As per case facts, disputes from a facility agreement led to an arbitral award in favor of the Petitioner against Respondent No. 1, which became final. The Petitioner alleged that ...
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 1 of 35
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 15.05.2026
Judgment pronounced on: 29.05.2026
+ O.M.P.(I) (COMM.) 531/2025 & I.A. 10418/2026 (For Delay
101 days in filing the Reply)
MORGAN SECURITIES AND CREDITS PVT. LTD.
.....Petitioner
Through: Mr. Simran Mehta, Mr.
Pushpendedra Jadon & Mr.
Archit Vashistha, Advs.
versus
BPL LIMITED & ORS. .....Respondents
Through: Mr. Ajit Warrier, Mr. Arjun
Perikal, Mr. Angad Kochhar,
Mr. Himanshu Setia, Mr Khush
Bhachawat & Ms. Aishwarya
Prasad, Advs. for R-1.
Mr. Ashish Dholakia, Sr. Adv.
with Ms. Tanvi Dubey, Ms.
Meghna Jandu, Mr. Yash
Dubey & Mr. Mekala Ganesh
Kumar Reddy, Advs. for R-2.
Mr. Shivam Narang, Advocate
for R-3.
Mr. Dayan Krishnan & Mr.
Ashok Panigrahi, Sr. Advs.
with Mr. Prateek Chadha, Mr.
Sukrit Seth, Mr. Shreedhar
Kale, Ms. Radhika Yadav, Mr.
Sreekar Aechuri, Mr. Aniket
Chauhaan & Ms. Surbhi Soni,
Advs. for R-4.
+ ARB.P. 835/2026 & I.A. 12815/2026 (Ex.)
MORGAN SECURITES AND CREDITS PVT LTD
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 2 of 35
.....Petitioner
Through: Mr. Simran Mehta, Mr.
Pushpendedra Jadon & Mr.
Archit Vashistha, Advs.
versus
BPL LIMITED & ORS. .....Respondents
Through: Mr. Ajit Warrier, Mr. Arjun
Perikal, Mr. Angad Kochhar,
Mr. Himanshu Setia, Mr Khush
Bhachawat & Ms. Aishwarya
Prasad, Advs. for R-1.
Mr. Ashish Dholakia, Sr. Adv.
with Ms. Tanvi Dubey, Ms.
Meghna Jandu, Mr. Yash
Dubey & Mr. Mekala Ganesh
Kumar Reddy, Advs. for R-2.
Mr. Shivam Narang, Advocate
for R-3.
Mr. Dayan Krishnan, Sr. Adv.
with Mr. Prateek Chadha, Mr.
Sukrit Seth, Mr. Shreedhar
Kale, Ms. Radhika Yadav, Mr.
Sreekar Aechuri, Mr. Aniket
Chauhaan & Ms. Surbhi Soni,
Advs. for R-4.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANAT HAN
SHANKAR
J U D G M E N T
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petitions, being O.M.P.(I)(COMM.) No. 531/2025
filed under Section 9 and ARB. P. No. 835/2026 filed under Section 11
of the Arbitration and Conciliation Act, 1996
1
, have been preferred
1
A&C Act
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 3 of 35
by the Petitioner and which arise out of disputes under the Bill
Discounting Facilities dated 27.12.2002 and 11.06.2003
2
.
2. Since the parties in both the Petitions are identical, arise from
the same factual matrix, and involve interconnected issues, the same
are being adjudicated and disposed of by way of this common
judgment.
BRIEF FACTS:
3. A brief factual background, to the extent necessary for the
adjudication of the present Petitions, is set out herein below:
(a) The Petitioner had extended financial facilities to Respondent
No. 1, BPL Ltd., under the Facility Agreement, which inter alia
contains an Arbitration clause governing the disputes inter se
the Petitioner and Respondent No.1.
(b) Disputes arising under the said Facility Agreement had earlier
culminated in an Arbitral Award dated 14.12.2016
3
in favour
of the Petitioner, and the said Award has attained finality upon
dismissal of the challenge thereto by the Hon‟ble Supreme
Court vide Judgment dated 04.12.2025.
(c) During the pendency of proceedings before the Hon‟ble
Supreme Court, vide Order dated 12.09.2025, Respondent No. 1
was directed to deposit an amount of Rs. 96 crores with its
Registry.
(d) Subsequently, the Promoters of the Respondent No. 1, i.e.,
Respondent Nos. 2 & 3, M/s ER Computers Private Limited &
Electro Investments Private Limited, had conjointly entered into
2
Facility Agreement
3
Award
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 4 of 35
a Pledge Agreement dated 12.09.2025
4
with Respondent No. 4,
Claypond Capital Partners Private Limited, thereby pledging
their respective shares in favour of Respondent No. 4 to secure
a loan amount of Rs. 96 Crores.
(e) Thereafter, Respondent No. 1 had called its Extra-Ordinary
General Meeting dated 11.11.2025
5
, whereby it was resolved
that Respondent Nos. 2 & 3, being the promoters, were
authorised to secure a loan by pledging or creating a charge
upon the tangible or intangible assets of Respondent No. 1 and,
in view thereof, the Respondent No.1 acquired a loan of Rs. 96
Crores from Respondent No. 2 to comply with the direction of
the Hon‟ble Supreme Court to deposit the aforesaid amount.
(f) It is the case of the Petitioner that the aforesaid transactions,
including the pledge of promoter shareholding and creation of
encumbrances in favour of Respondent No. 4, were undertaken
in violation of Clause 6 of the Facility Agreement, which reads
as follows:
“6. In the event of any amount remaining overdue on
any hundi/bill of exchange under the facility neither of the
Drawer and Drawee shall without the prior written
permission of the Discounting Company pass any
resolution for its winding up for its amalgamation/merger
or otherwise or for amalgamation/merger of any other
company into the Drawer or Drawee enter directly or
indirectly into any new area/filed of business/operation or
dispose off or sell or encumber any of its undertaking or
business or any of its investments in shares etc.
register/recognize any transfer of its shares by any of its
present promoters group; change its paid up share capital
or redeem any security; appoint or reappoint, or modify
any term and condition of appointment of any whole time
or managing director; pay any remuneration to any of its
4
Pledge Agreement
5
EGM
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 5 of 35
managing directors, whole time directors or the chairman;
or pay any dividend on any shares.”
(g) In particular, disclosures dated 16.09.2025 made to the Bombay
Stock Exchange
6
by Respondent No. 1 indicated that promoter
shareholding was pledged in favour of Respondent No. 4 and
that Respondent No. 1 had availed a loan of approximately Rs.
96 crores from Respondent No. 2, with authorisation to create a
charge over its tangible or intangible assets.
(h) The Petitioner claims to have discovered the aforesaid
transactions on 05.12.2025, which, according to it, gave rise to
a fresh cause of action and a new arbitrable dispute under the
said Facility Agreement.
