral award. Being so, the consequence of the order

of dismissal of the application for condonation of delay cannot

itself amount to an appealable order under section 34(1) for the

purpose of appeal under section 37(1) of the Act.”

32. This judgment cannot be said to state the law correctly as it does not

advert to the decision of this Court in Essar Constructions (supra), and

is against the interpretation of section 37(1)(c) of the Arbitration Act, 1996

given by us above. We may also add that this Court, in dismissing the Civil

Appeal against the aforesaid judgment, held:

“1. The appellants before this Court, in the first instance,

impugned the award rendered by the Chief Engineer on

30.06.2005, by preferring an appeal before the District Judge,

Nagpur. The District Judge, Nagpur, declined to entertain the

appeal on merits, as he found the same barred by limitation, and

as such, the application for condonation of delay was dismissed.

The District Judge, Nagpur in his order dated 23.12.2005

recorded as under:

“17. In nut-shell, what emerges from the material placed on the

record is that the applicants or in other words, party making

application under Section 34 duly received the award on

4.7.2005, but approached this Court on 18.11.2005. Time in

between 4.7.2005 and 18.11.2005 was consumed in taking

administrative decision. Beyond statutory period of limitation of

three months, further period of thirty days can be condoned, but

29

not thereafter. On 4.11.2005, entire period of four months

elapsed. In this view of the matter, this Court has no jurisdiction

to entertain the application for condonation of delay and for that

matter, application under Section 34 of the Act.”

2. The order dated 23.12.2005 was assailed by the appellants

before the High Court. Having remained unsuccessful, the

appellants have approached this Court. The primary issue, that

emerges for consideration is, whether the dismissal of the

application filed by the appellants under Section 34 of the

Arbitration and Conciliation Act, 1996 (hereinafter referred to as

the 'Arbitration Act'), by the District Judge, Nagpur, was justified

in law.

3. So far as the issue in hand is concerned, having heard

learned counsel for the rival parties, we are satisfied that on an

earlier occasion, the same proposition came up for

consideration before this Court, and stands declared by this

Court in State of Himachal Pradesh vs. Himachal Techno

Engineers (2010) 12 SCC 210. In view of the legal position

declared by this Court, on the subject of limitation under Section

34 of the Arbitration Act, we are of the view, that the order

passed by the District Judge, Nagpur, calls for no interference.”

33. The order of this Court does not in any manner touch upon the reasoning

of the Bombay High Court. On the contrary, this court refers to the

judgment of this Court in Himachal Pradesh Techno Engineers (supra),

which as has been held by us hereinabove, makes it clear that Section 5

of the Limitation Act is excluded by section 34(3) of the Arbitration Act,

1996 and that no condonation of delay can take place beyond the period

of 120 days. It is on this ground, citing the learned District Judge’s order,

that this Court did not interfere. Consequently, it cannot be said that this

Court approved of the judgment of the Division Bench of the Bombay High

Court. Likewise, the reasoning contained in Radha Krishna Seth (supra),

30

does not commend itself to us. Both these judgments therefore do not

state the law correctly and stand overruled.

34. Shri Rohatgi referred to the Statement of Objects and Reasons of the

Arbitration Act, 1996 and in particular clause 4(v), which reads as follows:

“4. Main objects of the Bill are as under:

xxx xxx xxx

(v) to minimise the supervisory role of courts in the arbitral

process;”

35. Shri Rohatgi then read section 5 of the Arbitration Act, 1996 to us.

According to him, in furtherance of this object, section 37 was enacted

giving a limited right of appeal. He argued that an appeal, being a creature

of statute should not, therefore, be enlarged beyond what is provided by

the Legislature. Section 5 of the Arbitration and Conciliation Act reads as

follows:

“5. Extent of judicial intervention.—Notwithstanding anything

contained in any other law for the time being in force, in matters

governed by this Part, no judicial authority shall intervene

except where so provided in this Part.”

36. This section does not take Shri Rohatgi’s argument much further, as after

the non-obstante clause, the section states that no judicial authority shall

intervene “except where so provided in this Part”. What is “provided in this

part” is section 37, which therefore brings us back to square one.

Undoubtedly, a limited right of appeal is given under section 37 of the

Arbitration Act, 1996. But it is not the province or duty of this Court to

31

further limit such right by excluding appeals which are in fact provided for,

given the language of the provision as interpreted by us hereinabove.

Thus, this last argument also has no legs on which to stand.

37. Consequently, the question of law is answered by stating that an appeal

under section 37(1)(c) of the Arbitration Act, 1996 would be maintainable

against an order refusing to condone delay in filing an application under

section 34 of the Arbitration Act, 1996 to set aside an award.

38. The appeal is accordingly allowed. The impugned judgment of the Division

Bench under appeal is set aside, and the matter is remitted to a Division

Bench of the High Court of Delhi to decide whether the Single Judge’s

refusal to condone delay is or is not correct.

39. The appeal is allowed in the aforesaid terms. All pending applications are

disposed of.

…………………..………………J.

(R. F. Nariman)

……………..……………………J.

(Navin Sinha)

……………..……………………J.

(K.M. Joseph)

New Delhi,

11

th

February, 2021.

Reference cases

Description

Legal Notes

Add a Note....