Contract dispute, Writ Petition, Arbitrary action, Natural Justice, Promissory Estoppel, Public contracts, JDA Jaipur, OTS Flyover, Rajasthan High Court
 02 Jun, 2026
Listen in 01:56 mins | Read in 159:00 mins
EN
HI

JCL Infra Private Limited Vs. Jaipur Development Authority and Ors.

  Rajasthan High Court S.B. Civil Writ Petition No. 17571/2024
Link copied!

Case Background

As per case facts, JCL Infra Private Limited was awarded an EPC contract for traffic improvement and beautification at OTS Crossing, Jaipur, based on a Detailed Project Report (DPR). The ...

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

[2026:RJ-JP:20730]

HIGH COURT OF JUDICATURE FOR RAJASTHAN

BENCH AT JAIPUR

S.B. Civil Writ Petition No. 8120/2025

JCL Infra Private Limited, Having Its Registered Office At

Industrial Estate, Delhi Road, Partapur, Meerut - 250103 Through

Its Managing Director Mr. Ajai Kumar Gupta.

----Petitioner

Versus

1. Jaipur Development Authority, Through Its Secretary,

Ram Kishor Vyas Bhawan, Indira Circle, Jawahar Lal

Nehru Marg, Jaipur-302004.

2. Commissioner, Jaipur Development Authority, Ram Kishor

Vyas Bhawan, Indira Circle, Jawahar Lal Nehru Marg,

Jaipur Rajasthan, 302005.

3. Executive Engineer - ROB/RUB-V, Jaipur Development Au -

thority, Ram Kishor Vyas Bhawan, Indira Circle, Jawahar

Lal Nehru Marg, Jaipur-302004

----Respondents

Connected With

S.B. Civil Writ Petition No. 17571/2024

JCL Infra Private Limited, Having Its Registered Office At Indus-

trial Estate, Delhi Road, Partapur, Meerut - 250103 Through Its

Authorized Signatory Mr. Ajai Kumar Gupta.

----Petitioner

Versus

1. Jaipur Development Authority, Through Its Commissioner,

Ram Kishor Vyas Bhawan, Indira Circle, Jawahar Lal

Nehru Marg, Jaipur - 302004.

2. Jaipur Development Authority, Through Its Executive En-

gineer - Traffic - Ii, Room No. 110, Ff, Main Building, Ram

Kishor Vyas Bhawan, Indira Circle, Jawahar Lal Nehru

Marg, Jaipur - 302004.

3. Sincere Architects Engineers Pvt. Ltd., 42, Lal Singh Judo

Colony, Near Jaipuria Hospital, Tonk Road, Jaipur, Ra -

jasthan - 302018. Through Its Authorized Signatory.

----Respondents

[2026:RJ-JP:20730] (2 of 106) [CW-8120/2025]

For Petitioner(s) : Mr. S. S. Hora with

Mr. Adesh Arora

Mr. OP Singh Tanwar

For Respondent(s) : Mr. Amit Kuri with

Mr. Ayush Sharma

Mr. Devendra Gupta, Director

Engineer JDA-1

HON'BLE MR. JUSTICE SAMEER JAIN

JUDGMENT

REPORTABLE :

1.Arguments Concluded on: 23.04.2026

2.Judgment Reserved on: 23.04.2026

3.Full Judgment/Operative Part Pronounced:Full Judgment

4.Pronounced on: 02.06.2026

1. In the present batch of writ petitions, the scope of the

controversy involved, albeit not limited to but is broadly and

predominantly defined as enumerated ad infra:

SBCWP No. 8120/2025: Is filed assailing the arbitrary and

illegal actions of the respondents whereby the respondents have

re-invited tender including the component of OTS Flyover in

respect of preparation of detailed project report (hereinafter

referred to as ‘DPR’) for proposed elevated road from Transport

Nagar to Balagi Tri Junction, Jagatpura and from Jothwara at OTS

junction, JLN Marg, JDA Jaipur, to extent of flyover at OTS

Junction vide NIB No. EE-ROB/RUB-B/01/2025-26 dated

03.04.2025; primarily being governed by the Public Works

Financial and Accounts Rules, Part-II.

SBCWP No. 17571/2024 : Is filed assailing the letter dated

24.04.2024 issued by the Jaipur Development Authority

[2026:RJ-JP:20730] (3 of 106) [CW-8120/2025]

(hereinafter referred to as ‘JDA’), thereby withdrawing the work

allotted to the petitioner vide the Letter of Acceptance No.

JDA/EE/TR WORKS-II/LOA/2022-2023/DEC/01 (hereinafter

referred to as ‘LoA’) dated 14.12.2022, without affording any

rationale of such withdrawal.

Consequently, considering the fact that the writ petitions

warrant adjudication on common questions of law and fact; with

the consent of learned counsel appearing on behalf of all the

parties, S.B. Civil Writ Petition No. 8120/2025 titled as JCL

Infra Private Limited V. Jaipur Development Authority and

Ors. is being taken up as the lead case. It is cautiously clarified

that any discrepancies in the present batch of writ petitions,

pertain purely to the factual narratives contained therein and not

vis-a-vis the questions of law to be determined by this Court; the

instant judgment shall be applicable on both the petitions

connected herein/henceforth on mutatis mutandis basis.

SUBMISSIONS ADVANCED AND CONTENTIONS PROFFERED

BY THE LEARNED COUNSEL APPEARING FOR AND ON

BEHALF OF THE PETITIONER HEREIN ARE AD-SERIATIM:

2. At the threshold, and before adverting to the

substantive arguments, the chronological particulars giving rise to

the instant controversy, as submitted by the learned counsel

appearing for and on behalf of the petitioner are set forth

hereinbelow:

2.1 At the very outset, learned counsel appearing on behalf

of the petitioner submitted that the petitioner is a company duly

[2026:RJ-JP:20730] (4 of 106) [CW-8120/2025]

incorporated under the provisions of the Companies Act, 2013,

bearing CIN U24231UP1980PTC005098, and having its registered

office in Meerut. It was submitted that the petitioner has been

constrained to approach this Court on account of the manifestly

arbitrary, capricious, and unlawful actions of the respondent

authorities in re-inviting consultancy services for the preparation

of a DPR in respect of the OTS Flyover, notwithstanding the

undisputed position that the DPR for the said project had already

been prepared and the work stood duly awarded to the petitioner,

pursuant to a valid and concluded tender process, and that the

petitioner has, in furtherance thereof, incurred substantial financial

expenditure and mobilised significant resources of men and

machinery.

2.2 It was submitted that the respondents issued a Notice

Inviting Bid bearing NIB No. EE-ROB/RUB-B/01/2025-26 dated

03.04.2025 for “Consultancy Services for Preparation of DPR for

proposed elevated road from Transport Nagar to Balagiri Tri

Junction, Jagatpura and from Jhotwara ROB to Khatipura ROB and

flyover at OTS Junction, JLN Marg, JDA Jaipur.” Learned counsel

had clarified that the petitioner has confined its challenge only to

that segment of the impugned NIB which pertains to the OTS

Flyover, inasmuch as the said project had already been awarded to

the petitioner through a lawful tendering process and was already

under active execution.

2.3 Elaborating further, it was submitted that the petitioner

had been awarded the EPC contract vide LoA dated 14.12.2022

[2026:RJ-JP:20730] (5 of 106) [CW-8120/2025]

bearing No. JDA/EE TR Works-II/LOA/2022-2023/Dec/01 for the

work of “Traffic improvement and beautification work at OTS

Crossing, JLN Marg, JDA Jaipur,” which was predicated upon a DPR

earlier prepared by the respondents’ appointed consultants,

namely, Sincere Architects Engineers Pvt. Ltd. Pursuant thereto, a

valid and binding Contract Agreement bearing No. 01/2022-23

came to be executed between the parties on 27.12.2022, and that

the said DPR itself was the culmination of a prior tender process

wherein Sincere Architects Engineers Pvt. Ltd. had been duly

selected, and on the strength of which the petitioner emerged as

the successful bidder for execution of the EPC contract. Learned

counsel submitted that in pursuance of the said contract, the

petitioner duly mobilised its men, machinery, and financial

resources, and commenced execution of the work strictly in

accordance with contractual stipulations. The petitioner submitted

various survey reports, investigations, and detailed design

documents through communications dated 23.02.2023,

24.02.2023, 27.02.2023, 02.03.2023, and 13.03.2023, and

further sought requisite approvals, including vide letter dated

17.03.2023, for execution of the flyover and allied works at the

OTS crossing. It was vehemently contended that despite

scrupulous adherence by the petitioner to all contractual

obligations, inter alia, submission of disposal plans, traffic

movement plans, and detailed engineering drawings through

letters dated 22.03.2023, 27.03.2023, 11.04.2023, and

26.04.2023, the respondents failed to accord the necessary site

approvals, thereby stultifying the progress of the project. It was

[2026:RJ-JP:20730] (6 of 106) [CW-8120/2025]

submitted that the petitioner made repeated representations on

28.03.2023, 25.05.2023, 01.09.2023, 20.02.2024, and

05.01.2024 seeking approvals; however, the respondents

remained supine and failed to discharge their corresponding

contractual obligations.

2.4 As a consequence of such inaction, the petitioner has

suffered grave financial prejudice, with men and machinery lying

idle and investments aggregating approximately Rs. 40 Crores

already having been made, out of which work to the extent of Rs.

20.41 Crores stood completed and duly communicated to the

respondents. it was further submitted that despite repeated

requests, including communications dated 01.11.2023,

26.12.2023, and 20.02.2024, no payments were released by the

respondents, nor was any communication forthcoming.

Subsequently, to the utter astonishment of the petitioner, that the

respondents issued a letter dated 03.01.2024 alleging that no

drawings had been submitted, in complete disregard of the

extensive documentation furnished by the petitioner between

27.02.2023 and 03.01.2024. It was further contended that

paradoxically, thereafter, the respondents issued a project

extension letter dated 04.01.2024 extending the completion

timeline till 30.04.2024, thereby unequivocally acknowledging

both the subsistence of the contract and the satisfactory progress

of the petitioner’s work.

2.5 In response, to the said time extension the petitioner

furnished a comprehensive representation dated 05.01.2024

[2026:RJ-JP:20730] (7 of 106) [CW-8120/2025]

detailing the progress achieved and sought payment on account of

price variation arising from the extended contractual period

beyond twelve months, vide letter dated 08.01.2024; however,

the same elicited no response from the respondents. It was

further contended that during a meeting held on 01.03.2024,

certain concerns were raised regarding the technical feasibility of

the project at Jhalana Rotary and MNIT Gate opening; however,

the said concerns stood conclusively addressed by the

respondents’ own consultant, Sincere Architects Engineers Pvt.

Ltd., vide letter dated 26.03.2024, affirming the technical

feasibility of the project. Despite this, the petitioner’s subsequent

request for site instructions vide letter dated 27.03.2024 remained

unanswered.

2.6 Learned counsel submitted that in a gross violation of

the principles of natural justice and in complete arbitrariness, the

respondents, without affording any opportunity of hearing or

assigning cogent reasons, invoked Clause 32 of the contract and

withdrew the awarded work vide letter dated 24.04.2024. The

petitioner, aggrieved thereby, furnished a legal notice dated

10.05.2024 seeking revocation of the said withdrawal, which too

went unheeded. Thereafter, Sincere Architects Engineers Pvt. Ltd.

submitted a further communication dated 05.07.2024 enclosing

final drawings and reaffirming the feasibility of the project,

thereby dispelling any residual doubts. It was submitted that the

petitioner was constrained to furnish second legal notice dated

26.08.2024, which was similarly disregarded. Aggrieved by such

arbitrary withdrawal, the petitioner instituted S.B. Civil Writ

[2026:RJ-JP:20730] (8 of 106) [CW-8120/2025]

Petition No. 17571/2024 , wherein notices were issued on

18.12.2024 and duly served on 20.12.2024. However, during the

pendency of the said proceedings, the respondents proceeded to

re-invite consultancy bids for the very same project vide NIB

dated 03.04.2025, which, inter alia, includes the OTS Flyover,

despite the matter being sub judice and despite the petitioner’s

prior execution and substantial investment.

2.7 Learned counsel submitted that the impugned action of

re-inviting a DPR consultancy tender for the OTS Flyover is

nothing short of an attempt to restart the project de novo, in

brazen disregard of the DPR already prepared by Sincere

Architects Engineers Pvt. Ltd. and the petitioner’s execution of

work amounting to Rs. 20.41 Crores and investment of

approximately Rs. 40 Crores. Such conduct, is ex facie arbitrary

and violative of the doctrine of promissory estoppel, inasmuch as

the petitioner acted to its detriment on the basis of the

respondents’ unequivocal representations and contractual

assurances, and now stands placed in a position of severe financial

jeopardy. Learned counsel submitted that Clause 32 of the

contract contemplates only partial withdrawal of work and does

not sanction unilateral termination of the entire contract. The

respondents’ action in withdrawing the whole of the work under

the guise of Clause 32 is therefore wholly illegal, unsustainable,

and contrary to the express terms of the contract. It was further

submitted that the EPC contract provided for stage-wise

payments, which were liable to be sub-categorised in terms of the

[2026:RJ-JP:20730] (9 of 106) [CW-8120/2025]

corrigendum dated 20.10.2022, and the petitioner had duly

complied with the same vide its letter dated 31.01.2023.

3.Learned counsel appearing on behalf of the petitioner further

submitted that the petitioner is engaged, inter alia, in the

execution of large-scale infrastructure development projects,

possessing the requisite technical expertise, financial wherewithal,

and professional acumen for undertaking complex urban mobility

works. It was contended that the OTS Crossing situated on JLN

Marg, Jaipur, constitutes one of the most critically congested

traffic bottlenecks within the city, plagued by incessant vehicular

load and chronic traffic snarls. In order to ameliorate the said

congestion and to ensure a signal-free corridor facilitating

uninterrupted and seamless vehicular movement, coupled with the

augmentation of the aesthetic character of JLN Marg, the

respondents conceived a project for traffic improvement and

beautification of the said crossing, including the construction of a

flyover and allied infrastructural components. Thus, in furtherance

of the aforesaid objective, the respondents issued a tender inviting

bids for the execution of the said project, thereby initiating a

formal procurement process in accordance with law. The said bid

was invited under the following title:

"Traffic Improvement and beautification work at

OTS crossing JLN Marg, JDA Jaipur (Construction of

suspended bridge, Traffic Island, Roatries,

Underground art gallery, Pedestrian pathway,

Sculpture, fountain, improvement of existing

drainage system and road surface etc.) on

[2026:RJ-JP:20730] (10 of 106) [CW-8120/2025]

Engineering Procurement and Construction (EPC)

basis."

