As per case facts, the petitioner, a subcontractor, completed ground improvement works for the Polavaram Irrigation Project under the main contractor. Due to the main contractor's financial distress, the State ...
Reserved on 10.12.2025
Pronounced on 08.01.2026
Uploaded on 08.01.2026
APHC010552292023
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3333]
THURSDAY,THE EIGHTH DAY OF JANUARY
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE SMT JUSTICE V.SUJATHA
WRIT PETITION NO: 28711/2023
Between:
1. KELLER GROUND ENGINEERING INDIA PRIVATE LIMITED,, A
COMPANY INCORPORATED UNDER THE COMPANIES ACT, 1956
AND HAVING ITS REGISTERED OFFICE AT 7TH FLOOR, EASTERN
WING, CENTENNIAL SQU ARE, 6A - DR. AMBEDKAR ROAD,
KODAMBAKKAM CHENNAI, TAMIL NADU, 600024. REPRESENTED
BY ITS AUTHORIZED REPRESENTATIVE, MR. M. GANESH KUMAR.
...PETITIONER
AND
1. STATE OF ANDHRA PRADESH, REPRESENTED BY ITS PRINCIPAL
SECRETARY, WATER RESOURCES DEPARTMENT, A.P.
SECRETARIAT VELAGAPUDI, GUNTUR DISTRICT.
2. THE CHIEF ENGINEER, POLAVARAM IRRIGATION PROJECT,
DOWLAISWARAM, EAST GODAVARI DISTRICT.
3. STATE OF ANDHRA PRADESH, REPRESENTED BY ITS PRINCIPAL
SECRETARY, FINANCE DEPARTMENT, A.P. SECRETARIAT,
VELAGAPUDI, GUNTUR DISTRICT
4. TRANSSTROY JSC EC UES JV, A COMPANY INCORPORATED
UNDER THE COMPANIES ACT, 1956 HAVING ITS OFFICE AT PLOT
NO. 201, 202 A AND 202 B, GUTTALA, BEGUMPET, KAVERI HILLS,
2
VS,J
W.P.No.28711 of 2023
HYDERABAD REPRESENTED BY ITS LIQUIDATOR DR.
GOVINDRAJULA VENKAT A NARASIMHA RAO
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased topleased to issue a writ, direction, or order more so in the nature of a
writ of mandamus- (a)declaring that the action of Respondent 1, the Water
Resources Department of the State of Andhra Pradesh (WRD) and
Respondent 2, the Chief Engineer, WRD, of withholding the amount due and
payable to the Petitioner towards the jet grouting, ECPT and vibro compaction
works completed at the Polavaram Irrigation Project is manifestly arbitrary,
unlawful and violates the Petitioner's rights under Articles 14 and 19 of the
Constitution of India, 1950, and consequently (b) direct the State of Andhra
Pradesh to remit amounts to the tune of INR 52,41,49,107/- (Rupees Fifty-
Two Crores Forty-One Lakh Forty-Nine Thousand One Hundred and Seven
only) (including GST) which are due and payable to the Petitioner along with
interest,
IA NO: 1 OF 2023
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
pleased to direct the Respondents Nos. 1, 2 and 3 to deposit the unlawfully
withheld amount of INR 52,41,49,107/- (Rupees Fifty-Two Crores Forty-One
Lakh Forty-Nine Thousand One Hundred and Seven only) due and payable to
the Petitioner with this Hon'ble Court and permit the Petitioner to withdraw the
aforesaid amount of INR 52,41,49,107/- (Rupees Fifty-Two Crores Forty-One
Lakh Forty-Nine Thousand One Hundred and Seven only) deposited by the
Respondents
Counsel for the Petitioner:
1. SAI SANJAY SURANENI
Counsel for the Respondent(S):
1. GP FOR FINANCE PLANNING
3
VS,J
W.P.No.28711 of 2023
2. GP FOR IRRIGATION COMM AREA DEV
The Court made the following:
4
VS,J
W.P.No.28711 of 2023
ORDER:
This Writ Petition came to be filed under Article 226 of the Constitution of
India seeking the following relief:-
“….to issue a writ, direction, or order more so in the nature of a writ of
mandamus- (a)declaring that the action of Respondent 1, the Water
Resources Department of the State of Andhra Pradesh (WRD) and
Respondent 2, the Chief Engineer, WRD, of withholding the amount due
and payable to the Petitioner towards the jet grouting, ECPT and vibro
compaction works completed at the Polavaram Irrigation Project is
manifestly arbitrary, unlawful and violates the Petitioner's rights under
Articles 14 and 19 of the Constitution of India, 1950, and consequently (b)
direct the State of Andhra Pradesh to remit amounts to the tune of INR
52,41,49,107/- (Rupees Fifty-Two Crores Forty-One Lakh Forty-Nine
Thousand One Hundred and Seven only) (including GST) which are due
and payable to the Petitioner along with interest….”
