As per case facts, ACIL invoked arbitration, leading to AAI unilaterally appointing a sole arbitrator. An award was rendered favoring ACIL. AAI filed a Section 34 petition on merits, but ...
FAO(OS) (COMM) 246/2026 Page 1 of 20
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 10.09.2026
Judgment pronounced on: 25.09.2026
Judgment uploaded on: 25.09.2026
# CNR No. DLHC010430852026
+ FAO(OS) (COMM) 246/2026, CM APPL. 61809/2026 and CM
APPL. 61810/2026
M/S AHLUWALIA CONTRACTS (INDIA) LIMITED (ACIL)
.....Appellant
Through: Mr. Anil Airi, Sr. Adv. with
Mr. Dhruv Rohatgi, Ms.
Chandrika Sachdev, Mr. Dhruv
Kumar & Mr. Harsh Gautam,
Advs.
versus
AIRPORTS AUTHORITY OF INDIA (AAI) .....Respondent
Through: Mr. Vaibhav Kalra, Ms. Neha
Bhatnagar & Mr. Deepankar
Singh, Advs.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MR. JUSTICE VIMAL KUMAR YADAV
J U D G M E N T
ANIL KSHETARPAL, J.:
1. The present Appeal under Section 37 of the Arbitration and
Conciliation Act, 1996 [hereinafter referred to as the „A&C Act‟], has
been preferred by the Appellant, M/s Ahluwalia Contracts (India) Ltd.
(„ACIL‟), assailing the judgment dated 20.07.2026 [hereinafter
referred to as „Impugned Judgment‟] passed by the learned Single
Judge in OMP (COMM.) No.512/2023, whereby the petition preferred
FAO(OS) (COMM) 246/2026 Page 2 of 20
by the Respondent [hereinafter referred to as „Section 34 Petition‟],
Airports Authority of India („AAI‟), under Section 34 of the A&C Act
was allowed and the arbitral award dated 10.08.2023 [hereinafter
referred to as „Award‟] was set aside.
2. The controversy in the present Appeal is confined to the
constitution of the Arbitral Tribunal and, in particular, the
appointment of the Sole Arbitrator by AAI. The principal grievance of
the Appellant is that the learned Single Judge, while entertaining the
challenge under Section 34 of the A&C Act, proceeded to examine the
validity of the appointment of the Sole Arbitrator on the basis of the
judgment of the Supreme Court in Bhadra International (India) Pvt.
Ltd. & Ors. v. Airports Authority of India
1
[hereinafter referred to as
„Bhadra International‟], although no challenge to the appointment of
the Sole Arbitrator had been raised by AAI either during the arbitral
proceedings or in its Section 34 Petition.
3. The Appellant contends that the factual premise underlying
Bhadra International was materially different, inasmuch as the
challenge therein was raised by the party which had not participated in
or made the unilateral appointment of the arbitrator. According to the
Appellant, the principle laid down therein cannot be mechanically
extended to a case where the very party which had appointed the Sole
Arbitrator itself seeks to question the appointment, after having
participated in the arbitral proceedings without demur and after the
Award had been rendered.
1
2026 INSC 6
FAO(OS) (COMM) 246/2026 Page 3 of 20
FACTUAL MATRIX:
4. The facts, insofar as relevant for adjudication of the present
Appeal, may briefly be noticed.
5. AAI awarded the work to ACIL on 21.01.2009, pursuant to
which the Contract Agreement was executed between the parties on
02.02.2009. The stipulated date of commencement of the work was
31.01.2009. Disputes subsequently arose between the parties, inter
alia, in relation to the levy of compensation by AAI. AAI issued a
Show Cause Notice dated 18.09.2015 proposing levy of
compensation, to which ACIL submitted its reply on 06.10.2015.
Thereafter, AAI, vide communication dated 29.12.2015, levied
compensation of Rs.1,45,50,192/- retrospectively.
6. ACIL thereafter invoked the contractual dispute resolution
mechanism and, on 07.05.2016, requested AAI to constitute the
Dispute Resolution Board [hereinafter referred to as „DRB‟] in terms
of Clause 57(a)(i) of the Contract Agreement. The DRB submitted its
recommendations on 05.10.2017. AAI, however, conveyed its
decision on 01.03.2019, rejecting the review of the delay analysis and
confirming the levy of compensation.
