As per case facts, an Arbitral Tribunal awarded a termination payment to Kurukshetra Expressway Private Limited due to an Indirect Political Force Majeure Event leading to agreement termination. The National ...
FAO(OS)(COMM) 211/2026 Page 1 of 39
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 15.09.2026
Judgment pronounced on: 28.09.2026
Judgment uploaded on: 28.09.2026
# CNR No. DLHC010371002026
+ FAO(OS) (COMM) 211/2026, CM APPL. 53404/2026, CM
APPL. 53405/2026, CM APPL. 53406/2026 and CM APPL.
53407/2026
KURUKSHETRA EXPRESSWAY PRIVATE LIMITED
.....Appellant
Through: Mr. Sandeep Sethi, Mr. Rajiv
Nayar and Mr. Dayan Krishnan,
Sr. Advs. along with Mr. Rishi
Agrawala, Dr. Sunil Mittal, Mr.
Daksh Arora, Mr. Rajat Sinha,
Mr. Ranjan Mukherjee, Mr.
Anant Shukla, Mr. Krisna
Gambhir and Ms. Shreya Sethi,
Advs.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA
.....Respondent
Through: Mr. A. K. Nijhawan and Mr.
Abdul Vahid, Advs.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MS. JUSTICE SHAIL JAIN
J U D G M E N T
ANIL KSHETARPAL , J.:
1. The present Appeal has been filed assailing the correctness of
the judgment dated 28.07.2026
1
passed by the learned Single Judge
2
,
1
hereinafter referred to as „Impugned Judgment‟
2
hereinafter referred to as „LSJ‟
FAO(OS)(COMM) 211/2026 Page 2 of 39
through which the petition filed by the Respondent (Respondent
before the Arbitral Tribunal) under Section 34 of the Arbitration and
Conciliation Act, 1996
3
, challenging the Arbitral Award dated
16.08.2024
4
passed by a majority comprising of two members out of
three member Tribunal
5
, was allowed, setting aside the Arbitral
Award to the extent of relief granted in respect of Claim Nos.1 and 2,
towards Termination Payment and interest thereon, respectively.
2. At the outset, it must be highlighted that the challenge before
this Court, akin to that before the LSJ, was confined only to the Claim
Nos.1 and 2 raised by the Appellant (Claimant before the Arbitral
Tribunal). Hence, the examination in the present judgment is also
confined to the aforesaid claims.
A. BRIEF FACTUAL BACKGROUND:
3. In order to appreciate the present controversy, the facts in brief
are required to be noticed.
4. The present controversy finds its genesis in the Concession
Agreement dated 13.07.2010
6
, executed between the parties, whereby
the Appellant was granted a concession, on a Design-Build-Finance-
Operate-Transfer (DBFOT) basis, for the four-laning of the Rohtak–
Bawal Section of NH-71 in the State of Haryana, under NHDP III, for
a concession period of 28 years commencing from the appointed date
of 10.05.2011.
5. Pursuant to the Agreement, provisional Completion Certificates
3
hereinafter referred to as „Act of 1996‟
4
hereinafter referred to as „Arbitral Award‟
5
hereinafter referred to as „Arbitral Tribunal‟
6
hereinafter referred to as „Agreement‟
FAO(OS)(COMM) 211/2026 Page 3 of 39
were issued on 24.08.2013 and 30.09.2014, toll collection commenced
on 01.09.2013, and the final Completion Certificate was issued on
13.08.2018. Notably, disputes between the parties had earlier been the
subject matter of two rounds of arbitration. However, the present
proceedings arise out of the third round of arbitration culminating into
the Arbitral Award.
6. The third round of arbitration came to be initiated by the
Appellant on account of the prolonged suspension of toll operations
occasioned by the Farmers‟ Agitation and the COVID-19 pandemic,
which the Appellant characterised as an Indirect Political Force
Majeure Event subsisting beyond 180 days within a continuous period
of 365 days. Accordingly, the Appellant, vide letter dated 07.10.2021,
terminated the Agreement under Clause 34.8 thereof and called upon
the Respondent to make a Termination Payment of Rs. 1,347.53 Crore
together with certain other sums. Since no payment was forthcoming,
the dispute was referred to a third round of arbitration, culminating in
the Arbitral Award.
7. Before the Arbitral Tribunal, the Appellant filed its Statement
of Claim, raising (06) six claims besides interest and cost, including a
claim towards the Termination Payment and interest thereon. In turn,
the Respondent filed its Statement of Defence alongwith (05) five
counter claims aggregating to Rs.368 Crore, besides interest and costs.
8. Amongst the various Claims and Counter Claims, adjudicated
upon by the Arbitral Tribunal, Claims Nos.1 and 2 alone form the
subject matter of the present Appeal. The Claim No.1 came to be
allowed by the Arbitral Tribunal to the extent of Rs. 911.13 Crore, as
FAO(OS)(COMM) 211/2026 Page 4 of 39
against Rs. 1,347.53 Crore claimed, along with interest on
Termination Payment under Claim No.2 at graded rates. Aggrieved
thereby, the Respondent approached the LSJ, who by way of the
Impugned Judgment, set aside the Arbitral Award to the extent of
Claim Nos.1 and 2. Aggrieved thereby, the Appellant has now
approached this Court by way of the present Appeal.
B. SUBMISSION OF THE PARTIES:
9. Learned senior counsel representing the Appellant, has made
the following submissions:
9.1 It has been contended that the Appellant, as a
Concessionaire, raised a debt of Rs. 794.06 crore and invested
Equity of Rs.251.49 crore for construction of the Project with the
express approval of the Respondent under Articles 4.1.3(e) to (f)
5.2.2 of the Agreement. The Financing Agreement, Financial
Model and Financial Package were furnished to the Respondent,
scrutinised, modified in terms of its comments, and thereafter
accepted as being „in order‟, culminating in the declaration of
Financial Closure on 17.05.2011 in accordance with the
Respondent‟s policy dated 12.05.2010.
9.2 Further, it has been argued that the Agreement
undisputedly stood terminated on account of an Indirect Political
Force Majeure Event, and the Respondent took over the Project
Highway on 12.12.2021. Despite Article 37.3.3 of the
Agreement, the Respondent neither paid the Termination
Payment within 15 days nor deposited the toll revenues into the
Escrow Account, thereby wrongfully appropriating
FAO(OS)(COMM) 211/2026 Page 5 of 39
approximately Rs. 320 crore, which ought to have been utilised
towards discharge of the lenders‟ dues under Article 31.4.1 of the
Agreement.
9.3 The central submission of the learned senior counsel
orbited around the decision given by the LSJ, who as per the
Appellant erred in treating the Total Cost Project (TPC) and
Termination Payment as synonymous, thereby importing the
definition of TPC under Article 48.1 into the computation of
Termination Payment under Article 34.9.2, and introducing the
lowest of three limbs test, capped at Rs. 650 Crore.
9.4 By doing so, it has been argued that the LSJ, failed to
appreciate that Article 34.9.2 is a distinct and self-contained
operative provision, expressly providing that, upon termination
on account of an Indirect Political Event, the Appellant is entitled
to a Termination Payment „in an amount equal to: (a) Debt
Due... and (b) 110% of the Adjusted Equity‟.
9.5 Relying upon the introductory paragraph of the definition
clause under Article 48.1, reference has heavily been made to the
expression, „unless repugnant to the context or meaning thereof‟,
to argue that the definition of TPC could not be mechanically
imported into Article 34.9.2 of the Agreement so as to introduce
a substantive limitation not contemplated by the parties, thereby
introducing words „subject to a maximum of Rs.650 crores‟, into
Article 34.9.2.
9.6. It has been submitted that the LSJ, in the Impugned
FAO(OS)(COMM) 211/2026 Page 6 of 39
Judgment, misapplied K.V. Muthu v. Angamuthu Ammal
7
,
which, read correctly, and as followed in Jagdeep Chowgule v.