2. The petitioner herein is a company incorporated under the provisions of
the Companies Act, 1956 and is engaged in the business of ground
improvement, which is a critical part of all construction projects. It is a well
known fact that Polavaram Irrigation Project is a multi-purpose public works
project that provides irrigation to the highland areas of Visakhapatnam, East
Godavari, West Godavari and Krishna districts. Polvaram Irrigation Project
was declared as a national project under Section 90 of the Andhra Pradesh
State Reorganization Act, 2014 and subsequently, the Polavaram Project
Authority was constituted by the Central Government vide gazette notification
dated 28.05.2014. Vide office memorandum F.No.1(2)/PF-1/2014, dated
5
VS,J
W.P.No.28711 of 2023
30.09.2016, the Government of India decided that the State of Andhra
Pradesh would execute all irrigation related construction works of the
Polavaram Irrigation Project on its behalf. The 1
st
respondent is the
responsible authority for the construction and development of irrigation
projects in the State of Andhra Pradesh such as the Polavaram Irrigation
Project and the 2
nd
respondent herein is the Chief Engineer for the Polavaram
Irrigation Project.
3. On 02.03.2013, the 2
nd
respondent entered into an Engineer,
Procurement and Construction agreement with the 4
th
respondent –
Transstroy JSC EC UES (JV), for carrying out construction works at the
Polavaram Irrigation Project which includes, surveying, investigation, sub-soil
exploration, designs, engineering, estimates and construction of the Earth
dams for Gap-I & Gap-III, Earth-cum-rock fill dam for Gap-II, spill channel and
excavation of foundations for a 960 MW hydroelectric power house including
approach channel, intake structure etc. A supplementary agreement was also
executed between the respondent authorities and the 4
th
respondent on
07.10.2016. In a meeting held on 08.06.2017 and 09.06.2017, the Dam
Designs Review Panel decided to carryout geotechnical investigations that are
necessary for the design of the Earth-cum-Rock Fill dam and to use jet
grouting for the cut-offs at the upstream and downstream coffer dams.
6
VS,J
W.P.No.28711 of 2023
4. Subsequently, the 4
th
respondent sub-contracted part of the scope of
work to the petitioner herein through the following work orders:
i. Work Order dated 03.06.2017 for Electronic Cone
Penetration Tests for an Earth-cum-Rock Fill dam base and
along the axis of upstream and downstream cofferdams for
the Polavaram Irrigation Project.
ii. Work Order dated 11.07.2017 for execution of jet grouting
works for cut-off at the upstream and downstream
cofferdams for the Polavaram Irrigation Project.
iii. Work orders dated 27.09.2017 and 03.02.2018 for carrying
out ground improvement using vibro-compaction for the
proposed Earth-cum-Rock Fill dam foundation at the
Polavaram Irrigation Project.
5. As the 4
th
respondent was in financial distress due to pending
insolvency proceedings, in order to ensure that the work undertaken by the
sub-contractors of the 4
th
respondent is not hindered, the State of Andhra
Pradesh sanctioned a special imprest amount (Rs.170,00,00,000/-) so that the
sub-contractors of the 4
th
respondent could be paid directly by the
respondents. Subsequently, vide Minutes of Meeting dated 12.06.2017, the 1
st
respondent instructed the 4
th
respondent and the petitioner herein to
7
VS,J
W.P.No.28711 of 2023
commence the work immediately. Accordingly, the petitioner commenced the
works as per the abovementioned work orders by incurring an initial
expenditure of Rs.15,00,00,000/- and Rs.13,79,00,000/- towards mobilization
of the requisite resources towards jet grouting work and the vibro-compaction
work.
