specific performance, contract enforcement, property law, Supreme Court India
0  12 Aug, 1999
Listen in 00:55 mins | Read in 13:00 mins
EN
HI

Lata Construction and Ors. Vs. Dr. Rameshchandra Ramniklal Shah and Anr.

  Supreme Court Of India Civil Appeal /2418/1996
Link copied!

Case Background

As per case facts, the respondents filed a complaint against the appellants, developers, for failing to provide a flat as agreed in 1987, despite receiving significant payments. Later, a second ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4

PETITIONER:

LATA CONSTRUCTION & ORS.

Vs.

RESPONDENT:

DR. RAMESHCHANDRA RAMNIKLAL SHAH AND ANR.

DATE OF JUDGMENT: 12/08/1999

BENCH:

S.Saghir Ahmad , R.P.Sethi

JUDGMENT:

S. SAGHIR AHMAD, J.

This appeal is directed against the judgment and order

dated 22nd November, 1995 passed by the National Consumer

Disputes Redressal Commission, New Delhi (for short, 'the

National Commission').

The respondents had approached the Commission with the

complaint that the appellants who were developers and had

promised, under a written agreement dated 27.1.1987, to

provide a flat to them, had failed to do so and, therefore,

they were guilty of "deficiency in service." It was

indicated in the complaint that the respondents who were, at

that time, in Libya and wanted to settle in India, had

entered into an agreement dated 27.1.1987 with M/s. Lata

Construction, the appellant No.1, which stipulated that the

appellants would develop, construct and hand over possession

of flat No. AG-2 on the ground floor with an area of 670

sq. ft. situated in a building named "Madhusudan", on Plot

No. 138, T.P.S. 11 and C.T.S. No.1166 and 1166(1) in Vile

Parle, Bombay 400057. It was indicated that the appellants

had earlier entered into a development agreement on

9.12.1985 with the owners in respect of the said property to

develop, construct and to sell flats in the proposed

building which was to be constructed on ownership basis. On

27th of January, 1987, the respondents had paid a sum of

Rs.3,38,000/- to the appellants in cash but without any

receipt and a sum of Rs.32,000/- by cheque against receipt.

The respondents also paid to the appellants on various

dates, as and when demanded by them, a further sum of Rs.

2,00,000/- against receipt. In June, 1988 when the

respondents returned from Libya, they requested the

appellants to deliver, on payment of balance amount of sale

consideration, possession of the flat to them as the

construction of the building was complete but the appellants

refused to accept the payment and deliver possession on the

plea that the building was still under construction

particularly as the electricity, plumbing, tiling and

fencing work was in progress. The appellants, however,

assured the respondents that as and when the building would

be completed in all respects, they would accept the balance

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4

amount of sale consideration and deliver possession to them.

In April, 1990, when the respondents again came back from

Libya on a short visit to India and visited the building,

they found that the flat was locked and outside the main

door of the flat, a name plate of "Indira Joshi" had been

put up. The respondents returned from Libya in January,

1991 and when they demanded the possession of the flat, the

appellants expressed their inability to give possession of

the flat to the respondents in compliance of the agreeement

dated 27.1.1987. The appellants, however, entered into a

fresh agreement with the respondents on 23.2.1991 agreeing

to pay to the respondents a sum of Rs. 9,51,000/- in lieu

of the flat in three instalments on or before 30.5.1991 as

under:-

1. Rs. 3,00,000/- - on or before 20.3.1991 2. Rs.

3,00,000/- - on or before 20.4.1991 3. Rs. 3,51,000/- - on

or before 30.5.1991

The respondents had entered into a fresh agreement

with the appellants without prejudice to their rights under

the earlier agreement dated 27.1.1987. Since the appellants

did not honour the commitments under both the agreements,

the respondents approached the National Commission which,

decreed the claim of the respondents for a sum of

Rs.9,51,000/- together with interest at the rate of 18% per

annum with effect from 23.2.1991 till the date of payment.

Another sum of Rs. 1,00,000/- was allowed as compensation

for pain and suffering undergone by the respondents. The

Commission also allowed a sum of Rs. 10,000/- to the

respondents as costs of the proceedings.