4. Learned counsel appearing on behalf of the petitioner

further submitted that the total EPC contract value, as delineated

in the LoA dated 14.12.2022, stood at Rs. 184.30 Crores. It was

submitted that the Special Conditions incorporating RPWR-100

were expressly made applicable and formed an integral part of the

contract (entered inter-se the parties) in terms of Annexure-19

i.e. the contract agreement, having been mutually agreed upon

between the parties. Learned counsel submitted that the

stipulated period for commencement and completion of the project

was from 06.01.2023 to 05.01.2024. However, the said period was

extended vide communication dated 04.01.2024 (Annexure-13) till

30.04.2024, thereby acknowledging the subsistence of the

contract and the continuing obligations of the parties.

Notwithstanding the same, in a wholly unilateral and ex parte

manner, the respondents invoked Clause 32 of the Contract

Agreement and withdrew the entire scope of work vide letter

dated 24.04.2024, which action has been impugned by the

petitioner in S.B. Civil Writ Petition No. 17571/2024 .

5. Learned counsel, in order to demonstrate the sequence

of events and the manifest arbitrariness of the respondents’

conduct, invited the attention of this Court to the following

chronology of material facts:

5.1 That initially, on 02.02.2021 and 03.02.2021, a Letter

of Acceptance was issued to consultants for preparation of the

DPR, followed by a work order amounting to Rs. 4.58 Crores

[2026:RJ-JP:20730] (11 of 106) [CW-8120/2025]

(Annexure-4). The said consultants prepared the DPR, which

subsequently formed the very foundation for the EPC tender

floated by the respondents and ultimately awarded to the

petitioner.

5.2 That on 14.12.2022, the respondents issued a LoA in

favour of the petitioner awarding the EPC contract for the OTS

flyover, based on the DPR prepared by the respondents’

consultants (Annexure-2). This culminated in the execution of a

formal Contract Agreement on 27.12.2022 between the petitioner

and the respondents, wherein RPWR-100 was incorporated as part

of the Special Conditions of Contract.

5.3 That on 31.01.2023, the petitioner addressed a

communication to the respondents proposing bifurcation of work

and stage-wise payments, as permissible under the corrigendum,

thereby demonstrating its readiness to proceed in a structured

and compliant manner (Annexure-24).

5.4 That on the same date, the respondents responded to

an earlier communication of the petitioner dated 30.01.2023,

raising certain queries and requirements with respect to site office

arrangements, GAD drawings, traffic diversion plans, and tree-

cutting permissions.

5.5 That in compliance thereof, the petitioner, vide letter

dated 23.02.2023, sought in-principle approval inter alia, general

Arrangement of Bridge Over Nallah on Gopalpur side [Drawing No.

OTS/JAIPUR/Nallah Bridge/01 (Conceptual Drawing)]; General

Arrangement of Flyover at OTS X-ing [Drawing No.

OTS/JAIPUR/Flyover/01 R-3]; Project Plan at OTS Crossing

[2026:RJ-JP:20730] (12 of 106) [CW-8120/2025]

[Drawing No.OTS/JAIPUR/OVERALL GAD Sheet 01 REV R-1];

Traffic Diversion Plan (Drg. No. OTS/JAIPUR/Traffic Diversion-

Sheet 01 REV 1); Land Acquisition Plan (Drg. No.

OTS/JAIPUR/Land Acquisition 01 Rev 1) thereby evidencing due

diligence and adherence to procedural requirements.

5.6 That despite continuous engagement, the petitioner,

vide letter dated 26.12.2023, once again apprised the respondents

of the mounting financial losses and requested payment for the

work already executed to the tune of Rs. 20.41 Crores. However,

in a stark departure from the factual record, the respondents

issued a communication dated 03.01.2024 alleging that no

drawings had been submitted by the petitioner, in complete

disregard of the extensive documentation furnished throughout

the year 2023.

5.7 That inconsistently, on the very next day i.e.,

04.01.2024, the respondents extended the project deadline till

30.04.2024 without any request from the petitioner, thereby

tacitly admitting that the delay was not attributable to the

petitioner.

5.8 That the petitioner, vide letter dated 05.01.2024,

referred to as many as eighteen prior communications and

reiterated that despite submission of all requisite drawings, plans,

and reports, no approvals or permissions had been granted,

resulting in substantial financial losses (Annexure-8). A

comprehensive list evidencing sixty-four communications sent by

the petitioner to the respondents was also placed on record

(Annexure-10).

[2026:RJ-JP:20730] (13 of 106) [CW-8120/2025]

5.8 That the petitioner, vide representation dated

08.01.2024, sought payment on account of price variation

occasioned by the extension of the contract beyond twelve

months. Thereafter, in a meeting culminating on 26.03.2024, the

respondents’ own consultants categorically clarified the technical

feasibility of the project, inter alia, stating that the proposed

structure would not interfere with the MNIT entrance and that the

rotary could be suitably shifted, thereby obviating the need for

additional land at OTS (Annexure-16, Pg. 489–491).

5.9 That in light of the aforesaid clarification, the petitioner,

vide letter dated 27.03.2024, requested directions to resume and

proceed with the pending work. However, instead of facilitating

execution, the respondents, in a wholly arbitrary and high-handed

manner, invoked Clause 32 of the Contract Agreement and

withdrew the entire project vide letter dated 24.04.2024, without

issuing any show cause notice or affording an opportunity of

hearing (Annexure-18).

5.10 That the petitioner promptly served a legal notice dated

10.05.2024 challenging the illegal withdrawal and seeking revival

of the project along with payment of outstanding dues amounting

to Rs. 20.41 Crores (Annexure-20). Thereafter, even the

respondents’ own consultants, vide communication dated

05.07.2024, furnished detailed drawings, including traffic

movement plans, land acquisition requirements, and general

arrangement drawings, thereby reaffirming the feasibility and

viability of the original DPR (Annexure-21).

[2026:RJ-JP:20730] (14 of 106) [CW-8120/2025]

5.11 That the petitioner issued a second legal notice dated

26.08.2024 reiterating its grievances, which also remained not

responded. In the interregnum, the respondents, vide letter dated

29.08.2024, called upon the petitioner to collect its bank

guarantees amounting to Rs. 5.52 Crores (Annexure P-4), which

were thereafter dispatched by post on 16.12.2024 (Annexure P-

5).

5.12 That the petitioner, vide letter dated 24.12.2024,

accepted the same under protest (Annexure P-6).

5.13 That in a most arbitrary and untenable development,

the respondents issued a fresh Notice Inviting Bid dated

03.04.2025 for preparation of a DPR for the same OTS flyover

project, valued at Rs. 6.67 Crores (Annexure-1, Pg. 34), thereby

effectively nullifying the earlier DPR, the concluded EPC contract,

and the petitioner’s substantial financial investment. Such action,

it was submitted, is ex facie illegal, arbitrary, and wholly

unsustainable in the eyes of law.

6. Learned counsel appearing on behalf of the petitioner

has assailed the impugned withdrawal notice dated 24.04.2024,

purportedly issued under Clause 32 of the Contract Agreement, as

being ex facie illegal, arbitrary, and vitiated by manifest non-

application of mind, qua which it was contended that the said

notice is liable to be set aside on, inter alia, the following grounds:

6.1 That the impugned notice is conspicuously vague,

bereft of reasons, and wholly non-speaking in nature, thereby

failing to disclose any intelligible basis for the drastic action

undertaken. Thus, such an unreasoned order stands in stark

[2026:RJ-JP:20730] (15 of 106) [CW-8120/2025]

contravention of the mandate of Clause 32 of the Contract

Agreement, which necessitates a reasoned determination founded

upon objective material and due consideration of relevant facts.

6.2 That the impugned notice itself contains a categorical

admission to the effect that the work under the contract could not

be completed within the stipulated or even the extended period on

account of prevailing site conditions and other attendant

circumstances. This, unequivocally establishes that the delay was

occasioned by factors beyond the control of the petitioner and,

therefore, cannot, by any stretch of reasoning, be attributed to

any default or lapse on the part of the petitioner.

6.3 That the impugned action is in flagrant violation of the

settled principles of natural justice. Clause 32 mandatorily

envisages that prior to invoking such a drastic measure, the

contractor ought to be afforded a reasonable opportunity of being

heard.

7. However, in the present case, no such opportunity was

granted to the petitioner, thereby rendering the action wholly

arbitrary and unsustainable in law. It was vehemently contended

that the doctrine of audi alteram partem has been palpably

breached, resulting in grave prejudice to the petitioner and

infringing the fundamental rights guaranteed under Articles 14,

19(1)(g), and 21 of the Constitution of India. In support of the

said contention, reliance was placed upon the ratio encapsulated

in State of Uttar Pradesh vs. Sudhir Kumar Singh & Ors.,

(2021) 19 SCC 706.

[2026:RJ-JP:20730] (16 of 106) [CW-8120/2025]

8. It was further submitted that a plain reading of Clause

32 would reveal that the power of withdrawal cannot be exercised

in respect of the entire contract on a wholesale basis. Rather, the

said clause contemplates invocation on a “risk and cost” basis,

confined to such portion of the work where failure is demonstrably

attributable to the contractor. In the present case, however, the

respondents have proceeded to withdraw the entire contract

without any such attribution or bifurcation, thereby acting in

patent excess of their contractual authority. Moreover, the

question as to whether the delay is attributable to the petitioner or

is a consequence of the respondents’ own lapses, as such failure

to hand over the site and non-approval of drawings, stands

conclusively answered in favour of the petitioner. It was submitted

that repeated delays on account of non-approval by the JDA

despite persistent follow-ups by the petitioner, are duly evidenced

from communications placed on record.

9. It was further contended that the conduct of the

respondents is wholly inconsistent with their present stance. The

grant of extension of time without imposition of any liquidated

damages, the unilateral release of the bank guarantee, and the

subsequent issuance of a fresh tender without invoking the “risk

and cost” mechanism or making any reference to Clause 2 of the

contract, collectively and unmistakably demonstrate that the delay

was neither attributable to the petitioner nor treated as such by

the respondents themselves. Learned counsel at this juncture had

drawn attention of the Court to the fact that the impugned

withdrawal notice itself acknowledges site-related impediments

[2026:RJ-JP:20730] (17 of 106) [CW-8120/2025]

and other extraneous factors, which, in essence, substantiates the

petitioner’s consistent stand. It was further submitted that

objections raised by MNIT/OTS in relation to site conditions and

execution constraints constituted the principal impediment in

carrying out the work, and these factors, being entirely beyond

the petitioner’s control, cannot be fastened upon it.

10. Further, it was contended that under the terms of the

Contract Agreement, the obligation to hand over the site in a

timely and workable condition squarely rested upon the

respondents, which obligation they have conspicuously failed to

discharge. In this regard, reliance was placed upon relevant

Clause in Annexure 3 I.e. contract dated 27.12.2022, which is

reproduced as under:

“Summary of Work

...

Lank is available. If additional land is required, then it

shall be made available by JDA."

11. Learned counsel further submitted that the petitioner

had duly invoked its contractual entitlement towards price

variation on account of delays attributable to the respondents, by

way of a detailed communication dated 08.01.2024 (Annexure–

15). It was contended that once such a claim has been raised in

consonance with the contractual stipulations, the respondents are

estopped from adopting a diametrically opposite stand so as to

attribute delay or non-performance upon the petitioner. Learned

counsel further submitted that the cumulative circumstances,

namely, persistent non-approval of drawings, failure to hand over

the site within time, grant of extension without levy of any penalty

[2026:RJ-JP:20730] (18 of 106) [CW-8120/2025]

or liquidated damages, and the unilateral return of the bank

guarantee, unequivocally establish the absence of any default on

the part of the petitioner.

12. It was further urged that it is a settled principle of

administrative law that an order must stand or fall on the reasons

contained therein, and the same cannot be supplemented by

subsequent affidavits or justifications sought to be introduced at

the stage of reply to the writ petition. Thus, any attempt on the

part of the respondents to improve upon or validate the impugned

action by introducing fresh grounds dehors the original record is

impermissible in law. In support of this proposition, reliance was

placed upon the dictum enunciated in Mohinder Singh Gill vs.

Chief Election Commissioner, (1978) 1 SCC 405.

13. Learned counsel had next contended that the present

case squarely attracts the doctrines of promissory estoppel and

legitimate expectation. It was submitted that acting upon the

unequivocal assurances and contractual obligations undertaken by

the respondents, the petitioner had mobilized extensive resources,

conducted surveys, prepared detailed drawings and designs,

procured requisite materials, and incurred substantial financial

expenditure. In such circumstances, it is impermissible for the

respondents to resile from their promise and arbitrarily withdraw

the project, particularly on account of extraneous considerations

such as a change in government or administrative stance;

nonetheless, such conduct, is antithetical to the principles of

fairness, reasonableness, and the well-established Wednesbury

doctrine governing administrative discretion. It was also

[2026:RJ-JP:20730] (19 of 106) [CW-8120/2025]

contended that the State, being an instrumentality under Article

12 of the Constitution of India, is under a constitutional and legal

obligation to act in a transparent, fair, non-discriminatory, and

reasonable manner. The impugned action, whereby the

respondents have unilaterally withdrawn the work order for

reasons attributable to their own lapses, constitutes a clear

abdication of such obligations.

14. In support of the submissions made insofar, learned

counsel had placed reliance upon, inter alia, IFGL Refractories

Ltd. vs. Orissa State Financial Corporation & Ors., 2020 SCC

OnLine SC 208; U.P. Power Corporation Ltd. vs. Sant Steels

& Alloys (P) Ltd., (2008) 2 SCC 777; and Sivanandan C.T.

vs. High Court of Kerala, (2024) 3 SCC 799.

15. It was further contended that the stand taken by the

respondents in their reply reveals that the issuance of a fresh DPR

was motivated by a change in governmental policy consequent

upon a change in political leadership; however, governance is a

continuous process, and the State, as a legal entity, remains

bound by its contractual commitments irrespective of political

transitions. Thus, the contractual obligations cannot be jettisoned

on account of shifting political considerations, as the same would

erode the sanctity of contracts and undermine public confidence in

governmental dealings. In the conspectus of the aforesaid facts,

learned counsel submitted that the project pertaining to the OTS

crossing was not conceived as an ad hoc or casual initiative, but

rather as a meticulously planned infrastructure undertaking of

considerable magnitude, aimed at alleviating traffic congestion

[2026:RJ-JP:20730] (20 of 106) [CW-8120/2025]

and ensuring seamless vehicular movement along the arterial JLN

Road, Jaipur. It was submitted that the petitioner has already

invested an amount approximating Rs. 40 Crores in furtherance of

the said project and has executed substantial portions of the work.

Thence, in such circumstances, the arbitrary withdrawal of the

contract, for reasons not attributable to the petitioner, amounts to

a gross breach of contractual and constitutional obligations.

Sequentially, whilst placing reliance upon the judgment passed in

Muhammed Nizar vs. State of Kerala, 2021 Supreme (Ker.)

