As per case facts, the petitioner applied for a new electricity service connection to establish a flour mill, fulfilling all required conditions, including payment and obtaining a No-Objection Certificate. Despite ...
APHC010145732026
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3504]
MONDAY, THE TWENTY SECOND DAY OF JUNE
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE SRI JUSTICE MAHESWARA RAO KUNCHEAM
WRIT PETITION NO: 8103/2026
Between:
1. KADAGALA SRINIVAS RAO, S/O LATE APPALA RAMULU, AGED
ABOUT 50 YEARS, R/O 1 -95, MAIN ROAD, PARAMPETA,
SRIKAKULAM, ANDHRA PRADESH - 532122
...PETITIONER
AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY ENERGY DEPARTMENT, SECRETARIAT, VELAGAPUDI
AMARAVATI, A.P. - 522238.
2. EASTERN POWER DISTRIBUTION COMPANY OF A P LTD APEPDCL,
REP. BY ITS CHAIRMAN AND MANAGING DIRECTOR CORPORATE
OFFICE, P AND T COLONY, SEETHAMMADHARA, VISAKHAPATNAM
DISTRICT, A.P. - 530013.
3. THE SUPERINTENDENT ENGINEER, OPERATION DIVISION,
ANDHRA PRADESH EASTERN POWER DISTRIBUTION COMPANY
OF ANDHRA PRADESH LIMITED (APEPDCL), VIZIANAGARAM
DISTRICT - 535002.
4. THE EXECUTIVE ENGINEER, OPERATION SECTION, ANDHRA
PRADESH EASTERN POWER DISTRIBUTION COMPANY OF
ANDHRA PRADESH LIMITED (APEPDCL), VIZIANAGARAM RURAL,
VIZIANAGARAM DISTRICT - 535002.
5. THE DEPUTY EXECUTIVE ENGINEER, OPERATION SECTION,
ANDHRA PRADESH EASTERN POWER DISTRIBUTION COMPANY
OF ANDHRA PRADESH LIMITED (APEPDCL), RAJAM,
VIZIANAGARAM DISTRICT-532127.
6. THE ASSISTANT ENGINEER, OPERATION SECTION, ANDHRA
2
PRADESH EASTERN POWER DISTRIBUTION COMPANY OF
ANDHRA PRADESH LIMITED (APEPDCL), 33/11 KV SUB -STATION,
REGIDI AMADALAVAIASA MANDAL, VIZIANAGARAM DISTRICT -
532122.
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased topleased to issue a writ order or direction more particularly one in the
nature of Writ of Mandamus to declare the action of the Respondents,
particularly Respondent No.6, in rejecting the Petitioner's application dated
20.09.2025 bearing Registration No. NSCREG03556196 for grant of new
electricity service connection without assigning any reasons, despite the
Petitioner having complied with all the statutory mandates, as illegal, arbitrary,
unreasonable and contrary to the provisions of the Electricity Act, 2003 and
the Andhra Pradesh Electricity Regulatory Commission Rules, besides being
violative of Articles 14, 19(1 )(g) and 21 of the Constitution of India, and
consequently direct the Respondents to issue a new electricity service
connection to the Petitioner herein
Counsel for the Petitioner:
1. YAMINI SAHU
Counsel for the Respondent(S):
1. GP FOR ENERGY
2. V V SATISH (SC for APEPDCL)
RESERVED ON : 08.05.2026
PRONOUNCED ON : 22.06.2026
UPLOADED ON : 22.06.2026
The Court made the following:
3
THE HONOURABLE SRI JUSTICE MAHESWARA RAO KUNCHEAM
WRIT PETITION NO: 8103/2026
ORDER:
The present writ petition under Article 226 of the Constitution of
India is filed to declare the action of the respondents, particularly
respondent No.6, in permanently rejecting the petitioner’s application
dated 20.09.2025 bearing Registration No.NSCREG0355196 for grant of
new electricity service connection without assigning any reasons,
despite the petitioner having complied with all the statutory provisions of
the Electricity Act, 2003 and the Andhra Pradesh Electricity Regulatory
Commission Rules, besides being violative of Articles 14, 19(1) (g) and
21 of the Constitution of India.
Brief facts of the case:
2. The case of the petitioner is that the petitioner is the owner and
possessor of the property bearing D.No.1-95 situated at Main Road,
Parampeta Village, Regidi Amadalavalasa Mandal, Vizianagaram
District, wherein, he intended to establish small flour mill to earn
livelihood and, in furtherance of the same, obtained requisite No-
Objection Certificate from Panchayat Secretary, Parampeta Village,
Regidi Amadalavalasa Mandal, Vizianagaram District. Subsequently,
the petitioner made application bearing Registr ation
4
No.NSCREG03556196 dated 20.09.2025 by paying the requisite fee for
the grant of Category-II electricity service connection to the 6
th
respondent Corporation.
3. It is further case of the petitioner that on 10.10.2025, the officials of
the 6
th
respondent, along with the village linemen, had brought the
service connection meter to premises of the petitioner for the purpose of
affecting the electricity connection, however, the said installation of
meter was stopped by the 6
th
respondent personnel midway due to some
local interference. Further, the petitioner has approached the office of
the 6
th
respondent again and again to enquire about the installation, but
there was no action taken by the respondent authorities and on the other
hand, his application status was shown as “Permanently Rejected” on
the online portal without providing any reasons. Thereafter, the
petitioner submitted representation dated 20.02.2026 to the respondent
Authorities by mentioning all the facts and requested them to furnish the
reasons for the permanent rejection of the application dated 20.09.2025
to reconsider the same and grant Category-II service Connection, but no
action has been taken by the respondents so far. Thus, challenging the
action of the respondents Corporation authorities, the petitioner
instituted the instant lis under Article 226 of the Constitution of India
before this Court.
