As per case facts, Petitioners, engaged in importing duty-free raw materials and exporting finished goods under Advance Authorisation Licences, were found to have diverted the imported materials to the domestic ...
W.P.(C) 5796/2025 Page 1 of 22
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 19.08.2026
Judgment pronounced on: 07.09.2026
Judgment uploaded on: 07.09.2026
# CNR No. DHC010260632025
+ W.P.(C) 5796/2025 & CM APPL. 26401/2025
GKEM INTERNATIONAL PVT LTD & ORS. ....Petitioner
Through: Mr. Deepak Gandhi and Ms.
Ida Bhatnagar, Advs.
versus
COMMISSIONER OF CUSTOMS ICD PPG AND OTHERS
ICDS .....Respondent
Through: Mr. Arjun Malik, SSC along
with Ms. Mayuri Makhija, Adv.
for R-1.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MS. JUSTICE SHAIL JAIN
J U D G M E N T
ANIL KSHETARPAL , J.
1. By way of the present Petition, the Petitioners seek declaration
of the Show Cause Notice (SCN) dated 24.06.2022, as non-est in view
of Section 28(9) of the Customs Act, 1962 [hereinafter referred to as
„Act of 1962‟]. Additionally, in the aforesaid backdrop, the Petitioners
also pray for recall of the Order-in-Original (OIO) dated 29.11.2024,
inasmuch as the Impugned SCN upon which it came to be premised
was beyond the prescribed period of limitation. It is not in dispute that
the Petitioners have an alternate remedy of Appeal against the
Impugned OIO. However, it is claimed that the OIO was passed
beyond the permissible period, hence, this Court should quash the
same in exercise of its writ jurisdiction.
W.P.(C) 5796/2025 Page 2 of 22
A. BRIEF FACTUAL BACKGROUND
2. The Petitioners herein are engaged in the business of importing
duty free raw materials, in form of Electorlytic Copper Rods and
exporting the same after value addition, i.e., by manufacturing Copper
Wire/Power Cables. To carry out the aforesaid business, Petitioner
Nos.1 and 2 availed duty-free import benefits under Advance
Authorisation Licences (AAL) issued by Director General of Foreign
Trade (DGFT) under Notification No. 18/2015-Cus dated 01.04.2015
[hereinafter referred to as „Notification 2015‟].
3. In pursuance thereof, the Petitioner No.2 was issued four such
licences between 16.12.2019 and 03.06.2020, while Petitioner No.1
was issued five licences between 12.03.2020 and 19.08.2020. In
accordance with the terms of AAL, the raw material had to be
imported within one year of the license, and the furnished goods
manufactured therefrom had to be exported within eighteen (18)
months of import. Additionally, the importers were also to execute a
bond in favour of the President of India, by which it undertook to
fulfil the Export Obligation (EO) and furnish proof of the same within
thirty days of expiry of the Export Obligation Period (EOP).
Genesis of the dispute
4. The genesis of the present dispute arises out of information
being received by the Customs Preventive Commissionerate, Delhi.
Following which an investigation was conducted, and it was revealed
that the Petitioner Nos.1 and 2, instead of manufacturing and
exporting the finished goods as mandated under the AAL, diverted the
W.P.(C) 5796/2025 Page 3 of 22
duty-free imported raw material into the domestic market, in the guise
of job work, without fulfilling the stipulated EO. The said action of
the Petitioners was treated as being violative of condition (x), the
actual user condition, of Notification 2015.
5. During the course of investigation, it was further revealed that
the firms to which the goods were purportedly sent for job work
existed only on paper. Moreover, as per statements recorded under
Section 108 of the Act of 1962 during investigation, it was admitted
that the imported materials had not been used for manufacture of
export goods and as such the EO had not been fulfilled.
6. It is on the basis of the aforestated that the Impugned SCN
came to be issued against the Petitioners, calling upon them to show
cause under Section 28(4) read with Section 28AAA of the Act of
1962, with reference to Notification No.96/2009-Cus dated
11.09.2009 and Notification 2015, as to why differential customs duty
of Rs. 11,11,45,550/- (against Petitioner No.1) and Rs.9,06,17,303/-
(against Petitioner No.2), cumulatively about Rs. 20.18 crore should
not be demanded/recovered, together with applicable interest, in terms
of the bonds executed by them.