636, and Vice-Chairman & Managing Director, City and

Industrial Development Corporation of Maharashtra Ltd. vs.

Shishir Realty Pvt. Ltd., (2022) 16 SCC 527, it was submitted

that the respondents cannot be permitted to take a volte-face

without cogent and legally sustainable justification, particularly

when such action undermines the sanctity of contractual relations

and adversely impacts public interest.

16. Learned counsel had also assailed the proposal of a

newly conceived flyover, contending that the same reflects a

regressive and restrictive approach towards traffic management

on JLN Road, allegedly undertaken to accommodate certain

influential institutions such as MNIT/OTS. In this regard, reliance

was placed upon the dictum encapsulated in State of Tamil

Nadu & Ors. vs. K. Shyam Sunder, (2011) 8 SCC 737. It was

next contended that the contractual framework governing the

petitioner permitted stage-wise payments and sub-categorization

of works, as envisaged under the EPC contract and specifically

delineated under the head “Payment” (Annexure–3). Learned

[2026:RJ-JP:20730] (21 of 106) [CW-8120/2025]

counsel submitteds that further clarification in this regard was

provided under Note–1 of the corrigendum dated 20.10.2022

(Annexure–23), and the petitioner had duly proposed bifurcation

and sub-categorization of works vide letter dated 31.01.2023,

thereby permitting rationalization or narrowing of scope along with

corresponding financial adjustments.

17. It was further submitted that the State is bound to act

fairly even in contractual matters, and the jurisdiction under

Article 226 of the Constitution of India is clearly maintainable

where the action of the State is arbitrary, illegal, or shocks the

conscience of the Court. In support of this proposition, reliance

was placed upon the dictum enunciated in Subodh Kumar Singh

Rathore vs. Chief Executive Officer & Ors., (2024) 15 SCC

461; ABL International Ltd. & Anr. vs. Export Credit

Guarantee Corporation of India Ltd., (2004) 3 SCC 553; and

Gujarat State Financial Corporation vs. Lotus Hotels (P)

Ltd., (1983) 3 SCC 379.

18. Additionally, it was submitted that the petitioner is

entitled to price variation strictly in terms of the contractual

provisions, for which a formal requisition had already been

submitted upon extension of the contract period. Reliance has

been placed upon Clause 45 of the RPWA-100 (Annexure–19),

which expressly governs the consideration and applicability of

price variation under stipulated conditions; and that the objection

raised by the respondents with regard to the locus standi of the

petitioner-company is wholly misconceived and untenable. It was

submitted that under Order XXIX Rule 1 of the Code of Civil

[2026:RJ-JP:20730] (22 of 106) [CW-8120/2025]

Procedure, the Managing Director is duly authorized to sign and

verify pleadings on behalf of the company. In the present case, a

valid Board Resolution dated 09.09.2024 (Annexure P–9) is placed

on record, authorizing the institution of the present proceedings.

Nevertheless, a company, being a distinct juristic entity, is fully

competent to authorize its directors or shareholders to act on its

behalf, and such authorization is, at best, a procedural

requirement. In support of this contention, reliance was placed

upon the authoritative pronouncement of the Hon’ble Supreme

Court in United Bank of India vs. Naresh Kumar, (1996) 6

SCC 660. Thus, it was stoutly pleaded that in view of the

aforementioned, the objection raised by the respondents deserves

to be rejected outright as being devoid of merit, and the instant

petitions deserve to be allowed.

SUBMISSIONS ADVANCED AND CONTENTIONS PROFFERED

BY THE LEARNED COUNSEL APPEARING FOR AND ON

BEHALF OF THE RESPONDENTS HEREIN ARE AD-SERIATIM:

19. Per contra, learned counsel appearing for the

respondents had, with considerable vehemence, opposed the

maintainability as well as the merits of the present writ petitions,

advancing the following submissions in a structured and multifold

manner:

20. At the very threshold, it was contended that the writ

petitions suffer from a foundational defect of maintainability,

inasmuch as they are not instituted by a duly authorized and

competent person on behalf of the petitioner-company. It was

submitted that no valid power of attorney or contemporaneous

[2026:RJ-JP:20730] (23 of 106) [CW-8120/2025]

authorization in favour of Shri Ajai Kumar Gupta was placed on

record, at the time of institution of the proceedings. Therefore, in

absence of such specific authorization, the petitions, filed

ostensibly on behalf of a juristic entity, are rendered non est in the

eyes of law, as per the ratio encapsulated in State of Travancore

v. Kingston Computers (P) Ltd., (2011) 11 SCC 524 ,; thus,

the proceedings initiated without proper authorization are liable to

be dismissed at the very inception, and so is the instant

petition(s).

21. It was further urged that the petitioner had approached

this Court with unclean hands and is guilty of gross suppression of

material facts; in this regard learned counsel submitted that

several communications issued by the JDA spanning a period of

approximately fifteen months, highlighting persistent deficiencies

in design, structural inadequacies, and non-compliance with

contractual obligations, have been deliberately withheld from the

Court, by the learned counsel representing the petitioner.

Nevertheless, such concealment, strikes at the very root of

equitable jurisdiction under Article 226 of the Constitution of

India, as also held in the ratio encapsulated in Prestige Lights

Ltd. v. State Bank of India, (2007) 8 SCC 449 , whereby it was

held that suppression of material facts disentitles a petitioner from

any discretionary relief. Further, on the substantive plane, it was

contended that the lis in question emanates purely from a

contractual relationship and is replete with seriously disputed

questions of fact. These include, inter alia, attribution of delay,

quantification of alleged pre-execution expenditure to the tune of

[2026:RJ-JP:20730] (24 of 106) [CW-8120/2025]

Rs. 20.41 Crores, interpretation and applicability of contractual

clauses, and the propriety of administrative decisions. It was

submitted that such issues cannot be adjudicated in writ

jurisdiction, which is ill-suited for evidentiary evaluation, and the

appropriate remedy lies before competent civil or commercial

courts for adjudication and award of damages; in support of the

said contention reliance was placed upon the dictum passed in

Radhakrishna Agarwal v. State of Bihar, (1977) 3 SCC 457.

22. Justifying the impugned action, learned counsel further

submitted that the withdrawal of the work order was squarely in

consonance with Clause 32 of the Contract Agreement, which

vests wide and unqualified discretion in the Engineer-in-Charge.

Elaborating the said contention, it was submitted:

22.1 That the Engineer-in-Charge constitutes a competent

authority under the contractual framework;

22.2 That Clause 32, by its very nature, permits withdrawal

of the work “for any reason whatsoever,” thereby conferring a

broad, non-restrictive power upon the respondents;

22.3 That multiple notices, correspondences, and review

meetings addressing delays, non-performance, and deficiencies

effectively constituted continuous notice to the petitioner, thereby

satisfying the requirements of natural justice, including the princi-

ple of audi alteram partem.

23. It was further contended that the EPC contract, being a

comprehensive and indivisible framework, does not admit of

unilateral modification, reduction, or re-categorization of work in

the manner suggested by the petitioner. Learned counsel had

[2026:RJ-JP:20730] (25 of 106) [CW-8120/2025]

additionally submitted that the respondents invoked the doctrine

of public trust and fiscal prudence, qua which it was submitted

that the decision to withdraw the contract was guided by

paramount public interest, particularly in light of the petitioner’s

failure to demonstrate any tangible progress over an extended

period of more than one year. It was argued that judicial review in

such policy-driven contractual decisions is exceedingly limited. To

support the said contention, learned counsel had placed reliance

upon the ratio enunciated in Jagdish Mandal v. State of Orissa,

(2007) 14 SCC 517 , and it was further submitted that where

public interest outweighs private commercial considerations, the

Court ought to exercise restraint. Auxiliary, amplifying the

allegations against the petitioner, it was contended that the

petitioner has acted in a manner tantamount to fraud by

suppressing critical facts pertaining to the submission and

approval of General Arrangement Drawings (GAD), which

constituted a sine qua non for commencement of substantive

work. Reference was made to the meeting dated 08.02.2023 and

document D-22 (letter dated 31.01.2023), evidencing that the

drawings submitted were grossly inadequate and fell short of

contractual requirements. It was further contended that the

petitioner lacks locus standi to assail the subsequent Notice

Inviting Bid (NIB) dated 03.04.2025 for DPR consultancy services,

on the following grounds:

23.1 That the earlier contract stood validly withdrawn under

Clause 32 of the GCC, thereby severing any subsisting legal

relationship;

[2026:RJ-JP:20730] (26 of 106) [CW-8120/2025]

23.2 That the fresh NIB pertains to an entirely distinct

project conceived under the Chief Minister’s Budget 2025–26,

involving construction of a flyover at the OTS junction with a

significantly altered financial outlay (Rs. 80 crores as against the

earlier Rs. 184 crores), rendering both projects mutually exclusive

and legally unconnected.

24. It was subsequently submitted that entertaining the

present petitions would set a deleterious precedent, enabling

unsuccessful or disgruntled contractors to stall or derail public

infrastructure projects through protracted litigation, particularly on

tenuous grounds of geographical or conceptual overlap. It is also

contended that any interim orders passed in the earlier

proceedings cannot enure to the benefit of the petitioner in the

context of the present, independent tender process. Learned

counsel reiterated that the appropriate forum for adjudication of

such disputes lies in a full-fledged civil or commercial trial, where

evidentiary appreciation can be undertaken, especially in light of

Sections 14 and 73 of the Indian Contract Act, 1872.

25. It was further emphatically contended that time was

the essence of the contract, which commenced on 06.01.2023 and

was to be completed by 05.01.2024. Despite repeated extensions

and opportunities, the petitioner failed to adhere to the stipulated

timelines and did not achieve even pro-rata progress. Apart from

delays, fundamental breaches of essential contractual conditions

are alleged, including failure to establish the JDA supervision

office, non-submission of comprehensive and approved drawings,

absence of a detailed traffic diversion plan in consultation with

[2026:RJ-JP:20730] (27 of 106) [CW-8120/2025]

traffic authorities, and failure to furnish periodic progress reports

and measurement records. Thus, the decision to withdraw the

contract was not arbitrary but was preceded by due application of

mind, taking into account multiple external factors such as

objections raised by MNIT Jaipur (letter dated 29.02.2024),

communications from OTS authorities (dated 19.02.2024),

concerns relating to the Bisalpur water tank, impediments in piling

operations, traffic management constraints, and the necessity to

reduce lane configurations from eight to six. These considerations

necessitated a fresh DPR and issuance of a new NIB aimed at

optimal utilization of public funds with reduced financial burden.

Learned counsel had placed reliance upon the ratio enunciated in

Air India Ltd. v. Cochin International Airport Ltd., (2000) 2

SCC 617, to submit that in matters of contractual and policy

decisions, the State enjoys considerable latitude, and a shift in

policy in furtherance of public good must prevail over private

commercial interests. Thus, the doctrines of promissory estoppel

and legitimate expectation are wholly inapplicable in the present

factual matrix, particularly in view of the petitioner’s own defaults,

negligible progress, and non-compliance with contractual

milestones. The extension of time and release of bank guarantees,

demonstrate the bona fide conduct of the respondents and cannot

be construed as admission of fault.

26. In culmination, it was submitted that the JDA has acted

as a prudent and model public authority, guided by considerations

of public interest, financial discipline, and contractual propriety.

The impugned action, being lawful, justified, and non-arbitrary,

[2026:RJ-JP:20730] (28 of 106) [CW-8120/2025]

warrants no interference under writ jurisdiction. Accordingly, it is

prayed that the writ petitions be dismissed with exemplary costs.

DELIBERATION OF RIVAL CONTENTIONS AND THE

ADJUDICATORY FINDINGS:

27. Upon according solicitous consideration to the rival

contentions advanced by the learned counsel qua the substantive

particulars delineated supra, and upon a meticulous scrutiny of the

documentary evidence in conjunction with the governing legal

tenets, the judgments cited at the Bar, and the records made

available for perusal by the respondent-JDA this court proceedeth

to record its opinion, noteworthy record and adjudicatory

determinations on the issues framed, ad-seriatim:

28. This Court has carefully perused the pleadings on

record, including the writ petitions, replies, rejoinders, and

additional documents placed before it. The original records

produced pursuant to the directions of this Court by the

respondent-JDA have also been minutely examined. Particular

attention has been accorded to the Contract Agreement dated

27.12.2022, the General and Special Conditions governing the

field, as well as the various communications exchanged between

the parties. Upon such comprehensive consideration, this Court is

of the opinion that certain aspects emerging from the record

assume material significance for adjudication of the controversy at

hand. A perusal of the original records produced by JDA, more

particularly File No. 5, which pertains to the financial bid and allied

decision-making process, reveals certain note sheets that throw

considerable light on the manner in which the impugned decision

[2026:RJ-JP:20730] (29 of 106) [CW-8120/2025]

came to be taken. These note sheets, forming part of the official

record, are relevant for examining the decision-making process

and the contemporaneous reasoning, if any, which guided the

respondents. The said note sheets, as extracted and reproduced

from the official records, are set out hereunder for ready reference

and consideration:

[2026:RJ-JP:20730] (30 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (31 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (32 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (33 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (34 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (35 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (36 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (37 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (38 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (39 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (40 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (41 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (42 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (43 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (44 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (45 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (46 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (47 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (48 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (49 of 106) [CW-8120/2025]

Relevant correspondence and note-sheets as on record of JDA, are

reproduced as under:-

[2026:RJ-JP:20730] (50 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (51 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (52 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (53 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (54 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (55 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (56 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (57 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (58 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (59 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (60 of 106) [CW-8120/2025]

[2026:RJ-JP:20730] (61 of 106) [CW-8120/2025]

29. Further, this Court also examined the Contract

Agreement along with the Special Conditions governing the

execution of the work. The relevant clauses of the Special

Conditions of Contract, as forming part of the record produced by

the respondent–JDA and applicable to the contractual relationship

inter se the petitioner and the respondents, are reproduced

hereinbelow for ready reference and proper appreciation of the

controversy:

Contract For Works

General Rules And Directions For the Guidance of

Contractors

Conditions of contract:-

Clause 1: Security Deposit

xxxxx

Clause 2: Compensation for Delay

xxx

Note: xxxxxx

The contractor shall, further be hornind to carry out

the work in accordance with the date and quantity

entered.

In case the delay inched to the tenderk is

attributable to the contractor, the spanwise

compensation, as lag down in this clause shall

be mandatory. However in case the slow

progess in on etime span is covered up within

original stipulated period then the amount of

such compensation levied earlier shall be

refunded. The price escalatiói, if any,

admissible under clause 45 of Conditions of

Contract would be admissible only on such

rates and cost of work, as would be

admissible if work would have been carrid out

in that particular time span. The Engineer-in.

charge shall review the progress achieved in every

time span, and grant stagewise extension in čase of

slow progress with compensation, if the delay is

attributable to contractor, otherwise without

compensation.

