As per the case facts, a power generator and distribution companies had a Power Purchase Agreement. A dispute arose over a supplementary bill, with the distribution companies arguing it should ...
2025 INSC 770
Civil Appeal Diary No. 26876 of 2024
1 of 32
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4336 OF 2025
(Arising out of CIVIL APPEAL DIARY NO. 26876 OF 2024)
JAIPUR VIDYUT VITRAN NIGAM
LTD. & ORS. …APPELLANT(S)
VERSUS
ADANI POWER RAJASTHAN LTD. & ANR. … RESPONDENT(S)
J U D G M E N T
M. M. Sundresh, J.
1. Admit.
2. We have heard the learned Senior Counsel, Mr. Shyam Divan and learned
Counsel, Mr. Karthik Seth appearing for the appellants and the learned
Senior Counsel, Dr. Abhishek Manu Singhvi appearing for the respondent
No. 1, at length. All the relevant documents, including the written
submissions of the parties, have been perused.
Civil Appeal Diary No. 26876 of 2024
2 of 32
3. In pursuance of the Letter of Intent issued to Adani Power Rajasthan Ltd.
(respondent No.1-Power Generator), on 17.12.2009, a Power Purchase
Agreement (hereinafter referred to as the “PPA”) dated 28.01.2010 was
entered into between appellant Nos.1, 2 and 3, who are the Rajasthan
Discoms engaged in the distribution and supply of electricity, on one side
and respondent No.1 on the other, for the supply of 1200 MW Aggregate
Contracted Capacity at a levelized tariff of Rs.3.238 per unit. The same
was duly approved by respondent No.2.
4. While the agreement was in operation, a Notification came to be issued at
the instance of M/s. Coal India Limited (hereinafter referred to as “CIL”),
dated 19.12.2017, imposing a levy of Evacuation Facility Charges
(hereinafter referred to as the “EFC”) with effect from 20.12.2017.
Immediately, on the very next day i.e. 20.12.2017, respondent No.1
informed appellant No. 4 that the Notification dated 19.12.2017
constituted a ‘change in law’ event. The Notification dated 19.12.2017 is
extracted below:
Civil Appeal Diary No. 26876 of 2024
3 of 32
“COAL INDIA LIMITED
A Maharatna Company
(A Govt. of India Enterprise)
COAL BHAWAN
Sales & Marketing Division
Ground & Floor, Premises No, 04 MAR, Plot No. AF-III, Action Area -1A
Rajarhat, New Town, Kolkata - 700156
Phone: 033-71104143, Fax: 033-23244229, Website:
………………………………
CIN: L23 L09WB1973GO1028844
PRICE NOTIFICATION: CIL:S&M: GM(F)Pricing 2017/ 1005 dated
19th Dec. 2017
Charge of Rs. 50 (Fifty) per tonne shall be levied as ‘Evacuation Facility
Charges’ on all despatches except despatch through rapid loading arrangement.
This is effective from 00:00 hour of 20" Dec. 2017. This issues with the
approval of the competent authority.
General Manager (M&S)
Marketing & Sales”
5. On its failure in eliciting a suitable reply, respondent No.1 filed a Petition
bearing No.1373/2018 before the Rajasthan Electricity Regulatory
Commission (hereinafter referred to as the “RERC”), invoking Section 86
of the Electricity Act, 2003 (hereinafter referred to as the “2003 Act”) read
with Article 10 of the PPA. While rejecting some of the reliefs, the RERC
did allow some of the other prayers sought for by respondent No.1. Against
Civil Appeal Diary No. 26876 of 2024
4 of 32
the refusal of some of the claims, the respondent No. 1 filed an appeal
before the Appellate Tribunal for Electricity (hereinafter referred to as the
“APTEL”).
6. The appeal under Section 111 of the 2003 Act was so made along with an
application seeking condonation of delay of 332 days in filing. Another
application was filed seeking to condone the delay of 236 days in re-filing
the appeal. Upon hearing both sides, the aforesaid applications were
allowed and, thereafter, the appeal was decided on merits. It is pertinent to
note that the common order by the APTEL, dated 23.01.2023, condoning
the delay on both counts, has attained finality for want of further challenge.
7. The APTEL, inter alia, held by its judgment dated 18.04.2024, after
elaborately considering the submissions made by both sides, that the
Notification dated 19.12.2017 would amount to a change in law, and the
respondent No. 1 would be entitled to the grant of compensation from the
date of the Notification, by taking note of the decision rendered by this
Court in GMR Warora Energy Ltd. v. CERC (2023) 10 SCC 401
(hereinafter referred to as “GMR Warora”) which, in turn, also placed
Civil Appeal Diary No. 26876 of 2024
5 of 32
reliance upon the earlier decisions of this Court. While doing so, it also
took into consideration, the fair submission made on behalf of the
appellants that the principal issue of levy of EFC, and consequently, the
date from which the respondent No. 1 would be entitled to the grant of
compensation, is covered by the aforementioned judgement. Further
reliance was placed on the said decision by the APTEL, for the purpose of
granting carrying cost at the rate of Late Payment Surcharge (hereinafter
referred to as “LPS”), on a compounding basis, which is to be reckoned
from the date of the Notification. The submission made by the appellants
before the APTEL that a supplementary bill is mandatory before seeking
relief for the LPS was also considered and rejected. Once again, the impact
of delay was argued and considered with specific reference to carrying
cost. Accordingly, the following conclusion was arrived at:
“X.CONCLUSION:
The Appellant shall, in terms of what has been indicated hereinabove, be
entitled for the benefit of the change in law event on account of evacuation
facility charges from the date on which the notification, issued by Coal India
Limited, was made applicable to them. The sum representing this benefit shall
be paid by Respondents 2 to 5 to the appellant along with carrying cost at LPS
rates. While the Appellant shall not be entitled for carrying cost (much less at
LPS rates), for the delay of 332 days in filing the Appeal, they shall be given
Civil Appeal Diary No. 26876 of 2024
6 of 32
credit for the sum of Rs.5 lakhs paid by them earlier as a condition for
condoning the delay in filing the Appeal, since they are now being denied
carrying cost for the said period of delay. The matter is remanded to the
Respondent-Commission to compute the amounts which the Appellant is
entitled to in terms of this Judgment. The Appeal is disposed of accordingly.”