7. Aggrieved by the aforesaid decision, ACIL, vide notice dated
16.04.2019, invoked arbitration under Clause 57(b) of the Contract
Agreement and requested AAI to appoint an independent arbitrator for
adjudication of the disputes between the parties.
FAO(OS) (COMM) 246/2026 Page 4 of 20
8. Pursuant thereto, AAI, vide email dated 10.05.2019, intimated
the proposed Sole Arbitrator regarding his appointment and called
upon him to convey his consent to the appointment. AAI also sought
the requisite declaration from the proposed Arbitrator in terms of the
Fifth and Sixth Schedules to the A&C Act. The proposed Sole
Arbitrator furnished his consent and declaration under Section
12(1)(b) of the A&C Act on 12.05.2019. Thereafter, vide letter dated
13.05.2019, AAI formally intimated the appointment of Shri S.C.
Gupta, Chief Engineer (Retd.), CPWD, as the Sole Arbitrator to
adjudicate the disputes between the parties.
9. The Sole Arbitrator entered upon the reference and conveyed
his acceptance of the appointment on 26.05.2019. During the course
of the arbitral proceedings, issues also arose regarding reference of
additional claims and the counter-claims of AAI. The Sole Arbitrator
sought appropriate approval from the competent authority of AAI for
reference of such claims. AAI thereafter took steps for reference of
Claim No. 5.7 and its counter-claims to the Sole Arbitrator.
10. The arbitral proceedings continued from 2019 to 2023. Both
parties participated in the proceedings and, as per the record placed
before this Court, no objection was raised by either party to the
appointment of the Sole Arbitrator or alleging any bias on his part.
The parties thereafter completed their respective pleadings and
arguments before the Sole Arbitrator.
11. On 10.08.2023, the Sole Arbitrator rendered the Award. Claim
No.1 was allowed and Claim No.4 was partly allowed in favour of
FAO(OS) (COMM) 246/2026 Page 5 of 20
ACIL, along with interest under Claim No.5. Claim Nos.2, 3 and 6 as
well as the counter-claims of AAI were rejected.
12. Aggrieved by the Award, AAI preferred the Section 34 Petition
before the learned Single Judge in November 2023. The challenge was
founded on the merits of the award, particularly with respect to the
consideration of Claim Nos.1, 4 and 5 and the rejection of the counter-
claims. Significantly, no ground challenging the appointment of the
Sole Arbitrator, including on the basis of Section 12(5) read with the
Seventh Schedule to the A&C Act, was raised in the Section 34
proceedings.
13. The Section 34 Petition was thereafter taken up for hearing on
13.07.2026. The arguments advanced on behalf of AAI remained
confined to the merits of the claims and counter-claims, and no
application or objection was raised by AAI concerning the unilateral
appointment or constitution of the Arbitral Tribunal. It was during the
course of the hearing that the learned Single Judge, suomotu, raised a
query regarding the appointment of the Sole Arbitrator and adjourned
the matter for further consideration.
14. On 20.07.2026, after hearing the Appellant on the aspect of the
appointment of the Sole Arbitrator, the learned Single Judge allowed
the Section 34 Petition and set aside the Award. While doing so, the
learned Single Judge placed reliance, inter alia, upon the judgment of
the Supreme Court in Bhadra International and the decisions of this
Court in Railways Board, Ministry of Railways v. Titagarh Rail
FAO(OS) (COMM) 246/2026 Page 6 of 20
Systems Ltd.
2
; and Engineering Projects (India) Ltd. v. Allied
Construction
3
.
15. It is in the aforesaid circumstances that the present Appeal has
been preferred. The Appellant principally assails the learned Single
Judge‟s decision to set aside the Award on a ground concerning the
appointment of the Sole Arbitrator, notwithstanding that the party
which had itself appointed the Sole Arbitrator had not raised any such
objection either before the Arbitral Tribunal or in the Section 34
proceedings.
CONTENTIONS OF THE P ARTIES:
16. Heard learned senior counsel and learned counsel representing
the respective parties, and with their able assistance, perused the paper
book.