(i) In this backdrop, the Petitioner, complying with the statutory
requirement under Section 21 of the A&C Act, issued a Notice
dated 20.12.2025 invoking the Arbitration Clause under the
Facility Agreement against the Respondents.
(j) Apprehending that the Respondents may proceed to further
encumber or alienate assets of Respondent No. 1, thereby
frustrating the Petitioner‟s rights, the Petitioner filed the
Petition, being O.M.P.(I)(COMM.) No. 531/2025, under Section
9 of the A&C Act, seeking the following prayers:
“In light of the abovementioned facts and circumstances, it
is respectfully prayed, that this Hon‟ble Court may be
pleased to pass orders:
A. Restraining the Respondents from acting in
furtherance of the resolution dated 11.11.2025, in
any manner whether directly or indirectly, in so
far as it seeks to create any encumbrance over the
assets of Respondent No. 1, in favour of any third
party, including but not confined to Respondent
No. 2.
6
BSE
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 6 of 35
B. Restraining Respondent No. 1 from registering and/or
recognizing any transfer of its shares held under promoter
category, by Respondents Nos. 2 & 3, to any one
including Respondent No. 4.
C. Restraining the Respondents from selling, disposing,
encumbering or creating any third-party interest,
whatsoever, in the assets, undertaking, business and
investments of Respondent No. 1.
D. Pass any other such/further Orders as this Hon‟ble Court
deems fit in facts of the present case.
E. Pass ad-interim ex-parte orders in terms of prayers A, B,
C and D above.”
(k) This Court, vide its Order 23.12.2025, passed in the said Section
9 Petition, considering the material on record, directed
Respondent No. 1 to refrain from acting in furtherance of its
EGM and creating any charge or pledge on its tangible or
intangible assets.
(l) Consequent upon the invocation of arbitration and in the
absence of any consensus between the parties with respect to
the appointment of the Arbitrator, the Petitioner has also filed
the Petition, being ARB. P. No. 835/2026, under Section 11 of
the A&C Act, seeking appointment of a Sole Arbitrator to
adjudicate upon the allegedly fresh cause of action stated to
have arisen inter se the parties. The said Arbitration Clause
reads as follows:
“Any dispute or difference whatsoever between the parties arising
out of or in connection with the present facility and for any other
transaction/s between the parties shall be settled by Arbitration of a
Sole Arbitrator appointed by Chairman of Morgan Securities &
Credits Private Limited, who would also have right to appoint
alternate Arbitrator in place of the aforesaid Arbitrator, in case of
his, death or being incapable or refusal to act or in the event of
termination of his mandate for any reason. The arbitration
proceedings shall be held at New Delhi. The power of the
Chairman to appoint a Sole Arbitrator shall not be challenged by
any party. Further, the parties agree that the Arbitrator so
appointed may be an employee and/or professional retainer and/or
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 7 of 35
a person who has a relation or interest in the company. The parties
agree not to ask for any adjournment except under extra-ordinary
reasons.”
4. In the aforesaid factual backdrop, these petitions are being
adjudicated by this Court.
SUBMISSIONS ON BEHALF OF THE PETITIONER :
5. Learned counsel for the Petitioner would submit that the
disputes between the parties arise out of the Facility Agreement, under
which substantial financial exposure was extended to Respondent No.
1, and which contains a binding Arbitration clause governing disputes
between the Petitioner and Respondent No.1.
6. He would submit that disputes arising under the said Facility
Agreement had earlier culminated in an Award, under which a sum
exceeding Rs. 1321 crores is payable by Respondent No. 1, and the
said Award has attained finality upon dismissal of the challenge
thereto by the Hon‟ble Supreme Court on 04.12.2025.
7. Learned counsel would emphasise that, despite the Award
having attained finality, the conduct of Respondent No. 1, in
connivance with its promoter, has consistently been directed towards
defeating and frustrating enforcement of the Petitioner‟s rights by
diluting and encumbering the asset base of Respondent No. 1, as is
also evident from the prior proceedings between the parties.
8. He would submit that Clause 6 of the Facility Agreement
imposes an express contractual restraint, inter alia, prohibiting
Respondent No. 1 and its promoters from encumbering assets,
transferring shareholding, or effecting any change in control without
prior consent of the Petitioner when dues remain outstanding.
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 8 of 35
9. Learned counsel would contend that the recent transactions
undertaken by the Respondents, including the pledge of promoter
shareholding in favour of Respondent No. 4 and the proposed creation
of a charge over the assets of Respondent No. 1 to secure a loan of Rs.
96 crores, are in the teeth of the aforesaid contractual stipulation and
constitute a clear breach thereof.
10. It would be submitted that the said transactions are not bona
fide commercial arrangements but constitute a colourable exercise to
indirectly effect a transfer of control and encumber the assets of
Respondent No. 1, thereby frustrating the Petitioner‟s rights and
rendering the arbitral award incapable of effective enforcement.
11. Learned counsel would further submit that Respondent Nos. 2
and 3, being promoter entities holding a controlling stake of
approximately 50.25% in Respondent No. 1, are not strangers to the
transaction but are integral to the contractual framework and its
performance, and together with Respondent No. 1 constitute a single
economic entity.
12. Learned counsel would further submit that the Arbitration is not
confined in its operation to the signatories alone, and can, in
appropriate cases, extend to non-signatories forming part of a
composite transaction. Reliance in this regard would be placed on the
decision of the Hon‟ble Supreme Court in Cox and Kings Ltd. v. SAP
India Pvt. Ltd.
7
, wherein it has been held that the doctrine of group of
companies permits binding of non-signatories where the
circumstances demonstrate a clear intention to bind such entities,
7
(2024) 4 SCC 1
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 9 of 35
having regard to their role in the negotiation, performance, and subject
matter of the transaction.
13. He would submit that the active and continued involvement of
Respondent Nos. 2 and 3 in the affairs of Respondent No. 1, including
their role in earlier arbitral proceedings and offering of assets as
security, clearly attracts the applicability of the group of companies’
doctrine, rendering them amenable to Arbitration, notwithstanding
their status as non-signatories.
14. It would be further submitted that Respondent No. 4, though a
non-signatory to the Facility Agreement, has, in collusion with the
Respondent Nos. 2 &3, entered into the Pledge Agreement that
effectively facilitates a structured transfer of control and encumbers
the assets of Respondent No. 1.
15. It would be contended that, having regard to the role and
involvement of Respondent Nos. 2, 3 and 4 in the aforesaid
transactions and keeping in view the principles enunciated in Cox and
Kings (supra), the said Respondents are not third parties but are
intrinsically connected with, and have a direct interest in, the
transactions forming the subject matter of the present dispute, and are
therefore liable to be brought within the fold of the arbitral
proceedings notwithstanding their status as non-signatories to the
Facility Agreement.
