Delhi High Court, Mahajan Imaging, PSRI Hospital, Section 9 Arbitration Act, Interim Injunction, Termination Notice Stay, Determinable Contract, Specific Relief Act, Irreparable Injury, Diagnostic Services Agreement, Justice Harish Vaidyanathan Shankar.
 26 Feb, 2026
Listen in 01:03 mins | Read in 15:00 mins
EN
HI

Mahajan Imaging Pvt Ltd Vs. Pushpawati Singhania Research Institute & Anr.

  Delhi High Court O.M.P.(I) (COMM.) 29/2026
Link copied!

Case Background

As per case facts, the Petitioner and Respondent No.1 had a Radiology Services Agreement for fifteen years, which had a substantial unexpired tenure. Respondent No.1 issued a Termination Notice alleging ...

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

O.M.P.(I) (COMM.) 29/2026 Page 1 of 42

$~

* IN THE HIGH COURT OF DELHI AT NEW DELHI

Judgment reserved on: 12.02.2026

Judgment pronounced on: 26.02.2026

+ O.M.P.(I) (COMM.) 29/2026 & I.A. 1983/2026 (Permission to

File a Lengthy Synopsis and List of Dates)

MAHAJAN IMAGING PVT LTD .....Petitioner

Through: Mr. Sandeep Sethi, Senior

Advocates along with Mr.

Varun Shankar, Ms. Ishita

Dahiya, Mr. Harsh Rastogi, Mr.

Ujjwal Barwal, Mr. Krishna

Gambhir, Mr. Naman

Maheshwari, Ms. Shreya Sethi

and Ms. Riya Kumar,

Advocates.

versus

PUSHPAWATI SINGHANIA RESEARCH INSTITUTE &

ANR. .....Respondents

Through: Mr. Rajeev K. Virmani, Senior

Advocate with Ms. Ritu Bhalla,

Mr. Siddhartha Das, Mr.

Himanshu Goel, Mr. Siddharth

Gautam, Ms. Shriya Gambhir

and Ms. Diva Saigal,

Advocates.

CORAM:

HON'BLE MR. JUSTICE HARISH VAIDYANATHAN

SHANKAR

JUDGMENT

HARISH VAIDYANATHAN SHANKAR, J.

1. The present petition has been filed under Section 9 of the

O.M.P.(I) (COMM.) 29/2026 Page 2 of 42

Arbitration and Conciliation Act, 1996

1

, seeking the following

reliefs:

“…..

A. Grant an ad-interim injunction on the operation and effect of

the Termination Notice dated 02.01.2026 issued by the

Respondents, and restrain the Respondents from giving effect

to the same or terminating the Radiology Services Agreement

dated 02.05.2016 (as amended) in any manner pending final

adjudication of the disputes through arbitration;

B. Direct the parties to maintain status quo with respect to the

operation, management, and functioning of the Radiology

Department at the Respondent No. 1 Hospital under the

Agreement, including uninterrupted access and services by the

Petitioner;

C. Grant a prohibitory ad-interim injunction restraining the

Respondents, their agents, assigns, or any persons claiming

through them, from creating any third-party rights or interests

in the Radiology Department, premises, equipment, or services

covered under the Agreement;

D. Grant a prohibitory ad-interim injunction restraining the

Respondents from installing any radiology equipment, or

rendering such services within the premises covered under the

Agreement;

E. Direct the Respondents to make the payments to the Petitioner

as per the timeline agreed in the Agreement in a transparent

and timely manner.

F. Restrain the Respondents from transferring, removing,

alienating, or otherwise dealing with any machinery,

equipment, or assets installed and operated by the Petitioner in

the Radiology Department at the Respondent No. 1 Hospital.

G. Grant any other order(s) that this Hon’ble Court deems fit and

proper.”

BRIEF FACTS:

2. The Petitioner is a company duly incorporated in India under

the Companies Act, 1956, having its registered office at K-18 Hauz

Khas Enclave, New Delhi, India. Respondent No. 1 is a company

engaged in the healthcare sector, having its registered office at 3,

Bahadur Shah Zafar Marg, Link House, New Delhi. Respondent No. 2

1

A&C Act

O.M.P.(I) (COMM.) 29/2026 Page 3 of 42

is the Chief Executive Officer of Respondent No.1.

3. On 02.05.2016, the Petitioner and Respondent No.1 executed a

Radiology Services Agreement

2

for a period of fifteen (15) years,

whereunder the Petitioner was entrusted with the responsibility of

establishing, managing and operating the Radiology Department at the

hospital premises of Respondent No.1 and was required, inter alia, to

render radiology services in a competent and uninterrupted manner in

compliance with applicable laws, to ensure that the equipment

installed met the prescribed standards, and to obtain and maintain the

requisite statutory permits and licences.

4. The Agreement was to remain in force until 02.05.2031, subject

to termination in accordance with Clause 10 thereof. Clause 10

provides for termination in specified contingencies, including

termination on account of a material breach, subject to issuance of

written notice and the grant of a cure period of forty-five (45) days.

Clause 13 of the Agreement contains the dispute resolution

mechanism, requiring the parties to first attempt resolution through

mutual discussions and, failing such resolution, to refer the disputes to

arbitration.

5. It is stated that after such an arrangement had been continuing

for several years, a meeting was convened between the representatives

of the parties. In the course of the said meeting, Respondent No.1

conveyed its intention to commence and operate the Radiology

Department independently with effect from 01.04.2026.

6. Thereafter, in December 2025, communications were

exchanged between the parties concerning various items of

2

Agreement

O.M.P.(I) (COMM.) 29/2026 Page 4 of 42

radiological equipment installed in the Radiology Department,

including matters relating to commissioning and de-commissioning of

equipment, servicing and maintenance, and compliance with the

provisions of the Pre-Conception and Pre-Natal Diagnostic

Techniques (Prohibition of Sex Selection) Act, 1994

3

and the

regulatory framework under the Atomic Energy Act, 1962

4

.

7. Pursuant to this, on 02.01.2026, Respondent No.1 issued a

Termination Notice

5

alleging breaches of contractual and statutory

obligations and stating that the Agreement would stand terminated

with effect from 02.02.2026.

8. The Petitioner, vide its reply dated 08.01.2026 to the Impugned

Termination Notice, disputed the validity of said Notice, contending

that the Agreement was binding for a fixed tenure of fifteen years and

could be terminated only in the event of a contractual breach or by

mutual consent of the parties, neither of which had arisen.

9. Alleging violations of contractual obligations under the

abovementioned Agreement, the Petitioner has approached this Court

by way of the present petition seeking urgent interim measures,

including ad-interim injunctions restraining the operation and effect of

the Impugned Termination Notice, maintenance of status quo with

respect to the Radiology Department, and a prohibitory ad-interim

injunction restraining the Respondents from creating any third-party

rights or installing any radiology equipment at the Hospital.

CONTENTIONS ON BEHALF OF THE PARTIES:

10. Mr. Rajeev K. Virmani, learned Senior Counsel appearing on

3

PC-PNDT Act

4

Atomic Energy Act

5

Impugned Termination Notice

O.M.P.(I) (COMM.) 29/2026 Page 5 of 42

behalf of the Respondents, would contend that the prayers sought in

the present petition are statutorily barred in view of Section 14(d) of

the Specific Relief Act, 1963

6

, as it states that a contract which is in

its nature determinable cannot be specifically enforced. It would be

submitted that Clause 10 of the Agreement renders the Agreement as

one that is determinable in nature.

11. Learned Senior Counsel for the Respondents, in furtherance of

the aforesaid submission with regard to the determinable nature of the

Agreement, would place reliance on the judgment of a Co-ordinate

Bench of this Court in National Highways Authority of India v. HK

Toll Road Pvt. Ltd.

7

to contend that a contract which provides for

termination upon the occurrence of specified contingencies would be

regarded as determinable in nature, and once a contract is found to be

determinable, an injunction staying such termination would, in effect,

amount to enforcement or restoration of the contract, which is

impermissible in law.

12. Learned Senior Counsel would further place reliance on the

decisions of the Hon’ble Supreme Court in Indian Oil Corporation

Ltd. v. Amritsar Gas Service

8

and of this Court in Rajasthan

Breweries Ltd. v. Stroh Brewery Co

9

, to submit that where a contract

is determinable, even if the termination is ultimately found to be

illegal, the remedy available to the aggrieved party is to seek

compensation for the wrongful termination and not in specific

performance of the agreement as between the parties. It would

therefore be contended that the present petition, insofar as it seeks to

6

SRA

7

2025 SCC OnLine Del 2376

8

(1991) 1 SCC 533

9

2000 SCC OnLine Del 481

O.M.P.(I) (COMM.) 29/2026 Page 6 of 42

restrain or nullify the termination and thereby continue the

Agreement, is legally untenable.