6. Thereafter, the petitioner has completed all the works entrusted to it
through the aforementioned work orders and the same was also noted in the
Minutes of Meetings dated 29.10.2018, recorded in the review meeting
conducted by the respondent authorities. Subsequently, in addition to the
special imprest amount sanctioned by the State of Andhra Pradesh of
Rs.170,00,00,000/-, the 1
st
respondent also recovered an amount of
Rs.302,10,00,000/- from the 4
th
respondent‟s running account bills and
encashed all the bank guarantees furnished by the 4
th
respondent to a tune of
Rs.689,83,00,000/-. In spite of the same, the 1
st
respondent only paid
Rs.2,00,00,000/- for the vibro-compaction work and Rs.71,26,62,284/- for the
jet grouting work completed by the petitioner, by withholding the balance
amount of Rs.52,41,49,107/- towards the work of Electronic Cone Penetration
Tests, on the ground that the rates for undertaking such work, which had
originally been submitted to the 1
st
respondent in the year 2017, are not
approved by the Board of Chief Engineers.
8
VS,J
W.P.No.28711 of 2023
7. On 27.08.2019, the Board of Chief Engineers rejected the rate analysis
submitted by the 2
nd
respondent and directed the 3
rd
respondent to take a
decision on the payment to be made to the petitioner in accordance with basic
parameters and the payment schedule incorporated in the Engineer,
Procurement and Construction agreement dated 02.03.2013. As per the said
decision of the Board of Chief Engineers, an amount of Rs.45,90,00,000/- is
payable by the 1
st
respondent towards the jet grouting work. Subsequently, the
2
nd
respondent, vide letter dated 29.12.2020 acknowledged the role of
subcontractors, including the petitioner in the development of Polavaram
Irrigation Project and recommended that an amount of Rs.45,90,00,000/- be
paid to the petitioner. Though the Board of Chief Engineers finalized the
amount to be paid to the petitioner towards jet grouting work on 27.08.2019,
the respondent authorities, vide letters dated 03.12.2021, 06.01.2022 and
06.05.2022 revised the rates applicable towards the jet grouting work, but,
however, no payment was made to the petitioner subsequently.
8. The letter dated 29.12.2020 addressed by the 2
nd
respondent was
challenged by „M/s Ratna Infrastructure Projects Private Limited‟ in
W.P.No.701 of 2021 before this Court, wherein, initially this Court was pleased
to pass an interim order on 07.01.2021 directing the 1
st
respondent not to
disburse any amount from the account of the 4
th
respondent and has granted
stay on all further proceedings pursuant to the letter dated 29.12.2020
9
VS,J
W.P.No.28711 of 2023
addressed by the 2
nd
respondent. In the said writ petition, the petitioner having
got impleaded as respondent No.10 and filed a vacate stay petition.
Thereafter, this Court, vide interim order dated 17.07.2023, modified the
earlier interim order dated 07.01.2021 by directing respondent Nos.1 and 2
herein to consider the claim and process the admitted amount of
Rs.45,90,00,000/- in favour of the petitioner herein within a period of six (6)
weeks. Consequently, the petitioner, duly enclosing the order copy dated
17.07.2023, addressed a letter dated 07.08.2023 to respondent Nos.1 to 3
with a request to release the amounts payable to the petitioner. As the
amounts payable to the petitioner were not released by the respondent
authorities, the present writ petition is filed.
9. The 2
nd
respondent filed a detailed counter affidavit and also an
additional counter affidavit. It is averred in the counter affidavit that the present
writ petition is not maintainable as the respondent authorities have not entered
into any work agreement with the petitioner and that there is no contractual
relationship between the petitioner and the respondent authorities.
Furthermore, it is stated that the agreement entered into by the respondent
authorities and the 4
th
respondent in the year 2013 was terminated vide
Lr.No.CE/PIPHWunit/Polavaram/DCE/-II/OT-1/AEE-1/529m, dated 30.10.2019
due to slow work progress and the petitioner being subcontractor of the 4
th
respondent would not have any right to claim the amounts for the alleged
10
VS,J
W.P.No.28711 of 2023
works completed by the petitioner in the Polavaram Irrigation Project. It is
further stated in the counter affidavit that though the petitioner is a
subcontractor of the 4
th
respondent, the respondent authorities do not have
any kind of relationship with the petitioner and that the 1
st
respondent has no
knowledge about the agreements that took place between the petitioner and
the 4
th
respondent.