16. Learned counsel would submit that the Petitioner became aware
of the aforesaid transactions only on 05.12.2025 upon perusal of
disclosures made to the BSE by the Respondent No. 1, which gave
rise to a fresh cause of action and a new arbitrable dispute under the
Facility Agreement.
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 10 of 35
17. He would further submit that in order to preserve the subject
matter of the dispute and to prevent the Respondents from rendering
the arbitral proceedings infructuous, the Petitioner has invoked the
jurisdiction of this Court under Section 9 of the A&C Act, whereupon
this Court, vide Order dated 23.12.2025, has already granted interim
protection by directing Respondent No. 1 to refrain from creating any
charge or pledge on its tangible or intangible assets, thereby
recognising the existence of an arbitrable dispute and the necessity to
preserve the subject matter thereof.
18. In these circumstances, learned counsel would submit that the
Petitioner has rightly invoked the arbitration afresh vide Notice dated
20.12.2025 and, in the absence of any agreement between the parties,
has approached this Court under Section 11 of the A&C Act.
19. It is thus urged that the interim protection already granted by
this Court in the proceedings under Section 9 of the A&C Act be
continued so as to preserve the subject matter of the dispute, and that
the Petition under Section 11 of the A&C Act, as preferred by the
Petitioner, be allowed and a Sole Arbitrator be appointed for effective
adjudication of the disputes arising under the Facility Agreement.
SUBMISSIONS ON BEHALF OF RESPONDENT S:
Respondent No. 1’s submissions:
20. Learned counsel for Respondent No. 1 would, at the outset,
submit that the present proceedings are fundamentally misconceived
and amount to an impermissible attempt by the Petitioner to re-agitate
the disputes which have already attained finality under the Award.
21. He would submit that the disputes arising under the Facility
Agreement had already culminated in the aforesaid Award, and the
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 11 of 35
Petitioner has admittedly initiated enforcement proceedings in respect
thereof before the competent court at Bengaluru, wherein applications
for attachment and restraint over assets of Respondent No. 1 have also
been pursued.
22. Learned counsel would contend that the present Petition under
Section 9 of the A&C Act is, in substance, a post-award proceeding
which seeks to secure the fruits of the award, and therefore, partakes
the character of enforcement rather than interim protection in aid of
arbitration.
23. It would be submitted that once the arbitral award has become
enforceable as a decree under Section 36 of the A&C Act, the remedy
of the Petitioner lies exclusively within the framework of execution
proceedings under Order XXI of the Code of Civil Procedure, 1908,
and the same cannot be circumvented by invoking the jurisdiction of
this Court under Section 9 of the A&C Act.
24. In this regard, reliance would be placed upon the Judgment of
the Hon‟ble Bombay High Court in Centrient Pharmaceuticals
(India) (P) Ltd. v. Hindustan Antibiotics Ltd.
8
, particularly
paragraphs 28 to 30 thereof, wherein it has been held that once an
award becomes enforceable, recourse must be taken to execution
proceedings and proceedings under Section 9 of the A&C Act cannot
be invoked as a substitute therefor.
25. Learned counsel would further submit that the reliefs sought in
the present Petition under Section 9 of the A&C Act are substantially
identical to those already sought in the enforcement proceedings,
including attachment and restraint on alienation of assets, and the
8
2019 SCC OnLine Bom 1614
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 12 of 35
Petitioner has failed to disclose the extent of such proceedings or
explain why similar reliefs could not be pursued therein.
26. It would be contended that the Petitioner, while asserting the
finality and enforceability of the Award, is simultaneously seeking to
invoke Arbitration afresh on the very same cause of action, which is
legally impermissible, as the liability adjudicated under the Award
forms an integral and inseparable part of the reliefs now sought, and
therefore cannot give rise to a fresh arbitrable dispute.
27. Learned counsel would submit that the purported “fresh cause
of action” pleaded by the Petitioner is illusory and is merely a device
to initiate a second round of Arbitration by way of clever drafting, in
order to overcome the limitations of enforcement proceedings.
28. It would be further submitted that permitting such a course
would amount to a collateral re-opening of issues already adjudicated,
and would constitute an abuse of the arbitral process, which cannot be
countenanced in law.
29. It would be contended by the learned counsel for Respondent
No. 1 that if the Section 9 Petition under the A&C Act is held to be
not maintainable, the premise of the existence of any fresh arbitrable
dispute would necessarily fail. Consequently, the Petition under
Section 11 of the A&C Act, being predicated on the same cause of
action, would also not survive and must meet the same fate.
Respondent No. 2’s submissions:
30. Learned senior counsel for Respondent No. 2 would submit that
the present proceedings, insofar as they seek to implead Respondent
No. 2, are wholly misconceived and liable to be rejected, as
Respondent No. 2 is admittedly a non-signatory to the Facility
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 13 of 35
Agreement and is neither a party to the underlying contract nor to the
Arbitration agreement contained therein.
31. He would submit that an arbitration agreement, being a creature
of consent within the meaning of Section 7 of the A&C Act, can bind
only those parties who have expressly or impliedly agreed to be bound
by it, and in the absence of any such consent, no proceedings, whether
under Section 9 or Section 11, can be maintained against a non-
signatory.
32. Learned senior counsel would further submit that the Petitioner
itself has admitted that Respondent No. 2 is a non-signatory to the
Facility Agreement, and is, therefore, estopped from seeking any
coercive or restraining relief against the Respondent No. 2.
33. It would be contended that the attempt of the Petitioner to
invoke the „group of companies‟ doctrine and to treat Respondent No.
2 as an alter ego or part of a single economic unit with Respondent
No. 1 is wholly misconceived and contrary to settled law.
34. Learned senior counsel would submit that, as clarified by the
Hon‟ble Supreme Court in Cox and Kings (supra), the said doctrine
cannot be invoked mechanically on the basis of common shareholding
or management, and can apply only where a clear intention of the
parties, including the non-signatory, to be bound by the arbitration
agreement is demonstrably established.
35. He would further submit that no such intention, whether express
or implied, has been pleaded or established in the present case, and
mere shareholding or corporate relationship does not suffice to bind
Respondent No. 2 to the arbitration agreement.
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 14 of 35
36. Learned senior counsel would also rely on settled principles that
a non-signatory cannot be treated as a party to an arbitration
agreement merely by virtue of being part of the same corporate group
or having common directors, and the burden to establish otherwise lies
heavily on the Petitioner, which has not been discharged.
37. It would be submitted that Respondent No. 2 is a separate and
distinct juristic entity, and the corporate veil cannot be lifted in the
absence of a specific case of fraud, sham, or façade, none of which has
been pleaded or established in the present proceedings.
38. It would also be submitted that any affidavit or undertaking
given by Respondent No. 2 in earlier proceedings cannot be construed
as a general submission to arbitral jurisdiction, as such an undertaking
is limited to the context of the earlier proceedings and is incapable of
being expanded to bind Respondent No. 2 in the present dispute.