5
4. Heard Ms. Yamini Sahu, learned counsel for the petitioner and
Ms. K. Aishwarya Chowdary, learned Junior Standing Counsel
representing Sri V.V. Satish, learned Standing Counsel for the
respondent Corporation. Perused the material available on record.
Arguments on behalf of the petitioner:
5. Learned counsel for the petitioner contended that the rejection of
the application by the respondent Authorities has affected the day to day
activities of the petitioner’s flour mill, for which, the petitioner is
essentially depended on electricity supply and in absence of the same,
the petitioner was deprived from carrying out the said occupation, which
directly effects on his livelihood thereby leading to violation of Articles
19(1) (g) and 21 of the Constitution of India.
6. Learned counsel vehemently submitted that under Clause 5.1 of
the General Terms and Conditions of the Supply (GTCS) r/w. Section 43
of the Electricity Act, 2003 and Andhra Pradesh Electricity Regulatory
Commission (Licensees’ Standards of Performance) Regulation, 2004
(in short ‘APERC’), the distribution licensee is under statutory obligation
to provide electricity supply to the owner or occupier of any premises
within the time frame stipulated therein., on an application being made in
the prescribed manner.
6
7. She submitted that the petitioner has made requisite application
with all the necessary requirements, but despite the same the
respondent authorities had failed to perform their statutory obligation.
8. Further, she asserted that as per APERC Consumer Rights
Statement governing the procedure for providing new electricity
connection, an applicant is entitled to be informed the reasons for any
rejection, to be afforded an opportunity of personal hearing, to prefer an
appeal and granted an opportunity to rectify any deficiencies at all.
9. Learned counsel also brought to the notice of this Court that in the
present case, the respondent authorities had failed to adhere to the said
mandate and violated the principles of natural justice as no prior notice
nor an opportunity of hearing before rejecting the application of the
petitioner, despite having approached the respondent Authorities on
several occasions. Therefore, she urged that the rejection of the
petitioner’s application without assigning any reasons renders the
impugned action of the respondent Corporation as non-speaking order.
11. To substantiate her arguments, the learned counsel placed
reliance on the judgments of Dilip (Dead) through LRs v. Satish &
Ors., K.C Ninan v. Kerala State Electricity Board and Kranti
Associates Pvt. Ltd. v. Masood Ahmed Khan.
7
Arguments on behalf of the respondent Corporation:
12. On the other hand, the 2
nd
respondent Corporation has not filed
counter affidavit in spite of granting reasonable opportunity. Anyhow, the
learned counsel appearing for the respondent Corporation submitted
that the petitioner had applied for new service connection vide
application dated 20.09.2025 bearing Registration
No.NSCREG03556196, the 2
nd
respondent Corporation personnel
approached the subject premises of the petitioner and found that there
was already an existing electricity connection bearing
No.133320N142000140, issued originally on 17.01.2019, in the name of
Smt. K. Madhura Meenakshi W/o. Kadagala Srinivas Rao.
13. She further submitted that the said service connection was
disconnected due to non-payment of C.C. charges. She further stated
that despite several phone calls made to the petitioner, no amount has
been paid by him, which resulted in non extension of the electricity
connection by the 2
nd
respondent Corporation authorities.
14. Learned counsel further stated that, if the petitioner pays the
requisite amounts, the 2
nd
respondent Corporation authorities, would
provide the electricity service connection to the petitioner, subject to the
fulfilment of statutory requirements.
8
15. At that juncture, learned counsel for the petitioner, with reference
to the Addl. Affidavit filed along with material papers in I.A. No.2 of 2026
in W.P. No.2103 of 2026, vehemently contended that the alleged
electricity connection bearing No.133320N142000140 stands in the
name of Smt.K.Madhura Meenakshi and not in the name of the
petitioner. She submitted that on transfer request made by the
petitioner’s wife Smt.K.Madhura Meenakshi, the 6
th
respondent Office
vide Notice Rc.No.201/2024 dated 12.07.2024 had removed the said
connection by giving specific assurance that they would provide
electricity service connection, but the 2
nd
respondent Corporation neither
restored nor reinstalled the electricity connection in her favour till today.
16. Learned counsel further contended that the petitioner’s wife lastly
paid electricity charges on 26.07.2024 and asserted that since there is
no electricity connection from 12.07.2024 onwards, the imposition of
charges on the disconnected service connection itself is baseless and
fictitious. She also raised that the very action of the 2
nd
respondent
Corporation authorities in not providing electricity service connection in
spite of the petitioner having fulfilled all the statutory pre-requisites in
terms of section 43 of the Electricity Act 2003 is arbitrary. More so, she
submitted that the 2
nd
respondent Corporation authorities, without stating
any reasons, simply by displaying the application of the petitioner as
9
permanently rejected., which is highly illegal and antithetical to the
settled legal provisions, apart from gross violation of the principles of
natural justice as well as transgression of Articles 19 & 21 of Constitution
of India.
17. At last, learned counsel submitted that the 2
nd
respondent
Corporation would consider the petitioner’s application as per the Rules
in vogue.
Analysis and Conclusion:
18. On the basis of the above pleadings as well as contentious
assertions raised by the respective counsels on either side, this Court
venture to address the following core point:
(1) Whether the action of the 2
nd
respondent Corporation authorities
in permanently rejecting the petitioner’s application for new
electricity service connection is valid or not?
19. In this context, it is relevant to note the significance of electricity in
its different forms that would also trace its clues in multiple ways in Vedic
period also.