10. It is further stated that during the course of execution of the work by the
4
th
respondent, due to cash flow problems, the State of Andhra Pradesh has
sanctioned an amount of Rs.170,00,00,000/- as a special imprest amount for
arranging payments directly to the parties concerned subject to recovering the
same from the subsequent RA bills of the 4
th
respondent. Subsequently, on a
request made by the 4
th
respondent, a total amount of Rs.446,32,00,000/- has
been released to various agencies and as a part of the same, the petitioner
received an amount of Rs.73,20,24,786/-. It is further averred that the
Assistant Commissioner of Central Tax, Guntur CGST Division, Guntur
communicated Form GST DRC -13 notice dated 05.09.2023 to the 2
nd
respondent informing that the 4
th
respondent is a defaulter of GST with
demand order No.OIO No.02/2020-21-GST in C.No.V/GGST/15/04/2020-Adj,
dated 30.06.2020, Reference no of recovery C.No.V/04/14/2019 -ARC,
period:July 2017-18 to March, 2019. It is further averred in the counter
affidavit that any disputes in the amounts payable to the petitioner have to be
11
VS,J
W.P.No.28711 of 2023
sorted out by the petitioner with the 4
th
respondent but should not have filed
the present writ petition against the respondent authorities as Water
Resources Department is not responsible for the claim of the petitioner. As
such, requested to dismiss the writ petition.
11. In reply to the counter affidavit filed by respondent No.2, the petitioner
filed a reply affidavit stating that it entered into agreement with the 4
th
respondent for executing the works as per the work orders (mentioned in
paragraph No.4) with the knowledge and approval of the 1
st
respondent. As
the 4
th
respondent was under financial distress, the State of Andhra Pradesh
sanctioned a special imprest amount in order to enable the sub-contractors
like the petitioner to work without interruption and in order to receive payments
directly from the Government. It is further averred that the 1
st
respondent
repeatedly gave directions to the petitioner directly with regard to
commencement and progress of work and accordingly, vide Minutes of
Meeting dated 12.06.2017 and in few subsequent review meetings held by the
Department; the petitioner was also assured of payment of the amount
payable for the work executed by the petitioner. With regard to the contention
of the respondents that the petitioner need not be paid any amount due to
closure of imprest amount, the petitioner contended that pursuant to sanction
of Rs.170,00,00,000/- by the State of Andhra Pradesh towards imprest
amount, the Water Resources Department recovered an amount of
12
VS,J
W.P.No.28711 of 2023
Rs.302,10,00,000/- from the 4
th
respondent‟s running account bills and
encashed all bank guarantees furnished by the 4
th
respondent to a tune of
Rs.689,83,00,000/-. Vide its letter dated 29.12.2020, the Water Resources
Department stated that an amount of Rs.842,03,00,000/- was available with it
against the assets of the 4
th
respondent and in the very same letter, the
department proposed to pay an amount of Rs.45,90,00,000/- to the petitioner
towards completion of jet grouting work. Further, the petitioner reiterated the
facts pertaining to filing of W.P.No.701 of 2021 by a similarly situated sub-
contractor and the modified interim order dated 17.07.2023, which was
already discussed hereinabove. With regard to the notice issued by the
Assistant Commissioner of Central Tax, Guntur CGST Division, Guntur as
averred in the counter affidavit, the petitioner states that any such purported
liability faced by the Water Resources Department towards any alleged unpaid
dues under the Central Goods and Services Act, 2017 cannot absolve the
liability of payment on the part of the respondent‟s department to the
petitioner.
12. Heard Sri. Gokul Holani, learned counsel appearing on behalf of Sri. Sai
Sanjay Suraneni, learned counsel for the petitioner on record and learned
Government Pleader for Irrigation, assisted by learned Assistant Government
Pleader for Irrigation.