39. Learned senior counsel would submit that the aforesaid
transaction, whereby Respondent No. 2 pledged its shareholding in
Respondent No. 1 in favour of Respondent No. 4, is a bona fide
commercial transaction undertaken in the ordinary course of business
and the Petitioner, being a stranger to the same, has no locus to
challenge or restrain such transaction.
40. He would further submit that the shares held by Respondent No.
2 are its independent property, and in the absence of any contractual
restriction binding upon it, no restraint can be imposed on Respondent
No. 2 in respect thereof.
41. Learned senior counsel would also submit that the Petitioner
has failed to satisfy the well-settled parameters for the grant of interim
relief under Section 9 of the A&C Act, namely, the existence of a
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 15 of 35
prima facie case, balance of convenience, and irreparable injury,
insofar as Respondent No. 2 is concerned.
42. It would be further submitted that the present proceedings,
insofar as they seek to implead Respondent No. 2, suffer from
misjoinder of parties and are an attempt to indirectly secure reliefs
against Respondent No. 1, which cannot be directly obtained, and
therefore ought not to be entertained.
43. In these circumstances, learned senior counsel would submit
that no relief under Section 9 of the A&C Act can be granted against
Respondent No. 2, and in the absence of any arbitration agreement
binding upon it, no proceedings under Section 11 of the A&C Act can
also be maintained.
Respondent No. 3’s submissions:
44. Learned counsel appearing on behalf of Respondent No. 3
would submit that no separate submissions are being advanced on its
behalf and that Respondent No. 3 adopts and relies upon the
submissions advanced on behalf of Respondent No. 2, to the extent
applicable.
Respondent No. 4’s submissions:
45. Learned senior counsel appearing on behalf of Respondent No.
4 would contend that its presence in the present proceedings is
misconceived, inasmuch as Respondent No. 4 derives its rights solely
under the Pledge Agreement and has no contractual relationship or
arbitration arrangement with the Petitioner under the Facility
Agreement.
46. He would submit that Respondent No. 4 is an independent
third-party commercial lender, whose sole connection to the present
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 16 of 35
dispute arises from the Pledge Agreement, whereby Respondent Nos.
2 and 3 pledged their shareholding in Respondent No. 1 in favour of
Respondent No. 4 to secure a loan of Rs. 96 crores. The said
transaction is distinct and independent of the underlying contractual
framework between the Petitioner and Respondent No. 1.
47. Learned counsel would contend that in the absence of any
arbitration agreement binding Respondent No. 4, no proceedings
under Section 11 of the A&C Act can be maintained against it, and
equally, no relief under Section 9 thereof can be granted against a
complete alien to the contract, save in exceptional circumstances,
none of which arise in the present case.
48. It would be submitted that the attempt of the Petitioner to
invoke the group of companies’ doctrine is wholly untenable, as
Respondent No. 4 is neither part of the corporate group of Respondent
Nos. 1 to 3, nor has it participated in the negotiation, execution, or
performance of the Facility Agreement, nor derived any benefit
thereunder.
49. It would be contended that the jurisdiction under Section 9 of
the A&C Act cannot be invoked so as to defeat vested third-party
rights, particularly those of a bona fide secured creditor, whose
security interest was created prior to the institution of the present
proceedings and without notice of any alleged contractual embargo.
50. Learned senior counsel would submit that the present Petition
is, in substance, an attempt to employ Section 9 of the A&C Act as a
parallel enforcement mechanism in aid of an arbitral award, which is
already the subject matter of execution proceedings before the
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 17 of 35
competent court, and such use of Section 9 is contrary to the scheme
of the A&C Act.
51. It would be further submitted that the Petitioner‟s case proceeds
on a fundamental misconception by treating the shares held by
Respondent Nos. 2 and 3 in Respondent No. 1 as assets of Respondent
No. 1 itself, whereas in law, shares are the property of the
shareholders and not of the company.
52. Learned counsel would submit that the pledge in question was
created by Respondent Nos. 2 and 3 in their capacity as shareholders
over their own shares, and Respondent No. 1 is neither the pledgor nor
the borrower in the said transaction. Consequently, no restriction
applicable to Respondent No. 1 can be extended to such independent
shareholder transactions or to Respondent No. 4 as pledgee.
53. It would be submitted that the right to transfer or encumber
shares, including by way of pledge, is a statutory right recognised
under Section 58(2) of the Companies Act, 2013, and the Petitioner
cannot, by relying upon a private contractual clause, seek to override
such statutory rights, particularly against a third party which is not
bound by the contract.
54. Learned senior counsel would further submit that Clause 6 of
the Facility Agreement, in any event, operates only inter se the
contracting parties and cannot bind Respondent No. 4, which had no
notice of such clause and was under no obligation to investigate
private contractual restrictions between the Petitioner and Respondent
No. 1.
55. It would be contended that the apprehension of change in
control of Respondent No. 1 is wholly speculative, as the pledge has
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 18 of 35
not been invoked, ownership and voting rights remain with
Respondent Nos. 2 and 3, and no transfer of shares has taken place.
56. Learned senior counsel would emphasise that even otherwise,
any eventual invocation of the pledge would be subject to the
regulatory framework under the Securities and Exchange Board of
India (Substantial Acquisition of Shares and Takeovers) Regulations,
2011, which adequately safeguards the interests of stakeholders,
including creditors.
57. It would also be submitted that the Petitioner has, in fact,
directly benefited from the very transaction it now seeks to impugn,
since the funds generated through the pledge were utilised to deposit
Rs. 96 crores before the Hon‟ble Supreme Court, which amount has
since been released in favour of the Petitioner.
58. Learned senior counsel would contend that having accepted and
retained the benefit of the said transaction, the Petitioner is estopped
from challenging the same, the conduct being hit by the doctrine of
approbate and reprobate, disentitling it to any equitable relief.
59. It would be further submitted that no case for the grant of
interim relief is made out against Respondent No. 4, as there is neither
any prima facie case nor any irreparable injury; thereby, the interim
Order dated 23.12.2025, passed by this Court in the present Petition
under Section 9 of the A&C Act, is required to be vacated.
ANALYSIS:
60. This Court has heard the learned counsel appearing on behalf of
the parties and, with their able assistance, has carefully perused the
paperbook and other material documents placed on record.
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 19 of 35
61. At the outset, this Court deems it apposite to note the
jurisdiction that is provided under Sections 9 and 11 of the A&C Act,
as the former being interim and protective in nature, is intended to
preserve the subject matter of the arbitration and safeguard the
efficacy of the arbitral process, and the latter being confined to a
prima facie examination of the existence of a valid arbitration
agreement and the referral of disputes to arbitration.
62. Accordingly, while considering a Petition under Section 9 of
the A&C Act, the Court is required to examine whether the well-
settled parameters governing the grant of interim relief, namely, the
existence of a prima facie case, the balance of convenience and the
likelihood of irreparable injury, stand satisfied. In ArcelorMittal
Nippon Steel (India) Ltd. v. Essar Bulk Terminal Ltd.