Sheela Chowgule
8
, and AICTE v. Shri Prince Shivaji Maratha
Boarding House's College of Architecture
9
, in fact supports the
Appellant‟s case, since it recognises that a defined term may bear
a different meaning where the context so demands, and that the
„unless repugnant to the context‟ qualification in the definition
clause itself permits departure from the defined meaning. In this
regard, it was further argued that the LSJ applied only the general
rule stated in that decision while ignoring the very exception on
which the Appellant‟s case rested and simultaneously overlooked
the opening words of Article 48.1 and the specific-clause-
prevails mandate of Article 1.4.2(a).
9.7 Relying upon the Agreement, it has been argued that it
prescribes a distinct formula for Termination payment depending
upon the nature of terminating events, highlighted under Articles
34.9.1, 34.9.2, 34.9.3 and 37.3.2. It was submitted that this
graded scheme, awarding progressively higher multiples of
Adjusted Equity depending on the degree of fault attributable to
the Respondent, is wholly irreconcilable with the existence of a
single, overriding Rs. 650 Crore ceiling common to all scenarios.
Since such a ceiling would render the enhanced 110%/150%
multiples otiose in precisely those cases where the formula, if
faithfully applied, would exceed Rs. 650 Crore. This internal
structure, it was submitted, is itself decisive of the parties‟
7
(1997) 2 SCC 53
8
(2026) 5 SCC 667
9
(2021) 12 SCC 629
FAO(OS)(COMM) 211/2026 Page 7 of 39
intention that TPC was never meant to operate as a ceiling on
Termination Payment.
9.8 Reliance has been placed on Articles 1.1.1 and 1.1.4 of
the RFP, to argued that Rs. 650 Crore was expressly described as
an estimated project cost at the bidding stage, with bidders
required to independently assess the actual project cost. Article
1.4.1 of the RFP, in particular, made it clear that this estimate
was not intended to survive as a cap on the Respondent‟s liability
upon termination.
9.9 Against this backdrop, it had been argued that the LSJ,
erred in elevating this estimated bid-stage figure into a binding
ceiling on Termination Payment, disregarding Article 1.4.1 of the
RFP, Article 2.2.4 of the Consultant Agreement, and Article
4.1.3(f) of the Agreement, and in doing so effectively re-
adjudicated the matter as though sitting in appeal over the
Arbitral Tribunal rather than exercising the limited jurisdiction
under Section 34 of the Act of 1996.
9.10. Relying on Nabha Power Ltd. v. Punjab State Power
Corporation Ltd.
10
, and Haris Marine Products v. Export Credit
Guarantee Corporation (ECGC) Ltd.
11
, it was submitted that a
commercial contract must be construed in a manner that accords
with business common sense and avoids commercial absurdity. It
was contended that capping the Termination Payment at Rs. 650
crores, despite the Respondent‟s knowledge and approval of the
10
(2018) 11 SCC 508
11
(2022) 20 SCC 776
FAO(OS)(COMM) 211/2026 Page 8 of 39
actual Debt of Rs. 794.06 crore and corresponding Equity, would
leave the Respondent with the commissioned highway while the
lenders remain unpaid, defeating the financing structure
underlying the PPP model.
9.11 It was further argued that the estimated TPC continues to
serve independent purposes under the CA, including bank
guarantees, Technical Expert‟s fee, change of scope thresholds
and appointment of an additional auditor. Thus, it was the LSJ‟s
interpretation, and not that of the Appellant, which rendered the
expressions „only the amounts so conveyed shall form the basis
of computing Termination Payment‟ and „amount equal to‟ in
Article 34.9.2 of the Agreement otiose.
9.12 It was the case of the Appellant that the view taken by the
Arbitral Tribunal was a plausible interpretation and not open to
interference under Section 34 of the Act of 1996. The Arbitral
Tribunal, upon construing Article 34.9.2 read with Article
1.4.2(a), the definition of Termination Payment and the
Disaggregation Letter dated 04.02.2019, awarded Rs. 561.30
crore towards Debt Due and Rs. 349.80 crore towards 110% of
Adjusted Equity, aggregating to Rs. 911.13 crore, strictly in
terms of the contractual formula. It was submitted that even the
Respondent, before the LSJ, had accepted that the Arbitral
Award was „at the least a plausible view‟, pointing to the
dissenting Member‟s own computation of Rs. 684.70 crore as
demonstrating that more than one reading of the contract was
reasonably possible.
FAO(OS)(COMM) 211/2026 Page 9 of 39
9.13. Reliance was placed on a consistent line of authority,
including Hindustan Construction Company v. NHAI
12
,
Konkan Railway Corporation Ltd. v. Chenab Bridge Project
Undertaking
13
, South East Asian Marine Engineering &
Construction Ltd. v. Oil India Ltd.
14
and Anglo American
Metallurgical Coal Pty. Ltd. v. MMTC Ltd.
15
, among others for
the settled proposition that a plausible interpretation adopted by
the Arbitral Tribunal cannot be substituted under Section 34
merely because another view is possible. It was further submitted
that, despite accepting the genuineness of the Disaggregation
Letter, the LSJ failed to give effect to it while computing the
Termination Payment.
9.14 As an additional and independent ground, a challenge has
also been raised, in the written submissions and the grounds of
appeal, to the findings returned by the LSJ on I.A. No. 540/2025.
However, the same was not pressed during the course of oral
arguments. Hence, we do not deem it appropriate to elaborate
upon the same.
10. Per contra, learned counsel representing the Respondent has
made the following submissions:
10.1 It was argued that Article 48 of the Agreement defines
TPC, as the lowest of three specified figures, namely, the capital
cost under the Financial Package, the actual capital cost upon
completion, and Rs. 650 crore, while Article 1.4.1 gives the
12
(2024) 2 SCC 613
13
2023 INS 742
14
(2020) 5 SCC 164
15
(2021) 3 SCC 308
FAO(OS)(COMM) 211/2026 Page 10 of 39
Agreement a precedence over other documents in case
consistency. It has been stated that the definition of Termination
Payment under Article 34.9.2 includes Debt Due and Adjusted
Equity, both of which being defined with reference to TPC,
makes the Termination Payment subject to the contractual ceiling
provided under Article 48.1 of the Agreement.
10.3 It was submitted that the Arbitral Tribunal, at paragraph
55 of the Arbitral Award, computed the Termination Payment on
the footing that the TPC was Rs. 1,045.5 Crore, in direct
contravention of the capped definition under Article 48.1, under
which the TPC could not exceed Rs. 650 Crore. This substitution
of a higher, uncapped figure for the contractually mandated
lowest-of-three limbs was not an exercise in interpretation but a
rewriting of the bargain between the parties.
10.4 It was further submitted that, independent of the above
error, the Arbitral Tribunal erred in additionally crediting a
separate equity component under Claim No.1. Since the debt
sanctioned to the Appellant by its lenders already exceeded/fully
covered the TPC (whether reckoned at Rs. 650 Crore or
otherwise), the TPC stood fully subsumed within the debt
component alone, leaving no occasion to separately reckon or
add an equity component. Since doing so would have resulted in
a double counting not contemplated by Articles 34.9.2 and 48 of
the Agreement.
10.5 In the alternative, and without prejudice to the foregoing,
it was submitted that even if both components, Debt Due and
FAO(OS)(COMM) 211/2026 Page 11 of 39
Adjusted Equity, are to be reckoned, their aggregate reflecting
the contractually envisaged debt-equity ratio of approximately
80:20, could not, in any event, exceed the overall TPC ceiling of
Rs. 650 Crore. On either analysis, the Arbitral Award of Rs.
911.13 Crore under Claim No.1 was demonstrably contrary to the
express terms of Articles 48.1 and 34.9.2 of the Agreement.
10.6 In support of the above, reliance was placed on Articles
4, 8, 26 and 31 to establish that the Respondent was not bound by
the Appellant‟s financing arrangements or the quantum of
debt/equity claimed by it, and the contractual obligations and
payment mechanism were governed by the Agreement itself. It
had further been submitted that Debt Due and related termination
entitlements could not exceed the contractually defined TPC, and
the Appellant will remain subject to its own obligations under the
Agreement.