8. When the appeal was filed before this Court, it was entertained, limiting
its scope only to the interpretation of Article 10.2.1 vis-à-vis 10.5 of the
PPA, with specific reference to 10.5.1 (ii). The following is the order
passed by this Court on 09.09.2024:
“We have heard learned senior counsel for the parties at length.
Most of the issues raised in the present matter are covered by earlier decisions
of this Court in ‘GMR Warora Energy Ltd. v. CERC & Ors.’, (2023) 10 SCC
401, ‘UHBVNL v. Adani Power (Mundra) Limited’, (2023) 2 SCC 624,
‘UHBVNL v. Adani Power Limited’, (2019) 5 SCC 325 and ‘MSEDCL v.
MERC & Ors.’, (2022) 4 SCC 657. We may note that the delay in refiling has
been duly considered earlier by the APTEL while condoning it. The said order
has attained finality.
The only issue which might arise for consideration in this appeal pertains
to the interpretation of Article 10.2.1 vis-à-vis Article 10.5 of the PPA with
specific reference to 10.5.1 (ii).
Learned senior counsel for the respondents seeks and is granted two weeks’
time to file a counter affidavit.
Rejoinder affidavit shall be filed within a period of two weeks thereafter.
List on 26.11.2024.”
(emphasis supplied)
Civil Appeal Diary No. 26876 of 2024
7 of 32
SUBMISSIONS ON BEHALF OF THE APPELLANTS
9. Notwithstanding the aforesaid order passed on 09.09.2024, the learned
Senior Counsel and learned Counsel appearing for the appellants, made
elaborate submissions on the other issues as well. It is submitted that the
delay has occasioned only due to the fault of respondent No.1 through the
litigation process and, therefore, what is to be applied is Article 10.5.1 (ii).
The APTEL was wrong in condoning the delay by allowing the
applications filed by respondent No.1. There is no basis for awarding
carrying cost at the rate of LPS, and the APTEL ought not to have awarded
the same as the LPS is granted only when there is a delay in the payment
of a supplementary bill. The learned Senior Counsel placed substantial
reliance on the PPA to contend that it is respondent No.1 who did not raise
the supplementary bill at the earliest point of time, as mandated under
Article 8 of the PPA. The decision rendered by this Court in GMR Warora
(supra) does not apply to the case of respondent No.1, considering that in
the said case, a supplementary bill was indeed raised. Unless a demand is
raised, there is no question of payment that would arise, as there is a clear
Civil Appeal Diary No. 26876 of 2024
8 of 32
distinction between the liability to pay, as against an obligation to pay. In
support of his contention, the learned Senior Counsel has also placed
reliance upon the decision of this Court in Prem Cottex v. Uttar Haryana
Bijli Vitran Nigam Ltd., (2021) 20 SCC 200.
SUBMISSIONS ON BEHALF OF THE RESPONDENTS
10. The learned Senior Counsel Dr. Abhishek Manu Singhvi appearing for the
respondent No. 1, submits that there exists a preliminary objection as
arguments have been made by the appellants beyond the scope of not only
the present appeal but also the order, dated 09.09.2024, of this Court. The
issues sought to be raised by the appellants have already been settled by
this Court in not only GMR Warora (supra) but also in two other
decisions of this Court in Uttar Haryana Bijli Vitran Nigam Ltd. v.
Adani Power Ltd., (2019) 5 SCC 325 (hereinafter referred to as
“UHBVNL 2019”) and Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani
Power (Mundra) Ltd., (2023) 2 SCC 624 (hereinafter referred to as
“UHBVNL 2023”).
Civil Appeal Diary No. 26876 of 2024
9 of 32
11. There is no question of raising a supplementary bill earlier, in view of the
definite stand taken by the appellants on the notification made by
respondent No.1 on 20.12.2017. It is nobody’s case that the appellants were
going to honour the bill if raised at the earliest point of time, as contended
by them. The APTEL itself has held that respondent No.1 is not entitled to
carrying cost for the period of delay in filing the appeal. The orders passed
on that count have attained finality. The appellants are making a futile
attempt at reopening the issues which are closed. Thus, it is a fit case where
the appeal has to be dismissed with costs, particularly when appropriate
orders have been passed by the RERC in pursuance of the order of remand
made by the APTEL.
12. Before we deal with the submissions made by the parties, we deem it
appropriate to discuss and elaborate on the scope of appeals under the 2003
Act.
SCOPE OF APPEALS UNDER THE ELECTRICITY ACT, 2003
13. Whenever a statute provides for an appeal, a Court is expected to restrain
itself to the contours of the powers conferred under it. The nature and status
Civil Appeal Diary No. 26876 of 2024
10 of 32
of the Court loses its significance as it only draws its powers from the
statute alone, and not beyond. After all, judicial restraint and sobriety,
when consciously restricted by the Legislature, forms an integral part of
the duties and functions of the Court.
Section 111 of the 2003 Act
“111. Appeal to Appellate Tribunal.— (1) Any person aggrieved by an order
made by an adjudicating officer under this Act (except under Section 127) or
an order made by the Appropriate Commission under this Act may prefer an
appeal to the Appellate Tribunal for Electricity:
Provided that any person appealing against the order of the adjudicating officer
levying any penalty shall, while filing the appeal, deposit the amount of such
penalty:
Provided further that where in any particular case, the Appellate Tribunal is of
the opinion that the deposit of such penalty would cause undue hardship to such
person, it may dispense with such deposit subject to such conditions as it may
deem fit to impose so as to safeguard the realisation of penalty.
(2) Every appeal under sub-section (1) shall be filed within a period of forty-
five days from the date on which a copy of the order made by the adjudicating
officer or the Appropriate Commission is received by the aggrieved person and
it shall be in such form, verified in such manner and be accompanied by such
fee as may be prescribed:
Provided that the Appellate Tribunal may entertain an appeal after the expiry
of the said period of forty-five days if it is satisfied that there was sufficient
cause for not filing it within that period.