Prior litigation before this Court
7. Notably, prior to the issuance of Impugned SCN, the Petitioner
Nos.1 and 2, through Petitioner No.3 had approached this Court on
two occasions in connection with the same AAL and the underlying
EO.
W.P.(C) 5796/2025 Page 4 of 22
8. The first Petition bearing No. W.P.(C) 3686/2021 captioned
Rajesh Gupta & Ors. v DGFT, was filed seeking directions to the
DGFT to permit the Petitioners to complete their EO by purchasing
additional copper of the same grade from the open market, and to
extend the time limit of the licences granted to them. However, the
same came to dismissed as withdrawn by Order dated 23.03.2021,
while granting liberty to make a representation before the DGFT, with
a direction to DGFT to consider and decide the same within 45 days.
9. Following the aforesaid Order, the Petitioners herein filed
representations dated 07.04.2021 and 12.04.2021. In the interregnum,
the Petitioners filed W.P.(C) 5756/2021 captioned Rajesh Gupta &
Ors. v DGFT, seeking extension of EOP by a further period of twelve
(12) months on account of the COVID-19 pandemic and the resultant
force majeure circumstances; a restraint on coercive recovery of
customs duty under Section 2.54 of Foreign Trade Policy (FTP)
during the extended period; permission to make good any shortfall in
raw material by procuring copper from the open market at their own
cost; and parity with the relaxations granted by the Government in
respect of statutory and contractual obligations during the pandemic
and lockdown.
10. This Court by way of its Order dated 03.06.2021, recorded that
the DGFT shall not initiate any coercive action against the Petitioners
until the final decision is rendered in this regard. Subsequently, the
DGFT rejected the representations made by the Petitioners by way of
its Order dated 23.06.2021. Following which, the said Petition was
also dismissed on 08.12.2023, while noting that the DGFT had duly
W.P.(C) 5796/2025 Page 5 of 22
considered and disposed of the Petitioners‟ representations in
accordance with the applicable provisions of the FTP and Handbook
of Procedures.
11. Additionally, it was also noted that the request to procure
copper from the domestic market to make good the shortfall was
rightly rejected in view of the “Actual User” condition governing
AAL. The Court further held that, in exercise of jurisdiction under
Article 226 of the Constitution, it was concerned with the decision-
making process and not with re-appreciation of the merits of the
decision. Finding the decision-making process fair and no violation of
the applicable statutory or policy provisions, the Court declined to
interfere with the DGFT Order dated 23.06.2021.
12. In the intervening period of 12.07.2023 till passing of Impugned
OIO dated 29.11.2024, the adjudication proceedings before the
Respondent proceeded as follows. On 12.07.2023, the Petitioners were
informed of a 08-month extension purportedly granted by the Chief
Commissioner under the first proviso to Section 28(9) of the Act of
1962 and were granted a personal hearing on 31.07.2023. At the
subsequent hearing on 16.08.2023, the Petitioners sought deferment of
proceedings on account of pendency of W.P.(C) 5756/2021 and the
Interim Order dated 03.06.2021 passed by this Court. Consequently,
on 18.08.2023, the Impugned SCN was transferred to the call book
under Section 28(9A)(b) of the Act of 1962.
13. However, upon dismissal of W.P.(C) 5756/2021, the
proceedings came to be revived culminating into the Impugned OIO,
whereby the Adjudicating Authority (AA) confirmed the proposed
W.P.(C) 5796/2025 Page 6 of 22
demand of differential customs duty of Rs.11,11,45,550/- against
Petitioner No.1 and Rs.9,06,17,303/- against Petitioner No.2, together
with applicable interest, under Sections 28(4), 28AA and 28AAA of
the Act of 1962. Aggrieved thereby, the Petitioners filed written
representations dated 11.02.2025 before the AA, seeking recall of the
order, inter alia, on the ground that the Impugned SCN had become
non-est and the adjudication proceedings were barred by limitation
under Sections 28(9) and 28(9A) of the Act of 1962.