13. Learned Senior Counsel for the Respondents would further

submit that, in any event, the reliefs sought in the present petition are

also barred under Section 14(b) of the SRA inasmuch as the

Agreement embodies continuing and reciprocal obligations requiring

sustained performance over a period of time. Grant of the reliefs

prayed for would necessarily involve constant judicial supervision of

such performance, which is impermissible in law. A contract

involving continuous duties that the Court cannot supervise is not

specifically enforceable.

14. Learned Senior Counsel would further contend that the present

petition does not disclose the complete and correct factual matrix

leading to the issuance of the Impugned Termination Notice. It would

be submitted that the termination was preceded by and founded upon

multiple and serious breaches on the part of the Petitioner, inter alia,

non-compliance with statutory requirements under the PC-PNDT Act

and the regulatory framework under the Atomic Energy Act, operation

and continued use of equipment which had reached end-of-life and

end-of-support status, failure to obtain or update requisite registrations

and endorsements in respect of installation and transfer of equipment,

engagement of unauthorised service agencies, and disruption of

uninterrupted radiology services owing to the non-functioning of

critical equipment.

15. Learned Senior Counsel would thus contend that these

violations, taken cumulatively, constituted breaches going to the root

of the Agreement and justified the action taken by Respondent No.1.

16. Per contra, Learned Senior Counsel for the Petitioner would

O.M.P.(I) (COMM.) 29/2026 Page 7 of 42

submit that the Respondents’ reliance on Section 14(d) of the SRA is

wholly misconceived. It would be contended that not every contract

containing a termination clause is determinable in nature, and to

bolster this argument, reliance would be placed by the learned Senior

Counsel, on the judgment of the Hon’ble Supreme Court in K.S.

Manjunath and Others v. Moorasavirappa alias Muttanna

Chennappa Batil

10

, particularly paragraphs 62, 64 and 65, wherein the

Apex Court has clarified that the determinability of a contract must be

assessed with reference to its terms and the nature of rights and

obligations flowing therefrom.

17. Learned Senior Counsel for the Petitioner would lay particular

emphasis on paragraph 66 read with paragraphs 47 to 51 of the said

judgment to submit that a contract is “in its nature determinable” only

where it is terminable at the will of a party, without reference to any

breach or contingency. The Agreement in the present case confers no

such unilateral or no-fault right of termination. Termination is

expressly conditioned upon the existence of a material breach and

compliance with the contractual cure mechanism. It would therefore

be contended that, so long as the Petitioner was ready and willing to

perform and no established default existed, the Agreement cannot be

characterised as inherently determinable so as to attract the bar under

Section 14(d) of SRA.

18. Learned Senior Counsel for the Petitioner would further submit

that the Respondents’ reliance on Section 14(b) of the SRA is equally

misplaced. The interim relief sought does not require this Court to

supervise continuous performance or undertake day-to-day monitoring

10

2025 SCC OnLine SC 2378

O.M.P.(I) (COMM.) 29/2026 Page 8 of 42

of reciprocal obligations. The Agreement has operated for nearly nine

years without judicial oversight, and the Petitioner merely seeks

preservation of the existing contractual framework and enforcement of

the negative covenants pending arbitration. Such limited protection

does not attract the statutory bar under Section 14(b) of the SRA.

19. Learned Senior Counsel for the Petitioner would contend that

the reliance placed on alleged “End-of-Life” communications,

temporary downtime of equipment, and supposed irregularities under

the PC-PNDT Act and other legal frameworks are wholly

misconceived, inasmuch as the equipment remained licensed, duly

maintained and compliant, and no adverse order has ever been passed

by any competent authority. The allegations, it would be urged, are

based on internal audit observations and selective reading of

documents, and do not disclose any fundamental violation warranting

termination of a long-term commercial contract.

20. Learned Senior Counsel for the Petitioner would further submit

that the Impugned Termination Notice is ex facie contrary to the

contractual mechanism. Even assuming any breach had occurred, the

Respondents were mandatorily required under Clause 10.2(a) to issue

a notice granting a cure period of forty-five (45) days. No such cure

notice was issued. It would therefore be contended that the termination

is arbitrary and in breach of the express terms of the Agreement.

21. It would further be submitted that once the foundational

requirement of a contractual cure period is disregarded, the

termination cannot be sustained in law, and all consequential steps

flowing therefrom would stand vitiated.

22. It would also be contended that the entire premise of the

Impugned Termination Notice is that the said breaches are incurable

O.M.P.(I) (COMM.) 29/2026 Page 9 of 42

in nature and the same is a unilateral determination without reference

to the contractual framework.

23. Lastly, learned Senior Counsel would submit that the well-

established triple test for the grant of an injunction stands satisfied in

the present case, with particular emphasis on the irreparable injury that

would be caused to the Petitioner in the form of loss of reputation and

erosion of goodwill, which are incapable of being adequately

compensated by damages or monetary relief and, therefore, necessitate

the interference of this Court by way of injunctive protection.

ANALYSIS:

24. This Court has heard the learned Senior Counsel appearing on

behalf of the parties and, with their able assistance, has carefully

perused the paperbook and other material documents placed on record.

25. At the outset, this Court notes that it is conscious of the limited

compass of its jurisdiction under Section 9 of the A&C Act. The

power conferred thereunder is interim and protective in nature,

intended to preserve the subject matter of the arbitration and to

safeguard the efficacy of the arbitral process. At this stage, the Court

is required only to examine whether the well-settled parameters

governing the grant of interim relief, namely, the existence of a prima

facie case, the balance of convenience, and the likelihood of

irreparable injury, stand satisfied for the purposes contemplated under

Section 9 of the A&C Act. In ArcelorMittal Nippon Steel (India) Ltd.

v. Essar Bulk Terminal Ltd.

11

, the Hon’ble Supreme Court has

expounded upon the contours of such jurisdiction in the following

terms:

11

(2022) 1 SCC 712.

O.M.P.(I) (COMM.) 29/2026 Page 10 of 42

“88. Applications for interim relief are inherently applications

which are required to be disposed of urgently. Interim relief is

granted in aid of final relief. The object is to ensure protection of

the property being the subject-matter of arbitration and/or

otherwise ensure that the arbitration proceedings do not become

infructuous and the arbitral award does not become an award on

paper, of no real value.

89. The principles for grant of interim relief are (i) good prima

facie case, (ii) balance of convenience in favour of grant of interim

relief and (iii) irreparable injury or loss to the applicant for interim

relief. Unless applications for interim measures are decided

expeditiously, irreparable injury or prejudice may be caused to the

party seeking interim relief.

90. It could, therefore, never have been the legislative intent that

even after an application under Section 9 is finally heard, relief

would have to be declined and the parties be remitted to their

remedy under Section 17.

91. When an application has already been taken up for

consideration and is in the process of consideration or has already

been considered, the question of examining whether remedy under

Section 17 is efficacious or not would not arise. The requirement to

conduct the exercise arises only when the application is being

entertained and/or taken up for consideration. As observed above,

there could be numerous reasons which render the remedy under

Section 17 inefficacious. To cite an example, the different

arbitrators constituting an Arbitral Tribunal could be located at far

away places and not in a position to assemble immediately. In such

a case, an application for urgent interim relief may have to be

entertained by the Court under Section 9(1).”

(emphasis supplied)

26. The Hon’ble Supreme Court, in Essar House Pvt. Ltd. v.

Arcelor Mittal Nippon Steel India Ltd.

12

, has made some pertinent

observations concerning the nature and contours of the jurisdiction of

the Court under Section 9 of the A&C Act, which are extracted

hereinbelow:

“48. Section 9 of the Arbitration Act confers wide power on the

Court to pass orders securing the amount in dispute in arbitration,

whether before the commencement of the arbitral proceedings,

during the arbitral proceedings or at any time after making of the

arbitral award, but before its enforcement in accordance with

Section 36 of the Arbitration Act. All that the Court is required to

12

(2022) 20 SCC 178

O.M.P.(I) (COMM.) 29/2026 Page 11 of 42

see is, whether the applicant for interim measure has a good prima

facie case, whether the balance of convenience is in favour of

interim relief as prayed for being granted and whether the applicant

has approached the court with reasonable expedition

*****

49. Proof of actual attempts to deal with, remove or dispose of the

property with a view to defeat or delay the realisation of an

impending Arbitral Award is not imperative for grant of relief

under Section 9 of the Arbitration Act. A strong possibility of

diminution of assets would suffice. To assess the balance of

convenience, the Court is required to examine and weigh the

consequences of refusal of interim relief to the applicant for

interim relief in case of success in the proceedings, against the

consequence of grant of the interim relief to the opponent in case

the proceedings should ultimately fail.”