(3) On receipt of an appeal under sub-section (1), the Appellate Tribunal may,
after giving the parties to the appeal an opportunity of being heard, pass such
orders thereon as it thinks fit, confirming, modifying or setting aside the order
appealed against.
Civil Appeal Diary No. 26876 of 2024
11 of 32
(4) The Appellate Tribunal shall send a copy of every order made by it to the
parties to the appeal and to the concerned adjudicating officer or the
Appropriate Commission, as the case may be.
(5) The appeal filed before the Appellate Tribunal under sub-section (1) shall
be dealt with by it as expeditiously as possible and endeavour shall be made by
it to dispose of the appeal finally within one hundred and eighty days from the
date of receipt of the appeal:
Provided that where any appeal could not be disposed of within the said period
of one hundred and eighty days, the Appellate Tribunal shall record its reasons
in writing for not disposing of the appeal within the said period.
(6) The Appellate Tribunal may, for the purpose of examining the legality,
propriety or correctness of any order made by the adjudicating officer or the
Appropriate Commission under this Act, as the case may be, in relation to any
proceeding, on its own motion or otherwise, call for the records of such
proceedings and make such order in the case as it thinks fit.”
Section 125 of the 2003 Act
“125. Appeal to Supreme Court.—Any person aggrieved by any decision or
order of the Appellate Tribunal, may, file an appeal to the Supreme Court,
within sixty days from the date of communication of the decision or order of
the Appellate Tribunal, to him, on any one or more of the grounds specified in
Section 100 of the Code of Civil Procedure, 1908 (5 of 1908):
Provided that the Supreme Court may, if it is satisfied that the appellant was
prevented by sufficient cause from filing the appeal within the said period,
allow it to be filed within a further period not exceeding sixty days.”
Section 100 of the Code of Civil Procedure, 1908
“100. Second appeal.— (1) Save as otherwise expressly provided in the body
of this Code or by any other law for the time being in force, an appeal shall lie
to the High Court from every decree passed in appeal by any Court subordinate
to the High Court, if the High Court is satisfied that the case involves a
substantial question of law.
Civil Appeal Diary No. 26876 of 2024
12 of 32
(2) An appeal may lie under this section from an appellate decree passed ex-
parte.
(3) In an appeal under this section, the memorandum of appeal shall precisely
state the substantial question of law involved in the appeal.
(4) Where the High Court is satisfied that a substantial question of law is
involved in any case, it shall formulate that question.
(5) The appeal shall be heard on the question so formulated and the respondent
shall, at the hearing of the appeal, be allowed to argue that the case does not
involve such question:
Provided that nothing in this sub-section shall be deemed to take away or
abridge the power of the Court to hear, for reasons to be recorded, the appeal
on any other substantial question of law, not formulated by it, if it is satisfied
that the case involves such question.”
14. Under Section 111 of the 2003 Act, the APTEL is vested with all the
powers that can possibly be exercised by the Regulatory Commission. In
other words, it is the final Court of fact and law.
15. However, under Section 125 of the 2003 Act, the powers expected to be
exercised by this Court is circumscribed and controlled by the pari materia
provision contained under Section 100 of the Code of Civil Procedure,
1908 (hereinafter referred to as “the CPC”). Thus, it is axiomatic that an
appellant has to raise a substantial question of law, which if the Court finds
to be in existence, shall accordingly frame it in whatever manner it deems
fit and proper, and put it to the other side to respond. It is for this Court to
Civil Appeal Diary No. 26876 of 2024
13 of 32
ultimately consider the existence of a substantial question of law and if it
does so, answer it accordingly. We will only clarify that there is no bar for
this Court to add any number of substantial questions of law even after
framing one earlier, in which case the respondents will have to be given
due notice of the same.
16. Section 100 of the CPC, after its amendment in the year 1978, consciously
concerns itself with a question of law which shall be substantial in nature.
Therefore, a mere question of law would not be sufficient enough to
entertain an appeal under Section 125 of the 2003 Act. Added to that, it
should be such that the substantial question of law, if answered in the
affirmative in favour of the appellant, shall have the effect of reversing the
decision of the APTEL. While deciding a substantial question of law, this
Court shall do so, based upon the findings of fact rendered by the APTEL,
unless by way of an exception, a perversity is found thereunder. In a case
where a finding is rendered contrary to the records, without assigning any
reason, and/or on a total misconception of the fact seen apparently on the
face of the record, may in a given case, give rise to a substantial question
Civil Appeal Diary No. 26876 of 2024
14 of 32
of law. Suffice it is to state that a substantial question of law has to be
framed by this Court in exercise of the power under Section 125 of the
2003 Act and, thereafter, to be answered accordingly.
17. In the facts of the instant case, we have indeed framed only one substantial
question of law vide order dated 09.09.2024, as aforementioned. Though
we did permit the appellants to raise all the other issues and considered
them as not feasible, the fact remains that they do not constitute substantial
questions of law.
DISCUSSION
18. The issue with respect to change in law over a notification issued by a
public authority and the resultant date to be reckoned has indeed attained
finality pursuant to the judgments delivered by this Court in GMR Warora
Energy Ltd. (supra), UHBVNL 2019 (supra) and UHBVNL 2023
(supra).
GMR Warora Energy Ltd. v. CERC (2023) 10 SCC 401
“95. For appreciating the rival submissions, we will have to construe the term
“Law”, which has been defined in the PPAs, which reads thus:
“ “Law” means, in relation to this Agreement, all laws including
Electricity laws in force in India and any statute, ordinance,
Civil Appeal Diary No. 26876 of 2024
15 of 32
regulation, notification or code, rule, or any interpretation of any of
them by an Indian Governmental Instrumentality and having force of
law and shall further include all applicable rules, regulations, orders,
notifications by an Indian Governmental Instrumentality pursuant to
or under any of them and shall include all rules, regulations, decisions
and orders of CERC and MERC.”