20. In view of the significance and importance attached to the
Electricity which is the inextricable and inseparable to the minute to
minute work in this generation and added to that, this Court within short
span of time with the present Roster of cases, noticed that the citizens
10
from the remote, isolated and under developed regions are anxiously
approaching Courts by invoking its extraordinary powers under Article
226 of the Constitution of the India seeking electricity service
connections for their right to eking out livelihood and overall
development, which is the central theme of our Indian Constitution.
21. It is apposite to state that electricity is one of the most important
necessities in our lives, and it is difficult to imagine a world without it.
From lighting rooms, to the computers and other advanced technology,
whether it is at homes, schools or workplaces, our daily routines heavily
rely upon the electricity. With the increase in digital technology in health
care, education, communication and numerous other fields, a stable
electricity supply is very essential and due to lack of such facility, the
very fundamental rights enunciated in Part III of our Indian Constitution
would be greatly affected.
22. In Chameli Singh v. State of Uttar Pradesh
1
, the Hon’ble
Supreme Court while dealing with the Right to Shelter had observed that
right to shelter does not just mean a right to roof but includes right to all
infrastructural necessity too, which enables the individuals to live and
develop as a human being with adequate living space, safe and decent
1
(1996) 2 SCC 549
11
structure, clean and decent surroundings, sufficient light, pure air, water,
electricity, sanitation and other civic amenities. The expression in terms
of our Apex Court reads as under:-
8. “In any organised society, right to live as a human being
is not ensured by meeting only the animal needs of man. It is
secured only when he is assured of all facilities to develop
himself and is freed from restrictions which inhibit his growth. All
human rights are designed to achieve this object. Right to live
guaranteed in any civilised society implies the right to food,
water, decent environment, education, medical care and shelter.
These are basic human rights known to any civilised society. All
civil, political, social and cultural rights enshrined in the
Universal Declaration of Human Rights and Convention or
under the Constitution of India cannot be exercised without
these basic human rights. Shelter for a human being, therefore,
is not a mere protection of his life and limb. It is home where he
has opportunities to grow physically, mentally, intellectually and
spiritually. Right to shelter, therefore, includes adequate living
space, safe and decent structure, clean and decent
surroundings, sufficient light, pure air and water, electricity,
sanitation and other civic amenities like roads etc. so as to have
easy access to his daily avocation. The right to shelter,
therefore, does not mean a mere right to a roof over one's head
but right to all the infrastructure necessary to enable them to
live and develop as a human being...”
23. Undisputedly, electricity, being a basic necessity, is an integral part
of “Right to Life” as enshrined under Article 21 of the Constitution of
India. In Dilip (Dead) through LRs. v. Satish & Ors.
2
, the Hon’ble
Supreme Court observed that electricity is a basic amenity of which a
person cannot be deprived and the electricity supply authority is required
2
2022 SCC OnLine SC 810
12
to examine whether the applicant for electricity connection is in
occupation of the premises in question.
24. The Electricity Act, 2003 was enacted with the object and
intendment to consolidate the laws relating to generation, transmission,
distribution, trading and use of electricity and also to protect the interest
of consumers and supply of electricity to all areas, more particularly, to
the rural regions. In fact, the Electricity Act, 2003 marked a paradigm
policy shift in power regime connoting specific responsibilities and duties
cast upon all the stakeholders in the power sector. In a nutshell, the
Electricity Act 2003 is a progressive legislation.
25. It is imperative to note the relevant provisions of the Electricity
Act, 2003. Part II, details the National Electricity Policy and Plan,
wherein, Section 5 of the Electricity Act, 2003 elaborates the National
Policy on electrification and local distribution in the rural areas. Section
6 of the Electricity Act, 2003, came into force on 15.06.2007 and casts a
joint responsibility on the State Government and Central Government in
rural electrification. In furtherance, the concerned governments
together have to take all steps to provide access to electricity to all
areas, including hamlets, villages, through development of rural
electricity infrastructure measures.
13
26. Part III of the Electricity Act, 2003 deals with the generation of
electricity, such as hydro-electric and captive generation. Part IV of the
Electricity Act, 2003 enunciates licensing of the electricity power, transit,
supply, etc. Part V of the Electricity Act, 2003 highlights the transmission
of electricity inter-state and intra-state, while Part VI of the Electricity Act,
2003 deals with distribution of Electricity Provisions with respect to
distribution licensees, wherein, Section 42 of the Electricity Act, 2003
relates to duties of distribution licensee and open access. Section 43 of
the Electricity Act, 2003 clearly elucidates the duty to supply on request
in respect of the electricity service connection to the required persons.
Part VII of the Electricity Act, 2003 relates to Tariff and Part VIII of the
Electricity Act, 2003 relates to Works of Licensees. The remaining
provisions of the Electricity Act, 2003 provide for the constitution of
electricity authorities, appellate forums, dispute resolution mechanism,
enforcement procedures and other protective clauses.
27. The Union of India also framed Electricity Rules, 2004 as well as
Forum of Regulators Rules, 2005, the Work of Licensees Rules,2006,
and the Appellate Tribunal for Electricity Rules, 2007, so as to give a
practical effect to the provisions of the Electricity Act, 2003.
28. In the wake of the above statutory realm, it is apt to note section
43 of the Electricity Act, 2003, which is extracted hereunder:-
14
“Section 43. (Duty to supply on request): ---
(1) 1[Save as otherwise provided in this Act, every distribution] licensee,
shall, on an application by the owner or occupier of any premises, give supply of
electricity to such premises, within one month after receipt of the application
requiring such supply: Provided that where such supply requires extension of
distribution mains, or commissioning of new sub-stations, the distribution
licensee shall supply the electricity to such premises immediately after such
extension or commissioning or within such period as may be specified by the
Appropriate Commission: ”.