13
VS,J
W.P.No.28711 of 2023
13. Sri.Gokul Holani, learned counsel appearing for the petitioner, during
the course of arguments, reiterated the entire facts that led to filing of the
present writ petition and further contended that the 4
th
respondent sub-
contracted a portion of the works pertaining to development of Polvaram
Irrigation Project to the petitioner herein by issuing work orders (mentioned in
paragraph No.4). Subsequently, due to financial distress of the 4
th
respondent,
with a view to ensure that the works executed by the sub-contractors are not
hindered, the State of Andhra Pradesh sanctioned a special imprest amount of
Rs.170,00,00,000/- to facilitate direct payment to the sub-contractors of the 4
th
respondent. Thereafter, the petitioner has commenced the works allotted to it
as per the instructions of the 2
nd
respondent and by October, 2018, the
petitioner completed all the works entrusted to it under the aforementioned
work orders, which fact was also recorded in the Minutes of Meetings dated
29.10.2018 during a review meeting conducted by the respondent authorities.
Learned counsel strenuously contended that though the authorities recovered
an amount of Rs.302,10,00,000/- from the running account bills of the 4
th
respondent and further encashed bank guarantees furnished by the 4
th
respondent, apart from recovering the special imprest amount of
Rs.170,00,00,000/-, the respondent authorities paid only Rs.2,00,00,000/-
towards vibro-compaction works and Rs.71,26,62,284/- towards jet grouting
14
VS,J
W.P.No.28711 of 2023
works executed by the petitioner, but has withheld an amount of
Rs.52,41,49,107/- payable towards Electronic Cone Penetration Tests.
14. Learned counsel, while referring to a letter addressed by the 2
nd
respondent to the 1
st
respondent on 29.12.2020 submitted that an amount of
Rs.45,90,00,000/- was admitted to be payable to the petitioner towards jet
grouting works. Further, when the said letter was challenged by M/s. Ratna
Infrastructure Projects Private Limited in W.P. No.701 of 2021 before this
Court, initially, this Court was pleased to pass an interim order dated
07.01.2021 directing the 1
st
respondent not to disburse any amount from the
account of the 4
th
respondent and stayed all further proceedings pursuant to
the said letter. However, subsequently, the petitioner herein was impleaded as
respondent No.10 in the said writ petition and filed a petition seeking vacating
of the stay. Thereafter, by an order dated 17.07.2023, this Court was pleased
to modify the earlier order and directed respondent Nos.1 and 2 to consider
the claim and process the admitted amount of Rs.45,90,00,000/- in favour of
the petitioner within a period of six weeks. Though the petitioner addressed a
letter dated 07.08.2023 to respondent Nos.1 to 3, enclosing a copy of the said
order and requesting release of the amounts due, the respondent authorities
failed to release the admitted dues. Learned counsel for the petitioner sought
attention of this Court to a judgment dated 03.07.2024 of this Court in
W.P.No.23091 of 2023, which was filed by the petitioner herein against the
15
VS,J
W.P.No.28711 of 2023
respondent Department aggrieved by its action in withholding an amount of
Rs.15,64,50,743/- due and payable to the petitioner towards the Vibro
Compaction works completed by the petitioner at Polavaram Irrigation Project.
By way of the said judgment, this Court has directed the respondent
authorities to release the balance amount of Rs.7,82,27,371/- to the petitioner
within a period of three (3) months.
15. With regard to the averments made by the 2
nd
respondent in the counter
affidavit and the additional counter affidavit, learned counsel contended that
though the petitioner is a subcontractor of the 4
th
respondent and though it is
an undisputed fact that the 1
st
respondent entered into an agreement in the
year 2013 with the 4
th
respondent, the petitioner was directly instructed by the
1
st
respondent with regard to progress of work and assured that the petitioner
would be paid the amounts for the works executed by it which is also a part of
the Minutes of Meeting recorded on 12.06.2017, 11.12.2017, 29.01.2018,
19.02.2018, 09.04.2018, 13.08.2018, 20.08.2018, 29.10.2018 and others. In
such a case, it cannot be contended that the respondent authorities do not
have any relationship directly with the petitioner.