9
, the Hon‟ble
Supreme Court has expounded upon the contours of such jurisdiction
in the following terms:
“88.Applications for interim relief are inherently applications
which are required to be disposed of urgently. Interim relief is
granted in aid of final relief. The object is to ensure protection of
the property being the subject-matter of arbitration and/or
otherwise ensure that the arbitration proceedings do not become
infructuous and the arbitral award does not become an award on
paper, of no real value.
89.The principles for grant of interim relief are (i) good prima facie
case, (ii) balance of convenience in favour of grant of interim relief
and (iii) irreparable injury or loss to the applicant for interim relief.
Unless applications for interim measures are decided
expeditiously, irreparable injury or prejudice may be caused to the
party seeking interim relief.
90.It could, therefore, never have been the legislative intent that
even after an application under Section 9 is finally heard, relief
would have to be declined and the parties be remitted to their
remedy under Section 17.
9
(2022) 1 SCC 712
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 20 of 35
91. When an application has already been taken up for
consideration and is in the process of consideration or has already
been considered, the question of examining whether remedy under
Section 17 is efficacious or not would not arise. The requirement to
conduct the exercise arises only when the application is being
entertained and/or taken up for consideration. As observed above,
there could be numerous reasons which render the remedy under
Section 17 inefficacious. To cite an example, the different
arbitrators constituting an Arbitral Tribunal could be located at far
away places and not in a position to assemble immediately. In such
a case, an application for urgent interim relief may have to be
entertained by the Court under Section 9(1).”
(emphasis supplied)
63. The Hon‟ble Supreme Court, in Essar House Pvt. Ltd. v.
Arcelor Mittal Nippon Steel India Ltd.
10
, has made some pertinent
observations concerning the nature and contours of the jurisdiction of
the Court under Section 9 of the A&C Act, which are extracted
hereinbelow:
“48. Section 9 of the Arbitration Act confers wide power on the
Court to pass orders securing the amount in dispute in arbitration,
whether before the commencement of the arbitral proceedings,
during the arbitral proceedings or at any time after making of the
arbitral award, but before its enforcement in accordance with
Section 36 of the Arbitration Act. All that the Court is required to
see is, whether the applicant for interim measure has a good prima
facie case, whether the balance of convenience is in favour of
interim relief as prayed for being granted and whether the applicant
has approached the court with reasonable expedition
*****
49. Proof of actual attempts to deal with, remove or dispose of the
property with a view to defeat or delay the realisation of an
impending Arbitral Award is not imperative for grant of relief
under Section 9 of the Arbitration Act. A strong possibility of
diminution of assets would suffice. To assess the balance of
convenience, the Court is required to examine and weigh the
consequences of refusal of interim relief to the applicant for
interim relief in case of success in the proceedings, against the
consequence of grant of the interim relief to the opponent in case
the proceedings should ultimately fail.”
10
(2022) 20 SCC 178
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 21 of 35
64. Likewise, the ambit provided under Section 11 of the A&C Act
is extremely circumscribed, whereby this Court only acts as a referral
court. In this regard, a three-Judge Bench of the Hon‟ble Supreme
Court in SBI General Insurance Co. Ltd. v. Krish Spinning
11
, after
taking into consideration the authoritative pronouncement of the
seven-Judge Bench in Interplay Between Arbitration Agreements
under Arbitration Act, 1996 & Stamp Act, 1899, In re
12
,
comprehensively delineated the contours of judicial intervention at the
stage of Section 11 of the A&C Act. The excerpt of Krish Spg (supra)
reads as under:-
“(c) Judicial interference under the 1996 Act
110. The parties have been conferred with the power to decide and
agree on the procedure to be adopted for appointing arbitrators. In
cases where the agreed upon procedure fails, the courts have been
vested with the power to appoint arbitrators upon the request of a
party, to resolve the deadlock between the parties in appointing the
arbitrators.
111. Section 11 of the 1996 Act is provided to give effect to the
mutual intention of the parties to settle their disputes by arbitration
in situations where the parties fail to appoint an arbitrator(s). The
parameters of judicial review laid down for Section 8 differ from
those prescribed for Section 11. The view taken inSBP &
Co. v. Patel Engg. Ltd., (2005) 8 SCC 618 and affirmed in Vidya
Drolia v. Durga Trading Corpn., (2021) 2 SCC 1 that Sections 8
and 11, respectively, of the 1996 Act are complementary in nature
was legislatively overruled by the introduction of Section 11(6-A)
in 2015. Thus, although both these provisions intend to compel
parties to abide by their mutual intention to arbitrate, yet the scope
of powers conferred upon the courts under both the sections are
different.
112. The difference between Sections 8 and 11, respectively, of the
1996 Act is also evident from the scope of these provisions. Some
of these differences are:
11
(2024) 12 SCC 1
12
(2024) 6 SCC 1
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 22 of 35
112.1. While Section 8 empowers any “judicial authority” to refer
the parties to arbitration, under Section 11, the power to refer has
been exclusively conferred upon the High Court and the Supreme
Court.
112.2. Under Section 37, an appeal lies against the refusal of the
judicial authority to refer the parties to arbitration, whereas no such
provision for appeal exists for a refusal under Section 11.
112.3. The standard of scrutiny provided under Section 8 is that of
prima facie examination of the validity and existence of an
arbitration agreement. Whereas, the standard of scrutiny under
Section 11 is confined to the examination of the existence of the
arbitration agreement.
112.4. During the pendency of an application under Section 8,
arbitration may commence or continue and an award can be
passed. On the other hand, under Section 11, once there is failure
on the part of the parties in appointing the arbitrator as per the
agreed procedure and an application is preferred, no arbitration
proceedings can commence or continue.
113. The scope of examination under Section 11(6-A) is confined
to the existence of an arbitration agreement on the basis of Section
7. The examination of validity of the arbitration agreement is also
limited to the requirement of formal validity such as the
requirement that the agreement should be in writing.
114. The use of the term “examination” under Section 11(6-A) as
distinguished from the use of the term “rule” under Section 16
implies that the scope of enquiry under Section 11(6-A) is limited
to a prima facie scrutiny of the existence of the arbitration
agreement, and does not include a contested or laborious enquiry,
which is left for the Arbitral Tribunal to “rule” under Section 16.
The prima facie view on existence of the arbitration agreement
taken by the Referral Court does not bind either the Arbitral
Tribunal or the Court enforcing the arbitral award.
115. The aforesaid approach serves a twofold purpose — firstly, it
allows the Referral Court to weed out non-existent arbitration
agreements, and secondly, it protects the jurisdictional competence
of the Arbitral Tribunal to rule on the issue of existence of the
arbitration agreement in depth.