Provided further that in case of a village or hamlet or area wherein no
provision for supply of electricity exists, the Appropriate Commission may
extend the said period as it may consider necessary for electrification of such
village or hamlet or area. 1[Explanation.- For the purposes of this sub-section,
“application” means the application complete in all respects in the appropriate
form, as required by the distribution licensee, along with documents showing
payment of necessary charges and other compliances.]
(2) It shall be the duty of every distribution licensee to provide, if required,
electric plant or electric line for giving electric supply to the premises specified in
sub-section (1) : Provided that no person shall be entitled to demand, or to
continue to receive, from a licensee a supply of electricity for any premises
having a separate supply unless he has agreed with the licensee to pay to him
such price as determined by the Appropriate Commission.
(3) If a distribution licensee fails to supply the electricity within the period
specified in sub-section (1), he shall be liable to a penalty which may extend to
one thousand rupees for each day of default.”
A plain reading of Section 43 of the Electricity Act 2003 clearly reveals
that duty rests upon the distribution licensee to supply electricity to the
owner or occupier’s premises within one month from the date of receipt
of application, subject to fulfilling the pre-requisites. The Section also
stipulates penalties and judicial intervention in the event of failure on the
part of distribution licensee to comply with its duties.
15
29. The A.P.R.E.C. being a statutory body constituted under Section
82 of the Electricity Act, 2003 approved the “General Terms and
Conditions of Supply of Distribution and Retail Supply Licensee in
Andhra Pradesh” (GTCS)., after following the due procedure and
considering the General Terms and Conditions of Supply by the
Distribution companies in the State of Andhra Pradesh. Clause 5 of the
GTCS deals with supply of Electricity. For the sake of comprehensive
view, the relevant clause 5 of the GTCS is extracted hereunder:
“5. Supply of Electricity
5.1 Company's Duty to Supply:
The Company shall, on an application by the owner or occupier
of any Premises, located in his area of supply, give supply of
electricity to such Premises in accordance with Section 43 of
the Act and the APERC ('Licensees' duty for supply of electricity
on request) Regulation, 2004 (No.3 of 2004) as well as the
APERC (Licensees' Standards of Performance) Regulation,
2004 (No.7 of 2004). The applicant must however ensure
compliance with the procedure specified in the GTCS.
5.2 Requisition for Supply:
The requisition shall be made by the owner or occupier of the
premises for which supply is required. The application form
complete in all respects and accompanied by the undertaking
and prescribed fees, charges and security, shall be submitted at
the office of the Officer specified in the Designated Officers'
Notification. The Company shall verify the application and the
enclosed documents at the time of receipt of application, and
shall issue a written acknowledgement.
………..”
30. The aforesaid clause mandate that requisition for electricity
supply preferred by the owner or occupier of the premises by submitting
16
complete application form along with requisites such as charges and
security deposits before the concerned authority upon receiving of said
complete application. In turn, the distribution licensee authorities are
duty bound to verify the said application along with accompanying
documents and issue written acknowledgment to that effect.
31. Coming to further relevant clause i.e., 5.2.6 of GTCS, which is
quoted here under:
“5.2.6 A consumer requiring supply for industrial or
commercial purposes for new or additional loads shall obtain
the necessary licence or permission or no-objection certificate
from the local authority or any other competent authority as
might be required under the statute.”
The above said clause also stipulates that any consumer seeking
electricity supply for industrial and commercial purposes is required to
obtain the necessary permission or No Objection Certificate from the
concerned local authority or competent authority.
32. It is also apt to mention that A.P.R.E.C., (Regulation No.6 of
2024) which was published in gazette on 28.08.2024 prescribes specific
standards to be followed by distribution licensee. Under Item IX of
Schedule II of the principal regulation, a mandatory duty is cast upon the
concerned distribution licensee to release the new connection after
receiving the required charges within the period of 15 days in rural
areas. It also provides that in the event of violation of the prescribed
17
standards, compensation shall be given to the consumer for each day of
default. For a holistic perspective, the above stated Regulation portion
which came into effect from 28.08.2024 onwards reads as follows:
Sl.No. Service
Area
Time
Standard
Compensation payable in case of
violation of standard
Compensation
payable to
individual
consumer if
the event
affects a
single
consumer
Compensation
payable to
individual
consumer if
the event
affects more
than one
consumer
IX Release of new connection/additional load upon payment of all
charges
i All cases if
connection is
feasible from
existing
network for
release of
supply
Within three
days in
metropolitan
areas,
Within seven
days in other
municipal areas
and
Within 15 days
in rural areas
Upon receipt of
the complete
application
(along with
prescribed
charges)
Rs.100 for each
day of the default
Not applicable
ii. Network expansion / enhancement required to release of
supply
a Release of
supply - Low
Tension
With in 30 days
of receipt of
prescribed
charges
Rs.100 for each
day of default
b Release of
supply - High
With in 60 days
of receipt of
Rs.100 for each
day of default
18
Tension 11
KV
prescribed
charges
Not applicable
c Release of
supply - High
Tension 33
KV
With in 90 days
of receipt of
prescribed
charges
Rs.500 for each
day of default
d Release of
supply –
Extra High
Tension
With in 180
days of receipt
of prescribed
charges
Rs.500 for each
day of default
e Erection of
substation
required to
release of
supply
Where such
supply requires
commissioning
of new
substations, the
distribution
licensee shall
supply the
electricity to
such premises
immediately
after such
commissioning
within a period
not exceeding
90 days
Rs.1000 for each
day of default
(BY ORDER OF THE COMMISSION)
Place: Kurnool P. KRISHNA,
Date: 27.08.2024 Commission Secretary (I/c).