27. The principal controversy in the present case turns upon the

question whether the Agreement executed between the parties is “in

its nature determinable” within the meaning of the SRA, as

contemplated under Section 14 thereof. This Court considers it

apposite to reproduce Section 14 of the SRA, which reads as follows:

“14. Contracts not specifically enforceable. —The following

contracts cannot be specifically enforced, namely: -

(a) where a party to the contract has obtained substituted

performance of contract in accordance with the provisions of

section 20;

(b) a contract, the performance of which involves the performance

of a continuous duty which the court cannot supervise;

(c) a contract which is so dependent on the personal qualifications

of the parties that the court cannot enforce specific performance of

its material terms; and

(d) a contract which is in its nature determinable.”

28. Having delineated the statutory contours, it becomes necessary

to advert to the termination clause contained in the Agreement, as the

issue of determinability must be assessed with reference to the

contractual stipulations; accordingly, Clause 10 of the Agreement,

which governs termination, is extracted hereinbelow for ready

reference:

O.M.P.(I) (COMM.) 29/2026 Page 12 of 42

“10. TERM & TERMINATION

10.1. This Agreement shall be valid and binding between the

Parties commencing on the Effective Date and shall remain in force

for a period of 15 years from the Effective Date. It is agreed that

three months prior to the expiry of the Term, the Parties shall

mutually discuss the possibility of extending/renewing the Term of

this Agreement.

10.2. Notwithstanding anything contained above, this Agreement

may be terminated:

(a) By either Party forthwith upon written notice to the

other Party in the event of a material breach of the

provisions, including without limitation the

representations and warranties of the Parties of this

Agreement by any Party hereof ('"Breaching Party"),

which breach has not been remedied by the Breaching

Panty within forty five (45) days of receipt of written

notice requiring remedy of the such breach:

(b) By either Party forthwith upon written notice to the

other Party, if any proceedings under any law relating to

insolvency are commenced against the other Party or if

any Party makes un application under any such law for

being adjudged/declared an insolvent:

(c) Either party may terminate this agreement with mutual

consent by giving a 90 day written notice to the other

party. MIPL agrees and undertakes to remove itself from

the premises on the expiry of the ter or on the sooner

termination of this agreement.

10.3. The right of either Party to terminate this Agreement will be

in addition to any other remedies it may have. All remedies to

either Party under this Agreement are cumulative and not

alternative and may be enforced successively or concurrently.

10.4 Expiry/termination of this Agreement will be without

prejudice to any rights that either Party may have accrued against

the other prior to termination.”

29. This Court takes note of the authoritative pronouncement of the

Hon’ble Supreme Court in K.S. Manjunath (supra). The said decision

undertakes a detailed contemplation of precedent on the concept of

contracts “in their nature determinable” within the meaning of Section

14 of the SRA, and elucidates the principles governing the grant or

refusal of specific performance in such cases. For the sake of ready

reference, the relevant paragraphs of the judgment are extracted

below:

O.M.P.(I) (COMM.) 29/2026 Page 13 of 42

“47. The High Court of Madras in A Murugan v. Rainbow

Foundation Ltd, 2019 SCC OnLine Mad 37961, had further

elaborated on the aspect of determinable contracts. For the purpose

of ascertaining determinability, the court bifurcated contracts into

several categories: (i) contracts that are unilaterally and inherently

revocable or capable of being dissolved such as licenses and

partnerships at will; (ii) contracts that are terminable unilaterally on

a “without cause” or “no fault” basis; (iii) contracts that are

terminable forthwith for cause or that cease to subsist “for cause”,

without a provision for remedying the breach; (iv) contracts which

are terminable for cause subject to a breach notice being issued and

an opportunity to cure the breach being given, and; (v) contracts

without a termination clause, which could be terminated for breach

of a condition but not a warranty, as per applicable common law

principles. The court held that the abovementioned (iii), (iv) and

(v) categories of contract are not determinable contracts. The court

further observed that although the (iv) and (v) categories

are terminable yet the same cannot be said to be in

nature determinable. The relevant observations are as under:

“17. On examining the judgments on Section 21(d) of SRA

1877 and Section 14(c) of the Specific Relief Act, as

applicable to this case, i.e. before Act 18 of 2018, I am of

the view that Section 14(c) does not mandate that all

contracts that could be terminated are not specifically

unenforceable. If so, no commercial contract would be

specifically enforceable. Instead, Section 14(c) applies to

contracts that are by nature determinable and not to all

contracts that may be determined. If one were to classify

contracts by placing them in categories on the basis of

ease of determinability, about five broad categories can be

envisaged, which are not necessarily exhaustive. Out of

these, undoubtedly, two categories of contract would be

considered as determinable by nature and, consequently,

not specifically enforceable : (i) contracts that are

unilaterally and inherently revocable or capable of being

dissolved such as licences and partnerships at will; and

(ii) contracts that are terminable unilaterally on “without

cause” or “no fault” basis. Contracts that are terminable

forthwith for cause or that cease to subsist “for cause”

without provision for remedying the breach would

constitute a third category. In my view, although

the Indian Oil case referred to clause 27 thereof, which

provided for termination forthwith “for cause”, the

decision turned on clause 28 thereof, which provided for

“no fault” termination, as discussed earlier. Thus, the

third category of contract is not determinable by nature;

nonetheless, the relative ease of determinability may be a

relevant factor in deciding whether to grant specific

O.M.P.(I) (COMM.) 29/2026 Page 14 of 42

performance as regards this category. The fourth category

would be of contracts that are terminable for cause

subject to a breach notice and an opportunity to cure the

breach and the fifth category would be contracts without a

termination clause, which could be terminated for breach

of a condition but not a warranty as per applicable

common law principles. The said fourth and fifth

categories of contract would, certainly, not be

determinable in nature although they could be terminated

under specific circumstances. Needless to say, the

rationale for Section 14(c) is that the grant of specific

performance of contracts that are by nature determinable

would be an empty formality and the effectiveness of the

order could be nullified by subsequent termination.”

(Emphasis Supplied)

48. In Narendra Hirawat & Co. v. Sholay Media Entertainment

Pvt. Ltd., 2020 SCC OnLine Bom 391, the Bombay High Court

observed that the phrase “a contract which is in its nature

determinable” would mean a contract which is determinable at the

sweet will of a party to it, without reference to the other party or

without reference to any breach committed by the other party or

without any eventuality or circumstance. In other words, the phrase

would contemplate a unilateral right in a party to a contract to

determine the contract without assigning any reason. The relevant

observation is as under:

*****

49. The Delhi High Court in DLF Home Developers

Limited v. Shipra Estate Limited, 2021 SCC OnLine Del 4902,

while considering an agreement to sell a property held that the

question whether a contract is in its nature determinable must be

answered by ascertaining whether the party against whom it is

sought to be enforced would otherwise have the right to terminate

or determine the contract when the other party is willing to perform

and is not in default. In other words, where a contract cannot be

terminated so long as the other party remains willing to perform its

part, such a contract is not determinable and, in equity, is

specifically enforceable. The relevant observation is as under:

“78. Section 14 of the Specific Relief Act, 1963 sets out

certain classes of contracts that are not specifically

enforceable. One such class of contracts comprises of

contracts, which are in their nature determinable. Clause

(d) of Section 21 of the Specific Relief Act, 1877 expressly

provided that contracts which are in their nature

„revocable‟ are unenforceable. The said statute was

repealed and replaced by the Specific Relief Act, 1963.

Clause (c) of Section 14(1) of the Specific Relief Act, 1963,

as was in force prior to Specific Relief Act, 1877,

expressly provided that contracts, which are in the nature

O.M.P.(I) (COMM.) 29/2026 Page 15 of 42

determinable, were not specifically enforceable. The word

„revocable‟ as used in Clause (d) of Section 21 of the

Specific Relief Act, 1877 was replaced by the word

„determinable‟. The rationale for excluding such

contracts, which are in their nature determinable, from the

ambit of those contracts which may be specifically

enforced, is apparent. There would be little purpose in

granting the relief of specific performance of a contract,

which the parties were entitled to terminate or otherwise

determine. The relief of specific performance is an

equitable relief. It is founded on the principle that the

parties to a contract must be entitled to the benefits from

the contracts entered into by them. However, if the terms

or the nature of that contract entitles the parties to

terminate the contract, there would be little purpose in

directing specific performance of that contract. Plainly, no

such relief can be granted in equity.