14. It is against the above factual backdrop that the Petitioners have
approached this Court seeking our indulgence.
B. SUBMISSION ON BEHALF OF THE PARTIES
15. Before proceeding to deal with the arguments advanced by the
learned counsel representing the Parties, we deem it appropriate to
note that no arguments were advanced by learned counsel representing
the Petitioner on the merits of case. The challenge in the present
Petition, rests solely upon the question of limitation/delayed
adjudication undertaken by the AA under Section 28(9) read with
Section 28(9A) of the Act of 1962.
16. Learned counsel representing the Petitioners has made the
following submissions:
16.1 It is argued that as per Section 28(9)(b) of the Act of 1962, the
Impugned SCN dated 24.06.2022 was required to be adjudicated
within one year, i.e. by 24.06.2023. However, no determination or
notice of personal hearing was made by the AA, with the first such
communication having been issued only on 12.07.2023.
W.P.(C) 5796/2025 Page 7 of 22
16.2 It is contended that the eight (08) months extension granted
under the first proviso to Section 28(9) of the Act of 1962, was itself
invalid, no opportunity of hearing was afforded to them, and no
reasons were recorded for the failure of the proper officer to
adjudicate within the prescribed period. It is urged that, in any event,
even assuming the extension to be valid, the extended period expired
on 24.02.2024, whereas the Impugned OIO was passed only on
29.11.2024.
16.3 Further, it is argued that the transfer of the Impugned SCN to
the Call Book on 18.08.2023 did not suspend or extend the statutory
period, as the Petitioners were neither duly intimated of such transfer
in terms of Para 9.4 of Master Circular No. 1053/02/2017-CX dated
10.03.2017 [hereinafter referred to as „Circular of 2017‟] nor
furnished the reasons for non-determination as contemplated under
Section 28(9A) of the Act of 1962. Consequently, the period from
18.08.2023 to 08.12.2023 could not be excluded in computing
limitation.
16.4 In support of his submissions, reliance has been placed on State
of Punjab v. Bhatinda District Coop. Milk P. Union Ltd.
1
, to argue
that limitation goes to the jurisdiction of the authority and may be
examined in writ proceedings notwithstanding an alternate remedy.
16.5 Further, reliance has also been placed on Shri Ram Agro
Chemical Pvt. Ltd. v. Union of India & Ors.
2
and Vos Technologies
1
(2007) 11 SCR
2
2019 SCC OnLine P&H 4918
W.P.(C) 5796/2025 Page 8 of 22
Private Limited v. Principal Additional Director General
3
to argue
that an extension under Section 28(9) of the Act of 1962 must be
preceded by disclosure of reasons for the delay and an opportunity of
hearing, and the extension must be duly communicated; failure to
comply with the statutory requirements, including those under Section
28(9A) of the Act of 1962, renders the proceedings time-barred.
17. Per contra, learned counsel representing the Respondents have
made the following submissions:
17.1 At the outset, a preliminary objection as to the maintainability
of the present Petition, has been raised. It is argued that in view of the
efficacious alternate remedy of appeal under the Customs Act, 1962,
and on account of lack of any argument pertaining to error of law or
jurisdiction, no interference is warranted by this Court.
17.2. Learned counsel, on merits, has argued that the diversion of
duty-free imported raw material to the domestic market without
fulfilling the EO under the AAL and in breach of the actual-user
condition under Notification 2015, stands admitted in the statements
recorded under Section 108 of the Act of 1962.
17.3 It is contended that the Interim Order dated 03.06.2021,
restraining coercive recovery, was in force prior to issuance of the
Impugned SCN dated 24.06.2022. Consequently, by virtue of Sections
28(9A)(a) and (b) of the Act of 1962, the proceedings were liable to
be placed in the Call Book from inception, and no separate intimation
of extension was necessary, particularly when the pendency of the
3
2024 SCC OnLine Del 8756
W.P.(C) 5796/2025 Page 9 of 22
writ petition and the interim order were brought to the Department‟s
notice by the Petitioners‟ counsel only on 16.08.2023.