33. In the light of above statutory provisions, coupled with relevant
Rules and regulatory schemes, it is evident that the one of the laudable
objectives of legislative bodies is to provide electricity supply to needy
people who applied by fulfilling procedural pre-requisites. Another
significant facet is that the above statutory prism also specifies that in
the event the licensee fails to supply electricity within a prescribed
period, the distribution licensee become liable to pay compensation for
each day of delay, as determined by the concerned regulatory authority.
19
Hence, the provisions of the Electricity Act, 2003, are mandatory in
nature. It is also well settled that ‘mandatory provision gives no
discretion to the concerned authorities, who are bound to follow
mandatory provisions without any retractions upon fulfilling the
prerequisites.
34. Importantly, the above statutory provisions encompassed in the
Electricity Act, 2003 and its rules were also extremely and vividly
articulated by the Constitutional Courts, out of which, some of pivotal
expressions are discussed here under with a sole object to gain a
complete picture.
35. In Chandu Khamaru v. Nayan Malik and Ors.
3
, the Apex Court
clarified that Section 43 of the Electricity Act, 2003 imposes statutory
and mandatory obligation on the distribution licensee to supply electricity
to any applicant who complies with the prescribed formalities and held
that supply cannot be denied on the basis of private disputes, including
ownership or third-party objections, as such, issues fall outside the
scope of the licensee’s authority. It also explains that timely access to
electricity is a basic necessity, and any unjustified refusal or delay would
be contrary to the object of Section 43 of the Electricity Act, 2003. The
relevant portion of the said judgment is extracted hereunder:-
3
(2011) 12 SCC 314
20
“7. ...Sub-section (1) of Section 43 provides that every distribution
licensee, shall, on an application by the owner or occupier of any premises,
give supply of electricity to such premises, within one month after receipt of
the application requiring such supply. These provisions in the Electricity
Act, 2003 make it amply clear that a distribution licensee has a statutory
duty to supply electricity to an owner or occupier of any premises located in
the area of supply of electricity of the distribution licensee, if such owner or
occupier of the premises applies for it, and correspondingly every owner or
occupier of any premises has a statutory right to apply for and obtain such
electric supply from the distribution licensee…….”
36. In Brihanmumbai Electric Supply & Transport Undertaking v.
Maharashtra Electricity Regulatory Commission
4
, the Hon’ble
Supreme Court, while interpreting Section 43 of the Electricity Act, 2003,
held that the provision imposes universal service obligation on every
distribution licensee to supply electricity to any owner or occupier within
its area upon application and also emphasized that this duty is statutory
and mandatory, reflecting the essential nature of electricity as a public
utility. At the same time, Apex Court also clarified that such obligation
operates within the framework of the Act, and regulations, allowing the
licensee to enforce reasonable conditions such as compliance with
technical requirements and payment of charges. Thus, Section 43 of the
Act, 2003 ensures a right to access electricity, balanced by regulatory
control to maintain efficiency and financial discipline in the power sector.
The relevant portion of the said judgment is extracted hereunder:
4
(2015) 2 SCC 438
21
26. “......Here, it excludes local authority, as distributor of electricity from
such an obligation. However, when it comes to the duty of distribution
licensee to supply the electricity under Section 43, it mandates that same is
to be given to the owner or occupier of any premises on his application
within one month from the receipt of the said application. This duty under
Section 43 imposed upon a distribution licensee does not distinguish
between a local authority and other distribution licensee. It is also not a
case of the appellant that in a particular area where a local authority is a
distribution licensee, there cannot be any other distribution licensee at
all……..”
37. In the case of Dilip (referred to supra), the Apex Court observed
that electricity supply is statutory service arising out of a contractual
relationship between the consumer and the electricity authority, and the
obligation to pay electricity charges is confined to the person who
consumed the electricity. It was held that such dues do not attach to the
property itself and therefore cannot be automatically enforced against a
subsequent purchaser. However, the authority is entitled to prescribe
lawful conditions, including clearance of arrears, for granting fresh
electricity connection, to safeguard its revenue.
9. “It is now well settled proposition of law that electricity is a basic amenity
of which a person cannot be deprived. Electricity cannot be declined to a
tenant on the ground of failure/refusal of the landlord to issue no objection
certificate....”
22
38. In K.C. Ninan v. Kerala State Electricity Borad
5
, the three (3)
Judge Bench of the Apex Court, held and clarified that the licensee is
entitled to insist upon compliance with statutory requirements, including
payment of outstanding dues attached to the premises, and adherence
to the supply code and emphasized that electricity supply is premises-
centric rather than purely consumer-centric. Therefore, new applicant
may be required to clear past dues linked to the property before granting
fresh connection. Thus, Section 43 creates a right to supply, but one
that is regulated by lawful conditions to ensure financial discipline and
prevent misuse.
39. In Smt. Villuri Sirisha Rani v. State of Andhra Pradesh (Writ
Petition No. 28943 of 2024, dated: 16.12.2024), this Hon’ble Court, while
interpreting Section 43 of the Electricity Act, 2003, held that statutory
duty is held upon the electricity distribution licensee to supply electricity
to any premises upon an application made by the owner or occupier
within the prescribed time and emphasized that this obligation is
mandatory in nature, cannot be denied merely on the ground of disputes
regarding title or alleged unauthorized construction. Relying on Section
43 of the Electricty Act, 2003, the Court concluded that electricity supply
as basic amenity, and the authorities were bound to restore the
connection notwithstanding objections from local authorities.