10.7 Against the aforestated, it had been argued that the
Arbitral Tribunal, while computing Claim Nos.1 and 2,
disregarded the capped definition of TPC under Article 48.1 and
thereby rewrote the contractual bargain, amounting to patent
illegality under Section 34(2A) of the Act of 1996. Accordingly,
the LSJ rightly set aside the Arbitral Award qua Claim Nos.1 and
2, leaving the remaining claims and counter-claims undisturbed
and the Impugned judgment, therefore, warrants no interference.
C. ANALYSIS AND REASONING:
11. Before entering into the merits of any challenge to the
Impugned Judgment passed by the LSJ, this Court exercising
FAO(OS)(COMM) 211/2026 Page 12 of 39
jurisdiction under Section 37(1)(c) of the Act of 1996 must first
remind itself of the narrow channel within which the present
jurisdiction flows. An appeal contemplated by Section 37 is not an
occasion to re-examine the Arbitral Award at large, rather it is merely
confined to testing whether the LSJ, while exercising jurisdiction
under Section 34 of the Act of 1996 remained within the four corners
of the grounds available under the said provision.
12. The aforesaid position also stands settled by a consistent line of
Supreme Court authority. In Bombay Slum Redevelopment Corpn.
(P) Ltd. v. Samir Narain Bhojwani
16
, the Supreme Court held that the
Section 37 forum‟s task is only to ascertain whether the Court acting
under Section 34 exercised its jurisdiction within the statutory
grounds, a jurisdiction narrower even than that available under Section
34 itself. The same principle was reiterated in Reliance Infrastructure
Ltd. v. State of Goa
17
, where the Court cautioned that a Court acting
under Section 37 cannot travel beyond Section 34 to independently
reappreciate evidence or the merits of the underlying dispute.
13. Further, in Haryana Tourism Ltd. v. Kandhari Beverages
Ltd.
18
, it was held that the appellate court cannot convert itself into a
first appellate forum against the arbitral award, and its interference
remains confined to the recognised Section 34 grounds. More
recently, in Somdatt Builders-NCC-NEC (JV) v. NHAI
19
, the
Supreme Court observed that because the jurisdiction under Section
34 is itself narrow, the appellate jurisdiction under Section 37 over an
16
(2024) 7 SCC 218
17
(2024) 1 SCC 479
18
(2022) 3 SCC 237
19
(2025) 6 SCC 757
FAO(OS)(COMM) 211/2026 Page 13 of 39
order made under Section 34 becomes narrower, acting as a double
filter, so to speak. Lastly, AC Chokshi Share Broker (P) Ltd. v. Jatin
Pratap Desai
20
, further reinforces the position that the Section 37
Court‟s function is to test whether the Section 34 Court properly
exercised its jurisdiction, not to substitute its own view of the contract
where the Section 34 Court‟s view was itself a reasonable one.
14. The upshot of this recognised position of law is that this Court
while examining the Impugned Judgment, asks itself a narrower and
logical question, „did the LSJ, in setting aside the Arbitral Award on
Claim No.1, stay within the grounds that Section 34 permits, or did he
overstep them?‟ It is with this touchstone alone that the present appeal
must be examined.
15. Turning now to the dispute that arises before this Court, we
may note that the entire controversy in the present case traces to a
single interpretive fork in the road, what is the Total Project Cost
(TPC) against which the Termination Payment payable to the
Appellant is to be computed?
Overview of the findings given by the Tribunal and the LSJ
16. The Tribunal by way of the Arbitral Award, while answering
the aforesaid question, held that the Disaggregation Letter dated
04.02.2019, by which the Concessionaire notified the Respondent of a
TPC of Rs.1,045.55 crore constituted the operative and binding basis
for computing the Termination Payment. On this footing, applying the
formula under Article 34.9.2 of the Agreement, the Tribunal arrived at
20
(2025) 5 SCC 321
FAO(OS)(COMM) 211/2026 Page 14 of 39
a Termination Payment of Rs. 911.13 crore.
17. While reaching this conclusion, the Tribunal reasoned that
Article 1.4.2(a) of the Agreement, which provides that a specific
clause relevant to the issue at hand prevails over other clauses,
rendered the Rs. 650 crore ceiling included in the definition of TPC
under Article 48.1 as irrelevant to the computation of Termination
Payment, on the basis of a reasoning that the definition of Termination
Payment itself referred to the disaggregation notified by the Appellant
as the operative basis.
18. On the contrary, the LSJ held that the construction provided by
the Tribunal could not be sustained. On his reading, the definition of
TPC under Article 48.1, as the lowest of (a) the capital cost per the
Financial Package, (b) the actual capital cost on completion, and (c)
Rs. 650 crore less Equity Support, was not a free-standing or
dispensable definition. It was his view that the said provision and the
three limbs provided thereunder, laid at the very heart of the risk
allocation the parties had struck, and was designed specifically to cap
Respondent‟s exposure on termination.
19. The LSJ, with respect to the Disaggregation Letter, was of the
view that, it served a wholly different function, by merely
apportioning an already-determined TPC between its Debt and Equity
components and was not a mechanism by which the Appellant could
unilaterally enlarge the TPC itself. Upon reading the definition clause
and the Termination Payment clause together, the LSJ concluded that
the Termination Payment could not lawfully exceed what the TPC
definition permitted and set aside the Arbitral Award to that extent.
FAO(OS)(COMM) 211/2026 Page 15 of 39
Scope of jurisdiction exercised by the LSJ
20. At this stage, we deem it appropriate to also highlight the
boundaries of Section 34 of the Act of 1996, within the four walls of
which, the LSJ was expected to perform the jurisdiction so vested
upon him. Section 34 does not clothe the Court with appellate
jurisdiction over the merits of an arbitral award. Instead, it permits
interference only on the limited grounds enumerated in the provision,
including, where the Tribunal has taken a view that is otherwise a
possible one, the ground of patent illegality where the Tribunal has
construed the contract in a manner that no fair-minded or reasonable
person could adopt. Ordinarily, where the Tribunal‟s interpretation of
a contractual term is a possible one, the Court acting under Section 34
must defer to it, no matter how much it may itself have preferred a
different view.
21. Therefore, what follows from the aforestated is that whether the
LSJ correctly identified and applied the limited ground of patent
illegality, i.e., whether he was right to conclude that the Tribunal‟s
construction was not a possible one, and whether in undoing that
construction he himself stayed within the same narrow confines,
without descending into a re-appreciation of evidence or a substitution
of one reasonable contractual reading for another.
Examination of findings returned by the LSJ
22. Before proceeding further, we deem it appropriate to reproduce
the relevant paragraphs of the Impugned Judgment, which form the
basis of our analysis. The same is reproduced hereunder:
“53. This three limbed definition, particularly the cap contained in
FAO(OS)(COMM) 211/2026 Page 16 of 39
sub-clause (c), lies at the very heart of the Concession Agreement and
cannot be treated as surplusage for the purpose of determining the
“Termination Payment”. The purpose of this provision is clearly to
limit the financial exposure of NHAI upon termination. Indeed, this
provision is at the very heart of risk allocation in the Concession
Agreement.
54. Evidently, NHAI, as a public authority, set out this cap in the RFP
document itself so that its maximum financial exposure upon
termination would be confined to the project cost. This cap serves a
specific and vital commercial purpose; it protects NHAI against cost
over-run incurred by the concessionaire (whether due to inefficiency,
over borrowing or for any other reason) being passed on to NHAI in
the guise of a “Termination Payment”. Without this cap, a
concessionaire could borrow far in excess of the sanctioned project
cost and on termination, present NHAI with a demand that NHAI
never agreed to underwrite. The award by accepting the “total project
cost” at Rs.1045.5 Crore has rendered sub-clause (c) entirely
nugatory, effectively reducing it to a dead letter.
55. A copy of Request for Proposal (RFP) has been filed by the
Respondent. Clause 1.1.1 of the RFP clearly mentions the estimated
project cost as Rs. 650 Crore. The relevant portion of the same is
reproduced as under –
56. Evidently, the figure of Rs. 650 crore represented the estimated
Project Cost as reckoned at the time of bidding. By making it the
ceiling in the definition of the “Total Project Cost,” the parties sought
to ensure that, even if the actual cost exceeded this amount, NHAI‟s
financial exposure towards Termination Payment would continue to
be anchored to this ceiling. The unmistakable commercial rationale
underlying the contractual provision is that NHAI assumes the risk of
cost overruns during construction only to the extent contemplated
under sub-clause (c), and not in respect of any unlimited or excessive
expenditure that the Concessionaire may incur.