17.4 It is further argued that in terms of Section 28(9A) of the Act of
1962, the period prescribed under Section 28(9) commenced only
upon cessation of the reason for non-determination, i.e. on
08.12.2023, when W.P.(C) 5756/2021 was dismissed. Therefore, the
Impugned OIO dated 29.11.2024 was, within the permissible period
ending on 07.12.2024.
17.5 It is argued that despite being afforded repeated opportunities of
hearing on 25.07.2023, 16.08.2023, 13.09.2024, 15.10.2024 and
04.11.2024, the Petitioners either failed to appear or sought
adjournments on the above-mentioned dates. Accordingly, the delay
cannot be attributed to the Respondent, in order to challenge the
Adjudication proceedings undertaken.
17.6 Reliance is placed on Collector of Central Excise, New Delhi
v. Bhagsons Paint Industry (India)
4
, Commissioner, GST, Central
Excise, Commissionerate-II, Chandigarh v. Swati Menthol and
Allied Chemicals Ltd.
5
, and CCE v. M/s Gujarat Ambuja Exports
Ltd.
6
, to contend that delay by itself does not necessarily bar
adjudication and, where no specific limitation applies, the question of
reasonable time must be determined having regard to the facts of each
case.
C. ANALYSIS AND FINDINGS:
4
2003 (158) E.L.T. 129 (S.C.)
5
2023 (385) E.L.T. 642 (S.C.)
6
(2016) 15 SCC 208
W.P.(C) 5796/2025 Page 10 of 22
18. Before proceeding to examine the controversy before us, we
deem it appropriate to reproduce the relevant provisions of the Act of
1962 forming basis of our analysis, which reads as under:
“28. Recovery of duties not levied or not paid or short-levied or
short-paid or erroneously refunded.—
(9) The proper officer shall determine the amount of duty or interest
under sub-section (8),—
(a) within six months from the date of notice, in respect of cases
falling under clause (a) of sub-section (1);
(b) within one year from the date of notice, in respect of cases
falling under sub-section (4):
[Provided that where the proper officer fails to so determine within the
specified period, any officer senior in rank to the proper officer may,
having regard to the circumstances under which the proper officer was
prevented from determining the amount of duty or interest under sub-
section (8), extend the period specified in clause (a) to a further period of
six months and the period specified in clause (b) to a further period of
one year:
Provided further that where the proper officer fails to determine within
such extended period, such proceeding shall be deemed to have
concluded as if no notice had been issued.]
(9-A) Notwithstanding anything contained in sub-section (9), where the
proper officer is unable to determine the amount of duty or interest under
sub-section (8) for the reason that—
(a) an appeal in a similar matter of the same person or any other
person is pending before the Appellate Tribunal or the High Court
or the Supreme Court; or
(b) an interim order of stay has been issued by the Appellate
Tribunal or the High Court or the Supreme Court; or
(c) the Board has, in a similar matter, issued specific direction or
order to keep such matter pending; or
(d) the Settlement Commission has admitted an application made
by the person concerned,
the proper officer shall inform the person concerned the reason for non-
determination of the amount of duty or interest under sub-section (8) and
in such case, the time specified in sub-section (9) shall apply not from the
date of notice, but from the date when such reason ceases to exist.]”
W.P.(C) 5796/2025 Page 11 of 22
19. At the outset, it is necessary to delineate that the present
Petition raises a challenge to the Impugned OIO principally, and in
substance exclusively, on the ground that the same came to be passed
beyond the period prescribed under Sections 28(9) and 28(9A) Act of
1962, and is, therefore, without jurisdiction. Significantly, the
Petitioners do not assail the substantive findings recorded by the AA
under Sections 28(4), 28AA or 28AAA of the Act of 1962. They have
neither disputed, on merits, the allegations concerning diversion of
duty-free imported material, non-fulfilment of EOs, or breach of the
conditions governing the Advance Authorisations, nor have they
identified any specific factual or evidentiary error in the OIO.