79. Viewed in the aforesaid perspective, it is at once

apparent that the contract is in its nature determinable if

the same can be terminated or its specific performance

can be avoided by the parties. Thus, contracts that can be

terminated by the parties at will or are in respect of

relationships, which either party can terminate; would be

contracts that in their nature are determinable. If a party

can repudiate the contract at its will, it is obvious that the

same cannot be enforced against the said party.

80. However, if a party cannot terminate the contract as

long as the other party is willing to perform its

obligations, the contract cannot be considered as

determinable and it would, in equity, be liable to be

enforced against a party that fails to perform the same.

Almost all contracts can be terminated by a party if the

other party fails to perform its obligations. Such a

contract cannot be stated to be determinable solely

because it can be terminated by a party if the other party

is in breach of its obligations. The party who is not in

default would, in equity, be entitled to seek performance of

that contract. In such cases, it cannot be an answer to the

non-defaulting party's claim that the other party could

avoid the contract of the party seeking specific

performance, had breached the contract; therefore, the

same is not specifically enforceable. Thus, the question

whether a contract is in its nature determinable, must be

answered by ascertaining whether the party against whom

it is sought to be enforced would otherwise have the right

to terminate or determine the contract even though the

other party are ready and willing to perform the contract

and are not in default.

O.M.P.(I) (COMM.) 29/2026 Page 16 of 42

81. The contention advanced on behalf of Indiabulls that

the ATS is in its nature determinable as Indiabulls could

terminate it on failure of the other parties to perform their

obligations is, plainly, unmerited. This contention is

premised on the basis that Indiabulls is correct in its

assumption that the other parties had breached the terms

of their obligation. Concededly, if the other parties were

ready and willing to fully perform their obligations,

Indiabulls would not have any recourse to the termination

clause. Such recourse is contingent on the failure of the

other parties to perform the contract. It cannot be stated

that the contract by its very nature is not specifically

enforceable because it entitles a party to terminate the

contract if the other parties have failed to perform their

obligations.

xxx xxx xxx

94. The question whether the contract by its very nature is

determinable is required to be answered by ascertaining

the nature of the contract. Contracts of agency,

partnerships, contracts to provide service, employment

contracts, contracts of personal service, contracts where

the standards of performance are subjective, contracts

that require a high degree of supervision to enforce, and

contracts in perpetuity are, subject to exceptions, in their

nature determinable. These contracts can be terminated by

either party by a reasonable notice.

(Emphasis Supplied)

50. In Affordable Infrastructure & Housing Projects (P)

Ltd. v. Segrow Bio Technics India (P) Ltd., 2022 SCC OnLine

Del 4436, the lease deed provided for a termination clause. Under

the termination clause, the respondent had an option to terminate

the lease deed by serving a 15 days' written notice in case the

petitioner failed to make the payment for two consecutive months.

The Delhi High Court on the strength of DLF Home (supra)

observed that almost all contracts can be terminated by a party, if

the other party fails to perform its obligations and that such

contracts cannot be stated to be determinable solely because it can

be terminated by a party if the other party is in breach of an

obligation. The non-defaulting party would in equity be entitled to

seek performance of that contract. The court held that the question

whether a contract is in its nature determinable must be answered

by ascertaining whether the party against whom it is sought to be

enforced would otherwise have a right to terminate or determine

the contract even though the other party is ready and willing to

perform the contract and is not in default. The relevant observation

is as under:

“37. The law as stated above mandates against grant of

stay against Termination Notice in respect of the

O.M.P.(I) (COMM.) 29/2026 Page 17 of 42

Contracts which are determinable. The petitioner has

relied upon DLF Home Developers Limited v. Shipra

Estate Limited, (2022) 286 DLT 100, wherein it was

observed that a party cannot terminate the Contract so

long as the other party is willing to perform its

obligations. The Contract cannot be considered as

determinable as it would in equity be liable to be enforced

against a party that fails to perform the same. Almost all

Contracts can be terminated by a party, if the other party

fails to perform its obligations. Such a Contract cannot be

stated to be determinable solely because it can be

terminated by a party if the other party is in breach of the

obligations. The party who is not in default would in

equity be entitled to seek performance of that Contract. In

such cases, it cannot be an answer to a non-defaulting

party's claim that the other party could avoid the Contract

of the party seeking specific performance and the same is

not specifically enforceable. Thus, the question whether

the Contract is in its nature determinable must be

answered by ascertaining whether the party against whom

it is sought to be enforced would otherwise have a right to

terminate or determine the Contract even though the other

party is ready and willing to perform the Contract and is

not in default.”

(Emphasis Supplied)

51. The Bombay High Court in Kheoni Ventures (P)

Ltd. v. Rozeus Airport Retail Ltd., (2024) 2 HCC (Bom) 60, also

observed that in order to arrive at a conclusion whether a contract

is determinable or not, it is to be ascertained whether the parties

have a right to terminate it on their own, without the stipulation of

any contingency and without assigning any reason. The relevant

observation is as under:

“11. In order to infer whether a contract is determinable

or otherwise, it is to be ascertained, whether the parties

have a right to terminate it on their own, without stipulation

of any contingency and without assigning any reason. An

inherently determinable contract would permit either party

to terminate it without assigning any reason and merely by

indicating, that the contract shall come to an end, either by

giving a notice for specified period, if stipulated or even

without such a notice.”

(Emphasis Supplied)

*****

62. Since in principle unilateral termination of the contract is

impermissible except where the agreement is determinable within

the meaning of Section 14 of Act of 1963, it also becomes

necessary, at this juncture, to examine whether the ATS dated

28.04.2000 was in its nature determinable. This question requires

O.M.P.(I) (COMM.) 29/2026 Page 18 of 42

to be answered on a scrutiny of the terms of the ATS and the nature

of the rights and obligations flowing therefrom.

****

64. In this backdrop, it would be useful to advert to the

classification set out in A. Murugan (supra), wherein the Madras

High Court categorised contracts into five broad classes depending

on their ease of determinability. Out of those, the first two i.e., (i)

contracts inherently revocable such as licences and partnerships at

will, and (ii) contracts terminable unilaterally on a “without-cause”

basis, were held to be determinable in nature. The remaining

classes, namely, (iii) contracts terminable for cause without

provision for cure, (iv) contracts terminable for cause with

notice and opportunity to cure, and (v) contracts without a

termination clause but terminable only for breach of a condition,

were all held not determinable in nature.

65. Further, as laid down in DLF Home (supra), the question

whether a contract is in its nature determinable lies in ascertaining

whether the party against whom specific performance is sought has

the right to terminate the contract even when the other party is

ready and willing to perform. This means if the contract cannot be

terminated so long as the other party stands willing to perform, it is

not determinable in its nature and would, in equity, be specifically

enforceable. The same reasoning was followed in Affordable

Infrastructure (supra), where it was held that a contract terminable

for breach cannot merely for that reason be regarded as

determinable, otherwise, no contract could ever be specifically

enforced.

66. Applying these principles, the ATS in the present case cannot

be said to be a determinable contract. Viewed in light of the

classification as set out in A. Murugan (supra), the ATS would

squarely fall within category (v) as mentioned above. The ATS was

devoid of any clause enabling termination for convenience or

otherwise empowering either party to terminate unilaterally. The

only conceivable circumstance in which ATS could be brought to

an end in the present case was upon a breach of a condition by

either of the parties. Thus, the original vendors did not possess any

contractual right to terminate the ATS in the absence of default by

the original vendees. The grounds cited in the notice of termination

dated 10.03.2003, namely, the subsistence of a status quo order and

the death of one of the original vendors cannot be said to be based

on any default or breach by the original vendees. The original

vendees had performed their part by paying a substantial amount

and were also ready and willing to perform the terms of ATS.”

(emphasis supplied)

30. It would suffice to observe that in paragraph 64 of the aforesaid

judgement, the Hon’ble Supreme Court has clearly delineated various

O.M.P.(I) (COMM.) 29/2026 Page 19 of 42

classes of contracts on the basis of the nature and manner of their

determinability. The Apex Court, approving the classification adopted

by the Madras High Court in A Murugan v. Rainbow Foundation

Ltd

13

, has clarified that contracts which are inherently revocable, such

as licences and partnerships at will, or those which are terminable

unilaterally on a “without cause” or “no fault” basis, would fall within

the ambit of Section 14(d) of the SRA, being determinable in nature.