However, if for any special job, a time schedule has

been submitted by the contractor before execution

of the agreement, and it is entered in agreement as

[2026:RJ-JP:20730] (62 of 106) [CW-8120/2025]

well as samé has been accepted by the Engineer-

in-charge, the contractor shall complete the work

within the said time schedule. In the event of the

contractor failing to comply with this condition, he

shall be liable to pay compensation as this clause

shall not exceed 10% of the value of the contract.

While granting extension in time attributable to the

Government, reasons shall be recorded för each

delay.

Clause 3 : Risk & Cost Clause

The Engineer-in-charge or the Competent Authority

defmd under rules may, without prejudice to his

rights against the Contractor, in respect of any

delay or inferior workmanship or otherwise, or any

claims för damages in respect of any breaches of

contract and without prejudice to any rights or

remedies under any of provisions of this contract or

otherwise, and whether the dáte för completion has

or has not clapsed by notice in writing, absortek

determine the contract in any of the following

cases.

(i) If Contractor having been given by the

Engineer-in-charge, a notice in writing to

rectify, reconstruct or replace any defective

work or that the work is being performed in

any inefficient or otherwise improper or

unworkmanlike manner, shall omit to comply

with the requirements of such notice för a

periód of seven days, thereafter, or if the

contractor shall delay or suspend the

execution of the work so that either in the

judgement of the Engineer-in-charge (which

shall be final-and binding) he will be unable to

secure completion of the work by the dáte för

completion of he already, failed to complete

ihe work by that date.

(ii) If the Contractor, being company, shall pass a

resolution or the Court shall make an order that the

company shall be wound up or if a receiver or a

manager, on behalf of a creditor, shall be appointed

or if circumstances shall arise, which entitle the

Court or Creditor to appoint a receiver or a

manager or which entitle the Court to make a

winding up order.

[2026:RJ-JP:20730] (63 of 106) [CW-8120/2025]

(iii) If the contractor commits breach of any

of the terms and conditions of this contract.

(iv) If the Contractor commits any acts

mentioned in Clause 19 hereof.

when the Contractor has made himself liable for

action under any of the cases aforesaid, the

Engineer-in-charge on behalf of the Governor of

Rajasthan shall have powers ...

a)To determine or rescind the contract, as

aforesaid (of which determination or

rescission notice in Contractor under the hand

of the Engineer-in-charge shall be conclusive

evidence) upon such determination or notice

in writing to the rescission, the earnest

money, full security deposit of the contract

shall be liable to be forfeited and shall be

absolutely at the disposal of the Government.

b)To employ labour paid by the Department and to

supply materials to debiting the Contractor with the

cost of the labour and the price of the materials (of

the amount of which cost and price materials to

carry out the work or any part of the work, certified

by the Engineer-in-charge shall be final and

conclusive against the Contractor) and crediting

him with the value of the work done in all respects

in the same manner and at the same rates, as if it

had been carried out by the Contractor under the

terms of this contract. The certificate of the

Divisional Officer, as to the value of the work done,

shall be final and conclusive evidence against the

Contractor provided always that action under the

sub- clause shall only be taken after giving notice

in writing to the Contractor. Frivided also that if the

expenses incurred by the department are less than

amount payable to the Contractor at his agreement

rates, the difference shall not be paid to the

Contractor.

c)After giving notice to the Contractor to measure

up the work of the contractor and to take fuch part

thereof, as shall be unexecuted out of his hands

and to give it to another contractor to complete, in

which čase any expenses which may be "incurred in

excess of the sum which would have been paid to

the original contractor, if the whole work had been

executed by him [of the amount of which excess,

the certificate in writing of the Engineer-in-charge

[2026:RJ-JP:20730] (64 of 106) [CW-8120/2025]

shall be final and conclusivej shall be borne and

paid by the originál contractor and may be

deducted From any money due to him by

Government under this contractor on any other

account. Whatsoever, or from his Earnest money.

Security Deposit, Enlistment security or the

proceeds or sales therof, or a'ufficient part thereof

as the ease may be. In the event of any one or

more of the above courese being adopted by the

Engineer-in-charge, the contractor shall have no

claim to compensation tor any loss sustained by

him by reason of his having purchased or procured

any materials or entered into any engagements or

made any advances on account or with a view to

the performance of contract. And, in čase action is

taken under any of privisions aforesaid, the

Contractor shall not be exaction of the work or the

entitled to recover or be paid, any work thereof or

actually performed under this contract unless and

the Engineer-in-charge has certified, in writing, the

performance of such work and the value payable in

respect thereof, and he shall only be entitled to be

paid the value so certified.

Clause 4: Contractor remains liable to pay

compensation, if action not taken under

Clause 3:

i) XXXXX

ii) In the event of the Engineer-in-charge

putting in force, powers vested in hins under

the precedin.' Hause 3 he may, if he so

desires, také possession of all or any tools,

plants, maierials and stores, in or upon the

works or the sue, thereof, or belonging to the

contractor or procured by him and inteded to

be used for the excction of the work or any

part thereof, paying or allowing for the same

in account, at the contract rates or, in čase of

these not being applicable, at current market

rates, to b artified by the Chief Engineer or

duly authorised Engineer [whose certificate,

thereof, shall be final and conclusive]. therwise

the Engineer-in chargé may, bè notice in writing to

the contractor or his clerk of the works, foreman,

or other authorised agent, require him to remove

such tools plánt, materials or stores form the

[2026:RJ-JP:20730] (65 of 106) [CW-8120/2025]

premises [within a time to be specified such

notice), and in the event of the Contractor failing to

comply with any requisition, the Chief Engineer or

other duly athorised Engineer may remove them at

the contractors expenses seTl them by auction or

priváte såle on.ccount of the contractor and at his

risk in all respects, and the certificat; of the Chief

Engineer or other duly authorised Engineer is to the

expense of any such removai, and the amount of

the proceeds and expense of any such Såle shall be

final and conclusive against the Contractor.

Clause 13: No compensation fór alteration in

or restraction of work to be carried out:

If, any time after the commencement of the

work, the Government, shall för any reason,

whatsoever, not require the whole work

thereof, as specified in the tender, to bé

carried out, the Engineer-in-charge shall give

notice in writing, of the fact to the Contractor,

who shall have no claim to any paymentys or

compensation, whatsoever, on account of any

profit or advantage which he might have

derived from the execution of the work in full

but which he did not derive in consequence of

the full amount of the work not having been

carried out, Neither, shall he have any claim

för compensation by reasons of alterations

having made in the originál specifications,

drawings and design and instructions, which

shall involve any cutrilment of the work, as

originally contemplated. Provided, that the

contractor shall be paid the charges for the

cartage only, of materials, actually brought to

theb site of the work by him för bonafide use

and rendered surplus as a result of the

adandonment or curtailment of the work any

portion thereof, and taken them back by the

Contractor provided, however that the

Engineer-in-charge shall have, in all such

cases, the option of taking over all or any

such materials at their purchase price or at

local market rates whichever may be less. In

the čase of such stores, having been issued from

Government stores, charges recovered, including

storage charges shall be refunded after lacking into

[2026:RJ-JP:20730] (66 of 106) [CW-8120/2025]

consideration any deduction fór claim on account of

any deterioration or damage while in the custody of

the contractor, and in this respect the decision of e

Engineer-in-charge shall be final.

Clause 21: Standing Comniittee for Settlement

of disputes:

If any question, difference of objection,

whatsoever shall arise in any way, in

connection with of arising out of this decision

of any such matter, as herein before provided

has been otherwise provided for and whether

it has been finally decided Instrument of the

meaning of operation of any part thereof, of

the right duties or liabilites of either part

then, save in so far, as the accordingly, or

whether the contract should be terminated, or

has been rightly terminated and as regards

the rights or obligations of the parties as the

result of such termination, shall be referrred

for decision to the empowered Standing

Committe, which would consist of the

followings.

(i) Addutinistrative Secretary concerned.

(ii) Finance Secretary or his nominee, not below the

rank of Deputy Secretary and/or Chief Accounts

officer

(iii) Law Secretary or his nominee, not below the

rank of Joint Legal Remembrancer.

(iv) Chief Engineer-cum-Addi, Secretary of the

concerned department.

(v) Chief Engineer concerned (Member-Secretary)

The Enginner-in-chargem on receipt of application

alon with non refufndable prescribed fee, (the fee

would be two percent of the amount in dišpute, not

exceeding Rs. One lac) from the contractor shall

refer the disputes to the committee within a periód

of oné month from dnte of receipt of application.

Procedure and Application för referring cases

för settlement by the Standing Committee

shall be as given in Form RPWA90

Clause 32: Withdrawal of work from the

Contractor:

If the Engineer-in-charge shall at any time

and för any reasons, whatever, including

inability to maintain prorata progress think

[2026:RJ-JP:20730] (67 of 106) [CW-8120/2025]

any portion of the work should not be

executed or should be withdrawn from the

contractor, he may by notice in writing to that

effect require the Contractor not to execute

the portion of the work specified in the notice,

or may withdeaw from the Cotractory the

portion of work, so specified, and the

Contractor shall nột bé entitled to any

compensation, by reason of soul portion of

work having been withdrawn from him. The

Enginee-in-chagre may supplement the work

by engaging another agerevare d portion of

the work at the cost of the originalo

contractory without prejudice to his rights

under clause 2 clause 2. He allo be competent

to levy compensation för delay in progress.

The recovery of excess cost shall be made

from next availar 3 running bili or any other

claim and shall nôt bé deferred.

Clause 37: Refund of Security Deposit:

Security will be refunded after the expiry of

the periód as prescribed below :-

(a) In case of contract relating to hiring of trucks

and other T &P trasnporation including the loading

unloading of materials, the amount of Security

Deposit is refundable alon with the final bill

(b) Suppliers of material: As per privisions of the

G.F. & A.R.

(c) Ordinary repairs: 3 months after completion of

the work provided the final bili has been paid.

(d) Originál works/special repairs works: Security

deposit will be refunded six months after

completion, or expiry of oné full rámy season, or

after expiry of defect liability periód as defined in

the special condition of agreement, whichever is

later provided the final bili has been paid.]

(e) In čase of PWD originál works/special repairs

works costing more than Rs. 10.00 lacs, partial

amount of Security Deposit will be refunded during

the defect liability periód @ 10% of ŠD amount

after lapse of one year of completion and there

after 10% of originál amount of ŠD at the end of

each subsequent year. The remaining amount of

ŠD bé refunded after the expiry of defect

liability periód.

[2026:RJ-JP:20730] (68 of 106) [CW-8120/2025]

Clause 45: Price Variation Clause:

If, during the progress of the contract of value

exceeding Rs. 50 lackh (accepted tendered

amount minus cost of im supplied 'by the

department), and where stipulated

completion period'is more than 3 months

(both the conditions shoi fulfilled), the price,

of any

materials/bitumen/diesel/petrol/cement arid

steel incorporated'in the works (nôt being

materials supplied by the department) and/or

wages of labour- increases or decreases, as

compared to the price and/or wages prevail;

the last dáte of submission of bids the

amounts payable to contractors for the work

shall be adjusted for increase or decrease in

the rates of materials (excepting those

materials supplied y the

department)/labour/bitumen/diesel and

petrol/cement/steel.

'[Increase or decrease in the cost of labour

/material/bitcemen/diesel/petrol and cement steel

shall be calculated quarter accordance with the

following formula:]

Clause 46: Force Majeure:

Neither party shall be liable to each other, för any

loss or damage, occasioned by or arising out of acts

or God such-as unprecedented floods, volcanic

eruptions, earthquake of other invasion of nature

and other acts.

Clause 48: Post payment Audit & Technical

Examination:

The Government shall have right to cause an

audit and technical examination of the works,

and the final bills of the contractor, including

all supporting vouchers, abstracts etc., to be

made witha-years after payment of the final

bili, and if, as a result of Such audit and

technical examination, any súm is found to

have been over paid in respect of any work

done by the Contractor under the contract/or

any work claimed by him to have been done

by him under the contract and found not to

have been executed below specification, the

[2026:RJ-JP:20730] (69 of 106) [CW-8120/2025]

Contractor shall be liable to refund the

amount of over payment,, and it shall be

lawful för department to recover the same

from him in the manner prescribed in Clause

50 or in any other manner legally permissible

and if it is found that the contractor was paid

less than what was due to him under the

contract in respect of any work executed by

him under it, the amount of such under

payment shall be duly paid by the Government

to the Contractor.

Clause 50: Recovery from Contractors:

Whenever any claim against the Contractor

for the payment of a sum of money arises out

of or under the contract, the Department shall

be entitled to recover šuch súm bé

appropiating in part or whole of the

Performance Guarantiee and/or Sceruity

Deposit. Security Deposit at the time of enlistment

of the Contractor. In the event of the security being

insufficinet, or if no security has been taken,

therealfirt,, may become due to the Contractor,

under this or any other contract with the Governor

of Rajasthan. Should this súm bé nôt sufficient to

cover the full amount recoverable the Contractor

shall pay to he Department on demand the balance

remaining dues.

The department shall, further, háve the right to

effect such recoveries under Public Demands

Recovery Act."

30. On the basis of the material available on record, the

terms and conditions of the Contract Agreement, as well as the

original files produced by the respondent–JDA, the following

factual and legal aspects emerge for consideration:

30.1 It is borne out from the record that pursuant to the

Budget Declaration for the financial year 2021–2022, the Hon’ble

Chief Minister of the State, under the then existing Government,

envisaged development of the OTS Crossing, situated on the

[2026:RJ-JP:20730] (70 of 106) [CW-8120/2025]

prominent Jawahar Lal Nehru Marg (JLN Marg), Jaipur. The said

location, being one of the most congested traffic bottlenecks in the

city, was identified for comprehensive infrastructural intervention

with the avowed objective of ensuring signal-free movement of

traffic, easing congestion, and enhancing the aesthetic value of

the corridor.

30.2 In furtherance thereof, a tender came to be floated by

the Jaipur Development Authority (JDA) with an extensive and

composite scope of work, which, inter alia, included “Traffic

Improvement and beautification work at OTS Crossing, JLN Marg,

JDA Jaipur (Construction of suspended bridge, traffic island,

rotaries, underground art gallery, pedestrian pathways, sculptures,

fountains, improvement of existing drainage system and road

surface, etc.) on Engineering, Procurement and Construction

(EPC) basis.”

30.3 The nature of the project thus reflects that it was not

merely a construction contract but a holistic urban infrastructure

project conceived with both functional and aesthetic objectives.

30.4 The record further reveals that the total contract value

under the EPC mode was quantified at Rs. 184.30 Crores. The

Letter of Acceptance (LOA) was issued in favour of the petitioner

on 14.12.2022, followed by execution of the formal Contract

Agreement on 27.12.2022, governed by the General Conditions

(RPWR-100) and the Special Conditions forming part thereof.