20. The same position emerges from the representation dated
11.02.2025 seeking recall of the Impugned OIO, which is directed
substantially towards limitation, the validity of the extension granted
under the statutory framework and the transfer of the proceedings to
the Call Book. Therefore, the controversy before us, is a narrow one
and principally concerns whether the Impugned OIO was rendered
beyond the statutory period so as to suffer from want of jurisdiction.
21. Before examining the statutory computation, we must highlight
that during the course of arguments, learned counsel representing the
Petitioners, has sought to place reliance upon Supreme Court‟s Order
dated 02.05.2025 passed in SLP(C) No. 5392/2025 captioned Union
of India & Ors. v. GMR Airport Infrastructure Ltd. Relying upon
this Order, the Petitioners have sought deferment of the present
proceedings in view of the following direction issued:
W.P.(C) 5796/2025 Page 12 of 22
“7. According to Mr. N. Venkataraman, the impugned judgment and
order passed by the High Court of Delhi needs to be suspended from
its operation as the same is creating lot of problems for the Revenue.
8. He pointed out that almost 250 matters came to be disposed of
by the Tribunal following the judgment of the High Court of Delhi.
9. Since we are looking into the larger issues involved in this matter,
we may only say that if any matter comes up for hearing before the
Tribunal or any of the High Courts on the subject in question, the
hearing may be deferred till we take an appropriate call in the
matter.
10. List the matter after Summer Vacation.”
22. However, we may also highlight that in its written pleadings,
the Petitioners have sought to rely upon the judgment of this Court in
Vos Technologies (Supra), which is a subject matter of consideration
before the Supreme Court in GMR Airport (Supra), and it was in
furtherance of this consideration that the Order dated 02.05.2025 came
to be passed. In view thereof, we shall now proceed to examine the lis
adjudicated by this Court in Vos Technologies (Supra), to cull out as
to whether the said judgment, and by extension the Order of the
Supreme Court, will be applicable to facts and circumstances,
requiring deferment of the present proceedings.
23. This Court in Vos Technologies (Supra), was dealing with a
batch of Petitions arising out of delayed adjudication in matters
pertaining to the Act of 1962 and Central Goods and Services Tax,
2017. It is in this backdrop that this Court recorded the principal
ground that arose before it, which is as follows:
“2. The principal ground of attack is the inordinate delay in the
finalisation of the adjudication proceedings with the writ petitioners
contending that the failure on the part of the respondents to conclude
adjudication within a reasonable period of time and inordinately
delaying the same for decades together would constitute a sufficient
ground to annul those proceedings. They would contend that the
W.P.(C) 5796/2025 Page 13 of 22
principles of a ‘reasonable period’ which courts have propounded in
connection with an adjudicatory function conferred upon an authority
would apply and the impugned SCNs’ and orders are liable to be
quashed on this short score alone.”
24. The aforestated makes it evident that the Court was concerned
with the application of the principle of a “reasonable period” to
adjudicatory proceedings which had remained pending for an
inordinately long duration. Since the dispute before us arises out of
Act of 1962, we shall proceed to examine the above-stated judgment
in this limited sense.
25. In substance, the Court therein was confronted with SCNs
which had remained dormant for approximately 15 to 18 years,
followed by repeated and mechanical transfers to the Call Book
without contemporaneous reasons being recorded or communicated to
the noticees. The Court found that such prolonged and unexplained
inaction defeated the legislative object of expeditious adjudication and
effectively converted the Call Book into a mechanism for indefinite
and unaccountable suspension of proceedings.
26. It is against the aforesaid factual backdrop that the Court
examined Section 28 of the Act of 1962. However, the factual
substratum of Vos Technologies (Supra) is materially distinct from
that arising in the present case inasmuch as the Impugned SCN, came
to be issued subsequent to the Finance Act, 2018, which brought
substantial changes to Section 28(9) of the Act of 1962. The
amendment deleted the expression „where it is possible to do so‟,
introduced second proviso to sub-section (9), incorporating a deeming
consequence where adjudication is not completed within the
W.P.(C) 5796/2025 Page 14 of 22
prescribed period, and inserted sub-section (9A), specifically
providing for circumstances in which determination under sub-section
(8) cannot be completed for reasons enumerated therein.