Learned counsel appearing on behalf of the appellants

has contended that the claim instituted by the respondents

before the Commission was beyond time inasmuch as it was

filed beyond the period of two years prescribed under

Section 24-A of the Consumer Protection Act, 1986 (for

short, 'the Act'). It is contended that since the

respondents had entered into a fresh agreement with the

appellants under which the entire amount of Rs. 9,51,000/-

had to be paid on or before 30th of May, 1991, the

respondents, if the amount was not paid, could have

instituted the claim petition before the Commission within

the period of limitation starting from 31.5.1991, and since

the claim was filed in July, 1993, it was clearly beyond

time. This plea has been negatived by the Commission on the

ground that since the right under the agreement of 1987 had

not been given up by the respondents, there was a continuing

cause of action running against the appellants and the claim

was, therefore, not beyond time.

A perusal of the agreement dated 23rd of February,

1991 would show that it was specifically stipulated therein

that the rights under the agreement dated 27th of January,

1987 would remain uneffected. It was for this reason that

in the claim petition filed before the Commission, it was

clearly mentioned that their rights under the agreement

dated 27th of January, 1987 as also those under the

agreement dated 23rd of February, 1991 may be enforced. It

was also specifically mentioned in the second agreement that

the first agreement of 1987 would be treated as terminated

only on full payment of the stipulated amount of

Rs.9,51,000/- to the respondents. Since the rights under

the agreement of 1987 had not been given up and the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4

appellants were constantly under an obligation to provide a

flat to the respondents and deliver possession thereof to

them, the Commission rightly treated "cause of action" to be

a "continuing cause of action" and came to the right

conclusion that the claim was not beyond time.

Moreover, under the terms of the agreement dated 23rd

of February, 1991, it was stipulated that if the entire

amount of Rs.9,51,000/- was not paid by 30th May, 1991, the

whole of the amount would become payable at once and it

would be open to the respondents to claim payment of full

amount together with interest after giving seven days'

notice to the appellants. It was further stipulated that in

case of default, the amount already paid by the appellants

shall stand forfeited. Since the whole of the amount had

not been paid to the respondents who could recover the whole

of the amount together with interest from the appellant on

giving seven days' notice, the rights under the old

agreement did not come to an end and they could legally

claim specific performance of that agreement for a flat

being provided to them. Their claim was, therefore, not

barred by time.

It was next contended that the agreement dated

27.1.1987 having been substituted by a fresh agreement dated

23.2.1991, under which the respondents themselves had agreed

to receive Rs.9,51,000/- as compensation for the flat not

having been provided to them under the earlier agreement,

they could only approach the civil court for recovery of

that amount but could not legally institute the claim

petition before the Commission for compensation on the

ground of "deficiency in service."

This plea has been rejected by the National Commission

by placing reliance upon the decision of this Court in

Lucknow Development Authority v. M.M. Gupta (1994) 1 SCC

243.

We have already held above that the rights under the

earlier agreement of 1987 were kept alive even after the

second agreement. The rights under the first agreement had

not been given up and there was no substitution of the

earlier agreement in its entirety by the new agreement.

We may, at this stage, refer to the provisions of

Section 62 of the Indian Contract Act which provides as

under :

"If the parties to a contract agree to substitute a

new contract for it, or to rescind or alter it, the original

contract need not be performed." This provision contains the

principle of "Novation" of contract.

One of the essential requirements of `Novation'; as

contemplated by Section 62, is that there should be complete

substitution of a new contract in place of the old. It is

in that situation that the original contract need not be

performed. Substitution of a new contract in place of the

old contract which would have the effect of rescinding or

completely altering the terms of the original contract, has

to be by agreement between the parties. A substituted

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4

contract should rescind or alter or extinguish the previous

contract. But if the terms of the two contracts are

inconsistent and they cannot stand together, the subsequent

contract cannot be said to be in substitution of the earlier

contract.

In the instant case, the rights under the original

contract were not given up as it was specifically provided

in the subsequent contract that the rights under the old

contract shall stand extinguished only on payment of the

entire amount of Rs.9,51,000/-. Since the amount was not

paid by the appellants as stipulated by the subsequent

contract, the rights under the original contract were still

available to the respondents and he could legally claim

enforcement of those rights. Obviously, under the original

contract, the appellants were under an obligation to provide

a flat to the respondents. This right would come to an end

only when the appellants had, in pursuance of the subsequent

contract, paid the entire amount of Rs.9,51,000/- to the

respondents. Since they had not done so, the respondents

could legally invoke the provisions of the earlier contract

and claim before the Commission that there was "deficiency

in service" on the part of the appellants.