96. Perusal of the definition of the term “Law” itself would clearly show that
the term “Law” would mean all laws including Electricity laws in force in India
and any statute, ordinance, regulation, notification or code, rule, or any
interpretation of any of them by an Indian governmental instrumentality and
having force of law. It would further reveal that the term “Law” shall also
include all applicable rules, regulations, orders, notifications by an Indian
governmental instrumentality and shall also include all rules, regulations,
decisions and orders of CERC and MERC.
97. In any case, the issue as to what would amount to “Law” is no more res
integra. This Court, in Energy Watchdog [Energy Watchdog v. CERC, (2017)
14 SCC 80 : (2018) 1 SCC (Civ) 133] , has observed thus : (SCC p. 131, para
57)
“57. Both the letter dated 31-7-2013 and the revised Tariff Policy are
statutory documents being issued under Section 3 of the Act and have the
force of law. This being so, it is clear that so far as the procurement of
Indian coal is concerned, to the extent that the supply from Coal India and
other Indian sources is cut down, the PPA read with these documents
provides in Clause 13.2 that while determining the consequences of
change in law, parties shall have due regard to the principle that the
purpose of compensating the party affected by such change in law is
to restore, through monthly tariff payments, the affected party to the
economic position as if such change in law has not occurred. Further,
for the operation period of the PPA, compensation for any
increase/decrease in cost to the seller shall be determined and be effective
from such date as decided by the Central Electricity Regulation
Commission. This being the case, we are of the view that though change
in Indonesian law would not qualify as a change in law under the
guidelines read with the PPA, change in Indian law certainly would.”
98. The aforesaid view of this Court taken in Energy Watchdog [Energy
Watchdog v. CERC, (2017) 14 SCC 80 : (2018) 1 SCC (Civ) 133] has been
approved by a Bench of three learned Judges of this Court in Adani Rajasthan
Civil Appeal Diary No. 26876 of 2024
16 of 32
case [Jaipur Vidyut Vitaran Nigam Ltd. v. Adani Power Rajasthan Ltd., (2021)
18 SCC 478] and also followed by this Court when the two linked matters out
of this batch of appeals were decided by this Court in Maharashtra State
Electricity Distribution Co. Ltd. v. Adani Power Maharashtra Ltd. [(2023) 7
SCC 401] It cannot be denied that CIL is an instrumentality of the
Government of India and its orders, insofar as price of fuel is concerned,
are binding on all its subsidiaries.
***
100. As discussed hereinabove, the term “Law” would also include all
applicable rules, regulations, orders, notifications issued by an Indian
governmental instrumentality.
101. It would thus be clear that all such additional charges which are
payable on account of orders, directions, notifications, regulations, etc.
issued by the instrumentalities of the State, after the cut-off date, will have
to be considered to be “change in law” events. The generators would be
entitled to compensation on the restitutionary principle on such changes
occurring after the cut-off date.
***
111. Undisputedly, EFC was imposed by CIL vide its Circular dated 19-12-
2017.
112. As already discussed hereinabove, CIL is an instrumentality of the
State. It is thus clear that, on the cut-off date, there was no requirement of
EFC, which has been brought into effect only on 19-12-2017. As such, the
circular of CIL dated 19-12-2017 would also amount to “change in law”.
***
117. For considering the rival submissions, it will be apposite to refer to the
following articles, which are almost common in most of the PPAs:
“11. Billing and payment.—
***
11.3. Payment of monthly bills.—
***
11.3.4. In the event of delay in payment of a monthly bill by any procurer
beyond its due date, a late payment surcharge shall be payable by the
procurer to the seller at the rate of two (2) per cent in excess of the applicable
Civil Appeal Diary No. 26876 of 2024
17 of 32
SBAR per annum, on the amount of outstanding payment, calculated on a
day-to-day basis (and compounded with monthly rest), for each day of the
delay.
***
11.8. Payment of supplementary bill.—
11.8.1. Either party may raise a bill on the other party (“supplementary bill”)
for payment on account of:
(i) Adjustments required by the Regional Energy Account (if applicable);
(ii) Tariff payment for change in parameters, pursuant to provisions in
Schedule 5; or
(iii) Change in law as provided in Article 13 and such bill shall be paid by
the other party.
***
11.8.3. In the event of delay in payment of a supplementary bill by either
party beyond one month from the date of billing, a late payment surcharge
shall be payable at same terms applicable to the monthly bill in Article
11.3.4.”
118. A perusal of Article 11.3.4 of the PPA would reveal that in the event of
delay in payment of a monthly bill by any procurer beyond its due date, a late
payment surcharge shall be payable by the procurer to the seller @ of 2% in
excess of the applicable State Bank Advance Rate (“SBAR” for short) per
annum, on the amount of outstanding payment, calculated on a day-to-day
basis (and compounded with monthly rest), for each day of the delay. Article
11.8 of the PPA deals with payment of supplementary bill. It enables either
party to raise a supplementary bill on the other party for payment on account
of certain events. Clause (iii) of Article 11.8.1 of the PPA deals with “change
in law” as provided in Article 13. It requires the bill to be paid by the other
party. Article 11.8.3 of the PPA also provides that in the event of delay in
payment of a supplementary bill by either party beyond one month from the
date of billing, a late payment surcharge shall be payable at same terms
applicable to the monthly bill in Article 11.3.4.
***
120. It could thus be seen that this Court in Adani Power [Uttar Haryana Bijli
Vitran Nigam Ltd. v. Adani Power Ltd., (2019) 5 SCC 325 : (2019) 2 SCC (Civ)
Civil Appeal Diary No. 26876 of 2024
18 of 32
657] has held that insofar as the “operation period” is concerned, compensation
for any increase/decrease in revenues or costs to the seller is to be determined
and effected from such date as is decided by the appropriate Commission. It
has further been held that the compensation is only payable for
increase/decrease in revenue or cost to the seller if it is in excess of an amount
equivalent to 1% of the letter of credit in aggregate for a contract year. It has
been held that restitutionary principles apply in case a certain threshold
limit is crossed. It has been held that an inbuilt restitutionary principle
compensates the party affected by such “change in law” and the affected
party must be restored through monthly tariff payment to the same
economic position as if such “change in law” had not occurred.