27. On the contrary, the SCNs considered in Vos Technologies
(Supra) had been issued prior to 29.03.2018 and, by virtue of
Explanation 4 to Section 28, continued to be governed by the
unamended Section 28(9) of the Act of 1962, meaning thereby the
2018 amendment did not itself govern the timeline applicable to those
proceedings. Consequently, the decision rested upon the ‘reasonable
period’ principle applicable under the earlier statutory regime,
coupled with the Respondents‟ failure to justify mechanical and
repeated transfers to the call book without recorded reasons or
communication to the noticees.
28. It is for these reasons that the findings in Vos Technologies
(Supra), cannot be said to govern the present proceedings so as to
warrant deferment thereof in terms of the Supreme Court‟s order dated
02.05.2025. It is also relevant to note that the deferment of
proceedings directed by the Supreme Court was occasioned by the fact
that nearly 250 matters had been disposed of by the Tribunal by
placing reliance upon Vos Technologies (Supra). It was in this limited
factual backdrop that the direction of deferment came to be issued.
Having already distinguished the said judgment on the facts and
circumstances arising in the present case, we find no reason to defer
the present proceedings merely on the strength of the aforesaid
direction.
W.P.(C) 5796/2025 Page 15 of 22
29. Turning now to the statutory timeline applicable to the facts of
the present case, it is noted that the Impugned SCN came to be issued
on 24.06.2022 under Section 28(4) of the Act of 1962. Since the
proceedings fall under sub-section (4), the applicable timeline under
Section 28(9) is that prescribed by clause (b) thereof, namely, one (01)
year from the date of notice, extendable by a further period of one (01)
year under the First Proviso. An extension of eight (08) months
granted by the Competent Authority under the First Proviso to Section
28(9) was communicated to the Petitioners vide letter dated
12.07.2023. Accordingly, absent the operation of Section 28(9A), the
proceedings were required to be concluded, as extended, by
24.06.2024.
30. However, the subsequent course of events assumes
determinative significance, since in the intervening period, the
Petitioners themselves, by way of a written reply dated 14.08.2023,
sought deferment of adjudication on account of pendency of W.P.(C)
5756/2021 before this Court and the interim Order dated 03.06.2021
operating therein, whereby the Respondent Department had been
directed to refrain from taking any coercive action. In the said reply,
the Petitioners expressly reserved their right to furnish a detailed reply
upon disposal of the said writ petition. Pursuant thereto, the
proceedings were transferred to the Call Book on 18.08.2023.
31. The Petitioners contend that such transfer neither suspended nor
extended the statutory period, since they were not separately intimated
of the Call Book transfer in terms of paragraph 9.4 of Circular of
2017, nor furnished the reasons for non-determination contemplated
W.P.(C) 5796/2025 Page 16 of 22
under Section 28(9A) of the Act of 1962. Consequently, it is urged
that the period from 18.08.2023 to 08.12.2023 must be counted for
limitation. However, this submission proceeds upon a conflation of
the administrative act of transferring a matter to the Call Book with
the statutory consequence flowing from Section 28(9A) of the Act of
1962.
32. Since the proceedings at this stage are found to be governed by
Section 28(9A) of the Act of 1962, we shall now proceed to examine
the requirements of the said provision, in order to determine whether
the timeline prescribed under the statutory regime was duly adhered to
by the Respondents.
33. Section 28(9A) is a non-obstante provision, dealing with two
facets. Firstly, it addresses a situation where the proper officer is
unable to determine the amount of duty or interest under sub-section
(8) for any of the reasons enumerated in clauses (a) to (d). Secondly,
where such a circumstance arises, the reasons for non-determination
are to be communicated to the person concerned, and the period
prescribed under sub-section (9) is to be reckoned from the date on
which the relevant circumstance ceases to exist. Therefore, the
provision does not, make the Call Book transfer itself the source of
any extension; rather, the statutory consequence flows from the
existence of the circumstance contemplated hereinabove.