57. The Concession Agreement is founded upon a concession
FAO(OS)(COMM) 211/2026 Page 17 of 39
framework, under which the termination liabilities of the Authority are
capped. It is on strength of this risk matrix that bids were invited, that
the premium of Rs.12 crore per annum (escalating at 5% annually)
was offered by the respondent, and that the financial exposure of the
public exchequer stood crystallised. The ceiling ensures that the
consequence/s of any cost overrun or over-leveraging is not
transmuted into a liability of the Authority upon termination. To
construe the Agreement in a manner which dissolves this ceiling is to
redistribute, ex post facto, the very risk which the parties had
definitively allocated inter-se.
THE APPROVAL OF THE FINANCIAL PACKAGE DOES NOT
ASSIST THE RESPONDENT
58. Considerable emphasis was laid on behalf of the respondent on
the circumstance that the Financial Package (reflecting a capital cost
of Rs.992.58 crore), the Financial Model and the Financing
Agreements were scrutinised and approved by NHAI prior to financial
close. The submission is of no avail to the respondent. Sub-clause (a)
of the definition of "Total Project Cost" itself refers to "the capital
cost of the Project, as set forth in the Financial Package". The parties
were, therefore, fully alive to the fact that the Financial Package
would reflect a capital cost, and that such cost might well exceed
Rs.650 crore; it is precisely for this reason that the definition
stipulates that the Total Project Cost shall be the lowest of the three
specified amounts. The Financial Package figure thus stands
internalised within the definition itself – it supplies limb (a); it does
not, and cannot, abolish limb (c). The scrutiny of the financing
documents by the Authority serves an altogether distinct purpose,
namely, to ensure that the Concessionaire does not enter into
arrangements with its lenders which imperil the interests of the
Authority; such scrutiny cannot be construed as an undertaking by the
Authority to underwrite the entirety of the said cost upon termination.
Moreover, in terms of Article 1.4.1 of the Concession Agreement, the
Agreement prevails over all other documents.
TERMINATION SPECIFIC PROVISO – CONFIRMING ITS
APPLICABILITY FOR THE PURPOSE OF DETERMINING
“TERMINATION PAYMENT ”
59. The definition of “Total Project Cost” contains the following
proviso:
“provided that in the event of Termination, the Total Project Cost
shall be deemed to be modified to the extent of variation in WPI or
Reference Exchange Rate occurring in respect of Adjusted Equity and
Debt Due, as the case may be, in accordance with the provisions of
this Agreement; provided further that in the event WPI increases, on
an average, by more than 6% (six per cent) per annum for the period
between the date hereof and COD the Parties shall meet, as soon as
reasonably practicable, and agree upon revision of the amount herein
FAO(OS)(COMM) 211/2026 Page 18 of 39
before specified such that the effect of increase in WPI, in excess of
such 6% (six per cent), is reflected in the Total Project Cost;”
60. This proviso is of significant importance. It expressly addresses
the termination scenario and provides for the modification of the
“Total Project Cost” figure, but only to the extent of variation in the
WPI. The fact that the Concession Agreement itself incorporates a
termination-specific proviso into the definition of the “Total Project
Cost” conclusively establishes two things:
(i) that the definition is intended to apply in the context of termination
and is neither rendered inapplicable nor repugnant for the purpose of
determining the “Termination Payment”. A definition which itself
provides for the termination scenario cannot, in the same breath, be
branded as repugnant to that very scenario ;
(ii) that the parties specifically contemplated that the “Total Project
Cost” might require upward revision in a termination scenario, but
only by way of WPI adjustment and, where the WPI exceeded 6% per
annum, through mutual agreement between the parties. There is no
mechanism under the Concession Agreement permitting the
Concessionaire to unilaterally enhance the “Total Project Cost” by
relying upon a disbursement letter reflecting actual project costs far
in excess of the contractual cap.
61. If the parties had intended that the actual project cost notified in
the disaggregation letter would entirely displace or render nugatory
the definition of “total project cost”, there would have been no need
whatsoever for this proviso. Its very existence, providing a measured /
WPI linked adjustment mechanism, demonstrates that the parties
never intended the contractual cap to be by-passed by a unilateral
cost notification / disaggregation letter.
62. A unilateral notification by the Concessionaire of its actual
expenditure is not a mode of modification of the "Total Project Cost"
recognised anywhere in the Agreement. It is elementary that a
contract can be varied only in the manner provided therein or by the
mutual agreement of the parties; it cannot be varied by the unilateral
act of one party. Yet, the construction adopted by the Tribunal
ascribes to the disaggregation letter (a unilateral communication), the
effect of an amendment of the contractually defined "Total Project
Cost" from Rs.650 crore to Rs.1045.55 crore. No canon of
interpretation sanctions such an outcome.
DEFINITION OF “TERMINATION PAYMENT” EXPRESSLY
INCORPORATES THE CEILING REFERRE D TO IN THE
DEFINITION OF “TOTAL PROJECT COST”
63. The definition of “Termination Payment” in Article 48.1 provides
FAO(OS)(COMM) 211/2026 Page 19 of 39
that it “may consist of payments on account of and restricted to, the
Debt Due and Adjusted Equity, as the case may be, which form part of
the Total Project Costin accordance with the provisions of this
Agreement”.
64. Three expressions in this definition are of significant importance
and, independently support the relevance of the ceiling for the
purpose of determining the Termination Payment:
(i) “Restricted to” – the use of these words is intended to limit the
extent of the Termination Payment and to make it circumscribed;
(ii) “Which form part of the Total Project Cost” – this is a qualifying
and limiting stipulation. Only such Debt Due and Adjusted Equity as
form part of the contractually defined “Total Project Cost” are
payable. The inevitable consequence is that payments in excess of the
“Total Project Cost” are expressly excluded;
(iii) “In accordance with the provisions of this Agreement” – this
cross-reference ties the computation of the “Termination Payment” to
the definition of the “Total Project Cost” and precludes the possibility
of importing a different “Total Project Cost” figure from outside that
is at variance with, or inconsistent with, the contractual ceiling
contained in the definition of the “Total Project Cost.”
THE DISAGGREGATION LETTER CANNOT OVERRIDE THE
CAP IN THE DEFINITION OF “TOTAL PROJECT COST”; IT
OPERATES WITHIN IT
65. The respondent‟s principal submission, as accepted by the
Arbitral Tribunal, is that the disaggregation letter clause contained in
the definition
of “Termination Payment” makes the notified “Total Project Cost”
figure the sole basis for computing the “Termination Payment,”
thereby displacing the contractual cap of Rs. 650 crore. This
argument fundamentally misconstrues the function and purpose of the
disaggregation letter.
66. The disaggregation letter clause requires the Concessionaire to
notify NHAI of the “Total Project Cost” as on the COD, together with
its disaggregation into Debt Due and Equity. The purpose of this
requirement is to inform NHAI how the “Total Project Cost”, already
determined under the Concession Agreement as the lowest of the three
alternatives, is apportioned between its Debt Due and Equity
components so that the formula prescribed under Article 34.9.2 (Debt
Due + 110% Adjusted Equity) can be correctly applied.
67. The word “disaggregation” is itself dispositive. To disaggregate
means to break down a whole into its component parts. The
disaggregation letter mechanism is intended to allocate the “Total
Project Cost” between Debt Due and Equity. It is not a mechanism by
which the Concessionaire has been granted carte blanche to
FAO(OS)(COMM) 211/2026 Page 20 of 39
unilaterally „re-determine‟ the “Total Project Cost” or to undermine
or nullify the contractual ceiling prescribed thereunder.
68. If the interpretation canvassed by the respondent were correct, the
disaggregation letter would become an instrument by which the
Concessionaire could inflate NHAI‟s termination liability simply by
notifying a higher “Total Project Cost” figure, regardless of the
contractual ceiling prescribed for the same. This would lead to absurd
consequences and would be manifestly contrary to the intention of the
parties, who deliberately defined the “Total Project Cost” as the
lowest of the three alternatives
precisely to prevent such an outcome.