121. From the perusal of para 9 of Adani Power [Uttar Haryana Bijli Vitran
Nigam Ltd. v. Adani Power Ltd., (2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657],
it would also be clear that in case the “change in law” happens to be by
way of adoption, promulgation, amendment, re-enactment or repeal of the
law or “change in law”, it has to be effected from the date on which such
change occurs.
122. In this respect, it will also be apposite to refer to the following
observations of this Court in Maharashtra State Electricity Distribution Co.
Ltd. v. Maharashtra Electricity Regulatory Commission [(2022) 4 SCC 657] :
(SCC pp. 719-20, paras 173-78)
“173. APTEL correctly found that: (Maharashtra Pradesh Electricity
Regulatory Commission case [Maharashtra State Electricity Distribution
Co. Ltd. v. Maharashtra Pradesh Electricity Regulatory Commission, 2021
SCC OnLine APTEL 13], SCC OnLine APTEL para 13)
‘13. … On the contrary, there is a conscious exclusion regarding any suo
motu change in the rate to be applied while calculating LPS, it being
incorrect to argue on the assumption that the contract permits automatic
change in system.’
174. This Court is unable to accept Mr Singh's submission that the
conclusion of APTEL that LPS is not tariff is erroneous. The meaning of the
expression tariff has to be considered, and has rightly been considered by
APTEL in the context of the relevant provision of the power purchase
agreements. The dictionary meaning of tariff may be charge. However, in
Article 13 of Stage 1 and Article 10 of Stage 2 power purchase agreements,
tariff means monthly tariff and tariff adjustment consequential to change in
law, is of monthly tariff in respect of supply of electricity.
Civil Appeal Diary No. 26876 of 2024
19 of 32
175. As argued by the respondent power generating companies appearing
through Mr Rohatgi, Mr Singhvi, Mr Mukherjee and Ms Anand respectively,
LPS is only payable when payment against monthly bills is delayed and not
otherwise.
176. The object of LPS is to enforce and/or encourage timely payment
of charges by the procurer i.e. the appellant. In other words, LPS
dissuades the procurer from delaying payment of charges. The rate of
LPS has no bearing or impact on tariff. Changes in the basis of the rates
of LPS do not affect the rate at which power was agreed to be sold and
purchased under the power purchase agreements. The principle of
restitution under the change in law provisions of the power purchase
agreements are attracted in respect of tariff.
177. LPS cannot be equated with carrying cost or actual cost incurred for the
supply of power. The appellant has a contractual obligation to make timely
payment of the invoices raised by the power generating companies, subject,
of course, to scrutiny and verification of the same. Mr Mukul Rohatgi has a
point that if the funding cost was so much lesser than the rate of LPS, as
contended by the appellant, the appellant could have raised funds at a lower
rate of interest, made timely payment of the invoices raised by the power
generating companies, and avoided LPS.
178. The proposition that courts cannot rewrite a contract mutually
executed between the parties, is well settled. The Court cannot, through
its interpretative process, rewrite or create a new contract between the
parties. The Court has to simply apply the terms and conditions of the
agreement as agreed between the parties, as observed by this Court in Shree
Ambica Medical Stores v. Surat People's Coop. Bank [(2020) 13 SCC 564] ,
para 20, cited by Ms Divya Anand. This appeal is an attempt to renegotiate
the terms of the PPA, as argued by Ms Divya Anand as also other counsel. It
is well settled that courts cannot substitute their own view of the presumed
understanding of commercial terms by the parties, if the terms are explicitly
expressed. The explicit terms of a contract are always the final word with
regard to the intention of the parties, as held by this Court in Nabha Power
Ltd. v. Punjab SPCL [(2018) 11 SCC 508 : (2018) 5 SCC (Civ) 1] , paras 45
& 72, cited by Ms Anand.”
(emphasis in original)
123. This Court has clearly held in Maharashtra State Electricity Distribution
Co. [Maharashtra State Electricity Distribution Co. Ltd. v. Maharashtra
Civil Appeal Diary No. 26876 of 2024
20 of 32
Electricity Regulatory Commission, (2022) 4 SCC 657] that the DISCOMS
have a contractual obligation to make timely payment of the invoices
raised by the power generating companies, subject to scrutiny and
verification of the same. This Court has rejected the contention that the
funding cost was much lesser than the rate of LPS. This Court has reiterated
the proposition that the courts cannot rewrite a contract which is executed
between the parties. This Court has emphasised that it cannot substitute its own
view of the presumed understanding of commercial terms by the parties, if the
terms are explicitly expressed. It has been held that the explicit terms of a
contract are always the final word with regard to the intention of the parties.
124. As already discussed hereinabove, Article 11.8 of the PPA entitles either
party to raise a supplementary bill on the other party on account of “change in
law” as provided in Article 13 and such bills are required to be paid by the
either party. Article 11.8.3 of the PPA specifically provides that in the event of
delay in payment of a supplementary bill by either party beyond one month
from the date of billing, a late payment surcharge shall be payable at the same
terms applicable to the monthly bill in Article 11.3.4. Article 11.3.4 of the PPA
specifically provides a late payment surcharge to be paid by the procurer to the
seller @ of 2% in excess of the applicable SBAR per annum on the amount of
outstanding payment calculated on day-to-day basis (and compounded with
monthly rest), for each day of the delay.
***
126. It is thus clear that this Court has reiterated in Adani Power (Mundra)
[Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd.,
(2023) 2 SCC 624 : (2023) 1 SCC (Civ) 31] that once carrying cost has been
granted, it cannot be urged that interest on carrying cost should be
calculated on simple interest basis instead of compound interest basis. It
has been held that grant of compound interest on carrying cost and that
too from the date of the occurrence of the “change in law” event is based
on sound logic. It has been held that it is aimed at restituting a party that
is adversely affected by a “change in law” event and restore it to its original
economic position as if such a “change in law” event had not taken place.