30.5 As per the contractual stipulations, the date of

commencement of the work was fixed as 06.01.2023, with a

stipulated period of completion of 12 months, i.e., by 05.01.2024.

[2026:RJ-JP:20730] (71 of 106) [CW-8120/2025]

It is an admitted position that during the subsistence of the

contract, the respondent–JDA granted suo motu extension of time

up to 30.04.2024, without levy of any penalty.

30.6 However, prior to the expiry of the extended period, the

respondents issued a communication dated 24.04.2024,

purporting to withdraw the contract by invoking Clause 32 of the

Special Conditions of Contract, which constitutes the primary

cause of action for the present proceedings.

30.7 It is further noteworthy that subsequent to such

withdrawal, the respondents proceeded to release the petitioner’s

bank guarantees on 16.12.2024, unconditionally. The petitioner,

however, accepted the same under protest, thereby preserving its

right to challenge the underlying action.

31. The petitioner has, thus, approached this Court by way

of the present petitions, assailing the legality and validity of the

withdrawal of the work order dated 24.04.2024 as being arbitrary

and unsustainable; and challenging the subsequent issuance of a

fresh Notice Inviting Bid (NIB) dated 03.04.2025, to the extent it

pertains to preparation of a DPR for the OTS flyover project,

during the pendency of the earlier writ petition. In light of the

above factual matrix, it is evident that the first cause of action

arose upon issuance of the withdrawal letter dated 24.04.2024,

whereby the respondents unilaterally rescinded the contract. The

legality, justification, and sustainability of the said communication

thus assume central importance in the adjudication of the present

dispute. The contents of the said withdrawal letter dated

24.04.2024, being material for examining the decision-making

[2026:RJ-JP:20730] (72 of 106) [CW-8120/2025]

process and the reasons recorded therein, are reproduced

verbatim hereunder:

"The aforesaid work was awarded to you vide this

office Work Order No JDA/EE TR

Works-II/WO/2022-2023/Dec/01 dated

27.12.2022 amounting Rs. 1,84,30,00,000.00

with stipulated dates of commencement and

completion as 06.01.2023 and 05.01.2024

respectively. The work was not started during the

stipulated period and also cannot be taken-up as

per EPC stipulation due to site conditions and

various to reasons. Therefore, the competent

authority of JDA has taken action as per the

relevant clause of agreement (R.P.W.R. 100) and

decided to withdraw the whole work of "Traffic

improvement and beautification work at OTS

crossing JLN Marg, JDA, Jaipur (Construction

of suspended bridge, Traffic island, Rotaries,

Underground art gallery, Pedestrian pathway,

Sculpture, fountain, improvement of existing

drainage system and road surface, etc.) on

Engineering, Procurement and Construction

(EPC) basis" amounting to Rs. 18430.00 lakhs

under Clause-32 of the Contract Agreement

(R.P.W.R. 100)."

32. The subsequent cause of action arose during the

pendency of the earlier writ proceedings, upon issuance of a fresh

Notice Inviting Bids (NIB) dated 03.04.2025 (Annexure–1),

whereby the respondents initiated a new tendering process for

preparation of a Detailed Project Report (DPR), inter alia, covering

the development of the OTS flyover. The issuance of the said NIB

assumes significance for multiple reasons. Firstly, it pertains, at

least in part, to the very subject matter and geographical location

forming the basis of the earlier contract awarded to the petitioner.

Secondly, the initiation of a fresh tender process, without resolving

or lawfully terminating the existing contractual relationship, raises

[2026:RJ-JP:20730] (73 of 106) [CW-8120/2025]

serious concerns regarding the continuity, fairness, and

transparency of State action. It is the case of the petitioner that

the fresh NIB is not an independent or distinct project, but is

intrinsically connected with, and substantially overlaps the scope

of, the original contract, thereby rendering the same arbitrary and

legally unsustainable. The respondents, on the other hand, have

sought to justify the same as a policy decision based on a revised

DPR and altered project configuration. In these circumstances, the

issuance of the NIB dated 03.04.2025 constitutes a distinct and

recurring cause of action, giving rise to an independent challenge

in Writ Petition No. 8120/2025, while also having a direct bearing

on the legality of the earlier withdrawal of the petitioner’s

contract.

33. Consequently, for the purposes of clarity and procedural

convenience, this court proceed to frame the following issues for

its determination:

Issue No. 1: Whether the present petitions are maintain -

able, as the same revolve around a dispute which is con -

tractual in nature, and allegedly improper authorization of

the deponent?

34. The respondents have raised a preliminary objection

assailing the maintainability of the present writ petitions on two

counts: firstly, that the petition has not been instituted by a duly

authorized person on behalf of the petitioner-company; and

secondly, that the dispute arises out of a contractual relationship

and is, therefore, not amenable to writ jurisdiction.

[2026:RJ-JP:20730] (74 of 106) [CW-8120/2025]

(A) Objection regarding authorization of the deponent

35. Insofar as the first limb of objection is concerned, it

was contended that the writ petition has been filed by Mr. Ajai

Kumar Gupta, Managing Director of the petitioner–company,

without proper authorization. Upon consideration of the record,

this Court finds that the petitioner is a company, which is a juristic

person distinct from its shareholders and directors, and

necessarily acts through natural persons. It is not in dispute that

Mr. Ajai Kumar Gupta is not only a shareholder but also the

Managing Director of the petitioner-company and has executed

the contract in question on behalf of the company. A resolution

authorizing him in this regard has also been placed on record.

Thus, the legal position in this regard is no longer res integra, as

in the ratio encapsulated in United Bank of India vs. Naresh

Kumar, (1996) 6 SCC 660, it has been categorically held that

since a company is a juristic entity, pleadings on its behalf have to

be signed and verified by a competent person, and even in the

absence of initial authorization, such defect is curable and can be

ratified subsequently. Further, under Order XXIX Rule 1 of the

Code of Civil Procedure, a company is competent to authorize any

person to sign and verify pleadings on its behalf, and such

authorization need not necessarily be contemporaneous, but can

be established on record at any stage. Thence, in view of the

aforesaid settled legal position and the material available on

record, this Court is satisfied that the objection raised by the

respondents is purely technical in nature and stands duly cured.

Accordingly, the same is rejected.

[2026:RJ-JP:20730] (75 of 106) [CW-8120/2025]

(B) Objection regarding maintainability of writ petition in

contractual matters

36. The second limb of objection pertains to the

maintainability of the writ petition on the ground that the dispute

arises out of a contract. Albeit it is true that ordinarily disputes

arising out of contractual obligations are not entertained in writ

jurisdiction, the said rule is subject to well-established exceptions;

as where the action of the State or its instrumentalities is

arbitrary, violative of principles of natural justice, or involves a

public law element, the writ court would be justified in exercising

jurisdiction under Article 226 of the Constitution. In the present

case, it is not disputed that a validly executed EPC contract

existed between the parties. The grievance of the petitioner,

however, is not confined to mere enforcement of contractual

terms. Rather, the challenge is directed against the manner in

which the contract has been withdrawn.

37. The record reveals that the contract was withdrawn

vide order dated 24.04.2024, which is alleged to have been

passed ex parte, without affording any opportunity of hearing to

the petitioner. It was further contended that the invocation of

Clause 32 of the Special Conditions of Contract is misconceived

and dehors the contractual framework. Additionally, it has been

brought on record that extensions of time were granted by the

respondents, and bank guarantees were dealt with unilaterally,

indicating subsistence of the contractual relationship; the delay, if

any, was attributable to the respondents themselves; and

thereafter, a fresh tender was floated by altering and reducing the

[2026:RJ-JP:20730] (76 of 106) [CW-8120/2025]

scope of work, allegedly without safeguarding the petitioner’s

interests and without resorting to “risk and cost” provisions.

The petitioner has also invoked the doctrines of promissory

estoppel and legitimate expectation, asserting that the

respondents, having induced the petitioner to act upon the

contract and having permitted continuation of work through

extensions, could not have abruptly withdrawn the contract in an

arbitrary manner. The aforesaid facts, taken cumulatively,

demonstrate that the controversy involves allegations of

arbitrariness, lack of fairness, and violation of natural justice by a

State instrumentality, thereby introducing a clear public law

element into the dispute; and in such circumstances, this Court is

of the considered view that the present case falls within the

recognized exceptions where judicial review in contractual matters

is permissible. Accordingly, the writ petitions are held to be

maintainable. To extract more strength, this Court deems it

appropriate to assert reliance upon the ratio encapsulated in Tata

cellular v. Union of India: (1994) 6 SCC 651 , Sudhir Kumar

Singh (supra) and ABL International Ltd. (Supra). The

relevant portion of the Sudhir Kumar Singh (supra) is

reproduced as under:

"21. Dr Singhvi's preliminary objection as to Re-

spondent 1 having to approach a civil court, and

not a writ court, for actions that pertain to

breach of contract, need not detain us. In ABL

International Ltd. v. Export Credit Guarantee

Corpn. of India Ltd. [ABL International

Ltd. v. Export Credit Guarantee Corpn. of In -

dia Ltd., (2004) 3 SCC 553] , this Court held

[2026:RJ-JP:20730] (77 of 106) [CW-8120/2025]

that it was no longer res integra that a writ

petition under Article 226 of the Constitution

is maintainable at the instance of an ag -

grieved party to enforce a contractual oblig -

ation of the State or its instrumentality

when the State acts in an arbitrary manner,

as follows : (SCC pp. 564-67, paras 8-14)….

11. In Gujarat State Financial Corpn. v.

Lotus Hotels (P) Ltd. [Gujarat State

Financial Corpn. v. Lotus Hotels (P) Ltd.,

(1983) 3 SCC 379] this Court following an

earlier judgment in Ramana Dayaram

Shetty v. International Airport Authority of

India [Ramana Dayaram Shetty v.

International Airport Authority of India,

(1979) 3 SCC 489] held : (Gujarat State

Financial Corpn. case [Gujarat State

Financial Corpn. v. Lotus Hotels (P) Ltd.,

(1983) 3 SCC 379], SCC p. 380)

‘The instrumentality of the State which

would be “other authority” under Article 12

cannot commit breach of a solemn

undertaking to the prejudice of the other party

which acted on that undertaking or promise

and put itself in a disadvantageous position.

The appellant Corporation, created under the

State Financial Corporations Act, falls within

the expression of “other authority” in Article

12 and if it backs out from such a promise, it

cannot be said that the only remedy for the

aggrieved party would be suing for damages

for breach and that it could not compel the

Corporation for specific performance of the

contract under Article 226.’

22. This principle in ABL International Ltd.

[ABL International Ltd. v. Export Credit

Guarantee Corpn. of India Ltd., (2004) 3 SCC

553] has been consistently upheld by this

[2026:RJ-JP:20730] (78 of 106) [CW-8120/2025]

Court in Noble Resources Ltd. v. State of Orissa

[Noble Resources Ltd. v. State of Orissa,

(2006) 10 SCC 236], para 15; Food Corpn. of

India v. SEIL Ltd. [Food Corpn. of India v.

SEIL Ltd., (2008) 3 SCC 440], para 16;

Central Bank of India v. Devi Ispat Ltd.

[Central Bank of India v. Devi Ispat Ltd.,

(2010) 11 SCC 186: (2010) 4 SCC (Civ) 401],

para 28; and Surya Constructions v. State of

U.P. [Surya Constructions v. State of U.P.,

(2019) 16 SCC 794], para 3.

43. Judged by the touchstone of these tests, it

is clear that Respondent 1 has been completely

in the dark so far as the cancellation of the

award of tender in his favour is concerned, the

audi alteram partem rule having been breached

in its entirety. As has been correctly argued by

Shri Rakesh Dwivedi, prejudice has indeed been

caused to his client, not only from the fact that

one year of the contract period has been taken

away, but also that, if the impugned High Court

judgment [Sudhir Kumar Singh v. State of U.P.,

2019 SCC OnLine All 5798] is to be set aside

today, his client will be debarred from bidding

for any of the Corporation's tenders for a period

of three years.

45.We, therefore, uphold the impugned judg-

ment [Sudhir Kumar Singh v. State of U.P., 2019

SCC OnLine All 5798] of the High Court on the

ground that natural justice has indeed been

breached in the facts of the present case, not

being a case of admitted facts leading to the

grant of a futile writ, and that prejudice has in-

deed been caused to Respondent 1. In view of

this finding, there is no need to examine the

[2026:RJ-JP:20730] (79 of 106) [CW-8120/2025]

other contentions raised by the parties before

us."

Issue No. 2 – Whether the invocation of Clause 32 of the

Special Conditions of Contract and consequent withdrawal

of the contract is legally sustainable in the facts of the

present case?

38. This Court has carefully perused the impugned order of

withdrawal as well as Clause 32 of the Special Conditions of

Contract. A conjoint reading of the same indicates that invocation

of Clause 32 is not unfettered, but is conditioned upon the

existence of certain foundational requirements. The following

ingredients must necessarily be satisfied before resorting to such

drastic action:

(i) existence of a justifiable and valid reason;

(ii) failure on the part of the contractor to maintain the stipulated

progress of work;

(iii) lapse or default attributable to the contractor in execution of

any part of the work;

(iv) issuance of a specific notice in writing calling upon the

contractor to remedy such default and failure to comply therewith;

(v) consequent engagement of another agency for execution of

the work;

(vi) continuation of the work in public interest through such

alternate agency; and

(vii) invocation of “risk and cost” provisions, including recovery of

losses occasioned due to such default from the contractor.

[2026:RJ-JP:20730] (80 of 106) [CW-8120/2025]

39. Upon a meticulous examination of the record,

particularly the note-sheets spanning from the year 2023 till

20.04.2024, it emerges that although reasons were recorded for

withdrawal of the contract, the same were not attributable to any

default on the part of the petitioner. On the contrary, the material

on record demonstrates that the impediments in execution arose

on account of factors beyond the control of the petitioner, inter

alia, including operation of the Model Code of Conduct, which

restrained decision-making by the authorities; objections and

protests raised by MNIT, OTS; difficulties in shifting of the Bisalpur

pipeline; requirement of felling of a substantial number of trees;

and proposed alteration in the scope of work, which, as per the

respondents themselves, was not permissible under the EPC

framework. These circumstances clearly indicate that the delay, if

any, was institutional and administrative in nature, and cannot be

fastened upon the petitioner.

40. It is further noteworthy that the petitioner was granted

extension of time suo motu by the respondents, without

imposition of any liquidated damages or penalty, as contemplated

under the relevant contractual clauses. Even more significantly,

after withdrawal of the contract, the bank guarantees furnished by

the petitioner were released without any deduction or adjustment

towards alleged losses. Such conduct on the part of the

respondents unequivocally establishes that the petitioner was not

treated as being in default; no loss was attributed to the

petitioner; and thus the essential preconditions for invoking

Clause 32, particularly those relating to default and risk-and-cost

[2026:RJ-JP:20730] (81 of 106) [CW-8120/2025]

consequences, were conspicuously absent. Withal, in the absence

of these foundational requirements, the invocation of Clause 32

stands vitiated and unsustainable in law.

