As per case facts, a developer was allotted land by CIDCO in Navi Mumbai, which the High Court later declared illegal, ordering restoration to its original condition. This led to ...
2026 INSC 551 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 13092 –13093 OF 2025
K. RAHEJA CORP. PRIVATE LIMITED …. APPELLANT
VERSUS
THE STATE OF MAHARASHTRA
& ORS. ETC. ... RESPONDENTS
WITH
CIVIL APPEAL NOS. 13094 –13095 OF 2025
AND
CIVIL APPEAL NOS. 13096 –13097 OF 2025
J U D G M E N T
ALOK ARADHE, J.
(I) INTRODUCTION
1. These Civil Appeals have been filed by the M/s. K. Raheja Corp.
Private Limited (‘the Developer’), the Employees of Shopping
Mall, Hotel, the Developer and the Retailers Association of
India, challenging the common judgment and order dated
20.11.2014 and 21.11.2014 passed by the Division Bench of
the High Court of Judicature at Bombay in PIL No. 131 of 2003
2
and PIL No. 48 of 2004. The central question before this Court
is not merely one of the legality of the original allotment which
was undoubtedly irregular but whether, in light of the profound
and irreversible economic and social consequences that have
since crystallised over two decades, the public interest is better
served by demolition or by a rigorously supervised
regularisation coupled with full financial restitution to the
public authority.
(II) FACTUAL BACKGROUND
2. In the late 1960s, the Government of Maharashtra took a policy
decision to develop Navi Mumbai as a planned twin city to the
metropolis of Mumbai, with the primary objective of
decongesting the city and providing a modern, self-sustaining
urban centre. The City and Industrial Development Corporation
Limited ('CIDCO'), a Government Company incorporated under
Section 617 of the Companies Act, 1956, was appointed as the
New Town Development Authority for the designated area in
exercise of powers conferred under Section 113(3A)(1) of the
Maharashtra Regional and Town Planning Act, 1966 ('MRTP
Act'). For this purpose, lands across 96 villages in the Thane
and Raigad Districts were acquired en bloc and placed at the
3
disposal of CIDCO for the systematic, planned development of
the new city.
3. Sector 30A at Vashi, Navi Mumbai, was specifically earmarked
for the promotion and development of Information Technology
industries and designated as the International Infotech Park ('IT
Park'). The total area so earmarked measured 57,180 sq.
metres, out of which CIDCO allotted 31,232 sq. metres to the
various IT companies. However, by the early 2000s, the global
IT sector witnessed a significant and prolonged downturn.
Taking cognizance of this changed economic reality, the Board
of Directors of CIDCO, by a Resolution dated 30.04.2003,
approved the conversion of 22,337 sq. metres within Sector 30A
for residential, commercial, and office use.
4. On 20.08.2003, the Developer submitted an application to
CIDCO for allotment of land in the aforesaid sector. The Board
of Directors of CIDCO, in its meeting held on 17.09.2003,
approved the allotment of plots measuring 29,000 sq. metres
bearing plot nos. 39/1 and 39/6 to 39/15 including a plot of
3,611 sq. metres ('the subject plot') in Sector 30A, Vashi, Navi
Mumbai in favour of the Developer, which had originally been
reserved for the IT use. The allotment was made with a Floor
4
Space Index ('FSI') of 3.0, at the rate of Rs. 10,250/- per sq.
metre, in anticipation of formal Government approval, and was
conditioned upon the Developer developing a garden at its own
cost on the adjoining Plot No. 40.
5. Pursuant to the said Resolution, a formal Letter of Allotment
dated 08.10.2003 was issued in respect of the subject plot, and
a Lease Agreement was executed between the CIDCO and the
Developer on 16.12.2003. The allotment was challenged by way
of two Public Interest Litigations, being PIL No. 131 of 2003 and
PIL No. 48 of 2004 filed before the High Court, seeking
cancellation of the allotment. A Division Bench issued a status
quo order on 17.12.2003, which was vacated on 23.04.2004
with the clarification that the allotment would be subject to the
final outcome of the PILs.
(III) THE SANKARAN COMMITTEE INQUIRY
6. The Chief Secretary, Government of Maharashtra, by a note
dated 01.01.2005, directed Dr. D.K. Sankaran, Additional Chief
Secretary, to conduct a discreet inquiry into the affairs of
CIDCO during the tenure of Mr. V.M. Lal as Vice Chairman and
Managing Director from 26.05.2003 to 28.12.2004. The
5
Sankaran Committee, after examining CIDCO's land pricing
and disposal policy alongside the relevant factual record,
submitted its report dated 31.03.2005.