31. In contradistinction, contracts which are terminable only for

cause, particularly where termination is conditioned upon the

existence of a breach and is subject to issuance of notice and affording

an opportunity to cure, do not fall within the category of contracts that

are determinable by their very nature.

32. Tested on the anvil of the aforesaid principles, Clause 10.2(a) of

the present Agreement does not confer an unfettered, unilateral, or at-

will right of termination. The right to terminate is expressly contingent

upon the occurrence of a material breach and is further circumscribed

by the mandatory requirement of issuance of a written notice granting

a cure period of forty-five (45) days. The contractual stipulation thus

squarely falls within the fourth category identified in paragraph 64 of

K.S. Manjunath (supra), namely, contracts terminable for cause

subject to notice and opportunity to cure, which have been held not to

be determinable in nature.

33. This Court also takes note of the judgment of this Court in HK

Toll (supra), which, after considering a catena of authorities, explains

the scope of the statutory embargo contained in Section 14(d) of the

SRA and underscores that the determinability of a contract must be

13

2019 SCC OnLine Mad 37961

O.M.P.(I) (COMM.) 29/2026 Page 20 of 42

examined in light of the termination stipulations agreed between the

parties. The reasoning adopted therein emphasizes that where

termination is conditioned upon specific contingencies or breaches,

and is not exercisable at the mere will of a party, the contract cannot

ipso facto be regarded as determinable in nature.

34. The above exposition, read holistically, clarifies that the

question whether a contract is “in its nature determinable” must

necessarily be answered with reference to the termination mechanism

embodied in the contract and the extent of the power reserved to the

parties thereunder. Where a contract envisages termination only upon

the occurrence of specified contingencies, particularly subject to

notice and cure provisions, and does not confer an unfettered right of

revocation, such a contract cannot be characterised as determinable in

the sense contemplated under Section 14(d) of the SRA.

35. Clause 10 of the Agreement in the present case provides for

termination strictly upon the occurrence of defined contingencies and

subject to compliance with a stipulated cure period. It does not vest

either party with an unqualified or at-will power of termination. The

issue of determinability must, therefore, be examined within that

contractual framework, and not divorced from the express stipulations

mutually agreed upon by the parties.

36. This Court finds merit in the submissions advanced by the

learned Senior Counsel for the Petitioner and is of the considered

opinion that the termination clause embodied in Clause 10 of the

Agreement is not in its nature determinable within the meaning of

Section 14(d) of the SRA. The mere existence of such a clause,

particularly one conditioned upon the occurrence of breach and

compliance with a cure mechanism, cannot operate as a statutory

O.M.P.(I) (COMM.) 29/2026 Page 21 of 42

embargo against consideration of interim protection. Consequently,

the bar under Section 14(d) of SRA is not attracted so as to preclude

the grant of interim relief against the Impugned Termination Notice.

37. Insofar as the objection founded upon Section 14(b) of SRA is

concerned, this Court is unable to accept the same. Section 14(b) of

SRA proscribes specific performance of a contract, the performance of

which involves a continuous duty that the Court cannot supervise. The

emphasis is on the nature of the obligation and the impracticability of

judicial supervision over its execution.

38. In the present case, Clause 10 of the Agreement does not

contemplate the enforcement of any continuous or minute operational

obligations requiring constant oversight by the Court. The relief

sought is confined to protection against termination pending arbitral

adjudication. A bare perusal of the Agreement itself delineates the

respective rights and obligations of the parties and does not require the

Court to regulate day-to-day performance or assume managerial

control over the arrangement.

39. To this Court’s mind, the bar as contemplated under Section

14(b) of SRA would arise only where the Court is compelled to

remain in seisin of the matter and supervise the ongoing execution of

reciprocal duties. No such situation is presented here. Accordingly, the

bar under Section 14(b) of SRA is not attracted.

40. As respects the rival submissions touching upon the validity or

otherwise of the Impugned Termination Notice are concerned, the

same traverse into the merits of the underlying disputes between the

parties. Nevertheless, for the sake of completeness and convenience,

this Court considers it appropriate to reproduce herein the tabular

statement filed along with the Rejoinder by the Petitioner, which is

O.M.P.(I) (COMM.) 29/2026 Page 22 of 42

extracted as follows:

RADIOLO

GY

EQUIPME

NT

ALLEGATIO

NS RAISED

VIDE REPLY

DATED

30.01.2026

RESPONSE DOCUMENT

Philips RES

MX16 - CT

Scan

8(a) @ Pg. 11:

11-year delay

in intimation of

CT Scan

Machine to

Respondents

the

(DOCUMENT

R-3; Page

110@ 112).

The said CT Machine

was being run prior

Petitioner entering to

the into the RSA

dated 02.05.2016.

The Petitioner took

over the machine

when it entered into

the RSA.

The license issued by

the Competent

Authority which is

valid till 05.11.2026,

thus on examination

of the date of end of

life as stated in the

letter dated

1.08.2025, it is clear

that that as per the

statutory authority

the equipment is safe

to use.

As per rule 3 of the

Atomic Energy

Rules, no person

shall operate any

radiation generation

equipment without

the license, therefore

licence has been

given by the AERB

after confirming

itself that equipment

it safe to use till

05.11.2026, hence,

DOCUMENT

[License issued

competent R-3 by

authority valid till

05.11.2026] (Pg.

113-115)

O.M.P.(I) (COMM.) 29/2026 Page 23 of 42

the allegation that the

equipment was

unsafe and unusable

for the patients is a

false and a malicious

statement to

somehow create a

breach in spite of a

valid license, issued

by the AERB

authority.

8(b)@ Pg. 12:

The Philips

RES MX16

achieved end

of life status on

31.12.2025 and

the same was

intimated

Respondent

The RSA nowhere

mandates the

Petitioner to convey

this information to

not the Respondents,

however when the

information was

sought on

18.12.2025, the same

was promptly replied

to on the same date

itself along with

supporting.

DOCUMENT R-3

[Email dt.

18.12.2025 issued

by Mrs. Dolly

Sharma to the

Respondent] (Pg.

110)

DOCUMENT - 7

[email dt.

18.12.2025, sent

by the Respondent

to the Petitioner]

Since the

machine has

reached end of

life, it will not

be serviced

anymore

DOCUMENT R-4 as

relied on by the

Respondents

nowhere states that

the manufacturer will

not service the

machine. What it

clearly states is that

the manufacturer will

provide support to

the best of its ability

however the same

would be dependent

on parts availability.

It is nowhere

written that the

machine will not be

serviced at all. In

DOCUMENT R-4

[End of life notice

dated 1.08.2025

sent by the

manufacturer] (Pg.

174)

O.M.P.(I) (COMM.) 29/2026 Page 24 of 42

fact, the

manufacturer stated

that it will continue

to honour the service

agreement subject to

the above. The

document relied on

nowhere states that

the machine has

become

unusable/unsafe. End

of Life does not

mean the end of

clinical life of an

equipment.

8(c) @Pg. 12:

The CT

machine has

stopped

functioning

since

28.12.2025.

The Petitioner had

itself informed the

Respondents about

the breakdown of the

CT machine and

further it was

informed vide dated

22.12.2025 that email

the Petitioner is in

the process of

ordering a new CT

machine in order to

replace the existing

MX-16 machine.

It was further

informed that in the

interim, CT scans of

the patients will be

done in other centres

of the Petitioner, in

compliance with

Clause 4.2 of the

RSA.

DOCUMENT -9

[Email

22.12.2025]

(Pg.330 @332)

DOCUMENT 10

[Purchase Order of

the new CT

machine dt.

23.12.2025] (Pg.

335)

DOCUMENT R-5

[WhatsApp dated

issued message

30.12.2025 the

Petitioner] (Pg.

175)

8(d) @Pg. 12:

The Petitioner

was asked in

continuation of

The Respondent was

well aware m

advance regarding

the new CT machine

DOCUMENT 9

[Email dt.

22.12.2025] (Pg.

330 @ 332 );

O.M.P.(I) (COMM.) 29/2026 Page 25 of 42

the

Termination

Notice period

on 07.01.2026

and was asked

to remove the

said CT

machine, in

order to let the

Respondent

make the

alternate

arrangements.

being ordered vide

communications

dated 22.12.2025,

02.01.2026 and email

sent by Dr. Vaze

prior to the

communication dated

07.01.2026.