16. Learned counsel further contended that though the imprest amount to a
tune of Rs.170,00,00,000/- sanctioned by the State of Andhra Pradesh has
purportedly been closed, the same does not preclude the respondent
16
VS,J
W.P.No.28711 of 2023
authorities from releasing the amount payable to the petitioner despite
recovering an amount of Rs.302,10,00,000/- from the running account bills of
the 4
th
respondent and encashing all the bank guarantees furnished by the 4
th
respondent. When the 2
nd
respondent, vide letter dated 29.12.2020
recommended for payment of Rs.45,90,00,000/- to the petitioner towards the
jet grouting work out of a designated amount of Rs.95,83,20,000/- which has
to be adjusted proportionately among other sub-contractors, the respondent
authorities, on one pretext or the other, have been postponing payment of
such admitted amounts. Though the agreement dated 02.03.2013 entered
between Water Resources Department and the 4
th
respondent was terminated
by the Government vide proceedings dated 30.10.2019 it cannot be stated
that the petitioner need not be paid the amount for completion of Electronic
Cone Penetration Tests for an Earth-cum-Rock Fill dam base. Having
permitted the petitioner to complete the works in the Polavaram Irrigation
Project, the respondent authorities are liable to pay the petitioner for the work
completed by it for Electronic Cone Penetration Tests for an Earth-cum-Rock
Fill dam base. Stating thus, learned counsel sought for a direction to the
respondent authorities to pay the amounts payable to the petitioner.
17. On the other hand, learned Government Pleader for Irrigation reiterated
the contents of the counter affidavit and as well as the additional counter
affidavit filed by the 2
nd
respondent. He further contends that when the
17
VS,J
W.P.No.28711 of 2023
Engineer, Procurement and Construction agreement was between the Water
Resources Department and the 4
th
respondent on 02.03.2013, the petitioner
being a subcontractor of the 4
th
respondent and having no direct relationship
with the Water Resources Department cannot claim that the department is
liable to pay the amounts as claimed by the petitioner. Further, when the
agreement dated 02.03.2013 entered between the Water Resources
Department and the 4
th
respondent itself is not in existence and was
terminated way back in the year 2019 vide termination proceedings dated
30.10.2019 due to slow work progress, paying the amounts to the petitioner
for the work completed by it as per the agreement entered with the 4
th
respondent would not arise. Thus, learned Government Pleader for Irrigation
requested this Court to dismiss the writ petition.
18. Perused the entire material available on record.
19. It is an undisputed fact that the petitioner is a leading specialist in the
business of ground improvement works and plays a crucial role in all
construction projects. In the year 2013, the Water Resources Department
entered into an Engineer, Procurement and Construction agreement with the
4
th
respondent to carryout various constructions in the Polavaram Irrigation
Project. In the year 2017, under three different work orders (as mentioned
supra), the 4
th
respondent subcontracted the petitioner herein for execution of
18
VS,J
W.P.No.28711 of 2023
few specific works and subsequently, to ensure that the work being executed
by the sub-contractors of the 4
th
respondent shall not be hindered on account
of issues pertaining to cash flow, vide Minutes of Meeting dated 13.03.2017,
the State of Andhra Pradesh sanctioned a special imprest amount.
20. On 12.06.2017, a virtual review meeting was conducted for Polavaram
Irrigation Project and on a perusal of its Minutes, it can be seen at Sl.No.5 that
the 1
st
respondent herein has directly instructed the petitioner herein to
commence the work immediately and that day-to-day schedule has to be
presented before the Hon‟ble Chief Minister in the review meetings. As per the
said instructions, the petitioner commenced the work and by October, 2018,
the petitioner has completed all the works entrusted to it. Till date, the Water
Resources Department has paid Rs.2,00,00,000/- and Rs.71,26,62,284/- only
for the two works completed as per the work orders dated 11.07.2017,
27.09.2017 and 03.02.2018, but, the petitioner was not paid the amount
payable to it for completing the work of Electronic Cone Penetration Tests for
an Earth-cum-Rock Fill dam base, on the ground that the rates submitted by
the Water Resources Department were not approved by the Board of Chief
Engineers.
21. The 2
nd
respondent, in a letter dated 29.12.2020 addressed to the
Special Chief Secretary to Government, Water Resources Department ,
19
VS,J
W.P.No.28711 of 2023
discussed to settle the accounts of the 4
th
respondent. The entire case of the
petitioner rests on the said letter dated 29.12.2020 as observed earlier. A
perusal of the said letter would go to show that the Superintending Engineer
made a request to obtain orders of the Government for filing appropriate claim
in National Company Law Tribunal for securing the penal amount of
Rs.269,29,00,000/- to be levied against the 4
th
respondent. The
Superintending Engineer reported that after recovering departmental liabilities
amounting to Rs.711.63 crores from the assets of the 4
th
respondent worth
Rs.742.97 crores, an amount of Rs.31.34 crores would be available with the
Department. In addition to the said amount, it was stated that Rs.99.06 crores
have to be adjusted and in total, the department will be holding Rs.130.40
crores of the 4
th
respondent which was proposed to be adjusted in the
following manner:
“As frequent reminders are received from the German
Embassy and ministry of commerce and industry, GOI to the
Government of Andhra Pradesh to finalize the accounts of M/s.