5
(2023) 14 SCC 431
23
40. In B. Munirathnam v. Andhra Pradesh Southern Power
Distribution Company Ltd. (Writ Petition No. 7120 of 2024, dated
26.03.2024), the Court addressed the arbitrary delay in granting an
electricity connection to the petitioner and held that access to electricity,
being a basic necessity, cannot be denied or kept pending without valid
justification and the lack of authority to communicate without giving clear
reasons or deficiencies in writing was found to be violative of the
principles of natural justice and fairness. Further, it is emphasised that
administrative authorities are duty-bound to act in transparent, reasoned
manner, and any unexplained inaction offends Articles 14 and 21 of the
Constitution.
41. Reverting to the case on hand, the petitioner placed Exs.P.3, P.4
& P.5. Ex.P.3 is an application for the supply of electricity bearing
registration No.NSCREG03556196 dated 20.09.2025 with relevant fee.
Ex.P.4 is No-Objection Certificate dated 20.09.2025 from the concerned
Gram Panchayat. Ex.P.5 is House tax receipt depicting the petitioner’s
name. A cumulative perusal of Ex.P.3 to Ex.P.5 submitted by the
petitioner clearly suggests that he has fulfilled all pre-requisite conditions
i.e., filling the application with the under taking form, requisite fee and
also no objection certificate from the concerned competent civic
authority for obtaining new electricity service connection.
24
42. The case canvassed by the petitioner is that, after completion of
the required period from the date of his application, he approached the
6
th
respondent office and enquired about his application status. Later, on
10.10.2025, the 6
th
respondent personnel came to the petitioner’s
premises along with village linemen so as to fix the electricity service
connection, but due to local political pressures, the 6
th
respondent
personnel stopped installation of the electricity service meter and went
away along with the said meter.
43. The petitioner also projected that in spite of his repeated
enquiries with the 2
nd
respondent Corporation personnel, they have not
informed any reasons for not extending the electricity service
connection. At last, the petitioner came to know through the online
portal maintained by the 2
nd
respondent Corporation that the application
was permanently rejected.
44. Evidently, as stated supra, the 2
nd
respondent Corporation
authorities have not filed any counter affidavit to deny the case asserted
by the petitioner. However, the 2
nd
respondent Corporation authorities'
version, as argued by the learned Junior Standing Counsel, is that the
respondent Corporation had not disputed the application dated
20.09.2025 (Ex.P.1) preferred by the petitioner for new electricity service
connection. She contended that the petitioner’s wife service connection
25
bearing No.133320N42000140 was disconnected and there was an
arrears still pending and in spite of the 6
th
respondent phone calls, to the
petitioner, there was no response for payment.
45. Apparently, the 2
nd
respondent Corporation authorities neither
denied nor disputed the rejection of the petitioner’s application
permanently through online web-portal for electricity supply connection
(Ex.P.1). So far as the assertion made by the petitioner regarding local
interference that was culminated into non-installation of the meter in the
subject premises, the petitioner except self-serving statement made in
the affidavit about the local political intervention., has not ventured to
array the said political personality as party respondent nor filed any
single scrap of paper to substantiate it. Hence, this court is not delving
into those superficial aspects.
46. The version of the 2
nd
respondent Corporation is that the subject
premises already ha s service connection bearing
No.133320N42000140, which was disconnected and arrears with regard
to the said service connection are pending. It is relevant to note that
even according to the version of the 2
nd
respondent’s Corporation, the
above service connection bearing No.133320N42000140 stands in the
name of Smt.K.Madhura Meenakshi, who is the wife of the petitioner.
26
47. Whereas, the assertion of the learned counsel for the petitioner
that the electricity service connection stands in the name of the
petitioner’s wife, Smt. K.Madhura Meenakshi, who made request to shift
the electricity connection, then the said connection was disconnected
and removed by the 6
th
respondent Authority after issuing the written
notice Rc.No.AE 201/2024, dated 12.07.2024. Further, the learned
counsel for the petitioner also contended that the 2
nd
respondent
corporation personnel are merely attempting to dispute the case of the
petitioner without any clarity.
48. Even assuming for a moment that the case exposed by the 2
nd
respondent Corporation is true and correct, indisputably, the electricity
service connection bearing No.133320N42000140 stands in the name of
Smt.K.Madhura Meenakshi, but not in the name of the petitioner and
even as per the Notice vide Rc.No.AE 201/2024 dated 12.07.2024 (filed
along with I.A 2 of 2026), the above service connection was removed by
the 6
th
respondent Authority. In view of specific assertions made by the
petitioner that she has paid certain amounts towards the due and by way
of official communication dated 12.07.2024, the 2
nd
respondent
Corporation informed the petitioner to clear the arrears, but not to the
petitioner’s wife. Moreover, the 2
nd
respondent corporation has also not
produced the relevant copy of said bills or any communication
27
addresses to the concerned. In the absence of above, the assertions of
the respondent Corporation remain pale and insignificant.
49. Evidently, the 2
nd
respondent Corporation did not take such a
ground or reason in permanently rejecting the petitioner’s new electricity
service connection. In this aspect, the law is well settled in the dictum
held by the Apex Court in K.S Gill Vs. Chief Election Commissioner of
India.
6
“…….The second equally relevant matter is that when a
statutory functionary makes an order based on certain grounds, its
validity must be judged by the reasons so mentioned and cannot
be supplemented by fresh reasons in the shape of affidavit or
otherwise. Otherwise, an order bad in the beginning may, by the
time it comes to court on account of a challenge, get validated by
additional grounds later brought out……..”