41. This Court likewise finds substance in the contention of

the petitioner that the stand now sought to be advanced by the

respondents is contrary to their own record; as the note-sheets

and contemporaneous correspondence, including letters dated

25.03.2023, 12.06.2024 addressed to the Chief Secretary,

communications from MNIT, the extension granted on 04.01.2024,

extending the contract till 30.04.2024, and the release of bank

guarantees on 29.07.2024, collectively demonstrate that the delay

was not attributable to the petitioner. It is a settled principle of

law that the validity of an administrative order must be judged on

the basis of the reasons contained therein and cannot be

supplemented by fresh reasons at a later stage. In this regard,

reliance is appositely placed on the principle laid down in

Mohinder Singh Gill (supra) , wherein it has been held that an

order must stand or fall on the reasons contained in it, and cannot

be improved upon subsequently, for orders “are not like old wine

becoming better as they grow older.” The relevant extract

therefrom is reiterated hereinbelow:

“8. The second equally relevant matter is

that when a statutory functionary makes an

order based on certain grounds, its validity

must be judged by the reasons so mentioned

and cannot be supplemented by fresh

reasons in the shape of affidavit or

otherwise. Otherwise, an order bad in the

beginning may, by the time it comes to

court on account of a challenge, get

validated by additional grounds later

[2026:RJ-JP:20730] (82 of 106) [CW-8120/2025]

brought out. We may here draw attention

to the observations of Bose, J. in

Gordhandas Bhanji [Commr. of

Police, Bombay v. Gordhandas Bhanji,

1951 SCC 1088 : AIR 1952 SC 16]:

“Public orders, publicly made, in

exercise of a statutory authority cannot

be construed in the light of explanations

subsequently given by the officer

making the order of what he meant, or

of what was in his mind, or what he

intended to do. Public orders made by

public authorities are meant to have public

effect and are intended to affect the actings

and conduct of those to whom they are

addressed and must be construed objectively

with reference to the language used in the

order itself.”

Orders are not like old wine becoming better

as they grow older.”

(Emphasis supplied)

42. In view of the aforesaid analysis, this Court holds that

the invocation of Clause 32 and the consequent withdrawal of the

contract is arbitrary, dehors the contractual framework, and

unsustainable in law, the essential preconditions for its invocation

having not been satisfied.

43. However, the pleadings in the reply affidavit and the

submissions advanced on behalf of the respondents by the Officer

In-charge Shri Sanjeevan Jain, and learned counsel representing

for and on behalf of JDA, qua the above-discussed appear to be an

afterthought and a misrepresentation of the factual position as

borne out from the official record. This Court cannot remain

oblivious to the conduct of the officers of the respondent–authority

and the submissions advanced on their behalf, which are found to

be contrary to the contemporaneous record and the contractual

[2026:RJ-JP:20730] (83 of 106) [CW-8120/2025]

framework governing the parties. Such conduct, particularly on

the part of a State instrumentality, deserves to be viewed

seriously and is accordingly taken note of adversely.

Issue No. 3 – Whether the Doctrines of Promissory

Estoppel and Legitimate Expectation be applicable in the

prevailing circumstances?

44. From the material placed on record, it stands

established that the petitioner, acting upon the assurances flowing

from a duly executed and legally enforceable EPC contract, had

altered its position to its detriment. The petitioner had mobilized

substantial resources, undertaken surveys, prepared drawings and

designs, procured materials to the extent of approximately Rs. 20

crores and incurred overall financial expenditure of nearly Rs. 40

crores in furtherance of the project. In such circumstances, the

principles of promissory estoppel and the doctrine of legitimate

expectation are clearly attracted. The respondents, having induced

the petitioner to act upon the contract and having permitted

continuation of the project over a considerable period, cannot be

permitted to resile from their promise in an arbitrary and

unilateral manner. The justification sought to be advanced by the

respondents, including change in Government or administrative

difficulties in execution of the project, cannot absolve them of

their obligations under a concluded and binding contract, as it is

well settled that State action must be informed by fairness,

reasonableness and non-arbitrariness, and the State cannot be

[2026:RJ-JP:20730] (84 of 106) [CW-8120/2025]

permitted to wriggle out of its contractual commitments on

extraneous or political considerations.

45. Thence, the impugned action of withdrawal of the

contract, coupled with the issuance of a fresh tender for

preparation of DPR, clearly indicates that the decision is not

founded on any contractual default attributable to the petitioner,

but is rather a consequence of a change in policy coinciding with

change in Government. Such action, in the considered opinion of

this Court, is arbitrary, capricious and violative of Article 14 of the

Constitution of India, and falls foul of the mandate governing

“State” under Article 12. In this regard, reliance placed by the

petitioner on the judgments in IFGL Refractories Ltd. (supra),

U.P. Power Corporation Ltd. (supra), and Sivanandan C.T.

(supra), is well-founded, as the said authorities reiterate that the

State and its instrumentalities are bound by the doctrines of

fairness, promissory estoppel and legitimate expectation, and

cannot act to the prejudice of a party who has altered its position

based on a representation or promise. Accordingly, the present

issue is answered in favor of the petitioner. Relevant portion of the

above said judgments can be summarized by reproducing the

relevant extract of the judgment IFGL Refractories Ltd.

(supra), which is as under:

“115. According to this Court, the true

principle of promissory estoppel seemed

to be that where one party has, by his

words or conduct, made to the other a

clear and unequivocal promise which is

intended to create legal relations or effect

[2026:RJ-JP:20730] (85 of 106) [CW-8120/2025]

a legal relationship to arise in the future,

knowing or intending that it would be

acted upon by the other party to whom

the promise is made. Where it is in fact so

acted upon by the other party, the

promise would be binding on the party

making it, and he would not be entitled

to go back upon it, if it would be

inequitable to allow him to do so, having

regard to the dealings which have taken

place between the parties. This would be

so irrespective of whether there is any pre-

existing relationship between the parties or

not.

116. It was further observed that it is not

necessary, in order to attract the applicability

of the doctrine of promissory estoppel, that

the promisee, acting on the promise, should

suffer any detriment. What is necessary is

only that the promisee should have

altered his position in reliance on the

promise. This Court was of the view that

the doctrine of promissory estoppel is

also applicable against the government,

where the government makes a promise

knowing or intending that it would be

acted upon by the promisee. Where, in

fact, the promisee, acting on it, alters his

position, the government would be held

bound by the promise. The promise would be

enforceable against the government at the

instance of the promisee, notwithstanding

that there is no consideration for the promise

and the promise is not recorded in the form

of a formal contract.

……..

[2026:RJ-JP:20730] (86 of 106) [CW-8120/2025]

133. This litigation is a fine specimen of the

bureaucratic lethargy. It is this bureaucratic

lethargy which gave rise to this long drawn

litigation. This Court in many of its decisions

has reminded various State Governments

that if the object of formulating the industrial

policy is to encourage investment,

employment and growth, the bureaucratic

lethargy of the State apparatus is clearly a

factor which will discourage

entrepreneurship.”

(Emphasis supplied)

Issue No. 4 - Nature, Scope, and Validity of the power

exercised under Clause 32 of the Contract by the

respondents:

47. In the present case, this Court finds that the delay in

execution of the project is not attributable to the petitioner, but is

squarely traceable to the respondents themselves. A bare perusal

of the impugned order dated 24.04.2024, purportedly issued

under Clause 32 of the Special Conditions of Contract, reveals that

no specific fault or breach has been imputed to the petitioner. The

impugned order employs vague and non-specific expressions such

as “site conditions” and “various reasons”, without delineating any

concrete default on the part of the petitioner. Such generalized

observations, in the absence of any specific finding of breach, fall

short of the requirements necessary for invoking a penal

contractual clause like Clause 32. On the contrary, the

contemporaneous record, including the note-sheets and official

correspondence placed before this Court ( inter alia,

[2026:RJ-JP:20730] (87 of 106) [CW-8120/2025]

communications addressed by the respondent–JDA to the Chief

Secretary; objections and correspondence emanating from MNIT,

OTS; difficulties in acquisition and handing over of clear and

encumbrance-free site; and other infrastructural and

administrative constraints affecting execution ), unequivocally

establishes that the impediments in execution existed from the

very inception of the contract till its withdrawal, and were entirely

beyond the control of the petitioner. The cumulative effect of

these documents clearly attributes the delay to systemic and

administrative shortcomings on the part of the respondent-JDA,

rather than any lapse on the part of the petitioner.

47. It is a settled principle that where delay is attributable

to the employer, the contractor cannot be penalized for non-

performance within the stipulated time . The absence of any

allegation of default, coupled with the existence of documented

impediments attributable to the respondents, renders the

invocation of Clause 32 wholly untenable. In this backdrop, it

becomes apposite to refer to the relevant provisions of the bid

document, particularly those contained in Schedule ‘C’ (Annexure–

3), which govern the obligations of the employer in providing

requisite site conditions and facilitating execution of the work. The

said clauses, which have a direct bearing on the issue at hand, are

reproduced hereunder:

“SCHEDULE C. – LIST OF DRAWINGS

TO BE SUPPLIED BY THE BIDDER

A.The successful bidder has to submit at

least three conceptual plans for the project

before the JDA committee and the committee

reserves the right for approval of plan.

[2026:RJ-JP:20730] (88 of 106) [CW-8120/2025]

B.The successful bidder has to submit the

planning and working drawings of approved

plan and finally to be vetted from MNIT/IIT

at his own cost. The structural design should

be prepared using latest software. The same

will need approval by JDA before execution.

C.The successful bidder must note that all

activities related to project must be completed

within 12 months of speculated period”

A condition for approval under the heading '"Scope of work &

specification" sub heading "Super-Structure" (Annexure-3) of the

Contract Agreement, which is reproduced as under:-

“SUPER STRUCTURE

1. The super structure shall be steel

based plate or composite girder of

grade E350 BR steel, preferably precast

and/or with sacrificial shuttering. The

make of steel plates can only be

SAIL/JINDAL/TATA STEEL. The contractor

shall be responsible for preparation of

QAP/WPSS and preliminary fabrication

drawings. After the preparation of these

documents, they shall be duly checked

and approved or get proof checked

from IIT/reputed institutions

empanelled consultant as approved by

EIC at his own cost and got approved

by JDA prior to use. Any direction by JDA

shall be incorporated as regards the same.

…..

21. All fabrication of structural steel work

should be carried out by Research Designs

and Standards Organization (RDSO) approved

vendors.”

48. The contractual framework, particularly the

aforementioned clauses as contained in Schedule ‘C’ (Annexure–

3), casts an obligation upon the employer to provide requisite site

conditions and facilitate unhindered execution of the work. Failure

[2026:RJ-JP:20730] (89 of 106) [CW-8120/2025]

on the part of the employer to discharge these foundational

obligations cannot be used as a ground to penalize the contractor.

Thus, in the present case, the material on record unmistakably

establishes that the respondents themselves failed to provide the

necessary conditions for execution of the project. Consequently,

the petitioner cannot be held responsible for non-achievement of

progress within the stipulated timeline.

49. In view of the aforesaid analysis, this Court holds that

the delay in execution of the contract is squarely attributable to

the respondents, and not to the petitioner. The essential

precondition for invoking Clause 32, namely default or failure on

the part of the contractor, being absent, the action of the

respondents in withdrawing the contract is rendered arbitrary,

unjustified, and contrary to the contractual provisions.

50. It is further noteworthy, that the contractual matrix

governing the parties unequivocally establishes that the obligation

to provide a clear, encumbrance-free site vested solely with the

respondent–JDA. The “Summary of Work” and the relevant clauses

of the Special Conditions of Contract make it abundantly clear that

the petitioner’s obligations were contingent upon the respondents

first fulfilling their foundational duties, namely:

(i)making available the land,

(ii)ensuring a clean and obstruction-free site, and

(iii)facilitating approvals of drawings and designs within a

reasonable time frame.

51. The record further demonstrates that the petitioner

had, in fact, diligently performed its reciprocal obligations. The

[2026:RJ-JP:20730] (90 of 106) [CW-8120/2025]

drawings and designs were prepared and submitted for approval;

procurement of steel was undertaken strictly from approved

manufacturers; and substantial mobilization of resources was

effected. However, the corresponding approvals and site

facilitation, which were prerequisites for meaningful execution,

remained pending due to administrative and institutional

constraints attributable to the respondents. The contemporaneous

correspondence forming part of the note-sheet assumes critical

importance. The letters exchanged between the parties, including

Annexure–13 i.e. letter dated 04.01.2024, whereby extension of

time was granted unilaterally without imposition of liquidated

damages, constitute a clear and unequivocal acknowledgment by

the respondents that the delay was not attributable to the

petitioner. This Court is of a stern view that in contractual

jurisprudence, such conduct amounts to a waiver of alleged

breach and operates as an admission against the employer .

Further, the petitioner’s representation/letter (Annexure–15)

seeking price variation upon extension of time reinforces the

position that the contract was treated as subsisting by both

parties. The respondents neither rejected the continuation of the

contract on grounds of default nor invoked any penal provisions

contemporaneously. Therefore, the fact of considerable

significance is that the respondents returned the bank guarantees

furnished by the petitioner without invoking Clauses 2, 3, and/or

37 of the Special Conditions of Contract, which otherwise provide

for consequences in the event of contractor default. This omission

is not merely procedural but substantive in nature, it thus,

[2026:RJ-JP:20730] (91 of 106) [CW-8120/2025]

unequivocally establishes that no breach or default was ever

crystallized against the petitioner.

52. In such circumstances, the subsequent invocation of

Clause 32 for withdrawal of work is ex facie inconsistent with the

prior conduct of the respondents and is legally untenable. A

contracting authority cannot approbate and reprobate, having

treated the contract as valid and subsisting, it cannot later

attribute delay to the contractor without any intervening material

change. This Court also finds substance in the petitioner’s

contention that the issuance of a fresh Notice Inviting Bid (NIB)

for preparation of a new DPR for the very same project is

manifestly arbitrary. The record does not disclose any rational or

technical basis necessitating a fresh DPR. On the contrary, the

material indicates that the core objectives of the project i.e.

decongestion of traffic, seamless flow, and enhancement of

aesthetic value of JLN Marg-remained unchanged across the

relevant period. In consequence, the attempt of the respondents

to draw a distinction between the projects of the years 2021–22

and 2024–25 is not borne out from any contemporaneous record.

Such a plea appears to be an afterthought devised to justify an

otherwise arbitrary decision, particularly when no substantive

alteration in scope, alignment, or purpose has been demonstrated.