17. Learned senior counsel representing the Appellant has made the
following submissions:
i. Learned Single Judge erred in applying the judgment in
Bhadra International to the facts of the present case. Bhadra
International concerned a challenge to a unilateral appointment
raised by the party which had not itself appointed the Arbitrator
and was consequently aggrieved by being denied an equal say in
the constitution of the Arbitral Tribunal. The present case,
according to the Appellant, stands on a materially different
footing, since it was AAI itself which appointed the Sole
2
2026:DHC:1720
3
2026:DHC:2540
FAO(OS) (COMM) 246/2026 Page 7 of 20
Arbitrator and subsequently participated in the arbitral
proceedings without raising any objection to his appointment.
ii. The expression „aggrieved party‟, in the context in which
the Supreme Court considered the issue in Bhadra International,
necessarily refers to a party aggrieved by the manner in which
the Arbitral Tribunal came to be constituted. A distinction must
therefore be maintained between a party which is aggrieved by
the appointment of an arbitrator and a party which, having
accepted the constitution of the Tribunal and participated in the
arbitral proceedings, is merely aggrieved by the ultimate award.
iii. AAI had consciously and expressly appointed Shri S.C.
Gupta as the Sole Arbitrator. Prior to the appointment, AAI had
itself called upon the proposed Arbitrator to furnish the requisite
declaration under the amended provisions of the A&C Act. The
Arbitrator thereafter furnished his declaration under Section
12(1)(b), and AAI proceeded with the arbitration without raising
any objection either to the declaration or to the constitution of the
Tribunal.
iv. The arbitration continued for nearly four years, during
which both parties participated in the proceedings, including in
relation to the reference of additional claims and counter-claims.
At no stage during this period was any objection raised by AAI
to the appointment of the Sole Arbitrator or any allegation made
regarding his independence or impartiality. AAI could not, after
having participated in the arbitral proceedings and suffered an
FAO(OS) (COMM) 246/2026 Page 8 of 20
Award adverse to it, seek to invalidate the entire arbitral process
on the basis of a defect in the very appointment which it had
itself made.
v. Learned Single Judge travelled beyond the scope of the
Section 34 proceedings in examining the appointment of the Sole
Arbitrator. AAI‟s Section 34 Petition did not contain any ground
under Section 12(5) read with the Seventh Schedule of the A&C
Act, and the challenge before the learned Single Judge was
confined to the merits of the claims and counter-claims. The
issue concerning the appointment was raised by the learned
Single Judge suomotu during the hearing and was thereafter
made the basis for setting aside the Award.
vi. The principle underlying Section 12(5) of the A&C Act
is intended to secure the independence and impartiality of the
Arbitral Tribunal and, in the context of a unilateral appointment,
principally protects the party which has not participated in the
appointment.
18. Per contra, learned counsel representing AAI, while supporting
the Impugned Judgment, has made the following submissions:
i. The mandate contained in Section 12(5) of the A&C Act,
as interpreted by the Supreme Court in Bhadra International,
cannot be defeated merely on the basis of the subsequent conduct
of the parties or their participation in the arbitral proceedings.
FAO(OS) (COMM) 246/2026 Page 9 of 20
ii. Learned Single Judge was, therefore, justified in
examining the validity of the appointment of the Sole Arbitrator
and in applying the principles laid down by the Supreme Court in
Bhadra International. The question of the validity of the
constitution of the Arbitral Tribunal is distinct from the merits of
the Award and, if the Tribunal itself was not validly constituted,
the resulting award could not be sustained.
iii. The fact that the objection to the appointment was not
specifically raised in the Section 34 Petition does not preclude
the Court from examining the legality of the constitution of the
Arbitral Tribunal where the defect goes to the root of the
proceedings. Reliance is accordingly placed upon the reasoning
adopted by the learned Single Judge in the Impugned Judgment.
19. No other submission has been advanced by learned senior
counsel and learned counsel representing the respective parties.
ANALYSIS AND FINDINGS:
20. This Court has considered the submissions advanced by learned
senior counsel and learned counsel representing the respective parties
and has perused the material placed on record.
21. As already noticed hereinabove, the question which arises for
consideration is whether, after the enforcement of the Arbitration and
Conciliation (Amendment) Act, 2015, the appointment of the Arbitral
Tribunal by one of the parties, in the absence of an express agreement
FAO(OS) (COMM) 246/2026 Page 10 of 20
in writing subsequent to the disputes having arisen, would amount to
waiver of the applicability of Section 12(5) of the A&C Act.