7. The Sankaran Committee classified the allotments it reviewed
into three categories: (i) cases involving serious irregularities;
(ii) doubtful cases of allotment; and (iii) cases that appeared
reasonable. With respect to the subject plot, the Committee
recorded the following findings:
(a) The subject plot ought to have been disposed of
through competitive tender in accordance with
CIDCO's prevailing land disposal policy.
(b) Based on the assessment of CIDCO's Chief
Economist, the market value of a residential-cum-
commercial plot in September 2002 was Rs.
20,791/- per sq. metre, whereas the subject plot was
allotted to the Developer at the substantially lower
rate of Rs. 10,250/- per sq. metre without any
competitive process resulting in a financial loss of
approximately Rs. 50 crores to CIDCO.
(c) The Committee recommended cancellation of the
allotment and its disposal by public tender, along
6
with strong action against the officers responsible for
the irregular allotment.
7.1 The Committee found that CIDCO had made 61 allotments in
violation of its regulations, causing an aggregate estimated loss
of Rs. 347 crores. It recommended either cancellation of all such
allotments or, where cancellation was impracticable, recovery
of the difference between the allotment price and the prevailing
market rate.
IV. SUBSEQUENT DEVELOPMENTS AND THE BANTHIA
COMMITTEE
8. The Board of Directors of CIDCO, in its Resolution dated
06.06.2005, resolved upon the implementation of the Sankaran
Committee's findings. Given that building permission had
already been granted and construction was already underway
on the subject plot, the Board resolved to issue a show cause
notice to the Developer and to take steps to recover the financial
loss. In compliance with a direction issued on 14.08.2008, the
Developer furnished a bank guarantee of Rs. 50 crores on
02.09.2008.
9. The Developer completed the development of the subject plot
comprising a Shopping Mall and a Hotel with a built-up area of
7
approximately 10,50,000 sq. feet at an investment of Rs.450
crores (Rupees Four Hundred Fifty Crores only). An Occupancy
Certificate was issued by the Navi Mumbai Municipal
Corporation on 16.09.2008, and the Mall and Hotel have been
in continuous commercial operation since 2009.
10. By its impugned common judgment and order dated
20.11.2014 and 21.11.2014, the High Court held the allotment
of the subject plot to be completely illegal and arbitrary, in
violation of Article 14 of the Constitution of India, and directed
the Developer to restore the subject plot to its original condition
and hand over vacant possession to CIDCO within six months.
However, recognizing the complexity of the situation, the High
Court also kept open the question of regularisation, granting
the Developer liberty to make an appropriate application in that
regard. The PIL petitioners did not challenge the liberty so
granted, and the regularisation policy of CIDCO itself was never
called into question.
11. An order dated 01.12.2014 was passed directing the Developer
to discontinue the unauthorised use of plot no.39/16 and to
hand over the vacant possession of the plot. The Deverloper
approached the High Court by filing a writ petition namely W.P.
8
No. 368 of 2015 in which the High Court by an order dated
16.01.2015 has directed the parties to maintain status quo. The
said writ petition is still pending.
12. Being aggrieved by the impugned common judgment and order
dated 20.11.2014 and 21.11.2014, the Developer, the
Employees of the shopping mall and hotel, and the Retailers
Association of India comprising 131 retailers approached this
Court by filing Special Leave Petitions. This Court, by an order
dated 22.01.2015 directed the parties to maintain status quo.
13. During the pendency of these appeals, the Developer filed an
application for regularisation in April 2015. The Government of
Maharashtra, by an order dated 27.07.2015, constituted a one-
man committee comprising Mr. J.K. Banthia, former Chief
Secretary, Government of Maharashtra ('Banthia Committee'),
to examine the feasibility and terms of regularisation of the
allotment of the subject plot. The Banthia Committee, in its
report dated 20.07.2017, took a pragmatic and governance -
oriented approach. It observed that once the allotment had been
judicially held to be illegal, the original concessional valuation
mechanism became irrelevant and that regulari sation, if
ordered, must be prospective in nature and based on the
9
market value as on the date of the High Court's judgment, i.e.,
November 2014. The Committee identified three alternatives for
regularisation:
(a) The Developer pays two-thirds of the fair market
value and CIDCO absorbs one-third.