69. No rational commercial party could have intended that the
applicability of a ceiling, negotiated for the protection of one party,
should depend upon the unilateral election of the very party whom it
constrains. The deeming provision in the definition of “Termination
Payment” demonstrates that whether or not a disaggregation letter is
furnished, the contractually defined "Total Project Cost" remains
operative; the letter fixes the internal apportionment between debt and
equity, and nothing more. On the face of it, the letter is intended to
convey a “disaggregation”, not a unilateral re-valuation.
MISCONCEIVED RELIANCE ON THE EXPRESSION “ ONLY
THE AMOUNT SO CONVEYED SHALL FORM THE BASIS OF
COMPUTING TERMINATION PAYMENT” (OCCURING IN
THE DEFINITION OF “TERMINATION PAYMENT” AS
DEFINED UNDER ARTICLE 48)
70. The reliance placed by the Arbitral Tribunal on this expression is
untenable. The Arbitral Tribunal has, unfortunately, laid emphasis on
only a part of the relevant contractual provision while overlooking the
preceding as well as the succeeding parts of the same clause. The first
paragraph of the relevant clause defining “Termination Payment”
makes it expressly clear that the “Termination Payment” is to be
restricted to Debt Due and Adjusted Equity, which form part of the
“Total Project Cost.” The succeeding clarificatory paragraph refers
to the “Total Project Cost” and requires the Concessionaire to notify
the Authority of its disaggregation into Debt Due and Equity. The
stipulation that only the amount so conveyed or notified shall form the
basis for computing the “Termination Payment” was clearly not
intended to override the contractual ceiling contained in the definition
of the “Total Project Cost.” Had that been the intention of the parties,
nothing would have been easier than to expressly provide so.
71. The use of the expression “only the amount so conveyed shall form
the basis of computing the Termination Payment” was intended only
to preclude reliance upon extraneous sources for the purpose of
disaggregation. The concluding portion of the same paragraph is
significant. It provides that, in the event such disaggregation is not
FAO(OS)(COMM) 211/2026 Page 21 of 39
notified to the Authority, the Equity shall be deemed to be the amount
arrived at by subtracting the Debt Due from the “Total Project Cost.”
72. The above clearly demonstrates that the disaggregation letter is
only intended for the purpose of internal split between debt due and
equity; the outer limit as set out in the definition of the “total project
cost” is not rendered irrelevant.
THE FINDINGS QUA THE DISAGGREGATION LETTER DO
NOT CONCLUDE THE ISSUE
73. The Tribunal has devoted considerable attention to establishing
that the disaggregation letter dated 04.02.2019 exists; that the delay
in its submission was not attributable to any default or malafide on the
part of the Concessionaire; that its contents were not specifically
traversed by the Authority in its pleadings; and that the Independent
Engineer treated it as the formal disaggregation for the purpose of
computing the Termination Payment (paras 33 to 46 of the award).
This Court has no reason to disturb any of the said findings; they are
findings of fact within the exclusive domain of the Tribunal. The said
findings, however, do not carry the matter any further, inasmuch as
the existence, genuineness and bona fides of the letter were never
determinative of the controversy. The controversy concerns the legal
effect of the letter under the Concession Agreement and as to whether
it is capable in law of enlarging the "Total Project Cost" beyond the
contractual ceiling.
74. The reliance placed by the Tribunal on National Highway
Authority of India v. PNC-BEL (JV), 2019 SCC OnLine Del 9461 (at
para 46 of the award) is misplaced. It was held therein that the
certification by the Independent Engineer in that case, of rates in
respect of non-BOQ items, which the Engineer had certified and
submitted for approval, cannot be selectively disregarded by the
Authority. Evidently, the certification in question pertained to a
function which the contract contemplated from the Engineer. No such
function (for re-determining “Total Project Cost” in
derogation/disregard of the contractual ceiling) has been committed
to the Independent Engineer in the present case (as is evident from
contractual provisions noticed hereinbelow).
75. The reliance on Jetpur Somnath Tollways Limited v. National
Highways Authority of India, 2017 SCC OnLine Del 9453 (at para
53 of the award) is equally misplaced. The said decision was rendered
on petitions under Section 9 of the A&C Act (by the concessionaire
therein and by its lender), seeking interim measures of protection
pending arbitration, in the nature of a direction to NHAI to secure the
termination payment. The observations therein were, ex facie,
rendered at a prima facie stage, for the limited purpose of moulding
interim relief; they did not constitute a final adjudication of the
quantum of the termination payment. Further, the question considered
in paragraph 81 of the said decision was an altogether different one.
FAO(OS)(COMM) 211/2026 Page 22 of 39
NHAI had sought, on the strength of Recital B to the Common Loan
Agreement dated 19.08.2011 executed in that case (which recorded a
debt-equity ratio of 72.58:27.42 ) to import the said ratio so as to
make a further adjustment to the "Debt Due". It was in that context
that the Court observed that there was "admittedly, no such
stipulation in the Termination Payment clause that any such
adjustment is to be made prior to payment of the Debt Due" and that
"only the actual Debt Due has to be taken into account". The decision
thus declined to permit an adjustment extraneous to the contractual
provisions. The said judgement did not deal with the operation of a
definitional ceiling, forming an express part of the contractual text
itself. The said decision points against the respondent rather than in
its favour inasmuch as its ratio is fidelity to the „Termination
Payment‟ provisions as written. In the present case, the award
disregards the contractual ceiling of Rs.650 crore, and the words of
restriction in the definition of "Termination Payment".
76. Pertinently also, the function assigned to the Independent
Engineer under the Concession Agreement do not extend to
determining the "Total Project Cost". Article 23.2.1 provides that the
Independent Engineer "shall discharge its duties and functions
substantially in accordance with the terms of reference set forth in
Schedule-Q." The relevant portions of Schedule-Q read as under:-
“3.1 The role and functions of the Independent Engineer shall include
the following:
(vi) determining, as required under the Agreement, the costs of any
works or services and/or their reasonableness; ...
8.1 The Independent Engineer shall determine the costs and/or their
reasonableness that are required to be determined by it under the
Agreement”
77. The cost-determination function of the Independent Engineer is a
power exercisable only in respect of costs which the Agreement
specifically requires his determination. No provision of the
Concession Agreement commits the determination of "Total Project
Cost" to the Independent Engineer. The definition of "Total Project
Cost" in Article 48.1 is self-executing: it is the lowest of three
arithmetically stated figures, subject only to the WPI proviso (as
already noticed). What the Independent Engineer was called upon to
examine was whether the disaggregation letter dated 04.02.2019 "be
considered by the Authority as acceptable within the definition as
stipulated in the Concession Agreement" ( para 34 of the award). This
is a question of the timeliness and procedural acceptability of the
letter. The Tribunal's treatment of the Independent Engineer's
recommendation as though it were a determination of quantum does
violence to both the language and purport of the contract. The
Agreement nowhere empowers the Independent Engineer to approve,
sanction or certify a substitute "Total Project Cost" put forward
FAO(OS)(COMM) 211/2026 Page 23 of 39
unilaterally by the Concessionaire.
REPUGNANCY ARGUMENTS
78. The respondent has vehemently argued that the definition of the
“Total Project Cost” as on the COD is repugnant to the meaning
sought to be given by NHAI thereto. The said argument is thoroughly
misconceived.
79. Repugnancy can be said to arise only where the application of the
contractual definition results in a direct contradiction or absurdity. It
cannot be said to arise merely because the application of the
contractual definition results in a financially inconvenient outcome or
yields a lower recovery than that which the respondent would prefer.
80. Applying the “Total Project Cost” cap in the context of
“Termination Payment” does not create any absurdity or
contradiction. On the contrary, it produces precisely the outcome that
the parties agreed to when they executed the Concession Agreement.
The cap is not repugnant to the context of the “Termination
Payment”, rather, it is entirely consonant with it.
81. Importantly, as noticed hereinabove, the definition of the “Total
Project Cost” itself contains a termination-specific proviso
addressing WPI adjustments. A definition that expressly accounts for
a termination scenario cannot simultaneously be said to be repugnant
to the context of “Termination Payment.”