53. Consecutively, it is equally germane to jot down that

the abrupt abandonment of the ongoing contractual process,

despite the petitioner having invested an amount exceeding Rs. 40

crores and the contract itself having been extended for a period of

two years, is not only inequitable but also violative of the

[2026:RJ-JP:20730] (92 of 106) [CW-8120/2025]

principles of fairness and reasonableness which govern State

action under Article 14 of the Constitution. The legal position in

this regard stands settled by the judgment of the Hon’ble

Supreme Court in K. Shyam Sunder (supra), wherein it has

been held that a change in government or policy cannot, by itself,

be a ground to annul or disturb a concluded and legally

enforceable contract, unless it is demonstrated that the earlier

decision was contrary to statutory provisions or against public

interest. The relevant extract from the ratio encapsulated in K.

Shyam Sunder (supra), is reproduced hereinbelow:

"35. Thus, it is clear from the above, that

unless it is found that act done by the

authority earlier in existence is either

contrary to statutory provisions, is

unreasonable, or is against public interest,

the State should not change its stand merely

because the other political party has come

into power. Political agenda of an

individual or a political party should not

be subversive of rule of law.”

(Emphasis laid)

54. The same has also been held in the dictum enunciated

in Shishir Realty Pvt. Ltd. (supra). The relevant portion of the

same is reproduced as under:-

"61. When a contract is being evaluated,

the mere possibility of more money in

the public coffers, does not in itself

serve public interest. A blanket claim by

the State claiming loss of public money

cannot be used to forego contractual

obligations, especially when it is not

based on any evidence or examination.

The larger public interest of upholding

contracts and the fairness of public

authorities is also in play. The courts need to

[2026:RJ-JP:20730] (93 of 106) [CW-8120/2025]

have a broader understanding of public

interest, while reviewing such contracts.

63. Similarly, this Court in A.P. Dairy

Development Corpn. Federation v. B.

Narasimha Reddy [A.P. Dairy Development

Corpn. Federation v. B. Narasimha Reddy,

(2011) 9 SCC 286] held as under : (SCC p.

306, para 40)

“40. In the matter of the Government of

a State, the succeeding Government is

duty-bound to continue and carry on the

unfinished job of the previous

Government, for the reason that the

action is that of the “State”, within the

meaning of Article 12 of the

Constitution, which continues to subsist

and therefore, it is not required that the

new Government can plead contrary to

the State action taken by the previous

Government in respect of a particular

subject. The State, being a continuing body

can be stopped from changing its stand in a

given case, but where after holding enquiry it

came to the conclusion that action was not in

conformity with law, the doctrine of estoppel

would not apply. Thus, unless the act

done by the previous Government is

found to be contrary to the statutory

provisions, unreasonable or against

policy, the State should not change its

stand merely because the other political

party has come into power . ‘Political

agenda of an individual or a political party

should not be subversive of rule of law.’

The Government has to rise above the nexus

of vested interest and nepotism, etc. as the

principles of governance have to be tested

on the touchstone of justice, equity and fair

play.”

(emphasis supplied)

55. Further, upon a comprehensive perusal of the

contractual stipulations, this Court is of the considered view that

[2026:RJ-JP:20730] (94 of 106) [CW-8120/2025]

the existing contract itself provided sufficient flexibility to

accommodate necessary modifications. It is evident that justifiable

and material alterations in the scope of work could have been

undertaken, particularly if such changes were effected in a timely

manner and upon due consideration of expert opinion. Notably,

the appointed consultant under the contract continued to remain

engaged and available for such evaluative inputs. The contractual

framework, in fact, envisaged stage-wise execution and

corresponding payments, coupled with sub-categorization of work

components. In such a scenario, it was well within the domain of

the respondents to restructure, reduce, or expand the scope of

work, and to proceed with execution in a phased manner, rather

than abandoning the contract in its entirety. Moreover, a specific

clause under the Special Conditions of Contract expressly

contemplates variation, alteration, or modification of the

contractual scope, even stipulating that no additional

compensation would be payable on such account. This clearly

indicates that the contract was designed to be adaptable to

evolving project requirements. Consequently, any required

adjustments could have been mutually deliberated and resolved

between the parties, without resorting to termination or

withdrawal.

56. This position finds support from the judgment in

enunciated in Yash Construction Company v. The Secretary,

Ministry of Road Transport and Highways (MoRT & H), Writ

Petition No. 9620/2022 , decided on 16.12.2022, wherein it has

been recognized that modifications in contractual scope, where

[2026:RJ-JP:20730] (95 of 106) [CW-8120/2025]

contractually permissible, ought to be addressed within the

framework of the existing agreement rather than leading to its

abrupt discontinuation. The relevant extract from the said ratio is

reiterated hereinbelow:

“23.To sum up, the decision of the

respondents to abort the process of

tender wherein the Petitioners were the

successful L1 bidders on the sole ground

that the notice inviting tender stipulated 24

months as the period for completion of the

work instead of 18 months and even when

the petitioners expressed their

readiness and willingness to complete

the work at the same cost offered by

them which does not suffer from the sin

of post tender negotiations, the

decisions of the respondents is clearly

arbitrary and would lead to a loss of

public money. The cases are fit to be

interfered with.”

(emphasis supplied)

57. It is also opined that when a contract is entered into

between the State or its instrumentalities and a private party upon

a duly concluded tender process, any dispute arising out of such

contractual relationship does not entirely oust the jurisdiction of

this Court under judicial review. It is well-settled that the actions

of the State, even in contractual matters, must withstand the test

of fairness, reasonableness, and non-arbitrariness, as enshrined

under Article 14 of the Constitution of India. Thus, the State

cannot be permitted to cloak arbitrary or unreasonable conduct

behind the mere existence of a contract, nor can it evade judicial

scrutiny on the specious plea of availability of alternate remedies.

The doctrine of fairness permeates all State actions, and

contractual dealings are no exception, particularly where such

[2026:RJ-JP:20730] (96 of 106) [CW-8120/2025]

actions bear a public law element. In exercising the power of

judicial review, this Court is therefore required to examine

whether the decision-making process adopted by the State is just,

transparent, and free from arbitrariness, and not merely whether

the action is in strict conformity with the terms of the contract.

The presence of contractual stipulations or dispute resolution

mechanisms does not denude this Court of its constitutional

obligation to ensure adherence to the mandate of Article 14.

58. In this regard, reliance is placed upon the celebrated

judgment of Subodh Kumar Singh (supra), wherein it has been

held that State action in contractual matters remains amenable to

judicial review, particularly when it is demonstrated that such

action is arbitrary, unfair, or actuated by extraneous

considerations, notwithstanding the existence of contractual

remedies. The relevant extract of the said judgment is reproduced

hereinbelow:

"126. The sanctity of public tenders lies in

their role in upholding the principles of equal

opportunity and fairness. Once a contract

has come into existence through a valid

tendering process, its termination must

adhere strictly to the terms of the

contract, with the executive powers to be

exercised only in exceptional cases by the

public authorities and that too in loathe.

The courts are duty bound to zealously

protect the sanctity of any tender that has

been duly conducted and concluded by

ensuring that the larger public interest of

upholding bindingness of contracts are

[2026:RJ-JP:20730] (97 of 106) [CW-8120/2025]

not sidelined by a capricious or arbitrary

exercise of power by the State. It is the

duty of the courts to interfere in

contractual matters that have fallen prey

to an arbitrary action of the authorities in

the guise of technical faults, policy

change or public interest, etc.

127. The sanctity of contracts is a

fundamental principle that underpins the

stability and predictability of legal and

commercial relationships. When public

authorities enter into contracts, they

create legitimate expectations that the

State will honour its obligations.

Arbitrary or unreasonable terminations

undermine these expectations and

erode the trust of private players from

the public procurement processes and

tenders. Once a contract is entered,

there is a legitimate expectation that

the obligations arising from the contract

will be honoured and that the rights

arising from it will not be arbitrarily

divested except for a breach or non-

compliance of the terms agreed

thereunder. In this regard we may make a

reference to the decision of this Court in

Sivanandan C.T. v. High Court of Kerala

wherein it was held that a promise made by a

public authority will give rise to a legitimate

expectation that it will adhere to its

assurances.

….

130. Cancellation of a contract

deprives a person of his very valuable

rights and is a very drastic step, often

[2026:RJ-JP:20730] (98 of 106) [CW-8120/2025]

due to significant investments having

already been made by the parties

involved during the subsistence of the

contract. Failure on the part of the

courts to zealously protect the binding

nature of a lawful and valid tender

would erode public faith in contracts

and tenders. Arbitrary terminations of

contract create uncertainty and

unpredictability, thereby discouraging

public participation in the tendering

process. When private parties perceive that

their contractual rights can be easily

trampled by the State, they would be

dissuaded from participating in public

procurement processes which may have a

negative impact on such other public-private

partnership ventures and ultimately it is the

public who would have to bear the brunt

thereby frustrating the very object of public

interest.

131.We caution the public authorities to

be circumspect in disturbing or wriggling out

of its contractual obligations through means

beyond the terms of the contract in exercise

of their executive powers. We do not say for

a moment that the State has no power to

alter or cancel a contract that it has entered

into. However, if the State deems it

necessary to alter or cancel a contract

on the ground of public interest or

change in policy then such

considerations must be bona fide and

should be earnestly reflected in the

decision-making process and also in the

final decision itself. Otherwise, it would

[2026:RJ-JP:20730] (99 of 106) [CW-8120/2025]

have a very chilling effect as

participating and winning a tender

would tend to be viewed as a situation

worse than losing one at the threshold.”

(emphasis supplied)

CONCLUSION:

59. In addition to the findings recorded hereinabove, this

Court deems it appropriate to observe that the present writ

petitions are maintainable inasmuch as the challenge laid is not to

a mere contractual dispute but to the arbitrary and unreasonable

exercise of State power, thereby attracting the rigours of Article 14

of the Constitution of India. The decision making process adopted

by the respondents fails to satisfy the settled parameters of

judicial review, being vitiated by non-application of mind,

disproportionality, and manifest unreasonableness, particularly

when less drastic alternatives such as modification of scope,

phased execution, or contractual adjustments, were admittedly

available under the contract itself. The contemporaneous record

further establishes that the respondents, by granting extensions

without levy of liquidated damages, returning bank guarantees,

and permitting continued performance, had effectively waived any

alleged default and induced legitimate expectation in favour of the

petitioner, who, acting upon such representation, altered its

position by making substantial financial investments. The

subsequent attempt to attribute delay to the petitioner is thus hit

by the doctrines of promissory estoppel and waiver, and cannot be

countenanced.

[2026:RJ-JP:20730] (100 of 106) [CW-8120/2025]

60. Further, the abrupt abandonment of the subsisting

contract and initiation of a fresh DPR process, in absence of any

documented policy change or technical justification, is not only

arbitrary but also indicative of malice in law, being founded on

extraneous considerations rather than public interest. The

respondents have failed to demonstrate that such action advances

any larger public good; rather, the same results in avoidable delay,

escalation of costs, and wastage of public resources, thereby

failing the test of proportionality. This Court also finds that the

impugned action is contrary to the principles governing State

contracts, as the petitioner has approached this Court with clean

hands and established its continuous readiness and willingness to

perform, while the respondents’ own record belies their stand

taken before this Court, rendering their defence unsustainable.

61. It is noteworthy that this Court has rendered its

findings strictly on the basis of contemporaneous official record

produced by the respondents themselves, and not on disputed

questions of fact, thereby obviating the necessity of relegating the

petitioner to an alternate remedy. The record, particularly the

internal note-sheets of the respondent–authority, unmistakably

reflects an admission on the part of the State that the withdrawal

of the contract was occasioned on account of site-related

constraints and other administrative reasons, none of which can

be attributed to the petitioner. It is hereby opined that from the

very inception of the contract, the petitioner was kept uninformed

of the material impediments affecting execution, on the contrary,

encouraged to proceed with mobilization, resulting in substantial

[2026:RJ-JP:20730] (101 of 106) [CW-8120/2025]

investment in machinery, manpower, and procurement of

materials. Despite the existence of contractual provisions

permitting alteration or modification of scope of work, the

respondents, for reasons best known to them, failed to exercise

such enabling provisions; and instead of adopting a pragmatic and

legally permissible course of restructuring the project, the

respondents proceeded to abruptly terminate a legally enforceable

contract by erroneously invoking Clause 32 of the contract, and

this Court is of an opinion that invocation of Clause 32 without

determination of default renders the action void ab initio, as also

addressed in details hereinabove; and that the same was wholly

inapplicable in the absence of any contractor default.

62. What further compounds the arbitrariness of the

respondents’ conduct is the immediate issuance of a fresh tender

for preparation of a DPR qua the same OTS flyover project,

without disclosing any rational basis or change in circumstances

warranting such action. This decision, viewed in light of the

existing contractual framework and the petitioner’s ongoing

performance, is manifestly arbitrary and indicative of non-

application of mind. The submissions advanced on behalf of the

respondents attributing delay and non-performance to the

petitioner stand squarely contradicted by their own record,

including the note-sheets and official correspondence placed

before this Court. Such conduct not only undermines the

credibility of the decision-making process but also borders upon

misrepresentation before the Court. From the material placed on

record, it prima facie emerges that the withdrawal of the contract

[2026:RJ-JP:20730] (102 of 106) [CW-8120/2025]

was influenced by extraneous considerations, including the need

to accommodate objections raised by certain institutions such as

MNIT and OTS, as well as other influential stakeholders. The

consequential decision to alter the project configuration, inter alia,

reducing the flyover capacity from eight lanes to six lanes and

eliminating service roads, further demonstrates a departure from

the original project objectives, thereby frustrating the very

purpose for which the contract was awarded. In light of the

foregoing analysis, this Court is of the considered opinion that the

impugned action of the respondents is arbitrary, unreasonable,

and violative of Article 14 of the Constitution of India, and the

principle of legitimate expectation, and cannot be sustained in law.

DIRECTIONS:

63. The writ petitions are accordingly allowed in terms of

the prayers made, with the following directions:

63.1 The impugned order dated 24.04.2024, issued under

Clause 32 of the Special Conditions of Contract, is hereby quashed

and set aside.

63.2 The Notice Inviting Bid (NIB/NIT) for preparation of

DPR, to the extent it pertains to the OTS flyover project, is also

quashed.

63.3 The petitioner shall get all consequential benefits, and it

be entitled to pursue its lawful claims arising out of the contract in

accordance with law.

63.4 The respondents are directed to proceed with the

execution of the project forthwith, in accordance with the

subsisting contract, and to take all necessary steps to ensure its

[2026:RJ-JP:20730] (103 of 106) [CW-8120/2025]

timely completion. While doing so, the respondents shall duly

consider price variation, contractual adjustments, and other

permissible claims, in accordance with law and the terms of the

contract.