(b) The Developer pays three-fourths of the fair market
value and CIDCO absorbs one-fourth.
(c) The Developer pays the full fair market value.
The Banthia Committee ultimately recommended that, given
the scale of irreversible investment and the magnitude of public
and economic interest involved, the Government consider a
heavily penalised regularisation under which the Developer
would be required to pay the full fair market value as of
approximately 2014.
14. The Government of Maharashtra thereafter sought the opinion
of the Advocate General of Maharashtra, who, by his opinion
dated 15.03.2019, recommended that the regulari sation be
decided on terms consistent with the manner in which other
similarly situated allottees had been regularised under the
10
CIDCO policy dated 06.06.2005, with due credit for the bank
guarantee of Rs. 50 crores already furnished by the Developer.
15. By communication dated 04.06.2019, the Government of
Maharashtra directed the Board of Directors of CIDCO to take
an independent decision on regularisation, subject to the
outcome of these appeals. This Court, by an interim order dated
27.10.2025, similarly directed CIDCO to consider the
Developer's regularisation application on its own merits and to
file its decision by way of an affidavit within eight weeks.
16. In compliance with the aforesaid direction, CIDCO filed an
affidavit on 09.03.2026 along with a copy of the Resolution
dated 04.02.2026 passed by its Board of Directors, approving
the regularisation of the subject plot subject to the following
conditions:
(i) Payment of Rs. 50 crores towards differential
premium as quantified in the Sankaran Committee
Report.
(ii) Payment of Rs. 1 crore representing the discount
factored in lieu of the development of the Japanese
Garden.
11
(iii) Payment of interest on the aforesaid sum from
16.12.2003 till the date of actual payment at the
prevailing CIDCO rate of interest, along with
applicable GST.
On the basis of the aforesaid formula, the total amount payable
by the Developer was computed at Rs. 257.87 crores (Rupees
Two Hundred Fifty-Seven Crores Eighty-Seven Lakhs only).
17. The Developer filed an Interlocutory Application, namely I.A. No.
104795 of 2026 stating that it is ready and willing to make
payment of the amount determined by the CIDCO in its
Resolution dated 04.02.2026 and the Civil Appeals be disposed
of in terms of the aforesaid Resolution approving the
regularisation of allotment of the subject plot. The PIL
petitioners have filed affidavits on 16.03.2026 and 07.04.2026
opposing the regularisation of the subject plot.
(V) SUBMISSIONS
18. Learned Senior Counsel for the Developer submitted that the
Regulation 4 of the New Bombay Disposal of the Lands
Regulations, 1975 expressly permits CIDCO to dispose of plots
either by public auction, by tender, or by considering individual
applications as the Corporation may, from time to time,
12
determine. It was contended that previous attempts to auction
the subject plot had failed and the allotment on an individual
application was, therefore, permissible under the extant
regulations and could not be characterised as per se illegal. It
was further urged that neither the regularisation policy of the
CIDCO nor the liberty granted by the High Court to the
Developer to apply for regularisation has ever been challenged
by the PIL petitioners. The Developer expressed its willingness
to pay Rs. 257.87 crores in terms of CIDCO's Resolution dated
04.02.2026 and prayed that the appeals be disposed of
accordingly.
19. Learned Senior Counsel for the Respondents, on the other
hand, contended that the Developer had encroached upon Plot
No. 39/16, which was never the subject of any allotment, and
is, therefore, not entitled to the benefit of regularisation. It was
urged that the Sankaran Committee had positively
recommended the cancellation of the allotment. It was also
pointed out that the Developer had failed to develop the
Japanese Garden on Plot No. 40 as required by the conditions
of the allotment. In the alternative, learned senior counsel
submitted that the PIL petitioners would be satisfied if the
13
Developer were directed to pay the amount equivalent to the fair
market value prevailing in the year 2014, in accordance with
the recommendations of the Banthia Committee.
(VI) ANALYSIS AND FINDINGS
A. The High Court's Order: Scope of Challenge
20. We have carefully considered the rival submissions and
perused the entire record. Before embarking upon an analysis
of the substantive issues, it is necessary to note the precise
scope and effect of the impugned common judgment and order.