50. That apart, the petitioner, by categorically mentioning his
requirement that he has to start flour mill business in his subject property
situated at Parampet, Srikakulum District, has applied for electricity
connection by paying the pre-requisite charges along with No-Objection
Certificate dated 20.09.2025 issued by the concerned Civic Authority.
Thereafter, the said application of the petitioner dated 20.09.2025 was
rejected permanently by the 2
nd
respondent Corporation authority on
their website portal without assigning any reasons at all.
6
1978 (1) SCC 405
28
51. Yet another significant aspect involved in the lis is that the
petitioner, after knowing the fact that his application dated 20.09.2025
has been permanently rejected through the online web portal, preferred
written representation dated 20.02.2026 to the 6
th
respondent by
marking the said copies to the other officials of the 2
nd
respondent
Corporation, so as to know the specific reasons for permanently
rejecting his application. In proof of the same, the petitioner placed
copy of written representation dated 20.02.2026 (Ex.P-2) along with
postal track delivery reports (Ex.P-6), which confirm that the said
representation dated 20.02.2026 was delivered to the 2
nd
respondent
Corporation authorities. In other words, the 2
nd
respondent Corporation
authorities, despite receiving the written representation dated
20.02.2026 from the petitioner, has not initiated any remedial measures
to rectify their unilateral action either.
52. Even if the petitioner’s application was incomplete due to lack of
proper enclosures at that juncture also, it is the duty of the 2
nd
respondent Corporation authorities to give specific reasons for rejection
of the petitioner’s application. Whereas, the 2
nd
respondent Corporation
simply mentioned in their online portal that the petitioner’s application
status as “Permanently Rejected”, without any reasons at all. Such an
action from the 2
nd
respondent Corporation on the primary ground
29
without giving specific reasons, is not only illegal, but also clear
transgression of principles of natural justice. Moreover, the right to
know the reasons for decision which adversely affects person or
property., is a basic right of every litigant (whether the forum be judicial
or administrative).
53. In this facet, it is apt to note the authoritative Constitution Bench
decision held in Shri Swamiji of Shri Admar Mutt etc. Vs. The
Commissioner, Hindu Religious and Charitable Endowments Dept.
and Ors.
7
. While giving the majority judgment, a reference was made to
Broom's Legal Maxims (1939 Edition, page 97), where the principle in
Latin reads as follows:
“ 29 …...Ces-sante Ratione Legis Cessat Ipsa Lex" in
general version "Reason is the soul of the law, and when the
reason of any particular law ceases, so does the law itself.”
54. Thus, way back in the year 1980 itself, the Constitutional dictum
emphasized the importance of reasons, holding that they are inextricable
and inseparable part of any orders passed by the adjudicating Foras.
55. Again, in the case of Kranti Associates (P) Ltd. v. Masood
Ahmed Khan
8
, the Hon’ble Supreme Court of India, after scanning the
authoritative judicial pronouncements in detail and articulated the
7
(1979) 4 SCC 642
8
(2010) 9 SCC 496
30
importance of reasoning by the judicial and quasi-judicial authorities, as
under:
“ 47. Summarising the above discussion, this Court holds:
a. In India the judicial trend has always been to record
reasons, even in administrative decisions, if such decisions affect
anyone prejudicially.
b. A quasi-judicial authority must record reasons in support of
its conclusions.
c. Insistence on recording of reasons is meant to serve the
wider principle of justice that justice must not only be done it
must also appear to be done as well.
d. Recording of reasons also operates as a valid restraint on
any possible arbitrary exercise of judicial and quasi-judicial or
even administrative power.
e. Reasons reassure that discretion has been exercised by the
decision maker on relevant grounds and by disregarding
extraneous considerations.
f. Reasons have virtually become as indispensable a
component of a decision making process as observing principles
of natural justice by judicial, quasi-judicial and even by
administrative bodies.
g. Reasons facilitate the process of judicial review by superior
Courts.
h. The ongoing judicial trend in all countries committed to rule
of law and constitutional governance is in favour of reasoned
decisions based on relevant facts. This is virtually the life blood of
judicial decision making justifying the principle that reason is the
soul of justice. i. Judicial or even quasi-judicial opinions these
days can be as different as the judges and authorities who
deliver them. All these decisions serve one common purpose
which is to demonstrate by reason that the relevant factors have
been objectively considered. This is important for sustaining the
litigants' faith in the justice delivery system.
j. Insistence on reason is a requirement for both judicial
accountability and transparency.
31
k. If a Judge or a quasi-judicial authority is not candid enough
about his/her decision making process, then it is impossible to
know whether the person deciding is faithful to the doctrine of
precedent or to principles of incrementalism. l. Reasons in
support of decisions must be cogent, clear and succinct. A
pretence of reasons or `rubber-stamp reasons' is not to be
equated with a valid decision making process.
m. It cannot be doubted that transparency is the sine qua non
of restraint on abuse of judicial powers. Transparency in decision
making not only makes the judges and decision makers less
prone to errors but also makes them subject to broader scrutiny.
(See David Shapiro in Defence of Judicial Candor (1987) 100
Harward Law Review 731-737).
n. Since the requirement to record reasons emanates from the
broad doctrine of fairness in decision making, the said
requirement is now virtually a component of human rights and
was considered part of Strasbourg Jurisprudence. See (1994) 19
EHRR 553, at 562 para 29 and Anya vs. University of Oxford,
2001 EWCA Civ. 405, wherein the Court referred to Article 6 of
European Convention of Human Rights which requires,
"adequate and intelligent reasons must be given for judicial
decisions".
o. In all common law jurisdictions judgments play a vital role in
setting up precedents for the future. Therefore, for development
of law, requirement of giving reasons for the decision is of the
essence and is virtually a part of “Due Process.”