22. The answer to the aforesaid question is no longer res integra.
The statutory scheme contained in Section 12(5) of the A&C Act, as
also the interpretation placed thereon by the Supreme Court and this
Court, makes it clear that the waiver contemplated by the proviso to
Section 12(5) is of a particular and specific nature. It cannot be
inferred merely from the conduct of the parties, from the fact that a
party itself appointed the arbitrator, or from the participation of the
parties in the arbitral proceedings.Waiver, in a general sense, may in
an appropriate case be inferred from conduct or from other
circumstances. However, where the statute itself prescribes the
manner in which a party may waive the applicability of a statutory
provision, the Court cannot substitute the statutorily prescribed mode
with an implied waiver. The proviso to Section 12(5) expressly
requires an agreement in writing, subsequent to the disputes having
arisen between the parties.
23. Section 12(5) of the A&C Act, as introduced by the Arbitration
and Conciliation (Amendment) Act, 2015, reads as under:
“12. Grounds for challenge
…
(5) Notwithstanding any prior agreement to the contrary, any person
whose relationship, with the parties or counsel or the subject-matter
of the dispute, falls under any of the categories specified in the
Seventh Schedule shall be ineligible to be appointed as an arbitrator:
Provided that parties may, subsequent to disputes having arisen
between them, waive the applicability of this sub-section by an express
agreement in writing.”
FAO(OS) (COMM) 246/2026 Page 11 of 20
24. On a plain reading of the aforesaid provision, it becomes
evident that the legislature has consciously prescribed three essential
requirements for waiver: (i) the waiver must be subsequent to the
disputes having arisen between the parties; (ii) it must be by
agreement between the parties; and (iii) such agreement must be
express and in writing. Thus, the statutory provision does not
contemplate a waiver by implication or by conduct.
25. The aforesaid interpretation has been authoritatively settled by
the Supreme Court in Bhadra International. The Supreme Court,
after examining the scope and effect of the proviso to Section 12(5) of
the A&C Act, has explained the requirements of such waiver in the
following terms:
“75. The essentials of the proviso to Section 12(5) are:-
i. The parties can waive their right to object under sub-section (5)
of Section 12;
ii. The right to object under the sub-section can be waived only
subsequent to a dispute having arisen between the parties;
iii. The waiver must be in the form of an express agreement in writing.
***
78. What flows from the aforesaid is when a right exists, i.e., the
right to object to the appointment of an ineligible arbitrator in terms
of
Section 12(5), such a right cannot be taken away by mere implication.
For a
party to be deprived of this right by way of waiver, there must be a
conscious
and unequivocal expression of intent to relinquish it. Needless to say,
for a
waiver to be valid, it is necessary that the actor demonstrates the
intention
to act, and for an act to be intentional, the actor must understand the
act and
its consequences.
***
FAO(OS) (COMM) 246/2026 Page 12 of 20
84. Undoubtedly, the statute does not prescribe a format for the
agreement. However, the absence of a prescribed format cannot be
construed t o
mean that the waiver may be inferred impliedly or through conduct.
We say so
because the legislature has consciously prefaced the term
“agreement” with the
word “express” and followed it with the phrase “in writing”. This
semantics
denote the intention of the legislature that the waiver under the
proviso to
Section 12(5) must be made only through an express and written
manifestation of
intention. ”
26. The significance of the aforesaid decision becomes apparent
from the facts of Bhadra International itself. In that case, the
Arbitrator had, in Procedural Order No.1, specifically recorded that
none of the parties had any objection to his appointment as the Sole
Arbitrator. Despite such factual position, the correctness of which was
not disputed, the Supreme Court held that such an observation
recorded in the procedural order could not amount to waiver,
particularly when the statute envisages waiver only by an express
agreement in writing subsequent to the disputes having arisen between
the parties.
27. Thus, the mere fact that a party may have proceeded with the
arbitration with knowledge of the constitution of the Arbitral Tribunal
cannot be elevated to an express agreement in writing as contemplated
by the proviso to Section 12(5) of the A&C Act. The statutory
requirement is not satisfied by acquiescence, participation or conduct.
The requirement is of an agreement, expressed in writing, between the
parties after the disputes have arisen.
FAO(OS) (COMM) 246/2026 Page 13 of 20
28. The aforesaid principle has also been applied by the Division
Bench of this Court in Titagarh Rail Systems(supra). The Division
Bench has specifically rejected the contention that following the
contractual procedure for appointment of an arbitrator, by itself, could
result in waiver of the applicability of Section 12(5) of the A&C Act.