63.5 The respondents shall also ensure that the project is

implemented in its true spirit, in alignment with the policy vision

reflected in the State Budget announcements for the years 2021–

2022 and 2024–2025.

64. This Court further deems it necessary to direct an

inquiry into the decision-making process leading to the withdrawal

of the contract, in view of the glaring inconsistencies between the

stand taken by the respondents before this Court and the

contemporaneous official record, including the note-sheets and

internal communications. The material placed on record prima

facie discloses that the impugned decision was not founded upon

any objective assessment of contractual breach, but was instead

influenced by extraneous considerations and administrative lapses,

thereby resulting in arbitrary exercise of power. This Court is of a

stern view that in matters involving public contracts, the State and

its instrumentalities are under a heightened obligation to act in a

fair, transparent, and accountable manner, particularly when

decisions entail significant financial implications and affect public

interest. The present case reveals that despite the availability of

lawful and contractual alternatives, the respondents chose to

adopt a course which not only defeated a subsisting contract, but

also led to potential loss to the public exchequer and delay in

execution of a project of public importance. Further, the fact that

[2026:RJ-JP:20730] (104 of 106) [CW-8120/2025]

the respondents have advanced submissions before this Court

which are not borne out from their own record raises serious

concerns regarding the integrity of the decision making process;

and it is opined that such conduct, if left unchecked, would erode

public confidence in administrative functioning and undermine the

rule of law.

65.This Court further considers it apposite to underscore that

while the State is entitled to act in furtherance of sovereign and

public interest, such doctrine cannot be invoked as a carte blanche

to justify actions which are otherwise arbitrary, disproportionate,

or unsupported by the record. The doctrine of sovereign interest,

read in conjunction with the principles of public trust, fairness in

administrative action, and accountability, mandates that every

decision of the State must demonstrably serve a legitimate public

purpose and withstand judicial scrutiny on the touchstone of

Article 14 of the Constitution of India. Any departure from an

existing contractual obligation must therefore be founded upon

cogent, transparent, and bona fide considerations, and not on

extraneous or undisclosed factors. Simultaneously, this Court

deems it necessary to observe that the Officer-in-Charge

representing the department before the Court bears a solemn

responsibility. Such officer, while swearing affidavits and placing

records before the Court, acts not merely as a departmental

functionary but as an extended arm of the justice delivery system,

rendering assistance to the learned counsel representing the

State. The officer thus assumes a position akin to that of an officer

of the Court, and is expected to maintain the highest standards of

[2026:RJ-JP:20730] (105 of 106) [CW-8120/2025]

candour, accuracy, and responsibility in all submissions made on

affidavit. Any statement made must be strictly in consonance with

the official record, and due diligence is expected before affirming

pleadings. Casual, misleading, or inconsistent averments not only

impair the adjudicatory process but also amount to a serious

dereliction of duty, warranting appropriate scrutiny.

66.Thus, a structured inquiry to ascertain the circumstances

under which such decision was taken, to identify any procedural

irregularities, lapses, or misconduct, and to ensure that

accountability is fixed upon the officers responsible, be taken.

Such a direction is not punitive in nature but is essential to uphold

the principles of good governance, administrative accountability,

and transparency in State action. Accordingly, the Chief Secretary,

of the State of Rajasthan, is directed to take appropriate measures

in this regard, strictly in consonance with the directives

enumerated herein, against the erring officer(s), within an upper

limit of two months from the date of pronouncement of this

judgment.

67. In addition, this Court deems it appropriate to record

that prima facie misrepresentation has been made before this

Court by the Officer-in-charge/erring officers, whose pleadings

were found to be inconsistent with the official record. The

competent authority is directed to initiate appropriate proceedings

and take action in accordance with law.

68. Consequently, the instant petitions stand allowed, with

above mentioned directions. There shall be no order as to costs.

Pending applications, if any, shall stand disposed of accordingly.

[2026:RJ-JP:20730] (106 of 106) [CW-8120/2025]

69.Registrar (Judicial) is directed to retain a xerox copy of file

no. 5 and 6 from the records furnished by the respondent-JDA;

and thereafter return the records, in toto, to the concerned officer,

strictly in compliance with the due procedure.

(SAMEER JAIN),J

Pooja /

Description

Rajasthan High Court Quashes Flyover Contract Withdrawal: A Deep Dive into State Arbitrariness and Contractual Fairness

In a significant ruling from the Rajasthan High Court Judgments, a recent decision underscores the critical importance of fairness and transparency in public contracting. This in-depth Contractual Dispute Analysis delves into the arbitrary withdrawal of a major infrastructure project, highlighting the court's strong stance against unilateral governmental actions. This landmark case, along with numerous other vital rulings, is now available on CaseOn, offering legal professionals easy access to comprehensive legal documentation and analysis.

Case Background: The OTS Flyover Project

JCL Infra Private Limited (the Petitioner) was awarded an Engineering, Procurement, and Construction (EPC) contract by the Jaipur Development Authority (JDA) for “Traffic improvement and beautification work at OTS Crossing, JLN Marg, JDA Jaipur.” This comprehensive project, valued at Rs. 184.30 Crores, aimed to alleviate traffic congestion and enhance the aesthetic value of a critical urban corridor. The contract was based on a Detailed Project Report (DPR) prepared by JDA’s consultants, Sincere Architects Engineers Pvt. Ltd. The work was set to commence on January 6, 2023, with a stipulated completion period of 12 months, i.e., by January 5, 2024.

However, despite the Petitioner mobilizing substantial resources (investing approximately Rs. 40 Crores, with Rs. 20.41 Crores of work completed) and diligently submitting required plans and reports, the project faced significant delays. These delays, as asserted by the Petitioner, were primarily due to the JDA's failure to provide site approvals and a clear, obstruction-free site. Subsequently, the JDA extended the project deadline suo motu until April 30, 2024, without imposing any penalties. To the Petitioner's astonishment, the JDA later issued a letter on April 24, 2024, withdrawing the entire work by invoking Clause 32 of the Special Conditions of Contract, without providing a rationale or prior hearing. Following this, the JDA proceeded to release the Petitioner’s bank guarantees unconditionally. Further compounding the issue, the JDA issued a fresh Notice Inviting Bid (NIB) on April 3, 2025, for consultancy services to prepare a DPR for the very same OTS Flyover project, effectively nullifying the existing contract and substantial investment.

Issues Before the Hon'ble Court

The Rajasthan High Court framed several key issues for its determination:

  1. Whether the present petitions are maintainable, considering the dispute’s contractual nature and allegations of improper authorization.
  2. Whether the invocation of Clause 32 of the Special Conditions of Contract and the subsequent withdrawal of the contract are legally sustainable.
  3. Whether the doctrines of Promissory Estoppel and Legitimate Expectation are applicable in the prevailing circumstances.

Issue 1: Maintainability of Writ Petitions

The Respondents initially challenged the maintainability of the writ petitions on two grounds: alleged lack of proper authorization for filing on behalf of the Petitioner-company, and the dispute arising purely from a contractual relationship, thus falling outside writ jurisdiction.

Rule: The Court referenced United Bank of India vs. Naresh Kumar, (1996) 6 SCC 660, affirming that a company’s pleadings can be signed by a competent person, and authorization can be established at any stage, making such objections technical and curable. For contractual disputes, the Court cited Tata Cellular v. Union of India (1994) 6 SCC 651, Sudhir Kumar Singh (supra), and ABL International Ltd. (supra), stating that writ petitions are maintainable against State instrumentalities when their actions are arbitrary, violate natural justice, or involve a public law element.

Analysis: The Court found the authorization objection purely technical and cured by a submitted Board Resolution. Regarding contractual disputes, the Court determined that the Petitioner’s grievance extended beyond mere contractual enforcement, alleging arbitrariness, lack of fairness, and violation of natural justice by a State instrumentality. These elements introduced a public law dimension, making the writ petitions maintainable.

Issue 2: Validity of Contract Withdrawal under Clause 32

The JDA invoked Clause 32 of the Special Conditions of Contract to withdraw the work, citing “site conditions and various reasons” for the project’s lack of progress.

Rule: Clause 32 allows withdrawal under specific conditions: a justifiable reason, contractor’s failure to maintain stipulated progress, default attributable to the contractor, a specific written notice to remedy the default, and the possibility of engaging an alternate agency with “risk and cost” provisions. The Court also relied on Mohinder Singh Gill vs. Chief Election Commissioner (1978) 1 SCC 405, which holds that an administrative order’s validity must be judged solely on the reasons contained therein, not by later justifications.

Analysis: The Court meticulously reviewed the JDA’s internal note-sheets and correspondence, finding no specific fault or breach attributed to the Petitioner in the withdrawal order. Instead, the record consistently indicated that project impediments—such as the Model Code of Conduct, objections from MNIT/OTS, pipeline shifting issues, tree felling requirements, and proposed scope alterations—were administrative and institutional, entirely beyond the Petitioner’s control. The JDA’s suo motu extension of time without penalties and the unconditional release of bank guarantees further demonstrated that the Petitioner was not considered in default. Therefore, the essential preconditions for invoking Clause 32 were not met. The Court concluded that the JDA’s subsequent arguments were an “afterthought” and inconsistent with their own contemporaneous records.

Legal professionals seeking to quickly grasp the nuances of such complex contractual disputes, including the intricate details of Rajasthan High Court Judgments and their implications, can greatly benefit from CaseOn.in’s 2-minute audio briefs. These concise summaries provide a rapid and effective way to analyze specific rulings and stay informed on key legal developments without sifting through lengthy documents.

Issue 3: Promissory Estoppel and Legitimate Expectation

The Petitioner argued that having invested substantially based on the contract and assurances, the JDA could not arbitrarily withdraw the project.

Rule: The Court cited IFGL Refractories Ltd. vs. Orissa State Financial Corporation & Ors., 2020 SCC OnLine SC 208; U.P. Power Corporation Ltd. vs. Sant Steels & Alloys (P) Ltd., (2008) 2 SCC 777; and Sivanandan C.T. vs. High Court of Kerala, (2024) 3 SCC 799. These precedents affirm that the State, as an instrumentality under Article 12, is bound by fairness, promissory estoppel, and legitimate expectation. It cannot resile from promises that induced detrimental reliance from a party. Furthermore, State of Tamil Nadu & Ors. vs. K. Shyam Sunder, (2011) 8 SCC 737, and Shishir Realty Pvt. Ltd. vs. City and Industrial Development Corporation of Maharashtra Ltd., (2022) 16 SCC 527, establish that a change in government or policy cannot be the sole basis to annul a valid contract unless the original decision was unlawful or against public interest.

Analysis: The Court found that the Petitioner had altered its position detrimentally by mobilizing resources and incurring significant financial expenditure based on the JDA’s contractual assurances. The JDA’s justification citing a change in government policy was deemed arbitrary and capricious, violating Article 14 of the Constitution. The project’s core objectives remained unchanged, and the original contractual framework allowed for modifications or phased execution, which the JDA failed to explore. The abrupt abandonment of the contract, despite substantial investment and extended timelines, was deemed inequitable and inconsistent with principles of fairness and reasonableness.

The Court's Analysis and Findings

The High Court found that the JDA’s decision-making process was flawed, characterized by “non-application of mind, disproportionality, and manifest unreasonableness.” The Court observed that less drastic alternatives, such as modifying the scope or phasing the execution, were available under the existing contract. The JDA’s actions—granting extensions without liquidated damages, returning bank guarantees, and permitting continued performance—were interpreted as a waiver of any alleged default by the Petitioner and an inducement of legitimate expectation. The subsequent attempt to blame the Petitioner for delays was thus rejected as being contrary to the doctrines of promissory estoppel and waiver.

The Court further noted that the issuance of a fresh NIB for the same project, without a rational or technical basis, was “manifestly arbitrary” and “indicative of non-application of mind.” The JDA’s submissions before the Court were found to be “squarely contradicted by their own record,” bordering on “misrepresentation.” The withdrawal was influenced by “extraneous considerations, including the need to accommodate objections raised by certain institutions such as MNIT and OTS, as well as other influential stakeholders,” departing from the original project objectives. This conduct was deemed arbitrary, unreasonable, and violative of Article 14.

Conclusion and Directions

Based on its comprehensive analysis, the Rajasthan High Court issued the following directions:

  • The impugned order dated April 24, 2024, withdrawing the contract, is quashed and set aside.
  • The Notice Inviting Bid (NIB/NIT) dated April 3, 2025, for the preparation of a DPR related to the OTS flyover project, is also quashed to the extent it pertains to the OTS flyover project.
  • The Petitioner is entitled to all consequential benefits and may pursue lawful claims arising from the contract in accordance with law.
  • The Respondents are directed to proceed forthwith with the execution of the project as per the subsisting contract, ensuring timely completion and duly considering price variation, contractual adjustments, and other permissible claims.
  • The project must be implemented in its true spirit, aligning with the State Budget announcements for 2021-2022 and 2024-2025.
  • The Chief Secretary of Rajasthan is directed to conduct a structured inquiry within two months into the decision-making process leading to the contract’s withdrawal, identify any procedural irregularities or misconduct, and ensure accountability for erring officers.
  • The Court further observed prima facie misrepresentation by the Officer-in-charge/erring officers, whose pleadings were inconsistent with the official record, and directed the competent authority to initiate appropriate proceedings and take action.

Why This Judgment is Essential for Legal Professionals

This judgment serves as a robust reminder of the principles governing State action in contractual matters. For lawyers and law students, it elucidates several critical points:

  • Scope of Writ Jurisdiction: It reinforces that Article 226 of the Constitution can be invoked in contractual disputes if State action is arbitrary, unfair, or violates natural justice, establishing a “public law element.”
  • Sanctity of Contracts: The ruling upholds the binding nature of concluded contracts, particularly when private parties have made significant investments based on State assurances.
  • Promissory Estoppel and Legitimate Expectation: It demonstrates the successful application of these doctrines against State instrumentalities, preventing arbitrary volte-face.
  • Accountability in Governance: The Court’s direction for an inquiry into the decision-making process and action against erring officers underscores the judiciary’s role in ensuring transparency, accountability, and good faith from public authorities.
  • “Mohinder Singh Gill” Principle: The judgment highlights that administrative orders must be justified by reasons recorded at the time of the decision, not by subsequent rationalizations.
  • Limits of Policy Change: It clarifies that a mere change in government policy or political leadership is insufficient grounds to terminate a valid contract unless the previous decision was unlawful or against public interest.

This case is a testament to the judiciary’s commitment to safeguarding contractual fairness and preventing arbitrary exercises of power by the State, offering valuable insights into administrative law and public procurement.

Disclaimer

All information provided in this article is for informational purposes only and does not constitute legal advice. While efforts have been made to ensure accuracy, readers should not act upon this information without seeking professional legal counsel. CaseOn.in is not responsible for any actions taken based on the information presented herein.

Legal Notes

Add a Note....