Incorrect date of

breakdown is

mentioned as the

same could be

confirmed

Respondents letter

from dated

07.01.2026 wherein

they have clearly

breakdown

30.12.2025.

DOCUMENT R -

10 [Response to

email dated

27.12.2025] (Pg.

219@228)

DOCUMENT 15

[Email dt.

07.01.2026 sent by

the Petitioner to

the Respondent]

(Pg. 378 )

DOCUMENT 16

[letter dated

07.01.2026 sent by

the Respondent]

(Pg. 380)

8(f) @Pg. 13:

The machine

has n ot

underwent any

preventive and

corrective

maintenance

and further

Philips has

clearly not

rendered any

such service.

Customer Service

Reports of Philips dt.

31.12.2025 which

clearly evidence the

preventive and

corrective

maintenance

undertaken by the

Petitioner. Even prior

to the same the

preventive and

corrective

maintenance has

taken place at all

times service reports

dt. 31.12.2025,

21.08.2025,24.02.202

520.02.2025,05.06.20

24, 28.05.2024 and

04.01.2024 attached.

Further the

preventive and

corrective services

printed by the

DOCUMENT P-4

[Customer service

Report]

DOCUMENT P-3

[PMS Reports]

O.M.P.(I) (COMM.) 29/2026 Page 26 of 42

manufacturer

25.08.2025, dated

14.02.2025,

05.08.2024,

06.01.2024 so as to

answer the

respondents

allegation that the

same was never

conducted by the

petitioner is attached

here as DOCUMENT B

8(g) @Pg. 13:

The Petitioner

has suppressed

the request

12.01.2026

letter dt. and

permission for

sale and

transfer dated

19.01.2026

obtained from

the appropriate

authority

There is no

suppression as the

Petitioner was

nowhere mandated

under the agreement

to intimate to the

respondent.

information been

sought by Whenever

has the Respondents,

the same has been

provided by the

Respondent. Further

such a permission is

required and

mandated as per

Rules 3a of the PC-

PNDT Rules, 1994

which the Petitioner

has scrupulously

followed.

DOCUMENT R-6

[Request for sale

and transfer of CT

machine to the

appropriate

authority vide

letter dt.

12.01.2026] (Pg.

176)

DOCUMENT R-7

[Permission for

sale and transfer of

the CT machine

issued by

appropriate

authority vide

letter dt.

19.01.2026] (Pg.

178)

8(j)@ Pg. 14-

15:

In accordance

with Rule 13 of

the PC-PNDT

Rules, at least

30 days

advance notice

is to be given

The Petitioner is in

due compliance with

the Rule 13 of the

PC-PNDT Rules as

the delivery at site is

subjected to the

statutory clearance.

In furtherance, to the

DOCUMENT 15

[Email dt.

07.01.2026] (Pg.

378)

DOCUMENT P-5

O.M.P.(I) (COMM.) 29/2026 Page 27 of 42

statutory to the

authorities

before

replacement of

any equipment,

same was not

given with

regard to the

Purchase order

Purchase Order dated

23.12.2025, the

Petitioner has

informed the

Respondents vide

email dated

05.02.2026 Wherein,

the Petitioner has

attached the

intimation letter

dated 05.02.2026,

and intimated the

Respondent about the

availability of the

new CT machine and

same to be installed

at Premises by the

Hospital 09.02.2026

subject to their

coordination to

which the

Respondent hasn't

respondent as of

06.02.2026

9 @Pg. 15-16:

The Petitioner

has been using

end of life and

end of support

equipment m

breach of its

duties and

obligations,

The allegations made

by the Respondents

1s unsupported and

mere speculations

without any

contractual or

statutory support,

with reference to the

end of life notice

(DOCUMENT R -4

@ Pg. 174) as relied

upon by the

Respondent also

finds no mentioning

that the said

equipment is not

usable or is unsafe.

GE Logiq l l(b)@Pg. 17: It is nowhere stated DOCUMENT 18 .

O.M.P.(I) (COMM.) 29/2026 Page 28 of 42

E9

Ultrasound

(S. No.

200239US5

)

The equipment

has achieved

end of Life

status in

March, 2025 as

declared by the

supplier Wipro

GE Healthcare

Pvt. Ltd. and

full support

cant be

provided to

machine

in the mentioned

letter that the said

machine should be

replaced after March

2025, it only states

that it cannot

guarantee spare part

availability and full

maintenance support

without any reference

to the usability or

safety of the

equipment in the

event of continued

use post March 2025.

(COLLY) [Letter

for installation

dated 08.06.2016]

(Pg.418)

DOCUMENT R-9

[letter dt.

23.02.2023 sent by

Wipro GE

Healthcare Pvt.

Ltd.] (Pg. 218)

l l(c)-(d) @ Pg.

17-18: The

Petitioner did

not dispute the

fact that the

said machine

has achieved

end of life

status. The

Petitioner

alleged that

this machine

provides

optimal

functioning, is

in operation

and is duly

maintained.

The petitioner is in

no way barred from

using the said

equipment if the

same is compliant

with the applicable

laws as evidenced

vide the PC-PNDT

certificate and the

same being issued by

the appropriate

authority.

DOCUMENT 18

(COLLY) [PC-

PNDT

CERTIFICATE

valid ti ll

27.04.2026] (Pg.

425)

11 (e) @Pg.

18: The

Petitioner has

suppressed its

response dated

02.01.2026,

which was an

attachment to

its email dated

The Petitioner has

not suppressed the

response dated

02.01.2026 as the

supports the same

Petitioner's case.

However, the

attachment was

inadvertently missed

DOCUMENT R -

10 [Petitioner's

Reply date d

02.01.2026 to the

Respondent No.1

email dated

27.12.2025] (Pg.

219@226)

O.M.P.(I) (COMM.) 29/2026 Page 29 of 42

02.01.2026. out by the Petitioner,

the same has been

evidently attached by

the Respondents in

its reply as Document

No. R-10. The same

supports the

Petitioner's case.

ll(g) @Pg. 18:

Continued use

of the said

machine post

its attainment

of the End of

Life is in

breach of

Clauses 2.1 and

2.3

No statutory or

contractual

obligations state that

the use of the said

equipment unreliable

or unsafe to the

patients. 1s These are

mere speculation

without any basis

whether statutory or

contractual.

Philips En

Visor CHD

Ultrasound

(S. No.

US7050669

4)

12 (c)@ Pg.

19: Petitioner

that informed

despite

equipment this

having

achieved end

of life status,

no steps were

taken by the

Petitioner to

get a new

equipment

No statutory or

contractual

obligations state that

the use of the said

equipment unreliable

or unsafe to the

patients.

DOCUMENT

[Principles

Practices R-8 and

for the Cyber

Security of Legacy

Medical Devices,

2023] (Pg. 179)

12(d)@ Pg.

19-20: The

petitioner did

not dispute the

fact that the

said machine

has achieved

end of life and

stated that

The achievement of

the End of-Life status

doesn't in any way

affects the usability

and safety of the said

equipment, the said

machine

decommissioned

permission letter was

DOCUMENT 18

(COLLY)

[permission for

sale and transfer

dated 02.07.2024]

(Pg. 414 )

DOCUMENT 18

(COLLY) [ non-

returnable gate

O.M.P.(I) (COMM.) 29/2026 Page 30 of 42

machine was

not in use since

many years and

was disposed

of as per PC-

PNDT has

produced

permission

dated

02.07.2024

intimation

dated

05.07.2024

vide dated

02.07.2024 issued by

the appropriate

authority, further the

machine has been

transferred to M/S

Calyx Infotech and

Services and

intimation regarding

the same could also

be evidenced vide

non-returnable gate

pass dated

05.07.2024

Issued by the

Respondent No. 1

itself.

pass dated

05.07.2024

Issued by

Respondent No.1]

(Pg. 416)

12(e)@ Pg. 20:

Certificate of

Registration

page 425 of the

present

petition reveals

that the said

equipment was

delete d from

the said

certificate more

than 10 months

physically over

after handing

over the said

equipment to

M/s Calyx

Infotech

Services on

05.07.2024.

The Petitioner has

intimated the

appropriate authority

about the handing

over of the said

equipment to M/s

Calyx Infotech

Services vide letter

dated 03.07.2024, the

delay in the deletion

certificate

attributable to the

administrating

processing by the

appropriate authority

which is beyond the

control of the

Petitioner.