56. Given the above statutory realm in vogue, coupled with the
authoritative pronouncements of the Apex Court as well as this Court, it
is crystal clear that the right to electricity is an integral and inextricable
part of Article 21 of the Constitution of India, and if there is any violation
of the same, it affects the fundamental rights enunciated in Part III of the
Constitution of India. In view of the significance & importance attached
to electricity as detailed above, right from the Vedic period till the present
32
contemptuous generation i.e., Gen-Z and Alpha., the usage of electricity
in multiple dimensions basic fundamental thing for minute to minute
work.
57. For the foregoing discussion and conclusion arrived at, this Court
is of the view that the 2
nd
respondent Corporation authorities are
required to follow the mandatory provisions of the Electricity Act, 2003 &
various Rules framed in terms of the above consolidated enactment that
would uplift the constitutional objects. Therefore, the writ petition is
disposed of, in the following terms:
i. The action of the 2
nd
respondent Corporation in permanently
rejecting the petitioner’s application dated 20.09.2025 for
grant of new electricity service connection bearing
registration No.NSCREG03556196., is set aside.
ii. The 2
nd
respondent Corporation authorities, are hereby
directed to process the petitioner’s application dated
20.09.2025 bearing registration No.NSCREG03556196.,
afresh, on collection of charges, if any, by following the true
letter and spirit of Section 43 of the Electricity Act, 2003 and
relevant Rules thereon, within a period of two (2) weeks,
from the date of receipt of copy of this Order.
iii. In view of the significance attached to electricity in the day-
to-day lives of people as discussed (supra), this Court also
deems it appropriate to direct the 1
st
respondent to initiate all
comprehensive and effective measures to implement the
statutory provisions, without any retraction. Hence, the 1
st
respondent is hereby directed to instruct all the distribution
licensees in the State of Andhra Pradesh to submit their
respective comprehensive reports for every three (03)
months., with particulars such as date of applications for
electricity service connection, processing time and final result
of the said application. Based on that, the 1
st
respondent
shall, in turn, conduct review of the said reports and issue
33
appropriate directions/guidelines to the distribution licensees
in order to fulfil the constitutional goals as well as the
statutory provisions of the Electricity Act, 2003 & relevant
Rules thereon., subject to the ground realities and
requirements.
58. Accordingly, the writ petition is disposed of. There shall be no
order as to costs. As a sequel, all pending applications shall stand
closed.
______________________________________
JUSTICE MAHESWARA RAO KUNCHEAM
Date: 22.06.2026
GVK
L.R to be marked
B/o.
GVK
34
01
THE HONOURABLE SRI JUSTICE MAHESWARA RAO KUNCHEAM
WRIT PETITION No: 8103 of 2026
Date: 22.06.2026
GVK
In a significant ruling by the High Court of Andhra Pradesh at Amaravati, the fundamental Right to Electricity was unequivocally upheld, reinforcing the mandatory obligations under the Electricity Act 2003. This pivotal judgment, now extensively analyzed on CaseOn, serves as a crucial precedent for consumer rights against arbitrary denials of essential services. The case, KADAGALA SRINIVAS RAO v. THE STATE OF ANDHRA PRADESH & ORS., WRIT PETITION NO: 8103/2026, delivered on June 22, 2026, underscores the judiciary's commitment to ensuring equitable access to power, particularly for those seeking to establish livelihoods.
The petitioner, Kadagala Srinivas Rao, sought a new electricity service connection for his small flour mill in Parampeta Village, Vizianagaram District. Despite completing all necessary application procedures, including obtaining a No-Objection Certificate (NOC) and paying requisite fees on September 20, 2025, his application was "permanently rejected" online by the 2nd respondent, the Eastern Power Distribution Company of A P Ltd (APEPDCL), without any stated reasons. An attempt to install the meter was reportedly halted due to "local interference," and subsequent inquiries and a written representation from the petitioner went unanswered. This prompted Mr. Rao to approach the High Court under Article 226 of the Constitution of India.
The core question for the High Court to address was:
The High Court meticulously examined various legal provisions and judicial precedents:
To deepen your understanding of these and other significant rulings, CaseOn.in offers concise 2-minute audio briefs that distill complex legal analyses into easily digestible summaries, proving invaluable for legal professionals navigating intricate case law.
The High Court observed that the 2nd respondent Corporation failed to file a counter-affidavit, leaving the petitioner's factual assertions largely unchallenged. The petitioner had duly submitted his application, requisite fees, and the No-Objection Certificate. The respondent's verbal claim of a pending disconnection and arrears related to a previous connection in the petitioner's wife's name was found to be unsubstantiated and lacked clarity, especially given the petitioner's assertion that the previous connection was removed upon request, not disconnected for non-payment, and that his wife had made payments. Crucially, the online "Permanent Rejection" without any stated reasons directly violated principles of natural justice and the mandatory provisions of the Electricity Act, 2003, and associated regulations. The Court reiterated that a statutory functionary's order must be judged by the reasons mentioned at the time of the order, not by subsequent justifications.
Based on its comprehensive analysis, the High Court:
The writ petition was thus disposed of, without costs.
This judgment serves as a robust reminder of several key legal principles:
This decision is a significant step towards ensuring transparency, accountability, and the protection of fundamental rights in the provision of essential public utilities.
All information provided in this article is for informational purposes only and does not constitute legal advice. While efforts have been made to ensure accuracy, readers should consult with a qualified legal professional for advice pertaining to their specific circumstances.
Legal Notes
Add a Note....