Even though the High Court found the allotment to be
completely illegal and arbitrary, it conspicuously refrained from
quashing it. The High Court simultaneously granted the
Developer liberty to apply for regularisation and expressly kept
open the question of whether CIDCO is entitled to regularise the
allotment and whether the Developer is entitled to such
regularisation. Crucially, neither the order granting this liberty
nor the regularisation policy of the CIDCO has been challenged
by the PIL petitioners before this Court. The foundation for the
regularisation, therefore, rests on undisturbed legal ground.
21. It is further relevant to note that the Regulation 4 of the New
Bombay Disposal of Lands Regulations, 1975 permits disposal
14
of the CIDCO plots not only by auction or tender, but also by
considering the individual applications, as the CIDCO may from
time to time determine. In circumstances where earlier tender
attempts had failed, the allotment on an individual application
was not per se illegal. The infirmity lay in the pricing
mechanism and the absence of transparent competitive
process, not in the mode of the allotment itself.
(B) Why Demolition Cannot Be the Answer: The Doctrine
of Proportionality and Irreversibility
22. The primary question before this Court is whether the direction
of the High Court to restore the subject plot to its original
condition which would necessarily entail the demolition of a
fully operational shopping mall and a hotel can be sustained.
In our considered opinion, it cannot, and we record our detailed
reasons therefor.
23. A Court must weigh not only the wrong that has been
committed but also the reality as it now stands. The doctrine of
proportionality, deeply embedded in constitutional
jurisprudence, demands that the severity of a remedial measure
must bear a rational and proportionate relationship to the
nature and magnitude of the wrong sought to be remedied. A
15
remedy that causes public harm disproportionate to the public
benefit it achieves is not a remedy that law ought to
countenance.
24. The passage of time and the accretion of economic and social
reality have rendered demolition not merely impractical but
demonstrably contrary to the public interest that the PIL
petitioners themselves invoke which is evident from the
following:-
(a) An investment of Rs. 450 crores was made by the
Developer in the construction of the mall and hotel,
a sum that cannot, under any legal order, be
recovered or restored.
(b) The occupancy certificate was issued by the Navi
Mumbai Municipal Corporation on 16.09.2008 and
the complex has been in continuous commercial
operation for over seventeen years, since 2009.
(c) Approximately 150 retailers operate within the
shopping mall, and around 8,000 individuals draw
their livelihood directly from the employment
generated by the complex.
16
(d) Irreversible third-party rights of retailers, hotel
operators, employees, and consumers have
crystallised over the course of seventeen years of
commercial operation.
25. The Banthia Committee, constituted by the State Government
itself, captured the essential dilemma with clarity and candour:
the need to enforce the rule of law and penalise unlawful
conduct must be balanced against the imperative of avoiding
disproportionate and destructive economic consequences. The
Committee rightly emphasised that the test, in a case such as
this, is not whether the original conduct was blameworthy but
whether the public interest is best served by a remedy that
erases the past or one that exacts a full price for the wrong while
preserving the economic and social good that has accrued in
the interregnum.
26. The answer to that question is, in our view, unambiguous.
Demolition of a fully operational commercial complex after
seventeen years, Rs. 450 crores of investment, 8,000
livelihoods, and Rs. 100 crores of annual tax revenue would not
vindicate the public interest. The financial prejudice caused to
CIDCO by the irregularity of the original allotment is entirely
17
capable of being remedied through a rigorous financial recovery
mechanism. The social and economic harm caused by
demolition, by contrast, would be catastrophic and irreparable.
Public law must be sensitive to the distinction between
remedies that restore public welfare and remedies that merely
punish, when punishment comes at the cost of the very public
the law seeks to protect.
27. An adjudication, as we have observed, cannot occur in a
vacuum divorced from subsequent reality. This case requires
that CIDCO be fully and fairly compensated for the financial
loss it suffered, that the Developer be penalised in proportion to
its wrongdoing, and that the livelihoods and economic activity
of thousands of innocent third parties be protected. A
regularisation conditioned upon payment of full market value
as of 2014 achieves all three objectives. Demolition achieves
none.
28. We are, accordingly, unable to concur with the direction of the
High Court to restore the subject plot to its original condition
and hand over vacant possession to the CIDCO.
18
(C) The Question of Regulari sation and the Quantum
Payable
29. Having concluded that the regularisation is the appropriate
remedy, we now address the terms upon which such
regularisation shall be granted, and specifically the question of
the quantum of the amount payable by the Developer.