****
117. In view of the observations made by this Court in Interplay
Between Arbitration Agreements under the Arbitration Act, 1996
& the Stamp Act, 1899, In re, (2024) 6 SCC 1, it is clear that the
scope of enquiry at the stage of appointment of arbitrator is limited
to the scrutiny of prima facie existence of the arbitration
agreement, and nothing else. For this reason, we find it difficult to
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 23 of 35
hold that the observations made inVidyaDrolia v. Durga Trading
Corpn., (2021) 2 SCC 1 and adopted inNTPC Ltd. v. SPML Infra
Ltd., (2023) 9 SCC 385 that the jurisdiction of the Referral Court
when dealing with the issue of “accord and satisfaction” under
Section 11 extends to weeding out ex facie non-arbitrable and
frivolous disputes would continue to apply despite the subsequent
decision inInterplay Between Arbitration Agreements under the
Arbitration Act, 1996 & the Stamp Act, 1899, In re,(2024) 6 SCC
1.
****
119. The question of “accord and satisfaction”, being a mixed
question of law and fact, comes within the exclusive jurisdiction of
the Arbitral Tribunal, if not otherwise agreed upon between the
parties. Thus, the negative effect of competence-competence would
require that the matter falling within the exclusive domain of the
Arbitral Tribunal, should not be looked into by the Referral Court,
even for a prima facie determination, before the Arbitral Tribunal
first has had the opportunity of looking into it.
120. By referring disputes to arbitration and appointing an
arbitrator by exercise of the powers under Section 11, the Referral
Court upholds and gives effect to the original understanding of the
contracting parties that the specified disputes shall be resolved by
arbitration. Mere appointment of the Arbitral Tribunal does not in
any way mean that the Referral Court is diluting the sanctity of
“accord and satisfaction” or is allowing the claimant to walk back
on its contractual undertaking. On the contrary, it ensures that the
principle of arbitral autonomy is upheld and the legislative intent
of minimum judicial interference in arbitral proceedings is given
full effect. Once the Arbitral Tribunal is constituted, it is always
open for the defendant to raise the issue of “accord and
satisfaction” before it, and only after such an objection is rejected
by the Arbitral Tribunal, that the claims raised by the claimant can
be adjudicated.
121. Tests like the “eye of the needle” and “ex facie meritless”,
although try to minimise the extent of judicial interference, yet
they require the Referral Court to examine contested facts and
appreciate prima facie evidence (however limited the scope of
enquiry may be) and thus are not in conformity with the
principles of modern arbitration which place arbitral autonomy and
judicial non-interference on the highest pedestal.
122. Appointment of an Arbitral Tribunal at the stage of Section 11
petition also does not mean that the Referral Courts forego any
scope of judicial review of the adjudication done by the Arbitral
Tribunal. The 1996 Act clearly vests the national courts with the
power of subsequent review by which the award passed by an
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 24 of 35
arbitrator may be subjected to challenge by any of the parties to the
arbitration.
*****
126. The power available to the Referral Courts has to be
construed in the light of the fact that no right to appeal is available
against any order passed by the Referral Court under Section 11 for
either appointing or refusing to appoint an arbitrator. Thus, by
delving into the domain of the Arbitral Tribunal at the nascent
stage of Section 11, the Referral Courts also run the risk of leaving
the claimant in a situation wherein it does not have any forum to
approach for the adjudication of its claims, if its Section 11
application is rejected.
127. Section 11 also envisages a time-bound and expeditious
disposal of the application for appointment of arbitrator. One of the
reasons for this is also the fact that unlike Section 8, once an
application under Section 11 is filed, arbitration cannot commence
until the Arbitral Tribunal is constituted by the Referral Court. This
Court, on various occasions, has given directions to the High
Courts for expeditious disposal of pending Section 11 applications.
It has also directed the litigating parties to refrain from filing bulky
pleadings in matters pertaining to Section 11. Seen thus, if the
Referral Courts go into the details of issues pertaining to “accord
and satisfaction” and the like, then it would become rather difficult
to achieve the objective of expediency and simplification of
pleadings.
128. We are also of the view that ex facie frivolity and dishonesty
in litigation is an aspect which the Arbitral Tribunal is equally, if
not more, capable to decide upon the appreciation of the evidence
adduced by the parties. We say so because the Arbitral Tribunal
has the benefit of going through all the relevant evidence and
pleadings in much more detail than the Referral Court. If the
Referral Court is able to see the frivolity in the litigation on the
basis of bare minimum pleadings, then it would be incorrect to
doubt that the Arbitral Tribunal would not be able to arrive at the
same inference, most likely in the first few hearings itself, with the
benefit of extensive pleadings and evidentiary material.”
(emphasis supplied)
65. Thus, the decision in Krish Spinning (supra) unequivocally
reiterates that the Referral Court, while exercising jurisdiction under
Section 11 of the A&C Act, is required to confine itself to a prima
facie examination of the existence of a valid Arbitration Agreement
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 25 of 35
and nothing beyond. The Court‟s role is facilitative and
procedural, namely, to give effect to the parties‟ agreed mechanism of
dispute resolution when it has failed, without embarking upon an
adjudication of contentious factual or legal issues, which are reserved
for the Arbitral Tribunal.
66. It is in the light of the aforesaid legal framework that the
contentions advanced on behalf of all the parties fall to be examined.
67. The central thread running through all the objections raised
before this Court, whether by Respondent No. 1 on maintainability, or
by Respondents Nos. 2, 3 and 4 on non-impleadment, ultimately
converge on a common issue, namely, whether the transactions of
pledging of promoter shareholding and creation of encumbrances over
the assets of Respondent No. 1, violate the Clause 6 of Facility
Agreement, giving rise to a fresh and independent arbitrable dispute
thereunder. In the considered view of this Court, the material on
record prima facie answers the said question in the affirmative, for the
reasons as set out below.
68. It is an undisputed fact that the earlier disputes inter se the
Petitioner and Respondent No. 1 arising out of the Facility Agreement
had culminated in an Award, whereby substantial amounts were held
payable by Respondent No. 1 to the Petitioner. The mere existence of
the said Award cannot, by itself, lead to the conclusion that every
subsequent dispute arising between the parties stands foreclosed.
69. This Court notes that the present proceedings are not directed
towards reopening or re-agitating issues already concluded; rather, the
grievance of the Petitioner in the present proceedings stems from
subsequent transactions which are alleged to be in breach of the
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 26 of 35
continuing contractual obligations under the Facility Agreement,
particularly Clause 6 thereof. These subsequent events, being distinct
in point of time and nature, prima facie give rise to an independent
cause of action, the adjudication of which falls within the domain of
Arbitration.
70. It is also noted that Clause 6 of the Facility Agreement, as
extracted hereinabove, imposes an express and unconditional
contractual embargo upon Respondent No. 1 and its promoter group
against, inter alia, encumbering any undertaking, business or
investments in shares, registering or recognising any transfer of shares
by the present promoter group, or changing the paid-up share capital,
in each case without the prior written permission of the Petitioner, so
long as any amount remains overdue.