DOCUMENT 18

(COLLY)

[Intimation letter

dated 03.07.2024]

(Pg. 415)

Siemens

Heliophos-

D X-Ray

13(a)-(e) @ Pg.

21-23: The said

equipment was

last serviced by

the supplier

The petitioner

regularly services the

equipment as and

when required,

servicing of the said

DOCUMENT 18

(COLLY)

[intimation for

decommissioning

to the competent

O.M.P.(I) (COMM.) 29/2026 Page 31 of 42

Siemens on

17.06.2021 and

thereafter third

party namely

M/s

Healthline

Engineers.

equipment has

always been

conducted by an

AERB authorized

agency 1.e. M/s

Bionation Imaging

pvt. Ltd., further,

contractual there or is

no statutory

obligation upon the

Petitioner to get the

servicing of the

equipment done only

through the

manufacturer, these

servicing have

nothing to do with

the machine said

achieving end of life.

Further the said

servicing is with

regard through Mis

Bionation Imaging

Pvt. Ltd. could also

evidenced through

the QA report dated

25.07.2025 as

attached in the

petition @ pg. 426.

authority dt.

14.08.2025] (Pg.

395)

DOCUMENT R -

12 [SERVICE

REPORT dt.

15.06.2021 &

17.06.2021] (Pg.

229)

DOCUMENT P-6

[M/s Bionation

AERB license]

DOCUMENT 18

(COLLY) [Quality

Assurance report

prepared by M/s

Bionation Imaging

Pvt. Ltd. Dt.

28.07.2025] (Pg.

426)

Allengers

MAR S-40

X-Rav

14 @ Pg. 23-24

The Petitioner

on 20.01.2026

requested

Respondent

No. 1 to allow

the Fujifilm

Engineer for

maintenance of

the Xray

system. M/s

Fujifilm are not

an approved

servicing

The information

about the 20.01.2026

has communication

been wrongfully

misrepresented by

the Respondent as the

same could be

evidenced vide email

dt. 20.01.2026 as

attached by the

Respondents as

DOCUMENT R -14

@ 235, the

communication

DOCUMENT R -

14 [Email dt.

20.01.2026] (Pg.

237)

DOCUMENT l

8(COLLY)

[AERB valid

License

14.08.2030] (Pg.

397)

O.M.P.(I) (COMM.) 29/2026 Page 32 of 42

agency the

same is a

statutory

violation

clearly states that the

said agency has been

contacted for

essential functioning

and maintenance CR

system of X-ray

equipment and not

AERB related

servicing, this

statement has been

knowingly

misrepresented in

order to misled the

court.

GE Logiq

E9 (S. No.

200230US5

)

17 @ Pg. 26:

The petitioner

claims that the

intimation for

installation of

the said

equipment is at

page 418 of the

Petition,

however, the

machine

referred to in

that email is

GE model

Logiq E9 serial

No. 1 -

5960363147

installed on

31.05.2016 is

currently

working at the

Respondent

No.1 hospital.

There is no

other

ultrasound

machine model

Logiq E9

shown in the

There has been a

typographical error in

the serial number of

the machine in the

list attached in the

email dated

18.12.2025, further it

stated the correct

serial number of the

machine is

200230US5 and the

said machine has

been installed at the

Hospital premises

vide letter dated

08.06.2016 and

remains fully

functional and

currently in use at the

hospital.

The ultrasound

machine model

Logiq E9 bearing

serial no. 200230US5

is currently installed

at the Hospital

premises and the

same is included in

the PC -PNDT

DOCUMENT 18

(COLLY)

[intimation letter

dt. 08.06.2016]

(Pg. 418)

DOCUMENT 18

(COLLY) [PC-

PNDT

CERTIFICATE]

(Pg. 425)

O.M.P.(I) (COMM.) 29/2026 Page 33 of 42

said list.

Further the PC-

PNDT

certificate

doesn't find

mentioning of

the said

machine.

certificate, further the

Respondent through

these confusing

statements is trying

to misled the Hon'ble

Court.

Sonoscape

P-20

Doppler (S.

No. 916)

18 @Pg. 27-

29: Prior

intimation for

installation was

given on

30.09.2024 and

it was installed

07.10.2024

which shows

the said

equipment was

installed within

7 days of

intimation

which is a clear

violation of

Rule 13 of the

PC-PNDT

Rules 30 days

advance notice

The said machine

was installed at the

hospital premises

only after obtaining

all the statutory

approvals and due

intimation was given

to the appropriate

authority of the said

change, the delay in

the addition of the

said machine is

purely attributable to

the administrative

processing by the

authority.

Moreover, the

Hon'ble Delhi High

Court in W.P. (C)

4009 of 2012 (Indian

Radiological and

Imaging Association

(IRIA) Vs. Union of

India and Medical

Council of India)

held that condition of

an advance of 30

days as per Rule 13

of the PC-PNDT

Rules, 1996 is

onerous, and further

directed an

arrangement qua

Rule 13 to be made

wherein for every

DOCUMENT

(COLLY)

[Intimation letter

dt. 07.10.2024]

(Pg. 417)

DOCUMENT P-2

[letter dated

16.10.2012 along

with the attached

order (W.P. (C)

4009 of 2012

(Indian

Radiological

Imaging and

Association

(IRIA) Vs. Union

of India and

Medical Council

of India))]

O.M.P.(I) (COMM.) 29/2026 Page 34 of 42

change in place,

equipment and

address an advance

notice of seven days

be given to the

Appropriate

Authority and for

every change in

employee intimation

can be given within 7

days of such change.

The Court also held

that a delay on the

part of the

Appropriate

Authority in

incorporating the

change and re-issuing

the certificate would

not prevent the

concerned clinics

from effecting the

change in place

address of the

equipment after a

lapse of seven days

and to continue with

their activities.

GE Voluson

E8 Expert

(S. No.

D00527)

19 @Pg. 29-

30: The

equipment was

registered two

months after

the installation

which is in

violation of

rule 18 (1) read

with rule 13 of

the PC-PNDT

Rules

The petitioner had

duly obtained the

said equipment vide

letter dt. 18.04.2022,

further the same was

installed at the

Hospital premises

only post the

installation

intimation dt.

26.04.2022, thus the

Petitioner has

completed the due

compliance and only

after that installed the

DOCUMENT 18

(COLLY)

[Permission dated

18.04.2022

intimation

installation

26.04.2022] (Pg.

423-424)

O.M.P.(I) (COMM.) 29/2026 Page 35 of 42

said equipment. The

delay in the addition

of the said machine

in the PC-PNDT

certificate is purely

attributable to the

administrative

processing by the

authority and as per

Indian Radiological

and Imaging

Association (IRIA)

Vs. Union of India

and Medical

Council of India

(Supra) the same

would not prevent the

concerned clinics

from effecting the

change in place

address of the

equipment after a

lapse of seven days

and to continue with

their activities.

Mindray

M7 (S. No.

NW420037

58)

21 @Pg. 31-

32:

The Petitioner

had obtained

the permission

for sale and

transfer from

the authority

vide letter

dated

02.07.2024, it

was further

sold to M/s

Calyx Infotech

Services on

05.07.2024, the

said equipment

was deleted

The with petitioner

had obtained the

permission for sale

and transfer from the

authority vide letter

dated 02.07.2024,

intimation letter for

the sale and transfer

of the said machine

was sent on

03.07.2024 and the

non-returnable gate

pass was issued by

the Respondent No.1

on 05.07.2024, this

clearly shows that the

lawfully transferred

the said machine and

DOCUMENT 18

(COLLY)

[Permission for

sale and transfer

dt. 02.07.2024,

intimation for sale

and transfer dt.

03.07.2024, Non-

returnable gate

05.07.2024 issued

by Respondent

No.1] (Pg. 414-

416)

O.M.P.(I) (COMM.) 29/2026 Page 36 of 42

from the PC-

PNDT

certificate on

22.05.2025

which after

more than 10

months post

the sale

not used it thereafter.

The delay in the

deletion of the said

machine in the

PCPNDT certificate

is purely attributable

to the administrative

processing by the

authority and as per

Indian Radiological

and Imaging

Association (IRIA)

Vs. Union of India

and Medical

Council of India

(Supra) the same

would not prevent the

concerned clinics

from effecting the

change in place

address of the

equipment after a

lapse of seven days

and to continue

activities.

Philips

IU22 (S.

No.