34. In the present case, the circumstance contemplated under clause
(b) of Section 28(9A) of the Act of 1962 is squarely attracted,
inasmuch as the issue forming the subject matter of W.P.(C)
5756/2021, namely, Petitioners‟ request for extension of EOP, and
W.P.(C) 5796/2025 Page 17 of 22
permission to procure copper from the open market in substitution of
the duty-free imported inputs, was directly germane to the
adjudication, since the Petitioners‟ liability to differential duty was,
inter alia, dependent upon compliance with the conditions governing
the relevant AAL. As a consequence, the pendency of the said writ
proceedings, coupled with the interim protection operating therein,
constituted the circumstance which prevented the proper officer from
proceeding to a final determination under Section 28(8) of the Act of
1962.
35. Thus, the Call Book entry of 18.08.2023 was merely
consequential to the circumstance already placed before the AA by the
Petitioners themselves. The Call Book was not the source of the
statutory exclusion; it was the administrative manifestation of the fact
that the adjudication could not, at that stage, appropriately proceed.
Therefore, the legal consequence must be traced to Section 28(9A) of
the Act of 1962 and not to the mere fact of transfer to the Call Book.
36. In these circumstances, the Petitioners‟ reliance upon the
Paragraph 9.4 Circular of 2017 does not lead to a different conclusion.
The Circular only regulates the administrative manner in which
matters transferred to the Call Book are to be dealt with and is
intended to secure transparency and accountability. However, absent
an express statutory consequence making such communication a
condition precedent to the operation of Section 28(9A), an
administrative instruction cannot override or displace the statutory
consequence which follows upon the existence of a circumstance
expressly contemplated by the Legislature.
W.P.(C) 5796/2025 Page 18 of 22
37. The requirement of communication under Section 28(9A) of the
Act of 1962 must, however, also be considered in the cumulative
factual matrix arising in the present controversy. That requirement, in
its terms, casts an obligation upon the proper officer to inform the
person concerned of the reason for non-determination, its legislative
purpose being to ensure that the noticee is not left unaware of the
circumstance which has prevented determination under Section 28(8)
of the Act of 1962. In the ordinary case, formal intimation by the
proper officer would be necessary to discharge this obligation.
38. However, in the present case, this requirement stands
substantially satisfied, and indeed its underlying purpose stands fully
served, since it was the Petitioners themselves who brought to the
notice of the Respondents the pendency of W.P.(C) 5756/2021 and the
interim order passed therein and identified that circumstance as the
very ground for seeking deferment. Therefore, the Petitioners were,
fully cognisant of the circumstance which impeded the AA from
proceeding with the determination, more so than would ordinarily
follow from a formal communication issued by the officer.
39. Having themselves relied upon the pendency of the said
proceedings and the protection operating thereunder, the Petitioners
cannot be considered to have been unaware of the same. Therefore,
this is not a case of literal compliance with the communication
requirement in the sense of intimation issuing from the proper officer;
it is a case where the object of that requirement stands independently
and fully achieved by the noticee‟s own conduct.
W.P.(C) 5796/2025 Page 19 of 22
40. The position would undoubtedly be different where the
Department sought to rely upon an undisclosed circumstance or where
proceedings were kept dormant for years without the noticee being
apprised of the reason for such inaction. That, however, is not the case
before us. The circumstance relied upon by the Respondents was
neither subsequently devised nor retrospectively invoked; it was the
very circumstance expressly pleaded and relied upon by the
Petitioners themselves. Therefore, it is the underlying statutory
circumstance, and not the administrative fact of Call Book transfer,
which governs the computation.
41. In the present case, the circumstance falling within clause (b)
ceased to exist on 08.12.2023, when W.P.(C) 5756/2021 came to be
dismissed by this Court. Consequently, it is from 08.12.2023 that the
02 years statutory period contemplated under sub-section (9) is
required to be reckoned.