82. The authorities cited on behalf of the respondent in this behalf, far
from advancing its case, affirm the settled position that the defined
meaning is the rule and its displacement the exception. In K.V. Muthu
v. Angamuthu Ammal, (1997) 2 SCC 53, the Supreme Court held that
where a definition is preceded by the words "unless the context
otherwise requires", the definition is ordinarily to be applied and
given effect to, and may be departed from only if there is something in
the context to show that the definition could not be applied at all.
(paragraphs 10 to 12)
2
.
CLAUSE 1.4.2(a): NEITHER ATTRACTED NOR OF ANY
ASSISTANCE TO THE RESPONDENT
83. The Arbitral Tribunal has relied upon Article 1.4.2(a), which
provides that between two or more clauses, the specific clause
relevant to the issue under consideration shall prevail. Article 34.9.2
is indeed the specific provision governing the quantum of the
“Termination Payment” in the event of an Indirect Political Event.
However, the impugned majority award overlooks the fact that Article
34.9.2 operates by reference to the defined terms “Debt Due” and
“Adjusted Equity,” both of which are, in turn, defined by reference to
the “Total Project Cost.”
84. Thus, it is wholly untenable for the purpose of Article 34.9.2 to
ignore the definition of “Total Project Cost” inasmuch as the latter
FAO(OS)(COMM) 211/2026 Page 24 of 39
gives content to the relevant components of “Termination Payment”.
23. The LSJ while reaching to the conclusion of setting aside the
Arbitral Award to the extent of Claim No.1, located his interference
squarely within the ground of patent illegality under Section 34(2A) of
the Act of 1996, on the footing that the Tribunal‟s construction of the
TPC definition was not a construction that a fair-minded or reasonable
adjudicator could have arrived at on the words of the contract.
24. Notably, the law on when an arbitrator‟s interpretive exercise
crosses over into patent illegality is well settled. In Associate Builders
v. Delhi Development Authority
21
, the Supreme Court recognised that
while construction of contractual terms is ordinarily the exclusive
domain of the Arbitrator, this deference yields where the arbitrator
adopts a construction that no fair-minded or reasonable person could
adopt. This principle was carried forward into the statutory text of
Section 34(2A) of the Act of 1996 itself, as explained in Ssangyong
Engineering & Construction Co. Ltd. v. National Highways
Authority of India
22
, wherein the Court clarified that if the arbitrator
wanders outside the terms of the contract, or adopts a reading no
reasonable person would adopt, an error of jurisdiction results, falling
squarely within the new patent-illegality ground.
25. The distinction that emerges from this line of authority, and
which the LSJ also correctly drew upon, is between „interpreting‟ a
contract and „rewriting‟ it. An interpretation is the ascription of a
meaning that the words of the contract are reasonably capable of
bearing, however debatable that meaning might be; it is protected, and
21
(2015) 3 SCC 49
22
(2019) 15 SCC 131
FAO(OS)(COMM) 211/2026 Page 25 of 39
a court must not disturb it merely because another view is equally or
even more plausible.
26. By contrast, rewriting involves adding to, subtracting from, or
overriding what the parties actually agreed, so as to produce a bargain
the parties never made. This is precisely the defect identified by the
Supreme Court in PSA SICAL Terminals Pvt. Ltd. v. Board of
Trustees of V.O. Chidambranar Port Trust, Tuticorin
23
, and also
relied upon by the LSJ, wherein the Court held that an award that
effectively imposed upon the parties a bargain they had never struck
was held to be liable to interference as shocking the conscience of the
Court.
27. Applying this test, the central question before the LSJ was not
which of the two interpretations was better. The question was whether
the Tribunal had merely interpreted the definition of TPC or had
effectively rewritten it. The LSJ held that the Tribunal had rewritten
the definition, and it is this conclusion that now falls for consideration.
28. At its core, the dispute now raises one simple question: whether
the TPC for calculating the Termination Payment, is (i) the amount
determined under the three limbed definition under Article 48.1,
which is subject to a cap (as held by the LSJ), or (ii) the amount
notified by the Appellant to the Respondent through the
Disaggregation Letter as the actual project cost (as held by the
Arbitral Tribunal)?
29. On a considered examination of the Agreement as a whole, this
23
2021 SCC OnLine SC 508
FAO(OS)(COMM) 211/2026 Page 26 of 39
Court finds itself unable to fault the reasoning of the LSJ, inasmuch as
several provisions of the Agreement, when read together, support the
conclusion reached by him, which are examined hereunder.
30. Firstly, in the opinion of this Court, the Tribunal erred in
treating Article 34.9.2, which prescribed the formula for Termination
Payment, i.e., Debt Due and 110% of Adjusted Equity, as the only
specific provision governing the subject and, on that basis, permitting
it to override the definition of TPC contained in Article 48.1 by
invoking Article 1.4.2(a) of the Agreement.
31. However, the definition of TPC is itself a specific provision. It
expressly contemplates computation upon termination and contains a
termination-specific proviso dealing with WPI-based adjustment.
More importantly, it provides the basis for determining “Debt Due”
and “Adjusted Equity”, which are the very components used in the
formula under Article 34.9.2.
32. Where two provisions of a contract deal with the same subject,
the proper approach is to read them together and give effect to both,
rather than allowing one to override the other. This is what the
Impugned Judgment endeavours to do, it treats the definition of TPC
as prescribing the ceiling, while Article 34.9.2 provides the formula
for calculating the Termination Payment within that ceiling.
33. Such an interpretation gave effect to both provisions and
avoided rendering any part of the Agreement meaningless. On the
other hand, the Tribunal‟s interpretation, effectively rendered sub-
clause (c) of the TPC definition redundant. The Agreement must, as
far as possible, be construed in a manner that gives meaning and effect
FAO(OS)(COMM) 211/2026 Page 27 of 39
to all its provisions. The aforesaid position also stands recognised by
the Supreme Court in BGS SGS SOMA JV v. NHPC
24
, wherein it was
held that conflicting portions of a judgment must be harmonised by
reading the judgment as a whole and the same interpretive discipline
applies to contractual instruments.
34. Secondly, the LSJ was right in holding that the definition of
Termination Payment does not simply say that it consists of Debt Due
and Adjusted Equity; it says that it is „restricted to‟ the Debt Due and
Adjusted Equity „which form part of the Total Project Cost.‟ Words of
restriction and qualification deliberately incorporated into a definition
clause must be given meaning and effect.
35. Their purpose is precisely to cap the outer limit of the
obligation being defined. To read the clause as the Tribunal did,
permitting a Termination Payment computed on a debt and equity
figure with no relationship to the capped TPC, empties these words of
any operative content. This Court is unable to accept that
commercially sophisticated parties, negotiating a public infrastructure
concession running into decades, inserted words of limitation into the
very definition of the Respondent‟s termination liability without
intending them to limit anything.
36. Thirdly, the LSJ was right in holding that the proviso to the
TPC definition confirms, rather than dilutes, its application on
termination. If the parties had truly intended that the contractually
fixed TPC would become irrelevant upon termination, displaced
entirely by whatever figure the Appellant chose to notify, there would
24
(2020) 4 SCC 234
FAO(OS)(COMM) 211/2026 Page 28 of 39
have been no occasion for them to have inserted, within that very
definition, a proviso addressing how the TPC is to be adjusted for
WPI variation specifically „in the event of Termination‟.
37. The Agreement provides a specific mechanism for such
adjustment, namely, adjustment based on WPI variation, and where
such variation exceeds the prescribed limit, the adjustment is subject
to mutual agreement. No provision, however, permits the
Concessionaire to unilaterally enhance the TPC through a
Disaggregation Letter.
38. If the intention was that the contractually determined TPC
would cease to apply upon termination and could be replaced by any
figure notified by the Concessionaire, there would have been no need
for a termination-specific mechanism for adjustment of the TPC. The
existence of such a mechanism supports the view of the learned Single
Judge that the TPC continues to govern the computation of the
Termination Payment and may be adjusted only in the manner
provided under the Agreement. The Disaggregation Letter cannot be
treated as an independent or additional mechanism for enhancing the
TPC.