30. The Developer has urged that it should be treated at parity with
other allottees whose cases were covered by the Sankaran
Committee Report and who were regularised under the CIDCO
policy dated 06.06.2005. We are unable to accept this
contention. The Developer is a large commercial enterprise of
considerable financial capacity that developed a major
commercial complex of 10,50,000 sq. feet. The other allottees
with whom parity is sought principally Multi Co -operative
Housing Societies and individual allottees occupy an entirely
different position in terms of scale, commercial purpose, and
financial capacity. The principle of equality under Article 14 of
the Constitution does not require that unequals be treated as
equals. The parity of treatment is warranted only among those
who are similarly situated in all material respects. The
Developer plainly is not.
19
31. Turning to the methodology for computing the amount payable,
two committee reports are before us: the Sankaran Committee
Report and the Banthia Committee Report. The CIDCO
Resolution dated 04.02.2026 adopts the Sankaran Committee's
methodology, computing the recoverable amount as interest on
Rs. 50 crores differential loss quantified in 2005, accrued from
16.12.2003 to the date of payment. This produces a total
liability of Rs. 262.87 Crores. The Developer has expressed its
willingness to pay the aforesaid amount as quantified in the
resolution dated 04.02.2026 passed by the Board of Directors
of CIDCO.
32. The Banthia Committee examined the matter from the
perspective of practical governance and overarching public
interest. From the opinion rendered by the Advocate General, it
is evident that the principle of parity was invoked to recommend
acceptance of the Sankaran Committee Report. However, as
already observed hereinabove, the principle of parity has no
application in the peculiar factual matrix of the present case. A
careful scrutiny of the Resolution dated 04.02.2026 passed by
the CIDCO reveals that no cogent reasons have been assigned
for discarding the methodology for recovery of loss adopted by
20
the Banthia Committee. The CIDCO has also failed to justify as
to why the recommendations of the Sankaran Committee were
accepted in preference to those of the Banthia Committee.
33. We, therefore, are not persuaded that the Sankaran Committee
methodology is the appropriate basis for computing the
regularisation amount in the present circumstances. The
Sankaran Committee conducted its inquiry in 2005 and
quantified the loss based on then-prevailing market conditions.
It did not, and could not, account for the dramatic appreciation
in land values that occurred over the subsequent decade. More
fundamentally, the Sankaran Committee's mandate was to
assess and recommend cancellation or recovery , it was not
designed to determine the regularisation price of an already
developed and fully operational commercial complex nearly two
decades later. To apply its 2005 valuation as the baseline for a
subsequent regularisation is to allow the Developer to benefit
from a valuation frozen at a point when land values were far
lower, thereby substantially understating the true cost of
regularisation. The CIDCO Resolution does not assign any
cogent reason for rejecting the Banthia Committee's
methodology, and we are unable to discern one.
21
34. The Banthia Committee, on the other hand, approached the
question while taking into account both the legal and economic
dimensions. Its central insight was as follows: once the
allotment has been judicially declared illegal, the original
concessional price paid by the Developer becomes entirely
irrelevant as a baseline. Regularisation is not a continuation of
the original transaction; it is a fresh grant of legal legitimacy,
prospective in nature, for which the Developer must pay what
the land was actually worth at the time of the court's judgment.
The Committee correctly identified November 2014, the date of
the High Court's judgment as the appropriate reference date for
market valuation. This approach is sound both in principle and
in policy:
(a) It prevents the Developer from benefiting from a
valuation frozen at the point of its irregular allotment
over two decades ago.
(b) It ensures that CIDCO receives the full economic
value of what it is effectively re-granting through
regularisation.
(c) It imposes a genuinely punitive financial
consequence on the Developer, proportionate to the
22
scale of its commercial enterprise and the degree of
its irregular conduct.
(d) It is consistent with the principle, well-established in
public law, that an entity seeking to regularise an
illegal act must bear the full cost of legality, not a
discounted historical price.
35. However, upon perusal of the Banthia Committee Report, we
find that the market value of the subject plot as on the year
2014 has not been specifically disclosed. We, accordingly,
queried learned senior counsel appearing for the Developer
regarding the ready reckoner rates applicable to Sector 30A,
Vashi, Navi Mumbai. Pursuant thereto, the ready reckoner
rates applicable at the relevant time were placed before us,
which disclose that the prevailing rate was Rs.54,400/- per
square metre. This figure represents the objective, State-
published benchmark of market value and constitutes the
appropriate basis for computing the regularisation amount.