The relevant observations read as under:
“27. While it may be true that the procedure followed by the parties
was that which was envisaged, in the contract between them, as
applying where there was waiver of Section 12(5), following of the
procedure cannot by itself result in such waiver. The argument
effectively puts the cart before the horse. There must, in the first
instance, be waiver of the applicability of Section 12(5) by written
agreement in writing as required by the proviso to the said clause
read with the decision in Bhadra International, and, only thereafter, if
there exists such express waiver in writing, would the arbitral
procedure envisaged in that situation as contained in Clause
2905(a)(ii) apply. The situation cannot be read in reverse. We cannot
accept the argument that by invoking the procedure applicable in a
case of waiver of Section 12(5), Section 12(5) stands waived, despite
the absence of any written agreement in writing to that effect.
28. In fact, the situation which exists in the present case is that the
very invocation of the procedure, envisaged in the contract between
the parties as being applicable in a case in which Section 12(5) stood
waived, was itself illegal. That procedure applies only where there is
waiver of the applicability of Section 12(5). Inasmuch as there was no
such waiver in the present case, the procedure itself would not apply.
By erroneously invoking the procedure which applies where Section
12(5) has been waived, waiver of Section 12(5) cannot be implied.”
29. The principle emerging from the aforesaid decisions is,
therefore, clear. The fact that a party has acted in accordance with the
contractual mechanism for appointment cannot, in the absence of an
express agreement in writing subsequent to the disputes, constitute
waiver of the applicability of Section 12(5) of the A&C Act. The
contractual mechanism cannot be permitted to operate in a manner
contrary to the mandatory statutory requirement.
FAO(OS) (COMM) 246/2026 Page 14 of 20
30. In the present case, it is not in dispute that AAI appointed the
Sole Arbitrator in exercise of the power conferred upon it under
Clause 57(c) of the Contract Agreement. It is also not in dispute that
the appointment was made after the disputes had arisen between the
parties. However, there is admittedly no express agreement in writing
between the parties, subsequent to the disputes having arisen, whereby
the applicability of Section 12(5) of the A&C Act was waived.
31. The Appellant seeks to overcome this statutory requirement
by placing reliance upon the fact that AAI itself appointed the Sole
Arbitrator, participated in the arbitral proceedings for several years
and did not raise any objection to the constitution of the Arbitral
Tribunal until after the Award was rendered. However, these
circumstances, even taken cumulatively, cannot constitute the express
agreement in writing mandated by the proviso to Section 12(5) of the
A&C Act.
32. In this regard, reliance placed by the Appellant upon the fact
that it was AAI itself which appointed the Sole Arbitrator is of no
avail. The precise question whether a party which has itself made the
unilateral appointment can subsequently object to the appointment has
also been considered by the Division Bench of this Court in Mahavir
Prasad Gupta and Sons v. Govt. of NCT of Delhi
4
. The Division
Bench considered the question whether the act of unilateral
appointment itself could constitute an express agreement to waive the
statutory ineligibility and held as under:
“79. Hence, exercise of power to unilaterally appoint the arbitrator by
a party cannot be termed as express agreement to waive the invalidity
4
2025 SCC OnLine Del 4241
FAO(OS) (COMM) 246/2026 Page 15 of 20
of the arbitration agreement providing for unilateral appointment. For
waiver under Section 12(5) of the Act after the dispute have arisen, the
parties are required to consciously agree in writing to waive the
ineligibility of the arbitrator. Grounds of ineligibility of the arbitrator
under Seventh Schedule are derived from Red List of IBA Rules on
Conflict of Interest in International Commercial Arbitration. The Act
was as amended in 2015 to provide a detailed framework to address
arbitrator bias. This framework includes the Fifth and Seventh
Schedules, which draw from the Orange and Red Lists of the IBA
Guidelines, respectively. The Fifth Schedule requires arbitrators to
disclose any circumstances that might reasonably affect their
impartiality, including relationships with the parties, counsel, or
subject matter of the dispute. The Seventh Schedule reflecting the Red
List, outlines scenarios of relationship conflict that would result in de
jure ineligibility of an arbitrator.”