Bauer. An amount of Rs.56.51 Crs shall be paid directly to M/s.
Bauer – L&T (JV) which is due from M/s. Transstroy JSC EC UES
(JV) from the balance amount of Rs.130.40 Crs of M/s. Transstroy
JSC EC UES (JV) assets available with the Department.
After completion of payment to M/s. Bauer- L&T (JV) dues of
Rs.56.51 Crs there will be a balance amount of Rs.73.89 Crs
(130.40-56.51) of M/s Transstroy JSC EC UES (JV) assets available
20
VS,J
W.P.No.28711 of 2023
with the Department. Small vendors and suppliers are also
significantly contributed in the work of Polavaram Irrigation Project,
an amount of Rs.23.958 Crs (List enclosed – Annexure – II) Shall be
paid directly from the balance amount of Rs.73.89 Crs.
After payment of dues of Small vendors and suppliers from the
assets of M/s. Transstroy JSC EC UES (JV) available with the
Department, there will be a balance amount of Rs.49.932 Crs (73.89
– 23.958) will be available with the Department.
The balance amount Rs.49.932 Crs will be available as assets
of M/s. Transstroy JSC EC UES (JV) with the Department. In
addition an amount of Rs.45.90 Crs will add to the assets of M/s.
Transstroy JSC EC UES (JV) after finalization of rate analysis of Jet
grouting. Hence a total amount of Rs.95.832 Crs (49.932+45.90)
shall be adjusted proportionately between M/s. Thriveni Earth
Movers Pvt Ltd, M/s. Geovale Services and M/s. Keller India Ltd.
Orders required from the competent authority for finalization of
accoutns of M/s. Transstroy JSC EC UES (JV), and to resolve the
issue of payments to M/s. Bauer – L&T (JV) and such other
vendors/contractors.
Further it is to submit that M/s Bauer and M/s Keller India
Limited are expert agencies in ground improvement works and they
are executing the works in Polavaram head works like Stone
columns, vibro compaction and deep soil mixing still they are
contributing the project and regularization of payment to them will
help in smooth progress of works without financial constraints to
these firms.”
21
VS,J
W.P.No.28711 of 2023
22. It can be seen from the above extracted portion of the letter addressed
by the 2
nd
respondent that the role of the petitioner herein in ground
improvement works in Polavaram Irrigation Project was recognized and out of
the remaining amount available with the department, the 2
nd
respondent
recommended the Government to pay Rs.45,90,00,000/- crores to the
petitioner herein. Admittedly, the Engineer, Procurement and Construction
agreement dated 02.03.2013 executed between the Water Resources
Department and the 4
th
respondent came to an end in the year 2019 vide
Lr.No.CE/PIPHWunit/Polavaram/DCE/-II/OT-1/AEE-1/529m, dated 30.10.2019
and the aforementioned letter of the 2
nd
respondent was addressed in the year
2020. In such a case, the arguments of learned Government Pleader for
Irrigation that the Government need not pay any amount to the petitioner as
the 2013 agreement itself was terminated in the year 2019, cannot be
sustained. Even after termination of the agreement between the department
and the 4
th
respondent in the year 2019, the 2
nd
respondent recommended the
Government to make payments to the petitioner, as extracted above, in the
year 2020, by which it can be inferred that the respondent authorities have
admitted/recognized that the petitioner has completed the work allocated to it.