36. We are, accordingly, of the opinion that the Banthia
Committee's recommendation requiring the Developer to pay
the fair market value of the subject plot as of approximately
2014 represents the correct, just, and proportionate basis for
23
regularisation. The Developer must make payment at the ready
reckoner rate of Rs. 54,400/- per sq. metre applicable to Sector
30A, Vashi, Navi Mumbai, as the consideration for
regularisation of the subject plot.
37. The Developer was allotted the subject plot measuring 30,582
sq. metres. As per the ready reckoner rate of Rs.54,400/- per
sq. metre applicable to Sector 30A, Vashi, Navi Mumbai, the
market value of the subject plot for the year 2014 works out to
Rs.1,66,36,60,800/- (Rupees One Hundred Sixty-Six Crores
Thirty-Six Lakhs and Sixty Thousand Eight Hundred only). On
the aforesaid amount, the Developer is liable to pay interest at
the rate of 8% (eight per cent) from 01.12.2014 till 30.04.2026.
The amount of interest is quantified at Rs.1,51,94,76,864/-
(Rupees One Hundred Fifty-One Crores Ninety-Four Lakhs and
Seventy-Six Thousand Eight Hundred Sixty-Four only). Thus,
in terms of the ready reckoner rate for the year, 2014, the
Developer is liable to pay an aggregate amount of
Rs.3,18,31,37,664/- (Rupees Three Hundred Eighteen Crores
Thirty-One Lakhs and Thirty-Seven Thousand Six Hundred
Sixty-Four only) inclusive of the principal amount interest
thereon. It is pertinent to note that the Developer has already
24
expressed willingness to pay the amount in terms of the
Resolution dated 04.02.2026 passed by the Board of Directors
of CIDCO, which is based on the recommendations of the
Sankaran Committee. The amount indicated in the aforesaid
Resolution is Rs.262.87/- crores (Rupees Two Hundred Sixty-
Two Crores and Eighty-Seven Lakhs only), which the Developer
is ready and willing to pay. The Developer had paid the amount
towards market value of the subject plot at the rate of Rs.10,250
per sq. metre. In view of our conclusion that the Developer is
liable to pay the market value of the subject plot for the year,
2014 as recommended by the Banthia Committee, that is at the
rate of Rs.54,400 per sq. metre. Thus, the Developer is further
liable to pay an additional sum of Rs.55,44,37,664/- (Rupees
Fifty-Five Crores Forty-Four Lakhs Thirty-Seven Thousand Six
Hundred Sixty-Four only), which is in public interest.
VII. OPERATIVE DIRECTIONS
38. In view of the foregoing analysis, we issue the following
directions:
(i) The Developer shall pay a sum of
Rs.3,18,31,37,664/- (Rupees Three Hundred
25
Eighteen Crores and Thirty-One Lakhs Thirty-Seven
Thousand Six Hundred Sixty-Four only) for the
entire area of the subject plot, being the fair market
value as established by the ready reckoner rates
applicable to Sector 30A, Vashi, Navi Mumbai, as of
November 2014.
(ii) The amount already paid by the Developer towards
the purchase price of the subject plot at the rate of
Rs.10,250/- per sq. metre shall be duly adjusted and
deducted from the total amount payable.
(iii) The Developer shall additionally pay a sum of Rs. 1
crore in lieu of the obligation to develop a garden on
Plot No. 40, which remained unfulfilled.
(iv) Subject to the payment of the aforesaid amount
within a period of four months from the date of this
judgment, the allotment of the subject plot in favour
of the Developer shall stand regularised.
(v) Needless to state that the dispute with regard to plot
No. 39/16 which is the subject matter of W.P. No.
368 of 2015 shall be decided by the High Court on
its own merits.
26
(VIII) CONCLUSION
39. For the reasons set out above, the impugned common judgment
and order dated 20.11.2014 and 21.11.2014 passed by the
High Court in PIL No. 131 of 2003 and PIL No. 48 of 2004 in so
far as it pertains to restoration of the subject plot to its original
condition and delivery of vacant possession to CIDCO, is hereby
quashed and set aside. To the aforesaid extent, the impugned
common judgment and order is modified.
40. The Civil Appeals are accordingly disposed of. There shall be no
order as to costs.
……………………………………………….J.
[PAMIDIGHANTAM SRI NARASIMHA]
……………………………………………….J.
[ALOK ARADHE]
NEW DELHI
MAY 26, 2026
Legal Notes
Add a Note....