We may also point out that the appellants had filed

only a written statement before the Commission but had not

produced any evidence in support of their pleas. Even an

affidavit in support of what they had stated in the written

statement was not filed before the Commission. Their case,

thus was not supported by any evidence and the Commission,

in the facts and circumstances of the case, was justified in

decreeing the claim of the respondents.

Learned counsel for the parties have stated before us

that in terms of the judgment passed by the Commission, the

entire amount due from the appellants has already been paid

to the respondents including interest at the rate of 18 per

cent per annum on the principal amount of Rs.9,51,000/-.

That being so, we are not prepared to entertain the plea of

the appellants that the decree passed by the Commission in

respect of Rs.1 lakh as compensation on account of the pain

and suffering undergone by the respondents may be reversed.

We find no merit in the appeal and the same is

accordingly dismissed with no order as to costs.

Reference cases

Description

Introduction to the Landmark Judgment

The Supreme Court of India's ruling in Lata Construction & Ors. v. Dr. Rameshchandra Ramniklal Shah and Anr., delivered on August 12, 1999, stands as a significant precedent concerning the **Consumer Protection Act** and the intricate principles of **Novation of Contract**. This pivotal judgment, which continues to be a crucial reference point for legal analysis, is thoroughly documented and readily available on CaseOn.in.

The Factual Matrix: A Developer's Promise and Persistent Delays

The case originated from a complaint filed by Dr. Rameshchandra Ramniklal Shah and his associate (the respondents) against Lata Construction & Ors. (the appellants), who were property developers.

Initial Agreement and Payments

In January 1987, the respondents, who were residing in Libya and planned to settle in India, entered into a written agreement with Lata Construction. The agreement stipulated that the appellants would develop, construct, and deliver possession of a 670 sq. ft. flat (No. AG-2) in a building named "Madhusudan" in Vile Parle, Bombay. The respondents made substantial payments totaling Rs. 3,38,000/- in cash (without receipt) and Rs. 32,000/- by cheque (against receipt). Subsequently, they paid an additional Rs. 2,00,000/- on various dates as demanded.

The First Breach and Failed Delivery

By June 1988, upon their return from Libya, the respondents found the construction incomplete, with essential works like electricity, plumbing, tiling, and fencing still pending. Despite the building appearing largely complete, the appellants refused to deliver possession, citing ongoing work. In April 1990, the respondents again visited India and found the flat locked with a different nameplate. When they returned in January 1991 and demanded possession, the appellants expressed their inability to comply with the 1987 agreement.

A Second Attempt: Monetary Compensation

Following this, in February 1991, a fresh agreement was signed. Under this new arrangement, the appellants agreed to pay the respondents a sum of Rs. 9,51,000/- in three installments by May 30, 1991, in lieu of the promised flat. Crucially, this agreement explicitly stated that the respondents' rights under the initial January 1987 agreement would remain unaffected. It further specified that the 1987 agreement would only be treated as terminated upon the full payment of the Rs. 9,51,000/-.

Consumer Redressal Sought

The appellants, however, failed to honor the commitments made in both agreements. Consequently, the respondents approached the National Consumer Disputes Redressal Commission (National Commission), alleging "deficiency in service." The National Commission decreed that the appellants pay Rs. 9,51,000/- with 18% interest from February 1991, plus Rs. 1,00,000/- as compensation for pain and suffering, and Rs. 10,000/- as costs. The appellants subsequently appealed this decision to the Supreme Court.

Issue Presented Before the Supreme Court

The primary issues for consideration before the Supreme Court were twofold:

  • Was the consumer complaint, filed in July 1993, time-barred under Section 24-A of the Consumer Protection Act, 1986, given that the last payment was due by May 1991 under the second agreement?
  • Had the initial agreement of January 1987 been completely substituted by the subsequent agreement of February 1991, thereby precluding a claim for "deficiency in service" under consumer law and relegating the respondents to a civil suit for monetary recovery?

Legal Principles Applied

To resolve these issues, the Supreme Court relied on fundamental principles of consumer protection and contract law.

The Consumer Protection Act, 1986 - Section 24-A (Limitation)

Section 24-A of the Consumer Protection Act stipulates that a consumer complaint must be filed within two years from the date on which the cause of action arises. The appellants argued that the cause of action arose by May 31, 1991, making the July 1993 complaint time-barred.