39. Fourthly, the LSJ rightly held that the function of
disaggregation is definitionally an internal apportionment, not a re-
valuation. The ordinary meaning of disaggregation, i.e., breaking a
known whole into its constituent parts, is itself instructive. The clause
requires the Appellant to notify the TPC as on COD and its break-up
between Debt and Equity. Whereas the deeming provision that
follows, equity to be treated as TPC less Debt Due, where no letter is
FAO(OS)(COMM) 211/2026 Page 29 of 39
furnished, shows that the entire clause is addressed to internal
allocation, not to establishing what the TPC itself is. To read a letter
whose stated purpose is disaggregation as instead performing the
function of re-fixing the aggregate itself is to invert the letter‟s own
name and purpose.
40. Fifthly, the LSJ was also right in holding that a unilateral
communication cannot vary a bilaterally agreed ceiling. It is
elementary that a written contract, once concluded, can be varied only
by the process the contract itself prescribes, or by the mutual
agreement of both parties and not by the unilateral act of one
contracting party purporting to notify a different figure to the other
contracting party. However, the Tribunal‟s approach effectively
permitted exactly this, it allowed a communication emanating solely
from the Appellant to operate as an amendment of a heavily
negotiated, capped definition from Rs. 650 crore (adjusted) to Rs.
1,045.55 crore. In this regard, it is to be noted that no principle of
contractual interpretation permits a party to unilaterally enlarge an
obligation which the other party undertook subject to a defined
ceiling.
41. Sixthly, the LSJ was right to say that the ceiling of Rs. 650
crore was based on the Respondent‟s estimated project cost at the RFP
stage and was intended to define the outer limit of its contingent
liability upon termination. To hold as the Tribunal did, that this ceiling
could be displaced merely because the Appellant subsequently
notified a higher actual cost would effectively shift the risk of cost
overruns and additional borrowing to the Respondent, without any
provision in the Agreement permitting such a reallocation.
FAO(OS)(COMM) 211/2026 Page 30 of 39
42. Seventhly, the reliance so placed on the Independent Engineer‟s
acceptance of the Disaggregation Letter also did not assist the
Tribunal‟s conclusion. This Court agrees that the Tribunal‟s treatment
of the Independent Engineer‟s recommendation as though it were a
determination of quantum does not do justice to both the language and
object of the contract, as the LSJ correctly held. Additionally, the
approval of the Financial Package also does not assist the Appellant,
and the LSJ rightly observed that, sub-clause (a) of the TPC definition
itself refers to the capital cost of the Project, as set forth in the
Financial Package, and the parties were fully alive to the fact that the
Financial Package would reflect a capital cost possibly exceeding Rs.
650 crore. As such, this figure stands internalised within the definition
itself under limb (a) and cannot render limb (c) otiose. This Court
finds no reason to disturb this reasoning and adopts it as its own.
Examination of contentions raised by the Appellant:
43. Learned counsel representing the Appellant has contended that
the debt and equity were raised with the approval of the Respondent,
following further scrutiny and acceptance of the Financial Package.
This contention, insofar as it rests on the proposition that such
approval assists the Appellant in enlarging the TPC, already stands
answered by this Court at paragraph no.42 above, where, adopting the
reasoning of the LSJ at paragraph no.58 of the Impugned Judgment, it
has been held that the Financial Package figure stands internalised
within limb (a) of the TPC definition and cannot render limb (c)
otiose. This Court sees no reason to re-examine that finding here and
confines the present discussion to the further and independent points
that arise from this contention.
FAO(OS)(COMM) 211/2026 Page 31 of 39
44. Independent of the observation made by the LSJ, we must
highlight that the consensual character of the Agreement precludes
any subsequent unilateral enlargement of the TPC; absent an express
contractual mechanism, mere review of the Financial Package cannot
be relied upon to enlarge the Respondent‟s liability.
45. While it is true that the Financial Package, reflecting a capital
cost of Rs. 992.58 crore was scrutinised and approved by the
Respondent prior to financial close. But this circumstance, far from
assisting the Appellant, only reinforces the correctness of the LSJ‟s
view. Had the parties intended, including at the stage of such
approval, that this higher, approved figure would operate as the TPC
for the purposes of Termination Payment, superseding the Rs. 650
crore ceiling, nothing prevented them from recording an express
amendment or addendum to the Agreement to that effect.
46. Indeed, Articles 5.2.2 and 5.2.3 of the Agreement required
drafts of the Financing Agreements and the Financial Package to be
submitted to the Respondent in advance, and provided that no change
or amendment thereto could be made without Respondent‟s written
consent. If the Appellant wished the reviewed and approved Financial
Package figure to serve as the operative TPC for termination purposes,
displacing or enhancing the Rs. 650 crore ceiling, it was open to it to
have this incorporated as an express stipulation or amendment to the
Agreement at that stage.
47. However, in the absence of any such contractually recorded
enhancement, the Agreement, having been entered into with the free
consent of both parties with full knowledge of the definitional cap,
FAO(OS)(COMM) 211/2026 Page 32 of 39
must be given effect to strictly as it stands; neither party can be
permitted to read into it, after the fact, a term enlarging its own
entitlement merely because a subsequent document, either the
Financial Package or the Disaggregation Letter, reflected a higher
figure.
48. It is a long-settled principle that where the terms of a contract
are unambiguous, effect must be given to them as they stand, and
neither a court nor a tribunal can substitute a different arrangement
merely because it may appear more fair or convenient. The Supreme
Court has repeatedly, by way its judgments in General Assurance
Society Ltd. v. Chandumull Jain
25
, and Nabha Power Ltd. v. Punjab
State Power Corporation Ltd.
26
, held that the commercial hardship or
subsequent convenience of a party cannot justify departing from the
terms expressly agreed between the parties.
49. Applying this principle, the subsequent review or approval of
the Financial Package by Respondent, in the absence of any
amendment to the Agreement enhancing the Rs. 650 crore ceiling
could not by itself alter the contractual TPC or enlarge the
Termination Payment. To hold otherwise would permit the Appellant
to unilaterally alter the agreed allocation of risk after the event. The
dispute before the Arbitral Tribunal was one concerning the
interpretation and application of the Agreement as executed, and not
an occasion to modify its terms or substitute a different bargain. Such
an interpretation would defeat the very purpose of reducing the
parties‟ bargain into a written and negotiated contract.
25
AIR 1966 SC 1644
26
(2018) 11 SCC 508
FAO(OS)(COMM) 211/2026 Page 33 of 39
50. The Appellant‟s contentions regarding the alleged conflation of
TPC with Termination Payment, and the characterisation of Article
34.9.2 as a self-contained provision, have already been addressed by
the LSJ in paragraph nos.83 and 84 of the Impugned Judgment and by
this Court at preceeding paragraph nos.30 to 33 above. Hence, there is
no need to revisit the same reasoning.
51. The contention of learned senior counsel representing the
Appellant, wherein heavy reliance was placed upon the expression
„unless repugnant to the context or meaning thereof‟, to argue that the
definition of TPC cannot be imported into Article 34.9.2 of the
Agreement, does not merit acceptance. This argument has also been
addressed by the LSJ under paragraph nos.78 to 82 of the Impugned
Judgment, wherein it was held that the cap provided under Article
48.1, in the context of Termination Payment, does not depict absurdity
or contradiction.
52. This Court finds the reasoning provided by the LSJ sound in
every particular. The relevant paragraphs of K.V. Muthu (Supra), as
extracted by the LSJ, make it clear that a „context otherwise requires‟
clause does not license departure from a defined term merely because
an alternative construction is available; rather it permits departure
only where the defined meaning cannot be applied at all to the
provision in question without producing an absurdity or contradiction,
which is a considerably higher threshold than mere inconvenience or a
less favourable financial outcome for one party.
53. The argument of the Appellant when analysed properly, does
not demonstrate that the TPC definition cannot be applied to Article
FAO(OS)(COMM) 211/2026 Page 34 of 39
34.9.2 of the Agreement; it only demonstrates that applying it yields a
smaller recovery than the Appellant would prefer, and this is precisely
the species of argument, paragraph no.79 of the Impugned Judgment
rejects.