42. On such computation, the base period of one year under clause
(b) of Section 28(9) of the Act of 1962 would have expired on
08.12.2024. Since the Impugned OIO came to be passed on
29.11.2024, within this unextended base period, it is unnecessary for
us to examine whether, or on what basis, the extension earlier granted
under the First Proviso would attach to the freshly reckoned period
commencing 08.12.2023. The time during which the proceedings
remained impeded by the circumstance contemplated under clause (b)
of Section 28(9A) could not, in any event, be reckoned against the
Respondents. The statutory clock, properly computed, commenced
only upon cessation of that circumstance on 08.12.2023; accordingly,
W.P.(C) 5796/2025 Page 20 of 22
the Impugned OIO was passed within the period prescribed by law,
and the Petitioners‟ challenge founded upon alleged expiry of the
statutory timeline is without merit.
43. Having concluded that the Impugned OIO does not suffer from
want of jurisdiction on grounds of limitation, we consider it
appropriate to briefly notice, as an independent and alternative
ground, certain aspects of the Petitioners‟ conduct which would in any
event disentitle them to discretionary relief under Article 226 of the
Constitution, a ground distinct from, and not necessary to, our finding
on limitation above.
44. The jurisdiction exercised by a writ Court under Article 226 of
the Constitution is equitable and discretionary in nature and cannot be
claimed as a matter of right. Ordinarily, where an efficacious
alternative statutory remedy is available, the Court would be slow to
exercise its writ jurisdiction, save in recognised exceptions. The
exercise of such jurisdiction may also be declined where the conduct
of the Petitioner is such that equitable relief ought not to be granted,
including where material facts have not been candidly disclosed.
45. In this regard, we note that the Petitioners have not, at any stage
of the present proceedings, sought to controvert the substantive
findings recorded in the Impugned OIO concerning diversion of the
duty-free imported goods, breach of the conditions governing the
Advance Authorisations, and consequent fraudulent evasion of duty,
findings which, on the record, resulted in a duty demand of
approximately Rs. 20.18 crore together with interest, redemption fines
and penalties. Their reply dated 14.08.2023 merely sought deferment
W.P.(C) 5796/2025 Page 21 of 22
of adjudication pending W.P.(C) 5756/2021 and expressly reserved
the right to file a substantive reply thereafter; no such reply was,
however, filed even after that writ petition came to be dismissed on
08.12.2023.
46. Further, and it is of particular significance, that the Impugned
OIO records a position also reflected in the Counter Affidavit, that the
dismissal of W.P.(C) 5756/2021 was not communicated to the AA by
the Petitioners, and that the Respondent came to learn of it only in the
course of its own review of matters pending in the Call Book. Having
sought deferment on the express basis of the pendency of that Petition
and having represented that a substantive reply would follow upon its
disposal, the Petitioners did not themselves intimate the AA of the
cessation of that very circumstance.
47. This conduct is relevant not to the statutory computation, which
stands concluded above, but to the equitable discretion of this Court. It
is in this limited context that the principle of approbate and reprobate
stands attracted. A party cannot, having invoked a circumstance as the
basis for keeping adjudication in abeyance, and having chosen not to
answer the substantive allegations during that period, subsequently
seek to derive an equitable advantage, by way of extraordinary writ
relief on limitation grounds alone, from the very passage of time
occasioned by the deferment it had itself sought.
D. CONCLUSION:
48. For the foregoing reasons and having found that the Impugned
OIO was passed within the period prescribed under Sections 28(9) and
W.P.(C) 5796/2025 Page 22 of 22
28(9A) of the Act of 1962, and, in any event and independently,
having regard to the availability of an efficacious alternative statutory
remedy and the circumstances surrounding the Petitioners‟ conduct
during the adjudication proceedings, we are not inclined to interfere
with the Impugned OIO/ Impugned SCN.
49. Accordingly, the present Petition, along with pending application,
is dismissed.
50. The Petitioners shall be at liberty to avail the statutory appellate
remedy available to them in accordance with law and to raise therein
all grounds and contentions available to them in respect of the merits
of the case.
51. It is clarified that no observation contained herein shall
prejudice the consideration of such contentions by the competent
Appellate Authority.
ANIL KSHETARPAL , J.
SHAIL JAIN, J.
SEPTEMBER 07, 2026
s.godara/hr
Legal Notes
Add a Note....