23. It has to be noted that the 2
nd
respondent, in the letter dated
29.12.2020, though has recommended that the petitioner shall be paid an
amount of Rs.45.90 crores, subjected the same to „finalization of rate analysis
22
VS,J
W.P.No.28711 of 2023
for Jet Grouting‟. On 27.08.2019, the Board of Chief Engineers rejected the
rate analysis submitted by the 2
nd
respondent and directed the 3
rd
respondent
to decide on the payment to be made to the petitioner in accordance with
basic parameters and the payment schedule incorporated in the Engineer,
Procurement and Construction agreement dated 02.03.2013. As per the said
decision of the Board of Chief Engineers, an amount of Rs.45,90,00,000/- is
payable by the 1
st
respondent towards the jet grouting work. Even after
finalization of the rate analysis for Jet Grouting by the Board of Chief
Engineers on 27.08.2019, the Water Resources Department has continued to
revise the rates by way of various letters dated 03.12.2021, 06.01.2022 and
06.05.2022.
24. The letter dated 29.12.2020 addressed by the 2
nd
respondent was
challenged by „M/s Ratna Infrastructure Projects Private Limited‟ in
W.P.No.701 of 2021 before this Court, wherein, initially this Court was pleased
to pass an interim order on 07.01.2021 directing the 1
st
respondent not to
disburse any amount from the account of the 4
th
respondent and stayed all
further proceedings pursuant to the letter dated 29.12.2020 addressed by the
2
nd
respondent. In the said writ petition, the petitioner got impleaded as
respondent No.10 and filed a vacate stay petition. Thereafter, this Court, vide
interim order dated 17.07.2023, modified the earlier interim order dated
07.01.2021 as under:
23
VS,J
W.P.No.28711 of 2023
“For the reasons stated in the affidavit, as well as in the vacate Petition
along With the proceedings issued by Respondent No.3 to Respondent
No.1 dated 29.12.2020, there is a prima facie case in favour of
Respondent No.10. Accordingly, an interim direction already passed dated
07.01.2021 as referred above has been modified, directing Respondent
No.3 and Respondent No.1 to consider the claim and process the
admitted/approved amount of Rs.45.90 Crores in favour of Respondent
No.10 within a period of six weeks from the date of receipt of copy of this
order.”
25. It can also be seen that in W.P.No.23091 of 2023, filed by the very same
petitioner before this Court seeking direction to the respondents to release the
amount payable to the petitioner towards the completion of vibro compaction
works, this Court, having observed that the Water Resources Department is
the beneficiary out of the subject contract work executed by the petitioner,
directed the respondents to pay an amount of Rs.7,82,27,371/- within three
months. In compliance to the said order, the respondents have already paid
the amounts payable to the petitioner for the vibro compaction works
completed by it.
26. In view of the same It cannot be contended that merely because the
agreement entered between the Water Resources Department and the 4
th
respondent was terminated in the year 2019, the Water Resources
Department is absolved of its obligation to make payment for the works that
were admittedly completed by the petitioner in the year 2018 itself, which is
prior to termination of the abovementioned agreement. Having enjoyed the
24
VS,J
W.P.No.28711 of 2023
benefit of the works executed by the petitioner, denial of payment for the same
by the Water Resources Department would be wholly arbitrary, unjust, and
unsustainable in law. Further, the contention of learned Government Pleader
for Irrigation that no contractual relationship exists between the petitioner and
the department on the ground that the 2013 agreement was executed only
between the 4
th
respondent and the Water Resources Department is
untenable.
27. The material available on record would clearly show that the petitioner
executed the works under the supervision of the Water Resources
Department, and significantly, received direct instructions from the
Government authorities (Minutes of Meeting, dated 12.06.2017) for the
commencement and execution of the works. In such circumstances, it cannot
be argued that the petitioner had no direct nexus with the Water Resources
Department. Furthermore, the fact that the work executed by the petitioner
was duly acknowledged by the Water Resources Department in the letter
dated 20.12.2020, strengthens the claim of the petitioner. In view of the above,
the petitioner is clearly entitled to receive payment of Rs.45,90,00,000/- and
this Court does not find the arguments putforth by the learned Government
Pleader for irrigation to be effective.
25
VS,J
W.P.No.28711 of 2023
28. In the result, this writ petition is disposed of and the respondents are
directed to pay the amount of Rs.45,90,00,000/- to the petitioner within a
period of eight (8) months from the date of receipt of a copy of this order.
There shall be no order as to costs.
Consequently, Miscellaneous Petitions, if any, pending in this Petition
shall stand closed.
_____________________
JUSTICE V.SUJATHA
.01.2026
Gss
Legal Notes
Add a Note....