127. The argument that there is no provision in the PPAs for payment of
compound interest from the date when the “change in law” event had
occurred, has been specifically rejected by this Court.
128. In view of this consistent position of law and application of restitutionary
principles and privity of contractual obligations between the parties as
Civil Appeal Diary No. 26876 of 2024
21 of 32
contained in the PPAs, we do not find that the view taken by the learned APTEL
with regard to carrying cost warrants interference.
***
177. It is further to be noted that this Court in Uttar Haryana Bijli Vitran Nigam
Ltd. v. Adani Power Ltd. [(2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657], has
specifically observed that the “change in law” events will have to accrue
from the date on which rules, orders, notifications are issued by the
instrumentalities of the State. Even in spite of this finding, the DISCOMS
are pursuing litigations after litigations.
178. We find that, when the PPA itself provides a mechanism for payment
of compensation on the ground of “change in law”, unwarranted litigation,
which wastes the time of the Court as well as adds to the ultimate cost of
electricity consumed by the end-consumer, ought to be avoided.
Ultimately, the huge cost of litigation on the part of DISCOMS as well as
the generators adds to the cost of electricity that is supplied to the end-
consumers.”
(emphasis supplied)
Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd.
(2023) 2 SCC 624
“20. It is clear that the restitutionary principles encapsulated in Article
13.2 would take effect for computing the impact of change in law. We see
no reason to interfere with the impugned judgment [Adani Power (Mundra)
Ltd. v. CERC, 2021 SCC OnLine APTEL 67] , wherein it has been held by the
Appellate Tribunal that Respondent 1 Adani Power had started claiming
change in law event compensation in respect of installation of FGD unit along
with carrying cost, right from the year 2012 and that it has approached several
fora to get this claim settled. Respondent 1 Adani Power finally succeeded in
getting compensation towards FGD unit only on 28-3-2018, but the carrying
cost claim was denied. The relief relating to carrying cost was granted to
Respondent 1 Adani Power by the Appellate Tribunal vide order dated 13-4-
2018 [Adani Power Ltd. v. CERC, 2018 SCC OnLine APTEL 5] which was
duly tested by this Court and upheld on 25-2-2019 [Uttar Haryana Bijli Vitran
Nigam Ltd. v. Adani Power Ltd., (2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657].
Once carrying cost has been granted in favour of Respondent 1 Adani
Power, it cannot be urged by the appellants that interest on carrying cost
should be calculated on simple interest basis instead of compound interest
Civil Appeal Diary No. 26876 of 2024
22 of 32
basis. Grant of compound interest on carrying cost and that too from the
date of the occurrence of the change in law event is based on sound logic.
The idea behind granting interest on carrying cost is not far to see, it is
aimed at restituting a party that is adversely affected by a change in law
event and restore it to its original economic position as if such a change in
law event had not taken place.
21. In the instant case, Respondent 1 Adani Power had to incur expenses to
purchase the FGD unit and install it in view of the terms and conditions of the
environment clearance given by the Ministry of Environment and Forests,
Union of India, in the year 2010. For this, it had to arrange finances by
borrowing from banks. The interest rate framework followed by scheduled
commercial banks and regulated by Reserve Bank of India mandates that
interest shall be charged on all advances at monthly rests. In this view of the
matter, Respondent 1 Adani Power is justified in stating that if the banks
have charged it interest on monthly rest basis for giving loans to purchase
the FGD unit, any restitution will be incomplete, if it is not fully
compensated for the interest paid by it to the banks on compounding basis.
22. We are of the opinion that interest on carrying cost is nothing but time
value for money and the only manner in which a party can be afforded the
benefit of restitution in every which way. In the facts of the instant case, the
Appellate Tribunal was justified in allowing interest on carrying cost in favour
of Respondent 1 Adani Power for the period between the year 2014, when the
FGD unit was installed, till the year 2021. There was no justification for the
Central Commission to have excluded the period between 2014 and 2018
and grant relief from the date of the passing of the order i.e. from 28-3-
2018 [Adani Power Ltd. v. Uttar Haryana Bijli Vitran Nigam Ltd., 2018 SCC
OnLine CERC 8] to 2021; nor is there any logic to such a segregation of
timelines, particularly when Respondent 1 Adani Power was prompt in raising
a claim on the appellants and pursuing its legal remedies.
23. We are not persuaded by the submission made on behalf of the
appellants that since no fault is attributable to them for the delay caused
in determination of the amount, they cannot be saddled with the liability
to pay interest on carrying cost; nor is there any substance in the argument
sought to be advanced that there is no provision in the PPAs for payment
of compound interest from the date when the change in law event had
occurred.
Civil Appeal Diary No. 26876 of 2024
23 of 32
24. The entire concept of restitutionary principles engrained in Article 13
of the PPAs has to be read in the correct perspective. The said principle
that governs compensating a party for the time value for money, is the very
same principle that would be invoked and applied for grant of interest on
carrying cost on account of a change in law event. Therefore, reliance on
Article 11.3.4 read with Article 11.8.3 on the part of the appellants cannot take
their case further. Nor does the decision in Priya Vart case [Priya Vart v. Union
of India, (1995) 5 SCC 437] have any application to the facts of the present
case as the said case relates to payment of compensation under the Land
Acquisition Act and the interest that would be payable in case of delayed
payment of compensation.”
(emphasis supplied)
Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd. (2019) 5
SCC 325
“9. It will be seen that Article 13.4.1 makes it clear that adjustment in
monthly tariff payment on account of change in law shall be effected from
the date of the change in law [see sub-clause (i) of clause 4.1], in case the
change in law happens to be by way of adoption, promulgation,
amendment, re-enactment or repeal of the law or change in law. As opposed
to this, if the change in law is on account of a change in interpretation of
law by a judgment of a Court or Tribunal or governmental
instrumentality, the case would fall under sub-clause (ii) of clause 4.1, in
which case, the monthly tariff payment shall be effected from the date of
the said order/judgment of the competent authority/Tribunal or the
governmental instrumentality. What is important to notice is that Article
13.4.1 is subject to Article 13.2 of the PPAs.