33. The aforesaid decision is of particular relevance to the
submission advanced by learned senior counsel representing the
Appellant. The mere fact that the appointment was made by AAI does
not amount to an express agreement in writing by both parties to
waive the applicability of Section 12(5) of the A&C Act. The act of
appointment and the statutory waiver contemplated by the proviso
operate in distinct fields and cannot be equated with each other.
34. Significantly, the Division Bench in Mahavir Prasad Gupta
(supra)ultimately upheld the setting aside of the award on the ground
of unilateral appointment. The Supreme Court thereafter declined to
interfere with the judgment of the Division Bench in the Special
Leave Petition. The aforesaid position thus lends further consistency
to the interpretation adopted by this Court regarding the mandatory
nature of the proviso to Section 12(5) of the A&C Act.
35. The question posed before this Court is also directly answered
by the judgment of the Supreme Court in Bharat Broadband Network
FAO(OS) (COMM) 246/2026 Page 16 of 20
Ltd. v. United Telecoms Ltd.
5
. In the said case, the Supreme Court
considered the precise question as to whether the appointment of an
ineligible arbitrator by the party having the power of appointment
could itself amount to an express waiver under the proviso to Section
12(5) of the A&C Act. The Supreme Court held that it could not.
36. The Supreme Court, in Paragraph No.20 of Bharat
Broadband (supra), interpreted the expression “express agreement in
writing” occurring in the proviso to Section 12(5) of the A&C Act in
the following terms:
“20. This then brings us to the applicability of the proviso to Section
12(5) on the facts of this case. Unlike Section 4 of the Act which deals
with deemed waiver of the right to object by conduct, the proviso to
Section 12(5) will only apply if subsequent to disputes having arisen
between the parties, the parties waive the applicability of sub-section
(5) of Section 12 by an express agreement in writing. For this reason,
the argument based on the analogy of Section 7 of the Act must also
be rejected. Section 7 deals with arbitration agreements that must be
in writing, and then explains that such agreements may be contained
in documents which provide a record of such agreements. On the
other hand, Section 12(5) refers to an “express agreement in writing”.
The expression “express agreement in writing” refers to an
agreement made in words as opposed to an agreement which is to be
inferred by conduct. Here, Section 9 of the Contract Act, 1872
becomes important. It states:
“9. Promises, express and implied.—Insofar as the
proposal or acceptance of any promise is made in words,
the promise is said to be express. Insofar as such proposal
or acceptance is made otherwise than in words, the
promise is said to be implied.”
It is thus necessary that there be an “express” agreement in writing.
This agreement must be an agreement by which both parties, with full
knowledge of the fact that Shri Khan is ineligible to be appointed as
an arbitrator, still go ahead and say that they have full faith and
confidence in him to continue as such. The facts of the present case
disclose no such express agreement. The appointment letter which is
relied upon by the High Court as indicating an express agreement on
the facts of the case is dated 17-1-2017. On this date, the Managing
5
(2019) 5 SCC 755
FAO(OS) (COMM) 246/2026 Page 17 of 20
Director of the appellant was certainly not aware that Shri Khan
could not be appointed by him as Section 12(5) read with the Seventh
Schedule only went to the invalidity of the appointment of the
Managing Director himself as an arbitrator. Shri Khan's invalid
appointment only became clear after the declaration of the law by the
Supreme Court in TRF Ltd. [TRF Ltd. v. EnergoEngg. Projects Ltd.,
(2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72] which, as we have seen
hereinabove, was only on 3-7-2017. After this date, far from there
being an express agreement between the parties as to the validity of
Shri Khan's appointment, the appellant filed an application on 7-10-
2017 before the sole arbitrator, bringing the arbitrator's attention to
the judgment in TRF Ltd. [TRF Ltd. v. EnergoEngg. Projects Ltd.,
(2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72] and asking him to declare
that he has become de jure incapable of acting as an arbitrator.
Equally, the fact that a statement of claim may have been filed before
the arbitrator, would not mean that there is an express agreement in
words which would make it clear that both parties wish Shri Khan to
continue as arbitrator despite being ineligible to act as such. This
being the case, the impugned judgment is not correct when it applies
Section 4, Section 7, Section 12(4), Section 13(2) and Section 16(2) of
the Act to the facts of the present case, and goes on to state that the
appellant cannot be allowed to raise the issue of eligibility of an
arbitrator, having itself appointed the arbitrator. The judgment under
appeal is also incorrect in stating that there is an express waiver in
writing from the fact that an appointment letter has been issued by the
appellant, and a statement of claim has been filed by the respondent
before the arbitrator. The moment the appellant came to know that
Shri Khan's appointment itself would be invalid, it filed an application
before the sole arbitrator for termination of his mandate.”