71. However, the existence of the aforesaid clause is not in dispute,
and since the question of whether Clause 6 was in fact violated and
what consequences flow therefrom is precisely the kind of mixed
question of fact and law, this Court deems it appropriate to be left
within the exclusive domain of the learned Arbitral Tribunal.
72. Turning to the objection raised by the Respondent No. 1 that the
present Petition under Section 9 of the A&C Act is, in substance, a
proceeding for enforcement of the Award, in view of this Court, is
devoid of any merit. It is noted that the reliefs sought by the Petitioner
in the Petition under Section 9 of the A&C Act are not directed
towards recovery of the awarded amount, nor do they seek attachment
of assets, payment of money, or any step in execution of the award.
Instead, what is sought is preservation of the existing assets of
Respondent No. 1 and restraint against any alteration in its
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 27 of 35
management or control, pending adjudication of disputes arising from
the alleged breach of Clause 6.
73. In the considered opinion of this Court, such reliefs as are
sought by the Petitioner are protective in nature and are sought in aid
of a fresh arbitral process. The distinction between measures in aid of
arbitration and steps in execution of an award is both factual and
material, and the present case squarely falls within the scope of
Section 9 of the A&C Act.
74. Further, the reliance placed by the Respondent No.1 upon the
decision of the Bombay High Court in Centrient Pharmaceuticals
(supra), to contend that the present proceeding under Section 9 of the
A&C Act is a disguised enforcement proceeding and cannot be
adjudicated under the present proceeding, is misplaced.
75. In Centrient Pharmaceuticals (supra), upon which Respondent
No. 1 has placed its reliance, is factually not similar to the present
case, as in the above-mentioned ruling, Section 9 of the A&C Act was
invoked as a substitute for execution in respect of an existing award.
However, in the present case, the subsequent transactions give rise to
a distinct cause of action and thus the need to preserve the subject
matter pending adjudication thereof. The ratio of the said judgment,
therefore, does not advance the case of Respondent No. 1.The
objection to the maintainability of the present proceedings is
accordingly rejected.
76. The contention advanced by Respondent No. 1 that the alleged
fresh cause of action, as asserted by the Petitioner, is illusory or
merely a device to reopen concluded disputes, also does not merit
acceptance. The transactions and events relied upon by the Petitioner,
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 28 of 35
including the Pledge Agreement, disclosures made to the BSE, the
loan transaction involving a sum of Rs. 96 crores, and the EGM
Resolution, are all subsequent developments that arose long after the
conclusion of the earlier arbitral proceedings.
77. In view of the foregoing, this Court finds that each of the above
transactions and findings by the Petitioner constitutes a distinct act,
alleged to be in breach of Clause 6 of the contractual framework, in
respect of which, Arbitration was invoked vide Notice dated
20.12.2025. The present invocation cannot be characterised as a re-
agitation of disputes already adjudicated, being in response to
subsequent and independent acts of alleged contractual violation.
While the agreement remains unchanged, the disputes, being founded
on fresh transactions, are clearly distinct and capable of independent
reference to Arbitration.
78. The further contention that the Petition under Section 11 of the
A&C Act is contingent upon the fate of the Petition under Section 9 of
the A&C Act is also misplaced.
79. The inquiry under Section 11 of the A&C Act, as envisaged
hereinabove, is confined to the existence of a valid arbitration
agreement and its invocation, both of which are undisputed in the
present case. The grant or refusal of interim relief under Section 9 of
the A&C Act is a separate consideration and does not affect the
maintainability of the Section 11 Petition. Accordingly, the present
objection raised by Respondent No. 1 is, therefore, rejected.
80. As regards the objections raised by Respondent Nos. 2 and 3,
this Court notes that both the said Respondents are admittedly non-
signatories to the Facility Agreement. However, the issue as to
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 29 of 35
whether a non-signatory may nevertheless be bound by an arbitration
agreement, including through application of the group of companies’
doctrine, is essentially a jurisdictional question falling within the
competence of the learned Arbitral Tribunal under Section 16 of the
A&C Act.
81. In this regard, reference may be made to the decisions of the
Hon‟ble Supreme Court in Cox and Kings (supra) and Interplay
Between Arbitration Agreements under Arbitration Act, 1996 &
Stamp Act, 1899, In re (supra), wherein it was authoritatively held
that the applicability of the group of companies doctrine is a fact-
intensive exercise requiring examination of multiple relevant factors,
including the role of the non-signatory entities in the underlying
transaction, the composite nature of the transaction, the conduct of the
parties, their mutual intention, and the degree of their participation in
the performance, negotiation, or termination of the contractual
arrangement.
82. It is also pertinent to note that the aforesaid judgments
recognise the width and scope of the jurisdiction conferred upon the
Arbitral Tribunal under Section 16 of the A&C Act to determine all
questions touching upon its own jurisdiction. Such jurisdiction would
necessarily include examination of the Respondents‟ objections
concerning the arbitrability of the disputes, the maintainability of
claims against non-signatories, the applicability of the group of
companies’ doctrine, the nature and extent of participation of
Respondent Nos. 2 and 3 in the underlying transaction, as well as all
other allied and incidental jurisdictional objections sought to be raised
before this Court.
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 30 of 35
83. At this stage, therefore, this Court does not deem it appropriate
to conclusively adjudicate upon such disputed and mixed questions of
fact and law, particularly when the statutory framework under Section
16 of the A&C Act specifically empowers the learned Arbitral
Tribunal to undertake such an examination in accordance with law.
84. In the present case, it is noted that Respondent Nos. 2 and 3 are
the controlling promoters of Respondent No. 1, holding 50.25%
conjointly; they are the pledgors in the very transaction alleged to
constitute the breach; and they are expressly identified within Clause 6
as the "present promoter group" whose conduct is restricted. In view
of these facts, this Court is of the prima facie view that these
circumstances raise a triable issue as to their amenability to
arbitration; however, it cannot be conclusively determined at this
stage.
85. It is also relevant to note that the interim protection granted by
this Court under Section 9 of the A&C Act is confined to the assets
and affairs of Respondent No. 1 under the contractual framework of
the Facility Agreement and is intended solely to preserve the subject
matter of the dispute pending arbitral proceedings. The said protection
operates qua Respondent No. 1, which is admittedly a party to the
Facility Agreement, and cannot be construed as a final determination
of any rights or obligations of Respondent Nos. 2 and 3.
86. Consequently, the mere objection raised by Respondent Nos. 2
and 3 on the basis of their non-signatory status does not, at this stage,
denude this Court of its jurisdiction to grant protective relief in aid of
Arbitration.
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 31 of 35
87. Accordingly, the interim protection granted under Section 9 of
the A&C Act shall continue to operate until commencement of the
arbitral proceedings or until varied by the learned Arbitral Tribunal in
exercise of its powers under Section 17 of the A&C Act. Insofar as the
proceedings under Section 11 are concerned, this Court does not
consider it either necessary or appropriate to conclusively determine
whether Respondent Nos. 2 and 3 are bound by the arbitration
agreement, the said issue being left open for consideration by the
learned Arbitral Tribunal, if and when the occasion so arises, in
accordance with law.