10. Article 13.2 is an in-built restitutionary principle which compensates
the party affected by such change in law and which must restore, through
monthly tariff payments, the affected party to the same economic position
as if such change in law has not occurred. This would mean that by this
clause a fiction is created, and the party has to be put in the same economic
position as if such change in law has not occurred i.e. the party must be
given the benefit of restitution as understood in civil law. Article 13.2,
however, goes on to divide such restitution into two separate periods. The first
period is the “construction period” in which increase/decrease of capital cost
Civil Appeal Diary No. 26876 of 2024
24 of 32
of the project in the tariff is to be governed by a certain formula. However, the
seller has to provide to the procurer documentary proof of such
increase/decrease in capital cost for establishing the impact of such change in
law and in the case of dispute as to the same, a dispute resolution mechanism
as per Article 17 of the PPA is to be resorted to. It is also made clear that
compensation is only payable to either party only with effect from the date on
which the total increase/decrease exceeds the amount stated therein.
11. So far as the “operation period” is concerned, compensation for any
increase/decrease in revenues or costs to the seller is to be determined and
effected from such date as is decided by the appropriate Commission. Here
again, this compensation is only payable for increase/decrease in revenue or
cost to the seller if it is in excess of an amount equivalent to 1% of the Letter
of Credit in aggregate for a contract year. What is clear, therefore, from a
reading of Article 13.2, is that restitutionary principles apply in case a
certain threshold limit is crossed in both sub-clauses (a) and (b). There is
no dispute that the present case is covered by sub-clause (b) and that the
aforesaid threshold has been crossed. The mechanism for claiming a
change in law is then set out by Article 13.3 of the PPA.
***
13. A reading of Article 13 as a whole, therefore, leads to the position that
subject to restitutionary principles contained in Article 13.2, the adjustment in
monthly tariff payment, in the facts of the present case, has to be from the date
of the withdrawal of exemption which was done by administrative orders dated
6-4-2015 and 16-2-2016. The present case, therefore, falls within Article
13.4.1(i). This being the case, it is clear that the adjustment in monthly
tariff payment has to be effected from the date on which the exemptions
given were withdrawn. This being the case, monthly invoices to be raised by
the seller after such change in tariff are to appropriately reflect the changed
tariff. On the facts of the present case, it is clear that the respondents were
entitled to adjustment in their monthly tariff payment from the date on which
the exemption notifications became effective. This being the case, the
restitutionary principle contained in Article 13.2 would kick in for the simple
reason that it is only after the order dated 4-5-2017 [Adani Power Ltd. v. Uttar
Haryana Bijli Vitran Nigam Ltd., 2017 SCC OnLine CERC 66] that CERC
held that the respondents were entitled to claim added costs on account of
change in law w.e.f. 1-4-2015. This being the case, it would be fallacious to say
that the respondents would be claiming this restitutionary amount on some
general principle of equity outside the PPA. Since it is clear that this amount of
Civil Appeal Diary No. 26876 of 2024
25 of 32
carrying cost is only relatable to Article 13 of the PPA, we find no reason to
interfere with the judgment of the Appellate Tribunal.”
(emphasis supplied)
19. Notwithstanding the aforesaid clear pronouncements of this Court, we
would like to throw a little more light on what constitutes a ‘change in law’
event, in view of the persuasive submissions made by Mr. Shyam Divan,
the learned Senior Counsel appearing for the appellants.
20. While Article 10 of the PPA, with specific reference to Article 10.2, deals
with application and principles for computing impact of change in law,
Article 10.5, being a facet of Article 10.2 of the PPA, concerns itself with
tariff adjustment payment on account of change in law. Article 10.2 and
Article 10.5 of the PPA are extracted as below:
“10.2 Application and Principles for computing impact of Change in Law
10.2.1 While determining the consequence of Change in Law under this Article
10, the Parties shall have due regard to the principle that the purpose of
compensating the Party affected by such Change in Law is to restore through
monthly Tariff Payment, to the extent contemplated in this Article 10, the
affected Party to the same economic position as if such Change in Law has not
occurred.
***
10.5 Tariff Adjustment Payment on account of Change in Law
Civil Appeal Diary No. 26876 of 2024
26 of 32
l0.5.1 Subject to Article 10.2, the adjustment in monthly Tariff Payment shall
be effective from:
(i) the date of adoption, promulgation, amendment, re-enactment or repeal of
the Law or Change in Law; or
(ii) the date of order/ judgment of the Competent Court or tribunal or Indian
Governmental Instrumentality, if the Change in Law is on account of a change
in interpretation of Law.
10.5.2 The payment for Change in Law shall be through Supplementary Bill as
mentioned in Article 8.8. However, in case of any change in Tariff by reason
of Change in Law, as determined in accordance with this Agreement, the
Monthly Invoice to be raised the Seller after such change in Tariff shall
appropriately reflect the changed Tariff.”
21. As held by this Court in the decisions referred to supra, Article 10.2.1 in
the instant PPA was incorporated based on the principle of restitution. The
idea of this principle is to compensate the affected party in order to restore
it to the same economic position, but for the change in law. This particular
provision is a substantive one, which in a normal circumstance, has to be
given effect to in letter and spirit.
22. Article 10.5 of the PPA deals with tariff adjustment payment occasioned
on account of change in law. Under Article 10.5.1 (i) of the PPA, the
adjustment would start from the date of change in law. Therefore, as a
matter of course, the adjustment in monthly tariff payment shall become
effective from the date notified in the change in law.
Civil Appeal Diary No. 26876 of 2024
27 of 32
23. Article 10.5.1 (ii) of the PPA might emerge in a factual scenario where
there is an adjudication by way of an order/judgment of a competent Court
or Tribunal or an Indian Governmental Instrumentality, as the case may be.
Rendering of an order/judgement would require an interpretation of law.