37. The aforesaid decision is directly relevant to the facts of the
present case. The Supreme Court has expressly rejected the
proposition that the party which itself appoints the arbitrator is thereby
precluded from questioning the validity of such appointment. More
importantly, the Supreme Court has made it clear that the appointment
letter itself cannot be treated as an express agreement in writing under
the proviso to Section 12(5) of the A&C Act.
38. The submission of learned senior counsel representing the
Appellant that the decision in Bhadra International ought to be
FAO(OS) (COMM) 246/2026 Page 18 of 20
confined to a case where the objection is raised by the party which did
not make the appointment, therefore, cannot be accepted. The
subsequent decision of the Division Bench in Mahavir Prasad Gupta
(supra) has expressly examined this very issue, and the principle has
thereafter received further support from the Supreme Court. The
statutory requirement of an express agreement in writing does not
depend upon which of the parties made the appointment.
39. Equally, the participation of AAI in the arbitral proceedings
cannot result in a different conclusion. The Supreme Court in Bhadra
International has specifically recognised that even conduct which
may otherwise appear to demonstrate acceptance of the Arbitral
Tribunal cannot substitute the express written agreement contemplated
by the proviso. The reason is apparent from the statutory language
itself. Section 12(5) of the A&C Act constitutes a specific statutory
departure from the general principle of waiver by conduct.
40. In the present case, the record discloses participation by AAI
in the arbitral proceedings from 2019 until the passing of the Award in
2023. However, there is no material to demonstrate that, subsequent to
the disputes having arisen, the parties entered into any express
agreement in writing whereby they consciously waived the
applicability of Section 12(5) of the A&C Act. Participation in the
arbitral proceedings, submission of pleadings, consideration of claims
and counter-claims, or failure to raise an objection before the Arbitral
Tribunal cannot be treated as a substitute for such statutory waiver.
FAO(OS) (COMM) 246/2026 Page 19 of 20
41. The contention that the objection was not raised in the Section
34 Petition also does not assist the Appellant. An objection founded
upon the inherent lack of jurisdiction of an Arbitral Tribunal, where
the statutory conditions rendering the arbitrator ineligible are
attracted, is not converted into a valid appointment merely because the
objection was not raised at an earlier stage. The Supreme Court in
Bhadra International has specifically recognised that an objection
going to the inherent jurisdiction of the Arbitral Tribunal may be
raised at the stage of a challenge to the Award under Section 34.
42. In the present case, therefore, the learned Single Judge was
justified in examining the validity of the constitution of the Arbitral
Tribunal. Once the appointment of the Sole Arbitrator was found to be
contrary to the mandatory provisions of Section 12(5) read with the
Seventh Schedule of the A&C Act, and there was no express
agreement in writing subsequent to the disputes waiving the
applicability of Section 12(5), the resulting Award could not be
sustained.
43. It is also relevant to note that the learned Single Judge has set
aside the Award only on the issue which forms the subject matter of
the present Appeal, namely, the validity of the unilateral appointment
of the Sole Arbitrator. The learned Single Judge has not proceeded to
examine or determine the merits of the claims adjudicated by the
Arbitral Tribunal.
44. Having regard to the statutory mandate contained in Section
12(5) of the A&C Act, the authoritative interpretation placed upon the
FAO(OS) (COMM) 246/2026 Page 20 of 20
proviso by the Supreme Court in Bharat Broadband (supra) and
Bhadra International, and the consistent view taken by the Division
Bench of this Court in Mahavir Prasad Gupta (supra) and Titagarh
Rail Systems (supra), this Court finds no merit in the submissions
advanced on behalf of the Appellant.
CONCLUSION:
45. Consequently, this Court finds no error in the conclusion
reached by the learned Single Judge in setting aside the Award on the
aforesaid ground.
46. Finding no merit in the present Appeal, the same is dismissed.
The pending applications also stand closed.
ANIL KSHETARPAL , J.
VIMAL KUMAR YADAV , J.
SEPTEMBER 25, 2026
sp/shah
Legal Notes
Add a Note....