88. Moving to the objections raised by Respondent No. 4, this
Court notes that the principal contention advanced is that Respondent
No. 4, being a non-signatory to the Facility Agreement and deriving
its rights independently under the Pledge Agreement executed with
Respondent Nos. 2 and 3, cannot be subjected to the consequences
arising out of the contractual arrangement between the Petitioner and
Respondent No. 1.
89. In this regard, it is relevant to note that the interim protection
granted vide Order dated 23.12.2025 is confined to preservation of the
subject matter of the dispute arising under the Facility Agreement and
operates qua Respondent No. 1 under its contractual framework. The
said order neither determines nor conclusively affects any rights that
Respondent No. 4 may independently claim under the Pledge
Agreement.
90. Learned senior counsel appearing for Respondent No. 4 has
also placed reliance upon Section 58(2) of the Companies Act, 2013,
to contend that the right to pledge shares is a statutory right and
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 32 of 35
cannot be curtailed by a private contractual arrangement. While this
Court finds no reason to dispute the said proposition as a general
statement of law, the issue in the present proceedings is not the
existence of such a right, but the effect of its exercise in the context of
the contractual obligations governing Respondent No. 1 under the
Facility Agreement.
91. It is also noted that during the course of oral submissions,
learned senior counsel for Respondent No. 4 urged that the interim
Order dated 23.12.2025 deserves to be vacated. It was firstly
contended that the Petitioner, having accepted and retained the benefit
of Rs. 96 crores generated through the pledge transaction, cannot seek
to impugn the same, as its conduct is hit by the doctrine of approbate
and reprobate. Secondly, it was contended that the restraint on the
creation of a charge or pledge over the assets of Respondent No. 1
cannot extend to shares held by Respondent Nos. 2 and 3, as such
shares are the property of the shareholders and not of the company.
92. This Court is not persuaded by either of those submissions. The
receipt of Rs. 96 crores by the Petitioner was pursuant to the
directions of the Hon‟ble Supreme Court and in partial satisfaction of
an adjudicated liability exceeding Rs. 1321 crores. Such a receipt
cannot be construed as a voluntary acceptance of the impugned
transaction, such as to invite the doctrine of approbate and reprobate.
93. Insofar as the second contention is concerned, while it is correct
that shares are, in law, the property of the shareholders and not assets
of the company, however, Clause 6 of the Facility Agreement
expressly restrains any transfer or recognition of transfer of promoter
shareholding without prior written consent of the Petitioner and
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 33 of 35
invocation of the pledge would, prima facie, may result in a change in
controlling interest and management of Respondent No. 1.
94. Therefore, this Court deems it apposite, at this stage, that such a
technical distinction cannot be permitted to dilute the protective scope
of an Order made to safeguard contractual rights pending adjudication,
and whether the said pledge falls within the precise ambit of Clause 6
is a matter to be adjudicated upon by the learned Arbitral Tribunal.
95. Accordingly, the objections raised by the Respondent No.4 are
rejected.
CONCLUSION:
I. ARB. P. No. 835/2026
96. Considering the foregoing discussion, with respect to the
Petition under Section 11 of the A&C Act, this Court, upon a prima
facie examination in terms of the principles laid down in Krish
Spinning(supra), is satisfied that a valid arbitration agreement exists
between the Petitioner and Respondent No. 1 under the Facility
Agreement; and that a fresh arbitrable dispute has been disclosed,
whereupon the statutory requirement under Section 21 of the A&C
Act invoking Arbitration has been duly complied vide Notice dated
20.12.2025; therefore this Court finds no impediment to appoint a
Sole Arbitrator to adjudicate the disputes as arisen inter se the parties
to the said agreement.
97. Insofar as Respondent Nos. 2, 3 and 4 are concerned, this Court
refrains from expressing any conclusive opinion at this stage on the
question as to whether they are bound by the arbitration agreement or
whether they constitute necessary or proper parties to the arbitral
proceedings.
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 34 of 35
98. The said issues or any other issue concerning the jurisdiction or
competence of the learned Arbitral Tribunal fall squarely within the
jurisdictional domain of the learned Arbitral Tribunal under Section
16 of the A&C Act, and shall be examined and adjudicated by the
learned Arbitral Tribunal independently, in accordance with law,
without being influenced by any observations made hereinabove.
99. This Court requests Hon’ble Mr. Justice U. U. Lalit, Former
Chief Justice of India, to enter into the reference and adjudicate the
disputes between the parties.
100. The learned Arbitrator shall be entitled to a fee as may be
agreed upon between the parties and the learned Arbitrator.
101. The learned Arbitrator is also requested to file the requisite
disclosure under Section 12 of the A&C Act within a week of entering
the reference.
II. O.M.P.(I)(COMM.) No. 531/2025
102. This Court, in regard to the Petition under Section 9 of the A&C
Act finds that the interim protection granted vide Order dated
23.12.2025 warrants confirmation as, upon a prima facie examination
of the pleadings and material on record, the balance of convenience
lies in favour of the Petitioner and any invocation of the pledge or
transfer of management and control of Respondent No. 1 would cause
irreversible consequences that cannot be undone or compensated in
monetary terms, whereas continuation of the status quo does not
causes irreparable harm to the Respondents.
103. Consequently, the interim protection granted vide Order dated
23.12.2025 in Section 9 Petition is confirmed and shall continue to
remain operative until such time as the same is modified, varied, or
O.M.P.(I) (COMM.) 531/2025 & Connected matter Page 35 of 35
vacated by the learned Arbitral Tribunal in exercise of its powers
under Section 17 of the A&C Act, in accordance with law.
104. It is made clear that, insofar as both the petitions are concerned,
all rights and contentions of the parties arising out of or in relation to
the arbitration agreement, including those pertaining to the claims and
counter-claims, are expressly kept open to be adjudicated by the
learned Arbitral Tribunal on their own merits, in accordance with law.
105. It is also made clear that the observations made hereinabove are
purely prima facie in nature and have been rendered only for the
purposes of adjudication of the present petitions. The same shall not
be construed as an expression of opinion on the merits of the disputes
between the parties, and the learned Arbitral Tribunal shall decide all
issues independently and uninfluenced by any observations contained
in the present judgment, in accordance with law.
106. The Registry is directed to send a copy of this Judgment to the
learned Arbitrator through all permissible modes, including through e-
mail.
107. Accordingly, both Petitions, being O.M.P. (I) (COMM.) No.
531/2025 & ARB. P. No. 835/2026, along with pending application(s),
if any, stand disposed of in the above terms.
108. No Order as to costs.
HARISH VAIDYANATHAN SHANKAR, J.
MAY 29, 2026/jk
Legal Notes
Add a Note....