Concept of "Continuing Cause of Action"

This doctrine allows for the extension of the limitation period when the wrong or non-compliance is ongoing. The National Commission had relied on this principle, stating that the appellants' failure to fulfill the original agreement created a continuing obligation.

Novation of Contract - Section 62 of the Indian Contract Act, 1872

Section 62 of the Indian Contract Act deals with novation, stating: "If the parties to a contract agree to substitute a new contract for it, or to rescind or alter it, the original contract need not be performed." Novation essentially means replacing an existing contract with a new one, thereby extinguishing the old obligations. A crucial aspect is whether the new contract *completely* replaces the old one, or merely supplements it.

For legal professionals seeking a rapid understanding of such complex rulings, CaseOn.in offers concise 2-minute audio briefs, enabling quick analysis of key legal arguments and judicial interpretations without extensive reading.

Supreme Court's Analysis and Rationale

The Supreme Court meticulously examined the arguments presented by both parties, aligning with the National Commission's findings.

Addressing the Limitation Argument

The Court upheld the National Commission's view regarding a "continuing cause of action." It highlighted the specific clause in the second agreement (February 1991) which unequivocally stated that the rights under the initial January 1987 agreement would remain "unaffected." These original rights were only to be terminated upon the full payment of Rs. 9,51,000/-. Since the appellants failed to make this full payment, their obligation to provide the flat under the 1987 agreement persisted. Consequently, the cause of action for "deficiency in service" continued, and the complaint was deemed not time-barred.

Scrutinizing the Novation Claim

The appellants contended that the second agreement constituted a complete novation, substituting the first. The Supreme Court, referencing Section 62 of the Indian Contract Act, clarified that for novation to occur, there must be a complete substitution, rescission, or alteration of the original contract. It emphasized that if the terms of two contracts are inconsistent and cannot stand together, the subsequent contract may be a substitution. However, in this case, the second agreement *expressly preserved* the rights of the first agreement until a specific condition (full payment) was met. As this condition was not fulfilled, the rights under the original contract were not extinguished. Therefore, the second agreement did not amount to a complete novation, and the respondents retained their right to pursue a claim under the first agreement for "deficiency in service."

The Importance of Contractual Clauses

This case underscored the critical importance of carefully drafted contractual clauses. The explicit preservation of rights from the first agreement within the second proved decisive in determining both the limitation period and the applicability of the novation principle.

Lack of Evidence from Appellants

The Supreme Court also noted that the appellants had failed to produce any evidence, beyond their written statement, to support their claims before the National Commission. This lack of substantiation further weakened their appeal.

Conclusion of the Supreme Court

In light of its analysis, the Supreme Court found no merit in the appeal. It affirmed the judgment and order of the National Consumer Disputes Redressal Commission, dismissing the appeal. The Court noted that the entire amount decreed by the Commission, including interest at 18% per annum on the principal sum of Rs. 9,51,000/-, had already been paid by the appellants. It specifically upheld the additional Rs. 1,00,000/- awarded as compensation for the pain and suffering endured by the respondents.

Why This Judgment Matters for Legal Professionals and Students

This Supreme Court judgment offers invaluable insights for anyone navigating property disputes, consumer protection, and contract law:

  • Consumer Protection Reinforcement: It strongly reinforces consumer rights against developers for contractual breaches and delays in property delivery, reaffirming the broad scope of "deficiency in service" under the Consumer Protection Act.
  • Clarity on Limitation Periods: The ruling provides critical guidance on the "continuing cause of action" doctrine, particularly in cases where contractual obligations remain unfulfilled over time, ensuring consumers are not unfairly barred by technicalities of limitation.
  • Nuances of Contractual Novation: It offers a detailed exposition on Section 62 of the Indian Contract Act, distinguishing between a complete novation (where an old contract is extinguished) and a supplementary agreement. This is crucial for understanding how subsequent agreements interact with preceding ones.
  • Importance of Drafting: The case highlights the paramount importance of precise and unambiguous contractual language, especially clauses pertaining to the preservation or extinguishment of prior rights, which can significantly impact legal outcomes.
  • Evidentiary Requirements: It serves as a reminder to all parties, particularly in consumer forums, to substantiate their claims with concrete evidence, as mere assertions may not suffice.

Disclaimer

All information provided in this analysis is for informational purposes only and does not constitute legal advice. While efforts have been made to ensure accuracy, readers are advised to consult with a qualified legal professional for advice on specific legal issues and before making any legal decisions.

Legal Notes

Add a Note....