54. Since the correctness of the LSJ‟s reliance on K.V. Muthu
(Supra) has been specifically assailed by learned senior counsel, it
deserves pointed examination. The decision does not permit a free
departure from a defined term merely because the contractual context
is perceived to be in tension with the defined meaning; rather, it
establishes a rule of restrained displacement, under which the
definition remains the governing rule, and the expression “unless the
context otherwise requires” operates only as an exception where
giving effect to the definition would defeat the object or purpose of
the instrument.
55. Measured against this standard, the LSJ was correct in holding
that the exception has no application in the present case. A definition
which expressly contemplates the termination scenario and prescribes
a specific mechanism for its adjustment in that eventuality cannot, in
the same breath, be rendered inapplicable merely because the context
is one of termination.
56. In respect to contention of the Appellant covered under
paragraph nos.9.8 and 9.9, it may be noted that the ceiling of Rs. 650
crore, traceable to the Respondent‟s estimated project cost at the RFP
stage, was intended to define the outer limit of its contingent liability
upon termination. It could not be displaced merely because the
Appellant subsequently notified a higher actual cost, as already stands
FAO(OS)(COMM) 211/2026 Page 35 of 39
examined and accepted by this Court at paragraph no.41 above. To
permit such displacement would effectively shift the risk of cost
overruns to the Respondent without contractual sanction. What
remains for independent examination is the further and more specific
submission that Article 1.4.1 of the RFP itself disclaims any intention
that the estimate survive as a binding cap, a submission which,
although not argued in these precise terms before the LSJ, must
nevertheless be addressed.
57. In the considered view of this Court, this further submission
does not alter the outcome already reached by the LSJ. Whatever the
RFP‟s own terms may say about the provisional character of the
estimate for purposes of the bidding process, that estimate ceased to
be a mere pre-contractual approximation the moment it was
consciously carried forward and written into the operative definition
clause of the executed Agreement, as one limb of the three-limbed
„lowest of‟ formula under Article 48.1 of the Agreement.
58. In any event, the RFP is a pre-contractual document, and the
LSJ, under paragraph no.58 of the Impugned Judgment, has already
noted, in the context of rejecting reliance on the approved Financial
Package, that „in terms of Article 1.4.1 of the Concession Agreement,
the Agreement prevails over all other documents‟. It necessarily
follows that whatever qualification Article 1.4.1 of the RFP may
purport to place on the continued applicability of the RFP‟s estimates,
it cannot override or dilute a term that the parties, with full knowledge
of such estimate's provenance, chose to incorporate as a binding limb
of the definition in the concluded Agreement itself.
FAO(OS)(COMM) 211/2026 Page 36 of 39
59. The Appellant‟s submission under paragraph no.9.10 was not
urged before the LSJ, and consequently, has also not been dealt with
thereof. However, even upon an independent examination of the said
argument and the reliance placed on Nabha Power (Supra) and Haris
Marine Products (Supra), this Court finds it to be misconceived.
60. The business-common-sense canon of construction, as
explained in Nabha Power (Supra), is a tool for resolving genuine
ambiguity or for declining to imply a term into a contract‟s silence. It
authorises a Court to prefer the construction that avoids commercial
absurdity only where the contractual language itself admits of more
than one meaning. Even then, the implication of any additional term
must satisfy the strict test of business necessity, not the lesser test of
mere reasonableness or convenience to one party.
61. Similarly, Haris Marine Products (Supra), stands on no
different footing, it also addresses the construction of doubtful or
silent contractual language, not the displacement of an express,
unambiguous limitation because one party finds its consequences
commercially not viable. Moreover, the underlying premise of the
Appellant‟s argument itself is not sound. The risk that the Appellant‟s
actual project debt might, at completion, exceed the ceiling negotiated
at the RFP and definitional stage was a risk that the Respondent and
its lenders assumed when they structured the financing of the project.
It was not a risk the Respondent undertook to absorb, and nothing in
the Agreement suggests otherwise.
62. The consequence of enforcing the cap may leave certain lenders
less than fully satisfied out of the Termination Payment is a
FAO(OS)(COMM) 211/2026 Page 37 of 39
consequence of the parties‟ own bargain, not an absurdity of the kind
that permits a court or tribunal to depart from the plain words of that
bargain. Accordingly, the Court finds no substance in the reliance
placed on Nabha Power (Supra) and Haris Marine Products (Supra),
and, if anything, this Court finds that the reasoning in Nabha Power
(Supra), if properly understood, operates against, rather than in favour
of, the Appellant‟s case.
Tribunal’s construction of the Agreement was not a possible view
63. Having examined the findings of the LSJ and the contentions of
the Appellant, it remains to determine, in the context of patent
illegality, why the Tribunal‟s interpretation falls outside the
permissible limits of contractual interpretation, despite the broad
latitude ordinarily available to an arbitral tribunal in interpreting a
contract.
64. In the present case, as discussed under paragraph nos. 30 to 62
of this judgment, the Tribunal‟s construction could not be sustained
merely as an alternative interpretation of the Agreement. An arbitral
tribunal is entitled to construe contractual provisions and to adopt a
plausible interpretation where the language admits of more than one
meaning. It cannot, however, give a provision a meaning which is
inconsistent with an express limitation elsewhere in the Agreement, or
confer upon a subsequent notification a contractual effect which the
Agreement does not provide.
65. The contractual scheme, read as a whole, does not permit the
TPC to be enlarged through the Disaggregation Letter or the
subsequently approved Financial Package so as to displace the agreed
FAO(OS)(COMM) 211/2026 Page 38 of 39
ceiling. In treating the Disaggregation Letter as capable of enhancing
the TPC notwithstanding the Rs. 650 crore ceiling, the Tribunal failed
to give effect to an express contractual limitation and thereby enlarged
the Respondent‟s liability without any contractual mechanism
authorising such variation.
66. Such an interpretation cannot be reconciled with the contractual
scheme as a whole and, in effect, substitutes a different allocation of
risk for that which the parties had agreed. It therefore travels beyond a
mere disagreement on interpretation and amounts to altering, rather
than interpreting, the contractual arrangement between the parties.
67. Therefore, this Court is unable to accept that the Tribunal‟s
construction can be characterised as a possible view merely because
an arbitral tribunal ordinarily enjoys latitude in interpreting a contract.
The Tribunal‟s construction consequently falls outside the permissible
limits of contractual interpretation and attracts the ground of patent
illegality as exercised by the LSJ.
68. Before parting, we must appreciate the clarity, depth and
analytical rigour with which the LSJ has dealt with the intricate
questions of contractual construction arising in the present case. The
Impugned Judgment reflects a careful and nuanced examination of the
contractual framework, the relevant provisions and the competing
interpretations advanced by the parties and demonstrates a faithful
application of settled principles governing the interpretation of
commercial contracts.
FAO(OS)(COMM) 211/2026 Page 39 of 39
D. CONCLUSION:
69. For the reasons set out above, this Court finds no error in the
learned Single Judge‟s decision to set aside the Arbitral Award insofar
as Claim Nos. 1 and 2 are concerned. The learned Single Judge
remained within the limited scope of Section 34 and correctly found
that the Tribunal‟s construction amounted to rewriting the Concession
Agreement, rather than a permissible interpretation of its terms,
thereby attracting the ground of patent illegality.
70. The learned Single Judge was also correct in reading the TPC
definition and the Termination Payment clause harmoniously, as
complementary provisions forming part of the same contractual
scheme. This Court, while exercising jurisdiction under Section 37,
has confined its examination to the legality of the exercise undertaken
under Section 34 and has not re-appreciated the merits of the dispute.
71. Therefore, no ground for interference under Section 37(1)(c) of
the Act of 1996 is made out.
72. Accordingly, the Impugned Judgment insofar as it sets aside the
Arbitral Award on Claim Nos.1 and 2, is affirmed, and the present
Appeal, stands dismissed.
73. Pending applications stands disposed of.
ANIL KSHETARPAL , J.
SHAIL JAIN, J.
SEPTEMBER 28, 2026
jai/hr
Legal Notes
Add a Note....