B05P8L)

22 @Pg. 32-

33:

The Petitioner

had obtained

the permission

for sale and

transfer from

the authority

vide letter

dated

02.07.2024, it

was further

sold to M/s

Calyx Infotech

Services on

05.07.2024, the

said equipment

was deleted

The petitioner had

obtained the

permission for sale

and transfer from the

authority vide letter

dated 02.07.2024,

intimation letter for

the sale and transfer

of the said machine

was 03.07.2024 and

the non-returnable

gate pass was issued

by the Respondent

No.1 on 05.07.2024,

this clearly shows

Respondent has

lawfully transferred

the said machine and

DOCUMENT 18

(COLLY)

[Permission for

sale and transfer

dt. 02.07.2024,

intimation for sale

and transfer dt.

03.07.2024, Non-

returnable pass dt.

gate 05.07.2024

issued by

Respondent No.1]

(Pg. 414-416)

O.M.P.(I) (COMM.) 29/2026 Page 37 of 42

from the

PCPNDT

certificate on

22.05.2025

which after

more than 10

months post

the sale

not used it thereafter.

The delay in the

deletion of the said

machine in the PC-

PNDT certificate

attributable is purely

to the administrative

processing by the

authority and as per

Indian Radiological

and Imaging

Association (IRIA)

Vs. Union of India

and Medical

Council of India

(Supra) the same

would not prevent the

concerned clinics

from effecting the

change in place

address of the

equipment after a

lapse of seven days

and to continue

activities.

Sonoscape

P-20 (S. No.

295)

23 @ Pg. 33-

34: The said

equipment was

handed over to

M/s Sonoscape

Medical India

Pvt. Ltd. by the

Petitioner vide

permission for

sale and

transfer dt.

11.12.2024, the

said equipment

was deleted

from the PC-

PNDT

certificate only

on 22.05.2025,

The petitioner had

obtained the

permission for sale

and transfer from the

authority vide letter

dated 11.12.2024,

intimation letter for

the sale and transfer

of the said machine

was sent on

13.12.2024 and the

non-returnable gate ·

pass was issued by

the Respondent No.l

on 13.12.2024, this

clearly shows that the

Respondent has

lawfully transferred

DOCUMENT 18

(COLLY)

[Permission for

sale and transfer

dt. 11 .12.2024,

intimation for sale

and transfer dt.

13.12.2024, Non-

returnable pass dt.

13.12.2024 issued

by Respondent

No.1] (Pg. 419-

421)

O.M.P.(I) (COMM.) 29/2026 Page 38 of 42

which is more

than 5 months

after the

permission for

sale and

transfer was

obtained by the

Petitioner

which is a clear

violation of the

PC-PNDT

Rules.

the said machine and

not used it thereafter.

The delay in the

deletion of the said

machine in the PC-

PNDT certificate is

purely attributable to

the administrative

processing by the

authority and as per

Indian Radiological

and Imaging

Association (IRIA)

Vs. Union of India

and Medical Council

of India (Supra) the

same would not

prevent the

concerned clinics

from effecting the

change in place

address of the

equipment after a

lapse of seven days

and to continue with

their activities.

41. This Court is of the opinion that, at this stage, while exercising

jurisdiction under Section 9 of the A&C Act and bearing in mind the

limited compass of such jurisdiction as noticed in the preceding

paragraphs, there arises no occasion to enter into these issues which

are purely on the merits of whether or not the Impugned Termination

Notice could have been issued.

42. In the aforesaid backdrop, this Court consciously refrains from

embarking upon a detailed examination of the merits of the various

allegations levelled by the parties, as such an inquiry would trench

upon issues that properly fall within the domain of the Arbitral

Tribunal. At this stage, it suffices to observe that, even assuming

O.M.P.(I) (COMM.) 29/2026 Page 39 of 42

disputes exist with respect to the functioning of the machines, as

contended by the Respondents, the resolution of such disputes must

strictly conform to the procedure contractually agreed between the

parties.

43. The Agreement, as between the parties, clearly stipulates, under

Clause 10, that in the event of an alleged material breach, a prior

notice is required to be issued specifying the breach complained of,

followed by a stipulated cure period of 45 days to enable rectification

or removal of such breach. Termination, therefore, is not an immediate

or unilateral remedy, but one conditioned upon compliance with the

agreed mechanism.

44. In the present case, even proceeding on an arguendo basis that

certain deficiencies existed in relation to the machines, the

Respondents were nonetheless bound to adhere to the termination

mechanism embodied in Clause 10 of the Agreement. The proper

course would have been to issue a notice identifying the alleged

material breach and affording the Petitioner the contractually

mandated opportunity to cure the same within the prescribed period. It

is only upon failure to rectify such breach within the stipulated time

that the right to issue a Termination Notice could have arisen.

45. As rightly contended by learned Senior Counsel for the

Petitioner, there could be no occasion for a unilateral determination by

the Respondents that the alleged defects were incurable, particularly in

the absence of compliance with the contractual cure mechanism. Such

a determination, without affording the Petitioner the agreed

opportunity to remedy the alleged breach, would be contrary to the

express terms of the Agreement.

46. In the considered opinion of this Court, the impugned act of

O.M.P.(I) (COMM.) 29/2026 Page 40 of 42

termination appears to have been effected in undue haste, placing the

cart before the horse, and is prima facie not in consonance with the

procedure and safeguards expressly incorporated in the Agreement.

47. Consequently, in view of the foregoing discussion and the

prima facie findings recorded hereinabove, this Court is of the

considered opinion that the relief sought by the Petitioner for staying

the operation and effect of the Impugned Termination Notice deserves

to be granted. The Respondents are, accordingly, directed to strictly

comply with and adhere to the terms and conditions of the Agreement,

including the procedure and safeguards expressly stipulated therein

with respect to termination.

48. At this interlocutory stage, the material placed on record prima

facie indicates a departure from, and non-adherence to, the termination

mechanism prescribed under Clause 10 of the Agreement. The

contractual requirement of issuance of notice specifying the alleged

material breach, coupled with the grant of a stipulated cure period,

does not appear to have been complied with in its true letter and spirit.

A prima facie case is thus made out, warranting the exercise of this

Court’s jurisdiction under Section 9 of the A&C Act.

49. Further, if the Impugned Termination Notice is permitted to

operate during the pendency of the arbitral proceedings, if any, the

consequences to the Petitioner would be both immediate and far-

reaching. The Agreement in question admittedly subsists for a

substantial unexpired tenure of approximately five years, during which

the Petitioner is entitled to perform its contractual obligations and

derive the corresponding commercial benefits.

50. In the considered opinion of this Court, a premature termination

at this stage would effectively divest the Petitioner of these valuable

O.M.P.(I) (COMM.) 29/2026 Page 41 of 42

contractual rights without the disputes having been adjudicated on

merits by the Arbitral Tribunal. Such a course would not only disturb

the contractual equilibrium between the parties but may also render

the arbitral process itself illusory in practical terms, inasmuch as the

subject matter of the dispute would stand irreversibly altered before a

final determination is rendered.

51. The balance of convenience, therefore, clearly tilts in favour of

preserving the status quo and maintaining the contractual relationship

pending adjudication. If interim protection is declined, in view of the

foregoing discussions, and the termination is allowed to take effect,

the Petitioner would suffer consequences that may not be capable of

complete restitution even if it ultimately succeeds.

52. In addition to financial implications, the Petitioner has

demonstrated a credible apprehension of serious prejudice to its

reputation, goodwill, and commercial standing as a premier agency

engaged in the provision of diagnostic services. Such reputational

harm, once occasioned, is inherently intangible and cannot be

adequately measured or compensated in monetary terms. The element

of irreparable injury is thus clearly established, warranting protective

intervention at this stage.

DECISION:

53. In view of the aforesaid analysis and findings, the Impugned

Termination Notice is stayed. The parties are directed to maintain

status quo with respect to the operation, implementation, and

performance of the Agreement as it stood immediately prior to the

issuance of the said Termination Notice.

54. At this stage, it is clarified that nothing contained in this

O.M.P.(I) (COMM.) 29/2026 Page 42 of 42

Judgment shall be construed as an expression of any final opinion by

this Court on the merits of the disputes between the parties. The

observations made herein are confined solely to the adjudication of the

present Petition and shall not be understood as a determination of the

substantive issues.

55. Accordingly, all rights and contentions of both parties are kept

open and expressly reserved to be urged before the appropriate forum,

in accordance with law.

56. In view thereof, the present petition, along with the pending

application, stands disposed of in the aforesaid terms.

57. No orders as to cost.

HARISH VAIDYANATHAN SHANKAR, J.

FEBRUARY 26, 2026/tk/sm/her

Description

Legal Notes

Add a Note....