When there is a change in the interpretation of law in rendering the
order/judgement, the date of such an order/judgment would constitute a
‘change in law’ under Article 10.5.1 (ii) of the PPA.
24. Hence, a mere difference in the understanding of a ‘change in law’ by one
party to the PPA, does not, by itself, preclude the other party from deriving
a benefit by invoking Article 10.5.1 (i) of the PPA. In other words, a
different understanding would not result in a different interpretation of law,
that would bar entitlement under Article 10.5.1 (i) of the PPA and,
therefore, such a situation would not fall within the purview of Article
10.5.1 (ii) of the PPA.
25. To make this position clear, Article 10.5.1 (ii) of the PPA is not applicable
to the facts of the instant case since there is no change in law which has
occasioned by way of an interpretation given by a Court or a Tribunal or
Civil Appeal Diary No. 26876 of 2024
28 of 32
an Indian Governmental Instrumentality. Recognising a change in law is
different from interpreting a notification as the one applicable to the
parties. We are only clarifying the position that there is no change in the
interpretation of law involved in the case at hand, particularly when the
said issue was not before the APTEL, for which the author of the change
in law should have been made a party to the proceedings, in order to defend
it. The Notification, dated 19.12.2017, and its application are not in
dispute. What is in dispute is whether it constitutes a change in law or not.
So long as there is no interpretation on the Notification with respect to its
applicability to the parties before us, Clause (ii) of Article 10.5.1 of the
PPA will have no application.
26. Article 10.5.2 of the PPA kicks in thereafter. Hence, a supplementary bill
has to be raised only after due adjudication by the competent forum. Our
view is fortified on a proper reading of Article 8 of the PPA.
“ARTICLE 8: BILLING AND PAYMENT
***
8.3 Payment of Monthly Bills
Civil Appeal Diary No. 26876 of 2024
29 of 32
8.3.1 The Procurers shall pay the amount payable under the Monthly Bill on
the Due Date to such account of the Seller, as shall have been previously
notified by the Seller in accordance with Article 8.3.4 below.
8.3.2 All payments made by the Procurer(s) shall be appropriated by the Seller
in the following order of priority:
i) towards Late Payment Surcharge, if any;
ii) towards the earlier unpaid Monthly Bill(s), if any; and
iii) towards the then current Monthly Bill.
***
8.3.5 In the event of delay in payment of a Monthly Bill by the Procurers
beyond its Due Date, a Late Payment Surcharge shall be payable by such
Procurers to the Seller at the rate of two percent (2%) in excess of the applicable
SBAR per annum, on the amount of outstanding payment, calculated on a day
to day basis (and compounded with monthly rest), for each day of the delay.
The Late Payment Surcharge shall be claimed by the Seller through the
Supplementary Bill.
***
8.6 Disputed Bill
8.6.1 If a Party does not dispute a Monthly Bill, Provisional Bill or a
Supplementary Bill raised by the other Party by the Due Date, such Bill shall
be taken as conclusive.
8.6.2 If a Party disputes the amount payable under a Monthly Bill, Provisional
Bill or a Supplementary Bill, as the case may be, that Party shall, within thirty
(30) days of receiving such Bill, issue a notice (the “Bill Dispute Notice”) to
the invoicing Party setting out:
i) the details of the disputed amount;
ii) its estimate of what the correct amount should be; and
iii) all written material in support of its claim.
***
8.8 Payment of Supplementary Bill
Civil Appeal Diary No. 26876 of 2024
30 of 32
8.8.l Either Party may raise a bill on the other Party ("Supplementary Bill”) for
payment on account of:
i) Adjustments required by the Regional Energy Account (if applicable);
ii) Tariff Payment for change in parameters, pursuant to provisions in Schedule
4; or
iii) Change in Law as provided in Article 10,
and such Supplementary Bill shall be paid by the other Party.
***
8.8.3 In the event of delay in payment of a Supplementary Bill by either Party
beyond its Due Date, a Late Payment Surcharge shall be payable at the same
terms applicable to the Monthly Bill in· Article 8.3.5.”
It is not in dispute that a supplementary bill is not a monthly bill. Article 8
of the PPA deals with billing and payment alone. Under Article 8.8, the
other party is duty-bound to make the payment when a supplementary bill
is raised due to a change in law event having occurred, as provided under
Article 10 of the PPA. This can happen only after due adjudication by the
competent forum, has taken place. For more clarity, one has to read Article
10.5.2 along with Article 8.8 of the PPA. It is only thereafter that Article
8.6 of the PPA might come into the picture when there exists a dispute on
the quantum of amount claimed in the supplementary bill raised after the
completion of due adjudication by the competent forum, on the issue
pertaining to the change in law.
Civil Appeal Diary No. 26876 of 2024
31 of 32
27. The incidental issue raised with respect to carrying cost at the rate of LPS
has also been dealt with in the decisions referred to in GMR Warora
Energy Ltd. (supra), UHBVNL 2019 (supra) and UHBVNL 2023
(supra) and, therefore, any fresh consideration would only be an academic
exercise. We also find that the decision relied upon by the learned Senior
Counsel appearing on behalf of the appellants, have no application to the
facts of the case.
28. For the aforesaid reasons, we find absolutely no reason to interfere with
the impugned judgment. Liability has been fastened upon the appellants
under the agreement. The contention that the supplementary bill ought to
have been raised earlier and, therefore, the payment can only be made
thereafter has neither a factual basis nor a legal one. We would only point
out the fact that respondent No.1 did notify the change in law event
immediately on the very next day of the notification having been issued.
In any case, we have been informed that in pursuance of the order of
remand made by the APTEL, further orders have been passed by the RERC
on 19.06.2024, which has not been challenged before this Court.
Civil Appeal Diary No. 26876 of 2024
32 of 32
29. In view of the aforesaid analysis, we find no merit in this appeal. The
appeal stands dismissed, accordingly.
30. Pending application(s), if any, shall stand disposed of.
...………………………. J.
(M. M. SUNDRESH)
…………………………. J.
(RAJESH BINDAL)
NEW DELHI;
MAY 23, 2025
Legal Notes
Add a Note....